JP2005067813A - Lifting device and lifting method for winch of elevator - Google Patents

Lifting device and lifting method for winch of elevator Download PDF

Info

Publication number
JP2005067813A
JP2005067813A JP2003300327A JP2003300327A JP2005067813A JP 2005067813 A JP2005067813 A JP 2005067813A JP 2003300327 A JP2003300327 A JP 2003300327A JP 2003300327 A JP2003300327 A JP 2003300327A JP 2005067813 A JP2005067813 A JP 2005067813A
Authority
JP
Japan
Prior art keywords
hoisting machine
rope
lifting
hoistway
winch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003300327A
Other languages
Japanese (ja)
Inventor
Naoki Bando
直樹 阪東
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Elevator and Building Systems Corp
Original Assignee
Toshiba Elevator Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Elevator Co Ltd filed Critical Toshiba Elevator Co Ltd
Priority to JP2003300327A priority Critical patent/JP2005067813A/en
Publication of JP2005067813A publication Critical patent/JP2005067813A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a winch of an elevator as improvement of the conventional arrangement in which a lifting machine is installed right over a winch which is installed on the top of an uppermost guide rail, involving such a problem wherein it is not possible to secure the stroke enough to lift the winch to its installing position. <P>SOLUTION: A base bracket 9 is installed on the side face 4 of a pit in such a way as positioned over the winch installing position. A wire rope 19 with one end attached to the winch 8 is guided by a pulley device 13 installed on the bracket 9, and the other end of the wire rope 19 is led to the position below the winch installing position. The winch 8 is lifted to the installing position by drawing the other end of the wire rope 19 downward by a chain block 22 in the position. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、エレベータの巻上機を昇降路内に設置するために用いられる揚重治具及びこれを用いた揚重方法に関する。   The present invention relates to a lifting jig used for installing an elevator hoist in a hoistway and a lifting method using the lifting jig.

昇降路に設置される巻上機の揚重は、巻上機が最上段ガイドレールの背面に取り付けられる場合には、揚重機を巻上機設置位置の真上に取り付けても巻上機を吊り上げるためのストロークを確保することができるので、容易であった。   The hoisting machine installed in the hoistway can be lifted when the hoisting machine is mounted on the back of the uppermost guide rail, even if the hoisting machine is installed directly above the hoisting machine installation position. Since a stroke for lifting can be secured, it was easy.

従来のこのような場合の巻上機の揚重方法を図5を用いて説明する。まず、昇降路101の天井102に設置したフック103にチェーンブロック104を吊り下げ支持させ、このチェーンブロック104を用いて巻上機105を昇降路101内に取り込む。   A conventional lifting method of the hoisting machine in such a case will be described with reference to FIG. First, the chain block 104 is suspended and supported by a hook 103 installed on the ceiling 102 of the hoistway 101, and the hoisting machine 105 is taken into the hoistway 101 using the chain block 104.

次に、ガイドレール106を取り外し、昇降路101の天井102における巻上機設置位置付近の箇所に予め設置しておいた吊り元107にチェーンブロック108を吊り下げ支持させ、このチェーンブロック108を用いて巻上機105を設置位置まで引き込む。   Next, the guide rail 106 is removed, and the chain block 108 is suspended and supported by a suspension base 107 installed in advance near a hoisting machine installation position on the ceiling 102 of the hoistway 101, and this chain block 108 is used. Then pull the hoisting machine 105 to the installation position.

そして、ガイドレール106を元の位置に取り付け、巻上機105をガイドレール106の背面側に取り付ける。   Then, the guide rail 106 is attached to the original position, and the hoisting machine 105 is attached to the back side of the guide rail 106.

このように巻上機を最上段ガイドレールの背面側に取り付けるのではなく、最上段ガイドレールの上端にマシンベッドを介して取り付ける場合には、巻上機上面と昇降路天井との間の隙間の高さが300mm程度しかないため、巻上機設置位置の真上に揚重機を取り付けると、巻上機を設置位置まで揚重するだけのストロークを確保することができない。   When the hoisting machine is not attached to the back side of the uppermost guide rail in this way, but attached to the upper end of the uppermost guide rail via a machine bed, the clearance between the upper surface of the hoisting machine and the hoistway ceiling Since the height of the hoisting machine is only about 300 mm, if a lifting machine is attached directly above the hoisting machine installation position, a stroke sufficient to lift the hoisting machine to the installation position cannot be secured.

解決しようとする問題点は、ガイドレール上端に巻上機を設置する場合に巻上機設置位置の真上に揚重機を取り付けると、巻上機を設置位置まで揚重するだけのストロークを確保することができない点である。   The problem to be solved is that when a hoisting machine is installed at the upper end of the guide rail, if a hoisting machine is installed directly above the hoisting machine installation position, a stroke sufficient to lift the hoisting machine to the installation position is secured. It is a point that cannot be done.

本発明の揚重治具は、ガイドレール上端に設定された巻上機設定位置よりも上方に位置するように昇降路側面に設置されるベースブラケットと、一端が巻上機に取り付けられるロープと、前記ベースブラケット上に設けられ前記ロープを長手方向に案内すると共に前記ロープの他端側を下方に導く案内手段とを具備し、前記ロープの他端側を下方に引っ張ることにより巻上機が上昇するようにしたことを特徴とする。   The lifting jig of the present invention is a base bracket installed on the side of the hoistway so as to be positioned above the hoisting machine setting position set at the upper end of the guide rail, a rope with one end attached to the hoisting machine, A guide means provided on the base bracket for guiding the rope in the longitudinal direction and guiding the other end side of the rope downward; the hoisting machine is lifted by pulling the other end side of the rope downward; It was made to do.

本発明は、ベースブラケットを巻上機設置位置よりも上方に位置するように昇降路側面に設置し、ロープを案内手段により案内させてロープの他端側を巻上機設置位置よりも下方の位置に導き、該位置でロープの他端側を揚重機により下方に引っ張って巻上機を巻上機設置位置まで上昇させるようにすることにより、巻上機を設置位置まで揚重するだけのストロークを確保することができるので、巻上機を容易に揚重することができる。   In the present invention, the base bracket is installed on the side of the hoistway so as to be positioned above the hoisting machine installation position, the rope is guided by the guide means, and the other end side of the rope is lower than the hoisting machine installation position. Just lift the hoisting machine to the installation position by guiding it to the position and pulling the other end of the rope downward by the hoisting machine at that position to raise the hoisting machine to the hoisting machine installation position. Since the stroke can be secured, the hoisting machine can be easily lifted.

巻上機設置位置よりも下方の位置で揚重を行うという目的を簡単且つ安価な構成で実現した。   The purpose of lifting at a position below the hoisting machine installation position was realized with a simple and inexpensive configuration.

図1は本発明の第1実施例の揚重治具及び昇降路上部の斜視図、図2は図1の要部拡大図3は図1の要部拡大平面図である。図1において、1は乗りかごを案内するガイドレールとしての本線レール、2は釣り合いおもりを案内するガイドレールとしてのC/Wレールで、それぞれ昇降路内に垂直に設置されている。本線ガイドレール1は複数個のレールブラケット3を介して昇降路側面4に固定されている。本線レール1、C/Wレール2の上端にはベース5、6を介してマシンベッド7が取り付けられる。このマシンベッド7の上面が巻上機8の設置位置となる。   FIG. 1 is a perspective view of the lifting jig and the upper part of the hoistway according to the first embodiment of the present invention, FIG. 2 is an enlarged view of the main part of FIG. 1, and FIG. In FIG. 1, 1 is a main rail as a guide rail for guiding a car, and 2 is a C / W rail as a guide rail for guiding a counterweight, which are vertically installed in the hoistway. The main guide rail 1 is fixed to the hoistway side surface 4 via a plurality of rail brackets 3. A machine bed 7 is attached to the upper ends of the main rail 1 and the C / W rail 2 via bases 5 and 6. The upper surface of the machine bed 7 is the installation position of the hoisting machine 8.

9はベースブラケットで、昇降路側面4の上部で巻上機8の設置位置の上方に設置される。ベースブラケット9は、昇降路側面4に固定される取付板10と、一端が取付板10の上端に左右対称に固定されると共に昇降路側面4に直交する方向に突出した左右一対のアーム11と、これらの上面間に架け渡された支持板12とを備えている。各アーム11は一対の断面L字形のレール状部材を組み合わせることにより構成されている。   A base bracket 9 is installed above the hoistway side surface 4 and above the installation position of the hoisting machine 8. The base bracket 9 includes a mounting plate 10 that is fixed to the hoistway side surface 4, and a pair of left and right arms 11 that have one end fixed to the upper end of the mounting plate 10 symmetrically and protrude in a direction perpendicular to the hoistway side surface 4. , And a support plate 12 spanned between the upper surfaces. Each arm 11 is configured by combining a pair of rail-shaped members having an L-shaped cross section.

支持板12上には案内手段としての滑車装置13が取り付けられている。この滑車装置13は、図2に示すように、滑車14と、この滑車14を回転自在に軸支する左右一対の軸受板15とからなっている。軸受板15の底壁には昇降路側面9と直交する方向に延びる長孔16(図3参照)が形成されている。各軸受板15はボルト17を介して支持板12に固定されていて、ボルト17を緩めることで長孔16の長手方向(昇降路側面4に接離する方向)に移動させることができる。このようにすることで、昇降路寸法が異なる複数の現場に一つの機種で対応することが可能となる。   On the support plate 12, a pulley device 13 as a guide means is attached. As shown in FIG. 2, the pulley apparatus 13 includes a pulley 14 and a pair of left and right bearing plates 15 that rotatably support the pulley 14. A long hole 16 (see FIG. 3) extending in a direction orthogonal to the hoistway side surface 9 is formed in the bottom wall of the bearing plate 15. Each bearing plate 15 is fixed to the support plate 12 via a bolt 17, and can be moved in the longitudinal direction of the long hole 16 (direction contacting and separating from the hoistway side surface 4) by loosening the bolt 17. By doing in this way, it becomes possible to respond | correspond to the some site where hoistway dimensions differ with one model.

また、各軸受板15にはロープ外れ止め手段18が設けられている。このロープ外れ止め手段18は、滑車14の外周部に巻き掛けられたワイヤロープ19(後述)が衝撃で滑車14の外周部から外れるのを防ぐためのもので、図3に示すように、両端にネジが形成された直線状の棒体18aと、その両端に螺着されたナット18bとから成っている。棒体18aは両端を軸受板15に形成された貫通孔15aに貫通させて両端にナット18bを螺着することにより各軸受板15に取り付けられる。   Each bearing plate 15 is provided with rope detachment preventing means 18. This rope detachment prevention means 18 is for preventing a wire rope 19 (described later) wound around the outer peripheral portion of the pulley 14 from coming off from the outer peripheral portion of the pulley 14 due to an impact, as shown in FIG. It comprises a straight bar 18a having a screw formed on it and nuts 18b screwed to both ends thereof. The rod body 18a is attached to each bearing plate 15 by passing both ends through through holes 15a formed in the bearing plate 15 and screwing nuts 18b to both ends.

次に、巻上機8の揚重を行う手順を説明する。まず、昇降路側面4に、ベースブラケット9を、その横方向中心が巻上機8の吊り下げ支点と対向する位置で、且つ滑車14にワイヤロープ19を巻き掛けることができる範囲において、できるだけ高い位置に取り付ける。   Next, a procedure for lifting the hoisting machine 8 will be described. First, the base bracket 9 is placed on the hoistway side surface 4 at a position where the lateral center is opposed to the suspension fulcrum of the hoisting machine 8 and within a range in which the wire rope 19 can be wound around the pulley 14. Install in position.

この際、ベースブラケット9の昇降路側面4への取り付けは、RC構造(コンクリートで造られた建物)の場合はアンカーボルトで、鉄骨構造の場合は溶接で、レールブラケット3を取り付けているポストビーム(図示せず)に固定する。   At this time, the base bracket 9 is attached to the side surface 4 of the hoistway by an anchor bolt in the case of an RC structure (a building made of concrete) or by welding in the case of a steel structure. (Not shown).

本線レール1、C/Wレール2の上端にベース5、6を取り付け、その上にマシンベッド7を取り付ける。そして、滑車装置13のロープ外れ止め手段18を外し、ワイヤロープ19を滑車14の外周部に巻き掛ける。そして、ロープ外れ止め手段18を取り付けてワイヤロープ19が外れないようにする。   Bases 5 and 6 are attached to the upper ends of main rail 1 and C / W rail 2, and machine bed 7 is attached thereon. Then, the rope detachment preventing means 18 of the pulley device 13 is removed, and the wire rope 19 is wound around the outer peripheral portion of the pulley 14. Then, the rope detachment preventing means 18 is attached so that the wire rope 19 does not come off.

昇降路外で巻上機8の上面に吊り元プレート20を取り付け、揚重機等を使用して巻上機8を昇降路内に取り込む。ワイヤロープ19の一端を掛止部21に取り付け、ワイヤロープ19の他端側を支持板12に形成された貫通孔(図示せず)を介して下方に導く。   A lifting plate 20 is attached to the upper surface of the hoisting machine 8 outside the hoistway, and the hoisting machine 8 is taken into the hoistway using a lifting machine or the like. One end of the wire rope 19 is attached to the retaining portion 21, and the other end side of the wire rope 19 is guided downward through a through hole (not shown) formed in the support plate 12.

そして、マシンベッド7よりも下方においてワイヤロープ19の他端に揚重機としてのチェーンブロック22を取り付ける。また、マシンベッド7の2、3段下のレールブラケット3にワイヤロープ23を掛けて、このワイヤロープ23をチェーンブロック22の可動フック24に掛ける。   Then, a chain block 22 as a lifting machine is attached to the other end of the wire rope 19 below the machine bed 7. Further, a wire rope 23 is hung on the rail bracket 3 of the machine bed 7 two or three steps below, and the wire rope 23 is hung on the movable hook 24 of the chain block 22.

チェーンブロックは、ギヤを収納したケースの上下にフックが設けられ、揚重用と操作用のチェーンを備えていて、上部のフックを吊り元に掛け、もう一方のフックを吊り荷に掛けて操作用のチェーンを巻き上げることで吊り荷を揚重するように構成したものである。   The chain block is equipped with hooks on the top and bottom of the case that houses the gear, and is equipped with a chain for lifting and operation, and the upper hook is hung from the suspension source and the other hook is hung on the suspended load for operation. The suspended load is lifted by winding up the chain.

チェーンブロック22を巻き上げるとワイヤロープ19が下方に引っ張られて巻上機8が上昇する。巻上機8をマシンベッド7の位置まで上昇させてマシンベッド7の上面に取り付ける。   When the chain block 22 is wound up, the wire rope 19 is pulled downward and the hoisting machine 8 is raised. The hoisting machine 8 is raised to the position of the machine bed 7 and attached to the upper surface of the machine bed 7.

このように、巻上機設置位置よりも上方にチェーンブロックを設置せず、巻上機設置位置よりも下方の位置でワイヤロープ19の他端側をチェーンブロック22により下方に引っ張って巻上機8を揚重するようにしたため、巻上機8を設置位置まで揚重するだけのストロークを確保することができるので、巻上機8を容易に揚重することができる。   In this way, the chain block is not installed above the hoisting machine installation position, and the other end of the wire rope 19 is pulled downward by the chain block 22 at a position below the hoisting machine installation position. Since the hoisting machine 8 is lifted, a stroke sufficient to lift the hoisting machine 8 to the installation position can be secured, so that the hoisting machine 8 can be easily lifted.

なお、本発明の揚重治具をセットする作業は、昇降路側面4にベースブラケット9を設置し、ワイヤロープ19を滑車装置13により案内させると共にワイヤロープ19の他端側を巻上機設置位置の下方に導くだけであるので、時間もかからず容易に行うことができる。   The operation of setting the lifting jig according to the present invention is performed by installing the base bracket 9 on the side surface 4 of the hoistway, guiding the wire rope 19 by the pulley device 13, and setting the other end of the wire rope 19 at the hoisting machine installation position. Since it is only guided below, it can be performed easily without taking time.

また、本発明の揚重治具はシンプルな構造であるため、安価に製作することができる。   Moreover, since the lifting jig of the present invention has a simple structure, it can be manufactured at low cost.

また、本実施形態では、巻上機8の揚重を行った後に、ベースブラケット9を、昇降路上部に取り付ける巻上機8以外の機器(例えばトスランダー、ガバナー、ロープヒッチ等)の取り付け台として使用することもできるようになっており、部品点数の低減を図ることができる。   In the present embodiment, after lifting the hoisting machine 8, the base bracket 9 is used as a mounting base for equipment other than the hoisting machine 8 attached to the upper part of the hoistway (for example, toslander, governor, rope hitch, etc.). It can also be used, and the number of parts can be reduced.

次に、本発明の第2実施例を説明する。図4は第2実施例の揚重治具の要部拡大図である。なお、本実施例において、第1実施例と同一又は類似の部分には同一符号を用いており、重複する説明は省略してある。   Next, a second embodiment of the present invention will be described. FIG. 4 is an enlarged view of a main part of the lifting jig of the second embodiment. In the present embodiment, the same reference numerals are used for the same or similar parts as those in the first embodiment, and duplicate descriptions are omitted.

本実施例では、昇降路側面4にプレート25をアンカーボルトや溶接等により取り付け、このプレート25にベースブラケット9をボルト26で取り付けるようにしている。   In this embodiment, the plate 25 is attached to the hoistway side surface 4 by anchor bolts or welding, and the base bracket 9 is attached to the plate 25 with bolts 26.

このようにすることで、ベースブラケット9を所望の位置に取り付けることができるようになるため、一種類の揚重治具で複数機種のエレベータに対応することができる。揚重治具が複数種類有る場合には、昇降路に取り付ける揚重治具を間違える恐れが有るが、本実施例のようにすると、揚重治具は一種類しかなくなるので、そのような恐れがなくなる。   By doing in this way, since it becomes possible to attach the base bracket 9 to a desired position, it is possible to deal with a plurality of types of elevators with one type of lifting jig. When there are a plurality of types of lifting jigs, there is a possibility that the lifting jigs attached to the hoistway may be mistaken. However, as in the present embodiment, there is only one type of lifting jigs, so such fears are eliminated.

本発明の第1実施例の揚重治具及び昇降路上部の斜視図である。It is a perspective view of the lifting jig and hoistway upper part of 1st Example of this invention. 図1の要部拡大図である。It is a principal part enlarged view of FIG. 図1の要部拡大平面図である。It is a principal part enlarged plan view of FIG. 本発明の第2実施例の揚重治具の要部拡大図である。It is a principal part enlarged view of the lifting jig of 2nd Example of this invention. 従来の巻上機の揚重方法の説明図である。It is explanatory drawing of the lifting method of the conventional winding machine.

符号の説明Explanation of symbols

1 本線レール(ガイドレール)
2 C/Wレール(ガイドレール)
4 昇降路側面
8 巻上機
9 ベースブラケット
13 滑車装置(案内手段)
18 ロープ外れ止め手段
19 ワイヤロープ
22 チェーンブロック(揚重機)
1 Main rail (guide rail)
2 C / W rail (guide rail)
4 Side of hoistway 8 Hoisting machine 9 Base bracket 13 Pulley device (guide means)
18 Rope detachment prevention means 19 Wire rope 22 Chain block (lifter)

Claims (5)

ガイドレール上端に設定された巻上機設定位置よりも上方に位置するように昇降路側面に設置されるベースブラケットと、一端が巻上機に取り付けられるロープと、前記ベースブラケット上に設けられ前記ロープを長手方向に案内すると共に前記ロープの他端側を下方に導く案内手段とを具備し、前記ロープの他端側を下方に引っ張ることにより巻上機が上昇するようにしたことを特徴とするエレベータの巻上機の揚重治具。 A base bracket installed on the hoistway side so as to be positioned above the hoisting machine setting position set at the upper end of the guide rail, a rope having one end attached to the hoisting machine, and the base bracket provided on the base bracket And a guide means for guiding the rope in the longitudinal direction and guiding the other end side of the rope downward, and pulling the other end side of the rope downward to raise the hoisting machine. Lifting jig for elevator hoisting machine. 前記ベースブラケットが昇降路上部に設置される巻上機以外の機器の取付台を兼ねることを特徴とする請求項1記載のエレベータの巻上機の揚重治具。 2. The lifting jig for an elevator hoist according to claim 1, wherein the base bracket also serves as a mounting base for equipment other than the hoist installed at the upper part of the hoistway. 前記案内手段が前記ベースブラケットに対して前記昇降路側面に接離する方向に移動可能に取り付けられたことを特徴とする請求項1又は請求項2記載のエレベータの巻上機の揚重治具。 The lifting jig for an elevator hoisting machine according to claim 1 or 2, wherein the guide means is attached to the base bracket so as to be movable toward and away from the side surface of the hoistway. 前記案内手段から前記ロープが外れるのを防止するロープ外れ止め手段を設けたことを特徴とする請求項1乃至請求項3のいずれか一項に記載のエレベータの巻上機の揚重治具。 The lifting jig for an elevator hoisting machine according to any one of claims 1 to 3, further comprising rope detachment prevention means for preventing the rope from coming off from the guide means. 請求項1乃至請求項4のいずれか一項に記載の揚重治具を用いたエレベータの巻上機の揚重方法であって、前記ベースブラケットを巻上機設置位置よりも上方に位置するように昇降路側面に設置し、前記ロープを前記案内手段により案内させて前記ロープの他端側を巻上機設置位置よりも下方の位置に導き、該位置で前記ロープの他端側を揚重機により下方に引っ張って巻上機を巻上機設置位置まで上昇させることを特徴とするエレベータの巻上機の揚重方法。 The elevator hoisting method using the lifting jig according to any one of claims 1 to 4, wherein the base bracket is positioned above the hoisting machine installation position. Is installed on the side of the hoistway, the rope is guided by the guide means, and the other end of the rope is guided to a position below the hoisting machine installation position, and the other end of the rope is lifted at the position. And lifting the hoisting machine to the hoisting machine installation position by pulling downward by means of a lifting method for an elevator hoisting machine.
JP2003300327A 2003-08-25 2003-08-25 Lifting device and lifting method for winch of elevator Pending JP2005067813A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003300327A JP2005067813A (en) 2003-08-25 2003-08-25 Lifting device and lifting method for winch of elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003300327A JP2005067813A (en) 2003-08-25 2003-08-25 Lifting device and lifting method for winch of elevator

Publications (1)

Publication Number Publication Date
JP2005067813A true JP2005067813A (en) 2005-03-17

Family

ID=34405292

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003300327A Pending JP2005067813A (en) 2003-08-25 2003-08-25 Lifting device and lifting method for winch of elevator

Country Status (1)

Country Link
JP (1) JP2005067813A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007210744A (en) * 2006-02-09 2007-08-23 Toshiba Elevator Co Ltd Device and method for lifting elevator equipment
JP2008105773A (en) * 2006-10-23 2008-05-08 Kuma Lift Gijutsu Kenkyusho:Kk Conveying device and method
JP2011068439A (en) * 2009-09-24 2011-04-07 Toshiba Elevator Co Ltd Installation method and installation device of hoisting machine
JP7362022B1 (en) 2022-07-06 2023-10-17 フジテック株式会社 Support device for elevator lifting equipment and its fixing method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007210744A (en) * 2006-02-09 2007-08-23 Toshiba Elevator Co Ltd Device and method for lifting elevator equipment
JP2008105773A (en) * 2006-10-23 2008-05-08 Kuma Lift Gijutsu Kenkyusho:Kk Conveying device and method
JP2011068439A (en) * 2009-09-24 2011-04-07 Toshiba Elevator Co Ltd Installation method and installation device of hoisting machine
JP7362022B1 (en) 2022-07-06 2023-10-17 フジテック株式会社 Support device for elevator lifting equipment and its fixing method

Similar Documents

Publication Publication Date Title
JPH07100582B2 (en) Elevator work platform and elevator installation method
KR20070049968A (en) Method of constructing a lift installation, and lift installation for that purpose
JP2004509032A (en) Lifting tool for integrated elevator installation
JP5224238B2 (en) elevator
JP2009173386A (en) Installation device of elevator
JP4828084B2 (en) How to install the hoist
JP2007210703A (en) Device and method for installing hoist machine in machine-room-less elevator
JP2005067813A (en) Lifting device and lifting method for winch of elevator
JP2011132012A (en) Method of installing hoisting machine of elevator
JPWO2018138831A1 (en) Elevator installation method
JP4957287B2 (en) Elevator control cable fixing method
JP2008222382A (en) Method for moving lifting device for installation
JP2012046296A (en) Method of mounting elevator hoist
JP2008285260A (en) Guide rail installation engineering method of machine room-less elevator
KR101976724B1 (en) Method for installing elevator guide rails without a machine room
JP6382391B1 (en) Elevator counterweight frame reinforcement support device and elevator balance weight frame reinforcement mounting method
JP2009062177A (en) Elevator
JP2007186274A (en) Method for installing elevator hoistway top part equipment
JP2003292263A (en) Elevator apparatus lifting device and method
JPH082850A (en) Work method in elevator shaft
JP2005154116A (en) Terminal support device for elevator rope
JP2015030559A (en) Main rope fixing device for elevator, and repair method for elevator
JP4978218B2 (en) Elevator installation apparatus and installation method
JP2004026396A (en) Balance weight hoisting device for elevator system
JP2008195487A (en) Hanging fixture of rope-stopping mechanism for elevator