CN107178210A - The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall - Google Patents
The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall Download PDFInfo
- Publication number
- CN107178210A CN107178210A CN201710561359.XA CN201710561359A CN107178210A CN 107178210 A CN107178210 A CN 107178210A CN 201710561359 A CN201710561359 A CN 201710561359A CN 107178210 A CN107178210 A CN 107178210A
- Authority
- CN
- China
- Prior art keywords
- line box
- wall
- construction method
- construction
- vertical supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall, comprise the following steps:S1:According to the intensity of wall line box, the cross-connecting apparatus of suitable length is chosen;S2:According to line box height, the vertical supporting device of appropriate length is chosen, bottom and the ground of vertical supporting device are fixed;S3:According to line box absolute altitude, vertical supporting device and cross-connecting apparatus are fixed;S4:With the squareness of the unified adjustment line box of infrared ray gradienter and from wall spacing;S5:Many line box are concentrated after pre-buried be fixed on cross-connecting apparatus, then spool is cut in length, access line box.The present invention can be carried out the integral manufacturing of support in advance, carry out modular construction, improve efficiency of construction according to building size and construction speed;Recruitment efficiency can be improved according to the electric provided box of working procedure schedule ahead, pipe construction, save recruitment cost;It is pre-buried in advance with this construction method, the work post process such as it is easily installed, builds by laying bricks or stones and interting, it is ensured that construction speed.
Description
Technical field
The present invention relates to a kind of accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall.
Background technology
Forming Quality to wall line box in modern China Democratic National Construction Association's engineering requires more and more higher, and third party's inspection had been included in recent years
The essential items for inspection of (out-of-competition testing) are looked into, while being also the inspection project of household acceptance.
The content of the invention
It is accurate using the multi-thread box of civil buildings wall it is an object of the invention to overcome the deficiencies of the prior art and provide one kind
Pre-embedded construction method, it is pre-buried to being carried out on wall at many line box concentrations before building wall, with cross-connecting apparatus and vertically
Support meanss are fixed, and pre-buried fixing intensity is good, rationally using the artificial duration, and many line box of entering of efficiently and accurately are installed concentratedly.
The purpose of the present invention is achieved through the following technical solutions:The accurate Embedment Construction side of many line box of China Democratic National Construction Association's wall
Method, comprises the following steps:
S1:According to the intensity of wall line box, the cross-connecting apparatus of suitable length is chosen;
S2:According to line box height, the vertical supporting device of appropriate length is chosen, bottom and the ground of vertical supporting device are consolidated
It is fixed;
S3:According to line box absolute altitude, vertical supporting device and cross-connecting apparatus are fixed;
S4:With the squareness of the unified adjustment line box of infrared ray gradienter and from wall spacing;Described is from waiting to build from wall spacing
0.5~2cm of wall, is 1cm preferably from wall spacing.
S5:Many line box are concentrated after pre-buried be fixed on cross-connecting apparatus, then spool is cut in length, access line box.
It is preferred that, in the step S5, spool is PVC spools, and PVC spools are passed and cut from beam and/or plate
Good length, is sequentially ingressed into line box, spatial arrangement is should be noted that during adapter, it is to avoid spool intersects.
It is preferred that, the bottom bending of vertical supporting device, and fixed by expansion bolt with ground.Build completion by laying bricks or stones
Afterwards, the expansion bolt on ground is detachable.
It is preferred that, described cross-connecting apparatus is zinc-plated C-type steel with holes, line box panel mounting hole and zinc-plated band
The hole correspondence of hole C-type steel, passes through correspondence hole using self-tapping screw shimming, zinc-plated C-type steel and line box with holes is effectively connected
Fixation is connect, the self-tapping screw and pad being connected with line box are detachable.Making support using eye c-type galvanized steel, (lateral connection is filled
Put), intensity is high, and good fixing effect, connecting bolt can be adjusted flexibly in eyelet, and installation site is accurate.
It is preferred that, if line box panel mounting hole and the hole of zinc-plated C-type steel with holes have deviation, power drill can be used
Corresponding aperture is bored in C-type steel.
It is preferred that, in ground mark positioning fixing point.
It is preferred that, with paint in ground mark positioning fixing point.
It is preferred that, the line box height designed according to blueprint chooses one section of zinc-plated C-type steel with holes and is used as vertical supporting
Device, one end bends 80~110 degree, and bending end passes through hole with expansion bolt, is fixed on the positioning fixed point on ground.Using
Eye c-type galvanized steel makees support (vertical supporting device), and intensity is high, and good fixing effect, connecting bolt can be flexible in eyelet
Adjustment, installation site is accurate.
It is preferred that, present invention additionally comprises step S6, S6:After the completion of building by laying bricks or stones, cross-connecting apparatus and vertical supporting
Device is detachable, after the completion of dismounting, can install and reuse in other floors, room.
It is preferred that, construction is with wall plastering face, based on line box center line and cassette bottom absolute altitude, to the collection of many line box
In it is pre-buried carry out accurate Three dimensions control, installation accuracy, quality are greatly improved.
The beneficial effects of the invention are as follows:
1st, it can carry out the integral manufacturing of support in advance according to building size and construction speed, carry out modular construction, carry
High efficiency of construction.
2nd, support (support includes cross-connecting apparatus and vertical supporting device) is installed, dismantled flexibly and easily, can be repeated
Use, reduce Master Cost.
3rd, recruitment efficiency can be improved according to the electric provided box of working procedure schedule ahead, pipe construction, saves recruitment cost.
4th, it is pre-buried in advance with this construction method, the work post process such as it is easily installed, builds by laying bricks or stones and interting, when reduces masonry and building cooperation by laying bricks or stones
Between, beneficial to process flexible arrangement, it is ensured that construction speed.
5th, the construction method efficiency of construction is high, saves recruitment, reduces auxiliary material materials, it is ensured that duration progress, improves construction matter
Amount, is that unit in charge of construction produces very big economic benefit, while also having larger social benefit, with higher popularization and application valency
Value.
Brief description of the drawings
Fig. 1 is the structural representation that cross-connecting apparatus of the present invention is connected with line box;
Fig. 2 is the structural representation of the fixed many line box of cross-connecting apparatus of the present invention series connection;
Fig. 3 is the structural representation that vertical supporting device of the present invention is connected with ground;
Fig. 4 is one of schematic structural view of the invention;
Fig. 5 is the two of schematic structural view of the invention;
In figure, 1- cross-connecting apparatus, 2- line box, 3- vertical supporting devices, 4- expansion bolts, 5- ground, 6- walls.
Embodiment
Technical scheme is described in further detail below in conjunction with the accompanying drawings, but protection scope of the present invention is not limited to
It is as described below.
As shown in Fig. 1~Fig. 5, devised and drawn the blueprint according to Hydroelectric Project Construction, concentrated in many line box 2 at wall 6, support is fixed
Line setting, with the good position of line box 2 for needing to connect of paint mark and the fixed position of support.Specifically, China Democratic National Construction Association's wall 6
The accurate pre-embedded construction method of many line box 2, comprises the following steps:
S1:As shown in figure 1, according to the intensity of the line box 2 of wall 6, choosing the cross-connecting apparatus 1 of suitable length;
S2:As shown in figure 3, according to the height of line box 2, choosing the vertical supporting device 3 of appropriate length, vertical supporting device 3
Bottom fixed with ground 5;
S3:As shown in Figure 4, Figure 5, according to the absolute altitude of line box 2, vertical supporting device 3 is fixed with cross-connecting apparatus 1;
S4:With the squareness of the unified adjustment line box 2 of infrared ray gradienter and from wall spacing;
S5:Many line box 2 concentrate pre-buried after being fixed on cross-connecting apparatus 1, then spool is cut into length, access line box 2
It is interior.
Preferably, in the step S5, spool is PVC spools, and PVC spools pass from beam and/or plate and cut length,
It is sequentially ingressed into line box 2, spatial arrangement is should be noted that during adapter, it is to avoid spool intersects.
Preferably, the bottom bending of vertical supporting device 3, and being fixed by expansion bolt 4 with ground 5.After the completion of building by laying bricks or stones,
Expansion bolt 4 on ground 5 is detachable.
Preferably, described cross-connecting apparatus 1 is zinc-plated C-type steel with holes, the panel mounting hole of line box 2 and zinc-plated C with holes
The hole correspondence of shaped steel, correspondence hole is passed through using self-tapping screw shimming, and zinc-plated C-type steel and line box 2 with holes are effectively connected
Fixed, the self-tapping screw and pad being connected with line box 2 are detachable.The preferred metallic gasket of pad.The pad is flat shim
Or spring shim.As shown in Fig. 2 at many concentrations of line box 2, according to position of the line box 2 on wall 6, line box 2 is connected successively
It is fixed in same zinc-plated C-type steel with holes, fixed form equally adds metallic gasket using self-tapping screw.
Preferably, can be with power drill in c-type if the panel mounting hole of line box 2 and the hole of zinc-plated C-type steel with holes have deviation
Corresponding aperture is bored on steel.
Preferably, in the mark positioning fixing point of ground 5.
Preferably, with paint in the mark positioning fixing point of ground 5.
Preferably, the height of line box 2 designed according to blueprint, chooses one section of zinc-plated C-type steel with holes and is used as vertical supporting device
3, one end bends 80~110 degree, and preferably 90 degree, bending end passes through hole with expansion bolt 4, and the positioning for being fixed on ground 5 is fixed
At point.
Preferably, present invention additionally comprises step S6, S6:After the completion of building by laying bricks or stones, cross-connecting apparatus 1 and vertical supporting device 3
Detachably, after the completion of dismounting, it can install and reuse in other floors, room.
Preferably, the present invention is installed is plastered face with wall 6, based on the center line of line box 2 and cassette bottom absolute altitude, to many line box 2
Concentration it is pre-buried carry out accurate Three dimensions control, installation accuracy, quality are greatly improved.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, it is noted that all
Any modifications, equivalent substitutions and improvements made within the spirit and principles in the present invention etc., should be included in the guarantor of the present invention
Within the scope of shield.
Claims (10)
1. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall, it is characterised in that:It comprises the following steps:
S1:According to the intensity of wall line box, the cross-connecting apparatus of suitable length is chosen;
S2:According to line box height, the vertical supporting device of appropriate length is chosen, bottom and the ground of vertical supporting device are fixed;
S3:According to line box absolute altitude, vertical supporting device and cross-connecting apparatus are fixed;
S4:With the squareness of the unified adjustment line box of infrared ray gradienter and from wall spacing;
S5:Many line box are concentrated after pre-buried be fixed on cross-connecting apparatus, then spool is cut in length, access line box.
2. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1, it is characterised in that:The step S5
In, spool is PVC spools, and PVC spools pass from beam and/or plate and cut length, be sequentially ingressed into line box, should be noted during adapter
Meaning spatial arrangement, it is to avoid spool intersects.
3. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1, it is characterised in that:Vertical supporting is filled
The bottom bending put, and fixed by expansion bolt with ground.
4. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1 or 2 or 3, it is characterised in that:It is described
Cross-connecting apparatus be zinc-plated C-type steel with holes, line box panel mounting hole is corresponding with the hole of zinc-plated C-type steel with holes, utilizes oneself
Tapping shimming passes through correspondence hole, and zinc-plated C-type steel and line box with holes are effectively connected.
5. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 4, it is characterised in that:If line box panel
There is deviation in mounting hole and the hole of zinc-plated C-type steel with holes, corresponding aperture can be bored in C-type steel with power drill.
6. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1, it is characterised in that:In ground mark
Position fixing point.
7. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1 or 6, it is characterised in that:With paint
In ground mark positioning fixing point.
8. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 7, it is characterised in that:Set according to blueprint
The line box height of meter, chooses one section of zinc-plated C-type steel with holes as vertical supporting device, one end bends 80~110 degree, and bending end is used
Expansion bolt passes through hole, is fixed on the positioning fixed point on ground.
9. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1 or 8, it is characterised in that:It is also wrapped
Include step S6, S6:After the completion of building by laying bricks or stones, cross-connecting apparatus and vertical supporting device are detachable, can be in other buildings after the completion of dismounting
Layer, room, which are installed, to be reused.
10. the accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall according to claim 1, it is characterised in that:Construction is with wall
Body is plastered face, based on line box center line and cassette bottom absolute altitude, pre-buried to the concentrations of many line box to carry out accurate Three dimensions control, is installed
Precision, quality are greatly improved.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710561359.XA CN107178210A (en) | 2017-07-11 | 2017-07-11 | The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710561359.XA CN107178210A (en) | 2017-07-11 | 2017-07-11 | The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107178210A true CN107178210A (en) | 2017-09-19 |
Family
ID=59845714
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710561359.XA Pending CN107178210A (en) | 2017-07-11 | 2017-07-11 | The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107178210A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108035542A (en) * | 2017-11-23 | 2018-05-15 | 中国五冶集团有限公司 | Wall pre-embedded alignment device and its routing method |
CN108316653A (en) * | 2018-03-20 | 2018-07-24 | 中国五冶集团有限公司 | Top plate fixes the accurate installation pre-buried structure and construction method of wall wire box holder |
CN108539687A (en) * | 2018-05-22 | 2018-09-14 | 中国五冶集团有限公司 | A kind of fine adjustment type civil buildings townhouse wire box accurately pre-installs structure and construction method |
CN108797954A (en) * | 2018-07-12 | 2018-11-13 | 江苏南通三建集团股份有限公司 | The limit construction method of the pre-buried wire box of structure |
CN109119957A (en) * | 2018-09-30 | 2019-01-01 | 中铁十六局集团城市建设发展有限公司 | A kind of electrical pre-buried PVC spool goes out terrestrial positioning protective device |
CN109586204A (en) * | 2018-12-24 | 2019-04-05 | 成都建工第二建筑工程有限公司 | Method for installing the fixed structure and the secondary piping of installation of secondary piping |
CN109914800A (en) * | 2019-03-15 | 2019-06-21 | 中国五冶集团有限公司 | A kind of civil buildings townhouse wire box accurately pre-installs structure and construction method |
CN111711116A (en) * | 2020-06-11 | 2020-09-25 | 德恩环保建材盐城有限公司 | Pre-embedding process for electric pipeline box of concrete light partition wall board strip |
CN111809869A (en) * | 2020-07-30 | 2020-10-23 | 广西建工集团第五建筑工程有限责任公司 | Positioning and fixing device and method capable of ensuring same surface of wire box and outer surface of installation wall |
CN113565335A (en) * | 2021-07-26 | 2021-10-29 | 广东善建建设股份有限公司 | BIM-based masonry engineering construction device and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05331949A (en) * | 1990-09-03 | 1993-12-14 | Nippon Pitsuto:Kk | Floor structure with duct and its construction |
JPH0923553A (en) * | 1995-07-07 | 1997-01-21 | Fujita Corp | Device and method for winding power cable elevator |
CN103321436A (en) * | 2013-07-10 | 2013-09-25 | 成都市第八建筑工程公司 | Pre-installation construction method for wire box on building bricked body and pre-installation supporting frame thereof |
CN104989099A (en) * | 2015-05-22 | 2015-10-21 | 重庆一建建设集团有限公司 | Pre-embedded wire box construction method |
CN205051281U (en) * | 2015-09-02 | 2016-02-24 | 中国建筑第八工程局有限公司 | Pre -buried location structure of shear force wall line box |
-
2017
- 2017-07-11 CN CN201710561359.XA patent/CN107178210A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05331949A (en) * | 1990-09-03 | 1993-12-14 | Nippon Pitsuto:Kk | Floor structure with duct and its construction |
JPH0923553A (en) * | 1995-07-07 | 1997-01-21 | Fujita Corp | Device and method for winding power cable elevator |
CN103321436A (en) * | 2013-07-10 | 2013-09-25 | 成都市第八建筑工程公司 | Pre-installation construction method for wire box on building bricked body and pre-installation supporting frame thereof |
CN104989099A (en) * | 2015-05-22 | 2015-10-21 | 重庆一建建设集团有限公司 | Pre-embedded wire box construction method |
CN205051281U (en) * | 2015-09-02 | 2016-02-24 | 中国建筑第八工程局有限公司 | Pre -buried location structure of shear force wall line box |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108035542A (en) * | 2017-11-23 | 2018-05-15 | 中国五冶集团有限公司 | Wall pre-embedded alignment device and its routing method |
CN108316653A (en) * | 2018-03-20 | 2018-07-24 | 中国五冶集团有限公司 | Top plate fixes the accurate installation pre-buried structure and construction method of wall wire box holder |
CN108539687B (en) * | 2018-05-22 | 2023-10-13 | 中国五冶集团有限公司 | Fine-tuning type civil building line-connecting and line-arranging box accurate pre-installation structure and construction method |
CN108539687A (en) * | 2018-05-22 | 2018-09-14 | 中国五冶集团有限公司 | A kind of fine adjustment type civil buildings townhouse wire box accurately pre-installs structure and construction method |
CN108797954A (en) * | 2018-07-12 | 2018-11-13 | 江苏南通三建集团股份有限公司 | The limit construction method of the pre-buried wire box of structure |
CN109119957A (en) * | 2018-09-30 | 2019-01-01 | 中铁十六局集团城市建设发展有限公司 | A kind of electrical pre-buried PVC spool goes out terrestrial positioning protective device |
CN109586204A (en) * | 2018-12-24 | 2019-04-05 | 成都建工第二建筑工程有限公司 | Method for installing the fixed structure and the secondary piping of installation of secondary piping |
CN109586204B (en) * | 2018-12-24 | 2024-04-19 | 成都建工第二建筑工程有限公司 | Fixing structure for installing secondary piping and method for installing secondary piping |
CN109914800A (en) * | 2019-03-15 | 2019-06-21 | 中国五冶集团有限公司 | A kind of civil buildings townhouse wire box accurately pre-installs structure and construction method |
CN109914800B (en) * | 2019-03-15 | 2021-02-26 | 中国五冶集团有限公司 | Accurate pre-installation structure and construction method for civil building line-connecting and line-arranging pipes |
CN111711116A (en) * | 2020-06-11 | 2020-09-25 | 德恩环保建材盐城有限公司 | Pre-embedding process for electric pipeline box of concrete light partition wall board strip |
CN111809869B (en) * | 2020-07-30 | 2023-08-18 | 广西建工第五建筑工程集团有限公司 | Positioning and fixing device and method capable of ensuring same surface of wire box and outer surface of installation wall |
CN111809869A (en) * | 2020-07-30 | 2020-10-23 | 广西建工集团第五建筑工程有限责任公司 | Positioning and fixing device and method capable of ensuring same surface of wire box and outer surface of installation wall |
CN113565335A (en) * | 2021-07-26 | 2021-10-29 | 广东善建建设股份有限公司 | BIM-based masonry engineering construction device and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107178210A (en) | The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall | |
CN106381948B (en) | A kind of GRC curtain wall panels mounting process | |
CN209585294U (en) | A kind of tower crane attachment pre-embedded device based on aluminum dipping form construction | |
CN102235094A (en) | Construction method for carrying out accurate adjustment on position of prefabricated part | |
CN214942417U (en) | Prefabricated PC concrete fire hydrant case entrance to a cave structure | |
CN102493471A (en) | Suspending installation construction process method of structural foot margin anchor bolt | |
CN207211784U (en) | A kind of positioner of prefabricated components installation reinforcing bar | |
CN103510715A (en) | Method for calibrating concrete prefabricated wallboard installation construction datum and calibrating device | |
CN114370188A (en) | Construction method for public pipe gallery of industrial plant area in severe cold region | |
CN108468431A (en) | A kind of fine adjustment type civil buildings electronic box accurately pre-installs construction method and structure | |
CN104153495A (en) | Multifunctional lightweight concrete curtain wall connecting structure | |
CN108539687A (en) | A kind of fine adjustment type civil buildings townhouse wire box accurately pre-installs structure and construction method | |
CN113374138B (en) | Construction method of concrete dry-hanging curtain wall | |
CN206784606U (en) | Adjustable built-in fitting | |
CN117489098A (en) | Construction method of aluminum alloy template of high-rise residence | |
CN205743048U (en) | Correction positioner installed by a kind of curtain wall large-size column | |
CN114934673B (en) | Construction method of glass curtain wall of wood structure system | |
JP2011074632A (en) | Unit structure of anchor bolt used for construction of foundation for equipment, and method of construction of foundation for equipment using the unit structure | |
CN208890166U (en) | Anti-deformation frame structure mounted in distribution box shell | |
CN203238657U (en) | Tool type anchor bolt mounting positioner | |
CN105735228A (en) | Construction method and installation accuracy control method of rack systems of high-lift rack climbing type ship lift | |
CN205933000U (en) | Super high-rise external hanging movable arm tower crane climbing supporting device | |
CN210685062U (en) | Plug-in structure for assembly type building wall | |
CN103953183A (en) | Wall ceramic tile fixing tool | |
CN207194449U (en) | A kind of anti-bank railing installation hole structure pre-embedded device of balcony |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |