CN107297810A - A kind of making of precast wall body component and installation method - Google Patents

A kind of making of precast wall body component and installation method Download PDF

Info

Publication number
CN107297810A
CN107297810A CN201710601532.4A CN201710601532A CN107297810A CN 107297810 A CN107297810 A CN 107297810A CN 201710601532 A CN201710601532 A CN 201710601532A CN 107297810 A CN107297810 A CN 107297810A
Authority
CN
China
Prior art keywords
wall
component
prefabricated
precast
wall body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710601532.4A
Other languages
Chinese (zh)
Inventor
李应心
葛振刚
张爱军
刘斌
冯善中
庞茜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201710601532.4A priority Critical patent/CN107297810A/en
Publication of CN107297810A publication Critical patent/CN107297810A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/04Producing shaped prefabricated articles from the material by tamping or ramming
    • B28B1/045Producing shaped prefabricated articles from the material by tamping or ramming combined with vibrating or jolting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/04Discharging the shaped articles
    • B28B13/06Removing the shaped articles from moulds
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/12Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed to form prestressed circumferential reinforcements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/38Treating surfaces of moulds, cores, or mandrels to prevent sticking
    • B28B7/384Treating agents

Landscapes

  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

The invention discloses a kind of making of precast wall body component and installation method, belong to technical field of building construction, the problem of solving traditional architecture low construction efficiency changes high energy consumption, the traditional mode of production mode of high pollution.There is framework of steel reinforcement and built-in fitting in precast wall body component, and be reserved with embedded bar hole, injected hole and steam vent, its preparation method:1), first according to the appearance and size supporting module of precast wall body component;2), framework of steel reinforcement and built-in fitting are placed in template;3), concrete prepare with pouring;4), precast wall body component steam curing;5), precast wall body component the demoulding;6), precast wall body component is turned on one's side, erected;7), precast wall body component inserts or by putting.The present invention carries out construction using precast wall body component, instead of traditional form of construction work, and architectural industrialization is realized in promotion, reduces energy resource consumption, reduces garbage emission, improves efficiency of construction, improves construction comprehensive quality, is easy to coordinated management.

Description

一种预制墙体构件的制作及安装方法Method for making and installing prefabricated wall components

技术领域technical field

本发明涉及建筑施工技术领域,具体地说是一种预制墙体构件的制作及安装方法。The invention relates to the technical field of building construction, in particular to a method for making and installing a prefabricated wall component.

背景技术Background technique

随着经济的快速发展,各行各业都在不断的推陈出新,以节约能源、降低污染、提高生产效率为宗旨,不断突破传统生产模式,向标准化结构体系迈进。我国建筑业仍是一个劳动密集型、建造方式相对落后的传统产业,尤其在房屋建造的整个生产过程中高能耗、高污染、低效率、粗放的传统建造模式还具有普遍性,与当前的新型城镇化、工业化、信息化发展要求不相适应,与发达国家相比差距较大。传统的建筑施工中,一般采用现场浇筑混凝土的方式施工,传统的施工方式存在技术集成能力低、管理方式粗放、劳动力素质低及生产手段落后等诸多弊端。With the rapid development of the economy, all walks of life are constantly innovating, with the aim of saving energy, reducing pollution, and improving production efficiency, constantly breaking through the traditional production mode and moving towards a standardized structural system. my country's construction industry is still a labor-intensive traditional industry with relatively backward construction methods. Especially in the whole production process of house construction, the traditional construction mode of high energy consumption, high pollution, low efficiency and extensive is still common, which is different from the current new The development requirements of urbanization, industrialization, and informatization are not compatible, and there is a big gap compared with developed countries. In traditional building construction, the method of pouring concrete on site is generally used for construction. The traditional construction method has many disadvantages such as low technical integration ability, extensive management method, low labor quality and backward production methods.

近年来,我国逐渐重视建筑产业化的发展,各地相继提出装配式建筑、绿色建筑等要求。建筑产业化是指运用现代化管理模式,通过标准化的建筑设计以及模数化、工业化的部品生产,实现建筑构部件的通用化和现场施工的装配化、机械化。建筑产业化有利于推动我国建筑业及住房城乡建设领域的转型升级,实现国家新型城镇化发展、节能减排战略的重要举措。In recent years, my country has gradually attached importance to the development of construction industrialization, and various places have successively put forward requirements for prefabricated buildings and green buildings. Building industrialization refers to the use of modern management models to realize the generalization of building components and the assembly and mechanization of on-site construction through standardized architectural design and modularized and industrialized parts production. Construction industrialization is conducive to promoting the transformation and upgrading of my country's construction industry and housing and urban-rural construction, and is an important measure to realize the national new urbanization development and energy conservation and emission reduction strategies.

目前,我国的建筑产业化还处于初期阶段,一些成品及半成品预制构件的生产工艺及安装流程,由于技术问题、生产管理、协同安装等工艺尚不完善,并没有普及应用。传统的预制墙体在灌浆时效果不佳,容易出现漏浆等现象,整体结构的稳定性不理想,同时生产效率低、综合质量差、资源消耗高、耗费大量的人力、物力。At present, my country's construction industrialization is still in the initial stage. The production process and installation process of some finished and semi-finished prefabricated components have not been widely used due to technical problems, production management, collaborative installation and other processes. The traditional prefabricated wall is not effective in grouting, prone to grout leakage and other phenomena, the stability of the overall structure is not ideal, and at the same time, the production efficiency is low, the comprehensive quality is poor, the resource consumption is high, and it consumes a lot of manpower and material resources.

发明内容Contents of the invention

本发明的技术任务是针对以上不足之处,提供一种预制墙体构件的制作及安装方法,施工中直接将预制墙体构件安装,推动实现建筑产业化,解决传统建筑施工效率低,耗能高,不易管理的问题。The technical task of the present invention is to provide a method for making and installing prefabricated wall components in view of the above deficiencies. During construction, the prefabricated wall components are directly installed to promote the realization of building industrialization and solve the problem of low construction efficiency and energy consumption of traditional buildings. High, unmanageable problems.

本发明解决其技术问题所采用的技术方案是:The technical solution adopted by the present invention to solve its technical problems is:

一种预制墙体构件的制作方法,所述预制墙体构件内具有钢筋骨架和预埋件,并留有预埋钢筋孔洞、注浆孔和排气孔,其制作方法如下;A method for making a prefabricated wall component, wherein the prefabricated wall component has a steel bar skeleton and embedded parts, and has pre-embedded steel bar holes, grouting holes and vent holes, and the manufacturing method is as follows;

1)、首先根据预制墙体构件的外形尺寸支设模板。模板根据预制墙体构件进行设计,精度控制在2mm内;模板支设时需要注意装饰面的平整度、钢筋及预埋件的位置精度、预制墙体构件结构尺寸精度并且易于振捣密实。1) First, support the formwork according to the external dimensions of the prefabricated wall components. The formwork is designed according to the prefabricated wall components, and the accuracy is controlled within 2mm; when the formwork is supported, it is necessary to pay attention to the flatness of the decorative surface, the position accuracy of the steel bars and embedded parts, the structural dimensional accuracy of the prefabricated wall components, and the ease of vibration and compaction.

模板安装时模板隔离剂不得有漏涂或流淌,模板的安装、固定要平直、紧密、不倾斜,并且尺寸要准确。When the template is installed, the template release agent must not leak or flow. The installation and fixing of the template must be straight, tight, not inclined, and the size must be accurate.

2)、在模板内放置钢筋骨架和预埋件。半成品钢筋切断、对焊、成型的加工时要保证尺寸超差不应大于允许偏差的1.5倍,弯曲成型的钢筋应控制其弯曲直径。由于墙体构件属于板类构件,钢筋的主筋保护层相对较小,因此要采用专门的成型架成型钢筋骨架保证尺寸准确。2) Place the reinforced skeleton and embedded parts in the formwork. When cutting, butt welding, and forming semi-finished steel bars, it is necessary to ensure that the size tolerance should not be greater than 1.5 times the allowable deviation, and the bending diameter of the bent and formed steel bars should be controlled. Since the wall components are plate components, the protective layer of the main reinforcement of the steel bars is relatively small, so a special forming frame should be used to form the steel bar skeleton to ensure accurate dimensions.

开孔部位配置加强筋,加强筋不少于三处绑扎固定点。钢筋骨架轻放入模,入模后不得移动钢筋骨架,钢筋骨架采用垫、吊等方式,满足钢筋各部位的保护层厚度。钢筋入模安装时,保证钢筋笼平直、无损伤,表面不得有油污、颗粒状或片状老锈;钢筋安装时,钢筋网和钢筋骨架安装位置不得超出允许偏差。Reinforcing ribs shall be arranged at the openings, and the reinforcing ribs shall be bound at no less than three fixing points. The steel frame should be put into the mold lightly, and the steel frame should not be moved after being put into the mold. The steel frame should be cushioned or hung to meet the thickness of the protective layer of each part of the steel bar. When the steel bar is installed in the mold, ensure that the steel bar cage is straight and free of damage, and the surface must not have oil, granular or flaky old rust; when the steel bar is installed, the installation position of the steel bar mesh and the steel bar frame must not exceed the allowable deviation.

固定在模板上的预埋件、预留孔和预留洞的安装位置不应超过允许偏差。The installation position of the embedded parts, reserved holes and reserved holes fixed on the formwork shall not exceed the allowable deviation.

3)、混凝土的制备与浇筑。混凝土的各种材料全部装入搅拌机至出料的搅拌时间不少于90秒;混凝土的运输在固定模台采用提吊式运输及布料方式,在流水线生产车间采用鱼雷罐送料、自动布料机布料方式;每次运输方量应与浇灌方量、浇灌速度相适应,以保证拌合物在灌筑时具有良好的和易性。3) Preparation and pouring of concrete. All kinds of concrete materials are loaded into the mixer and the mixing time is not less than 90 seconds; the concrete is transported by lifting and distributing on the fixed formwork platform, and the torpedo tank feeding and automatic distributing machine are used in the assembly line production workshop. Method; each transportation volume should be compatible with the pouring volume and pouring speed, so as to ensure that the mixture has good workability during pouring.

混凝土浇筑前,模板清理干净并涂刷脱模剂;浇捣成型时,浇筑时间不超过30分钟,每批要按规定做好抗压试块和同条件养护试块的留样和试验。混凝土振捣应密。Before the concrete is poured, the formwork shall be cleaned and the mold release agent shall be applied; when the concrete is poured and formed, the pouring time shall not exceed 30 minutes, and the compression test blocks and the same condition curing test blocks shall be retained and tested according to the regulations for each batch. The concrete should be vibrated densely.

4)、预制墙体构件蒸汽养护,混凝土浇筑后,静停不小于2小时,升温不小于2小时,升温速度不大于15℃/小时;恒温不小于4小时,恒温养护温度范围在55℃~60℃;降温不小于3小时,降温速度不大于10℃/小时。4) For steam curing of prefabricated wall components, after concrete pouring, stop for not less than 2 hours, heat up for not less than 2 hours, and the heating rate is not greater than 15°C/hour; keep the temperature for not less than 4 hours, and the temperature range for constant temperature curing is 55°C~ 60°C; the cooling rate is not less than 3 hours, and the cooling rate is not greater than 10°C/hour.

5)、脱模,预制构件达到混凝土抗压强度设计值的75%,且不小于15N/ mm 时脱模,拆模强度以试验室对同条件养护试块的抗压强度检测结果为准。根据模具结构和拆除顺序拆除模具,避免对预制墙体构件造成损坏,且不得用振动构件方式拆模。使用外力先顶推预制墙体构件使之与模具脱离,脱模后,对水洗面进行冲洗。预制墙体构件采用平吊出模,起吊的吊点宜4~6点吊进行。在构件醒目位置进行编码,编码应用水性环保涂料或塑料贴模等可清除材料。5) Demoulding. When the prefabricated components reach 75% of the design value of the concrete compressive strength and not less than 15N/mm, the demoulding strength is subject to the test results of the compressive strength of the test blocks cured under the same conditions in the laboratory. Remove the mold according to the mold structure and removal sequence to avoid damage to the prefabricated wall components, and the formwork must not be removed by vibrating components. Use external force to push the prefabricated wall components first to separate them from the mold, and rinse the water-washed surface after demoulding. The prefabricated wall components should be lifted out of the mold by flat lifting, and the lifting points should be lifted at 4 to 6 points. Coding is carried out at a conspicuous position of the component, and the coding should be made of removable materials such as water-based environmental protection paint or plastic molding.

6)、构件侧翻、立起后,运送至堆场,预制墙体构件采用竖直立放式运输,可采用堆放架辅助式立放。6) After the components are turned sideways and erected, they are transported to the storage yard. The prefabricated wall components are transported vertically, and can be stored vertically with the aid of stacking racks.

7)、预制墙体构件采用插放或靠放,堆放架有足够的刚度,并支垫稳固。堆场将相邻堆放架连成整体,预制外墙板将外饰面朝外,对连接止水条、高低口、墙体转角等薄弱部位,采用定型保护垫块或专用式附套件加强保护。7) The prefabricated wall components are inserted or leaned on, and the stacking frame has sufficient rigidity, and the pads are stable. The stacking yard connects the adjacent stacking racks into a whole, and the prefabricated exterior wall panels face outwards. For weak parts such as connecting waterstops, high and low openings, and wall corners, use shaped protective pads or special accessories to strengthen protection .

进一步的,所述预埋件包括长螺母、钢丝绳、钢环和伞柄钩,其中,Further, the embedded parts include long nuts, steel wire ropes, steel rings and umbrella handle hooks, wherein,

长螺母的预埋,长螺母预埋端焊接固定有横向辅助钢筋,横向钢筋通过铁丝绑扎固定于板内筋;For the pre-embedding of the long nut, the pre-embedded end of the long nut is welded and fixed with a horizontal auxiliary steel bar, and the horizontal steel bar is fixed to the inner reinforcement of the plate by binding iron wires;

钢丝绳的预埋,钢丝绳的两预埋端端部散开,散开长度大于400mm,散开部分用铁丝绑扎固定于板内筋,每三股一组与板内筋搭接固定,设置有辅助筋将钢丝绳限位;Pre-embedding of steel wire rope, the two pre-embedded ends of the steel wire rope are spread out, and the spread length is greater than 400mm. The loose part is bound and fixed to the inner rib of the plate with iron wires, and each group of three strands is lapped and fixed with the inner rib of the plate, and auxiliary ribs are provided. Limit the wire rope;

钢环的预埋,钢环为开口钢环,开口端两固定脚固定于板内筋固定,设置辅助筋辅助定位;The pre-embedding of the steel ring, the steel ring is an open steel ring, the two fixed feet at the open end are fixed to the inner ribs of the plate, and auxiliary ribs are set to assist positioning;

伞柄钩的预埋,钩端勾住板内筋固定。The umbrella handle hook is pre-embedded, and the hook end hooks the inner rib of the board to fix it.

进一步的,预制墙体构件包括预制剪力墙构件和预制隔墙构件,预制剪力墙构件的预埋件还包括预埋铁盒,预埋铁盒一面开口露在预制剪力墙构件墙外,且外露部分开设有安装孔洞,用做预制隔墙构件的固定连接处;预制隔墙构件的预埋件还包括至少两个连接螺栓,所述连接螺栓的直径小于所述安装孔洞的最小尺寸;预制隔墙构件与预制剪力墙构件固定时利用连接螺栓与预埋铁盒的连接固定。预制隔墙构件还预留有管线接口槽和楼板凹槽,用于预制隔墙构件的预埋管线连接和楼板安装。Further, the prefabricated wall components include prefabricated shear wall components and prefabricated partition wall components, and the embedded parts of the prefabricated shear wall components also include prefabricated iron boxes, and one side of the prefabricated iron box is exposed outside the wall of the prefabricated shear wall components , and the exposed part is provided with an installation hole, which is used as a fixed joint of the prefabricated partition wall component; the embedded part of the prefabricated partition wall component also includes at least two connecting bolts, and the diameter of the connecting bolt is smaller than the minimum size of the installation hole ; Prefabricated partition wall components and prefabricated shear wall components are fixed by connecting bolts and pre-embedded iron boxes. The prefabricated partition wall components are also reserved with pipeline interface grooves and floor grooves, which are used for the embedded pipeline connection and floor slab installation of the prefabricated partition wall components.

进一步的,预制隔墙构件还预埋有至少2个φ6锚固钢筋,φ6锚固钢筋用于预制隔墙构件与现浇墙体的锚固。Further, the prefabricated partition wall component is also pre-embedded with at least two φ6 anchoring steel bars, which are used for anchoring the prefabricated partition wall component and the cast-in-situ wall.

进一步的,预制剪力墙构件的预埋件还包括用于固定膨胀螺栓的螺丝套筒,螺丝套筒用于剪力墙安装斜撑时放置膨胀螺栓,螺丝套筒水平放置预埋,其一端与墙面平齐,便于膨胀螺栓的安放。Further, the embedded parts of the prefabricated shear wall components also include screw sleeves for fixing the expansion bolts. The screw sleeves are used to place the expansion bolts when the shear wall is installed with braces. The screw sleeves are embedded horizontally, and one end It is flush with the wall to facilitate the placement of expansion bolts.

进一步的,蒸汽养护方式包括立体养护窑和推拉折叠式养护罩。对于在自动化流水线车间生产的构件采用立体养护窑的方式进行蒸汽养护,温湿度均为自动监测、自动控制;对于在固定模台生产的构件采用推拉折叠式养护罩的方式进行蒸汽养护,每隔0.5小时进行温湿度测量及控制。Further, the steam curing method includes a three-dimensional curing kiln and a push-pull folding curing cover. For the components produced in the automatic assembly line workshop, the three-dimensional curing kiln is used for steam curing, and the temperature and humidity are automatically monitored and controlled; for the components produced on the fixed mold table, the push-pull folding curing cover is used for steam curing. 0.5 hours for temperature and humidity measurement and control.

该预制墙体构件的制作方法同样适用于预制楼梯、预制阳台、预制空调板的生产。The manufacturing method of the prefabricated wall component is also applicable to the production of prefabricated stairs, prefabricated balconies, and prefabricated air-conditioning panels.

一种预制墙体构件,包括预制剪力墙构件和预制隔墙构件,使用模具由混凝土浇筑而成,预制墙体构件内具有钢筋骨架和预埋件,预埋件包括长螺母、钢丝绳、钢环和伞柄钩;并预留有预埋钢筋孔洞、注浆孔和排气孔。其中,预制剪力墙构件的预埋件还包括预埋铁盒,预埋铁盒一面开口并露出预制墙体,外露部分开设螺栓连接孔洞。预制隔墙构件的预埋件还包括至少两个连接螺栓和锚固钢筋,所述连接螺栓的直径小于所述螺栓安装孔洞的最小尺寸。所述连接螺栓用于与所述预埋铁盒连接,从而连接预制隔墙构件和预制剪力墙构件;所述锚固钢筋用于预制隔墙构件与现浇墙体锚固。A prefabricated wall component, including a prefabricated shear wall component and a prefabricated partition wall component, which is formed by pouring concrete using a mold. The prefabricated wall component has a steel skeleton and embedded parts, and the embedded parts include long nuts, steel wire ropes, steel Ring and umbrella handle hook; and pre-embedded steel holes, grouting holes and vent holes are reserved. Among them, the embedded parts of the prefabricated shear wall components also include a pre-embedded iron box, one side of the pre-embedded iron box is open and exposes the prefabricated wall, and the exposed part is provided with bolt connection holes. The embedded part of the prefabricated partition wall component also includes at least two connecting bolts and anchoring steel bars, and the diameter of the connecting bolts is smaller than the minimum size of the bolt installation hole. The connecting bolt is used to connect with the pre-embedded iron box, thereby connecting the prefabricated partition wall component and the prefabricated shear wall component; the anchoring steel bar is used for anchoring the prefabricated partition wall component and the cast-in-situ wall.

预制隔墙构件还预留有管线接口槽和楼板凹槽,管线接口槽用于预制隔墙构件的管线安装,楼板凹槽用于预制隔墙构件与楼板的安装。The prefabricated partition wall component is also reserved with a pipeline interface groove and a floor groove, the pipeline interface groove is used for pipeline installation of the prefabricated partition wall component, and the floor slab groove is used for the installation of the prefabricated partition wall component and the floor slab.

一种预制墙体构件的安装方法,对上述的制作方法制作而成的预制墙体构件以及上述的一种预制墙体构件进行现场安装,安装步骤如下:A method for installing a prefabricated wall component. The prefabricated wall component produced by the above-mentioned manufacturing method and the above-mentioned prefabricated wall component are installed on site. The installation steps are as follows:

1)、确定下层剪力墙插筋位置,测量放线,安放标高垫块;测量放线时应注意先确定首层定位轴线的四个基准外角点,利用四个基准外角点放出楼层四周外墙轴线,以四周外墙轴线为基准线先放四个外墙角位置线,后放外墙中部墙体位置线,先放楼梯间的三面内墙位置线,再放其它内墙位置线;先放大墙位置线,后放小墙位置线;先放承重墙位置线,后放非承重墙位置线。放出预制墙体构件外边四周控制轴线时,保证外墙大角在转角处成900规方。再放出每片墙体的位置控制线及抄平每片墙体的标高控制块,每片墙体下的标高控制块不少于2块。1) Determine the location of the lower shear wall inserting ribs, measure and set out the line, and place the elevation block; when measuring and setting out the line, you should first determine the four reference outer corner points of the positioning axis of the first floor, and use the four reference outer corner points to release the outside of the floor around the floor. For the axis of the wall, place the position lines of the four outer wall corners first, and then the position lines of the middle wall of the outer wall, first place the position lines of the three inner walls of the stairwell, and then place the position lines of other inner walls; Enlarge the position line of the wall, then place the position line of the small wall; place the position line of the load-bearing wall first, and then place the position line of the non-bearing wall. When releasing the control axis around the outer edge of the prefabricated wall components, ensure that the large corners of the outer walls form 900 square meters at the corners. Then release the position control line of each wall and level the elevation control block of each wall. The elevation control block under each wall should be no less than 2 pieces.

使用水准仪利用楼层标高控制点,控制好预制墙体下垫块表面标高。Use the level gauge to control the surface elevation of the cushion block under the prefabricated wall by using the floor elevation control point.

2)、吊装预制剪力墙构件,使下层剪力墙预留插筋进入吊装的预制剪力墙构件中,构件安装就位后与预先弹放的控制线吻合。2) Hoist the prefabricated shear wall components, so that the inserted ribs reserved for the lower shear wall enter the hoisted prefabricated shear wall components. After the components are installed in place, they coincide with the control lines that have been ejected in advance.

3)、安装斜撑,斜撑位置设置于墙体的2/3处,斜撑与水平线夹角范围在55°~65°,每块预制剪力墙体构件设置至少2个斜撑;3) Install diagonal braces. The location of the diagonal braces is set at 2/3 of the wall. The angle between the diagonal braces and the horizontal line ranges from 55° to 65°. At least 2 diagonal braces are installed for each prefabricated shear wall component;

斜撑两端分别与预制剪力墙构件和楼板均利用膨胀螺栓固定。预制剪力墙构件通过预埋的螺丝套筒安放膨胀螺栓,楼板采用电钻打孔后放置预埋螺栓。使用固定斜撑的微调功能调节墙体的垂直度;应用的斜撑以拉压两种功能的为主。The two ends of the diagonal brace are respectively fixed with the prefabricated shear wall components and the floor slab with expansion bolts. The prefabricated shear wall components are placed with expansion bolts through the pre-embedded screw sleeves, and the floor slab is drilled with an electric drill to place the pre-embedded bolts. Use the fine-tuning function of the fixed diagonal brace to adjust the verticality of the wall; the applied diagonal brace mainly has two functions of tension and compression.

4)、封堵墙下缝,将1.5~1.8倍缝宽的遇水膨胀止水条预先粘牢于外墙水平缝部位,如采取搭接连接时,搭接宽度不得小于30mm,然后封打发泡密封胶,再用密封膏嵌缝,底部捻1:2干硬性水泥砂浆;竖向缝自缝隙内侧采用板条临时固定,施打发泡胶,再用密封膏嵌缝,外敷玻纤网格布抗裂加强面;4) To seal the lower seam of the wall, pre-glue the water-swellable water-stop strip with a width of 1.5 to 1.8 times to the horizontal seam of the outer wall. If a lap joint is used, the lap joint width shall not be less than 30mm, and then seal and send Foam sealant, then caulk with sealant, twist 1:2 dry hard cement mortar at the bottom; temporarily fix the vertical joints from the inside of the gap with lath, apply foam glue, caulk with sealant, and apply glass fiber grid outside Anti-crack reinforcement surface of cloth;

当平缝过宽或墙板错台过大时,可先将墙板底部清理干净,浇水湿润,但同样要采取隔离条等遮挡措施,避免砂浆进入墙体底部内而削弱断面尺寸。然后用细石砼封堵,再捻1:2干硬性砂浆,并应捻塞密实,避免注浆时漏浆。When the flat seam is too wide or the staggering of the wall panel is too large, the bottom of the wall panel can be cleaned first and watered to moisten it. However, shielding measures such as isolation strips should also be taken to prevent the mortar from entering the bottom of the wall and weakening the section size. Then block it with fine stone concrete, and then twist 1:2 dry hard mortar, and twist the plug tightly to avoid grout leakage during grouting.

5)、预制剪力墙体后浇带钢筋绑扎,先安放后浇带焊接钢筋环,再放置竖向主筋,然后将下层墙体的预留主筋与本层主筋绑扎,水平箍筋与主筋及预制剪力墙构件墙体预留水平环筋进行绑扎。5) Binding of prefabricated shear walls with post-pouring steel bars, place the post-casting belt welding steel bar ring first, then place the vertical main bars, then tie the reserved main bars of the lower wall with the main bars of this layer, horizontal stirrups and main bars and The prefabricated shear wall component walls reserve horizontal ring bars for binding.

6)、预制剪力墙体后浇带支模,包括一字型墙体后浇带支模、转角处墙体后浇带支模和T字型墙体后浇带支模,模板采用胶合板,配合60×60木方,用穿墙螺栓固定。6) Prefabricated shear wall post-cast strip support formwork, including one-shaped wall post-cast strip support formwork, corner wall post-cast strip support formwork and T-shaped wall post-cast strip support formwork, the template is made of plywood , with a 60×60 wooden square, fixed with through-wall bolts.

7)、确定下层隔墙插筋位置,吊装预制隔墙构件,使下层预留插筋进入吊装的预制隔墙构件中,构件安装就位后与预先弹放的控制线吻合。7) Determine the location of the ribs on the lower partition wall, hoist the prefabricated partition wall components, and make the reserved ribs on the lower layer enter the hoisted prefabricated partition wall components. After the components are installed in place, they coincide with the pre-release control lines.

8)、预制隔墙构件与相邻已安装的预制剪力墙构件的连接采用螺栓连接,通过预制隔墙构件内预埋的至少两个连接螺栓与预制剪力墙构件内预埋铁盒连接。铁盒与预制剪力墙整体连接牢固,铁盒一面开口露在墙外留一洞口,且洞口应开得略大,便于调整。在螺栓与铁盒间放置一块与铁盒壁厚相同比洞口略大的垫片。现场安装时,待预制隔墙的标高和水平、垂直都到位后,把螺栓拧紧。8) The connection between the prefabricated partition wall components and the adjacent installed prefabricated shear wall components is connected by bolts, and at least two connecting bolts embedded in the prefabricated partition wall components are connected with the pre-embedded iron box in the prefabricated shear wall components . The overall connection between the iron box and the prefabricated shear wall is firm, and one side of the iron box is exposed to the outside of the wall to leave a hole, and the hole should be slightly larger for easy adjustment. Place a gasket with the same wall thickness as the iron box and slightly larger than the hole between the bolt and the iron box. When installing on site, tighten the bolts after the elevation, level and vertical of the prefabricated partition are in place.

9)、预制隔墙构件与相邻现浇墙体连的接通过预埋钢筋锚固,通过隔墙内预埋的2个φ6锚固钢筋与现浇墙体进行锚固;9) The connection between the prefabricated partition wall components and the adjacent cast-in-place wall is anchored by pre-embedded steel bars, and the two φ6 anchor bars pre-buried in the partition wall are anchored to the cast-in-place wall;

10)、预制隔墙构件的预埋管线连接,预制隔墙构件下部预留有管线接头凹槽,预制隔墙构件墙内的预埋管线在所述凹槽处甩出接头,使预制隔墙构件的管线与下层管线连接;预制隔墙构件的预留管线接头在上部叠合板交接处与现浇板内铺设的管线连接,接头处,用胶带缠绑紧密。10) The prefabricated partition wall components are connected by pre-embedded pipelines. The lower part of the prefabricated partition wall components is reserved with pipeline joint grooves. The pipeline of the component is connected with the pipeline of the lower layer; the reserved pipeline joint of the prefabricated partition wall component is connected with the pipeline laid in the cast-in-place slab at the junction of the upper laminated slab, and the joint is tightly wrapped with tape.

11)、预制隔墙构件与楼板安装,预制隔墙构件预留有楼板凹槽,楼板对应位置处也预留有相应凹槽,预制隔墙构件安装完成后用水泥砂浆抹平所述凹槽。11) The prefabricated partition wall components are installed with the floor slab. The prefabricated partition wall components are reserved with floor grooves, and corresponding grooves are also reserved at the corresponding positions of the floor slabs. After the prefabricated partition wall components are installed, smooth the grooves with cement mortar .

12)、预制隔墙构件安装完毕后,用砂浆封堵四周。对于墙体特别是外墙的安装,局部安装不规范,及其连接处易出现水泥浆外渗漏现象,严重影响墙体的观感。因此制定了将外墙的阳角采取一次性制作成型,使外保温与墙体砼成为一体化,现场简化工序,能够有效控制墙体制作安装、水泥浆外渗漏和墙体观感等通病问题得到改善。12) After the prefabricated partition wall components are installed, seal the surroundings with mortar. For the installation of the wall, especially the exterior wall, the local installation is not standardized, and the leakage of cement slurry is prone to occur at the joints, which seriously affects the appearance of the wall. Therefore, it is formulated that the external corners of the external wall should be manufactured and formed at one time, so that the external thermal insulation and the wall concrete can be integrated, the process can be simplified on site, and the common problems such as wall production and installation, cement slurry leakage and wall appearance can be effectively controlled. Improved.

13)、进行预制墙体构件的竖孔注浆孔灌浆和预制剪力墙体后浇带浇筑;后浇带内的空腔用大功率吸尘器进行清理,在混凝土浇筑前基层及后浇带内必须用水充分湿润。13) Carry out vertical hole grouting hole grouting of prefabricated wall components and prefabricated shear wall post-casting tape pouring; the cavity in the post-casting tape is cleaned with a high-power vacuum cleaner, and the base layer and post-casting tape before concrete pouring It must be well moistened with water.

14)、混凝土养护及脱模。14), Concrete curing and demoulding.

优选的,斜撑的上下两端分别与预制剪力墙构件和楼板采用膨胀螺栓固定,斜撑上部通过预制剪力墙构件内的预埋螺栓套筒安放膨胀螺丝固定,斜撑下部通过膨胀螺栓打入楼板固定。Preferably, the upper and lower ends of the diagonal brace are respectively fixed to the prefabricated shear wall component and the floor with expansion bolts, the upper part of the diagonal brace is fixed by the pre-embedded bolt sleeve in the prefabricated shear wall component and the expansion screw is placed, and the lower part of the diagonal brace is fixed by the expansion bolt Drive into the floor to fix.

优选的,所述下层剪力墙插筋为梯子筋,梯子筋主筋规格和外形尺寸根据预制剪力墙构件的预埋钢筋孔洞而定。Preferably, the lower shear wall insertion bars are ladder bars, and the specifications and dimensions of the main bars of the ladder bars are determined according to the pre-embedded reinforcement holes of the prefabricated shear wall components.

本发明的一种预制墙体构件的制作及安装方法和现有技术相比,具有以下有益效果:Compared with the prior art, a method for making and installing a prefabricated wall component of the present invention has the following beneficial effects:

实现设计、生产、施工一体化、精细化,通过标准化、装配化形成集成技术。现场装配,生产效率高,减少用工成本;装配安装可以将误差控制毫米级,墙体无渗漏、无裂缝;室内可实现100%无抹灰工程;施工中能做到节水、节材、节能,减少垃圾的产生、减少脚手架及支撑架的使用;施工现场基本无扬尘、废水、噪音,进一步保护环境;Realize the integration and refinement of design, production and construction, and form integrated technology through standardization and assembly. On-site assembly, high production efficiency, and reduced labor costs; assembly and installation can control errors to the millimeter level, and the wall has no leakage or cracks; indoors can achieve 100% no plastering; construction can save water, materials, Energy saving, reducing the generation of garbage, reducing the use of scaffolding and support frames; there is basically no dust, waste water, and noise on the construction site, further protecting the environment;

将设计标准化、产品工业化、作业机械化有效结合,代替传统的手工建筑施工,借助于信息技术手段,用整体综合集成的方法把工程建设的全部过程组织起来,使设计、采购、施工、机械设备和劳动力实现资源配置更加优化组合,采用工程总承包的组织管理模式,在有限的时间内发挥最有效的作用,提高资源的利用效率,创造更大的效用价值。Effectively combine design standardization, product industrialization, and operation mechanization to replace traditional manual building construction. With the help of information technology, use the method of overall comprehensive integration to organize the entire process of engineering construction, so that design, procurement, construction, mechanical equipment and The labor force achieves a more optimized combination of resource allocation, adopts the organization and management model of general contracting, plays the most effective role within a limited time, improves the utilization efficiency of resources, and creates greater utility value.

附图说明Description of drawings

图1是预制墙体构件的制作流程图;Fig. 1 is the production flowchart of prefabricated wall body member;

图2是预埋长螺母的绑扎固定示意;Figure 2 is a schematic diagram of the binding and fixing of the embedded long nut;

图3是预埋钢丝绳的固定示意图;Fig. 3 is the fixed sketch map of embedded wire rope;

图4是预埋钢环的固定示意图;Figure 4 is a schematic diagram of fixing the embedded steel ring;

图5是预埋伞柄钩的固定示意图;Fig. 5 is the fixing sketch map of embedded umbrella handle hook;

图6是剪力墙构件的斜撑安装示意图;Fig. 6 is a schematic diagram of the installation of the diagonal brace of the shear wall member;

图7是一字型剪力墙后浇带支模结构示意图;Fig. 7 is a schematic diagram of the post-cast belt formwork structure of the in-line shear wall;

图8是转角处剪力墙墙体后浇带支模结构示意图;Fig. 8 is a schematic diagram of the post-cast belt formwork structure of the shear wall at the corner;

图9是T字型剪力墙墙体后浇带支模结构示意图。Fig. 9 is a schematic diagram of the post-cast belt formwork structure of the T-shaped shear wall.

图中:1、长螺母,2、铁丝,3、板内筋,4、钢丝绳,4-1钢丝绳散开段,5、辅助筋,6、钢环,7、伞柄钩,8、预制剪力墙构件,9、预埋螺丝套筒,10、膨胀螺栓,11、预制叠合板,12、现浇楼板,13、斜撑,14、钢管,15、塑料套管,16、对拉螺栓,17、水泥撑条,18、固定螺母,19、3字卡扣,20、模板。In the figure: 1. Long nut, 2. Iron wire, 3. Inner reinforcement of the plate, 4. Steel wire rope, 4-1 steel wire rope spreading section, 5. Auxiliary reinforcement, 6. Steel ring, 7. Umbrella handle hook, 8. Prefabricated shear Force wall components, 9. Embedded screw sleeves, 10. Expansion bolts, 11. Prefabricated laminated slabs, 12. Cast-in-place floor slabs, 13. Diagonal braces, 14. Steel pipes, 15. Plastic sleeves, 16. Pull bolts, 17, cement stays, 18, fixed nuts, 19, 3 word buckles, 20, formwork.

具体实施方式detailed description

下面结合附图和具体实施例对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

一种预制墙体构件的制作方法,所述预制墙体构件内具有钢筋骨架和预埋件,并留有预埋钢筋孔洞、注浆孔和排气孔,其制作方法如下;A method for making a prefabricated wall component, wherein the prefabricated wall component has a steel bar skeleton and embedded parts, and has pre-embedded steel bar holes, grouting holes and vent holes, and the manufacturing method is as follows;

1)、首先根据墙体的外形尺寸支设模板;根据混凝土构件的设计图纸进行模具设计,模具精度控制在2mm内,模具要满足装饰面平整度的要求、钢筋及预埋件的位置精度要求、预制构件结构尺寸精度要求以及易于振捣密实。1) First, support the formwork according to the external dimensions of the wall; design the mold according to the design drawings of the concrete components, and control the precision of the mold within 2mm. , Prefabricated component structural dimensional accuracy requirements and easy vibration compaction.

模板安装时需要注意模板必须清理干净,模板隔离剂不得有漏涂或流淌现象,模板的安装、固定、要求平直、紧密、不倾斜,并且尺寸要求准确。When installing the formwork, it is necessary to pay attention that the formwork must be cleaned, the formwork release agent must not leak or flow, the installation and fixation of the formwork must be straight, tight, not inclined, and the size must be accurate.

2)、在模板内放置钢筋骨架和预埋件,半成品钢筋切断、对焊、成型的加工时要保证尺寸超差不应大于允许偏差的1.5倍,弯曲成型的钢筋应控制其弯曲直径;由于墙体构件属于板类构件,钢筋的主筋保护层相对较小,因此,钢筋的骨架尺寸必须准确,故要采用专门的成型架成型;钢筋成品(骨架)中钢筋、配件和埋件的品种、规格、数量和位置等应符合有关标准规定和设计文件要求,开孔部位应根据图纸要求配置加强筋,加强筋不少于三处绑扎固定点。钢筋骨架应轻放入模,入模后不得移动钢筋骨架,钢筋骨架应采用垫、吊等方式,满足钢筋各部位的保护层厚度;钢筋入模安装时,保证钢筋笼平直、无损伤,表面不得有油污、颗粒状或片状老锈;钢筋安装时,钢筋网和钢筋成品(骨架)安装位置不得超出允许偏差。2) Place the steel bar skeleton and embedded parts in the formwork. When cutting, butt welding, and forming semi-finished steel bars, it is necessary to ensure that the size tolerance should not exceed 1.5 times the allowable deviation. The bending diameter of the bent steel bars should be controlled; because Wall components belong to plate components, and the protective layer of the main reinforcement of the steel bar is relatively small. Therefore, the skeleton size of the steel bar must be accurate, so a special forming frame should be used for forming; the types of steel bars, accessories and embedded parts in the finished steel bar (skeleton), Specifications, quantity and location shall comply with relevant standards and requirements of design documents. Reinforcing ribs shall be arranged in openings according to drawing requirements, and there shall be no less than three binding and fixing points for reinforcing ribs. The steel frame should be put into the mold lightly, and the steel frame should not be moved after it is put into the mold. The steel frame should be cushioned, hung, etc. to meet the thickness of the protective layer of each part of the steel; when the steel is installed in the mold, ensure that the steel cage is straight and free There must be no oil stains, granular or flaky old rust on the surface; when the steel bars are installed, the installation positions of the steel mesh and finished steel bars (skeleton) must not exceed the allowable deviation.

固定在模板上的预埋件、预留孔和预留洞的安装位置不应超过允许偏差。The installation position of the embedded parts, reserved holes and reserved holes fixed on the formwork shall not exceed the allowable deviation.

3)、混凝土的制备与浇筑,按照实验室的混凝土配合比单及指定材料进行混凝土的拌制,各材料重量偏差在规定范围内。混凝土的各种材料全部装入搅拌机至出料的搅拌时间不少于90秒,混凝土的运输在固定模台采用提吊式运输及布料方式,在流水线生产车间采用鱼雷罐送料、自动布料机布料方式,每次运输方量应与浇灌方量、浇灌速度相适应,以保证拌合物在灌筑时具有良好的和易性。3) For the preparation and pouring of concrete, the concrete is mixed according to the concrete mix list and specified materials in the laboratory, and the weight deviation of each material is within the specified range. All kinds of concrete materials are loaded into the mixer and the mixing time for discharging is not less than 90 seconds. The concrete is transported on the fixed formwork by lifting and distributing. In the assembly line production workshop, torpedo tank feeding and automatic distributing machine are used. The method, each transportation volume should be adapted to the pouring volume and pouring speed, so as to ensure that the mixture has good workability during pouring.

混凝土浇筑前,检查模具、支架、钢筋和埋件,模板要清理干净并涂刷脱模剂;浇捣成型时,确保浇筑时间不超过30分钟,生产成型时确保平整光滑,有棱有角,且密实度有保证,每批要按规定做好抗压试块和同条件养护试块的留样和试验。Before pouring concrete, check molds, brackets, steel bars and embedded parts. The formwork should be cleaned and painted with release agent; when pouring and forming, ensure that the pouring time does not exceed 30 minutes, and ensure that it is smooth and smooth with edges and corners during production and molding. And the compactness is guaranteed. For each batch, the reserved samples and tests of the compression test blocks and the same condition curing test blocks should be done according to the regulations.

混凝土振捣应密。The concrete should be vibrated densely.

4)、预制墙体构件蒸汽养护,混凝土浇筑后,静停不小于2小时,升温约2小时,升温速度不大于15℃/小时;恒温月4小时,恒温养护温度范围在55℃~60℃;降温月3小时,降温速度不大于10℃/小时。4) Steam curing of prefabricated wall components. After concrete pouring, stop for not less than 2 hours, heat up for about 2 hours, and the heating rate is not more than 15°C/hour; constant temperature is 4 hours, and the temperature range of constant temperature curing is 55°C~60°C ;The cooling time is 3 hours, and the cooling rate is not more than 10°C/hour.

对于在自动化流水线车间生产的构件采用立体养护窑的方式进行蒸汽养护,温湿度均为自动监测、自动控制。For the components produced in the automatic assembly line workshop, the three-dimensional curing kiln is used for steam curing, and the temperature and humidity are automatically monitored and controlled.

对于在固定模台生产的构件采用推拉折叠式养护罩的方式进行蒸汽养护,安排专人每隔0.5小时进行温湿度测量及控制。For the components produced on the fixed mold table, the push-pull folding curing cover is used for steam curing, and special personnel are arranged to measure and control the temperature and humidity every 0.5 hours.

5)、脱模,预制墙体构件达到混凝土抗压强度设计值的75%,且不小于15N/ mm 时脱模,拆模强度以试验室对同条件养护试块的抗压强度检测结果为准。5) Demoulding, when the prefabricated wall components reach 75% of the design value of the concrete compressive strength and not less than 15N/mm, the demoulding strength is based on the test results of the compressive strength of the test block under the same conditions in the laboratory. allow.

根据模具结构和拆除顺序拆除模具,避免对预制构件造成损坏,且不得用振动构件方式拆模。使用外力先顶推构件使之与模具脱离,脱模后,对水洗面进行冲洗。除去墙板边缘多余的混凝土渣,构件采用平吊出模,预制墙体构件起吊前应确认构件与模具间的连接部分完全拆除,避免构件与模具之间产生过大的吸附力而导致保护层破坏,起吊的吊点宜4~6点吊进行。Remove the mold according to the mold structure and removal sequence to avoid damage to the prefabricated components, and do not use vibration components to remove the mold. Use external force to push the component first to separate it from the mold, and rinse the water-washed surface after demoulding. Remove the excess concrete slag on the edge of the wall panel, and the components are lifted out of the mold. Before lifting the prefabricated wall components, it is necessary to confirm that the connection between the component and the mold is completely removed, so as to avoid excessive adsorption between the component and the mold and cause the protective layer to be damaged. If it is damaged, the lifting point should be lifted at 4 to 6 points.

建立预制构件编码系统,在构件醒目位置根据编码方案进行编码,编码应用水性环保涂料或塑料贴模等可清除材料。Establish a coding system for prefabricated components, and code according to the coding scheme at the conspicuous position of the components, and use water-based environmental protection paint or plastic molding and other removable materials for coding.

6)、构件侧翻、立起后,运送至堆场,预制墙体构件采用竖直立放式运输,可采用平放或堆放架辅助式立放。预制墙体构件运输选用低平板车,车上设有专用架,有可靠的稳定构件措施。预制墙体构件混凝土强度达到设计强度时方可外运。6) After the components are turned over and erected, they are transported to the storage yard. The prefabricated wall components are transported vertically, and can be placed flat or assisted by stacking racks. Prefabricated wall components are transported on low-bed vehicles with special racks and reliable measures to stabilize components. The concrete strength of the prefabricated wall components can only be transported outside when the strength reaches the design strength.

7)、预制墙体构件采用插放或靠放,堆放架有足够的刚度,并支垫稳固。堆场将相邻堆放架连成整体,预制外墙板将外饰面朝外,对连接止水条、高低口、墙体转角等薄弱部位,采用定型保护垫块或专用式附套件加强保护。7) The prefabricated wall components are inserted or leaned on, and the stacking frame has sufficient rigidity, and the pads are stable. The stacking yard connects the adjacent stacking racks into a whole, and the prefabricated exterior wall panels face outwards. For weak parts such as connecting waterstops, high and low openings, and wall corners, use shaped protective pads or special accessories to strengthen protection .

其中,所述预制墙体构件的预埋件包括长螺母1、钢丝绳4、钢环6和伞柄钩7,Wherein, the embedded part of the prefabricated wall component includes a long nut 1, a steel wire rope 4, a steel ring 6 and an umbrella handle hook 7,

长螺母1的预埋,长螺母1预埋端焊接固定有横向辅助筋5,横向辅助钢筋通过铁丝2绑扎固定于板内筋3,如图2所示;For the pre-embedding of the long nut 1, the pre-embedded end of the long nut 1 is welded and fixed with a transverse auxiliary reinforcement 5, and the lateral auxiliary reinforcement is bound and fixed to the inner rib 3 of the panel by iron wire 2, as shown in Figure 2;

钢丝绳4的预埋,钢丝绳4的两预埋端端部散开,钢丝绳散开段4-1的散开长度大于400mm,散开部分用铁丝2绑扎固定于板内筋3,每三股一组与板内筋3搭接固定,设置有辅助筋5将钢丝绳4限位,如图3所示;Pre-embedding of steel wire rope 4, the two pre-embedded ends of steel wire rope 4 are spread out, the spread length of steel wire rope spread out section 4-1 is greater than 400mm, and the spread out part is bound and fixed to panel inner reinforcement 3 with iron wire 2, and each set of three strands It is lapped and fixed with the inner rib 3 of the plate, and an auxiliary rib 5 is provided to limit the position of the steel wire rope 4, as shown in Figure 3;

钢环6的预埋,钢环6为开口钢环,开口端两固定脚固定于板内筋3固定,设置辅助筋5辅助定位,如图4所示;The pre-embedding of the steel ring 6, the steel ring 6 is an open steel ring, the two fixed feet at the open end are fixed to the ribs 3 inside the plate, and the auxiliary ribs 5 are set to assist positioning, as shown in Figure 4;

伞柄钩7的预埋,钩端勾住板内筋3固定,如图5所示。The pre-embedding of the umbrella handle hook 7, the hook end hooks the rib 3 in the plate and fixes it, as shown in Figure 5.

预制墙体构件包括预制剪力墙构件和预制隔墙构件,预制剪力墙构件的预埋件还包括预埋铁盒,预埋铁盒一面开口露在预制剪力墙构件墙外,且外露部分开设有安装孔洞,用做预制隔墙构件的固定连接处;预制隔墙构件的预埋件还包括至少两个连接螺栓,所述连接螺栓的直径小于所述安装孔洞的最小尺寸;预制隔墙构件与预制剪力墙构件固定时利用连接螺栓与预埋铁盒的连接固定。Prefabricated wall components include prefabricated shear wall components and prefabricated partition wall components. The embedded parts of prefabricated shear wall components also include prefabricated iron boxes. Some installation holes are provided for the fixed connection of the prefabricated partition wall components; the embedded parts of the prefabricated partition wall components also include at least two connecting bolts, and the diameter of the connecting bolts is smaller than the minimum size of the installation hole; the prefabricated partition wall components When the wall components and the prefabricated shear wall components are fixed, the connecting bolts and the pre-embedded iron boxes are used for fixing.

预制隔墙构件还预留有管线接口槽和楼板凹槽,用于预制隔墙构件的预埋管线连接和楼板安装。The prefabricated partition wall components are also reserved with pipeline interface grooves and floor grooves, which are used for the embedded pipeline connection and floor slab installation of the prefabricated partition wall components.

预制隔墙构件还预埋有至少2个φ6锚固钢筋,φ6锚固钢筋用于预制隔墙构件与现浇墙体的锚固。The prefabricated partition wall component is also pre-embedded with at least two φ6 anchoring steel bars, which are used for anchoring the prefabricated partition wall component and the cast-in-place wall.

预制剪力墙构件的预埋件还包括用于固定膨胀螺栓的螺丝套筒,螺丝套筒用于剪力墙安装斜撑时放置膨胀螺栓,螺丝套筒水平放置预埋,其一端与墙面平齐,便于膨胀螺栓的安放。The embedded parts of prefabricated shear wall components also include screw sleeves for fixing expansion bolts. The screw sleeves are used to place expansion bolts when the shear wall is installed with braces. Flat, easy to place expansion bolts.

一种预制墙体构件,包括预制剪力墙构件和预制隔墙构件,使用模具由混凝土浇筑而成,预制墙体构件内具有钢筋骨架和预埋件,预埋件包括长螺母、钢丝绳、钢环和伞柄钩;并预留有预埋钢筋孔洞、注浆孔和排气孔。其中,预制剪力墙构件的预埋件还包括预埋铁盒,预埋铁盒一面开口并露出预制墙体,外露部分开设螺栓连接孔洞。预制隔墙构件的预埋件还包括至少两个连接螺栓和锚固钢筋,所述连接螺栓的直径小于所述螺栓安装孔洞的最小尺寸。所述连接螺栓用于与所述预埋铁盒连接,从而连接预制隔墙构件和预制剪力墙构件;所述锚固钢筋用于预制隔墙构件与现浇墙体锚固。A prefabricated wall component, including a prefabricated shear wall component and a prefabricated partition wall component, which is formed by pouring concrete using a mold. The prefabricated wall component has a steel skeleton and embedded parts, and the embedded parts include long nuts, steel wire ropes, steel Ring and umbrella handle hook; and pre-embedded steel holes, grouting holes and vent holes are reserved. Among them, the embedded parts of the prefabricated shear wall components also include a pre-embedded iron box, one side of the pre-embedded iron box is open and exposes the prefabricated wall, and the exposed part is provided with bolt connection holes. The embedded part of the prefabricated partition wall component also includes at least two connecting bolts and anchoring steel bars, and the diameter of the connecting bolts is smaller than the minimum size of the bolt installation hole. The connecting bolt is used to connect with the pre-embedded iron box, thereby connecting the prefabricated partition wall component and the prefabricated shear wall component; the anchoring steel bar is used for anchoring the prefabricated partition wall component and the cast-in-situ wall.

预制隔墙构件还预留有管线接口槽和楼板凹槽,管线接口槽用于预制隔墙构件的管线安装,楼板凹槽用于预制隔墙构件与楼板的安装。The prefabricated partition wall component is also reserved with a pipeline interface groove and a floor groove, the pipeline interface groove is used for pipeline installation of the prefabricated partition wall component, and the floor slab groove is used for the installation of the prefabricated partition wall component and the floor slab.

一种预制墙体构件的安装方法,对于上述的制作方法制作而成的预制墙体构件以及上述的一种预制墙体构件进行现场安装,安装前的准备工作包括:A method for installing a prefabricated wall component. The prefabricated wall component made by the above-mentioned manufacturing method and the above-mentioned prefabricated wall component are installed on site. The preparatory work before installation includes:

根据预制构件吊装及施工要求,确定现场外脚手架采用形式,如采用外挑架,给定预留槽钢位置和洞口位置,墙体现浇位置;According to the hoisting and construction requirements of prefabricated components, determine the form of scaffolding outside the site, such as using an external cantilever frame, specify the reserved channel steel position and opening position, and the pouring position of the wall;

楼板中预留放线洞口位置,在当前楼层四个基准外角点相对应的正上方预留一个20cm×20cm方洞,以便于上层轴线定位放线时,经纬仪对下层基准点的引用。根据规划给定的基准线及基准点,对引入楼层的控制线、控制点的轴线及标高进行复合检查。Reserve the location of the opening for the release of wires in the floor, and reserve a 20cm×20cm square hole directly above the four reference outer corners of the current floor, so that the theodolite can reference the reference points of the lower floor when the axis of the upper floor is positioned and the release is made. According to the given datum line and datum point in the plan, compound inspection is carried out on the control line of the incoming floor, the axis and the elevation of the control point.

在预制构件上标出轴线位置,以便于安装方向的控制。Mark the axis position on the prefabricated components to facilitate the control of the installation direction.

确定首层预制剪力墙插筋位置。根据预制墙体构件预留插筋空洞固定插筋位置,用与剪力墙设计相同的主筋规格焊接做成梯子筋,现场施工时控制梯子筋第一排主筋位置。Determine the location of the first-floor prefabricated shear wall reinforcement. According to the prefabricated wall components, the holes for inserting ribs are reserved to fix the position of the inserting ribs, and the ladder ribs are welded with the same main rib specifications as the shear wall design, and the position of the first row of main ribs of the ladder ribs is controlled during on-site construction.

预制构件与混凝土基层结合面在构件安装前进行凿毛、剔除表面浮浆并洒水湿润等工作,即按混凝土施工缝进行基层面处理。预制混凝土构件安装时的混凝土强度,不低于同条件养护的混凝土设计强度等级值的75%。The joint surface of the prefabricated components and the concrete base should be chiseled before the components are installed, the surface laitance should be removed, and the surface should be sprinkled and wetted, that is, the base surface should be treated according to the concrete construction joints. The concrete strength of precast concrete components during installation shall not be lower than 75% of the design strength grade value of concrete cured under the same conditions.

安装步骤如下:The installation steps are as follows:

1)、确定下层剪力墙插筋位置,测量放线,安放标高垫块;1) Determine the location of the lower shear wall to insert reinforcement, measure and set out the line, and place the elevation block;

测量放线时先确定首层定位轴线的四个基准外角点,即距相邻两条外轴线1m的垂线交点,用经纬仪从四周龙门桩上引入,或用全站仪从现场GPS坐标定位的基准点引入;楼层标高控制点用水准仪从现场水准点引入。When measuring and setting out the line, first determine the four reference outer corner points of the positioning axis on the first floor, that is, the intersection point of the vertical line 1m away from the two adjacent outer axes, and use the theodolite to introduce it from the surrounding gantry piles, or use the total station to locate it from the GPS coordinates on the spot The reference point is introduced; the floor elevation control point is introduced from the on-site benchmarking point with a level gauge.

进行首层定位放线,使用经纬仪利用引入的四个基准外角点放出楼层四周外墙轴线。待轴线复核无误后,作为本层的基准线。Carry out the positioning and laying out of the first floor, and use theodolite to use the introduced four reference outer corner points to release the axis of the outer wall around the floor. After the axis is rechecked and correct, it will be used as the baseline of this layer.

以四周外墙轴线为基准线,使用5m钢卷尺放出外墙安装位置线。先放四个外墙角位置线,后放外墙中部墙体位置线。Taking the axis of the surrounding exterior walls as the reference line, use a 5m steel tape to release the installation position line of the exterior wall. Place the position lines of the four exterior corners first, and then place the position lines of the middle wall of the exterior wall.

待四周外墙位置线放好后,以此为控制线,以50m钢卷尺为工具放内墙位置线。先放楼梯间的三面内墙位置线,再放其它内墙位置线;先放大墙位置线,后放小墙位置线;先放承重墙位置线,后放非承重墙位置线。After the surrounding outer wall position lines are placed, use this as the control line, and use a 50m steel tape measure as a tool to place the inner wall position lines. First place the position lines of the three interior walls in the stairwell, and then place the other interior wall position lines; first enlarge the wall position lines, and then place the small wall position lines; first place the load-bearing wall position lines, and then place the non-load-bearing wall position lines.

在预留门洞处准确无误的放出门洞线。Accurately release the door opening line at the reserved door opening.

在外墙内侧,内墙两侧20cm处放出墙体安装控制线。On the inner side of the outer wall, let out the wall installation control line at 20cm on both sides of the inner wall.

使用水准仪利用楼层标高控制点,控制好预制墙体下垫块表面标高。Use the level gauge to control the surface elevation of the cushion block under the prefabricated wall by using the floor elevation control point.

待预制墙体构件安装好后,使用水准仪利用楼层标高控制点,在墙体放出50控制线,以此做为预制叠合梁、板和现浇板模板安装标高控制线。After the prefabricated wall components are installed, use the level gauge to use the floor elevation control point to release the 50 control line on the wall, and use it as the installation elevation control line for prefabricated composite beams, slabs and cast-in-place slab formwork.

放出预制墙体构件外边四周控制轴线时,保证外墙大角在转角处成900规方。再放出每片墙体的位置控制线及抄平每片墙体的标高控制块,每片墙体下的标高控制块不少于2块。When releasing the control axis around the outer edge of the prefabricated wall components, ensure that the large corners of the outer walls form 900 square meters at the corners. Then release the position control line of each wall and level the elevation control block of each wall. The elevation control block under each wall should be no less than 2 pieces.

标高控制块安放方法:先将垫块一面用角磨机磨平后(垫块长度小于墙体2mm),用砂浆座浆安放垫块,水准仪配合标尺调整垫块表面标高,待垫块养护强度达到要求,方可吊装预制墙体构件。Elevation control block placement method: First, grind one side of the block with an angle grinder (the length of the block is less than 2mm of the wall), place the block with mortar, adjust the surface elevation of the block with the level gauge and the ruler, and wait for the strength of the block to be maintained. Only when the requirements are met can the prefabricated wall components be hoisted.

2)、吊装预制剪力墙结构件,吊索与水平线夹角不小于600,下落至安装部位0.5米处缓慢就位。墙体构件吊装由3人对墙体构件对位、扶正,使下层剪力墙预留插筋进入吊装的预制剪力墙构件中,构件安装就位后与预先弹放的控制线吻合。2) When hoisting the prefabricated shear wall structure, the angle between the sling and the horizontal line is not less than 60°, and it falls slowly to the installation site at 0.5 meters. The hoisting of the wall components requires three people to align and straighten the wall components, so that the inserted ribs reserved for the lower shear wall enter the hoisted prefabricated shear wall components. After the components are installed in place, they coincide with the pre-release control lines.

3)、如图6所示,安装斜撑13,斜撑13位置设置于预制剪力墙构件8墙体的2/3处,斜撑13与水平线夹角范围在55°~65°,每块预制剪力墙体构件8设置至少2个斜撑13;3) As shown in Figure 6, install the diagonal brace 13. The position of the diagonal brace 13 is set at 2/3 of the wall of the prefabricated shear wall member 8. The angle between the diagonal brace 13 and the horizontal line ranges from 55° to 65°. The block prefabricated shear wall member 8 is provided with at least two diagonal braces 13;

斜撑13两端分别与预制剪力墙构件8和现浇楼板12及预制叠合板11均利用膨胀螺栓10固定。预制剪力墙构件8通过预埋螺丝套筒9安放膨胀螺栓10,预制叠合板11采用电钻打孔后放置预埋螺栓10。膨胀螺栓10与现浇楼板12及预制叠合板11固定,膨胀螺栓10长度易为9cm,保证膨胀螺栓10进入预制叠合板11内3cm。使用斜撑13的微调功能调节预制剪力墙构件8的垂直度;应用的斜撑13以拉压两种功能的为主,斜撑13统一固定于预制剪力墙构件的一侧,留出过道,便于其他物品运输。Both ends of the diagonal brace 13 are respectively fixed with the prefabricated shear wall member 8 , the cast-in-place floor slab 12 and the prefabricated laminated slab 11 with expansion bolts 10 . The prefabricated shear wall member 8 places expansion bolts 10 through the prefabricated screw sleeve 9, and the prefabricated laminated plate 11 is drilled with an electric drill to place the prefabricated bolts 10. Expansion bolt 10 is fixed with cast-in-place floor slab 12 and prefabricated laminated slab 11, and the length of expansion bolt 10 is easily 9cm, guarantees that expansion bolt 10 enters 3cm in prefabricated laminated slab 11. Use the fine-tuning function of the diagonal brace 13 to adjust the verticality of the prefabricated shear wall component 8; the applied diagonal brace 13 mainly has two functions of tension and compression, and the diagonal brace 13 is uniformly fixed on one side of the prefabricated shear wall component, leaving Aisle for easy transportation of other items.

4)、封堵墙下缝,将1.5~1.8倍缝宽的遇水膨胀止水条预先粘牢于外墙水平缝部位,采取搭接连接时,搭接宽度不得小于30mm,然后封打发泡密封胶,再用密封膏嵌缝;周边严密,不得鼓出或折裂。外墙(内墙)板底部捻1:2干硬性水泥砂浆。竖向缝自缝隙内侧采用板条临时固定,施打发泡胶后再用20厚的密封膏嵌缝,外敷100mm宽玻纤网格布抗裂加强面,墙板就位后要达到上下两板垂直平整,垫块高度合适。1.5~1.8倍缝宽的膨胀止水条作为勾缝砂浆的底模。4) To seal the lower seam of the wall, glue the water-swellable water-stop strip 1.5 to 1.8 times the width of the seam to the horizontal seam of the outer wall in advance. When adopting lap joint connection, the lap joint width shall not be less than 30mm, and then seal and foam Sealant, and then caulk with sealant; the perimeter is tight and must not bulge or crack. Lay 1:2 dry hard cement mortar on the bottom of the outer wall (inner wall) board. The vertical seam is temporarily fixed from the inside of the seam with slats, and after applying styrofoam, caulk the seam with 20 thick sealant, and apply a 100mm wide glass fiber mesh cloth anti-crack reinforcement surface. After the wall board is in place, it must reach the upper and lower boards. It is vertical and flat, and the height of the spacer is suitable. The expansion water-stop strip with 1.5~1.8 times the joint width is used as the base form of the joint mortar.

平缝过宽或墙板错台过大时,可先将墙板底部清理干净,浇水湿润,但同样要采取隔离条等遮挡措施,避免砂浆进入墙体底部内而削弱断面尺寸。然后用细石砼封堵,再捻1:2干硬性砂浆,并应捻塞密实,避免注浆时漏浆。When the flat seam is too wide or the staggering of the wall panel is too large, the bottom of the wall panel can be cleaned first and watered to moisten it. However, shielding measures such as isolation strips should also be taken to prevent the mortar from entering the bottom of the wall and weakening the section size. Then use fine stone concrete to seal, and then twist 1:2 dry hard mortar, and twist the plug tightly to avoid grout leakage during grouting.

5)、剪力墙体后浇带钢筋绑扎,先安放后浇带焊接钢筋环,再放置竖向主筋,然后将下层墙体的预留主筋与本层主筋绑扎,水平箍筋与主筋及墙体预留水平环筋进行绑扎。暗柱下部3~4道箍筋可采取“”形状进行连接。5) For the binding of post-cast steel bars on the shear wall, first place the post-cast steel bar rings, then place the vertical main bars, then tie the reserved main bars of the lower wall with the main bars of this layer, and the horizontal stirrups with the main bars and the wall The body reserves horizontal ring bars for binding. The 3~4 stirrups at the lower part of the hidden column can be " ” shapes to connect.

6)、剪力墙体后浇带支模,包括一字型墙体后浇带支模、转角处墙体后浇带支模和T字型墙体后浇带支模,分别对应图7、图8和图9所示,模板20采用胶合板,使用对拉螺栓16配合钢管14、固定螺母18和3字卡扣19将模板20 固定,对拉螺栓16外设塑料套管15,模板20内有水泥撑条17作为支撑。一字型墙体后浇带支模结构如图7所示、转角处墙体后浇带支模结构如图8所示,T字型墙体后浇带支模结构如图9所示。6) Post-cast belt formwork for shear walls, including one-shaped wall post-cast belt formwork, corner wall post-cast belt formwork and T-shaped wall post-cast belt formwork, respectively corresponding to Figure 7 , shown in Fig. 8 and Fig. 9, formwork 20 adopts plywood, uses pull bolt 16 to coordinate steel pipe 14, fixed nut 18 and 3 character buckle 19 and formwork 20 is fixed, and pull bolt 16 is peripherally equipped with plastic casing 15, formwork 20 Concrete stay 17 is arranged as support in the interior. Figure 7 shows the post-cast formwork structure of the one-shaped wall, Figure 8 shows the post-cast formwork structure of the corner wall, and Figure 9 shows the T-shaped wall post-cast formwork support structure.

7)、确定下层隔墙插筋位置,吊装预制隔墙构件,使下层预留插筋进入吊装的预制隔墙构件中;7) Determine the location of the reinforcement for the lower partition wall, hoist the prefabricated partition wall components, and make the reserved reinforcement for the lower layer enter the hoisted prefabricated partition wall components;

8)、预制隔墙构件与相邻已安装的预制剪力墙构件的连接采用螺栓连接,通过预制隔墙构件内预埋的至少两个连接螺栓与预制剪力墙构件内预埋铁盒连接:铁盒与预制剪力墙整体连接牢固,铁盒一面开口露在墙外留一洞口,且洞口应开得略大,便于调整。在螺栓与铁盒间放置一块与铁盒壁厚相同比洞口略大的垫片。现场安装时,待预制隔墙的标高和水平、垂直都到位后,把螺栓拧紧。8) The connection between the prefabricated partition wall components and the adjacent installed prefabricated shear wall components is connected by bolts, and at least two connecting bolts embedded in the prefabricated partition wall components are connected with the pre-embedded iron box in the prefabricated shear wall components : The overall connection between the iron box and the prefabricated shear wall is firm, and one side of the iron box is exposed outside the wall to leave a hole, and the hole should be opened slightly larger for easy adjustment. Place a gasket with the same wall thickness as the iron box and slightly larger than the hole between the bolt and the iron box. When installing on site, tighten the bolts after the elevation, level and vertical of the prefabricated partition are in place.

9)、预制隔墙构件与相邻现浇墙体连的接通过预埋钢筋锚固,通过隔墙内预埋的2个φ6锚固钢筋与现浇墙体进行锚固;9) The connection between the prefabricated partition wall components and the adjacent cast-in-place wall is anchored by pre-embedded steel bars, and the two φ6 anchor bars pre-buried in the partition wall are anchored to the cast-in-place wall;

10)、预制隔墙构件的预埋管线连接,预制隔墙构件下部预留有管线接头凹槽,宽10cm×高20cm×厚5cm,预制隔墙构件墙内的预埋管线在所述凹槽处甩出接头,使预制隔墙构件的管线与下层管线连接;预制隔墙构件的预留管线接头在上部叠合板交接处与现浇板内铺设的管线连接,接头处,用胶带缠绑紧密。10) The pre-embedded pipeline connection of the prefabricated partition wall component, the lower part of the prefabricated partition wall component is reserved with a pipeline joint groove, 10cm wide x 20cm high x 5cm thick, and the embedded pipeline in the prefabricated partition wall component wall is in the groove The joints are thrown out at the joints to connect the pipelines of the prefabricated partition wall components to the lower pipelines; the reserved pipeline joints of the prefabricated partition wall components are connected to the pipelines laid in the cast-in-place slab at the junction of the upper laminated slabs, and the joints are wrapped tightly with adhesive tape .

11)、预制隔墙构件与楼板安装,预制隔墙构件预留有2cm楼板凹槽,楼板对应位置处也预留有相应的2cm凹槽,预制隔墙构件安装完成后用水泥砂浆抹平所述凹槽;11) Install prefabricated partition wall components and floor slabs. Prefabricated partition wall components are reserved with 2cm floor grooves, and corresponding 2cm grooves are also reserved at the corresponding positions of the floor slabs. After the prefabricated partition wall components are installed, smooth them with cement mortar. said groove;

12)、预制隔墙构件安装完毕后,用砂浆封堵四周。12) After the prefabricated partition wall components are installed, seal the surroundings with mortar.

13)、进行预制墙体构件的竖孔灌浆和剪力墙体后浇带浇筑;后浇带内的空腔用大功率吸尘器进行清理,在混凝土浇筑前基层及后浇带内必须用水充分湿润。13) Carry out vertical hole grouting of prefabricated wall components and pouring of post-casting strips of shear walls; the cavity in the post-casting strips shall be cleaned with a high-power vacuum cleaner, and the base and post-casting strips must be fully moistened with water before concrete pouring .

14)、混凝土养护及脱模。14), Concrete curing and demoulding.

通过上面具体实施方式,所述技术领域的技术人员可容易的实现本发明。但是应当理解,本发明并不限于上述的具体实施方式。在公开的实施方式的基础上,所述技术领域的技术人员可任意组合不同的技术特征,从而实现不同的技术方案。Through the above specific implementation manners, those skilled in the technical field can easily realize the present invention. However, it should be understood that the present invention is not limited to the specific embodiments described above. On the basis of the disclosed embodiments, those skilled in the art can arbitrarily combine different technical features, so as to realize different technical solutions.

除说明书所述的技术特征外,均为本专业技术人员的已知技术。Except for the technical features described in the instructions, all are known technologies by those skilled in the art.

Claims (10)

1. a kind of preparation method of precast wall body component, it is characterised in that there is framework of steel reinforcement and pre-buried in precast wall body component Part, and embedded bar hole, injected hole and steam vent are reserved with, its preparation method is as follows:
1), first according to the appearance and size supporting module of precast wall body component;
2), framework of steel reinforcement and built-in fitting are placed in template;
3), concrete prepare with pouring, brushing releasing agent before concreting;During pouring pounding molding, the time is poured no more than 30 points Clock, concrete vibrating;
4), precast wall body component steam curing, after concreting, it is quiet stop be not less than 2 hours, heating be not less than 2 hours, heating Speed is not more than 15 DEG C/h;Constant temperature is not less than 4 hours, and thermostatic curing temperature range is at 55 DEG C ~ 60 DEG C;Cooling is small not less than 3 When, cooling rate is not more than 10 DEG C/h;
5), precast wall body component the demoulding, precast wall body component reaches the 75% of concrete crushing strength design load, and is not less than It is stripped during 15N/ mm;
6), precast wall body component is turned on one's side, erected;
7), precast wall body component inserts or by putting.
2. the preparation method of a kind of precast wall body component according to claim 1, it is characterised in that the built-in fitting includes Long nut, steel wire rope, steel loop or umbrella stem hook,
Long nut it is pre-buried, the pre-buried end of long nut is welded with horizontal auxiliary bar, and horizontal auxiliary bar passes through iron wire colligation It is fixed on muscle in plate;
Steel wire rope it is pre-buried, two pre-buried end ends of steel wire rope are scattered, and fall-out length is more than 400mm, and ravel tied up with iron wire Bundle is fixed on muscle in plate;
Steel loop it is pre-buried, steel loop be opening steel loop, openend two fix pin be fixed on muscle and auxiliary bar in plate;
Umbrella stem hook it is pre-buried, hook end catches on muscle in plate and fixed.
3. a kind of preparation method of precast wall body component according to claim 1 or 2, it is characterised in that the precast wall body Component includes precast shear wall component and prefabricated partition wall component, and the built-in fitting of precast shear wall component includes pre-buried can, pre-buried Can one side opening is exposed at outside precast shear wall component, and exposed parts offer installation hole;Prefabricated partition wall component it is pre-buried Part includes at least two connecting bolts, and the diameter of the connecting bolt is less than the minimum dimension of the installation hole, prefabricated partition wall Component is also reserved with pipeline interface groove and floor groove.
4. the preparation method of a kind of precast wall body component according to claim 3, it is characterised in that prefabricated partition wall component is also It is embedded with the anchor bars of at least two φ 6.
5. a kind of preparation method of precast wall body component according to claim 3, it is characterised in that precast shear wall component Built-in fitting also include for fixed expansion bolt screw socket.
6. a kind of preparation method of precast wall body component according to claim 1, it is characterised in that steam curing mode bag Include three-dimensional curing kilns and push-pull folding curing cover.
7. a kind of precast wall body component, including precast shear wall component and prefabricated partition wall component, it is characterised in that it uses mould Formed by concreting, there is framework of steel reinforcement and built-in fitting, and be reserved with embedded bar hole, slip casting in precast wall body component Hole and steam vent;Wherein, the built-in fitting of precast shear wall component includes pre-buried can, and pre-buried can one side is open and exposed prefabricated Wall, exposed parts open up bolt connection hole;The built-in fitting of prefabricated partition wall component includes at least two connecting bolts and anchoring Reinforcing bar, the diameter of the connecting bolt is less than the minimum dimension in the bolt mounting holes hole, and prefabricated partition wall component is also reserved with pipe Line interface groove and floor groove.
8. a kind of installation method of precast wall body component, it is characterised in that to the making described in any one in claim 1~6 The precast wall body component that method is made carries out in-site installation, and installation steps are as follows:
1), determine lower floor's shear wall joint bar position, surveying setting-out lays absolute altitude cushion block;
2), hoisting prefabricated shearing wall member, lower floor shear wall reserved joint bar is entered in the precast shear wall component of lifting;
3), diagonal brace is installed, diagonal brace position is arranged at the 2/3 of wall, diagonal brace and horizontal line angular range 55 °~65 °, every piece Precast shear wall body component sets at least two diagonal brace;
4), stitch under block wall, the water expandable waterstop of 1.5~1.8 times of slit widths is cemented in exterior wall horizontal joint position in advance, so Envelope dismisses bubble fluid sealant afterwards, then uses sealing compound filleting;Vertical seam is fixed temporarily from the inside of gap using lath, injection foamed glue, Sealing compound filleting is used again, and external application glass fiber reticular cloth cracking resistance strengthens face;
5), the reinforcing bar colligation of shear wall post-cast strip, first lay post-cast strip welded reinforcement ring, then place vertical cage bar, then will under The reserved cage bar of layer wall and this layer of cage bar colligation, horizontal hoop reserve horizontal annular steel bar with cage bar and wall and carry out colligation;
6), shear wall post-cast strip formwork, template uses glued board, fixed with through-wall bolt;
7), determine lower floor's partition wall joint bar position, hoisting prefabricated partition wall component makes lower floor's reserved joint bar enter the prefabricated partition wall of lifting In component;
8), prefabricated partition wall component and adjacent mounted precast shear wall component connection be connected by screw bolts, by it is prefabricated every At least two pre-buried connecting bolts are connected with pre-buried can in precast shear wall component in wall member:
9), the connection of prefabricated partition wall component and adjacent cast-in-situ wall even embedded bar anchor, pass through 2 φ pre-buried in partition wall 6 anchor bars are anchored with cast-in-situ wall;
10), prefabricated partition wall component preheating embedding line connection, prefabricated partition wall component bottom is reserved with pipe joint groove, it is prefabricated every The preheating embedding line of wall member within the walls throws away joint in the groove, the pipeline of prefabricated partition wall component is connected with lower floor pipeline; The reserved pipe joint of prefabricated partition wall component is connected in top superimposed sheet junction with the pipeline laid in Bars In Poured Concrete Slab;
11), prefabricated partition wall component and floor install, prefabricated partition wall component is reserved with floor groove, and floor corresponding position is also pre- Corresponding recesses are left, the floating groove of cement mortar is used after prefabricated partition wall component installation;
12), after prefabricated partition wall component installs, surrounding is blocked with mortar;
13), carry out precast wall body component injected hole grouting and precast shear wall body post-cast strip pour;
14), concrete curing and the demoulding.
9. a kind of installation method of precast wall body component according to claim 8, it is characterised in that the upper and lower ends of diagonal brace Fixed respectively with precast shear wall component and floor using expansion bolt, diagonal brace top passes through pre-buried in precast shear wall component Bolt collar is laid setscrew and fixed, and diagonal brace bottom is squeezed into floor by expansion bolt and fixed.
10. a kind of installation method of precast wall body component according to claim 8, it is characterised in that lower floor's shear wall Joint bar is ladder muscle, depending on the embedded bar hole of ladder muscle cage bar specification and appearance and size according to precast shear wall component.
CN201710601532.4A 2017-07-21 2017-07-21 A kind of making of precast wall body component and installation method Pending CN107297810A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710601532.4A CN107297810A (en) 2017-07-21 2017-07-21 A kind of making of precast wall body component and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710601532.4A CN107297810A (en) 2017-07-21 2017-07-21 A kind of making of precast wall body component and installation method

Publications (1)

Publication Number Publication Date
CN107297810A true CN107297810A (en) 2017-10-27

Family

ID=60134062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710601532.4A Pending CN107297810A (en) 2017-07-21 2017-07-21 A kind of making of precast wall body component and installation method

Country Status (1)

Country Link
CN (1) CN107297810A (en)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108044775A (en) * 2018-01-22 2018-05-18 吴成国 A kind of concrete prefabricated element integrates final-assembly die and construction method
CN108130964A (en) * 2018-01-22 2018-06-08 中交四航局港湾工程设计院有限公司 A kind of construction method of assembled light concrete wall
CN108149819A (en) * 2018-01-31 2018-06-12 山东海龙建筑科技有限公司 Construction bottom strengthens area's integration overlapping exterior wall and its production and construction method
CN108193712A (en) * 2018-01-07 2018-06-22 中铁四局集团建筑工程有限公司 Factory construction device and method for structural components of superimposed assembly pipe gallery
CN108356973A (en) * 2018-04-27 2018-08-03 有利华建筑预制件(深圳)有限公司 Precast facade production line
CN108798703A (en) * 2018-07-03 2018-11-13 上海市城市建设设计研究总院(集团)有限公司 Implement the construction method and its constructing structure in upper heat extraction air duct in compound tube coupling station
CN109203222A (en) * 2018-10-10 2019-01-15 苏州建设(集团)有限责任公司 Building assembly beam slab intelligence production method
CN109505368A (en) * 2018-12-25 2019-03-22 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled architecture
CN109707090A (en) * 2019-03-01 2019-05-03 中建二局第二建筑工程有限公司 A kind of superimposed sheet reinforces pre-buried anti-faulting of slab ends structure and construction method under band plate
CN109822736A (en) * 2019-04-18 2019-05-31 山东省滨州市坤合建筑工程有限公司 A kind of production technology of assembled wallboard
CN109853785A (en) * 2019-01-22 2019-06-07 河南聚誉帆工程技术咨询有限公司 Assembled integral fills partition wall and fabrication and installation method
CN109868903A (en) * 2019-03-11 2019-06-11 沙洲职业工学院 A kind of assembled architecture lower part grout construction method
CN109986687A (en) * 2018-12-29 2019-07-09 龙信集团江苏建筑产业有限公司 The production technology of the prefabricated concrete panel containing rough surface
CN110000892A (en) * 2019-05-22 2019-07-12 浙江元筑住宅产业化有限公司 A kind of production technology of prefabricated component stair
CN110042930A (en) * 2019-04-16 2019-07-23 江苏楷正建设有限公司 The construction method that combined concrete structure is quickly spliced
CN110370449A (en) * 2019-08-02 2019-10-25 宇创环保产业有限公司 A kind of domestic garbage burning electricity generation clinker regenerated aggregate production light wall board system
CN110409771A (en) * 2019-07-23 2019-11-05 天元建设集团有限公司 A kind of prefabricated outer wall panel installation auxiliary device and its application method
CN110614718A (en) * 2019-09-30 2019-12-27 泰安市骏鸣新材料有限公司 Production process of precast concrete shear wall external wall panel
CN110696180A (en) * 2019-10-08 2020-01-17 广东乾兴建设工程有限公司 Concrete prefabricated wallboard and production process thereof
CN110924568A (en) * 2019-10-24 2020-03-27 中天西北建设投资集团有限公司 Method for constructing stair partition wall by adopting precast concrete hollow wall board
CN111677170A (en) * 2020-05-19 2020-09-18 浙江新中源建设有限公司 Laminated floor slab structure and construction method thereof
CN112277154A (en) * 2020-10-28 2021-01-29 广东中建新型建筑构件有限公司 Production method of FRP rib precast beam
CN112809891A (en) * 2021-01-06 2021-05-18 天津丰桥筑工住宅工业有限公司 Construction method of prefabricated wall board and used preformed hole tool
CN113090022A (en) * 2021-03-02 2021-07-09 福建省泷澄建设集团有限公司 Site construction method for assembled shear wall structure wallboard in hot-in-summer and warm-in-winter areas
CN114718217A (en) * 2022-05-10 2022-07-08 新余学院 Structure and construction method of a new type of prefabricated shear wall horizontal joint
CN115179416A (en) * 2022-06-22 2022-10-14 中煤远大淮北建筑产业化有限公司 Production method of decoration integrated prefabricated external wall panel
CN116001080A (en) * 2023-02-20 2023-04-25 连云港先至远大建筑工业有限公司 A production device and method for prefabricated PC components with automatic quality inspection function

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0937834A1 (en) * 1998-02-18 1999-08-25 RPM/Belgium, naamloze vennootschap Expansion joint in concrete constructions
CN103711238A (en) * 2013-12-28 2014-04-09 中国建筑第七工程局有限公司 Assembly-type concrete shear wall structure system buckled and anchored through ring ribs
CN104895193A (en) * 2015-06-26 2015-09-09 长沙远大住宅工业集团有限公司 Precast outer wallboard connecting box and connecting joint
CN106677356A (en) * 2017-03-08 2017-05-17 黄坤坤 Water-proof structures of joint of pre-fabricating outer wall of fabricated building
CN106869330A (en) * 2017-01-18 2017-06-20 黄坤坤 A kind of assembled ring muscle is fastened and is anchored concrete shear force wall bilateral floor connection structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0937834A1 (en) * 1998-02-18 1999-08-25 RPM/Belgium, naamloze vennootschap Expansion joint in concrete constructions
CN103711238A (en) * 2013-12-28 2014-04-09 中国建筑第七工程局有限公司 Assembly-type concrete shear wall structure system buckled and anchored through ring ribs
CN104895193A (en) * 2015-06-26 2015-09-09 长沙远大住宅工业集团有限公司 Precast outer wallboard connecting box and connecting joint
CN106869330A (en) * 2017-01-18 2017-06-20 黄坤坤 A kind of assembled ring muscle is fastened and is anchored concrete shear force wall bilateral floor connection structure
CN106677356A (en) * 2017-03-08 2017-05-17 黄坤坤 Water-proof structures of joint of pre-fabricating outer wall of fabricated building

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张波等: "《装配式混凝土结构工程》", 30 September 2016 *
本书编委会: "《桥涵施工员一本通》", 31 January 2009 *

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193712A (en) * 2018-01-07 2018-06-22 中铁四局集团建筑工程有限公司 Factory construction device and method for structural components of superimposed assembly pipe gallery
CN108044775A (en) * 2018-01-22 2018-05-18 吴成国 A kind of concrete prefabricated element integrates final-assembly die and construction method
CN108130964A (en) * 2018-01-22 2018-06-08 中交四航局港湾工程设计院有限公司 A kind of construction method of assembled light concrete wall
CN108149819A (en) * 2018-01-31 2018-06-12 山东海龙建筑科技有限公司 Construction bottom strengthens area's integration overlapping exterior wall and its production and construction method
CN108149819B (en) * 2018-01-31 2024-01-30 山东海龙建筑科技有限公司 Integrated superposed outer wall of building bottom reinforcing area and production and construction method thereof
CN108356973A (en) * 2018-04-27 2018-08-03 有利华建筑预制件(深圳)有限公司 Precast facade production line
CN108798703A (en) * 2018-07-03 2018-11-13 上海市城市建设设计研究总院(集团)有限公司 Implement the construction method and its constructing structure in upper heat extraction air duct in compound tube coupling station
CN108798703B (en) * 2018-07-03 2023-10-03 上海市城市建设设计研究总院(集团)有限公司 Construction method for implementing upper heat extraction air duct in composite pipe joint station and construction structure thereof
CN109203222A (en) * 2018-10-10 2019-01-15 苏州建设(集团)有限责任公司 Building assembly beam slab intelligence production method
CN109505368B (en) * 2018-12-25 2024-05-14 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled building
CN109505368A (en) * 2018-12-25 2019-03-22 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled architecture
CN109986687A (en) * 2018-12-29 2019-07-09 龙信集团江苏建筑产业有限公司 The production technology of the prefabricated concrete panel containing rough surface
CN109853785A (en) * 2019-01-22 2019-06-07 河南聚誉帆工程技术咨询有限公司 Assembled integral fills partition wall and fabrication and installation method
CN109707090B (en) * 2019-03-01 2024-03-19 中建二局第二建筑工程有限公司 Pre-buried dislocation preventing structure under laminated plate reinforced band plate and construction method
CN109707090A (en) * 2019-03-01 2019-05-03 中建二局第二建筑工程有限公司 A kind of superimposed sheet reinforces pre-buried anti-faulting of slab ends structure and construction method under band plate
CN109868903A (en) * 2019-03-11 2019-06-11 沙洲职业工学院 A kind of assembled architecture lower part grout construction method
CN109868903B (en) * 2019-03-11 2023-08-22 沙洲职业工学院 Lower grouting construction method for assembled building
CN110042930A (en) * 2019-04-16 2019-07-23 江苏楷正建设有限公司 The construction method that combined concrete structure is quickly spliced
CN109822736A (en) * 2019-04-18 2019-05-31 山东省滨州市坤合建筑工程有限公司 A kind of production technology of assembled wallboard
CN110000892A (en) * 2019-05-22 2019-07-12 浙江元筑住宅产业化有限公司 A kind of production technology of prefabricated component stair
CN110409771A (en) * 2019-07-23 2019-11-05 天元建设集团有限公司 A kind of prefabricated outer wall panel installation auxiliary device and its application method
CN110409771B (en) * 2019-07-23 2024-05-03 天元建设集团有限公司 Prefabricated external wall panel installation auxiliary device and application method thereof
CN110370449A (en) * 2019-08-02 2019-10-25 宇创环保产业有限公司 A kind of domestic garbage burning electricity generation clinker regenerated aggregate production light wall board system
CN110614718A (en) * 2019-09-30 2019-12-27 泰安市骏鸣新材料有限公司 Production process of precast concrete shear wall external wall panel
CN110696180A (en) * 2019-10-08 2020-01-17 广东乾兴建设工程有限公司 Concrete prefabricated wallboard and production process thereof
CN110924568A (en) * 2019-10-24 2020-03-27 中天西北建设投资集团有限公司 Method for constructing stair partition wall by adopting precast concrete hollow wall board
CN111677170A (en) * 2020-05-19 2020-09-18 浙江新中源建设有限公司 Laminated floor slab structure and construction method thereof
CN112277154A (en) * 2020-10-28 2021-01-29 广东中建新型建筑构件有限公司 Production method of FRP rib precast beam
CN112809891A (en) * 2021-01-06 2021-05-18 天津丰桥筑工住宅工业有限公司 Construction method of prefabricated wall board and used preformed hole tool
CN113090022A (en) * 2021-03-02 2021-07-09 福建省泷澄建设集团有限公司 Site construction method for assembled shear wall structure wallboard in hot-in-summer and warm-in-winter areas
CN114718217A (en) * 2022-05-10 2022-07-08 新余学院 Structure and construction method of a new type of prefabricated shear wall horizontal joint
CN115179416A (en) * 2022-06-22 2022-10-14 中煤远大淮北建筑产业化有限公司 Production method of decoration integrated prefabricated external wall panel
CN116001080B (en) * 2023-02-20 2023-09-08 连云港先至远大建筑工业有限公司 Prefabricated pc component production device and method with automatic quality inspection function
CN116001080A (en) * 2023-02-20 2023-04-25 连云港先至远大建筑工业有限公司 A production device and method for prefabricated PC components with automatic quality inspection function

Similar Documents

Publication Publication Date Title
CN107297810A (en) A kind of making of precast wall body component and installation method
CN106013811B (en) A kind of installation method of assembled architecture
CN104594387B (en) Improved post-cast strip advance water stop construction method
CN104018598B (en) A kind of exterior wall structure and construction installation method
CN104358341B (en) A kind of building masonry and construction masonry method
CN101956458B (en) Construction method of overlong and superhigh single-side fair-faced concrete wall
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN110552440B (en) Safe and environment-friendly construction process for high-strength assembled integral sandwich heat-insulating shear wall
CN103866885B (en) Construction method of energy-saving heat-insulating structure of lighting window
CN108589986A (en) One kind being based on bolted assembled composite wall structure and its construction method
CN109811878A (en) Integrated structure and construction method of cast-in-place laminated formwork for prefabricated buildings
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN105484391A (en) Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks
CN107268878A (en) The fabrication and installation method of prefabricated sandwich wallboard
CN110872869A (en) Waterproof construction method for joints of external wall panels
CN113202222A (en) Construction method for assembled type superposed beam slab
CN103883022B (en) Construction method of building envelope inner and outer wall anti-seismic, sound insulation and anti-cracking integrated structure
CN105201101A (en) Light aggregate concrete small hollow block building masonry construction method
CN107190889A (en) Steel frame lightweight sandwich board integrated wall and its construction method
CN108005255A (en) A method of building a wall
CN107345439A (en) A kind of making of precast stair component and installation method
CN216787893U (en) Prefabricated shear wall positioner
CN101906858A (en) Multi-line segment art GRC board seamless installation process
CN207176990U (en) A steel frame lightweight sandwich panel integrated wall
CN220469309U (en) Installation structure of prefabricated concrete exhaust pipes in high-rise residential buildings that is easy to replace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination