JP2008121079A - 高炉炉壁の構築方法 - Google Patents

高炉炉壁の構築方法 Download PDF

Info

Publication number
JP2008121079A
JP2008121079A JP2006307522A JP2006307522A JP2008121079A JP 2008121079 A JP2008121079 A JP 2008121079A JP 2006307522 A JP2006307522 A JP 2006307522A JP 2006307522 A JP2006307522 A JP 2006307522A JP 2008121079 A JP2008121079 A JP 2008121079A
Authority
JP
Japan
Prior art keywords
furnace
stave
joint
furnace wall
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2006307522A
Other languages
English (en)
Other versions
JP5569948B2 (ja
Inventor
Masao Fujita
昌男 藤田
Takashi Ida
傑 井田
Takahiro Kumeta
隆弘 久米田
Kenichi Shimodaira
賢一 下平
Takumi Moriki
匠 森木
Takashi Maeda
貴志 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
JFE Refractories Corp
Original Assignee
JFE Steel Corp
JFE Refractories Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp, JFE Refractories Corp filed Critical JFE Steel Corp
Priority to JP2006307522A priority Critical patent/JP5569948B2/ja
Publication of JP2008121079A publication Critical patent/JP2008121079A/ja
Application granted granted Critical
Publication of JP5569948B2 publication Critical patent/JP5569948B2/ja
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

【課題】ステーブクーラまわりの炉壁構築作業を短期間のうちにかつ容易に行うことができると共に、それ自身強固で炉内ガス漏洩などの障害を招くことがない高炉炉壁の構築技術を提供することにある。
【解決手段】ステーブクーラ相互間で生じる目地および該ステーブクーラと鉄皮との間に生じる間隙に不定形耐火材料を充填するのに先立ち、隣接する該ステーブクーラの炉内側の面に布製シールテープを貼着して前記目地を塞ぎ、その後、ステーブクーラ相互間目地と該ステーブクーラと鉄皮との間の空隙に不定形耐火材料を充填する方法。
【選択図】図4

Description

本発明は、高炉炉壁の構築方法に関し、とくに、鉄皮内にステーブクーラを設置して炉壁を構築する際に、該ステーブクーラまわりの間隙内に不定形耐火材料を充填して炉壁の一部にするのに有効な方法を提案する。
従来、前記ステーブクーラ相互間に生じる目地、該ステーブクーラと鉄皮との間に形成される間隙内に、不定形耐火材料を充填して炉壁を構築する方法としては、特許文献1、2などにも開示されているが、不定形耐火材料の充填に先立ち、まず、ステーブクーラ相互間に、(a)シール用当板を取付ける方法、(b)金網を取付ける方法、(c)金属製の固定金物(シールプレート)を取付ける方法、などが知られている。
例えば、図1、図2は、上記(c)の金属製固定金物を使ってステーブクーラ相互間の目地を処理する方法を示している。この方法は、ステーブクーラ1、2相互間の目地Sに、隣接するステーブクーラ1、2間にかけ渡すように、溶接固定した止金3…に、取付けボルト4を介して短冊状の金属製シールプレート5を配設し、その後、その目地S内の金属プレート5まわりに不定形耐火材料(スタンプ材)を圧入して該目地Sを塞ぎ、しかる後、該ステーブクーラ1、2と鉄皮6との間に形成される間隙S中に、不定形耐火材料(流し込み材)を流し込んで充填して炉壁の構築を行う技術である。
特開平2−267205号公報 特開平7−278626号公報
従来技術による炉壁の構築、即ち、高炉の新設や改修時に、鉄皮と炉壁耐火れんがとの間に、ステーブクーラを設置したり、不定形耐火材料の吹き付けや流し込み、圧入充填によって炉壁を構築する技術は、以下に述べるような問題点があった。
従来技術は、ステーブクーラ相互間に、不定形耐火材料を充填するために短冊状の金属製のシールプレート5を設置する作業があり、とくに大型の高炉ではステーブクーラ1段の施工に3日も要していた。その上、該ステーブクーラ間に配設するシールプレートまわりに不定形耐火材料を圧入充填するのにも1日を要し、さらにその耐火材料の硬化にも2日を要していた。しかも、鉄皮6とステーブクーラ1、2との間に不定形耐火材料を流し込み施工したとき、流し込み材がしばしば洩れることがあった。即ち、その問題点をさらに詳しく述べると、以下のとおりである。
a.金属製シールプレートの施工は溶接などを伴う煩雑な工事であり、しかもそのシールプレート部への目地塞ぎのための不定形耐火材料の施工、養生、その後、鉄皮とステーブクーラとの間に生じる間隙中への不定形耐火材料の流し込み施工までに5〜6日の工事期間を必要とする。
b.目地部への不定形耐火材料の流し込み不良から、鉄皮とステーブクーラとの間の間隙に充填した流し込み材がしばしば漏洩し、流し込み施工のやり直しや漏洩した流し込み材の撤去作業等、工程進捗の障害になることが多い。
c.ステーブクーラ相互間の目地への不定形耐火材料の充填層の強度が低いため、操業開始の早い時期にこの充填層が炉内原料によって損傷し、これが炉内熱風ガスの通り道となり、ステーブクーラ損耗の起点となって、ステーブクーラの寿命を短かくする。
d.ステーブクーラ間の目地に配設する金属製シールプレートの施工は製缶工が行うが、その後の作業は築炉工の施工担当となるため、工事の連続性が損なわれ、施工期間の延長を招く。
e.ステーブクーラ相互間の目地は、施工精度により±20mm前後の誤差があり、目地が広い場合は前記シールプレートの幅より広くなるため、鉄皮−ステーブクーラ間の間隙に不定形耐火材料を流し込んだときにその圧力に耐えられず、流し込み材の漏洩を招く一方、目地幅が狭い場合には、逆に、その金属製シールプレートが目地内に収まらず、現地でカットする必要が生じて施工作業が増える。
そこで、本発明の目的は、ステーブクーラまわりの炉壁構築作業を短期間のうちにかつ容易に、そして望ましい炉壁構造にすることができると共に、それ自身強固で炉内ガス漏洩などの障害を招くことがない高炉炉壁の構築技術を確立することにある。
従来技術の上記課題について検討するうちに、発明者らは、金網や金属製シールプレートを用いてステーブクーラ相互間の目地を仮に塞ぐ方法を改め、それらに代えて布製シールテープを用いることを思いついた。それは、従来の金属製シールプレートに代えて布地を用いると、上述した止金3やボルト4、さらには金属製シールプレート5を目地内に収容保持するという予備的な作業がない分だけ作業が簡易になると共に、不定形耐火材料の余分な水分を速やかに除去することができ、それ故にステーブクーラ間目地部の強固な封止を果すことができる。
本発明は、正に、このような知見に基づいて開発したものであって、高炉の鉄皮の内側にステーブクーラを設置すると共に、さらにその内側には耐火れんがを施工して炉壁を構築する方法において、該ステーブクーラ相互間で生じる目地および該ステーブクーラと鉄皮との間に生じる間隙に不定形耐火材料を充填するのに先立ち、隣接する該ステーブクーラの炉内側の面に布製シールテープを貼着して前記目地を塞ぎ、その後、ステーブクーラ相互間目地と該ステーブクーラと鉄皮との間の間隙に不定形耐火材料を充填することを特徴とする高炉炉壁の構築方法を要旨構成とする。
本発明において用いる前記布製シールテープは、吸水性が良好で柔軟な素材である天然繊維もしくは有機繊維もしくは無機繊維を使った織物、編物、不織布を用いることが好ましい。
また、前記布製シールテープをステーブクーラの炉内側(耐火れんが側)の面に貼着する際、鋼−布での接着力が大きな接着剤、即ち、接着剪断強さが100(N/cm)以上、好ましくは490(N/cm)以上の特性を示す接着剤を用いて接着固定することが好ましい。
以上説明した構成に係る本発明方法を採用した場合、
a.金属製シールプレートを用いる煩雑な設置作業や、目地耐火物の吹き付け施工を省略することができるから、迅速な施工が可能となり、施工時間の大幅な短縮が期待できる。
b.施工作業のすべてを築炉作業員だけで行うことができるようになるので、作業員の配置調整が容易となり、施工期間の短縮と施工費のコストダウンが図れる。
c.柔軟な素材である布製シールテープを使用するため、流し込み用不定形耐火材料の施工時に布製シールテープが膨らみ変形を起すことより、施工時の流し込み用不定形耐火材料の施工面レベルが管理可能となり、施工が容易になる。しかも、施工後、前記シールテープをはがして、流し込み用不定形耐火材料が確実に目地に充填しているかどうかを、直に確認することが可能になり、施工管理が容易であり、かつ施工壁の品質が大幅に向上する。
d.水浸透性が良好で柔軟ないわゆる吸水質可撓性のソフト布製シールテープを使用することにより、このシールテープに接触する流し込み用不定形耐火材料の水分をこのシールテープがよく吸収し揮散させるので、従来、弱点であったステーブクーラ間目地の炉内面側がより緻密で低水分の強固な目地を形成することができる。即ち、ステーブクーラ損耗の起点となる目地部耐火物の強度アップを果すことができ、ステーブクーラ寿命が大幅に向上する。
e.ステーブクーラ相互間の目地精度に影響されることなく、短時間で確実に流し込み用不定形耐火材料に対するシールが可能となる。
などの効果を得ることができる。
図3は、本発明の一実施形態を例示するものであり、鉄皮21と、この鉄皮から所定の間隔をおいて配置されるカーボンれんがなどからなる炉壁耐火れんが(図示省略)との間に、炉体冷却用ステーブクーラ22、23を設置したもようを示している。この図からも明らかなように、本発明は、上下・左右に隣り合うステーブクーラ22、23相互間で形成される目地S部分を塞ぐために、布製シールテープ24を利用する点に特徴がある。
即ち、本発明に係る構築方法では、まず、図4に示すように、鉄皮21の内側に配設されたステーブクーラ22、23間の目地Sの炉内側の部分を封塞するため、前記布製シールテープ25を該ステーブクーラ22、23の炉内側の面に接着剤24を介して接着する。なお、通常の目地の間隔は、20mm〜50mm程度であり、この程度の間隙を塞ぐには前記布製シールテープで十分な強度が得られる。
本発明方法では、次に、炉内側が前記布製シールプレートにて塞がれた目地Sを含め、このステーブクーラ22、23と鉄皮21との間隙Sの両方の空間に、流し込み用不定形耐火材料を一挙に流し込み施工し、または吹き付け施工などによって充填する。
なお、このステーブクーラ22、23の炉内側は、その後、炉壁耐火れんがを積み上げることにより完成された高炉の炉壁を構築することができる。
本発明において、特徴的な構成である布製シールテープとしては、柔軟なソフト素材である天然繊維もしくは有機繊維もしくは無機繊維を使った織物、編物、不織布などを用いることが好ましい。より好ましくは、吸水性が良好で柔軟なソフト素材である有機繊維もしくは無機繊維を使った織物、編物、不織布などを用いることが好ましい。すなわち、水浸透性の大きいシート状布を用いる。例えば、キャンバス(帆布)地やデニム地等の厚地の織物で吸水性の高いものが好適である。
このように、吸水性、即ち、水浸透特性の良好な布製シールテープ25を用いると、流し込み材である不定形耐火材料26中の水分が、この布製シールテープ25に隣接する部分から炉内側に脱水していくので、前記目地S中の不定形耐火材料の部分が緻密な充填耐火物となり、耐火物強度の上昇、ひいては耐火物寿命の向上に寄与する。
しかも、このとき、図4(c)に示すように、布製シールテープ25は、この素材の可撓製(柔軟性)に起因して、高水分含有不定形耐火材料を充填した時に、変形して炉内側に膨らむものの、該不定形耐火材料の脱水により収縮することから、この膨らみと収縮とがバランスして、所期した目地面を形成することができる。
なお、このような施工を担保するために、本発明では、前記布製シールテープ25をステーブクーラ22、23に強固に接着する必要がある。この要求に応えられる接着剤24としては、前記布製シールテープをステーブクーラの炉内側(耐火れんが側)に貼着する際、接着力(鋼―布)の大きな接着剤、好ましくは接着剪断強さが100(N/cm)程度以上、好ましく490(N/cm)以上の特性を示す接着剤を用いる。例えば、ポリアミドアミンを硬化剤とするエポキシ樹脂接着剤、変成脂肪族ポリアミンや変性ポリアミド樹脂、ポリアミドアミンを硬化剤とする変性エポキシ樹脂などの可撓性エポキシ樹脂が好適に用いられる。
上述した図3、図4に示す本発明に適合する方法で、ステーブクーラまわりの炉壁を構築したところ、大型高炉でのステーブクーラ1段当たりの不定形耐火材料充填施工作業期間が、従前は1週間かかっていたが、3日間で施工を終了することができた。また、ステーブクーラの寿命も一般には20〜25年であるが、本発明方法に従って施工したものでは、それ以上の寿命が期待できるものと推定される。
本発明は、高炉の炉壁構築方法であるが、前記吸水質可撓性の布製シールテープを使って目地をシールして流し込み用不定形耐火材料を充填するような他の冶金用炉の炉壁耐火物施工技術としても利用が可能である。
従来のステーブクーラ設置構造を示す部分斜視図である。 従来のステーブクーラまわりの炉壁構築方法の工程を説明する略線図である。 本発明のステーブクーラ設置構造を示す部分斜視図である。 本発明のステーブクーラまわりの炉壁構築方法の工程を説明する略線図である。
符号の説明
目地
鉄皮とステーブクーラとの間の間隙
21 鉄皮
22、23 ステーブクーラ
24 接着剤
25 布製シールテープ
26 不定形耐火材料(流し込み材)

Claims (3)

  1. 高炉の鉄皮の内側にステーブクーラを設置すると共に、さらにその内側には耐火れんがを施工して炉壁を構築する方法において、該ステーブクーラ相互間で生じる目地および該ステーブクーラと鉄皮との間に生じる間隙に不定形耐火材料を充填するのに先立ち、隣接する該ステーブクーラの炉内側の面に布製シールテープを貼着して前記目地を塞ぎ、その後、ステーブクーラ相互間目地と該ステーブクーラと鉄皮との間の間隙に不定形耐火材料を充填することを特徴とする高炉炉壁の構築方法。
  2. 前記布製シールテープは、柔軟な素材である天然繊維もしくは有機繊維もしくは無機繊維を使った織物、編物、不織布を用いることを特徴とする請求項1に記載の高炉炉壁の構築方法。
  3. 前記布製シールテープをステーブクーラの炉内側に貼着するには、接着剤を用いることを特徴とする請求項1または2に記載の高炉炉壁の構築方法。
JP2006307522A 2006-11-14 2006-11-14 高炉炉壁の構築方法 Active JP5569948B2 (ja)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006307522A JP5569948B2 (ja) 2006-11-14 2006-11-14 高炉炉壁の構築方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006307522A JP5569948B2 (ja) 2006-11-14 2006-11-14 高炉炉壁の構築方法

Publications (2)

Publication Number Publication Date
JP2008121079A true JP2008121079A (ja) 2008-05-29
JP5569948B2 JP5569948B2 (ja) 2014-08-13

Family

ID=39506155

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006307522A Active JP5569948B2 (ja) 2006-11-14 2006-11-14 高炉炉壁の構築方法

Country Status (1)

Country Link
JP (1) JP5569948B2 (ja)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
LU91455B1 (en) * 2008-06-06 2009-12-07 Wurth Paul Sa Gap-filler insert for use with cooling plates for a metallurgical furnace
KR100932737B1 (ko) 2009-03-23 2009-12-21 주식회사 한양 에프엔티 가열로 벽체의 형성방법
JP2011214076A (ja) * 2010-03-31 2011-10-27 Jfe Steel Corp 高炉炉壁の構築方法
JP2013224465A (ja) * 2012-04-20 2013-10-31 Nippon Steel & Sumikin Engineering Co Ltd 高炉羽口部充填材シール構造、高炉羽口部充填材シール方法および高炉羽口部構造
JP2016098428A (ja) * 2014-11-26 2016-05-30 新日鐵住金株式会社 高炉ステーブクーラー周辺への不定形耐火物の施工方法
CN107099633A (zh) * 2017-06-21 2017-08-29 山东钢铁股份有限公司 高炉筑炉勾缝设备
WO2020017152A1 (ja) * 2018-07-19 2020-01-23 日鉄エンジニアリング株式会社 ステーブおよびステーブの設置方法
CN110819750A (zh) * 2019-11-15 2020-02-21 上海宝冶集团有限公司 一种高炉及一种高炉炉壳与冷却壁用封堵装置

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863072B (zh) * 2019-11-29 2021-08-27 上海宝冶集团有限公司 高炉、炉缸及炉壳与冷却壁间灌浆封堵炉基煤气泄漏方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51132102A (en) * 1975-05-06 1976-11-17 Nippon Steel Corp A method of installing refractories for blast furnaces
JPS6257098U (ja) * 1985-09-27 1987-04-09
JPH0290643U (ja) * 1988-12-28 1990-07-18
JPH1025334A (ja) * 1996-07-09 1998-01-27 Shinko Kagaku Kogyo Kk 潜在性硬化型樹脂組成物及びこれを用いて形成した潜在性硬化型接着性シート

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51132102A (en) * 1975-05-06 1976-11-17 Nippon Steel Corp A method of installing refractories for blast furnaces
JPS6257098U (ja) * 1985-09-27 1987-04-09
JPH0290643U (ja) * 1988-12-28 1990-07-18
JPH1025334A (ja) * 1996-07-09 1998-01-27 Shinko Kagaku Kogyo Kk 潜在性硬化型樹脂組成物及びこれを用いて形成した潜在性硬化型接着性シート

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9039959B2 (en) 2008-06-06 2015-05-26 Paul Wurth S.A. Cooling plate arrangement and method for installing cooling plates in a metallurgical furnace
KR101642302B1 (ko) * 2008-06-06 2016-07-25 풀 부르스 에스.에이. 냉각판 배열 및 야금로의 냉각판 설치방법
KR101790675B1 (ko) * 2008-06-06 2017-10-26 풀 부르스 에스.에이. 냉각판 배열 및 야금로의 냉각판 설치방법
KR20110015468A (ko) * 2008-06-06 2011-02-15 풀 부르스 에스.에이. 냉각판 배열 및 야금로의 냉각판 설치방법
LU91455B1 (en) * 2008-06-06 2009-12-07 Wurth Paul Sa Gap-filler insert for use with cooling plates for a metallurgical furnace
RU2501864C2 (ru) * 2008-06-06 2013-12-20 Поль Вурт С.А. Система холодильной плиты и способ установки холодильных плит в металлургической печи
WO2009147251A1 (en) * 2008-06-06 2009-12-10 Paul Wurth S.A. Cooling plate arrangement and method for installing cooling plates in a metallurgical furnace
CN102057242A (zh) * 2008-06-06 2011-05-11 保尔伍斯股份有限公司 冷却板装置以及将冷却板安装到冶金炉中的方法
KR100932737B1 (ko) 2009-03-23 2009-12-21 주식회사 한양 에프엔티 가열로 벽체의 형성방법
JP2011214076A (ja) * 2010-03-31 2011-10-27 Jfe Steel Corp 高炉炉壁の構築方法
JP2013224465A (ja) * 2012-04-20 2013-10-31 Nippon Steel & Sumikin Engineering Co Ltd 高炉羽口部充填材シール構造、高炉羽口部充填材シール方法および高炉羽口部構造
JP2016098428A (ja) * 2014-11-26 2016-05-30 新日鐵住金株式会社 高炉ステーブクーラー周辺への不定形耐火物の施工方法
CN107099633A (zh) * 2017-06-21 2017-08-29 山东钢铁股份有限公司 高炉筑炉勾缝设备
WO2020017152A1 (ja) * 2018-07-19 2020-01-23 日鉄エンジニアリング株式会社 ステーブおよびステーブの設置方法
CN110819750A (zh) * 2019-11-15 2020-02-21 上海宝冶集团有限公司 一种高炉及一种高炉炉壳与冷却壁用封堵装置
CN110819750B (zh) * 2019-11-15 2021-08-06 上海宝冶集团有限公司 一种高炉及一种高炉炉壳与冷却壁用封堵装置

Also Published As

Publication number Publication date
JP5569948B2 (ja) 2014-08-13

Similar Documents

Publication Publication Date Title
JP5569948B2 (ja) 高炉炉壁の構築方法
RU2536720C2 (ru) Защитный элемент, бетонный элемент и способ изготовления бетонного элемента
CN112324475A (zh) 一种加固盾构隧道衬砌结构的方法
CN106704717B (zh) 套管缝隙封堵装置及封堵方法
CN105780940A (zh) 建筑物伸缩缝防渗漏结构
JP2006283485A (ja) 組石造外壁の改修工法
JP4076496B2 (ja) コンクリート養生装置
JP5691225B2 (ja) 高炉炉壁の構築方法
JP4800830B2 (ja) ステーブクーラーの炉内への取り付け工法
KR101326185B1 (ko) 터널공사용 방수시트 및 그 시공방법
CN107504816A (zh) 高温设备顶部结构的预制耐火衬里及其施工方法
JP2008184736A (ja) ひび割れ誘発目地構造の施工方法
JP3926804B2 (ja) オープンケーソン工法における底盤止水方法
CN112664208A (zh) 一种跨活动断层隧道减震缝结构、隧道结构及施工方法
JP7165022B2 (ja) 鋼製矢板継手部の遮水方法及び遮水構造
JP5166134B2 (ja) コンクリート構造物に於ける超高強度繊維補強コンクリート板の設置構造
CN107700540A (zh) 一种沉管半刚性节段接头防水体系及其水密检漏方法
JP2657943B2 (ja) トンネルコンクリートの止水強化工法
CN110195475A (zh) 一种混凝土结构大型水池缩缝防渗漏方法
WO2020017152A1 (ja) ステーブおよびステーブの設置方法
CN109371915A (zh) 一种矩形渠道的修复方法及修复结构
RU146803U1 (ru) Дымовая труба
KR101156217B1 (ko) 교량의 신축 이음 장치
CN206771992U (zh) 组合式弹性软密封
US11592128B2 (en) Sealing profile for embedding into a moulding of curable material

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091102

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20091127

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120124

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120131

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120329

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120717

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120918

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20130219

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20130403

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130423

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20130520

A912 Re-examination (zenchi) completed and case transferred to appeal board

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20130719

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140325

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140619

R150 Certificate of patent or registration of utility model

Ref document number: 5569948

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250