JP2008123151A - Operation management system and operation management program - Google Patents

Operation management system and operation management program Download PDF

Info

Publication number
JP2008123151A
JP2008123151A JP2006304725A JP2006304725A JP2008123151A JP 2008123151 A JP2008123151 A JP 2008123151A JP 2006304725 A JP2006304725 A JP 2006304725A JP 2006304725 A JP2006304725 A JP 2006304725A JP 2008123151 A JP2008123151 A JP 2008123151A
Authority
JP
Japan
Prior art keywords
work
period
date
scheduled
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2006304725A
Other languages
Japanese (ja)
Other versions
JP4774354B2 (en
Inventor
Koichi Takahashi
康一 高橋
Hiromi Hayashi
広海 林
Masayuki Chatani
雅之 茶谷
Takeshi Baba
健 馬場
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2006304725A priority Critical patent/JP4774354B2/en
Publication of JP2008123151A publication Critical patent/JP2008123151A/en
Application granted granted Critical
Publication of JP4774354B2 publication Critical patent/JP4774354B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To accurately decide a coexisting operation even when occurrence of a delayed operation is not reported even when the number of operations is large. <P>SOLUTION: An operation management program 21 installed in the HD 20 of a computer 10 of an operation management system 1 includes an area overlapping operation extracting function 21a for extracting an operation to be performed in the same area as an operation as the object of decision from an operation information DB22; a period extension function 21b for extending an operation scheduled period by extracting an operation whose operation state is under operation, and whose operation scheduled period terminates prior to a present time from the area overlapping operations; a period overlapping operation extraction function 21c for extracting an operation whose operation scheduled period overlaps with the operation as the object of decision about an operation list processed by the period extension function 21b; and an output function 21d for outputting the overlapping operations extracted by both the area overlapping operation extraction function and the period overlapping operation extraction function as the coexisting operations which overlap with the operation as the object of decision. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、発電所、工場などの保守点検が必要な施設において行われる複数の保守点検等の作業の日程をコンピュータにより管理する作業管理システム、及び、このようなシステムとしてコンピュータを機能させる作業管理プログラムに関する。   The present invention relates to a work management system that uses a computer to manage a plurality of work schedules such as maintenance inspections that are performed in facilities that require maintenance inspection such as power plants and factories, and work management that allows the computer to function as such a system. Regarding the program.

保守点検が必要な施設、例えば火力発電所では、特に法令で定められた定期定検作業時に、多くの点検・保修作業が短期間に集中する。このような場合、複数の作業が同一エリアで同時期に行われると、作業事故が発生する確率が高くなる。例えば、機器の点検作業中に試運転を行い、近接する別作業の作業員に危害を与えたり、フロア天井部分の作業で工具等が落下して床面の作業員に危害を与えたりする可能性がある。   In facilities that require maintenance and inspection, for example, thermal power plants, many inspections and maintenance work are concentrated in a short period of time, especially during regular periodic inspection work stipulated by laws and regulations. In such a case, if a plurality of operations are performed at the same time in the same area, the probability that a work accident will occur increases. For example, there is a possibility that a test run may be performed during equipment inspection work, harming another nearby worker, or a tool or the like may fall due to work on the floor ceiling and harm the floor worker. There is.

このような事故を未然に防止するため、混在作業(作業期間及び作業エリアが重複する作業)を特定し、これらの作業を担当する作業員に対して事前に注意を喚起する必要がある。従来から、火力発電所の作業現場においては,以下のような方法で混在作業をチェックしている。   In order to prevent such an accident in advance, it is necessary to identify mixed work (work with overlapping work periods and work areas) and call attention to workers in charge of these work in advance. Conventionally, mixed work is checked at the work site of a thermal power plant by the following method.

すなわち、作業の計画段階では、各作業の責任者が作業予定に関するミーティングを実施し、混在作業が発生すると判断される場合には,混在作業の作業予定一覧表を作成する。そして、作業の実施段階では、混在作業を担当する作業員に作業前ミーティングなどの場で周知する。また、混在作業の作業予定一覧を現場に掲示したり、掲示板にフロアの平面図を貼り付け、混在作業の位置をマグネットやピンでマークしたりしている。作業中は、各作業員は作業手順などを口頭で連絡し合い、調整を取りながら作業を進める。   That is, at the work planning stage, the person in charge of each work conducts a meeting regarding work schedules, and when it is determined that mixed work occurs, a work schedule list for mixed work is created. Then, in the work execution stage, the worker in charge of the mixed work is informed at a pre-work meeting or the like. In addition, a work schedule list of mixed work is posted on the site, a floor plan is pasted on a bulletin board, and the position of the mixed work is marked with a magnet or a pin. During the work, each worker verbally communicates work procedures, etc., and works while making adjustments.

ただし、上述した従来のチェック方法には、以下のような問題がある。
(1) 人手による判断に基づいているため、チェックミスが発生し易い。火力発電所では、作業が集中する場合は1日に数百件の作業が実施されるため、資料の目視確認により混在作業を正確に抽出することは困難である。
(2) いずれかの作業が遅延して予定期間内に終了しなかった場合には、計画段階で行った混在作業の判定をやり直す必要があるが、特に作業数が多い場合には時間的、コスト的な問題からやり直しができない可能性が高い。
(3) 作業遅延の報告が遅れると、翌日の作業に影響及ぼす恐れがある。混在作業無しと判定されていた作業が、その作業開始日の前日に作業終了予定であった作業の作業遅延により混在作業有りの状態となる可能性があるが、作業遅延の報告が遅れると、混在作業無しの認識で作業に着手することになる。
However, the conventional check method described above has the following problems.
(1) Check mistakes are likely to occur because it is based on manual judgment. In a thermal power plant, when work is concentrated, hundreds of work is performed per day, so it is difficult to accurately extract mixed work by visual confirmation of materials.
(2) If any work is delayed and does not end within the scheduled period, it is necessary to redo the mixed work judgment performed at the planning stage. There is a high possibility that it will not be possible to redo due to cost problems.
(3) Delay in reporting work delays may affect the next day's work. Work that has been determined to have no mixed work may be in a mixed work state due to work delays for work that was scheduled to end on the day before the work start date, but if work delay reporting is delayed, Work starts with recognition without mixed work.

人手によるチェックには上記のような問題があるため、コンピュータを利用した日程管理方法も従来から提案されている。例えば、特許文献1には、保守作業の予定作業日程を工程データベースに記録しておき、これを必要に応じて端末から呼び出して表示できるようにした工程管理システムが開示されている。   Since manual checks have the above-mentioned problems, a schedule management method using a computer has been proposed. For example, Patent Document 1 discloses a process management system in which a scheduled work schedule of maintenance work is recorded in a process database and can be called up and displayed from a terminal as necessary.

特開2003−233409号公報JP 2003-233409 A

しかしながら、特許文献1に開示されるシステムでは、いずれかの作業が遅延した場合には、管理者が端末を操作して日程を修正する必要があるが(段落0054参照)、一般に作業が遅延している場合には、実際の作業の進行が優先され、端末への入力は後回しにされる可能性が高く、修正が遅れて上記(3)と同様の問題を生じる可能性がある。   However, in the system disclosed in Patent Document 1, if any work is delayed, the administrator needs to correct the schedule by operating the terminal (see paragraph 0054), but generally the work is delayed. In such a case, the progress of the actual work is given priority, and there is a high possibility that the input to the terminal will be postponed.

本発明は、上記の従来技術の問題点に鑑みてなされたものであり、その課題は、作業数が多い場合においても、かつ、遅延作業の発生が報告されなかった場合においても、正確に混在作業の判定ができる作業管理システム及び作業管理プログラムを提供することにある。   The present invention has been made in view of the above-described problems of the prior art, and the problem is that even when the number of operations is large and the occurrence of delayed operations is not reported, it is accurately mixed. An object of the present invention is to provide a work management system and a work management program capable of judging work.

本発明にかかる作業管理システムは、コンピュータに登録された作業情報に基づいて複数の作業予定が施設内の同一エリアで同一期間に重複するか否かを管理するシステムにおいて、作業毎に登録される作業エリアと作業予定期間と作業状態とを格納する作業情報格納手段と、作業情報格納手段から判定対象となる作業と同一エリアで行われる作業を抽出するエリア重複作業抽出手段と、作業情報格納手段から作業状態が作業中であり、作業予定期間の終端が現在以前である作業を抽出して作業予定期間を所定期間延長する期間延長手段と、期間延長手段により処理された作業リストについて、判定対象となる作業と作業予定期間が重複する作業を抽出する期間重複作業抽出手段と、エリア重複作業抽出手段及び期間重複作業抽出手段の両手段により重複して抽出された作業を判定対象となる作業と重複する混在作業として出力する出力手段と、を備えることを特徴とする。   The work management system according to the present invention is registered for each work in a system that manages whether or not a plurality of work schedules overlap in the same area in a facility based on work information registered in a computer. Work information storage means for storing a work area, scheduled work period, and work state, area overlapping work extraction means for extracting work performed in the same area as the work to be determined from the work information storage means, and work information storage means From the period extension means to extract the work whose work status is working and the scheduled work period ends before the present time and extend the scheduled work period by a predetermined period, and the work list processed by the period extension means Both hands of a period overlapping work extracting means for extracting a work whose scheduled work period overlaps with the work to be, and an area overlapping work extracting means and a period overlapping work extracting means Characterized in that it comprises an output means for outputting the work extracted in duplicate as a mixed operation of overlapping the work to be determined, the a.

上記の期間延長手段は、エリア重複作業抽出手段により抽出された作業を対象に処理を行うことが望ましい。また、作業予定期間は、登録時に入力される開始予定日、終了予定日と、期間延長手段により設定される終了判定日とのフィールドを有し、期間延長手段は、作業状態が作業中であり、終了予定日が現在日付以前である作業の終了判定日に所定期間延長した日付を設定し、それ以外の作業の終了判定日に終了予定日を設定し、期間重複作業抽出手段は、開始予定日と終了判定日とにより規定される作業期間に基づいて重複の有無を判定することが望ましい。   It is desirable that the above-mentioned period extension means performs processing for the work extracted by the area duplication work extraction means. Further, the scheduled work period has fields of a scheduled start date and a scheduled end date input at the time of registration, and an end determination date set by the period extension means. , Set the date extended for a predetermined period on the end date of work whose scheduled end date is before the current date, set the scheduled end date on the end date of work other than that, and the period duplicate work extraction means will start It is desirable to determine the presence or absence of duplication based on the work period defined by the date and the end determination date.

一方、本発明にかかる作業管理プログラムは、登録された作業情報に基づいて複数の作業予定が施設内の同一エリアで同一期間に重複するか否かを管理する作業管理装置としてコンピュータを機能させるプログラムにおいて、コンピュータに、作業毎に登録される作業エリアと作業予定期間と作業状態とを格納する作業情報データベースから判定対象となる作業と同一エリアで行われる作業を抽出するエリア重複作業抽出機能と、エリア重複作業抽出機能により抽出された作業から作業状態が作業中であり、作業予定期間の終端が現在以前である作業を抽出して作業予定期間を所定期間延長する期間延長機能と、期間延長機能により処理された作業リストについて、判定対象となる作業と作業予定期間が重複する作業を抽出する期間重複作業抽出機能と、エリア重複作業抽出機能及び期間重複作業抽出機能の両機能により重複して抽出された作業を判定対象となる作業と重複する混在作業として出力する出力機能と、を実現させることを特徴とする。   On the other hand, the work management program according to the present invention is a program that causes a computer to function as a work management apparatus that manages whether or not a plurality of work schedules overlap in the same area in a facility based on registered work information. In the computer, an area duplication work extraction function for extracting work to be performed in the same area as the work to be determined from the work information database storing the work area registered for each work, the work scheduled period, and the work state; The period extension function that extracts the work whose work status is being worked from the work extracted by the area overlapped work extraction function, and the scheduled work period ends before the present time, and extends the scheduled work period by a predetermined period, and the period extension function For the work list processed by, the period overlap work that extracts the work that is to be judged and the work scheduled period is duplicated The output function and the output function that outputs the work extracted redundantly by both the area overlapping work extraction function and the period overlapping work extraction function as a mixed work that overlaps with the work to be judged are realized. And

なお、作業情報データベースは、作業予定期間として、登録時に入力される開始予定日、終了予定日と、期間延長機能により設定される終了判定日とのフィールドを有し、期間延長機能は、作業状態が作業中であり、終了予定日が現在日付以前である作業の終了判定日に所定期間延長した日付を設定し、それ以外の作業の終了判定日に終了予定日を設定し、期間重複作業抽出機能は、開始予定日と終了判定日とにより規定される作業期間に基づいて重複の有無を判定することが望ましい。   In addition, the work information database has fields of a scheduled start date and a scheduled end date input at the time of registration and an end determination date set by the period extension function as the scheduled work period. Set a date that is extended for a predetermined period on the work end judgment date for which the scheduled end date is before the current date, and set the scheduled end date on the other work end judgment date to extract duplicate work. It is desirable for the function to determine the presence or absence of duplication based on the work period defined by the scheduled start date and the end determination date.

以上のように構成された本発明の作業管理システム/プログラムによれば、コンピュータを利用したチェックにより、作業数が膨大な場合でも、混在作業を迅速かつ正確に判定することができ、かつ、システム側で自動的に遅延作業の発生を認定し、これに基づいて混在作業のチェックを再実行できるため、遅延作業の発生が報告、入力されなくとも、正確に混在作業を認定することができる。したがって、作業員に対して適切に混在作業に関する注意を喚起することができ、作業の安全に資することができる。   According to the work management system / program of the present invention configured as described above, even when the number of work is enormous, it is possible to quickly and accurately determine mixed work by a check using a computer, and the system Therefore, the mixed work can be accurately recognized even if the occurrence of the delayed work is not reported or entered. Therefore, it is possible to appropriately alert the worker about the mixed work and contribute to work safety.

以下、本発明にかかる作業管理プログラム及びこれを適用した作業管理システムの実施形態を図面に基づいて説明する。最初に、図1に基づいて本実施形態の作業管理プログラムが適用される作業管理システムの概要を説明する。この作業管理システム1は、単独のコンピュータ10と、周辺機器とから構成されている。コンピュータ10は、CPU11、並びにこのCPU11に接続されたハードディスク(HD)20、メモリ(RAM)12及びインターフェイス13を備えている。   Embodiments of a work management program according to the present invention and a work management system to which the work management program is applied will be described below with reference to the drawings. First, an outline of a work management system to which the work management program of the present embodiment is applied will be described with reference to FIG. The work management system 1 includes a single computer 10 and peripheral devices. The computer 10 includes a CPU 11, a hard disk (HD) 20, a memory (RAM) 12, and an interface 13 connected to the CPU 11.

なお、コンピュータ10のCPU11には、周辺機器としてディスプレイ30、プリンタ31、キーボード32がインターフェイス13を介して接続されている。   Note that a display 30, a printer 31, and a keyboard 32 are connected to the CPU 11 of the computer 10 via the interface 13 as peripheral devices.

HD20には、図示せぬオペレーティングシステムの他、作業管理プログラム21がインストールされると共に、作業情報データベース(DB)22が構築されている。CPU11は、起動するとHD20からオペレーティングシステムをRAM13上に読み出して実行し、このオペレーティングシステム上で作業管理プログラム21を実行する。   In addition to an operating system (not shown), a work management program 21 is installed in the HD 20 and a work information database (DB) 22 is constructed. When activated, the CPU 11 reads the operating system from the HD 20 onto the RAM 13 and executes it, and executes the work management program 21 on the operating system.

なお、図1には、作業管理システムが単独のコンピュータにより構成される例を示したが、このコンピュータをサーバとしてネットワークを介して複数の端末を接続し、各端末から入力、閲覧ができるようにしてもよい。   FIG. 1 shows an example in which the work management system is configured by a single computer, but a plurality of terminals are connected via a network using this computer as a server so that input and browsing can be performed from each terminal. May be.

HD20にインストールされた作業管理プログラム21は、作業情報DB22に登録された作業情報に基づいて複数の作業予定が施設内の同一エリアで同一期間に重複するか否かを管理する作業管理装置としてコンピュータ10を機能させる。このプログラム21は、作業毎に登録される作業エリアと作業予定期間と作業状態とを格納する作業情報DB22から判定対象となる作業と同一エリアで行われる作業を抽出するエリア重複作業抽出機能21aと、エリア重複作業抽出機能21aにより抽出された作業から作業状態が作業中であり、作業予定期間の終端が現在以前である作業を抽出して作業予定期間を所定期間延長する期間延長機能21bと、期間延長機能21bにより処理された作業リストについて、判定対象となる作業と作業予定期間が重複する作業を抽出する期間重複作業抽出機能21cと、エリア重複作業抽出機能及び期間重複作業抽出機能の両機能により重複して抽出された作業を判定対象となる作業と重複する混在作業として出力する出力機能21dとをモジュールとして含んでいる。   The work management program 21 installed in the HD 20 is a computer as a work management apparatus that manages whether or not a plurality of work schedules overlap in the same area within the facility in the same period based on the work information registered in the work information DB 22. Make 10 work. This program 21 includes an area overlapping work extraction function 21a for extracting work performed in the same area as the work to be determined from the work information DB 22 storing the work area registered for each work, the work scheduled period, and the work state. A period extension function 21b for extracting a work whose work state is being worked from the work extracted by the area duplication work extraction function 21a and whose work end is before the present time and extending the work scheduled period by a predetermined period; For the work list processed by the period extension function 21b, both a period overlapping work extraction function 21c that extracts a work whose judgment target period overlaps with a work to be determined, an area overlapping work extraction function, and a period overlapping work extraction function An output function 21d that outputs the work extracted in duplicate as a mixed work overlapping with the work to be determined. It contains as Le.

また、HD20に構築された作業情報DB22は、各作業の作業状態及び作業予定期間を定義する作業日程テーブル22aと、各作業が施設内のいずれのエリアで行われるかを定義する作業エリアテーブル22bとを備えている。   The work information DB 22 constructed in the HD 20 includes a work schedule table 22a that defines the work status and work schedule period of each work, and a work area table 22b that defines in which area each work is performed. And has.

作業日程テーブル22aは、以下の表1にサンプルデータを示すように、各作業を識別するためにシステムで自動付番される一意の番号である作業コードと、作業の進行状態を示す作業状態と、作業の件名を示す作業件名との各フィールドと、作業予定期間として、登録時に人手で入力される開始予定日、終了予定日と、期間延長機能21bにより設定される終了判定日とのフィールドを有する。なお、作業状態には、作業情報を新規に登録した直後に設定される「計画中」、計画中の作業で、作業開始日より作業着手することが承認された場合に設定される「承認済」、承認済の作業で、作業開始日が到来した場合に設定される「作業中」、作業中の作業に対し、人手により作業完了登録処理が行われた場合に設定される「作業完了」の4種類がある。また、作業開始日、終了予定日は、当該作業の作業期間の始期と終期の予定日であり、終了判定日は、通常は終了予定日と同じ日付となるが、遅延が生じた場合には、期間延長手段21bにより延長された期日が入力される。作業日程テーブルでは、1つの作業は1行のレコードとして表される。   The work schedule table 22a, as shown in the sample data in Table 1 below, includes a work code that is a unique number automatically assigned by the system to identify each work, and a work state that indicates the progress of work. , Each field of a work subject indicating a work subject, and a field of a scheduled start date and a scheduled end date that are manually input at the time of registration and an end determination date set by the period extension function 21b as a scheduled work period Have. The work status is set to “under planning”, which is set immediately after new work information is registered, and “approved”, which is set when work is started from the start date of work under planning. "Approved work" is set when the work start date has arrived, "work in progress", "work complete" set when the work completion registration process is performed manually for the work in progress There are four types. In addition, the work start date and the scheduled end date are the start and end scheduled dates of the work period, and the end judgment date is usually the same date as the scheduled end date, but if a delay occurs The date extended by the period extension means 21b is input. In the work schedule table, one work is represented as one line record.

一方、作業エリアテーブル22bは、以下の表2にサンプルデータを示すように、表1と同じ作業コードの他、建家、フロア、選択エリアの3つのフィールドを持つ。すなわち、この例では、対象としている火力発電所に、複数の建家があり、1つの建家には複数のフロアがあることを前提としている。そして、各フロアを、格子状に縦15×横20で合計300エリアに区画している。「建家」は当該作業を行う建家、「フロア」は建家内のフロア、「選択エリア」はフロア内の選択された区画を表すデータであり、300ビットの2進数で表現されている(表2では上位35ビットのみ示されている)。この2進数は、1ビット目〜300ビット目がエリア1〜エリア300に対応しており、各ビットの値は、そのエリアが作業エリアとして選択された場合には「1」、選択されない場合には「0」となる。   On the other hand, as shown in Table 2 below, the work area table 22b has three fields of a building, a floor, and a selection area in addition to the same work code as in Table 1. In other words, in this example, it is assumed that the target thermal power plant has a plurality of buildings, and one building has a plurality of floors. Each floor is partitioned into a total of 300 areas of 15 × 20 in a grid pattern. `` Building '' is the building that performs the work, `` Floor '' is the floor in the building, `` Selection area '' is the data representing the selected section in the floor, and is represented by a 300-bit binary number ( Table 2 shows only the upper 35 bits). In this binary number, the 1st to 300th bits correspond to areas 1 to 300, and the value of each bit is “1” when the area is selected as a work area, and when the area is not selected. Becomes “0”.

コンピュータ画面から作業エリアを選択登録する際には,建家及びフロアをプルダウンメニュー等で表示される選択肢の中から選択し、フロア内のエリアは、フロア平面図を300個の升目で格子状に区切った画面を表示し、作業エリアに対応する升目を1つずつマウスクリック等により選択する。   When selecting and registering the work area from the computer screen, the building and floor are selected from the options displayed in the pull-down menu, etc., and the area within the floor is arranged in a grid with 300 squares of the floor plan view. Display the divided screen and select the cells corresponding to the work area one by one with a mouse click.

作業エリアテーブルでは、1件の作業の1フロア分の作業エリア情報を1行分のデータとして表現している。表2の例では、作業コード00002の作業は2つのフロア(ボイラー建家の1Fと2F)に跨って作業が行われるため2行のレコードがあり、それ以外の作業は1つのフロア内での作業であるため1行ずつであることが示されている。   In the work area table, work area information for one floor of one work is expressed as one line of data. In the example in Table 2, there is a two-line record because the work with work code 00002 is carried out across two floors (both 1F and 2F of the boiler building), and other work is within one floor. Since it is a work, it is shown that it is one line at a time.

作業管理プログラム21は、上記の作業情報DBに登録された情報に基づいて、混在作業の有無を計算により求める。判定方法は、判定対象となる1つの作業(自作業)と、他の複数の作業(他作業1〜他作業n)とを比較し、以下の条件1〜3を全て満たす他作業を混在作業と判定する。
[条件1] 比較先となる他作業は作業完了状態ではない。
[条件2] 自作業と他作業とで作業エリアが重複する。
[条件3] 自作業と他作業とで作業期間(作業開始日〜終了判定日)が重複する。
The work management program 21 calculates the presence / absence of mixed work based on information registered in the work information DB. Judgment method compares one work (self work) to be judged with a plurality of other work (other work 1 to other work n), and mixes other work that satisfies all of the following conditions 1 to 3 Is determined.
[Condition 1] The other work as the comparison destination is not in a work completion state.
[Condition 2] The work area overlaps between own work and other work.
[Condition 3] The work period (work start date to end determination date) overlaps between the own work and the other work.

次に、上記の作業管理システム1において実行される作業管理処理の内容を、図2及び図3に示すフローチャートに基づいて説明する。以下の説明では、現在日付を2006/01/13と仮定する。まず、判定に先立って作業情報DBに作業日程情報、作業エリア情報を登録する(S001)。そして、判定対象となる1つの作業(自作業)を作業日程テーブル22aから選択する(S002)。例えば、以下の表3に示すように作業Cを自作業として選択する。   Next, the contents of the work management process executed in the work management system 1 will be described based on the flowcharts shown in FIGS. In the following description, it is assumed that the current date is 2006/01/13. First, prior to determination, work schedule information and work area information are registered in the work information DB (S001). Then, one work (self work) to be determined is selected from the work schedule table 22a (S002). For example, as shown in Table 3 below, the operation C is selected as the own operation.

続いて、表1に示した作業日程テーブル22aに規定される作業から、自作業と作業状態が「作業完了」となっている完了作業とを除外し(S003)、比較対象となる他作業のリスト(第1作業リスト)を生成する。この例では、作業Aが完了作業、作業Cが自作業であるため、これらを除いた第1作業リストは以下の表4に示す通りとなる。   Subsequently, from the work specified in the work schedule table 22a shown in Table 1, the self work and the completed work whose work status is “work completed” are excluded (S003), and other work to be compared is compared. A list (first work list) is generated. In this example, work A is a completed work and work C is a self-work, so the first work list excluding these is as shown in Table 4 below.

次に、第1作業リストに基づいて、このリストに含まれる他作業から、自作業と作業エリアが重複する作業を抽出し(S004)、第2作業リストを生成する。ここでは、図3に示すように、自作業のエリア情報を作業エリアテーブル22bから読み出し(S101)、第1作業リストに含まれる他作業のエリア情報を作業エリアテーブル22bから読み出す(S102)。表5は、自作業のエリア情報、表6は、他作業のエリア情報である。   Next, based on the first work list, a work whose work area and work area overlap is extracted from other work included in this list (S004), and a second work list is generated. Here, as shown in FIG. 3, the area information of the own work is read from the work area table 22b (S101), and the area information of other work included in the first work list is read from the work area table 22b (S102). Table 5 shows area information for own work, and Table 6 shows area information for other work.

そして、表6に含まれる作業を1行ずつ選択し(S103)、選択された他作業の建屋が自作業と同じか否か(S104)、フロアが同じか否か(S105)を判断する。建家とフロアの一方が異なればS109に進み、両者が同じ場合には、自作業と他作業の選択エリアの値の対応するビット毎の論理積を計算する(S106)。この計算により求められた300ビットの論理積の値が0か否かを判断し(S107)、0であれば作業エリアの重複はないものと判断してS109に進み、0でなければ作業エリアの重複があるものと判断して当該作業を第2作業リストに追加し(S108)、S109に進む。S109では、選択されている行が最終行か否かを判断し、行が残っていれば、S103に戻って次の行を選択して上記の判定を繰り返し、最終行であれば図2のフローに戻る。このような処理により、エリアが重複する作業を、表7に示すように第2作業リストとして抽出することができる。   Then, the work included in Table 6 is selected line by line (S103), and it is determined whether the selected building of the other work is the same as the own work (S104) and whether the floor is the same (S105). If one of the building and the floor is different, the process proceeds to S109, and if both are the same, the logical product for each bit corresponding to the value of the selection area of the own work and the other work is calculated (S106). It is determined whether or not the value of the 300-bit logical product obtained by this calculation is 0 (S107). If it is 0, it is determined that there are no overlapping work areas, and the process proceeds to S109. Therefore, the task is added to the second task list (S108), and the process proceeds to S109. In S109, it is determined whether or not the selected line is the last line. If there is a remaining line, the process returns to S103 to select the next line and repeat the above determination. Return to. As a result of such processing, work with overlapping areas can be extracted as the second work list as shown in Table 7.

次に、第2作業リストとして抽出された他作業から、作業期間が自作業と重複するものを抽出して第3作業リストを生成する(S005-S012)。ここでは、まず、第2作業リストの作業コードに基づいて作業日程テーブル22aから該当する他作業の作業状態及び作業期間(作業開始日、終了予定日)を抽出する(S005)。抽出結果は以下の表8の通りとなる。   Next, from the other tasks extracted as the second task list, a task whose work period overlaps with the own task is extracted to generate a third task list (S005-S012). Here, first, based on the work code of the second work list, the work status and work period (work start date, scheduled end date) of the corresponding other work are extracted from the work schedule table 22a (S005). The extraction results are as shown in Table 8 below.

上記の抽出結果から、1行ずつ選択し(S006)、選択された作業が遅延作業であるか否かを判断する(S007, S008)。すなわち、ここでは、作業状態が「作業中」であり(S007, Yes)、かつ、終了予定日が現在日付より古い(S008, Yes)他作業を遅延作業と判断する。そして、遅延作業と判断した他作業の行には、終了判定日のフィールドに終了予定日に1年加算した日付を設定し(S009)、遅延作業でないと判断した他作業の行には、終了判定日のフィールドに終了予定日の日付をそのまま設定する(S010)。設定の結果は表9に示す通りとなる。すなわち、現在日付が2006/01/13であると仮定しているため、作業BはS007, S008の判断が共にYesとなる条件を満たしており、終了判定日には終了予定日に1年を追加した日付2007/01/11が設定される。作業Eは遅延作業には該当しないため終了判定日には終了予定日と同じ2006/01/20が設定される。   One line is selected from the above extraction result (S006), and it is determined whether the selected work is a delayed work (S007, S008). In other words, here, it is determined that other work is “delayed work” in which the work state is “working” (S007, Yes) and the scheduled end date is older than the current date (S008, Yes). Then, in the line of other work judged to be delayed work, a date obtained by adding one year to the scheduled end date is set in the field of end judgment date (S009), and to the line of other work judged not to be delayed work The date of the scheduled end date is set as it is in the judgment date field (S010). The setting results are as shown in Table 9. That is, since it is assumed that the current date is 2006/01/13, work B satisfies the condition that both the judgments of S007 and S008 are Yes, and the end judgment date is one year on the scheduled end date. Added date 2007/01/11 is set. Since the work E does not correspond to the delayed work, 2006/01/20 which is the same as the scheduled end date is set as the end determination date.

図示は省略するが、自作業についても、同様の判断をして終了判定日を設定する。この結果、自作業Cについては表10に示すように終了判定日に終了予定日が設定される。   Although illustration is omitted, the end determination date is set by making the same determination for the own work. As a result, for the self-work C, the scheduled end date is set on the end determination date as shown in Table 10.

続いて、作業開始日から終了判定日に至る期間を作業期間と捉え、自作業の作業期間と他作業の作業期間とが重複するか否かを判断し(S011)、重複する他作業を混在作業として第3作業リストに追加する(S012)。S011の期間重複の判断においては、自作業と他作業の作業期間の関係は表11に示す6パターンに分類できる。各パターンについての作業期間の関係性は、表12に示される。   Next, the period from the work start date to the end determination date is regarded as the work period, and it is determined whether the work period of the own work and the work period of other work overlap (S011), and the overlapping other work is mixed. The work is added to the third work list (S012). In the determination of overlapping periods in S011, the relationship between the work period of the own work and the other work can be classified into six patterns shown in Table 11. Table 12 shows the relationship between the work periods for each pattern.

上記の6パターンの中で期間重複の関係となるのは,パターン2,3,4,6の4種類のみである。この4種類のいずれかに該当するかは次の2つの条件式で判定できる。S011における期間重複の判定は、以下の2つの条件を満たすか否かにより行われる。
自作業の作業開始日 ≦ 他作業の終了判定日 かつ,
他作業の作業開始日 ≦ 自作業の終了判定日
Of the above six patterns, there are only four types of patterns 2, 3, 4, and 6 that have a period overlap relationship. Whether one of the four types is applicable can be determined by the following two conditional expressions. The determination of period overlap in S011 is made based on whether or not the following two conditions are satisfied.
Work start date for own work ≦ Date for judging end of other work and
Work start date of other work ≤ Date of end of own work

そして、上記のS006〜S012の処理を、最終行 (S013, Yes) となるまで、すなわち、第2作業リストに含まれる他作業全てついて行うことにより第3作業リストを生成し、これをディスプレイ30に表示し、あるいは、プリンタ31からプリントアウトする(S014)。第3作業リストの内容は、以下の表13に示す通りとなる。   Then, the third work list is generated by performing the processes of S006 to S012 until the last line (S013, Yes), that is, all other work included in the second work list, and this is displayed on the display 30. Or printed out from the printer 31 (S014). The contents of the third work list are as shown in Table 13 below.

以上の作業管理処理により、この例では、現在日付2006/01/13において自作業Cに対して混在作業となるのは、作業Bであることが確定する。   Through the above-described work management processing, in this example, it is determined that work B is the mixed work for the self work C on the current date 2006/01/13.

上記のように、遅延作業を作業状態と終了予定日と現在日付とに基づいてシステム側で自動的に判断することにより、遅延が発生した場合にも人手によりコンピュータに作業の終了予定日を変更登録する必要がなく、混在作業の判定を確実に行うことができる。   As described above, the system automatically determines the delayed work based on the work status, the scheduled end date, and the current date, so that even if a delay occurs, the scheduled end date for the task is manually changed on the computer. There is no need to register, and it is possible to reliably determine mixed work.

以下、本発明のように遅延作業の自動設定を行う場合と、行わない場合とで具体的にどのような相違が生じるか説明する(以下の説明では作業エリアが重複することを前提とする)。遅延作業を考慮せず,作業期間を作業の計画段階に設定された作業開始日〜終了予定日として考えた場合,表14に示すように作業状態が作業中である作業B,C間には作業期間の重複はないため、作業Cを自作業として判断すると、混在作業は無しという判定結果となる。   Hereinafter, a specific difference between the case where delay work is automatically set and the case where it is not performed as in the present invention will be described (in the following description, it is assumed that work areas overlap) . If the work period is considered as the work start date to the scheduled end date set in the work planning stage without considering the delayed work, as shown in Table 14, between work B and C whose work status is in work Since there is no overlap of work periods, if work C is determined as a self-work, the result of determination is that there is no mixed work.

これに対し、本発明のシステムでは、2006/01/13の時点で作業Bに遅延が生じていると判断されて終了予定日を1年延長した終了判定日を基準に期間重複を判定するため、表15に示すように作業状態が作業中である作業B,C間には作業期間の重複があると判断され、自作業Cに対して作業Bが混在作業となるとの判定結果となる。   On the other hand, in the system of the present invention, it is determined that the work B is delayed as of January 13, 2006, and the period overlap is determined on the basis of the end determination date obtained by extending the scheduled end date by one year. As shown in Table 15, it is determined that there is an overlap of work periods between the work B and C whose work state is being worked, and the determination result is that the work B is a mixed work with respect to the self work C.

一方、作業Bを自作業として混在作業の判定を行うと、作業Bと作業エリアが重複する作業のうち,作業開始日〜終了予定日が期間重複する作業に加え、今後1年間に渡り作業開始が予定される作業も混在作業として判定されるため、遅延作業側から他作業に対して注意喚起を伝達することができる。また、今後作業開始が予定されている作業を自作業として混在作業の判定を行った場合にも、遅延作業が混在作業として判定されるため、作業の計画段階から混在作業の危険性を検知することができ、安全性を向上させることができる。   On the other hand, when the work B is determined as a self-work, the mixed work is determined, and among the work in which work B and work area overlap, the work starts over the next year in addition to the work whose work start date to scheduled end date overlap. Since the work scheduled to be performed is also determined as a mixed work, it is possible to transmit an alert to other work from the delayed work side. In addition, even if a work that is scheduled to start in the future is determined as a mixed work and the delayed work is determined as a mixed work, the risk of mixed work is detected from the work planning stage. Can improve safety.

本発明の実施形態にかかる作業管理システムを示すブロック図である。It is a block diagram which shows the work management system concerning embodiment of this invention. 図1に示す作業関しシステムの作用を示すフローチャートである。It is a flowchart which shows the effect | action of the work system shown in FIG. 図2に示すフローチャートのうち、S004の処理を詳細に示すフローチャートである。It is a flowchart which shows the process of S004 in detail among the flowcharts shown in FIG.

符号の説明Explanation of symbols

1 作業管理システム
10 コンピュータ
11 CPU
12 ram
13 通信アダプタ
20 HD
21 作業管理プログラム
21a エリア重複作業抽出機能
21b 期間延長機能
21c 期間重複作業抽出機能
21d 出力機能
22 作業情報DB
22a 作業日程テーブル
22b 作業エリアテーブル
1 Work Management System 10 Computer 11 CPU
12 ram
13 Communication adapter 20 HD
21 Work management program 21a Area overlap work extraction function 21b Period extension function 21c Period overlap work extraction function 21d Output function 22 Work information DB
22a Work schedule table 22b Work area table

Claims (5)

コンピュータに登録された作業情報に基づいて複数の作業予定が施設内の同一エリアで同一期間に重複するか否かを管理する作業管理システムにおいて、
作業毎に登録される作業エリアと作業予定期間と作業状態とを格納する作業情報格納手段と、
前記作業情報格納手段から判定対象となる作業と同一エリアで行われる作業を抽出するエリア重複作業抽出手段と、
前記作業情報格納手段から作業状態が作業中であり、作業予定期間の終端が現在以前である作業を抽出して作業予定期間を所定期間延長する期間延長手段と、
前記期間延長手段により処理された作業リストについて、前記判定対象となる作業と作業予定期間が重複する作業を抽出する期間重複作業抽出手段と、
前記エリア重複作業抽出手段及び前記期間重複作業抽出手段の両手段により重複して抽出された作業を前記判定対象となる作業と重複する混在作業として出力する出力手段と、
を備えることを特徴とする作業管理システム。
In a work management system for managing whether or not a plurality of work schedules overlap in the same area in a facility based on work information registered in a computer,
A work information storage means for storing a work area, a work schedule period, and a work state registered for each work;
Area overlapping work extraction means for extracting work performed in the same area as the work to be determined from the work information storage means;
A period extension means for extracting a work whose work state is being worked from the work information storage means and whose work schedule period ends before the present time and extending the work schedule period by a predetermined period;
For the work list processed by the period extension means, a period overlapping work extraction means for extracting work that overlaps the work to be determined and the work scheduled period;
Output means for outputting the work extracted redundantly by both means of the area overlapping work extracting means and the period overlapping work extracting means as a mixed work overlapping with the work to be determined;
A work management system comprising:
前記期間延長手段は、前記エリア重複作業抽出手段により抽出された作業を対象に処理を行うことを特徴とする請求項1に記載の作業管理システム。   The work management system according to claim 1, wherein the period extension unit performs processing on the work extracted by the area duplication work extraction unit. 前記作業予定期間は、登録時に入力される開始予定日、終了予定日と、前記期間延長手段により設定される終了判定日とのフィールドを有し、前記期間延長手段は、作業状態が作業中であり、終了予定日が現在日付以前である作業の終了判定日に所定期間延長した日付を設定し、それ以外の作業の終了判定日に前記終了予定日を設定し、前記期間重複作業抽出手段は、開始予定日と終了判定日とにより規定される作業期間に基づいて重複の有無を判定することを特徴とする請求項1又は2に記載の作業管理システム。   The scheduled work period has fields of a scheduled start date and a scheduled end date that are input at the time of registration, and an end determination date set by the period extension means. Yes, set a date extended for a predetermined period on the end determination date of the work whose scheduled end date is before the current date, set the expected end date on the end determination date of the other work, The work management system according to claim 1, wherein presence / absence of duplication is determined based on a work period defined by a scheduled start date and an end determination date. 登録された作業情報に基づいて複数の作業予定が施設内の同一エリアで同一期間に重複するか否かを管理する作業管理装置としてコンピュータを機能させる作業管理プログラムにおいて、
コンピュータに、
作業毎に登録される作業エリアと作業予定期間と作業状態とを格納する作業情報データベースから判定対象となる作業と同一エリアで行われる作業を抽出するエリア重複作業抽出機能と、
前記エリア重複作業抽出機能により抽出された作業から作業状態が作業中であり、作業予定期間の終端が現在以前である作業を抽出して作業予定期間を所定期間延長する期間延長機能と、
前記期間延長機能により処理された作業リストについて、前記判定対象となる作業と作業予定期間が重複する作業を抽出する期間重複作業抽出機能と、
前記エリア重複作業抽出機能及び前記期間重複作業抽出機能の両機能により重複して抽出された作業を前記判定対象となる作業と重複する混在作業として出力する出力機能と、
を実現させることを特徴とする作業管理プログラム。
In a work management program that causes a computer to function as a work management device that manages whether a plurality of work schedules overlap in the same area within a facility based on registered work information,
On the computer,
An area duplicate work extraction function that extracts work performed in the same area as the work to be judged from the work information database that stores the work area, work schedule period, and work status registered for each work;
A period extension function for extracting a work whose work state is being worked from the work extracted by the area duplication work extraction function and whose work schedule period ends before the present time and extending the work schedule period by a predetermined period;
For the work list processed by the period extension function, a period overlapping work extraction function that extracts work that is scheduled to overlap with the work to be determined,
An output function for outputting the work extracted redundantly by both the area overlapping work extracting function and the period overlapping work extracting function as a mixed work overlapping the work to be determined;
The work management program characterized by realizing.
前記作業情報データベースは、作業予定期間として、登録時に入力される開始予定日、終了予定日と、前記期間延長機能により設定される終了判定日とのフィールドを有し、前記期間延長機能は、作業状態が作業中であり、終了予定日が現在日付以前である作業の終了判定日に所定期間延長した日付を設定し、それ以外の作業の終了判定日に前記終了予定日を設定し、前記期間重複作業抽出機能は、開始予定日と終了判定日とにより規定される作業期間に基づいて重複の有無を判定することを特徴とする請求項4に記載の作業管理プログラム。   The work information database includes fields of a scheduled start date and a scheduled end date that are input at the time of registration, and an end determination date set by the period extension function, as the scheduled work period. Set a date that is extended for a predetermined period on the work end determination date that is in the work status and the scheduled end date is before the current date, set the scheduled end date on the other work end determination date, and set the period 5. The work management program according to claim 4, wherein the duplicate work extraction function determines whether or not there is duplication based on a work period defined by a scheduled start date and an end determination date.
JP2006304725A 2006-11-10 2006-11-10 Work management system and work management program Expired - Fee Related JP4774354B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006304725A JP4774354B2 (en) 2006-11-10 2006-11-10 Work management system and work management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006304725A JP4774354B2 (en) 2006-11-10 2006-11-10 Work management system and work management program

Publications (2)

Publication Number Publication Date
JP2008123151A true JP2008123151A (en) 2008-05-29
JP4774354B2 JP4774354B2 (en) 2011-09-14

Family

ID=39507858

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006304725A Expired - Fee Related JP4774354B2 (en) 2006-11-10 2006-11-10 Work management system and work management program

Country Status (1)

Country Link
JP (1) JP4774354B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002251509A (en) * 2001-02-23 2002-09-06 Ns Solutions Corp Device and method for preparing plan, recording medium, and program
JP2005031824A (en) * 2003-07-09 2005-02-03 Hitachi Ltd Road occupying construction information management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002251509A (en) * 2001-02-23 2002-09-06 Ns Solutions Corp Device and method for preparing plan, recording medium, and program
JP2005031824A (en) * 2003-07-09 2005-02-03 Hitachi Ltd Road occupying construction information management system

Also Published As

Publication number Publication date
JP4774354B2 (en) 2011-09-14

Similar Documents

Publication Publication Date Title
US8682707B2 (en) Simulation-based risk analysis for finite capacity scheduling
JP4736733B2 (en) Production management apparatus, production management system, production management method, control program, and recording medium
US20030036939A1 (en) Method and system configure to manage a maintenance process
Zhang Quality improvement through Poka–Yoke: from engineering design to information system design
CN102024181A (en) Artificial intelligence maintenance system and method
KR102391207B1 (en) 3D modeling based worker location management system
JPH09259181A (en) Work flow managing system
Williams Benefits of IVHM: an analytical approach
JP5453354B2 (en) Production management system, production management method, control program, and readable storage medium
JP2009157690A (en) Manufacturing process management apparatus, manufacturing process management method, program and recording medium for the same
JP4774354B2 (en) Work management system and work management program
JP2012256143A (en) Maintenance management system, work priority calculation method and program
CN104021499A (en) Semiconductor manufacture control method
JP2009187330A (en) Improvement guide system of job quality
Kang et al. Discrete event simulation to reduce the effect of uncertainties on project planning
WO2013078099A1 (en) Model plant construction systems and processes
JP2005228025A (en) Maintenance management system for building
US20220383233A1 (en) Work support system, work support method, and work support program
CN116050774A (en) Maintenance data processing method and system for industrial Internet equipment
JP5492031B2 (en) Work management system
JP2019032642A (en) Plant construction plan support system, construction plan support method and construction plan support program
JP4324522B2 (en) Program for causing computer to execute processing for supporting manufacturing plan of product, manufacturing plan supporting system, and manufacturing plan supporting method
JP6771505B2 (en) A device for detecting abnormalities in the maintenance status of septic tanks
JP3403822B2 (en) production management system
JP2005267183A (en) Production scheduling apparatus

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20081117

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101220

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110111

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110309

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110607

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110627

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140701

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4774354

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees