JP4698875B2 - Construction work management system for structures - Google Patents

Construction work management system for structures Download PDF

Info

Publication number
JP4698875B2
JP4698875B2 JP2001127744A JP2001127744A JP4698875B2 JP 4698875 B2 JP4698875 B2 JP 4698875B2 JP 2001127744 A JP2001127744 A JP 2001127744A JP 2001127744 A JP2001127744 A JP 2001127744A JP 4698875 B2 JP4698875 B2 JP 4698875B2
Authority
JP
Japan
Prior art keywords
work
management
construction
management device
amount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001127744A
Other languages
Japanese (ja)
Other versions
JP2002324154A (en
Inventor
謙太郎 比翼
Original Assignee
株式会社アイ・エイチ・アイ マリンユナイテッド
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社アイ・エイチ・アイ マリンユナイテッド filed Critical 株式会社アイ・エイチ・アイ マリンユナイテッド
Priority to JP2001127744A priority Critical patent/JP4698875B2/en
Publication of JP2002324154A publication Critical patent/JP2002324154A/en
Application granted granted Critical
Publication of JP4698875B2 publication Critical patent/JP4698875B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Description

【0001】
【発明の属する技術分野】
本発明は、構造物の建造作業管理システムに関する。
【0002】
【従来の技術】
大型構造物の1つである例えば船殻を建造する場合には、船殻全体を複数に分割したブロックを工場で予め組み立て、各ブロックをドック等に搬入して所定の順番で積み上げると共に、各ブロック間の接合を順次行う。例えば、最も船底に位置する複数のブロックがまず最初にドックに配置されてブロック相互間の接合が行われ、この上に各ブロックが順次積み上げられて相互間の接合がさらに行われる。
【0003】
このような船殻の建造では、主に各ブロックを構成する部材間の溶接によって各ブロックが相互接合される。したがって、船殻の建造における主な作業は、各作業員による溶接作業であり、この溶接作業は、各ブロックの搭載順序(搭載日程表)に基づいて行われる。搭載日程表の作成段階では、ブロックの設計図面に基づいて溶接対象部材毎に、その長さや板厚あるいは開先並びに溶接作業時の作業者の作業姿勢(溶接姿勢)を考慮した作業量が算出され、この結果として各ブロックの搭載に係わるトータル作業量が管理量として算出される。
【0004】
そして、実際の作業段階では、当該各ブロックの管理量に基づいて作業日程表が作成され、作業分担が各作業日毎に作業指示書として各作業員に指示される。各作業員は、この作業指示書に記載された作業箇所について指示当日内に溶接作業を完了する。また、各作業員には、当日の作業終了時に作業報告をすることが義務づけられており、この作業報告に基づいて作業進捗が管理されるようになっている。
【0005】
【発明が解決しようとする課題】
ところで、上述した従来技術には、以下のような問題点がある。
(1)上記管理量の計算は、手計算によって行われているために、時間を要すると共に計算ミスが発生し易い。
(2)上記作業指示書は、例えば作業班の班長が手書きで作成しているので、記入ミスや記入漏れ等が発生し易く、また指示内容が作業員に正確に伝達されない場合がある。これに起因して作業のやり残しや作業遅れが生じ易い。
(3)各作業者の作業能力を客観的に把握することが困難であり、作業進捗は、作業班の班長と作業員(班員)との裁量に委ねられている。したがって、作業が遅れた場合に、その原因(例えば管理量によるものか、要員計画によるものなのか、あるいは作業者の能力によるものなのか)を正確に把握することができず、結果として作業遅れに対して的確な対応を取ることが困難である。
(4)作業進捗が各作業員からの作業報告に基づく作業日程表上の消し込みによって管理されており、すなわち作業実績が定量的に累積管理されていないので、作業進捗の変化状態を正確に把握することが困難である。
(5)船殻建造における全体的な作業進捗状態を一目で確認できるものがないために、船殻建造の全体的な作業進捗について的確な把握や作業遅延に対する処置を施すことが困難である。
【0006】
本発明は、上述した問題点に鑑みて成されたものであり、正確な管理量を短時間で計算すると共に各作業者に作業内容を正確に伝達し、かつ、作業進捗の適切な管理を実現することを目的とするものである。
【0007】
【課題を解決するための手段】
上記目的を達成するために、本発明は、構造物の建造作業管理システムに係わる第1の手段として、複数の部材から構成される構造物の建造作業を管理するシステムにおいて、構造物の設計モデルに関する3次元形状データを用いて部材の接合位置における接続辺と水平面との相対角度を溶接姿勢として算出し、当該溶接姿勢と前記接合部位の形状とを変数とする評価関数を用いて部材間の接合に要する作業量を管理量として算出し、この管理量を前記3次元形状データに付加し設計データとして出力する管理量演算装置と、3次元形状データに基づいて設計モデルの3次元画像を表示すると共に、当該3次元画像を参照することにより操作入力された選択指示に応じた作業対象部材の溶接作業を指定された作業者に割り付ける処理を行い、割り付けた作業対象部材の総管理量に対する作業当日における溶接作業の目標値を示す作業指示書を作成する作業管理装置とを具備する手段を採用する。
【0008】
また、構造物の建造作業管理システムに係わる第2の手段として、上記第1の手段において、複数の部材によって予め構築された複数のブロックを相互接合して構造物を建造する場合には、現在接合対象となっているブロックに関する設計データのみを作業管理装置に提供する上位管理装置2を備えるという手段を採用する。
【0010】
構造物の建造作業管理システムに係わる第3の手段として、上記第1または第2の手段において、作業管理装置は、操作入力によって作業者と3次元画像内の部材が指定されると、作業者毎に作業内容を指示する作業指示書を作成するという手段を採用する。
【0011】
構造物の建造作業管理システムに係わる第4の手段として、上記第1〜第3いずれかの手段において、作業管理装置は、所定の操作入力に基づいて作業対象部材のみを3次元表示するという手段を採用する。
【0012】
構造物の建造作業管理システムに係わる第5の手段として、上記第1〜第4いずれかの手段において、作業管理装置は、操作入力された各作業日の作業実績に応じて各部材の管理量を更新するという手段を採用する。
【0013】
構造物の建造作業管理システムに係わる第6の手段として、上記第1〜第5いずれかの手段において、作業管理装置は、3次元画像内の各部材を管理量に応じて色分け表示するという手段を採用する。
【0014】
構造物の建造作業管理システムに係わる第7の手段として、上記第2〜第6いずれかの手段において、各ブロックは船殻を構成するものであるという手段を採用する。
【0020】
【発明の実施の形態】
以下、図面を参照して、本発明に係わる構造物の建造作業管理システムの一実施形態について説明する。
【0021】
なお、本実施形態は、本発明を構造物の1つである船殻の建造作業管理に適用したものであり、すなわち船殻を構成する複数のブロックを工場で予め組立て、これらブロックをドック等に搬入して相互接合することにより船殻を建造する際の作業管理に関するものである。この場合、まず最初に、船底部に位置するブロック同士が互いに接合され、この上にブロックが順次積み上げられて船殻が建造される。各ブロック間の接合では、互いに隣り合うブロックの特定部材(接合対象部材)が相互に溶接接合される。
【0022】
図1は、本実施形態のシステム構成図である。この図に示すように、本建造作業管理システムは、通信回線によって相互接続された管理量演算装置1と上位管理装置2と作業管理装置3とから構成されている。
【0023】
管理量演算装置1は、船殻(構造物)の設計部門に備えられるものであり、当該設計部門において設計された船殻の設計モデルに関する3次元形状データに基づいて上記接合対象部材間の接合に要する作業量を算出すると共に、この作業量を接合対象部材の属性データとして3次元形状データに付加し、設計データとして上位管理装置2に出力する。この管理量演算装置1は、例えば3次元形状データに基づいて接合対象部材の接合部位における接続辺と水平面との相対角度を溶接姿勢(接合姿勢)として算出し、当該溶接姿勢と上記接合部位の形状(板厚、開先形状及び溶接脚長)とを変数とする評価関数を用いてβNL値を算出する。このように算出されたβNL値は、接合対象部材を溶接接合する際に必要となる標準的な作業量(作業時間)を示す数値である。
【0024】
上位管理装置2は、プロダクション・エンジニアリングを担当する部門に配置されるものであり、通信回線を介して管理量演算装置1から受信された上記設計データの中から現在接合対象となっているブロックに関する設計データ(作業ブロック設計データ)のみを抽出して作業管理装置3に順次提供する。上位管理装置2を設けることにより、実際に現在行っている作業に関係する作業ブロック設計データのみを上記管理量演算装置1や上位管理装置2に比較して処理能力が劣る作業管理装置3に供給する。管理量演算装置1や上位管理装置2は例えばエンジニアリング・ワークステーションであるが、作業管理装置3は、例えば汎用のパーソナルコンピュータである。
【0025】
作業管理装置3は、作業現場に配置されるものであり、各作業者に対する作業指示書の作成機能と作業進捗状況の管理機能とを備えるものである。作業管理装置3は、設計データに含まれる3次元形状データに基づいて現在の作業対象(接合対象)となっているブロックに関する設計モデルの3次元画像を表示すると共に、当該3次元画像を参照することにより操作者(作業班の班長等の作業責任者)によって操作入力された作業手順と設計データに含まれる接合対象部材のβNL値とに基づいて作業指示書を作成する。
【0026】
また、作業管理装置3は、所定の操作入力に基づいて設計モデルの3次元画像のうち接合対象部材(つまり属性情報としてβNL値が含まれる部材)のみを作業指示書作成支援画像(SECT画像)として選択的に表示するように構成されており、操作者が操作入力によって作業者とSECT画像内の接合対象部材を指定すると、当該作業者に当該指定された接合対象部材の溶接作業を割り付ける。そして、作業者毎に上記作業を繰り返すことにより、複数の作業員に溶接作業を割り付け、この割付結果を各作業者毎の作業指示書として印刷出力する。なお、この作業指示書の作成手順の詳細については、後述する。
【0027】
また、作業管理装置3は、キーボード等の操作によって溶接作業の実績値が入力されると、当該進捗度に応じて各接合対象部材のβNL値を更新するように構成されており、上記SECT画像に表示された各接合対象部材をβNL値から実績値を差し引いた残管理量に応じて色分け表示すると共に、任意の接合対象部材をポインティングデバイス等によって操作指示することにより当該接合対象部材の残管理量を数値表示するように構成されている。
【0028】
次に、このように構成された本建造作業管理システムの時系列的な動作について、図2に示すフローチャートに沿って説明する。なお、このフローチャートは、作業管理装置3を用いた作業指示書の作成手順を示すものである。
【0029】
本建造作業管理システムでは、上位管理装置2によって設計データの中から作業ブロック設計データのみが抽出された状態において、作業管理装置3が種々の目的で操作されて作業指示書の作成や作業の進捗状況の確認等が行われる。すなわち、作業現場で各ブロックの接合作業が行われる時点では、管理量演算装置1によるβNL値の算出や当該βNL値と3次元形状データとに基づく設計データの生成処理及び上位管理装置2による作業ブロック設計データの抽出処理は、前処理として既に完了している。このような状態において、各作業員の作業指示書は、作業管理装置3を用いて以下のように作成される。
【0030】
ここで、βNL値は、作業対象ブロックの3次元形状データから得られた溶接姿勢及び接合部位の形状(板厚、開先形状及び溶接脚長)を変数とする評価関数を用いることにより管理量演算装置1によって自動計算される。すなわち、本実施形態では、従来手計算されていたβNL値が管理量演算装置1によって自動計算されるので、βNL値の計算に要する時間が短縮されると共に計算ミスが発生する余地が極めて少ない。
【0031】
さて、作業指示書の作成処理では、まず最初に設計データ(作業ブロック設計データ)の取り込みが行われる。操作者が作業ブロック設計データの取り込み指示を操作入力すると、作業管理装置3は通信回線を介して上位管理装置2から作業ブロック設計データを取得する(ステップS1)。この結果、作業管理装置3には、作業ブロック設計データに基づいて作業対象のブロックの3次元形状が画像表示される。そして、操作者がSECT画像の表示を操作指示すると、作業管理装置3は、属性情報としてβNL値が付与されている接合対象部材のみを抽出し、SECT画像として表示する(ステップS2)。
【0032】
これ以降の処理は、各作業班の作業者毎に特定の接合対象部材を作業対象として割り付ける処理となる。操作者が作業班の班長名及び作業者名並びに作業開始時間及び作業終了時間を操作入力し(ステップS3)、さらにSECT画像上の特定の接合対象部材を操作指定すると、当該接合対象部材は、上記作業者名に該当する作業者に割り付けられる(ステップS4)。ここで、SECT画像上における接合対象部材の操作指定を繰り返すことにより、複数の接合対象部材を上記作業者名に該当する作業者に割り付けることもできる。
【0033】
通常、船殻の溶接作業は複数の作業班によって、また各作業班は複数の作業者によって構成されているので、ステップS5における判断は「No」となるので、操作者が他の作業者名を操作入力することにより、上記ステップS2,S3の各所理が繰り返され、他の作業者名に該当する各作業班の作業者への作業割付が順次行われる。そして、以上のようにして全作業者への作業割付が完了し、操作者が印刷を操作指示すると、作業管理装置3は、上記ステップS2,S3の各所理による設定データをプリンタに送出して各作業者に対する作業指示書をカラー印刷させ(ステップS6)、作業指示書の作成処理が終了する。
【0034】
このような作業指示書の作成処理によれば、操作者は、複数の接合対象部材を的確かつ正確に各作業者に割り付けることが可能であり、割付ミスや割付もれ等の発生する余地が極めて少なくなる。
【0035】
また、本実施形態の作業指示書には、作業対象ブロックの3次元形状と作業対象として割り付けられた接合対象部材の3次元形状、並びに作業当日の作業予定が記載されている。この作業予定は、作業対象として割り付けられた単一あるいは複数の接合対象部材の総βNL値に対する作業当日の目標値をグラフ表示するものである。このように構成された作業指示書によって、各作業員には作業箇所が正確に指示される。
【0036】
続いて、各作業員は、上記のように作成された作業指示書に基づいて溶接作業を行い、1日の作業が終了すると、各接合対象部材に係わる溶接作業の実績値を各班長に報告する。この各接合対象部材の実績値は、キーボード等を用いて作業管理装置3に操作入力される。作業管理装置3は、実績値が入力されると、各接合対象部材のβNL値から実績値を差し引いた残管理量を算出し、各接合対象部材のβNL値を残管理量に更新する。
【0037】
この結果、進捗確認用画像(3次元画像)上に表示される各接合対象部材は、上記残管理量に応じて色分け表示されると共に、任意の接合対象部材をポインティングデバイス等によって操作指示すると、当該接合対象部材の残管理量が数値表示される。したがって、このように更新された残管理量に基づくSECT画像によって各接合対象部材について溶接作業の進捗状況を容易に確認することができる。
【0038】
また、上記進捗確認用画像では、実績値に基づいて作業当日の進捗状況を確認することができる。すなわち、進捗確認用画像上に表示される各接合対象部材は、作業当日の実績値に応じて色分け表示されると共に、操作指示された接合対象部材の実績値が数値表示される。このような進捗確認用画像を用いることにより、翌日の作業計画を容易に立案することができる。
【0039】
【発明の効果】
以上説明したように、本発明に係わる構造物の建造作業管理システムによれば、複数の部材から構成される構造物の建造作業を管理するシステムであって、構造物の設計モデルに関する3次元形状データを用いて部材の接合位置における接続辺と水平面との相対角度を溶接姿勢として算出し、当該溶接姿勢と前記接合部位の形状とを変数とする評価関数を用いて部材間の接合に要する作業量を算出し、この作業量を前記3次元形状データに付加し設計データとして出力する管理量演算装置と、3次元形状データに基づいて設計モデルの3次元画像を表示すると共に、3次元画像を参照することにより操作入力された選択指示に応じた作業対象部材の溶接作業を指定された作業者に割り付ける処理を行い、割り付けた作業対象部材の総管理量に対する作業当日における溶接作業の目標値を示す作業指示書を作成する作業管理装置とを具備するので、正確な管理量を短時間で計算すると共に、当該管理量に基づいて作成された作業指示書によって各作業者に作業内容を正確に伝達することができる。
【図面の簡単な説明】
【図1】 本発明の一実施形態に係わる構造物の建造作業管理システムの機能構成を示すシステム図である。
【図2】 本発明の一実施形態に係わる構造物の建造作業管理システムの動作を示すフローチャートである。
【符号の説明】
1……管理量演算装置
2……上位管理装置
3……作業管理装置
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction work management system structure.
[0002]
[Prior art]
For example, when building a hull, which is one of large structures, a block in which the entire hull is divided into a plurality of blocks is assembled in advance at the factory, and each block is loaded into a dock or the like and stacked in a predetermined order. Bonding between blocks is performed sequentially. For example, a plurality of blocks located at the bottom of the ship are first placed in the dock and the blocks are joined together, and the blocks are stacked on top of each other to further join each other.
[0003]
In the construction of such a hull, the blocks are mutually joined mainly by welding between members constituting the blocks. Therefore, the main work in the construction of the hull is a welding work by each worker, and this welding work is performed based on the mounting order (mounting schedule) of each block. At the stage of creating the mounting schedule, the amount of work is calculated for each member to be welded based on the design drawing of the block, taking into account the length, thickness, groove, and worker's work posture (welding posture) during welding work. As a result, the total work amount related to the mounting of each block is calculated as the management amount.
[0004]
In the actual work stage, a work schedule is created based on the management amount of each block, and work assignment is instructed to each worker as a work instruction for each work day. Each worker completes the welding work within the day of the instruction at the work location described in the work instruction. Each worker is obliged to report the work at the end of the day's work, and the work progress is managed based on the work report.
[0005]
[Problems to be solved by the invention]
By the way, the above-described conventional technology has the following problems.
(1) Since the calculation of the management amount is performed manually, it takes time and a calculation error is likely to occur.
(2) Since the above-mentioned work instruction is created by hand of the team leader, for example, entry mistakes or omissions are likely to occur, and the contents of the instruction may not be accurately transmitted to the worker. Due to this, it is easy for unfinished work and work delay to occur.
(3) It is difficult to objectively grasp the work ability of each worker, and the work progress is left to the discretion of the team leader and the worker (group member). Therefore, when the work is delayed, the cause (for example, due to the management amount, due to the personnel plan, or due to the ability of the worker) cannot be accurately grasped, resulting in the work delay. It is difficult to take an appropriate response.
(4) Since the work progress is managed by erasing on the work schedule based on the work report from each worker, that is, the work performance is not cumulatively managed, the change status of work progress is accurately determined. It is difficult to grasp.
(5) Since there is nothing that can confirm at a glance the overall progress of work in the hull construction, it is difficult to accurately grasp the overall work progress in the hull construction and take measures against work delays.
[0006]
The present invention has been made in view of the above-mentioned problems, calculates an accurate management amount in a short time, accurately transmits the work contents to each worker, and appropriately manages the work progress. It is intended to be realized.
[0007]
[Means for Solving the Problems]
To achieve the above object, the present invention provides, as a first means related to a construction work management system for a structure, a system for managing the construction work of a structure composed of a plurality of members. The relative angle between the connecting edge and the horizontal plane at the joining position of the member is calculated as a welding posture using the three-dimensional shape data regarding the welding position, and between the members using an evaluation function having the welding posture and the shape of the joining portion as variables Calculates the amount of work required for joining as a management amount, adds this management amount to the 3D shape data and outputs it as design data, and displays a 3D image of the design model based on the 3D shape data while, a process to allocate a worker to the specified welding work object member corresponding to the operation input selection instruction by referring to the 3-dimensional image, Employing means for and a work management unit to create work instruction indicating a target value of the welding operations in the work day to the total management of the operation target member Attach.
[0008]
In addition, as a second means related to a construction work management system for a structure, in the first means, when a structure is constructed by mutually joining a plurality of blocks constructed in advance by a plurality of members, A means is provided that includes a higher level management device 2 that provides only the design data related to the blocks to be joined to the work management device.
[0010]
As a third means related to the construction work management system for a structure, in the first or second means, the work management device is configured such that the worker and the member in the three-dimensional image are designated by the operation input. A method of creating a work instruction sheet for instructing work contents for each time is adopted.
[0011]
As a fourth means related to the construction work management system for a structure, in any one of the first to third means, the work management device displays only the work target member three-dimensionally based on a predetermined operation input. Is adopted.
[0012]
As a fifth means related to the construction work management system for a structure, in any one of the first to fourth means, the work management device is configured to manage the amount of each member according to the work performance of each work day input by the operation. The method of updating is adopted.
[0013]
As a sixth means related to the construction work management system for a structure, in any one of the first to fifth means, the work management device color-codes and displays each member in the three-dimensional image according to the management amount. Is adopted.
[0014]
As a seventh means related to the construction work management system for a structure, a means is adopted in which each block constitutes a hull in any one of the second to sixth means.
[0020]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a construction work management system for a structure according to the present invention will be described with reference to the drawings.
[0021]
In this embodiment, the present invention is applied to construction work management of a hull, which is one of the structures. That is, a plurality of blocks constituting the hull are assembled in advance at a factory, and these blocks are docked. It is related to the work management when building a hull by carrying in and joining together. In this case, first, the blocks located at the bottom of the ship are joined together and the blocks are sequentially stacked on top of each other to construct a hull. In joining between the blocks, specific members (joining target members) of blocks adjacent to each other are welded together.
[0022]
FIG. 1 is a system configuration diagram of this embodiment. As shown in this figure, the construction work management system is composed of a management amount calculation device 1, a higher level management device 2, and a work management device 3 interconnected by a communication line.
[0023]
The managed amount calculation device 1 is provided in the design department of the hull (structure), and the joining between the joining target members based on the three-dimensional shape data relating to the design model of the hull designed in the design department. The amount of work required for this is calculated, and this amount of work is added to the three-dimensional shape data as attribute data of the members to be joined, and output to the upper management apparatus 2 as design data. The managed amount calculation device 1 calculates, for example, a relative angle between a connection side and a horizontal plane at a joining portion of a joining target member based on three-dimensional shape data as a welding posture (joining posture), and the welding posture and the joining portion. A βNL value is calculated using an evaluation function having the shape (plate thickness, groove shape, and weld leg length) as variables. The βNL value calculated in this way is a numerical value indicating a standard work amount (work time) required when welding the joining target members.
[0024]
The upper management device 2 is arranged in a department in charge of production engineering, and relates to a block currently joined from the design data received from the management amount calculation device 1 via a communication line. Only design data (work block design data) is extracted and sequentially provided to the work management apparatus 3. By providing the upper management device 2, only the work block design data related to the actual work currently being performed is supplied to the work management device 3 having a lower processing capacity than the management amount calculation device 1 and the higher management device 2. To do. The management amount calculation device 1 and the upper management device 2 are engineering workstations, for example, while the work management device 3 is a general-purpose personal computer, for example.
[0025]
The work management device 3 is arranged at a work site, and has a function for creating work instructions for each worker and a function for managing work progress. The work management device 3 displays a 3D image of a design model related to a block that is a current work object (joining object) based on the 3D shape data included in the design data, and refers to the 3D image. Thus, a work instruction is created on the basis of the work procedure input by the operator (the work manager such as the head of the work team) and the βNL value of the joining target member included in the design data.
[0026]
In addition, the work management device 3 selects only a joining target member (that is, a member including a βNL value as attribute information) from a three-dimensional image of the design model based on a predetermined operation input. When an operator designates a worker and a joining target member in the SECT image by an operation input, the welding work of the designated joining target member is assigned to the worker. Then, by repeating the above work for each worker, a welding work is assigned to a plurality of workers, and the assignment result is printed out as a work instruction for each worker. The details of the procedure for creating the work instruction will be described later.
[0027]
Further, the work management device 3 is configured to update the βNL value of each joining target member according to the progress when the actual value of the welding work is input by operating the keyboard or the like. Each member to be welded is color-coded according to the remaining management amount obtained by subtracting the actual value from the βNL value, and the remaining management of the member to be joined is instructed by an operation instruction with a pointing device or the like. The quantity is configured to be displayed numerically.
[0028]
Next, a time-series operation of the construction work management system configured as described above will be described with reference to the flowchart shown in FIG. This flowchart shows a procedure for creating a work instruction sheet using the work management apparatus 3.
[0029]
In this construction work management system, in the state where only the work block design data is extracted from the design data by the host management apparatus 2, the work management apparatus 3 is operated for various purposes to create work instructions and the progress of work. The situation is confirmed. That is, at the time when the joining work of each block is performed at the work site, the βNL value is calculated by the management amount calculation device 1, the design data generation process based on the βNL value and the three-dimensional shape data, and the work by the upper management device 2 The block design data extraction processing has already been completed as preprocessing. In such a state, the work instruction for each worker is created as follows using the work management device 3.
[0030]
Here, the βNL value can be calculated by using an evaluation function having variables of the welding posture and the shape of the joint part (plate thickness, groove shape, and weld leg length) obtained from the three-dimensional shape data of the work target block. It is automatically calculated by the device 1. That is, in the present embodiment, since the βNL value that has been manually calculated is automatically calculated by the management amount calculation device 1, the time required to calculate the βNL value is shortened and there is very little room for calculation errors.
[0031]
In the work instruction creation process, first, design data (work block design data) is fetched. When the operator inputs a work block design data import instruction, the work management device 3 acquires the work block design data from the host management device 2 via the communication line (step S1). As a result, the work management apparatus 3 displays an image of the three-dimensional shape of the work target block based on the work block design data. When the operator gives an instruction to display the SECT image, the work management apparatus 3 extracts only the joining target member to which the βNL value is assigned as the attribute information and displays it as the SECT image (step S2).
[0032]
The subsequent processing is processing for assigning a specific joining target member as a work target for each worker of each work group. When the operator inputs and inputs the team leader name and the worker name, the work start time and the work end time of the work group (step S3), and further specifies a specific joining target member on the SECT image, the joining target member is It is assigned to the worker corresponding to the worker name (step S4). Here, by repeating the operation designation of the joining target member on the SECT image, a plurality of joining target members can be assigned to the worker corresponding to the worker name.
[0033]
Usually, since the hull welding operation is composed of a plurality of work groups and each work group is composed of a plurality of workers, the judgment in step S5 is “No”, so that the operator can name other workers. The operations of steps S2 and S3 are repeated, and work assignments to workers of work groups corresponding to other worker names are sequentially performed. When the work assignment to all workers is completed as described above and the operator gives an operation instruction for printing, the work management device 3 sends the setting data based on the reasons in steps S2 and S3 to the printer. The work instructions for each worker are printed in color (step S6), and the work instruction creation process ends.
[0034]
According to such a work instruction creation process, the operator can accurately and accurately assign a plurality of members to be joined to each worker, and there is room for occurrence of assignment mistakes or assignment leakage. Extremely less.
[0035]
Further, the work instruction sheet of the present embodiment describes the three-dimensional shape of the work target block, the three-dimensional shape of the joining target member assigned as the work target, and the work schedule on the work day. This work schedule is a graph display of the target value of the work day for the total βNL value of single or plural joining target members assigned as work targets. With the work instruction sheet configured as described above, each worker is accurately instructed on the work location.
[0036]
Subsequently, each worker performs welding work based on the work instruction sheet prepared as described above, and when one day of work is completed, the actual value of welding work related to each joining target member is reported to each group head. To do. The actual value of each member to be joined is input to the work management apparatus 3 using a keyboard or the like. When the actual value is input, the work management device 3 calculates a remaining management amount obtained by subtracting the actual value from the βNL value of each joining target member, and updates the βNL value of each joining target member to the remaining management amount.
[0037]
As a result, each joining target member displayed on the progress confirmation image (three-dimensional image) is color-coded according to the remaining management amount, and when an operation instruction is given to any joining target member using a pointing device or the like, The remaining management amount of the joining target member is displayed numerically. Therefore, it is possible to easily confirm the progress of the welding operation for each joining target member by the SECT image based on the remaining management amount updated in this way.
[0038]
In the progress confirmation image, the progress status of the work day can be confirmed based on the actual value. In other words, each joining target member displayed on the progress confirmation image is color-coded according to the actual value on the day of the work, and the actual value of the joining target member that has been instructed for operation is numerically displayed. By using such a progress confirmation image, a work plan for the next day can be easily drafted.
[0039]
【The invention's effect】
As described above , according to the construction work management system for a structure according to the present invention, a system for managing the construction work of a structure composed of a plurality of members, the three-dimensional shape relating to the design model of the structure Calculate the relative angle between the connecting edge and the horizontal plane at the joining position of the member as data using the data as a welding posture, and work required for joining between the members using an evaluation function with the welding posture and the shape of the joining portion as variables A management amount calculation device that calculates the amount, adds this work amount to the three-dimensional shape data, and outputs it as design data; displays a three-dimensional image of the design model based on the three-dimensional shape data; It performs a process of allocating a reference to the specified welding work object member corresponding to the operation input selection instruction by an operator, the total administration amount of the operation target member allocation Because and a work management unit to create work instruction indicating a target value of the welding operations in the work day which, together to calculate the exact administration amount in a short period of time, work instructions created based on the management amount The work content can be accurately transmitted to each worker.
[Brief description of the drawings]
FIG. 1 is a system diagram showing a functional configuration of a construction work management system for a structure according to an embodiment of the present invention.
FIG. 2 is a flowchart showing an operation of a construction work management system for a structure according to an embodiment of the present invention.
[Explanation of symbols]
1... Management amount calculation device 2... Upper management device 3... Work management device

Claims (5)

複数の部材から構成される構造物の建造作業を管理するシステムであって、
前記構造物の設計モデルに関する3次元形状データを用いて部材の接合位置における接続辺と水平面との相対角度を溶接姿勢として算出し、当該溶接姿勢と前記接合部位の形状とを変数とする評価関数を用いて部材間の接合に要する作業量を管理量として算出し、この管理量を前記3次元形状データに付加し設計データとして出力する管理量演算装置(1)と、
前記3次元形状データに基づいて前記設計モデルの3次元画像を表示すると共に、当該3次元画像を参照することにより操作入力された選択指示に応じた作業対象部材の溶接作業を指定された作業者に割り付ける処理を行い、割り付けた作業対象部材の総管理量に対する作業当日における溶接作業の目標値を示す作業指示書を作成する作業管理装置(3)と、
を具備することを特徴とする構造物の建造作業管理システム。
A system for managing construction work of a structure composed of a plurality of members,
An evaluation function that uses the three-dimensional shape data relating to the design model of the structure as a welding posture to calculate the relative angle between the connection side and the horizontal plane at the joining position of the members, and uses the welding posture and the shape of the joining portion as variables. and manage calculation unit for outputting the amount of work required for the bonding is calculated as the management amount, as design data by adding the management amount to the three-dimensional shape data between the members with (1),
An operator who displays a three-dimensional image of the design model based on the three-dimensional shape data and is designated to perform a welding operation on a work target member in accordance with a selection instruction input by referring to the three-dimensional image. A work management device (3) for creating a work instruction indicating a target value of the welding work on the work day with respect to the total management amount of the assigned work target members ;
A construction work management system for a structure, comprising:
複数の部材によって予め構築された複数のブロックを相互接合して構造物を建造する場合には、現在接合対象となっているブロックに関する設計データを作業管理装置(3)に提供する上位管理装置(2)を備える、ことを特徴とする請求項1記載の構造物の建造作業管理システム。  When building a structure by mutually joining a plurality of blocks constructed in advance by a plurality of members, an upper management device (3) that provides design data relating to the block currently being joined to the work management device (3). The structure construction management system according to claim 1, comprising 2). 作業管理装置(3)は、操作入力によって作業者と3次元画像内の部材が指定されると、作業者毎に作業内容を指示する作業指示書を作成する、ことを特徴とする請求項1または2記載の構造物の建造作業管理システム。The work management device (3) creates a work instruction sheet for instructing work contents for each worker when a worker and a member in a three-dimensional image are designated by an operation input. Or the construction work management system of the structure of 2 description. 作業管理装置(3)は、所定の操作入力に基づいて作業対象部材のみを3次元表示する、ことを特徴とする請求項1〜3いずれかに記載の構造物の建造作業管理システム。The construction management system for a structure according to any one of claims 1 to 3, wherein the work management device (3) three-dimensionally displays only the work target member based on a predetermined operation input. 作業管理装置(3)は、操作入力された各作業日の作業実績に応じて各部材の管理量を更新する、ことを特徴とする請求項1〜4いずれかに記載の構造物の建造作業管理システム。The work management device (3) updates the management amount of each member in accordance with the work performance of each work day input by operation, and the construction work of the structure according to any one of claims 1 to 4 Management system.
JP2001127744A 2001-04-25 2001-04-25 Construction work management system for structures Expired - Fee Related JP4698875B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001127744A JP4698875B2 (en) 2001-04-25 2001-04-25 Construction work management system for structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001127744A JP4698875B2 (en) 2001-04-25 2001-04-25 Construction work management system for structures

Publications (2)

Publication Number Publication Date
JP2002324154A JP2002324154A (en) 2002-11-08
JP4698875B2 true JP4698875B2 (en) 2011-06-08

Family

ID=18976552

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001127744A Expired - Fee Related JP4698875B2 (en) 2001-04-25 2001-04-25 Construction work management system for structures

Country Status (1)

Country Link
JP (1) JP4698875B2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02127773A (en) * 1988-11-08 1990-05-16 Nippon Atom Ind Group Co Ltd Plant construction process control support system
JPH06168303A (en) * 1991-03-01 1994-06-14 Hitachi Ltd Method for supporting instalation plan and its device
JPH0773157A (en) * 1993-06-15 1995-03-17 Ishikawajima Harima Heavy Ind Co Ltd Evaluating method for welding workability in large structure
JPH11237000A (en) * 1998-02-25 1999-08-31 Chiyoda Corp Pipeline construction planning administrative system
JPH11328276A (en) * 1998-03-16 1999-11-30 Mitsubishi Heavy Ind Ltd Scheduling system
JP2000076333A (en) * 1998-08-27 2000-03-14 Komatsu Ltd Working progress designing device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02127773A (en) * 1988-11-08 1990-05-16 Nippon Atom Ind Group Co Ltd Plant construction process control support system
JPH06168303A (en) * 1991-03-01 1994-06-14 Hitachi Ltd Method for supporting instalation plan and its device
JPH0773157A (en) * 1993-06-15 1995-03-17 Ishikawajima Harima Heavy Ind Co Ltd Evaluating method for welding workability in large structure
JPH11237000A (en) * 1998-02-25 1999-08-31 Chiyoda Corp Pipeline construction planning administrative system
JPH11328276A (en) * 1998-03-16 1999-11-30 Mitsubishi Heavy Ind Ltd Scheduling system
JP2000076333A (en) * 1998-08-27 2000-03-14 Komatsu Ltd Working progress designing device

Also Published As

Publication number Publication date
JP2002324154A (en) 2002-11-08

Similar Documents

Publication Publication Date Title
Staub-French et al. 3D and 4D modeling for design and construction coordination: issues and lessons learned
US5016170A (en) Task management
JP4450775B2 (en) Hull block mounting method and hull block mounting simulation system usable in the method
JPH09268760A (en) Schedule control support system
KR20130016620A (en) 3d process management method for bim(building information modeling)
WO2009135183A1 (en) Automated generation of 3d models from 2d computer-aided design (cad) drawings
JP6451139B2 (en) Arrangement plan support system, arrangement plan support method, and arrangement plan support program
JP2017188118A (en) System for digitally supporting work process
US8326664B2 (en) System for supporting carry-in operation planning
JP2011053999A (en) Plant construction management system and operation process management method therefor
CN109903019A (en) Project progress monitor system based on BIM
US20100274374A1 (en) System and process for the detailed design and production of reinforcement for buildings
JP2020119240A (en) Construction material calculating system
JP2010128646A (en) Marshaling support system
Ko et al. Making formwork design lean
Tiwari et al. Pull planning as a mechanism to deliver constructible design
JP4698875B2 (en) Construction work management system for structures
Yang et al. VIZOR: facilitating cyber-physical workflows in prefabrication through augmented reality
KR20120009237A (en) Support Modeling & Drawing creation system and method
CN109680946A (en) Based on assembled feed back on-site decoration implementation method, device, equipment and medium
JP6799344B1 (en) Architectural system
JP2009020728A (en) Process control system and method
TWI438705B (en) Method for coordinated operation of architecture design
JP2022155087A (en) Integrated data generation system, construction plan management system, integrated data generation method, construction plan management method, and program
JP2014071651A (en) Process management system

Legal Events

Date Code Title Description
A625 Written request for application examination (by other person)

Free format text: JAPANESE INTERMEDIATE CODE: A625

Effective date: 20080227

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100607

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100622

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100811

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110222

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110302

R150 Certificate of patent or registration of utility model

Ref document number: 4698875

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140311

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140311

Year of fee payment: 3

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees