JP2019032642A - Plant construction plan support system, construction plan support method and construction plan support program - Google Patents

Plant construction plan support system, construction plan support method and construction plan support program Download PDF

Info

Publication number
JP2019032642A
JP2019032642A JP2017152352A JP2017152352A JP2019032642A JP 2019032642 A JP2019032642 A JP 2019032642A JP 2017152352 A JP2017152352 A JP 2017152352A JP 2017152352 A JP2017152352 A JP 2017152352A JP 2019032642 A JP2019032642 A JP 2019032642A
Authority
JP
Japan
Prior art keywords
information
plant
construction plan
policy
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017152352A
Other languages
Japanese (ja)
Other versions
JP6862309B2 (en
Inventor
亮介 末田
Ryosuke Sueda
亮介 末田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Energy Systems and Solutions Corp
Original Assignee
Toshiba Corp
Toshiba Energy Systems and Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Energy Systems and Solutions Corp filed Critical Toshiba Corp
Priority to JP2017152352A priority Critical patent/JP6862309B2/en
Publication of JP2019032642A publication Critical patent/JP2019032642A/en
Application granted granted Critical
Publication of JP6862309B2 publication Critical patent/JP6862309B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To provide a technology for reducing a burden on a user required for examining a plant construction plan.SOLUTION: A plant construction plan support system 20 includes a first contradiction determination unit 23a for referring to provisional construction plan information 31 and determined construction plan information 32 and determining whether or not operation states of devices at an isolation execution time are in contradiction between an additional working process and a fixed working process, a second contradiction determination unit 23b for determining whether or not the operation states of the devices at a system operation time are in contradiction, and a measure existence/non-existence determination unit 24 for referring to know-how information 33 when the second contradiction determination unit determines that the operation states of the devices are in contradiction and determining whether there exists an actual measure performed in a section to which the device determined to be in contradiction by the second contradiction determination unit belongs, thereby outputting the measure determined to exist to an output unit 22.SELECTED DRAWING: Figure 1

Description

本発明は、プラントの工事計画支援システム、工事計画支援方法および工事計画支援プログラムに関する。   The present invention relates to a plant construction plan support system, a construction plan support method, and a construction plan support program.

例えば、発電、化学、食品、製鉄、環境などのプラントでは、定期的に実施される定期点検の他、不定期に工事の必要性が生じ得る。プラントにおける工事の実施に際しては、産業保安上の観点から法令が定められており、当該法令を考慮した作業計画を立案する必要がある。   For example, in plants such as power generation, chemistry, food, iron making, and environment, there may be occasions where work is required irregularly in addition to periodic inspections that are regularly performed. When implementing construction at the plant, laws and regulations are established from the viewpoint of industrial security, and it is necessary to formulate work plans that take into account those laws and regulations.

例えば、発電プラントの場合、電気事業法第42条において、保安規程の策定および遵守が義務付けられているため、当該保安規定で定められる安全管理要領を考慮した作業計画を立案する必要がある。   For example, in the case of a power plant, it is required to formulate and comply with the safety regulations in Article 42 of the Electricity Business Law, so it is necessary to formulate a work plan that takes into account the safety management guidelines stipulated in the safety regulations.

プラントの定期点検等の作業計画の立案を支援するシステムとして、例えば、原子力発電プラントにおける定期点検の工程を適切に管理する観点から、点検工程間の干渉などが生じないよう点検工程を追加または変更することを支援する工程管理システムが提案されている。   As a system that supports the planning of work plans such as periodic plant inspections, for example, from the viewpoint of appropriately managing the periodic inspection process at nuclear power plants, the inspection process is added or changed so that interference between inspection processes does not occur A process management system that supports this is proposed.

特開2010−122053号公報JP 2010-122053 A

発電プラントにおける工事計画においては、プラント系統運用工程と既に計画が確定している工事計画の成立性とを確認した上で新たな工事計画の実施時期を検討する。当該検討の中では、保安規定を逸脱しないようにプラント系統の制約条件についても考慮する。   In the construction plan in the power plant, the execution timing of the new construction plan is examined after confirming the plant system operation process and the feasibility of the construction plan that has already been confirmed. In this study, the constraints of the plant system are also taken into consideration so as not to deviate from the safety regulations.

例えば、特許文献1に記載される工程管理システムなどの従来のプラントの工事計画支援システムでは、同一時期に重複して作業対象となる機器があるか否かを判断し、重複して点検対象となる機器の有無をもって、固定の点検工程と追加の点検工程との干渉の有無を判定する。   For example, in a conventional plant construction planning support system such as the process management system described in Patent Document 1, it is determined whether there are devices that are to be worked on at the same time, and the inspection target is duplicated. Whether there is any interference between the fixed inspection process and the additional inspection process is determined based on the presence or absence of the device.

また、点検対象となる機器ごとに当該機器の点検時期、系統隔離(アイソレーション)時期、単体試験時期および試運転時期を判定して得られる結果と、各プラント系統を運用する上で必要となる機器の情報とから、各プラント系統の運転可能時期、アイソレーション時期、単体試験時期および試運転時期を判定する。さらに、各プラント系統の運転可能時期、アイソレーション時期、単体試験時期および試運転時期について、保安規定に適合するか否かを判定する。   In addition, for each device to be inspected, the results obtained by determining the inspection time, system isolation (isolation) time, unit test time, and test operation time of the device, and the equipment required for operating each plant system From the above information, the operation possible time, isolation time, unit test time and test operation time of each plant system are determined. Further, it is determined whether or not each plant system can be operated, isolation time, unit test time, and test operation time comply with the safety regulations.

しかしながら、特許文献1などの従来のプラントの工事計画支援システムでは、既に予定が確定している(固定の)点検工程と追加の点検工程との干渉の有無を判定することはできるものの、干渉が有ると判定した場合にシステム上で干渉を回避する案を検討し提案することはできない。従って、システムが干渉有りと判定した場合にはユーザが工事計画を再検討し、新たな点検工程を作成し、再度干渉の有無を判定する必要が生じるという課題がある。   However, in a conventional plant construction planning support system such as Patent Document 1, it is possible to determine whether or not there is interference between a fixed (fixed) inspection process and an additional inspection process, but there is interference. If it is determined that there is, it is not possible to study and propose a plan to avoid interference on the system. Therefore, when the system determines that there is interference, there is a problem that the user needs to review the construction plan, create a new inspection process, and determine again whether there is interference.

また、工事計画を立案する際には、系統運用に関わる重要設備が損傷して系統運用に支障が出る事態を確実に回避することが重要である。系統運用に関わる重要設備の損傷を確実に回避するためには、アイソレーション時期や保安規定の他、現場の作業環境などについても考慮して立案する必要があるが、特許文献1などの従来のプラントの工事計画支援システムでは、現場の作業環境などについては考慮されていない。   Also, when planning a construction plan, it is important to reliably avoid a situation in which important equipment related to system operation is damaged and troubles system operation. In order to surely avoid damage to important equipment related to system operation, it is necessary to plan in consideration of the work environment in the field as well as the time of isolation and safety regulations. In the plant construction plan support system, the work environment at the site is not taken into consideration.

従って、アイソレーション時期や保安規定上の問題は生じていないものの、現場の作業環境などによっては系統運用に関わる重要設備が損傷し得る工程が含まれている状態で工事計画が承認されて、途中まで工事が進行している場合もある。この場合、重要設備の損傷を回避するための突発的な工程の見直し(いわゆる後戻り作業)が必要となり、ユーザのみならず工事現場作業員にかかる負担は少なくない。   Therefore, although there are no problems with the time of isolation or safety regulations, the construction plan is approved in the state where important facilities related to grid operation are damaged depending on the work environment at the site. In some cases, construction is underway. In this case, it is necessary to suddenly review the process (so-called reverse operation) in order to avoid damage to important equipment, and the burden on not only the user but also the construction site worker is not small.

本発明は、上述した事情に鑑みてなされたものであり、プラントの工事計画の検討に要するユーザの負担を軽減するプラントの工事計画支援システム、工事計画支援方法および工事計画支援プログラムを提供することを目的とする。   The present invention has been made in view of the above-described circumstances, and provides a plant construction plan support system, a construction plan support method, and a construction plan support program that reduce the burden on the user required for studying the plant construction plan. With the goal.

本発明の実施形態に係るプラントの工事計画支援システムは、上述した課題を解決するため、1以上の系統を備えるプラントの未確定の工事計画における、工事日時の情報と前記プラントを構成する機器の識別情報とアイソレーション(系統隔離)実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む仮工事計画情報と、前記プラントの確定している工事計画における、工事日時の情報と前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む確定工事計画情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第1の矛盾判定部と、前記仮工事計画情報と、前記系統の運用計画に沿う作業工程における日時および作業内容と、前記プラントを構成する機器のうち、前記作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む前記系統の運用工程情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第2の矛盾判定部と、前記第2の矛盾判定部が前記機器の動作状態が矛盾すると判定した場合、前記系統の機能を喪失する最小単位で区分けした場合の区分を示す区分情報と、過去に実施した工事において前記区分の内部で実際に行った方策の情報と、前記機器の識別情報とが関連付けられているノウハウ情報を参照し、前記第2の矛盾判定部が前記機器の動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策の有無を判定する方策有無判定部とを具備し、前記方策有無判定部は、動作状態が矛盾すると判定された前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策を、出力部に出力するように構成されることを特徴とする。   In order to solve the above-described problems, a plant construction plan support system according to an embodiment of the present invention provides information on construction date and time of an unconfirmed construction plan for a plant including one or more systems and the devices constituting the plant. Temporary construction plan information including identification information and isolation state information indicating an operation state of the equipment at the time of isolation (system isolation), construction date and time information in the construction plan determined by the plant, and the plant To determine whether or not the operation state of the device is inconsistent with reference to the confirmed construction plan information including the identification information of the device constituting the device and the isolation state information indicating the operation state of the device at the time of isolation. A first contradiction determination unit, the temporary work plan information, the date and time of the work process in accordance with the operation plan of the system, and the work content; Whether the operation state of the device is inconsistent with reference to the operation process information of the system including information indicating the operation state of each device that is necessary for performing the work process The second contradiction determination unit for determining whether or not the second contradiction determination unit determines that the operation state of the device is inconsistent, and indicates a classification when the system is divided by the minimum unit that loses the function of the system The second contradiction determining unit refers to the know-how information in which the information, the information of the policy actually performed in the section in the construction performed in the past, and the identification information of the device are associated with each other. A policy presence / absence determination unit for determining the presence / absence of a policy actually performed in a category to which the device determined to have a contradictory operation state belongs, and the policy presence / absence determination unit determines that the operation state is inconsistent Belongs to If it is determined that the minute actually went strategy there, a certain and the determined measures, characterized in that it is configured to output to the output unit.

本発明の実施形態に係るプラントの工事計画支援方法は、上述した課題を解決するため、多段階に条件を判定する判定手段として機能させるコンピュータを用いて1以上の系統を備えるプラントの未確定の工事計画の妥当性を判定することによって前記プラントの工事計画を支援する方法であって、前記判定手段が、前記プラントの未確定の工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む仮工事計画情報と、前記プラントの確定している工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む確定工事計画情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第1の矛盾判定ステップと、前記判定手段が、前記仮工事計画情報と、前記系統の運用計画に沿う作業工程における日時および作業内容と、前記プラントを構成する機器のうち、前記作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む前記系統の運用計画情報とを参照し、前記機器の動作状態が矛盾する第2の矛盾判定ステップと、前記判定手段が、前記第2の矛盾判定ステップで前記機器の動作状態が矛盾すると判定した場合、前記系統の機能を喪失する最小単位で区分けした場合の区分を示す区分情報と、過去に実施した工事において前記区分の内部で実際に行った方策の情報と、前記機器の識別情報とが関連付けられているノウハウ情報を参照し、前記機器の動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策の有無を判定する方策有無判定ステップと、前記判定手段が、前記方策有無判定ステップで動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策を出力部に出力するステップとを備えることを特徴とする。   In order to solve the above-described problem, a plant construction plan support method according to an embodiment of the present invention uses a computer that functions as a determination unit that determines conditions in multiple stages, and has not yet confirmed a plant including one or more systems. A method of supporting the construction plan of the plant by judging the validity of the construction plan, wherein the judging means is isolated from the identification information of the equipment constituting the plant in the unconfirmed construction plan of the plant. Temporary work plan information including the isolation state information indicating the operation state of the equipment at the time of execution, and the identification information of the equipment constituting the plant and the above-mentioned at the time of isolation in the work plan determined by the plant With reference to the finalized construction plan information including the isolation state information indicating the operation state of the device. A first contradiction determination step for determining whether or not there is a contradiction, and the determination means constitutes the plant, the temporary work plan information, the date and work contents in the work process along the operation plan of the system, and the plant A second contradiction determination step in which the operation state of the device is inconsistent with reference to the operation plan information of the system including information indicating the operation state of each device required for performing the work process among the devices. And when the determination unit determines that the operation state of the device is inconsistent in the second contradiction determination step, classification information indicating a classification when the unit is classified by a minimum unit that loses the function of the system, and in the past It is determined that the operation status of the device is inconsistent with reference to know-how information in which the information of the policy actually performed in the section in the construction performed is associated with the identification information of the device. The policy presence / absence determination step for determining the presence / absence of the policy actually performed in the category to which the device belongs and the determination means actually performed in the category to which the device determined that the operation state is inconsistent in the policy presence / absence determination step belong. And a step of outputting the policy determined to be present to the output unit when it is determined that the policy is present.

本発明の実施形態に係るプラントの工事計画支援プログラムは、上述した課題を解決するため、コンピュータを多段階に条件を判定する判定手段として機能させ、1以上の系統を備えるプラントの未確定の工事計画の妥当性を判定することによって前記プラントの工事計画を支援するプログラムであって、前記判定手段が、前記プラントの未確定の工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む仮工事計画情報と、前記プラントの確定している工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む確定工事計画情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第1の矛盾判定ステップと、前記判定手段が、前記仮工事計画情報と、前記系統の運用計画に沿う作業工程における日時および作業内容と、前記プラントを構成する機器のうち、前記作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む前記系統の運用計画情報とを参照し、前記機器の動作状態が矛盾する第2の矛盾判定ステップと、前記判定手段が、前記第2の矛盾判定ステップで前記機器の動作状態が矛盾すると判定した場合、前記系統の機能を喪失する最小単位で区分けした場合の区分を示す区分情報と、過去に実施した工事において前記区分の内部で実際に行った方策の情報と、前記機器の識別情報とが関連付けられているノウハウ情報を参照し、前記機器の動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策の有無を判定する方策有無判定ステップと、前記判定手段が、前記方策有無判定ステップで動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策を出力部に出力するステップとを備える手順を実行させることを特徴とする。   In order to solve the above-described problems, a plant construction plan support program according to an embodiment of the present invention causes a computer to function as a determination unit that determines conditions in multiple stages, and an unconfirmed construction of a plant including one or more systems. A program for supporting the construction plan of the plant by judging the validity of the plan, wherein the judging means executes the identification information of the equipment constituting the plant and the isolation in the unconfirmed construction plan of the plant. Temporary construction plan information including isolation state information indicating an operation state of the equipment at the time, identification information of equipment constituting the plant and the equipment at the time of isolation in the construction plan determined by the plant And the confirmed construction plan information including the isolation state information indicating the operation state of the A first contradiction determination step for determining whether or not the operation state is inconsistent; and the determination means includes the temporary work plan information, the date and work contents in the work process along the operation plan of the system, and the plant. A second contradiction in which the operation state of the device is inconsistent with reference to the operation plan information of the system including information indicating an operation state of each device necessary for performing the work process among the devices to be configured. When the determination step and the determination means determine that the operation state of the device is inconsistent in the second contradiction determination step, the division information indicating the division when the division is performed in the smallest unit that loses the function of the system, Refers to know-how information associated with the policy information actually implemented in the section in the past construction and the identification information of the device, and the operation state of the device is inconsistent The policy presence / absence determination step for determining the presence / absence of the policy actually performed in the category to which the determined device belongs, and the determination means actually in the category to which the device determined that the operation state is inconsistent in the policy presence / absence determination step. When it is determined that there is a policy that has been performed, a procedure including a step of outputting the policy determined to be present to the output unit is executed.

本発明の実施形態によれば、プラントの工事計画の検討に要するユーザの負担を軽減することができる。   According to the embodiment of the present invention, it is possible to reduce the burden on the user required for studying the plant construction plan.

実施形態に係るプラントの工事計画支援システムの基本構成を概略的に示した概略図。The schematic diagram showing roughly the basic composition of the construction plan support system of the plant concerning an embodiment. 仮工事計画情報および確定工事計画情報の内容を示す説明図。Explanatory drawing which shows the content of temporary construction plan information and fixed construction plan information. ノウハウ情報の一例を示した説明図。Explanatory drawing which showed an example of know-how information. ノウハウ情報に含まれる区分および機器の境界を例示する説明図。Explanatory drawing which illustrates the division | segmentation contained in know-how information, and the boundary of an apparatus. 運用工程情報の内容を示す説明図であり、(A)がプラントを適切に運用する上で必要とされる工程および期間の例を示す説明図、(B)が(A)に示される工程Aに必要となる機器毎の動作状態を示す説明図。It is explanatory drawing which shows the content of operation process information, (A) is explanatory drawing which shows the example of the process and period which are required when operating a plant appropriately, (B) is process A shown by (A) Explanatory drawing which shows the operation state for every apparatus required for the. 保安規定情報の一例を説明する説明図。Explanatory drawing explaining an example of security regulation information. 作業エリア情報の一例を示す説明図であり、(A)が大きさの範囲が1パターンの場合を示す説明図、(B)が大きさの範囲が2パターンの場合を示す説明図。It is explanatory drawing which shows an example of work area information, (A) is explanatory drawing which shows the case where a size range is 1 pattern, (B) is explanatory drawing which shows the case where a size range is 2 patterns. 作業エリアの位置情報の定義例を示す説明図であり、(A)が平面(縦方向および横方向)についての定義例を示す説明図、(B)が高さ方向(Z軸方向)の定義例を示す説明図である。It is explanatory drawing which shows the definition example of the positional information on a work area, (A) is explanatory drawing which shows the example of a definition about a plane (vertical direction and horizontal direction), (B) is the definition of a height direction (Z-axis direction). It is explanatory drawing which shows an example. 重要設備情報の一例を示す説明図であり、(A)は重要であるか否かで重要度を設定する場合を示す説明図、(B)は重要である場合を複数段階に分けて重要度を設定する場合を示す説明図。It is explanatory drawing which shows an example of important equipment information, (A) is explanatory drawing which shows the case where importance is set by whether it is important, (B) is divided into several steps when importance is important. Explanatory drawing which shows the case where is set. 実施形態に係るプラントの工事計画支援方法の第1の例(第1の工事計画支援処理手順)について、処理の流れを示す流れ図(フローチャート)。The flowchart (flowchart) which shows the flow of a process about the 1st example (1st construction plan assistance processing procedure) of the construction plan assistance method of the plant which concerns on embodiment. アイソレーション実行時の機器#1について、作業工程実施時における動作状態を時系列(t〜t)で表した説明図。For devices # 1 at the time of isolation run, explanatory view showing an operation state during the working process carried out in time series (t 1 ~t 7). 実施形態に係るプラントの工事計画支援方法における、第1の判定の動作状態の一致および不一致を説明する説明図であり、(A)および(B)は、それぞれ、動作状態が一致する場合および不一致の場合を説明する説明図。It is explanatory drawing explaining the agreement and mismatch of the operation state of the 1st determination in the construction plan support method of the plant which concerns on embodiment, (A) and (B) are the case where an operation state corresponds, respectively, and mismatch Explanatory drawing explaining the case of. 実施形態に係るプラントの工事計画支援方法の第2の例(第2の工事計画支援処理手順)について、処理の流れを示す流れ図(フローチャート)。The flowchart (flowchart) which shows the flow of a process about the 2nd example (2nd construction plan support processing procedure) of the construction plan support method of the plant which concerns on embodiment. 実施形態に係るプラントの工事計画支援方法の第3の例(第3の工事計画支援処理手順)について、処理の流れを示す流れ図(フローチャート)。The flowchart (flowchart) which shows the flow of a process about the 3rd example (3rd construction plan support processing procedure) of the construction plan support method of the plant which concerns on embodiment.

以下、本発明の実施形態に係るプラントの工事計画支援システム、工事計画支援方法および工事計画支援プログラムを添付の図面に基づいて説明する。   Hereinafter, a plant construction plan support system, a construction plan support method, and a construction plan support program according to embodiments of the present invention will be described with reference to the accompanying drawings.

図1は、本発明の実施形態に係るプラントの工事計画支援システムの一例であるプラント工事計画支援システム20の基本構成を概略的に示した概略図である。   FIG. 1 is a schematic diagram schematically showing a basic configuration of a plant construction plan support system 20 which is an example of a plant construction plan support system according to an embodiment of the present invention.

プラント工事計画支援システム20は、複数の条件を段階的に判定することによって、工事計画の見直しの要否を判定するシステムであり、より具体的には、未確定の工事計画などの追加の作業工程が固定の作業工程と干渉した場合に、過去に実施した工事計画により蓄積したノウハウを活用し、保安規定を逸脱しない範囲でプラントの運用を継続できるか否か、すなわち当該プラントのプラント系統における制約条件を回避できるか否かをさらに検討した上で、工事計画の見直しの要否を判定する。   The plant construction plan support system 20 is a system for judging the necessity of reviewing a construction plan by judging a plurality of conditions in stages, and more specifically, additional work such as an unconfirmed construction plan. If the process interferes with a fixed work process, whether or not the plant operation can be continued within the scope that does not deviate from the safety regulations by utilizing the know-how accumulated in the past construction plan, that is, in the plant system of the plant After further studying whether or not the constraint conditions can be avoided, it is determined whether the construction plan needs to be reviewed.

固定の作業工程とは、既に予定が確定している作業工程である。固定の作業工程としては、例えば、予定が確定している工事の作業工程や予定が確定しているプラントの運用計画に沿う作業工程などがある。   A fixed work process is a work process whose schedule has already been determined. Examples of the fixed work process include a work process for a construction for which a schedule has been established and a work process in accordance with a plant operation plan for which a schedule has been established.

プラント工事計画支援システム20は、例えば、追加の作業工程における機器の動作状態が、予定が確定している工事計画(以下、「確定工事計画」とする。)の作業工程における機器の動作状態と矛盾しているか否かを判定する第1の判定を行う機能と、予定が確定しているプラントの運用計画に沿う作業工程における機器の動作状態と矛盾しているか否かを判定する第2の判定を行う機能と、予定が確定しているプラントの運用計画に沿う作業工程における機器の動作状態と矛盾している場合に蓄積したノウハウの有無を判定する第3の判定を行う機能と、第1、第2および第3の判定の判定結果を出力する機能とを有する。   For example, the plant construction plan support system 20 may be configured such that the operation state of the equipment in the additional work process is the operation state of the equipment in the work process of the construction plan whose schedule is fixed (hereinafter referred to as “confirmed construction plan”). A function for performing the first determination for determining whether or not there is a contradiction, and a second for determining whether or not there is a conflict with the operation state of the device in the work process according to the operation plan of the plant for which the schedule is fixed. A function for performing the determination, a function for performing a third determination for determining the presence or absence of accumulated know-how when there is a contradiction with the operation state of the equipment in the work process according to the operation plan of the plant whose schedule is fixed, And a function of outputting the determination results of the first, second and third determinations.

プラント工事計画支援システム20は、蓄積したノウハウが有る場合に、このノウハウを活用してプラント系統の制約条件を回避できるか否か、より具体的にはプラントの保安規定を順守できるか否かを判定する第4の判定を行う機能と、第4の判定の判定結果を出力する機能とを有していてもよい。   When there is accumulated know-how, the plant construction plan support system 20 uses this know-how to determine whether or not the constraint conditions of the plant system can be avoided, more specifically, whether or not the plant safety regulations can be observed. You may have the function to perform the 4th determination to determine, and the function to output the determination result of a 4th determination.

プラント工事計画支援システム20は、プラントの運用計画に沿う作業工程で使用される機器が使用されるエリアと追加の作業工程で使用される機器が使用されるエリアとがそれぞれの使用期間内で干渉するか否かを判定する第5の判定を行う機能と、第5の判定の判定結果を出力する機能とを有していてもよい。また、第5の判定を行う際には、プラントの運用計画に沿う作業工程で使用される機器に対して設定される重要度の情報を考慮するようにし、第5の判定を行う対象を重要度が高い機器に限定したり、重要度の高低に応じたさらなる干渉判定、すなわち第5の判定とはエリアの大きさが異なるなどの異なる基準に基づく干渉判定(第6の判定)をしたりしてもよい。   In the plant construction plan support system 20, an area where equipment used in a work process according to a plant operation plan is used interferes with an area where equipment used in an additional work process is used within each use period. It may have a function of performing a fifth determination for determining whether or not to perform, and a function of outputting a determination result of the fifth determination. In addition, when the fifth determination is made, the importance information set for the equipment used in the work process according to the operation plan of the plant is taken into consideration, and the target for the fifth determination is important. Limited to high-level equipment, or further interference determination according to the level of importance, that is, interference determination (sixth determination) based on different criteria such as the area size is different from the fifth determination May be.

上述した機能を有するプラント工事計画支援システム20は、例えば、CPU(Central Processing Unit)などのプロセッサ並びにROM(Read-Only Memory)およびRAM(Random-Access Memory)などの記憶回路を有する記憶装置を備えるハードウェア資源としてのコンピュータと、コンピュータに上述した機能を実現するソフトウェアである工事計画支援プログラム(以下、プログラムを「PG」と省略し、「工事計画支援PG」とする。)とが協働することによって実現される。   The plant construction plan support system 20 having the functions described above includes, for example, a storage device having a processor such as a CPU (Central Processing Unit) and storage circuits such as a ROM (Read-Only Memory) and a RAM (Random-Access Memory). A computer as a hardware resource and a construction plan support program (hereinafter, the program is abbreviated as “PG” and referred to as “construction plan support PG”), which is software that realizes the above-described functions in the computer, cooperate. Is realized.

工事計画支援PGは、換言すれば、追加の作業工程が固定の作業工程と干渉した場合に、過去に実施した工事計画により蓄積したノウハウを活用してプラント系統における制約条件を回避できるか否かをさらに検討した上で、工事計画の見直しの要否を判定して工事計画を支援する処理手順(以下、「工事計画支援処理手順」とする。)をコンピュータに実行させるプログラムである。工事計画支援PGを実行することによりコンピュータ内に工事計画支援処理手順を実行する具体的手段を具備したプラント工事計画支援システム20が実現される。   In other words, whether the construction plan support PG can avoid the constraints in the plant system by utilizing the know-how accumulated in the past construction plan when the additional work process interferes with the fixed work process. Is a program that causes a computer to execute a processing procedure (hereinafter referred to as a “construction plan support processing procedure”) for determining whether or not a review of the construction plan is necessary and supporting the construction plan. By executing the construction plan support PG, the plant construction plan support system 20 having specific means for executing the construction plan support processing procedure in the computer is realized.

より具体的な構成例を説明すれば、プラント工事計画支援システム20は、例えば、入力部21と、出力部22と、判定手段としての機器状態矛盾判定部23(23a,23b)、方策有無判定部24、方策適用可否判定部25および作業エリア干渉判定部26と、記憶部28と、制御部29とを具備する。   To describe a more specific configuration example, the plant construction plan support system 20 includes, for example, an input unit 21, an output unit 22, a device state contradiction determination unit 23 (23 a, 23 b) as a determination unit, and a policy presence / absence determination. Unit 24, policy applicability determination unit 25, work area interference determination unit 26, storage unit 28, and control unit 29.

ここで、仮工事計画情報31、確定工事計画情報32などの記憶部28の内部に示される各種の情報31〜38は、工事計画支援処理手順を実行する際に、必要に応じて読み出し(リード)または書き込み(ライト)される情報である。   Here, various kinds of information 31 to 38 shown in the storage unit 28 such as the temporary work plan information 31 and the finalized work plan information 32 are read out as necessary when executing the work plan support processing procedure (read). ) Or information to be written (written).

入力部21は、例えば、コンピュータとインターフェイスを介して接続される入力装置またはコンピュータ自身が備えるキーボードやマウス等の入力手段によって実現される。入力部21は、情報の入力を受け付け、受け付けた情報を制御部29に与える。入力部21から入力される情報には、例えば、各種処理の実行要求、仮工事計画などの情報の入力、各種条件の設定要求などがある。   The input unit 21 is realized by, for example, an input device connected to a computer via an interface or input means such as a keyboard or a mouse provided in the computer itself. The input unit 21 receives input of information and gives the received information to the control unit 29. The information input from the input unit 21 includes, for example, various processing execution requests, input of information such as temporary work plans, and various condition setting requests.

出力部22は、例えば、コンピュータとインターフェイスを介して接続される表示装置またはコンピュータ自身が備えるディスプレイなどの表示手段、コンピュータとインターフェイスを介して接続されるプリンタ等の印字手段などによって実現され、表示機能や印字機能などの出力機能を有する。   The output unit 22 is realized by, for example, a display device connected to a computer via an interface or a display means such as a display provided in the computer itself, a printing means such as a printer connected to the computer via an interface, and the like. And output functions such as printing functions.

表示機能を有する出力部22は、表示要求を受け取ると、当該表示要求に応じた内容を表示する。また、印字機能を有する出力部22では、印字要求を受け取ると、当該印字要求に応じた内容を印字出力する。   When receiving the display request, the output unit 22 having a display function displays the content corresponding to the display request. When the output unit 22 having a print function receives a print request, the output unit 22 prints out the content corresponding to the print request.

機器動作状態矛盾判定部23は、第1の機器動作状態矛盾判定部23aと第2の機器動作状態矛盾判定部23bとを備える。   The appliance operating state contradiction determining unit 23 includes a first appliance operating state contradiction determining unit 23a and a second appliance operating state contradiction determining unit 23b.

第1の機器動作状態矛盾判定部23aは、例えば、仮工事計画情報31と確定工事計画情報32とを参照し、追加された仮(未確定)の工事計画におけるアイソレーション実行時の機器の動作状態と既に確定した工事計画におけるアイソレーション実行時の機器の動作状態とが矛盾するか一致する(否)かを判定する。   The first equipment operation state contradiction determination unit 23a refers to, for example, the temporary work plan information 31 and the finalized construction plan information 32, and the operation of the equipment when performing isolation in the added temporary (unconfirmed) construction plan. It is determined whether the state and the operation state of the device at the time of isolation in the construction plan that has already been confirmed are inconsistent or coincident (no).

第1の機器動作状態矛盾判定部23aが行う機器の動作状態が矛盾するか否かの判定(第1の矛盾判定)は、上述した第1の判定に相当する。第1の機器動作状態矛盾判定部23aは、判定結果を、出力部22に出力したり、記憶部28に判定結果情報38として保存したりする。   The determination (first contradiction determination) on whether or not the operation state of the device is contradictory performed by the first device operation state contradiction determination unit 23a corresponds to the first determination described above. The first device operation state contradiction determining unit 23 a outputs the determination result to the output unit 22 or stores it as determination result information 38 in the storage unit 28.

第2の機器動作状態矛盾判定部23bは、例えば、仮工事計画情報31と運用工程情報34とを参照し、未確定の工事計画における機器の動作状態と既に確定した運用計画に沿う作業工程における機器の動作状態とが矛盾するか一致する(否)かを判定する。   The second equipment operation state contradiction determination unit 23b refers to, for example, the temporary work plan information 31 and the operation process information 34, and in the work process according to the operation state of the equipment in the unconfirmed construction plan and the operation plan that has already been confirmed. It is determined whether the operation state of the device is inconsistent or coincides (not).

第2の機器動作状態矛盾判定部23bが行う機器の動作状態が矛盾するか否かの判定(第2の矛盾判定)は、上述した第2の判定に相当する。第2の機器動作状態矛盾判定部23bは、判定結果を、出力部22に出力したり、記憶部28に判定結果情報38として保存したりする。   The determination (second contradiction determination) as to whether or not the device operation state is contradictory performed by the second device operation state contradiction determination unit 23b corresponds to the above-described second determination. The second device operating state contradiction determining unit 23 b outputs the determination result to the output unit 22 or stores it as determination result information 38 in the storage unit 28.

方策有無判定部24は、機器の動作状態の矛盾があったとしても、何らかの方策を採ることによって保安規定を順守しつつ(逸脱することなく)確定している運用計画に影響を及ぼすことなく工事を成立させる余地はあることを考慮して設けられた判定手段である。方策有無判定部24は、ノウハウ情報33を参照して、動作状態の矛盾が生じている機器が属するプラント内の区分において、過去に実施済みの工事などで実際に行った方策の有無を判定する。   Even if there is a contradiction in the operation state of the device, the policy presence / absence determination unit 24 does not affect the operation plan that has been established while complying with the safety regulations (without deviating) by taking some measures. The determination means is provided in consideration of the fact that there is a room to establish. The policy presence / absence determination unit 24 refers to the know-how information 33 to determine the presence / absence of a policy that has actually been performed in the past in the section of the plant to which the equipment in which the operation state contradiction belongs belongs. .

方策有無判定部24が行う方策有無の判定(方策有無判定)は、上述した第3の判定に相当する。方策有無判定部24は、方策の有無について判定した判定結果を、出力部22に出力したり、記憶部28に判定結果情報38として保存したりする。   The determination of the presence / absence of a policy (policy presence / absence determination) performed by the policy presence / absence determination unit 24 corresponds to the above-described third determination. The policy presence / absence determination unit 24 outputs the determination result determined for the presence / absence of the policy to the output unit 22 or saves the determination result information 38 in the storage unit 28.

方策適用可否判定部25は、方策有無判定部24が方策有りと判定している方策から選択を受け付けた方策をプラントの保安規定を逸脱することなく適用できるか否かを判定する機能を有する。方策適用可否判定部25は、方策有無判定部24が方策有りと判定している方策から選択を受け付けると、ノウハウ情報33および保安規定情報35を参照し、プラントの保安規定を逸脱しない範囲で選択を受け付けた方策を適用できるか否かを判定する。   The policy applicability determination unit 25 has a function of determining whether or not the policy accepted from the policy determined by the policy presence / absence determination unit 24 can be applied without departing from the plant safety regulations. When the policy applicability determination unit 25 receives a selection from the policies determined by the policy presence / absence determination unit 24, the policy applicability determination unit 24 refers to the know-how information 33 and the safety regulation information 35 and selects within a range that does not deviate from the plant safety regulations. It is determined whether or not the policy for accepting can be applied.

方策適用可否判定部25が行う方策適用可否の判定(方策適用可否判定)は、上述した第4の判定に相当する。方策適用可否判定部25は、判定結果を、出力部22に出力したり、記憶部28に判定結果情報38として保存したりする。   The policy applicability determination (policy applicability determination) performed by the policy applicability determination unit 25 corresponds to the above-described fourth determination. The policy applicability determination unit 25 outputs the determination result to the output unit 22 or stores it as determination result information 38 in the storage unit 28.

なお、方策適用可否判定が、追加の作業工程が固定の作業工程と干渉するか否かの最終段階の判定となることもある。この場合、方策適用可否判定部25は、追加の作業工程が固定の作業工程と干渉するか否かの最終的な判定結果を出力部22に出力する。   The policy applicability determination may be the final determination as to whether or not the additional work process interferes with the fixed work process. In this case, the policy applicability determination unit 25 outputs a final determination result as to whether or not the additional work process interferes with the fixed work process to the output unit 22.

作業エリア干渉判定部26は、未確定の工事計画における作業工程が、既に予定が確定しているプラント系統の運用計画に沿った工事計画における作業工程に対して、作業工程が行われる作業期間内に作業エリアが重複(干渉)するか否かを判定する機能を有する。   The work area interference determination unit 26 determines that the work process in the unconfirmed work plan is within the work period in which the work process is performed with respect to the work process in the work plan according to the operation plan of the plant system for which the schedule has already been confirmed. Have a function of determining whether the work areas overlap (interfere).

作業エリア干渉判定部26は、まず、作業エリア情報36を参照し、未確定の工事計画における作業工程で使用される機器、当該機器の位置、作業エリアの大きさおよび作業期間が、プラント系統の運用計画に沿った工事計画における作業工程で使用される機器、当該機器の位置、作業エリアの大きさおよび作業期間と干渉するか否かを判定する。   First, the work area interference determination unit 26 refers to the work area information 36, and the equipment used in the work process in the unconfirmed construction plan, the position of the equipment, the size of the work area, and the work period are determined based on the plant system. It is determined whether or not it interferes with the equipment used in the work process in the construction plan according to the operation plan, the position of the equipment, the size of the work area, and the work period.

また、作業エリア干渉判定部26は、設備の重要度を考慮した判定を行うことができる。この場合、作業エリア干渉判定部26は、重要度の有無や高低などの違いに応じて、干渉を禁止する干渉禁止エリアの大きさ(広狭)を変えたり、判定の段階数を変えたりして判定する。   In addition, the work area interference determination unit 26 can perform determination in consideration of the importance of the equipment. In this case, the work area interference determination unit 26 changes the size (wide or narrow) of the interference prohibition area that prohibits interference or changes the number of determination steps according to the presence or absence of importance or the difference in level. judge.

作業エリア干渉判定部26が行う作業エリア干渉の判定(作業エリア干渉判定)は、上述した第5の判定および第6の判定に相当する。作業エリア干渉判定部26は、判定結果を、出力部22に出力したり、記憶部28に判定結果情報38として保存したりする。   The work area interference determination (work area interference determination) performed by the work area interference determination unit 26 corresponds to the above-described fifth determination and sixth determination. The work area interference determination unit 26 outputs the determination result to the output unit 22 or stores it as determination result information 38 in the storage unit 28.

なお、上述した第5の判定および第6の判定は、追加の作業工程が固定の作業工程と干渉するか否かを判定する最終段階の判定であるため、作業エリア干渉判定部26が行う判定結果には、追加の作業工程が固定の作業工程と干渉するか否かの最終的な判定結果も含まれる。   The fifth determination and the sixth determination described above are final determinations as to whether or not the additional work process interferes with the fixed work process, and thus the determination performed by the work area interference determination unit 26. The result also includes the final determination result of whether or not the additional work process interferes with the fixed work process.

記憶部28は、情報の読み出し(リード)および書き込み(ライト)が可能な記憶領域を備え、当該記憶領域に情報を保持する機能を有する。記憶部28は、機器動作状態矛盾判定部23、方策有無判定部24、方策適用可否判定部25、作業エリア干渉判定部26および制御部29に対して、情報の読み出しおよび書き込み可能な記憶領域を提供し、各々の処理実行に必要な情報の読み出し(リード)および書き込み(ライト)が行われる。   The storage unit 28 includes a storage area where information can be read (read) and written (write), and has a function of holding information in the storage area. The storage unit 28 provides storage areas in which information can be read and written to the device operation state contradiction determination unit 23, the policy presence / absence determination unit 24, the policy applicability determination unit 25, the work area interference determination unit 26, and the control unit 29. And reading (reading) and writing (writing) information necessary to execute each process.

工事計画支援処理手順を実行する際には、記憶部28において、例えば、仮工事計画情報31、確定工事計画情報32、ノウハウ情報33、運用工程情報34、保安規定情報35、作業エリア情報36、重要設備情報37および判定結果情報38の何れかを含む情報が適宜読み書きされる。各情報31〜38の詳細については後述する。   When executing the construction plan support processing procedure, in the storage unit 28, for example, temporary construction plan information 31, finalized construction plan information 32, know-how information 33, operation process information 34, safety regulation information 35, work area information 36, Information including any of the important facility information 37 and the determination result information 38 is appropriately read and written. Details of each piece of information 31 to 38 will be described later.

制御部29は、プラント工事計画支援システム20のシステム全体の処理を制御する処理部であり、入力部21、出力部22、機器状態矛盾判定部23(23a,23b)、方策有無判定部24、方策適用可否判定部25、作業エリア干渉判定部26および記憶部28と相互に情報を授受し、これらを制御する機能を有する。   The control unit 29 is a processing unit that controls processing of the entire system of the plant construction plan support system 20, and includes an input unit 21, an output unit 22, an equipment state contradiction determination unit 23 (23a, 23b), a policy presence / absence determination unit 24, The policy applicability determination unit 25, the work area interference determination unit 26, and the storage unit 28 have a function of exchanging information with each other and controlling them.

制御部29は、例えば、ユーザから情報の表示要求があった場合、表示要求があった情報と関係する処理部21,23〜26,28から表示要求があった情報を受け取り、受け取った情報を出力部22の一例である表示部に表示する表示指令を与える。当該表示指令を受けた表示部には、表示要求があった情報が表示される。   For example, when there is a display request for information from the user, the control unit 29 receives the information requested for display from the processing units 21, 23 to 26, 28 related to the information requested for display, and receives the received information. A display command to be displayed on the display unit which is an example of the output unit 22 is given. Information that has been requested to be displayed is displayed on the display unit that has received the display command.

例えば、方策有無判定部24による方策有無判定の判定結果を表示する要求があった場合、制御部29は、当該表示要求があった方策有無判定を行う方策有無判定部24から方策有無判定の判定結果を受け取るとともに、当該表示要求に従って受け取った判定結果を出力部22の一例である表示部に表示する表示指令を与える。判定結果は、当該表示指令に従って表示部に表示される。   For example, when there is a request to display the determination result of the policy presence / absence determination by the policy presence / absence determination unit 24, the control unit 29 determines the policy presence / absence determination from the policy presence / absence determination unit 24 that performs the policy presence / absence determination for which the display request has been made. While receiving a result, the display command which displays the determination result received according to the said display request on the display part which is an example of the output part 22 is given. The determination result is displayed on the display unit according to the display command.

なお、プラント工事計画支援システム20は、機器状態矛盾判定部23(23a,23b)と、方策有無判定部24とを具備し、情報の授受が可能に構成されていればよく、必ずしも、方策適用可否判定部25および作業エリア干渉判定部26を具備していなくてもよい。   The plant construction plan support system 20 only needs to include the equipment state contradiction determination unit 23 (23a, 23b) and the policy presence / absence determination unit 24 and be configured to be able to exchange information. The availability determination unit 25 and the work area interference determination unit 26 may not be provided.

また、プラント工事計画支援システム20において、方策有無判定部24および方策適用可否判定部25は、両判定部の機能を集約して単一の構成としてまとめられていてもよい。   In the plant construction plan support system 20, the policy presence / absence determination unit 24 and the policy applicability determination unit 25 may be integrated as a single configuration by integrating the functions of both determination units.

さらに、コンピュータと工事計画支援PGとが協働して実現されるプラント工事計画支援システム20では、コンピュータが備える外部装置とのインターフェイス手段を介して接続される入力装置や表示装置などの出力装置を入力手段や出力手段として適用してもよい。すなわち、プラント工事計画支援システム20では、外部装置である入力装置を入力部21として適用したり、外部装置である出力装置を出力部22として適用したりすることができる。   Furthermore, in the plant construction plan support system 20 realized by the cooperation of the computer and the construction plan support PG, an output device such as an input device or a display device connected via an interface unit with an external device provided in the computer is provided. You may apply as an input means or an output means. That is, in the plant construction plan support system 20, an input device that is an external device can be applied as the input unit 21, and an output device that is an external device can be applied as the output unit 22.

続いて、工事計画支援システム20で用いられる仮工事計画情報31、確定工事計画情報32、ノウハウ情報33、運用工程情報34、保安規定情報35、作業エリア情報36、重要設備情報37および判定結果情報38について、それぞれ説明する。   Subsequently, temporary construction plan information 31, finalized construction plan information 32, know-how information 33, operation process information 34, safety regulation information 35, work area information 36, important equipment information 37, and determination result information used in the construction plan support system 20 Each of 38 will be described.

図2は、工事計画情報としての仮工事計画情報31および確定工事計画情報32の内容を示す説明図である。   FIG. 2 is an explanatory diagram showing the contents of temporary construction plan information 31 and finalized construction plan information 32 as construction plan information.

なお、図2に示される機器#1、機器#2および機器#3は、それぞれ、第1機器、第2機器および第3機器である。以下の説明では、第1機器〜第n機器を、それぞれ、図2などと同様に、機器#1〜機器#nとする。   Note that the device # 1, the device # 2, and the device # 3 illustrated in FIG. 2 are a first device, a second device, and a third device, respectively. In the following description, the first device to the n-th device are referred to as device # 1 to device #n, respectively, similarly to FIG.

仮工事計画情報31は、工事を計画しているプラントの未確定の工事計画における、工事日時の情報と、プラントを構成する機器の識別情報と、アイソレーション状態情報とを含み、相互に関連付けられている。   The temporary construction plan information 31 includes construction date and time information, identification information of devices constituting the plant, and isolation state information in an unconfirmed construction plan of the plant that is planning construction, and is associated with each other. ing.

確定工事計画情報32は、工事を計画しているプラントの確定した工事計画における、工事日時の情報と、プラントを構成する機器の識別情報と、アイソレーション状態情報とを含み、相互に関連付けられている。すなわち、仮工事計画情報31に対し、工事計画が確定している点で相違するがその他の点は実質的に相違しない。   The confirmed construction plan information 32 includes construction date and time information, identification information of devices constituting the plant, and isolation state information in the confirmed construction plan of the plant that is planning the construction, and is associated with each other. Yes. That is, it differs from the temporary work plan information 31 in that the work plan is fixed, but the other points are not substantially different.

例えば、工事の日時が開始日2016年10月1日(2016/10/1:図2)から終了日2016年10月10日(2016/10/10:図2)がプラント工事計画支援システム20に入力されると、工事の工程内で使用される機器が第1機器から第3機器(機器#1、機器#2および機器#3:図2)、当該工事の期間における各機器#1〜#3の入切状態(ONまたはOFF:図2)として、機器#1および機器#2については、開始から終了直前までが入状態(ON)であって終了時に切状態(OFF)となり、機器#3については、開始から終了直前までが切状態(OFF)であって終了時に入状態(ON)となる場合、プラント工事計画支援システム20は、図2に例示されるように、2016年10月1日から2016年10月10日までの工事期間における工事の工程内で使用される機器毎の入切状態を時系列で認識する。   For example, the plant construction plan support system 20 has a construction date from October 1, 2016 (2016/10/1: FIG. 2) to the end date October 10, 2016 (2016/10/10: FIG. 2). Is input from the first device to the third device (device # 1, device # 2, and device # 3: FIG. 2), and each device # 1 to # 1 in the construction period is used. As the on / off state of # 3 (ON or OFF: FIG. 2), the device # 1 and the device # 2 are in the on state (ON) from the start to immediately before the end, and are turned off (OFF) at the end. As for # 3, when it is in the off state (OFF) from the start to immediately before the end and is in the on state (ON) at the end, the plant construction plan support system 20 is set to 2016 10 as illustrated in FIG. 1st to 2016 It recognizes the on-off state of each device used in the construction steps in the construction period until October 10th chronologically.

上記情報においては、工事日のみを示しているが時間まで設定しても良く、日にちのみ、時間のみまたは日時を含めて以下、工事の日時と呼ぶ。   In the above information, only the construction date is shown, but it may be set up to the time, and only the date, only the time or the date and time will be referred to as the construction date and time hereinafter.

図3はノウハウ情報33の一例を示した説明図である。
図4はノウハウ情報33に含まれる区分および機器の境界を例示する説明図である。
FIG. 3 is an explanatory diagram showing an example of know-how information 33.
FIG. 4 is an explanatory diagram exemplifying the divisions included in the know-how information 33 and the boundaries between devices.

ノウハウ情報33(図3)は、少なくとも、工事を計画しているプラントの系統の機能を喪失する最小単位(以下、「区分」という。)毎に、機器の識別情報と、過去に実施した工事において実際に行った方策(ノウハウ)の情報とを含み、区分を示す区分情報、機器の識別情報および方策の情報が相互に関連付けられている。また、ノウハウ情報33(図3)は、ノウハウの適用に条件が必要となる場合、ノウハウに加えてさらにノウハウ適用のためのノウハウ適用条件をさらに含む。   The know-how information 33 (FIG. 3) includes at least equipment identification information and construction performed in the past for each minimum unit (hereinafter referred to as “classification”) that loses the function of the plant system where the construction is planned. In addition, information on the policy (know-how) actually taken in Fig. 1 is included, and category information indicating the category, device identification information, and policy information are associated with each other. In addition, know-how information 33 (FIG. 3) further includes know-how application conditions for applying know-how in addition to know-how when conditions are required for applying know-how.

図3に例示されるノウハウ情報33は、図4に例示されるプラントの流体供給機能が喪失する最小単位である区分Sを対象とする内容である。   The know-how information 33 illustrated in FIG. 3 is content that targets the section S, which is the minimum unit in which the fluid supply function of the plant illustrated in FIG. 4 is lost.

図3に例示されるノウハウ情報33は、区分Sに属する機器#1〜#n(nは複数)の識別情報および機器毎に過去に実施した工事において実際に行った方策であるノウハウに加え、さらに、各機器#1〜#nの境界となる境界弁を特定する境界識別情報としての境界弁番号と、境界状態情報としての境界弁状態とを含む。つまり、図3に例示されるノウハウ情報33では、境界弁および当該境界弁状態がノウハウ適用条件となっている。   The know-how information 33 illustrated in FIG. 3 includes, in addition to the identification information of the devices # 1 to #n (n is a plurality) belonging to the category S and the know-how that is actually implemented in the construction performed in the past for each device, Furthermore, the boundary valve number as boundary identification information which specifies the boundary valve used as the boundary of each apparatus # 1- # n, and the boundary valve state as boundary state information are included. That is, in the know-how information 33 illustrated in FIG. 3, the boundary valve and the boundary valve state are the know-how application conditions.

ここで、図4に示される区分Sを例に、境界弁について補足すると、流体供給用のラインL1に設けられている機器#1の場合、流体の流れ方向に対して機器#1の直近の上流に設けられる開閉弁43が機器#1の境界弁である。   Here, taking the section S shown in FIG. 4 as an example and supplementing the boundary valve, in the case of the device # 1 provided in the fluid supply line L1, the closest to the device # 1 with respect to the fluid flow direction. The on-off valve 43 provided upstream is the boundary valve of the device # 1.

なお、ノウハウ情報33は、確定工事計画情報32などの工事計画情報と一体的に構成されていてもよい。すなわち、プラントの系統の区分毎に、機器の識別情報と、工事日時の情報と、アイソレーション状態情報と、方策の情報とを含み、相互に関連付けた情報を、工事計画情報およびノウハウ情報33として準備してもよい。   The know-how information 33 may be integrated with construction plan information such as the confirmed construction plan information 32. That is, for each system division of the plant, information including equipment identification information, construction date and time information, isolation state information, and policy information is associated with each other as construction plan information and know-how information 33. You may prepare.

図5(図5(A)および図5(B))は、運用工程情報34の内容を示す説明図であり、図5(A)がプラントを適切に運用する上で必要とされる工程および期間の例を示す説明図、図5(B)が図5(A)に示される工程Aに必要となる機器毎の動作状態を示す説明図である。   FIG. 5 (FIG. 5 (A) and FIG. 5 (B)) is explanatory drawing which shows the content of the operation process information 34, and the process and FIG. 5 (A) are required when operating a plant appropriately. Explanatory drawing which shows the example of a period, FIG.5 (B) is explanatory drawing which shows the operation state for every apparatus required for the process A shown by FIG. 5 (A).

運用工程情報34は、例えば、プラントの系統の運用計画に沿う作業工程における日時および作業内容と、プラントを構成する機器のうち、当該作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む。プラントの系統の運用計画に沿う作業工程は、事前に保安規定を順守するように検討され決定されている。すなわち、プラントの系統の運用計画に沿う作業工程は、予定が確定しており、保安規定を常に順守する。運用工程情報34には、保守および点検を含めたプラントの運用上実施が予定される全ての工程が含まれている。   The operation process information 34 indicates, for example, the date and time of the operation process in accordance with the operation plan of the plant system, and the operation state of each device necessary for performing the operation process among the devices constituting the plant. Information. The work process according to the operation plan of the plant system is examined and determined in advance so as to comply with the safety regulations. In other words, the work process according to the plant system operation plan has a fixed schedule and always observes the safety regulations. The operation process information 34 includes all processes scheduled to be implemented in the operation of the plant including maintenance and inspection.

図5(A)および図5(B)に示される運用工程情報34を例により具体的に説明する。運用工程情報34は、例えば、図5(A)に示されるように、上位の情報として、プラントの系統を運用する上で実施することが確定している作業工程Aなどの作業工程が、工程A1、A2およびA3などのより詳細な工程を含んでいることを表す情報を有している。なお、図5(A)中の丸印「〇」およびバツ印「×」は、それぞれ、当該工程を実施することおよび実施しないことを表している。   The operation process information 34 shown in FIGS. 5A and 5B will be specifically described by way of example. For example, as shown in FIG. 5 (A), the operation process information 34 includes, as upper information, a work process such as a work process A that has been confirmed to be performed when operating a plant system. It has information indicating that more detailed processes such as A1, A2 and A3 are included. In addition, the circle mark “◯” and the cross mark “X” in FIG. 5A indicate that the process is performed and not performed, respectively.

また、運用工程情報34は、例えば、図5(B)に示されるように、下位の情報として、上位の作業工程である作業工程Aに含まれる工程A1などの下位の(より詳細な)作業工程の各々に対して、当該下位の作業工程を行う上で必要となる機器毎に要求される機器の動作状態を表す情報を有している。   Further, for example, as shown in FIG. 5B, the operation process information 34 includes lower-order (more detailed) work such as process A1 included in work process A, which is a higher-order work process, as lower-order information. For each process, there is information representing the operating state of the equipment required for each equipment required for performing the subordinate work process.

図6は、保安規定情報35の一例である保安規定順守判定ロジックを説明する説明図である。   FIG. 6 is an explanatory diagram for explaining the security regulation compliance determination logic, which is an example of the security regulation information 35.

保安規定情報35(図6)は、例えば、作業工程Aなどの実施する作業工程に対して保安規定が要求する条件、すなわち保安規定を順守するための条件を満たすか否かを判定するための保安規定順守判定ロジックである。   The security regulation information 35 (FIG. 6) is used to determine whether, for example, a condition required by the security regulation for a work process such as work process A, that is, a condition for complying with the safety regulation is satisfied. It is a security regulation compliance judgment logic.

プラント工事計画支援システム20では、例えば、作業工程Aの実施に関して、図6に示される保安規定順守判定ロジックに従った手順(ステップS1〜S4)で判定を行い、保安規定を順守するために必要とされる条件を判定する。   In the plant construction plan support system 20, for example, with respect to the execution of the work process A, it is necessary to perform the determination according to the procedure (steps S1 to S4) according to the safety rule compliance determination logic shown in FIG. To determine the condition.

図6に例示される保安規定順守判定ロジックは、プラント内の設備Xの状態が何れの状態にあるかに応じて、保安規定を順守するために必要とされる条件が、条件(i)から条件(iii)の何れの条件であるかを判定するためのロジックである。   The safety regulation compliance determination logic illustrated in FIG. 6 is based on the condition (i) that is required to comply with the safety regulations depending on which state of the equipment X in the plant is. This is a logic for determining which condition (iii) is satisfied.

設備Xの状態(ステップS1)が「運転」の場合、工程A1および工程A2の両工程を実施しなくても保安規定を順守することができる「条件(i)」となる(ステップS2)。設備Xの状態(ステップS1)が「停止」の場合、工程A1および工程A2の両工程のうち一方(工程A1または工程A2)を実施すれば保安規定を順守することができる「条件(ii)」(ステップS3)となる。設備Xの状態(ステップS1)が「その他」の場合、工程A1および工程A2の両工程を実施すれば保安規定を順守することができる「条件(iii)」(ステップS4)となる。   When the state of the equipment X (step S1) is “operation”, it becomes “condition (i)” that allows the safety regulations to be observed without performing both the process A1 and the process A2 (step S2). When the state of the equipment X (step S1) is “stopped”, if one of the steps A1 and A2 (step A1 or step A2) is performed, the safety regulations can be observed. “Condition (ii) (Step S3). When the state of the equipment X (step S1) is “others”, the “condition (iii)” (step S4) that can comply with the safety regulations can be achieved by performing both the process A1 and the process A2.

プラント工事計画支援システム20は、保安規定を順守できるか否かの判定が必要となった場合、保安規定順守判定ロジックに従う判定の結果として得られた条件(i)などの条件を満たすか否かを判定することによって、保安規定を順守できるか否かを判定する。   When it is necessary to determine whether or not the safety regulations can be complied with, the plant construction plan support system 20 satisfies the conditions such as the condition (i) obtained as a result of the determination according to the safety regulations compliance determination logic. It is determined whether the safety regulations can be complied with.

図7(図7(A)および図7(B))は、作業エリア情報36の一例を示す説明図であり、図7(A)が大きさの範囲が1パターンの場合を示す説明図、図7(B)が大きさの範囲が2パターンの場合を示す説明図である。   FIG. 7 (FIGS. 7A and 7B) is an explanatory diagram showing an example of the work area information 36, and FIG. 7A is an explanatory diagram showing a case where the size range is one pattern. FIG. 7B is an explanatory diagram showing a case where the size range is two patterns.

図8(図8(A)および図8(B))は作業エリアの位置情報の定義例を示す説明図であり、図8(A)が平面(縦方向および横方向)についての定義例を示す説明図、図8(B)が高さ方向(Z軸方向)の定義例を示す説明図である。   FIG. 8 (FIG. 8A and FIG. 8B) is an explanatory diagram showing a definition example of work area position information, and FIG. 8A is a definition example for a plane (vertical direction and horizontal direction). FIG. 8B is an explanatory diagram illustrating a definition example in the height direction (Z-axis direction).

作業エリア情報36(図7)は、例えば、作業に使用される機器の識別情報、作業エリアの位置情報、作業エリアの大きさ情報および作業期間情報を含む。位置情報の定義は、例えば、空間上の1点(原点)を選定し、選定した1点を原点とする三次元直交座標系を設定したり、作業エリアを直方体状の空間領域に区切るなどすることによって行う。   The work area information 36 (FIG. 7) includes, for example, identification information of devices used for work, work area position information, work area size information, and work period information. The position information is defined by, for example, selecting one point (origin) in the space, setting a three-dimensional orthogonal coordinate system with the selected point as the origin, or dividing the work area into rectangular space areas, etc. By doing.

図8(A)および図8(B)に例示される位置情報は、作業エリアが第1号建屋(図中では「建屋#1」と記す。)の屋内である場合の例であり、高さについては建屋のフロア45(45a〜45d)毎に区切って定義されている。また、各フロアの平面(エリア)の位置については、各フロアの平面領域46を、縦方向(X軸方向)および横方向(Y軸方向)に、それぞれ、p(pは複数)等分およびq(qは複数)等分した分割平面領域47によって定義されている。   The position information illustrated in FIGS. 8A and 8B is an example when the work area is indoors of the first building (denoted as “building # 1” in the figure). The size is defined by dividing each floor 45 (45a to 45d) of the building. In addition, regarding the position of the plane (area) of each floor, the plane area 46 of each floor is equally divided into p (p is plural) in the vertical direction (X-axis direction) and the horizontal direction (Y-axis direction), respectively. It is defined by a divided plane area 47 divided into q (q is plural).

例えば、図7(A)および図7(B)に示される位置情報の一例である、エリア「X2Y2」およびフロア「1F」の位置情報が示す位置は、図8に例示される位置情報の定義に従えば、建屋1階(1F)のフロア45cであって、縦方向が基準位置(原点O)から2番目の範囲「X2」と横方向が基準位置(原点O)から2番目の範囲「Y2」とが交わる分割平面領域47aである。   For example, the position indicated by the position information of the area “X2Y2” and the floor “1F”, which is an example of the position information illustrated in FIGS. 7A and 7B, is the definition of the position information illustrated in FIG. The floor 45c on the first floor (1F) of the building is the second range “X2” from the reference position (origin O) in the vertical direction and the second range “X2” from the reference position (origin O) in the horizontal direction. This is a divided plane region 47a where “Y2” intersects.

作業エリアの大きさ情報は、他の作業などでエリアが干渉すると自己作業を遂行する上で支障をきたす領域を示す情報である。換言すれば、作業エリアの大きさは、干渉禁止エリアの大きさを表している。作業エリアの大きさ情報は、例えば、X軸方向およびY軸方向に必要な長さを設定したり、円領域となる範囲に対して中心位置および半径を設定したりするなど、範囲を特定可能な情報によって定義される。   The size information of the work area is information indicating an area that hinders self-work if the area interferes with other work. In other words, the size of the work area represents the size of the interference prohibition area. The size of the work area can be specified, for example, by setting the required length in the X-axis direction and the Y-axis direction, or by setting the center position and radius for the circular area. Defined by various information.

図7に示される「機器#1」の大きさ「X1,Y1」は、分割平面領域47の大きさを基準とする大きさの定義であり、自己の位置を示すエリア「X2Y2」を中心としてX軸方向に1個分、Y軸方向に1個分の大きさであることを示す。   The size “X1, Y1” of “device # 1” shown in FIG. 7 is a definition of the size based on the size of the divided plane area 47, and the area “X2Y2” indicating its own position is the center. The size is one for the X-axis direction and one for the Y-axis direction.

なお、作業エリア情報36に含まれる大きさ情報は、後述する設備の重要度を考慮する場合、それぞれ異なる大きさを示す複数個の大きさ情報を含んでいてもよい。例えば、図7(B)に示されるように、重要度が高と低の2段階であって、重要度の高と低とに応じて、異なる大きさが設定されていてもよい。   Note that the size information included in the work area information 36 may include a plurality of size information indicating different sizes in consideration of the importance of the facility described later. For example, as shown in FIG. 7B, there are two stages of high and low importance, and different sizes may be set according to the high and low importance.

また、大きさ情報は、X軸方向およびY軸方向に必要な長さなどの直接的に大きさを規定する情報であるが、間接的に大きさを規定する情報が存在する場合、間接的に大きさを規定する情報を用いてもよい。   In addition, the size information is information that directly specifies the size such as the length required in the X-axis direction and the Y-axis direction, but indirectly when there is information that indirectly specifies the size. Information defining the size may be used.

間接的に大きさを規定する情報が存在する場合としては、例えば、機器の種類に応じて大きさを何パターンかに分類できる場合であって、機器の種類を表す機種コードと機器の種類に応じた大きさを表す大きさ情報とを関連付けた機器管理情報(図示せず)が準備されている場合などがある。この場合、大きさのパターンと関連付けられている機種コードが間接的に大きさを規定する情報となり、この機種コードを作業エリア情報36に含まれる大きさ情報として用いることができる。   For example, when there is information that indirectly specifies the size, for example, the size can be classified into several patterns according to the type of device. There may be a case where device management information (not shown) in association with size information representing the corresponding size is prepared. In this case, the model code associated with the size pattern is information that indirectly defines the size, and this model code can be used as the size information included in the work area information 36.

図9(図9(A)および図9(B))は、重要設備情報37の一例を示す説明図であり、図9(A)は重要であるか否かで重要度を設定する場合を示す説明図、図9(B)は重要である場合を例えば3段階などの複数段階に分けて重要度を設定する場合を示す説明図である。   FIG. 9 (FIGS. 9A and 9B) is an explanatory diagram showing an example of the important facility information 37. FIG. 9A shows a case where the importance is set depending on whether or not it is important. FIG. 9B is an explanatory diagram illustrating a case where importance is set by dividing a case of importance into a plurality of stages such as three stages.

重要設備情報37は、例えば、機器の識別情報に対して、少なくとも所定の重要度を満たす重要設備であるか否かを識別する重要度情報を含む。   The important equipment information 37 includes, for example, importance information for identifying whether or not the equipment is the important equipment satisfying at least a predetermined importance with respect to the device identification information.

ここで、重要度とは、重要でない場合も含めた重要さの度合いをいう。図9(A)に例示される重要設備情報37では、重要度が重要であることを示す丸印(図9(A)において「〇」印)と重要ではないことを示すバツ印(図9(A)において「×」印)とに設定されている。また、図9(B)に例示される重要設備情報37では、重要度が重要であって重要さの程度を示す1(重要度:低)〜3(重要度:高)の3段階と、重要ではないことを示す0の1段階の計4段階に設定されている。   Here, the importance level refers to a degree of importance including a case where it is not important. In the important facility information 37 illustrated in FIG. 9A, a round mark indicating that the importance is important (“◯” in FIG. 9A) and a cross mark indicating that it is not important (FIG. 9). (A) is set to “×”. Further, in the important facility information 37 illustrated in FIG. 9B, the three levels of 1 (importance: low) to 3 (importance: high) indicating the importance and the degree of importance, It is set to 4 levels, 1 level of 0 indicating that it is not important.

プラント工事計画支援システム20が図9(A)に示される重要設備情報37を参照する場合、プラント工事計画支援システム20は、機器#1などの重要度が丸印「○」である機器を重要設備と判定する一方、機器#2などの重要度がバツ印「×」であるその他の機器については重要設備ではない設備(以下、「非重要設備」とする。)と判定する。   When the plant construction plan support system 20 refers to the important facility information 37 shown in FIG. 9A, the plant construction plan support system 20 considers the equipment whose importance level is “O”, such as equipment # 1, as important. On the other hand, it is determined that the equipment is an equipment that is not an important equipment (hereinafter, referred to as “non-important equipment”) for the other equipment having an importance level of “X”, such as the equipment # 2.

また、数字の大小と重要度の高低とが対応するように重要度を設定した重要設備情報37(図9(B))が参照される場合、プラント工事計画支援システム20は、重要度が1である機器#nよりも重要度が3である機器#1の方がより重要度が高い設備として機器を識別する。   Further, when the important facility information 37 (FIG. 9B) in which the importance is set so that the magnitude of the number corresponds to the level of importance is referred to, the plant construction plan support system 20 has an importance of 1. The device # 1 having the importance 3 is identified as the equipment having the higher importance than the device #n.

なお、重要設備情報37は、必ずしも、全ての機器に対して、重要であるか否かを示す情報を設定していなくてもよい。重要である場合を複数段階で判定する必要がないのであれば、重要設備である機器の識別情報のみを含む構成としてもよい。この場合、重要設備情報37に含まれる機器の識別情報を有する機器を、重要設備として判定することができる。   The important facility information 37 does not necessarily have to set information indicating whether or not it is important for all devices. If it is not necessary to determine the case where it is important in a plurality of stages, it may be configured to include only identification information of a device that is an important facility. In this case, a device having device identification information included in the important facility information 37 can be determined as an important facility.

また、重要設備情報37は、作業エリア情報36などの機器の識別情報を有する他の情報に含まれていてもよい。すなわち、作業に使用される機器の識別情報、位置情報および作業期間の情報を含んでいる作業エリア情報36に加えて、さらに、重要設備情報37に含まれるプラントの保安規定に重要な設備機器として機能確保が要求される機器の識別情報を含んだ作業エリア情報36を準備してもよい。   The important facility information 37 may be included in other information having device identification information such as the work area information 36. In other words, in addition to the work area information 36 including the identification information, position information, and work period information of the equipment used for the work, the equipment is also important for the plant safety regulations included in the important equipment information 37. You may prepare the work area information 36 containing the identification information of the apparatus for which function ensuring is requested | required.

判定結果情報38は、例えば、上述した第1から第6の判定の判定結果など、プラント工事計画支援システム20が最終的に工事計画の見直しの要否を判定するために行う判定のうち、少なくとも1個の判定結果の情報を含む。なお、判定結果情報38は、必ずしも記憶部28に読み出し可能に保存されることを要するものではなく、保存が省略されることもある。   The determination result information 38 is, for example, at least of the determinations made by the plant construction plan support system 20 to finally determine whether the construction plan needs to be reviewed, such as the determination results of the first to sixth determinations described above. Contains information on one determination result. Note that the determination result information 38 does not necessarily need to be stored in the storage unit 28 so as to be readable, and the storage may be omitted.

次に、実施形態に係るプラントの工事計画支援方法について、プラント工事計画支援システム20が行う工事計画支援処理手順(第1の工事計画支援処理手順から第3の工事計画支援処理手順)を例に説明する。   Next, regarding the plant construction plan support method according to the embodiment, the construction plan support processing procedure (from the first construction plan support processing procedure to the third construction plan support processing procedure) performed by the plant construction plan support system 20 is taken as an example. explain.

図10は、プラント工事計画支援システム20が行う工事計画支援処理手順の一例(第1の例)である第1の工事計画支援処理手順(ステップS11〜S19)の処理の流れを示す流れ図(フローチャート)である。なお、図10中に示される、〇の内にIおよびIIが記入されている記号は、それぞれ、処理フローを結合する結合子である。   FIG. 10 is a flowchart (flow chart) showing a processing flow of a first construction plan support processing procedure (steps S11 to S19), which is an example (first example) of a construction plan support processing procedure performed by the plant construction plan support system 20. ). In FIG. 10, the symbols in which I and II are entered in the circles are connectors that combine the processing flows.

第1の工事計画支援処理手順(ステップS11〜S19)は、例えば、多段階に条件を判定する判定手段としての、方策有無判定部24および方策適用可否判定部25が、1以上の系統を備えるプラントの未確定の工事計画の妥当性を判定することによってプラントの工事計画を支援する処理ステップを備える。   In the first construction plan support processing procedure (steps S11 to S19), for example, the policy presence / absence determination unit 24 and the policy applicability determination unit 25 as a determination unit that determines conditions in multiple stages include one or more systems. Processing steps are provided for supporting the plant construction plan by determining the validity of the plant indeterminate construction plan.

第1の工事計画支援処理手順では、まず、プラント工事計画支援システム20が、追加の(未確定の)作業工程について、対象となる機器、工程の実施日時およびアイソレーション実行時の機器の動作状態(アイソレーション状態)の情報の入力を受け付ける(ステップS11)。すなわち、仮の工程票X(図11,12)を作成し、仮工事計画情報31とする。   In the first construction plan support processing procedure, first, the plant construction plan support system 20 makes the target device, the execution date and time of the process, and the operation state of the device at the time of isolation for an additional (undefined) work process. The input of (isolation state) information is accepted (step S11). That is, a temporary process slip X (FIGS. 11 and 12) is created and used as temporary work plan information 31.

続いて、機器動作状態矛盾判定部23(第1の機器動作状態矛盾判定部23a)が、仮工事計画情報31(図1)および確定工事計画情報32(図1)を参照して、追加の作業工程におけるアイソレーション実行時の機器の動作状態が、確定工事計画の作業工程におけるアイソレーション実行時の機器の動作状態と矛盾しているか否かを判定する(第1の判定:ステップS12)。   Subsequently, the device operation state contradiction determining unit 23 (first device operation state contradiction determining unit 23a) refers to the temporary construction plan information 31 (FIG. 1) and the confirmed construction plan information 32 (FIG. 1), and adds It is determined whether or not the operation state of the device at the time of performing the isolation in the work process is inconsistent with the operation state of the device at the time of performing the isolation in the work process of the confirmed construction plan (first determination: step S12).

ここで、第1の判定(ステップS12)について、機器の動作状態が矛盾する場合および矛盾しない場合を、より具体的に説明する。   Here, the case where the operation states of the devices are contradictory and the case where there is no contradiction will be described more specifically with respect to the first determination (step S12).

図11は、仮工事計画情報31および確定工事計画情報32に基づき、未確定の作業工程と確定した作業工程との両者に共通するアイソレーション実行時の機器である機器#1について、作業工程実施時における動作状態を時系列(t〜t)で表した説明図である。 FIG. 11 shows that the work process is performed for the device # 1 that is the device at the time of isolation common to both the unconfirmed work process and the confirmed work process based on the temporary work plan information 31 and the confirmed work plan information 32. it is an explanatory view showing in time series (t 1 ~t 7) the operating state at the time.

図12は、第1の判定における動作状態の一致および不一致を説明する説明図であり、図12(A)および図12(B)は、それぞれ、図11に例示される未確定の作業工程と確定した作業工程とがある場合に機器#1の動作状態が一致する場合(動作状態に矛盾が生じていない場合)を説明する説明図および機器#1の動作状態が不一致の場合(動作状態に矛盾を生じる場合)を説明する説明図である。   FIG. 12 is an explanatory diagram for explaining the coincidence and disagreement of the operation state in the first determination. FIGS. 12A and 12B are respectively an unconfirmed work process illustrated in FIG. An explanatory diagram for explaining the case where the operation state of the device # 1 matches when there is a confirmed work process (when there is no contradiction in the operation state) and the case where the operation state of the device # 1 does not match (the operation state is changed) It is explanatory drawing explaining the case where a contradiction arises.

なお、図12に示される黒丸印は、アイソレーションを実行する場合におけるアイソレーション状態の開始点であり、黒菱形印は、アイソレーションから復旧した状態(復旧状態)の開始点である。   In addition, the black circle mark shown in FIG. 12 is the start point of the isolation state when performing isolation, and the black rhombus mark is the start point of the state (restoration state) restored from the isolation.

第1の判定(ステップS12)では、まず、第1の機器動作状態矛盾判定部23aが、仮工事計画情報31を参照し、計画する追加の作業工程におけるアイソレーションの対象となる機器について、作業日時および機器の動作状態を取得する一方、確定工事計画情報32を参照し、既に確定した工事計画におけるアイソレーション対象となる機器について、作業日時および機器の動作状態を取得する。   In the first determination (step S12), first, the first device operation state contradiction determination unit 23a refers to the temporary work plan information 31 and performs an operation on a device to be isolated in an additional work process to be planned. While acquiring the date and time and the operating state of the equipment, the work date and time and the operating state of the equipment are acquired for the equipment to be isolated in the already determined construction plan with reference to the confirmed construction plan information 32.

続いて、第1の機器動作状態矛盾判定部23aは、アイソレーション対象となる機器について、確定工事計画情報32を参照し、既に作業工程が確定している工事計画の工程票から追加の作業工程におけるアイソレーションの対象となる機器が同一であって、作業日時の少なくとも一部が重複する工程票が存在するかを検索する。例えば、図11に示されるように、追加の作業工程におけるアイソレーションの対象となる機器が同一であって、作業日時の少なくとも一部が重複する工程票として、第1の機器動作状態矛盾判定部23aが工程票A、工程票Bおよび工程票Cを抽出したものとする。   Subsequently, the first equipment operation state contradiction determination unit 23a refers to the confirmed construction plan information 32 for the equipment to be isolated, and adds an additional work process from the work plan process slip for which the work process has already been confirmed. It is searched whether there are process slips that have the same device to be isolated and have at least part of the work date and time duplicated. For example, as shown in FIG. 11, the first device operation state contradiction determining unit is used as a process slip in which the devices to be isolated in the additional work process are the same and at least a part of the work date and time is duplicated. It is assumed that 23a has extracted the process slip A, the process slip B, and the process slip C.

続いて、第1の機器動作状態矛盾判定部23aは、未確定の作業工程に関する工程票Xと抽出した確定の作業工程に関する工程票の各々、すなわち工程票A、工程票Bおよび工程票Cの各々について、重複するタイミングの端点における機器の動作状態を比べる。   Subsequently, the first device operation state contradiction determining unit 23a includes each of the process slip X regarding the unconfirmed work process and the process slip regarding the extracted work process, that is, the process slip A, the process slip B, and the process slip C. For each, the operation state of the device at the end point of the overlapping timing is compared.

図12(A)に例示される工程票Xおよび工程票Aが表す重複するタイミングの端点は、重複が始まる重複開始点が日時tであり、重複が終わる重複終了点が日時tである。また、工程票Xおよび工程票Bが表す重複するタイミングの端点は、重複が始まる重複開始点が日時tであり、重複が終わる重複終了点が日時tである。 Endpoints of overlapping timing represented by step form X and step form A is illustrated in FIG. 12 (A), duplicate starting point overlap begins is time t 4, overlapping end point overlapping ends is a time t 7 . Also, the end points of the overlapping timing represented by step form X and step form B is overlapped starting point overlap begins is time t 3, overlapping the end point overlapping ends is time t 5.

工程票Xと工程票Aとについては、重複開始点tでは、機器#1の機器の動作状態が何れも「入」であり、重複終了点tでは機器#1の機器の動作状態が何れも「切」であるため、第1の機器動作状態矛盾判定部23aは、工程票Aが表す作業工程に対しては機器の動作状態が矛盾していない(一致)と判定する。また、工程票Xと工程票Bとについても、重複開始点tでは、機器#1の機器の動作状態が何れも「入」であり、重複終了点tでは機器#1の機器の動作状態が何れも「入」であるため、第1の機器動作状態矛盾判定部23aは、工程票Bが表す作業工程に対しては機器の動作状態が矛盾していない(一致)と判定する。 For a step form X a step form A, the overlap starting point t 4, an operation state of the equipment device # 1 are all "ON", the operation state of the apparatus of the overlapping end point t 7 the device # 1 is Since both are “OFF”, the first device operation state contradiction determination unit 23a determines that the operation state of the device is not inconsistent (matched) with respect to the work process represented by the process slip A. As for the a step form X and step form B, the overlap starting point t 3, is any operating state of the apparatus # 1 of the device "ON", the overlapping end point t 5 equipment # operation for one of the devices Since the states are both “ON”, the first device operation state contradiction determining unit 23a determines that the operation state of the device is not inconsistent (matched) with respect to the work process represented by the process slip B.

一方、工程票Xと工程票Cとについては、図12(B)に例示される工程票Xおよび工程票Cが表す重複するタイミングが、工程票Xが表す作業工程におけるアイソレーション状態の開始点かつ工程票Cが表す作業工程における復旧状態の開始点の日時tの一点となる。日時tにおける機器#1の機器の動作状態は、工程票Xが表す作業工程では「入」である一方、工程票Cが表す作業工程では「切」であるため、第1の機器動作状態矛盾判定部23aは、工程票Cが表す作業工程に対しては機器の動作状態が矛盾している(不一致)と判定する。 On the other hand, for the process slip X and the process slip C, the overlapping timing represented by the process slip X and the process slip C illustrated in FIG. 12B is the starting point of the isolation state in the work process represented by the process slip X and a single point of time t 2 of the beginning of the recovery state in the working step of step form C represents. Operation state of the equipment of the device # 1 at time t 2, while the work process steps votes X represents an "ON", since the work process of step form C represents a "OFF", the first device operating state The contradiction determination unit 23a determines that the operation state of the device is inconsistent (inconsistent) with respect to the work process represented by the process slip C.

図10に戻り、第1の判定(ステップS12)に続くステップS13以降の処理フローについて説明する。   Returning to FIG. 10, the processing flow after step S13 following the first determination (step S12) will be described.

第1の判定(ステップS12)の結果、確定している作業工程の各々に対して、未確定の作業工程の実施時において、共通する機器の動作状態が矛盾しない場合(ステップS13でNOの場合)、第2の機器動作状態矛盾判定部23bが、第2の判定を行う。   As a result of the first determination (step S12), when the undetermined work process is performed for each of the confirmed work processes, the operation state of the common device is consistent (in the case of NO in step S13) ), The second device operation state contradiction determination unit 23b performs the second determination.

第2の判定(ステップS14)は、第1の判定に対して、共通する機器の動作状態が矛盾するか否かを判定する対象となる工程が、運用工程情報34を参照して読み出す運用計画に沿う作業工程である点で相違するが、その他の点は実質的に第1の判定(ステップS12)と相違しない。従って、第2の判定(ステップS14)では、第1の判定(ステップS12)と同様にして、運用計画に沿う予定が確定している作業工程に対して、共通する機器の動作状態が作業工程の実行時において矛盾するか否かが判定される。   The second determination (step S14) is an operation plan that is read by referring to the operation process information 34 for a process to be determined as to whether or not the operation state of the common device is inconsistent with the first determination. However, the other points are not substantially different from the first determination (step S12). Therefore, in the second determination (step S14), as in the first determination (step S12), the operation state of the common device is the work process with respect to the work process in which the schedule according to the operation plan is fixed. It is determined whether or not there is a contradiction during the execution of.

第2の判定の結果、運用計画に沿う予定が確定している作業工程に対して、共通する機器の動作状態が作業工程の実行時において矛盾する場合(ステップS15でYESの場合)、続いて、方策有無判定部24が過去に実施済みの工事などで実際に行った方策をノウハウとして有しているか否(ノウハウが無い)かを判定する(第3の判定:ステップS16)。   As a result of the second determination, when the operation state of the common device is contradictory at the time of execution of the work process with respect to the work process for which the schedule according to the operation plan is confirmed, then, in the case of YES in step S15, Then, it is determined whether or not the policy presence / absence determination unit 24 has, as know-how, a policy actually performed in construction that has been performed in the past (third know-how: step S16).

方策有無判定部24がノウハウ情報(実際に行った実施済み工事情報)33を参照して方策の有無を判定した結果、方策が有る場合(ステップS16でYESの場合)、続いて、方策適用可否判定部25が、有ると判定した方策を適用する場合にプラントの保安規定を逸脱することなく順守することができるか否かを判定する(第4の判定:ステップS17)。なお、方策が複数個ある場合、方策適用可否判定部25は、複数個の中から選択を受け付け、受け付けた方策について第4の判定を行う。   When the policy presence / absence determination unit 24 refers to the know-how information (actually performed construction information) 33 and determines the presence / absence of the policy, if there is a policy (YES in step S16), then whether the policy is applicable or not When applying the policy determined to be present by the determination unit 25, it is determined whether or not compliance can be made without departing from the plant safety regulations (fourth determination: step S17). When there are a plurality of policies, the policy applicability determination unit 25 receives a selection from the plurality of policies, and performs a fourth determination on the received policies.

第4の判定の結果、プラントの保安規定を逸脱することなく順守することができる場合(ステップS17でYESの場合)、追加の作業工程は確定している作業工程と干渉しないと判定し(ステップS18)、第1の工事計画支援処理手順を終了する(END)。   As a result of the fourth determination, when it is possible to comply without departing from the plant safety regulations (YES in step S17), it is determined that the additional work process does not interfere with the confirmed work process (step S18), the first construction plan support processing procedure is terminated (END).

一方、第1の判定(ステップS12)の結果、確定している作業工程の各々に対して、未確定の作業工程の実施時において、共通する機器の動作状態が矛盾する場合(ステップS13でYESの場合)、第1の機器動作状態矛盾判定部23aは、追加の作業工程の日程などの再検討が必要と判定する(ステップS19)。再検討が必要である旨の判定結果は、ユーザが認識できるように、例えば、出力部22(図1)に出力される。   On the other hand, as a result of the first determination (step S12), when the unconfirmed work process is performed with respect to each of the confirmed work processes, the operation state of the common device is inconsistent (YES in step S13). In this case, the first device operation state contradiction determining unit 23a determines that it is necessary to review the schedule of the additional work process (step S19). The determination result indicating that the review is necessary is output to, for example, the output unit 22 (FIG. 1) so that the user can recognize it.

第1の機器動作状態矛盾判定部23aが再検討を必要と判定した後、第1の工事計画支援処理手順の処理フローは、ステップS19からステップS11に戻り、再検討後の新たな追加の作業工程の入力を受け付ける。   After the first equipment operation state contradiction determining unit 23a determines that reexamination is necessary, the process flow of the first construction plan support processing procedure returns from step S19 to step S11, and a new additional work after reexamination. Accepts process input.

また、第3の判定の結果において方策が無い場合(ステップS16でNOの場合)や第4の判定の結果においてプラントの保安規定を順守できない場合(ステップS17でNOの場合)、第1の工事計画支援処理手順の処理フローは、ステップS19に進み、さらにステップS11に戻る。すなわち、第3の判定の結果において方策が無い場合や第4の判定の結果においてプラントの保安規定を順守できない場合、追加の作業工程は日程などの再検討が必要という判定結果となり、プラント工事計画支援システム20は再検討後の新たな追加の作業工程の入力を受け付ける。   In addition, when there is no measure in the result of the third determination (NO in step S16) or in the case of failure to comply with the plant safety regulations in the result of the fourth determination (NO in step S17), the first construction The processing flow of the plan support processing procedure proceeds to step S19, and further returns to step S11. In other words, if there is no measure in the result of the third determination or if the plant safety regulations cannot be observed in the result of the fourth determination, the additional work process becomes a determination result that requires a reexamination of the schedule, etc. The support system 20 receives an input of a new additional work process after the review.

なお、上述した第1の工事計画支援処理手順は、第3の判定の結果において方策が有る場合、続いて第4の判定を行う例であるが、第1の工事計画支援処理手順は、必ずしも第4の判定を行うことを要さない。例えば、追加の作業工程に対して機器の動作状態が矛盾する場合に矛盾を回避する方策の有無を判定するまでに止めたり、矛盾を回避する方策の有無を判定した結果、矛盾を回避する方策が有る場合に矛盾を回避する方策を抽出してユーザに提示するまでに止めたりすることもできる。すなわち、少なくとも第3の判定を行えば、残りの処理ステップは必ずしも行うことを要しない。   The first construction plan support processing procedure described above is an example in which the fourth determination is subsequently performed when there is a policy in the result of the third determination, but the first construction plan support processing procedure is not necessarily the same. It is not necessary to perform the fourth determination. For example, if the operation status of the device is inconsistent with the additional work process, stop until determining whether there is a measure for avoiding the contradiction, or determine whether there is a measure for avoiding the contradiction. If there is a problem, it is possible to extract a measure for avoiding the contradiction and stop it before presenting it to the user. That is, if at least the third determination is made, the remaining processing steps are not necessarily performed.

図13および図14は、それぞれ、プラント工事計画支援システム20が行う工事計画支援処理手順の一例の処理の流れを示す流れ図(フローチャート)であり、図13が工事計画支援処理手順の第2の例としての第2の工事計画支援処理手順(ステップS31〜S37)、図14が工事計画支援処理手順の第3の例としての第3の工事計画支援処理手順(ステップS31,S32,S34〜S37,S39)である。なお、図13および図14中に示される、〇の内にIIIが記入されている記号は、処理フローを結合する結合子である。   FIG. 13 and FIG. 14 are flow charts (flow charts) showing an example of the construction plan support processing procedure performed by the plant construction plan support system 20, respectively. FIG. 13 shows a second example of the construction plan support processing procedure. FIG. 14 shows a third construction plan support processing procedure (steps S31, S32, S34 to S37) as a third example of the construction plan support processing procedure. S39). In FIG. 13 and FIG. 14, symbols in which III is written in circles are connectors that combine the processing flows.

第2の工事計画支援処理手順は、第1の工事計画支援処理手順に対して、さらに、作業エリアの干渉の有無を判定するステップを備える点で相違するが、その他の点については、実質的に相違しない。そこで、本手順の説明では、第1の工事計画支援処理手順の相違点を中心に説明し、重複する説明を省略する。   The second construction plan support processing procedure is different from the first construction plan support processing procedure in that it further includes a step of determining the presence or absence of interference in the work area. There is no difference. Therefore, in the description of this procedure, the description will focus on the differences in the first construction plan support processing procedure, and a duplicate description will be omitted.

第2の工事計画支援処理手順では、まず、第1の工事計画支援処理手順の処理ステップ(ステップS11〜S19:図10)が行われ(ステップS31:図13)、続いて、重要設備情報37の有無に応じた作業エリアの大きさを設定し、作業エリアの干渉の有無が判定される(第5の判定:ステップS34)。   In the second construction plan support processing procedure, first, the processing steps of the first construction plan support processing procedure (steps S11 to S19: FIG. 10) are performed (step S31: FIG. 13). The size of the work area corresponding to the presence or absence of the work area is set, and the presence or absence of interference in the work area is determined (fifth determination: step S34).

作業エリア干渉判定部26が作業エリアの干渉の有無を判定するにあたり、重要設備情報37が有る場合(ステップS32でYESの場合)、設備の重要度を考慮して作業エリアの大きさを設定した上で(ステップS33)、作業エリアの干渉の有無を判定する(ステップS34)。一方、重要設備情報37が無い場合(ステップS32でNOの場合)、作業エリア情報36に従い作業エリアの大きさを設定した上で作業エリアの干渉の有無を判定する(ステップS34)。   When the work area interference determination unit 26 determines the presence or absence of interference in the work area, if there is important equipment information 37 (YES in step S32), the size of the work area is set in consideration of the importance of the equipment. Above (step S33), the presence / absence of interference in the work area is determined (step S34). On the other hand, if there is no important equipment information 37 (NO in step S32), the size of the work area is set according to the work area information 36, and the presence / absence of interference in the work area is determined (step S34).

判定の結果、作業エリアの干渉が無い場合(ステップS35でNOの場合)、追加の作業工程は確定している作業工程と干渉しないと判定し(ステップS36)、第2の工事計画支援処理手順を終了する(END)。   As a result of the determination, when there is no interference in the work area (NO in step S35), it is determined that the additional work process does not interfere with the confirmed work process (step S36), and the second construction plan support processing procedure End (END).

一方、作業エリアが干渉する場合(ステップS35でYESの場合)、作業エリア干渉判定部26は、追加の作業工程について再検討が必要と判定する(ステップS37)。作業エリア干渉判定部26が再検討を必要と判定した後、第2の工事計画支援処理手順の処理フローは、ステップS37からステップS31に戻り、再検討後の新たな追加の作業工程の入力を受け付ける。   On the other hand, when the work area interferes (in the case of YES in step S35), the work area interference determination unit 26 determines that the additional work process needs to be reexamined (step S37). After the work area interference determination unit 26 determines that reexamination is necessary, the processing flow of the second construction plan support processing procedure returns from step S37 to step S31 to input a new additional work process after reexamination. Accept.

なお、上述した第2の工事計画支援処理手順は、第5の判定(ステップS34)の前に重要設備情報37を参照して設備の重要度を考慮し、設備の重要度を考慮した大きさを設定して作業エリアの干渉判定(第5の判定:ステップS34)を行う場合の例であるが、図14に例示される第3の工事計画支援処理手順のように、第5の判定(ステップS34)の後に別途設備の重要度の高低に応じた条件を考慮して作業エリアの干渉判定(第6の判定:ステップS39)を行うようにしてもよい。   The above-described second construction plan support processing procedure takes into account the importance of the equipment with reference to the important equipment information 37 before the fifth determination (step S34), and the size considering the importance of the equipment. Is the example of performing interference determination of the work area (fifth determination: step S34), but the fifth determination (step S34) illustrated in FIG. After step S34), the interference determination of the work area (sixth determination: step S39) may be performed in consideration of the condition according to the level of importance of the equipment.

また、第2の工事計画支援処理手順における重要度を考慮した作業エリアの大きさの設定(ステップS33)には、作業工程に係る機器が重要設備である場合、未確定の作業工程と確定している作業工程との間で、同一期間内の同一フロア内または同一建屋内の作業を禁止するなどの作業エリアの大きさを直接的には規定しないが、作業エリアの大きさに制約を加える条件(制約条件)を付加することによって、実質的に干渉を禁止する作業エリアの大きさを設定する場合も含まれる。   Further, in the setting of the size of the work area in consideration of the importance in the second construction plan support processing procedure (step S33), when the equipment related to the work process is an important facility, the work process is determined as an indeterminate work process. The size of the work area, such as prohibiting work on the same floor or in the same building within the same period, is not specified directly, but restricts the size of the work area. This includes a case where the size of the work area that substantially prohibits interference is set by adding a condition (constraint condition).

すなわち、上述した重要度を考慮した作業エリアの大きさの設定は、重要設備情報37に含まれる作業エリアの大きさの情報が複数個である場合(大きさの範囲が複数パターンの場合)に限定されるものではなく、1個(大きさの範囲が1パターンの場合)であっても、重要度の高低に応じて作業エリアの大きさを異にして設定可能な場合がある。   That is, the setting of the size of the work area in consideration of the importance described above is performed when there are a plurality of pieces of work area size information included in the important equipment information 37 (when the size range is a plurality of patterns). The number of work areas may be set differently depending on the level of importance even if there is one (when the size range is one pattern).

例えば、上述した図7(A)に示される作業エリア情報36において、作業エリアの大きさ情報は、各機器について1個である。ここで、機器#1と機器#nとが何れも重要設備であって、重要設備についての同一期間内の同一フロアの作業を禁止する制約条件を付加している場合、作業エリア干渉判定部26が重要設備情報37を参照して得られた重要度を考慮する場合、作業エリアの大きさを1階(1F)全体として設定したり(ステップS33)、作業エリア情報36の作業エリアの大きさ情報に基づく干渉判定(第5の判定:ステップS34)を行った後に、別途、付加した「同一期間内の同一フロアの作業を禁止する」制約条件に基づく条件判定(第6の判定:ステップS39)をしたりすることができる。   For example, in the work area information 36 shown in FIG. 7A described above, the work area size information is one for each device. Here, when both the device # 1 and the device #n are important facilities and a constraint condition for prohibiting the work on the same floor within the same period for the important facilities is added, the work area interference determination unit 26 When considering the importance obtained by referring to the important facility information 37, the size of the work area is set as the entire first floor (1F) (step S33), or the size of the work area of the work area information 36 is set. After performing interference determination based on information (fifth determination: step S34), a condition determination based on a separately added "prohibit work on the same floor within the same period" constraint condition (sixth determination: step S39) ).

このように、重要設備情報37に含まれる作業エリアの大きさ情報が1個であっても、プラント工事計画支援システム20では、制約条件を付加することによって、重要設備と非重要設備とで実質的に作業エリアの大きさの判定基準を変えて、作業エリアの干渉の有無を検討することができる。   As described above, even if the size information of the work area included in the important equipment information 37 is one, the plant construction plan support system 20 adds the constraint condition so that the important equipment and the non-important equipment are substantially separated. Thus, the presence or absence of interference in the work area can be examined by changing the criteria for determining the size of the work area.

以上、プラント工事計画支援システム20、第1から第3の工事計画支援処理手順および工事計画支援PGによれば、追加の作業工程が固定の作業工程と干渉するか否かについて検討することができ、さらに、追加の作業工程が固定の作業工程と干渉する場合であっても、過去に実施した工事計画により蓄積したノウハウの有無を確認し、有る場合にはそのノウハウを活用して保安規定を逸脱しない範囲で行うことができるか否かを検討することができる。従って、過去に実施した工事計画により蓄積したノウハウを活用することで保安規定を逸脱しない範囲で追加の作業工程が可能となる方策を提案するなど、従来よりも柔軟かつ幅広く工程を検討することができる。   As described above, according to the plant construction plan support system 20, the first to third construction plan support processing procedures, and the construction plan support PG, it is possible to examine whether the additional work process interferes with the fixed work process. In addition, even if the additional work process interferes with the fixed work process, it is confirmed whether there is any know-how accumulated in the past construction plan, and if there is, use that know-how to establish safety regulations. It is possible to examine whether or not it can be performed without departing from the scope. Therefore, by utilizing the know-how accumulated in the construction plan implemented in the past, it is possible to examine the process more flexibly and broadly than before, such as proposing measures that enable additional work processes without departing from the safety regulations. it can.

また、プラント工事計画支援システム20、第1から第3の工事計画支援処理手順および工事計画支援PGによれば、系統運用工程に応じて変化する重要機器設備など、流動的に変化する現場状況を考慮した工事計画の成立性を判定することができる。従って、流動的に変化する現場状況に対する検討不足に起因する工事計画の後戻りの発生を未然に防ぐことができる。   Moreover, according to the plant construction plan support system 20, the first to third construction plan support processing procedures, and the construction plan support PG, the on-site situation that changes dynamically such as important equipment facilities that change according to the system operation process can be obtained. The feasibility of the considered construction plan can be determined. Therefore, it is possible to prevent the occurrence of a work plan return due to a lack of examination of the field situation that changes dynamically.

さらに、プラント工事計画支援システム20、第1から第3の工事計画支援処理手順および工事計画支援PGによれば、重要設備に対して複数段階に分けて重要度を設定することもできるので、重要度の高低を考慮して工事計画の成立性を判定することができる。   Furthermore, according to the plant construction plan support system 20, the first to third construction plan support processing procedures, and the construction plan support PG, the importance can be set in a plurality of stages for the important equipment. The feasibility of the construction plan can be determined in consideration of the degree of degree.

なお、上述した実施形態において記載した各手法は、コンピュータに実行させることのできるプログラムとして、例えば、磁気ディスク、光ディスク、半導体メモリ等の記憶回路を有する記憶媒体に書き込んでプロセッサを有する各種装置に適用したり、通信媒体により伝送して各種装置に適用することもできる。   Note that each method described in the above-described embodiment is applied to various apparatuses having a processor by writing in a storage medium having a storage circuit such as a magnetic disk, an optical disk, or a semiconductor memory as a program that can be executed by a computer. Or can be applied to various devices by being transmitted by a communication medium.

また、上述した実施形態において説明した「プロセッサ」とは、例えば、専用または汎用のCPU、GPU(Graphics Processing Unit)、特定用途向け集積回路(Application Specific Integrated Circuit:ASIC)、プログラマブル論理デバイス(例えば、単純プログラマブル論理デバイス(Simple Programmable Logic Device:SPLD)、複合プログラマブル論理デバイス(Complex Programmable Logic Device:CPLD)、およびフィールドプログラマブルゲートアレイ(Field Programmable Gate Array:FPGA))等のプログラムを実行可能な演算処理回路を意味する。プロセッサは、記憶回路に保存されるプログラムを読み出して実行することにより、各種機能を実現する。   In addition, the “processor” described in the above-described embodiments includes, for example, a dedicated or general-purpose CPU, a GPU (Graphics Processing Unit), an application specific integrated circuit (ASIC), a programmable logic device (for example, Arithmetic processing circuits that can execute programs such as simple programmable logic devices (SPLD), complex programmable logic devices (CPLD), and field programmable gate arrays (FPGA) Means. The processor implements various functions by reading and executing a program stored in the storage circuit.

また、記憶回路にプログラムにプログラムを保存するかわりに、プロセッサを構成する回路内にプログラムを直接組み込むよう構成してもよい。この場合、プロセッサは回路内に組み込まれたプログラムを読み出して実行することで各種機能を実現する。   Further, instead of storing the program in the storage circuit, the program may be directly incorporated in the circuit constituting the processor. In this case, the processor implements various functions by reading and executing a program incorporated in the circuit.

さらに、複数の独立したプロセッサを組み合わせてプログラムを実行可能な演算処理回路を構成し、各プロセッサがプログラムを実行することにより各機能を実現してもよい。プロセッサが複数設けられる場合、プログラムを記憶する記憶回路は、プロセッサごとに個別に設けられてもよいし、複数のプロセッサの機能に対応するプログラムを幾つか集約して設けてもよい。   Further, an arithmetic processing circuit capable of executing a program may be configured by combining a plurality of independent processors, and each function may be realized by each processor executing the program. In the case where a plurality of processors are provided, the storage circuit for storing the program may be provided for each processor individually, or several programs corresponding to the functions of the plurality of processors may be provided collectively.

なお、本発明は上述した実施形態そのままに限定されるものではなく、実施段階では、上述した実施例以外にも様々な形態で実施することができる。本発明は、発明の要旨を逸脱しない範囲で、種々の省略、追加、置き換え、変更を行うことができる。これら実施形態やその変形は、発明の範囲や要旨に含まれるとともに、特許請求の範囲に記載された発明とその均等の範囲に含まれる。   Note that the present invention is not limited to the above-described embodiments as they are, and can be implemented in various forms other than the above-described examples in the implementation stage. The present invention can be variously omitted, added, replaced, and changed without departing from the gist of the invention. These embodiments and modifications thereof are included in the scope and gist of the invention, and are included in the invention described in the claims and the equivalents thereof.

20…プラント工事計画支援システム、21…入力部、22…出力部、23…機器状態矛盾判定部、23a…、23b…、24…方策有無判定部、25…方策適用可否判定部、26…作業エリア干渉判定部、28…記憶部、29…制御部、31…仮工事計画情報、32…確定工事計画情報、33…ノウハウ情報、34…運用工程情報、35…保安規定情報、36…作業エリア情報、37…重要設備情報、38…判定結果情報、…、43…開閉弁、45(45a〜45d)…フロア、46…平面領域、47(47a)…分割平面領域、S…区分、L1…流体供給用のライン。   DESCRIPTION OF SYMBOLS 20 ... Plant construction plan support system, 21 ... Input part, 22 ... Output part, 23 ... Equipment state contradiction determination part, 23a ..., 23b ..., 24 ... Policy presence / absence determination part, 25 ... Policy applicability determination part, 26 ... Work Area interference determination unit, 28 ... storage unit, 29 ... control unit, 31 ... provisional construction plan information, 32 ... confirmed construction plan information, 33 ... know-how information, 34 ... operation process information, 35 ... safety regulation information, 36 ... work area Information 37 ... Important equipment information 38 ... Judgment result information 43 ... Open / close valve 45 (45a-45d) ... Floor 46 ... Planar area 47 (47a) ... Divided plane area S ... Section L1 ... Fluid supply line.

Claims (7)

1以上の系統を備えるプラントの未確定の工事計画における、工事日時の情報と前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む仮工事計画情報と、前記プラントの確定している工事計画における、工事日時の情報と前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む確定工事計画情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第1の矛盾判定部と、
前記仮工事計画情報と、前記系統の運用計画に沿う作業工程における日時および作業内容と、前記プラントを構成する機器のうち、前記作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む前記系統の運用工程情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第2の矛盾判定部と、
前記第2の矛盾判定部が前記機器の動作状態が矛盾すると判定した場合、前記系統の機能を喪失する最小単位で区分けした場合の区分を示す区分情報と、過去に実施した工事において前記区分の内部で実際に行った方策の情報と、前記機器の識別情報とが関連付けられているノウハウ情報を参照し、前記第2の矛盾判定部が前記機器の動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策の有無を判定する方策有無判定部とを具備し、
前記方策有無判定部は、動作状態が矛盾すると判定された前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策を、出力部に出力するように構成されることを特徴とするプラントの工事計画支援システム。
Temporary information including construction date and time information, identification information of devices constituting the plant, and isolation state information indicating an operation state of the device at the time of isolation in an unconfirmed construction plan for a plant having one or more systems Construction plan information, construction date and time information, identification information of equipment constituting the plant, and isolation state information indicating an operation state of the equipment at the time of isolation are included in the construction plan determined by the plant. A first contradiction determination unit that refers to the confirmed construction plan information and determines whether or not the operation state of the device is inconsistent;
The temporary construction plan information, the date and time in the work process according to the operation plan of the system, and the information indicating the operation state of each equipment required for performing the work process among the equipment constituting the plant A second contradiction determining unit that determines whether or not the operating state of the device is inconsistent with reference to the operation process information of the system including
When the second contradiction determination unit determines that the operation state of the device is inconsistent, the division information indicating the division when the unit is divided by the minimum unit that loses the function of the system, and the classification information Reference is made to the know-how information in which the policy information actually taken inside is associated with the identification information of the device, and the second contradiction determination unit determines that the operation state of the device is inconsistent A policy presence / absence determination unit for determining the presence / absence of the policy actually performed in the classification,
The policy presence / absence determination unit is configured to output a policy determined to be present to the output unit when it is determined that there is a policy actually performed in a category to which the device determined to have an inconsistent operation state belongs. A plant construction planning support system.
前記方策有無判定部が、動作状態が矛盾すると判定された前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策の選択を受け付け、選択を受け付けた方策を適用する場合に、前記ノウハウ情報および前記機器の識別情報と前記プラントの保安規定が要求する前記機器の状態の情報とを含む保安規定情報を参照し、前記プラントの保安規定を逸脱しない範囲で前記方策を適用できるか否かを判定する方策適用可否判定部を具備する請求項1記載のプラントの工事計画支援システム。 When the policy presence / absence determination unit determines that there is a policy actually performed in the category to which the device determined to have an inconsistent operation state, the selection of the policy determined to be present is accepted, and the policy that has received the selection is applied In this case, referring to the safety regulation information including the know-how information, the identification information of the equipment, and the information on the state of the equipment required by the safety regulation of the plant, the policy within a range not deviating from the safety regulation of the plant. The plant construction plan support system according to claim 1, further comprising a policy applicability determination unit that determines whether or not the method can be applied. 作業に使用される機器の識別情報、位置情報、大きさ情報および作業期間情報を含む作業エリア情報を参照し、前記追加の作業工程が、前記系統の運用計画に沿う作業工程に対して、前記追加の作業工程が行われる作業期間内に作業エリアが干渉するか否かを判定する作業エリア干渉判定部を具備する請求項1または2に記載のプラントの工事計画支援システム。 With reference to work area information including equipment identification information, position information, size information and work period information used for work, the additional work process is the work process according to the operation plan of the system, The plant construction plan support system according to claim 1, further comprising a work area interference determination unit that determines whether or not the work area interferes within a work period in which the additional work process is performed. 前記作業エリア情報は、前記系統の運用計画に沿う作業工程のうち、前記プラントの保安規定に重要な設備機器として機能確保が要求される機器の識別情報をさらに含んでおり、
前記作業エリア干渉判定部は、前記プラントの保安規定に重要な設備機器として機能確保が要求される機器が使用されるエリアと前記追加の作業工程が行われる作業期間内に作業エリアが干渉するか否かを判定するように構成される請求項3記載のプラントの工事計画支援システム。
The work area information further includes identification information of a device whose function is required to be secured as an important equipment device in the safety regulations of the plant among the work processes along the operation plan of the system,
Whether the work area interference determination unit interferes with an area in which equipment required to secure a function as an important equipment for the safety regulations of the plant is used and a work area within a work period in which the additional work process is performed The plant construction plan support system according to claim 3, which is configured to determine whether or not.
前記第1の矛盾判定部、前記第2の矛盾判定部および方策有無判定部は、自己の判定結果を前記出力部に出力するように構成されており、
前記第1の矛盾判定部が前記機器の動作状態が矛盾すると判定した場合、前記第2の矛盾判定部が矛盾すると判定した場合、および前記第2の矛盾判定部によって動作状態が矛盾すると判定された前記機器が属する区分で実際に行った方策が無いと判定した場合の少なくとも何れかの場合、前記未確定の工事計画の見直しを要請する旨の情報を前記出力部に出力するように構成される請求項1から4の何れか1項に記載のプラントの工事計画支援システム。
The first contradiction determination unit, the second contradiction determination unit, and the policy presence / absence determination unit are configured to output their own determination results to the output unit,
When the first contradiction determination unit determines that the operation state of the device is contradictory, the second contradiction determination unit determines that the operation state is contradictory, and the second contradiction determination unit determines that the operation state is contradictory. In at least one of the cases where it is determined that there is no policy actually performed in the category to which the equipment belongs, the output unit is configured to output information to request the review of the unconfirmed construction plan. The plant construction plan support system according to any one of claims 1 to 4.
多段階に条件を判定する判定手段として機能させるコンピュータを用いて1以上の系統を備えるプラントの未確定の工事計画の妥当性を判定することによって前記プラントの工事計画を支援する方法であって、
前記判定手段が、前記プラントの未確定の工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む仮工事計画情報と、前記プラントの確定している工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む確定工事計画情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第1の矛盾判定ステップと、
前記判定手段が、前記仮工事計画情報と、前記系統の運用計画に沿う作業工程における日時および作業内容と、前記プラントを構成する機器のうち、前記作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む前記系統の運用計画情報とを参照し、前記機器の動作状態が矛盾する第2の矛盾判定ステップと、
前記判定手段が、前記第2の矛盾判定ステップで前記機器の動作状態が矛盾すると判定した場合、前記系統の機能を喪失する最小単位で区分けした場合の区分を示す区分情報と、過去に実施した工事において前記区分の内部で実際に行った方策の情報と、前記機器の識別情報とが関連付けられているノウハウ情報を参照し、前記機器の動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策の有無を判定する方策有無判定ステップと、
前記判定手段が、前記方策有無判定ステップで動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策を出力部に出力するステップとを備えることを特徴とするプラントの工事計画支援方法。
A method of supporting a construction plan of the plant by judging the validity of an unconfirmed construction plan of a plant having one or more systems using a computer that functions as a judging means for judging conditions in multiple stages,
The determination means includes provisional construction plan information including identification information of devices constituting the plant and isolation state information indicating an operation state of the devices at the time of isolation in the unconfirmed construction plan of the plant; In the confirmed construction plan of the plant, with reference to the confirmed construction plan information including the identification information of the equipment constituting the plant and the isolation state information indicating the operation state of the equipment at the time of isolation, A first contradiction determination step for determining whether or not the operating states of the devices are inconsistent;
The determination means includes the temporary work plan information, the date and time and the work content in the work process along the operation plan of the system, and the equipment that constitutes the plant, for each equipment that is necessary for performing the work process. A second contradiction determination step in which the operation state of the device is inconsistent with reference to the operation plan information of the system including information indicating the operation state;
When the determination means determines that the operation state of the device is inconsistent in the second contradiction determination step, classification information indicating a classification when the system is classified by a minimum unit that loses the function of the system, and implemented in the past Refers to know-how information associated with the policy information actually taken in the construction in the construction and the identification information of the equipment, and is actually used in the classification to which the equipment determined that the operation status of the equipment is inconsistent belongs. A policy presence / absence determination step for determining the presence / absence of a policy performed in
A step of outputting to the output unit the policy determined to be present when the determination means determines that there is a policy actually performed in the category to which the device that has been determined that the operation state is inconsistent in the policy presence / absence determination step; A plant construction plan support method characterized by comprising:
コンピュータを多段階に条件を判定する判定手段として機能させ、1以上の系統を備えるプラントの未確定の工事計画の妥当性を判定することによって前記プラントの工事計画を支援するプログラムであって、
前記判定手段が、前記プラントの未確定の工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む仮工事計画情報と、前記プラントの確定している工事計画における、前記プラントを構成する機器の識別情報とアイソレーション実行時の前記機器の動作状態を示すアイソレーション状態情報とを含む確定工事計画情報とを参照し、前記機器の動作状態が矛盾するか否かを判定する第1の矛盾判定ステップと、
前記判定手段が、前記仮工事計画情報と、前記系統の運用計画に沿う作業工程における日時および作業内容と、前記プラントを構成する機器のうち、前記作業工程を行う上で必要となる機器毎の動作状態を示す情報とを含む前記系統の運用計画情報とを参照し、前記機器の動作状態が矛盾する第2の矛盾判定ステップと、
前記判定手段が、前記第2の矛盾判定ステップで前記機器の動作状態が矛盾すると判定した場合、前記系統の機能を喪失する最小単位で区分けした場合の区分を示す区分情報と、過去に実施した工事において前記区分の内部で実際に行った方策の情報と、前記機器の識別情報とが関連付けられているノウハウ情報を参照し、前記機器の動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策の有無を判定する方策有無判定ステップと、
前記判定手段が、前記方策有無判定ステップで動作状態が矛盾すると判定した前記機器が属する区分で実際に行った方策が有ると判定した場合、有ると判定した方策を出力部に出力するステップとを備える手順を実行させることを特徴とするプラントの工事計画支援プログラム。
A program that supports a construction plan of the plant by functioning as a judging means for judging conditions in multiple stages and judging the validity of an unconfirmed construction plan of a plant having one or more systems,
The determination means includes provisional construction plan information including identification information of devices constituting the plant and isolation state information indicating an operation state of the devices at the time of isolation in the unconfirmed construction plan of the plant; In the confirmed construction plan of the plant, with reference to the confirmed construction plan information including the identification information of the equipment constituting the plant and the isolation state information indicating the operation state of the equipment at the time of isolation, A first contradiction determination step for determining whether or not the operating states of the devices are inconsistent;
The determination means includes the temporary work plan information, the date and time and the work content in the work process along the operation plan of the system, and the equipment that constitutes the plant, for each equipment that is necessary for performing the work process. A second contradiction determination step in which the operation state of the device is inconsistent with reference to the operation plan information of the system including information indicating the operation state;
When the determination means determines that the operation state of the device is inconsistent in the second contradiction determination step, classification information indicating a classification when the system is classified by a minimum unit that loses the function of the system, and implemented in the past Refers to know-how information associated with the policy information actually taken in the construction in the construction and the identification information of the equipment, and is actually used in the classification to which the equipment determined that the operation status of the equipment is inconsistent belongs. A policy presence / absence determination step for determining the presence / absence of a policy performed in
A step of outputting to the output unit the policy determined to be present when the determination means determines that there is a policy actually performed in the category to which the device that has been determined that the operation state is inconsistent in the policy presence / absence determination step; A construction plan support program for a plant, characterized by causing a procedure to be provided to be executed.
JP2017152352A 2017-08-07 2017-08-07 Plant construction plan support system, construction plan support method and construction plan support program Active JP6862309B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017152352A JP6862309B2 (en) 2017-08-07 2017-08-07 Plant construction plan support system, construction plan support method and construction plan support program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017152352A JP6862309B2 (en) 2017-08-07 2017-08-07 Plant construction plan support system, construction plan support method and construction plan support program

Publications (2)

Publication Number Publication Date
JP2019032642A true JP2019032642A (en) 2019-02-28
JP6862309B2 JP6862309B2 (en) 2021-04-21

Family

ID=65523452

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017152352A Active JP6862309B2 (en) 2017-08-07 2017-08-07 Plant construction plan support system, construction plan support method and construction plan support program

Country Status (1)

Country Link
JP (1) JP6862309B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020154820A (en) * 2019-03-20 2020-09-24 株式会社東芝 Isolation work planning assist system, method, and program

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62126406A (en) * 1985-11-27 1987-06-08 Hitachi Ltd Method and apparatus for backing up maintenance and control of plant
JPH096428A (en) * 1995-06-23 1997-01-10 Toshiba Corp Plant monitoring equipment
JP2009211164A (en) * 2008-02-29 2009-09-17 Toshiba Corp Plant maintenance plan support system and method
JP2010122053A (en) * 2008-11-19 2010-06-03 Toshiba Corp Periodic inspection process management system in nuclear power plant
JP2012208744A (en) * 2011-03-30 2012-10-25 Tokyo Electric Power Co Inc:The Process management system and process management method
US20140039648A1 (en) * 2012-08-01 2014-02-06 Saudi Arabian Oil Company System for inspection and maintenance of a plant or other facility

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62126406A (en) * 1985-11-27 1987-06-08 Hitachi Ltd Method and apparatus for backing up maintenance and control of plant
JPH096428A (en) * 1995-06-23 1997-01-10 Toshiba Corp Plant monitoring equipment
JP2009211164A (en) * 2008-02-29 2009-09-17 Toshiba Corp Plant maintenance plan support system and method
JP2010122053A (en) * 2008-11-19 2010-06-03 Toshiba Corp Periodic inspection process management system in nuclear power plant
JP2012208744A (en) * 2011-03-30 2012-10-25 Tokyo Electric Power Co Inc:The Process management system and process management method
US20140039648A1 (en) * 2012-08-01 2014-02-06 Saudi Arabian Oil Company System for inspection and maintenance of a plant or other facility

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020154820A (en) * 2019-03-20 2020-09-24 株式会社東芝 Isolation work planning assist system, method, and program
JP7118916B2 (en) 2019-03-20 2022-08-16 株式会社東芝 Isolation work planning support device, method and program

Also Published As

Publication number Publication date
JP6862309B2 (en) 2021-04-21

Similar Documents

Publication Publication Date Title
Abd Jamil et al. Contractual challenges for BIM-based construction projects: a systematic review
Sawhney et al. A modified FMEA approach to enhance reliability of lean systems
Haight et al. Safety management systems: comparing content & impact
US20210294307A1 (en) Assisted engineering design and development management system
US11853794B2 (en) Pipeline task verification for a data processing platform
US20100125528A1 (en) System and method to supplement and/or modify an iso quality system program to comply with nuclear power plant government regulation requirements and/or standards organization requirements
Hugo et al. The strategic value of human factors engineering in control room modernization
Rojas-Arce et al. The methodology for strategic plan implementation
JP2019032642A (en) Plant construction plan support system, construction plan support method and construction plan support program
Papachatzi et al. Risk management in construction projects using building information modelling
US9600245B2 (en) Computer-implemented method for generating control unit program code and message management environment relating thereto
Hugo Towards a unified HFE process for the nuclear industry
US20180247238A1 (en) Work range visualization device and work range visualization method
Matthei et al. The impact of implementing Building Information Modeling (BIM) on Occupational Health and Safety (OHS) during construction
Duffuaa et al. Turnaround maintenance
Bunyakiat et al. Resilience Techniques for an Automatic Car Parking System
Barbarosoglu Early Detection of Maintainability Issues in MEP Systems Using BIM
Pavych et al. Formation of recommendations for quality assurance software
Lowe¹ et al. Human Factors and Systems Interaction, Vol. 84, 2023, 300-307 AHFE
de Souza et al. The application of lean six sigma methodology in execution process, management and attribution of maintenance activities
Wotschke et al. Construction Auditing: Planning-Implementation-Use
Lowe et al. The Usage of 3D Building Information Management (BIM) and Digital Twin Models to Support the Identification and Management of Human Factors Integration Issues
Reiman et al. Safety Culture in Nuclear Power Plant Construction
Wahidi Charting Progress in the Software Acquisition Pathway
Higgins Fitness of simulation: advancing the application of discrete event simulation within the automotive industry

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20171127

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20171128

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200210

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201124

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20201222

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210215

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210302

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210331

R150 Certificate of patent or registration of utility model

Ref document number: 6862309

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150