CN108797954A - The limit construction method of the pre-buried wire box of structure - Google Patents
The limit construction method of the pre-buried wire box of structure Download PDFInfo
- Publication number
- CN108797954A CN108797954A CN201810763662.2A CN201810763662A CN108797954A CN 108797954 A CN108797954 A CN 108797954A CN 201810763662 A CN201810763662 A CN 201810763662A CN 108797954 A CN108797954 A CN 108797954A
- Authority
- CN
- China
- Prior art keywords
- wire box
- group
- pvc
- constituted
- buried
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses the limit construction methods of the pre-buried wire box of structure, when carrying out building structure body construction, the first step:First buy the pvc pipe of finished product;Second step:The pvc pipe of finished product is processed into PVC short tubes and PVC casings, is allowed to meet(What 3 or more single wire box were constituted)The pre-buried size requirement of group's wire box;Third walks:By 3 or more single wire box group wire box and PVC casings and PVC short tube organic assemblings, formed(What 3 or more single wire box were constituted)Group's wire box module;4th step:Wire box space is filled using objects such as sawdusts, is formed(What 3 or more single wire box were constituted)Group's wire box component;5th step:According to different structures, complete(What 3 or more single wire box were constituted)Group's wire box component it is pre-buried;6th step:Cleaning(What 3 or more single wire box were constituted)Sundries in group's wire box;7th step:The PVC short tubes in wire box are cut off with hand-operated tools.
Description
Technical field
The present invention relates on a kind of structure(What 3 or more single wire box were constituted)The pre-buried construction skill of group's wire box
Art, and in particular to the limit construction method of the pre-buried wire box of structure.
Background technology
In current building, the functional apparatus such as indoor corresponding illumination, air-conditioning are available in all varieties.Regardless of setting
It is standby, it can all be related to the panel with control actions such as control illumination, air-conditionings;The quality of panel installation will directly influence building
Beautiful and functions of the equipments realizations, especially(What 3 or more single wire box were constituted)The panel installation quality of group's wire box is just
Seem particularly significant.By traditional pre-buried wire box of method, especially(What 3 or more single wire box were constituted)Group's wire box it is pre-
Bury spacing disunity between often will appear wire box, irregular above and below wire box;It is too small even to there is wire box spacing, without embedding between wire box
Fill out phenomena such as object, panel can not be installed.
It is pre-buried for wire box, especially(What 3 or more single wire box were constituted)The difficulty of the pre-buried operation of group's wire box,
Unit in charge of construction by holding a meeting, implement the measures such as tell somebody what one's real intentions are and strengthen the sense of responsibility of operator, reinforce project management department quality management people
The tours of inspection of member, find to go wrong many kinds of measures such as rectification immediately, but the spacing for remaining difficult to thoroughly solve between wire box is not united
One, irregular problem above and below wire box.Therefore(What 3 or more single wire box were constituted)The pre-buried spacing of group's wire box is uneven, no
Phenomena such as neat, is customary at the construction field (site), and therefore, construction site is badly in need of offer one kind and is thoroughly solved(3 or more single
What wire box was constituted)The technical solution of the pre-buried difficulty of group's wire box.
Invention content
It is thoroughly solved the technical problem to be solved in the present invention is to provide a kind of(What 3 or more single wire box were constituted)Group
The construction method of the pre-buried difficulty of wire box.
Distance is irregular between box to solve 3 or more the pre-buried middle appearance of single wire box, upper and lower technical problems such as irregular,
The present invention provides the pre-buried limit group wire box of structure, including wire box, sets PVC short tubes in the wire box, is used between the wire box
PVC casing connections, space is filled with filler in the wire box.
Further filler is sawdust, luminous agent or cystosepiment.
The limit construction method of the pre-buried wire box of structure, includes the following steps:
Group's wire box establishment of component:
The first step:Prepare PVC long tubes and PVC short tubes;20 ㎜ of PVC long tubes diameter, length=wire box number * 86+(Wire box number -1)*
20;PVC short tubes diameter 25 ㎜, 20 ㎜ of length, do not go here and there wire box;
Second step:3 or more single wire box and PVC long tubes and PVC short tube organic assemblings, PVC short tubes are placed on PVC long tubes
On;PVC long tube strings take 3 or more single wire box, and in PVC long tube PULL BOXs, intermittent puts on PVC short tubes, so that it is guaranteed that
Wire box spacing is to separate as 20 ㎜ by the distance between two adjacent lines boxes, PVC short tubes;It is formed(3 or more single wire box are constituted
's)Group's wire box module;
Third walks:Wire box space is filled using filler, is formed(What 3 or more single wire box were constituted)Group's wire box
Component;
When applying to in-situ reinforced concrete slab, using following steps:
4th step:It is good with dipstick metering after the completion of platform template installs, it is used in combination paint to carry out drawing group's wire box group on stencil plane
The pre-buried position of part;
5th step:Sequentially fixed in platform floor template(What 3 or more single wire box were constituted)Group's wire box component and
Pre-buried pvc pipe;Group's wire box component is connected with pre-buried pvc pipe;
6th step:Reinforcing bar binding, formwork erection, concreting are completed according to a conventional method:
7th step:After concreting meets form removal condition, according to《Concrete structure engineering job specfication》GB50666-2011
In the 4.5.2 articles of regulation tear platform end template open, expose pre-buried(What 3 or more single wire box were constituted)Group's wire box group
Part;
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The pvc pipe in wire box is cut off with hand-operated tools;
When applying to cast in situ ferroconcrete wall plate, using following steps:
4th step:After the completion of wall steel bar binding, the burial place that is identified on wall steel bar:With dipstick metering or spirit level, laser
Shu Dingwei, brush paints to calibrate the burial place of group of group wire box component on framework of steel reinforcement;
5th step:Sequentially fixed on wall steel bar(What 3 or more single wire box were constituted)Group's wire box component and pre-buried
Pvc pipe, group's wire box component are connected with pre-buried pvc pipe;Using framework of steel reinforcement as binding(3 or more single wire box are constituted
's)The holder of group's wire box component using additional assembling reinforcement, then uses iron wire or adhesive tape will(3 or more single wire box structures
At)Group's wire box component is fixed on framework of steel reinforcement;
6th step:Steel reinforcing, formwork erection, concreting;
7th step:After concreting meets form removal condition, striking job is carried out;According to《Concrete structure engineering job specfication》
The 4.5.3 articles of regulation in GB50666-2011 removes side form;Expose pre-buried(What 3 or more single wire box were constituted)Group
Body wire box component.
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The PVC short tubes in wire box are cut off with hand-operated tools.
When applying to blockwork, using following steps:
4th step:After the completion of block masonry is built by laying bricks or stones, the burial place of group's wire box component is drawn on masonry with marking pen;
5th step:The line drawn on masonry along marking pen, is cut with hand-hold electric, then is carried out with flat chisel
Chisel masonry is picked, digging is sequentially drawn on block masonry wall(It is reserved when masonry is built by laying bricks or stones)For fixing(3 or more single wire box structures
At)The hole of group's wire box component;
6th step:It is put into the wall masonry hole completed(What 3 or more single wire box were constituted)Group's wire box group
Part and pre-buried pvc pipe, group's wire box component are connected with pre-buried pvc pipe;
7th step:Existed with mortar(What 3 or more single wire box were constituted)Group's wire box periphery carries out pointing;
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The PVC short tubes in wire box are cut off with hand-operated tools.
Further, PVC long tubes penetrate 86 molded line boxes of finished product, and PVC short tubes are placed on PVC long tubes.
Further, 3 or more single wire box and PVC casings and PVC short tube organic assemblings, form(3 or more single
What wire box was constituted)Group's wire box module.
Further, the filler in wire box space is sawdust, luminous agent, cystosepiment.
Beneficial effects of the present invention:It is covered by using processing finished product pvc pipe short tube and PVC casings, by PVC short tubes and PVC
Group's wire box that pipe is constituted with 3 or more single wire box.(What 3 or more single wire box were constituted)The modularization of group's wire box
It is pre-buried, the beautiful needs of group's wire box panel installation had both been met, labor intensity has been reduced, saves the consumption of labour, together
When prevented to do over again etc. caused by waste.
Description of the drawings
Fig. 1 is group's wire box structure chart of the present invention.
Fig. 2 is present invention fixed group wire box component diagram in concrete floor platform template.
Fig. 3 is to bind platform reinforcing bar schematic diagram after concrete floor of the present invention sets up group's wire box component.
Fig. 4 is that concrete floor platform reinforcing bar of the present invention binds after-pouring platform concrete and form removal schematic diagram.
Fig. 5 is that the present invention binds group's wire box component diagram on the wall steel bar skeleton of reinforced concrete wall panel.
Fig. 6 is the molding schematic diagram of reinforced column wall template of the present invention.
Fig. 7 is concreting schematic diagram after the molding of reinforced concrete wall panel of the present invention.
Fig. 8 is that blockwork of the present invention draws borehole hole schematic diagram.
Fig. 9 is that the present invention installs group's wire box component diagram in the hole of blockwork.
Figure 10 is to fill out embedding mortar schematic diagram after blockwork of the present invention installs group's wire box component.
In figure, 1, wire box, 2, PVC short tubes, 3, PVC long tubes, 4, platform template, 5, group's wire box component, 6, pre-buried PVC
Pipe, 7, wall steel bar skeleton, 8, platform reinforcing bar, 9, platform concrete, 10, reinforced concrete wall, 11, blockwork, 12, glue
Tie object.
Specific implementation mode
In order to deepen the understanding of the present invention, below in conjunction with embodiment and attached drawing, the invention will be further described, should
Embodiment is only used for explaining the present invention, does not restrict the protection scope of the present invention.
As shown in Figure 1, the pre-buried limit group wire box of structure, including wire box 1, PVC long tubes 3 are set in the wire box 1, it is described
It is connected with PVC short tubes 2 between wire box 1, space is filled with filler in the wire box 1.The filler be sawdust, luminous agent,
Cystosepiment.
As Figure 1-10 shows, the limit construction method of the pre-buried wire box of structure of the invention, when carrying out structure body construction,
Include the following steps:
Group's wire box establishment of component:
The first step:According to(What 3 or more single wire box were constituted)1 size of group's wire box, buys the PVC of finished product on the market
Pipe forms PVC long tubes 3 and PVC short tubes 2 further according to the length of calculating with the cutting of anodontia cutting machine.Length=line of PVC long tubes 3
Box number * 86+(Wire box number -1)* 20,20 ㎜ of diameter.20 ㎜ of length of PVC short tubes 2,25 ㎜ of diameter;PVC long tubes 3 are used as string and take 3
A or more single wire box 1, PVC long tubes 3 pass through the preformed hole of 86 molded line boxes 1.Feature is that the wire box 1 of two ends only punches side
Hole, intermediate wire box punch two holes on opposite.PVC long tubes 3 penetrate in 1 hole of wire box, and in PVC 3 PULL BOXs of long tube, intermittent is worn
Good PVC short tubes 2, i.e., ensure wire box spacing with PVC short tubes 2.So that it is guaranteed that the distance between two adjacent lines boxes is consistent, wire box spacing
For 20 ㎜.
Second step:By 3 or more single wire box and 2 organic assembling of PVC long tubes 3 and PVC short tubes, formed(3 or more
What single wire box was constituted)Group's wire box module.The rectangular 86 molded line box of 3 and the above finished product is unified into an entirety, ensures wire box
Spacing is balanced, geometric identity, keep the pre-buried line of wire box parallel.PVC long tubes penetrate 86 type terminal boxes of finished product, due to connecing
Wire box, which is finished product, PVC long tubes 3, has certain rigidity, PVC long tubes 3 to be through in the preformed hole in 86 type terminal box 1 of finished product, can reach
To control group wire box neat effect up and down.
Third walks:Wire box space is filled using sawdust, luminous agent or cystosepiment, is formed(3 or more single lines
What box was constituted)The component 5 of group's wire box;The purpose of filling is that the rectangular 86 molded line box 1 of finished product is penetrated into when preventing concreting
It is interior, the consumption of the recruitment and amount of concrete of cleaning concrete is reduced, and sawdust, luminous agent and cystosepiment are the useless of construction site
Gurry, waste reclamation reach green, the purpose of environmental protection.
Such as Fig. 2-4, when applying to in-situ reinforced concrete slab, using following steps:
4th step:It is good with dipstick metering in template after the completion of platform template 4 installs, it is used in combination paint to be drawn on stencil plane
The burial place of group's wire box component 5;
5th step:Sequentially fixed in platform template 4(What 3 or more single wire box were constituted)Group's wire box component 5;Using
Iron nail is followed closely in template, and is aided with iron wire to fix, and assembly and template are reliably connected together.Ensure 3 and with
The combination body position of the rectangular 86 molded line box of upper finished product is accurate.
6th step:8 binding of completion platform reinforcing bar, formwork erection, platform concrete 9 pour according to a conventional method:
7th step:After concreting meets form removal condition, striking job is carried out;According to《Concrete structure engineering job specfication》
The 4.5.2 articles of regulation tears platform end template open in GB50666-2011.Prevent template shift to an earlier date form removal may cause board bottom sink and
Cracking;Meanwhile exposing pre-buried(What 3 or more single wire box were constituted)Group's wire box component.
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The PVC long tubes in wire box are cut off with hand-operated tools.The PVC long tubes for being originally used as strut occupy in wire box in itself
Just very narrow space, when group's wire box component has been secured in position, the effect of strut has removed, can will be in wire box
PVC long tubes are cut away, and are released and are utilized space.Due to wire box space very little, and the hardness of pvc pipe itself is also little, usually
It is cut using the widely used hacksaw blade in construction site, or directly cuts with a knife and cut.
Such as Fig. 5-7, when applying to cast in situ ferroconcrete wall plate, using following steps:
4th step:After the completion of wall steel bar binding, the method that the levelling of spirit level can also be used with dipstick metering controls the height of wire box
Degree can also control position and the absolute altitude of wire box, the method for usually using dipstick metering at the construction field (site), in wall with laser beam positioning etc.
It is painted with brush on body framework of steel reinforcement 7 or the mackintosh gluing that is used with electrician is in reinforcing bar or cured line, bar bender's hand with unwrapping wire
In tied silk be bundled in reinforcing bar, identified the burial place of group's wire box component 5;
5th step:Using additional assembling reinforcement, then use iron wire or adhesive tape will(What 3 or more single wire box were constituted)Group's line
Case assembly 5 sequentially fixes on wall steel bar skeleton 7(What 3 or more single wire box were constituted), and by group's wire box component 5
It is connected with the pre-buried pvc pipe 6 in wall steel bar.Using wall steel bar skeleton 7 as binding(3 or more single wire box are constituted
's)The holder of group's wire box component, it is ensured that(What 3 or more single wire box were constituted)Group's wire box module position is embedded accurate.
6th step:Steel reinforcing, according to the conventional method carry out wallboard template install, concreting;
7th step:After concreting meets form removal condition, striking job is carried out, forms the reinforcing bar embedded with group's wire box component 5
Concrete wall 10.According to《Concrete structure engineering job specfication》The 4.5.3 articles of regulation in GB50666-2011, i.e., when mixed
Solidifying soil intensity can guarantee its point have corner angle it is injury-free when, remove side form.Ensure that the perception of column metope is good, meanwhile, dew
Go out pre-buried(What 3 or more single wire box were constituted)Group's wire box component 5.
8th step:It removes(What 3 or more single wire box were constituted)Sundries in 5 box of group's wire box component;
9th step:The PVC long tubes in wire box 1 are cut off with hand-operated tools.When group's wire box component has been secured in position, it was used as originally
The pvc pipe of strut is just without existing value, and the presence of strut is also possible to occupy sky inherently very narrow in wire box
Between.Due to wire box space very little, and the hardness of pvc pipe itself is also little, usually using the widely used hacksaw in construction site
Item is cut, or is directly cut with a knife and cut.
Such as Fig. 8-10, when applying to blockwork, using following steps:
4th step:After the completion of blockwork 11 is built by laying bricks or stones, is identified on blockwork 11 with marking pen according to design and place group
The burial place of wire box component 5;
5th step:The line drawn on blockwork 11 along marking pen, is cut, then use flat chisel with hand-hold electric
Son carries out picking chisel blockwork 11, and digging is sequentially drawn on blockwork 11 and meets fixation(What 3 or more single wire box were constituted)
The hole of group's wire box component 5;It first cuts and picks chisel again, advantageously reduce the influence to pit slot periphery, while reducing blockwork
11 cutting quantity and the embedding benefit amount of mortar.
6th step:It is installed in hole(What 3 or more single wire box were constituted)Group's wire box component 5:It completes
11 hole of blockwork in be put into(What 3 or more single wire box were constituted)Group's wire box component 5 and pre-buried pvc pipe 6, by group
Body wire box component 5 is connect with pre-buried pvc pipe 6, and mortar is used in combination to carry out embedding benefit.Between the wire casing and pre-buried pvc pipe 6 of blockwork 11
Cement can also be filled, cement can also be filled between wire casing and group's wire box component 5.The mortar embedding added time is being carried out,
Pit hole on masonry wall has been drawn digging and has been completed, and cleans out, and the method for generally use point scab slurry consolidates group's wire box component 5
It is fixed, simultaneously because there is certain plasticity in mortar early stage, it can be pressed with hand or be aided with tool group's wire box component is positioned, had
Effect is fixed(What 3 or more single wire box were constituted)Group's wire box component 5, it is ensured that horizontal line level above and below group's wire box component.
To ensure 5 plane of group's wire box component and masonry planes align.Mortar thickness and coat of plaster consistency of thickness.Construction and decoration designs
Plastering layer thickness be usually 15 ~ 20 ㎜.
7th step:It removes(What 3 or more single wire box were constituted)Sundries in 5 box of group's wire box component;
8th step:The PVC long tubes in wire box, hacksaw blade or pocket knife cutting are cut off with hand-operated tools.
Claims (6)
1. the pre-buried limit group wire box of structure, it is characterised in that:Including wire box, PVC short tubes, the wire box are set in the wire box
Between connected with PVC long tubes, space is filled with filler in the wire box.
2. the pre-buried limit group wire box of structure described in accordance with the claim 1, it is characterised in that:The filler be sawdust,
Luminous agent or cystosepiment.
3. the limit construction method of the pre-buried wire box of structure, it is characterised in that:Include the following steps:
Group's wire box establishment of component:
The first step:Prepare PVC long tubes and PVC short tubes;20 ㎜ of PVC long tubes diameter, length=wire box number * 86+(Wire box number -1)*
20;PVC short tubes diameter 25 ㎜, 20 ㎜ of length, do not go here and there wire box;
Second step:3 or more single wire box and PVC long tubes and PVC short tube organic assemblings, PVC short tubes are placed on PVC long tubes
On;PVC long tube strings take 3 or more single wire box, and in PVC long tube PULL BOXs, intermittent puts on PVC short tubes, so that it is guaranteed that
Wire box spacing is to separate as 20 ㎜ by the distance between two adjacent lines boxes, PVC short tubes;It is formed(3 or more single wire box are constituted
's)Group's wire box module;
Third walks:Wire box space is filled using filler, is formed(What 3 or more single wire box were constituted)Group's wire box
Component;
When applying to in-situ reinforced concrete slab, using following steps:
4th step:It is good with dipstick metering after the completion of platform template installs, it is used in combination paint to carry out drawing group's wire box group on stencil plane
The pre-buried position of part;
5th step:Sequentially fixed in platform floor template(What 3 or more single wire box were constituted)Group's wire box component and
Pre-buried pvc pipe, group's wire box component are connected with pre-buried pvc pipe;
6th step:Reinforcing bar binding, formwork erection, concreting are completed according to a conventional method:
7th step:After concreting meets form removal condition, according to《Concrete structure engineering job specfication》GB50666-2011
In the 4.5.2 articles of regulation tear platform end template open, expose pre-buried(What 3 or more single wire box were constituted)Group's wire box group
Part;
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The PVC long tubes in wire box are cut off with hand-operated tools;When applying to cast in situ ferroconcrete wall plate, using such as
Lower step:
4th step:After the completion of wall steel bar binding, the burial place that is identified on wall steel bar:With dipstick metering or spirit level, laser
Shu Dingwei, brush paints to calibrate the burial place of group of group wire box component on framework of steel reinforcement;
5th step:Sequentially fixed on wall steel bar(What 3 or more single wire box were constituted)Group's wire box component and pre-buried
Pvc pipe;Using framework of steel reinforcement as binding(What 3 or more single wire box were constituted)The holder of group's wire box component, use are attached
Add assembling reinforcement, then uses iron wire or adhesive tape will(What 3 or more single wire box were constituted)Group's wire box component is fixed on reinforcing bar
On skeleton;Group's wire box component is connected with pre-buried pvc pipe;
6th step:Steel reinforcing, formwork erection, concreting;
7th step:After concreting meets form removal condition, striking job is carried out;According to《Concrete structure engineering job specfication》
The 4.5.3 articles of regulation in GB50666-2011 removes side form;Expose pre-buried(What 3 or more single wire box were constituted)Group
Body wire box component;
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The PVC long tubes in wire box are cut off with hand-operated tools;
When applying to blockwork, using following steps:
4th step:After the completion of block masonry is built by laying bricks or stones, the burial place of group's wire box component is drawn on masonry with marking pen;
5th step:The line drawn on masonry along marking pen, is cut with hand-hold electric, then is carried out with flat chisel
Chisel masonry is picked, digging is sequentially drawn on block masonry wall(It is reserved when masonry is built by laying bricks or stones)For fixing(3 or more single wire box structures
At)The hole of group's wire box component;
6th step:It is put into the wall masonry hole completed(What 3 or more single wire box were constituted)Group's wire box group
Part and pre-buried pvc pipe, group's wire box component are connected with pre-buried pvc pipe;
7th step:Existed with mortar(What 3 or more single wire box were constituted)Group's wire box component periphery carries out pointing;
8th step:It removes(What 3 or more single wire box were constituted)Sundries in the box of group's wire box component;
9th step:The PVC long tubes in wire box are cut off with hand-operated tools.
4. the limit construction method of the pre-buried wire box of structure according to claim 1, it is characterised in that:The PVC long tubes
86 molded line boxes of finished product are penetrated, PVC short tubes are placed on PVC long tubes.
5. the limit construction method of the pre-buried wire box of structure according to claim 2, it is characterised in that:Described 3 or more
Single wire box and PVC long tubes and PVC short tube organic assemblings, form(What 3 or more single wire box were constituted)Group's wire box module.
6. the limit construction method of the pre-buried wire box of structure according to claim 3, it is characterised in that:The wire box space
Filler be sawdust, luminous agent, cystosepiment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810763662.2A CN108797954A (en) | 2018-07-12 | 2018-07-12 | The limit construction method of the pre-buried wire box of structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810763662.2A CN108797954A (en) | 2018-07-12 | 2018-07-12 | The limit construction method of the pre-buried wire box of structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108797954A true CN108797954A (en) | 2018-11-13 |
Family
ID=64075011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810763662.2A Pending CN108797954A (en) | 2018-07-12 | 2018-07-12 | The limit construction method of the pre-buried wire box of structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108797954A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110593566A (en) * | 2019-09-02 | 2019-12-20 | 中冶天工集团天津有限公司 | Novel pre-buried wire box and construction method |
CN111749481A (en) * | 2020-06-29 | 2020-10-09 | 刘鑫 | Construction method for pre-buried wire box |
CN113788649A (en) * | 2021-10-09 | 2021-12-14 | 界首市宝业瑞祥建筑工业化有限公司 | Preparation method of infilled wall component |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09200921A (en) * | 1996-01-12 | 1997-07-31 | Sekisui Chem Co Ltd | Wiring work in building and building therewith |
CN105019651A (en) * | 2014-04-23 | 2015-11-04 | 重庆建工第四建设有限责任公司 | High efficient installation construction method for rowed cable boxes in hollow brick filled wall |
CN206144109U (en) * | 2016-11-04 | 2017-05-03 | 中冶建工集团有限公司 | Wear muscle line box precasting structure |
CN107178210A (en) * | 2017-07-11 | 2017-09-19 | 中国五冶集团有限公司 | The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall |
CN206542144U (en) * | 2017-03-02 | 2017-10-03 | 中国建筑第八工程局有限公司 | A kind of prefabricated integrated line box building element |
CN208918206U (en) * | 2018-07-12 | 2019-05-31 | 江苏南通三建集团股份有限公司 | The pre-buried limit group wire box of structural body |
-
2018
- 2018-07-12 CN CN201810763662.2A patent/CN108797954A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09200921A (en) * | 1996-01-12 | 1997-07-31 | Sekisui Chem Co Ltd | Wiring work in building and building therewith |
CN105019651A (en) * | 2014-04-23 | 2015-11-04 | 重庆建工第四建设有限责任公司 | High efficient installation construction method for rowed cable boxes in hollow brick filled wall |
CN206144109U (en) * | 2016-11-04 | 2017-05-03 | 中冶建工集团有限公司 | Wear muscle line box precasting structure |
CN206542144U (en) * | 2017-03-02 | 2017-10-03 | 中国建筑第八工程局有限公司 | A kind of prefabricated integrated line box building element |
CN107178210A (en) * | 2017-07-11 | 2017-09-19 | 中国五冶集团有限公司 | The accurate pre-embedded construction method of many line box of China Democratic National Construction Association's wall |
CN208918206U (en) * | 2018-07-12 | 2019-05-31 | 江苏南通三建集团股份有限公司 | The pre-buried limit group wire box of structural body |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110593566A (en) * | 2019-09-02 | 2019-12-20 | 中冶天工集团天津有限公司 | Novel pre-buried wire box and construction method |
CN111749481A (en) * | 2020-06-29 | 2020-10-09 | 刘鑫 | Construction method for pre-buried wire box |
CN113788649A (en) * | 2021-10-09 | 2021-12-14 | 界首市宝业瑞祥建筑工业化有限公司 | Preparation method of infilled wall component |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Allouzi et al. | Conventional construction and 3D printing: A comparison study on material cost in Jordan | |
CN108797954A (en) | The limit construction method of the pre-buried wire box of structure | |
US20190184602A1 (en) | Sand aerated concrete panel embedded with wire box and wire conduit and method for preparing same | |
CN107297810A (en) | A kind of making of precast wall body component and installation method | |
US20040168330A1 (en) | Levelling rod for building construction | |
CN105019651B (en) | Hollow brick fills wall into the efficient installation engineering method of winding box | |
CN109853832A (en) | A kind of construction method of filling wall masonry and electrical pre-embedded pipe synchronous construction | |
CN201180366Y (en) | Ultra-large area concrete construction surface construction and partition seam remaining construction apparatus | |
CN106121231A (en) | A kind of skyscraper interts cross construction method | |
CN108468413A (en) | A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering | |
CN109577674A (en) | A kind of metope flexure type crack repairing structure and its construction method | |
Gibbons | How a House Is Built (New & Updated) | |
CN109138215A (en) | A kind of construction wall integral construction method | |
CN208918206U (en) | The pre-buried limit group wire box of structural body | |
CN109555238A (en) | The processing method that a kind of aluminum alloy mould plate concrete body exempts from plastering | |
CN202099901U (en) | Troweling structure for treatment on junction part of concrete wall column and filler wall | |
CN106186942B (en) | A kind of self-compacting mortar and its grout construction method | |
CN105888084A (en) | Whole outer wall internal thermal insulation system construction method by using enhanced composite thermal insulation material | |
CN208337097U (en) | Suit wears reinforcing bar wire box | |
CN208073001U (en) | A kind of cast-in-site concrete floor thickness control tool | |
CN102296827A (en) | Mounting method of light-weight partition wall board | |
CN109853949A (en) | Pipe laying preformed groove technique after a kind of cast-in-place concrete wall | |
CN206554360U (en) | A kind of assembled porcelain earthenware brick for building and the house built using the porcelain earthenware brick | |
CN202596045U (en) | Pseudo-classic architectural concrete eave with reversely nailed wooden rafter and reversely constructed roof boarding | |
CN102182323A (en) | Process for dry laying of autoclaved aerated concrete blocks in low-latitude plateaus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |