JP2005005213A - Power generation/hot water supplying cogeneration system including solid electrolyte fuel cell - Google Patents

Power generation/hot water supplying cogeneration system including solid electrolyte fuel cell Download PDF

Info

Publication number
JP2005005213A
JP2005005213A JP2003169694A JP2003169694A JP2005005213A JP 2005005213 A JP2005005213 A JP 2005005213A JP 2003169694 A JP2003169694 A JP 2003169694A JP 2003169694 A JP2003169694 A JP 2003169694A JP 2005005213 A JP2005005213 A JP 2005005213A
Authority
JP
Japan
Prior art keywords
power generation
hot water
water
combustion chamber
exhaust gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003169694A
Other languages
Japanese (ja)
Other versions
JP4508557B2 (en
Inventor
Takashi Shigehisa
高志 重久
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kyocera Corp
Original Assignee
Kyocera Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kyocera Corp filed Critical Kyocera Corp
Priority to JP2003169694A priority Critical patent/JP4508557B2/en
Publication of JP2005005213A publication Critical patent/JP2005005213A/en
Application granted granted Critical
Publication of JP4508557B2 publication Critical patent/JP4508557B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/30Hydrogen technology
    • Y02E60/50Fuel cells

Abstract

<P>PROBLEM TO BE SOLVED: To improve the utilization efficiency of resource by effectively utilizing the large amount of heat generated at a power generation system as many as possible, by improving a power generation /hot water supplying cogeneration system constructed by combining the hot water supplying system (4) with the power generation system (2) including a solid electrolyte fuel cell (22). <P>SOLUTION: Heat of an exhaust gas exhausted from a power generation/combustion chamber (16) in the power generation system (2) is used for heating an oxygen containing gas supplied to the fuel cell (22), after that, the heat is used for heating the water in the hot water supplying system (4), thus, the effective utilization efficiency of the heat of the exhaust gas is increased. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、固体電解質型燃料電池を含む発電システムに給湯システムを組み合わせた発電・給湯コジェネレーションシステムに関する。
【0002】
【従来の技術】
下記特許文献1には、固体電解質型燃料電池を含む発電システムに給湯システムを組み合わせた発電・給湯コジェネレーションシステムが開示されている。この発電・給湯コジェネレーションシステムにおいては、発電システムから排出される高温の排ガスと給湯システムにおける給湯槽に流入される水との間で熱交換するための熱交換手段が配設されている。従って、発電システムにおける排ガスの熱が給湯システムにおける水の加熱に利用され、かくして資源の利用効率を向上せんとしている。
【0003】
【特許文献1】
特開2001−325982公報
【0004】
【発明が解決しようとする課題】
上記特許文献1に開示されている発電・給湯コジェネレーションシステムにおいては、発電システムにおける排ガスの熱を給湯システムにおける水の加熱に利用しており、この点において資源の有効利用が図られている。しかしながら、固体電解質型燃料電池を含む発電システムにおいては、固体電解質型燃料電池の作動温度が相当高く、例えば1000℃程度である故に、相当多量の熱が生成される。そして、給湯システムにおける水を排ガスの熱を利用して加熱するのみでは、生成される多量の熱の一部が利用されるにすぎず、相当多量の熱が無駄にされている。
【0005】
本発明は上記事実に鑑みてなされたものであり、その主たる技術的課題は、固体電解質型燃料電池を含む発電システムに給湯システムを組み合わせた発電・給湯コジェネレーションシステムを改良して、発電システムにおいて生成される多量の熱を可及的に有効利用して資源の利用効率を一層向上することである。
【0006】
【課題を解決するための手段】
本発明によれば、上記主たる技術的課題を達成するために、発電システムにおける発電・燃焼室から排出される排ガスの熱を、固体電解質燃料電池に供給される酸素含有ガスの加熱に利用し、しかる後に給湯システムにおける水の加熱に利用し、かくして排ガスの熱の有効利用を増大する。
【0007】
即ち、本発明によれば、上記主たる技術的課題を達成する発電・給湯コジェネレーションシステムとして、
発電システムと給湯システムとを備え、
該発電システムは発電・燃焼室、該発電・燃焼室内に配設された複数個の固体電解質型燃料電池を含む電池スタック、該電池スタックに燃料ガスを供給するための燃料ガス供給手段、該電池スタックに酸素含有ガスを供給するための酸素含有ガス供給手段、及び該発電・燃焼室内から排ガスを排出するための排ガス排出手段を具備し、
該給湯システムは貯湯槽及び該貯湯槽に水を流入せしめる水流入手段を具備する、
発電・給湯コジェネレーションシステムにおいて、
該排ガス排出手段によって排出される排ガスと該酸素含有ガス供給手段によって該電池スタックに供給される酸素含有ガスとの間で熱交換せしめるための第一の熱交換手段、及び該排ガス排出手段によって排出される排ガスと該水流入手段によって該貯湯槽に流入される水との間で熱交換せしめるための第二の熱交換手段を備え、排ガスの流動方向に見て、該第一の熱交換手段は該第二の熱交換手段よりも上流に配設されている、ことを特徴とする発電・給湯コジェネレーションシステムが提供される。
【0008】
好ましくは、該燃料ガス供給手段は炭化水素系ガスを水素リッチな燃料ガスに改質せしめる改質手段を含み、該改質手段は該発電・燃焼室内に配設されており、該発電・燃焼室内の熱が改質に利用される。更に、該燃料ガス供給手段は水を蒸発せしめるための気化手段を含み、該気化手段も該発電・燃焼室内に配設されており、該発電・燃焼室内の熱が水の蒸発に利用されるのが好適である。該給湯システムは該貯湯槽から加熱水を流出するための加熱水流出手段を含み、該加熱水流出手段は流出せしめられる加熱水を必要に応じて常温水と混合して冷却するための混合手段、及び流出せしめられる加熱水を必要に応じて加熱するための加熱手段を有するのが好適である。
【0009】
【発明の実施の形態】
以下、添付図面を参照して、本発明に従って構成された発電・給湯コジェネレーションシステムの好適実施形態について詳細に説明する。
【0010】
図1は本発明に従って構成された発電・給湯コジェネレーションシステムの好適実施形態の全体的構成を簡略に示している。図示の発電・給湯コジェネレーションシステムは全体を番号2で示す発電システムと全体を番号4で示す給湯システムとを備えている。
【0011】
図1と共に図2を参照して説明すると、発電システム2は燃料電池組立体6を具備しており、この燃料電池組立体6は略直方体形状のハウジング8を含んでいる。ハウジング8は耐熱金属板から形成された外枠体10とこの外枠体10の内面に配設された断熱材層12とから構成されている。断熱材層12は適宜のセラミックから形成することができる。ハウジング8の下部には実質上水平に延在する仕切壁14が配設されており、ハウジング8は仕切壁14よりも上方の発電・燃焼室16と仕切壁14よりも下方の付属室18とに気密に区画されている。発電・燃焼室16内には3個の電池スタック20a、20b及び20cが並列配置されている。付属室18内には燃料ガスタンク21が配設されている。
【0012】
図2と共に図3を参照して説明を続けると、電池スタック20a、20b及び20cの各々は、鉛直方向、即ち図2において上下方向、図3において紙面に垂直な方向、に細長く延在する固体電解質型燃料電池22を図2において紙面に垂直な方向、図3において上下方向に複数個(図示の場合は5個)配置して構成されている。図3に明確に図示する如く、燃料電池22の各々は、電極支持基板24、内側電極層である燃料極層26、固体電解質層28、外側電極層である酸素極層30及びインターコネクタ32から構成されている。図2から理解される如く、燃料電池22の各々は仕切壁14上に直立せしめられており、発電・燃焼室16の上下方向中間部よりも幾分上方まで延びている。電極支持基板24は鉛直方向に細長く延びる板状片であり、平坦な両面と半円形状の両側面とを有する。電極支持基板24にはこれを鉛直方向に貫通する複数個(図示の場合は4個)のガス通路34が形成されている。かような電極支持基板24の各々は上記仕切壁14上に、例えば耐熱性に優れたセラミック接着剤によって接合される。仕切壁14には図2おいて左右方向及び紙面に垂直な方向に間隔をおいて左右方向に延びる複数個(図示の場合は15個)のスリット(図示していない)が形成されており、電極支持基板24の各々に形成されているガス通路34がスリットの各々に連通せしめられている。ハウジング8の下端部に区画されている付属室18に配設されている上記燃料ガスタンク21の上壁は仕切壁14によって規定されており、従って燃料ガスタンク21内は仕切壁14に形成されている上記スリットによって電極支持基板24の各々に形成されているガス通路34に連通せしめられている。インターコネクタ32は電極支持基板24の片面(図3の燃料電池スタック20aにおいて上面)上に配設されている。燃料極層26は電極支持基板24の他面(図3の燃料電池スタック20aにおいて下面)及び両側面に配設されており、その両端はインターコネクタ32の両端に接合せしめられている。固体電解質層28は燃料極層26の全体を覆うように配設され、その両端はインターコネクタ32の両端に接合せしめられている。酸素極層30は、固体電解質層28の主部上、即ち電極支持基板24の上記他面を覆う部分上、に配置され、電極支持基板板24を挟んでインターコネクタ32に対向して位置せしめられている。
【0013】
電池スタック20a、20b及び20cの各々における隣接する燃料電池22間には集電部材36が配設されており、一方の燃料電池22のインターコネクタ32と他方の燃料電池22の酸素極層30とを接続している。電池スタック20a、20b及び20cの各々において両端、即ち図3において上端及び下端に位置する燃料電池22の片面及び他面にも集電部材36が配設されている。そして、電池スタック20a及び20bの、図3において下端に配設された集電部材36は導電部材38によって接続され、電池スタック20b及び20cの、図3において上端に配設された集電部材36も導電部材38によって接続されている。更に、電池スタック20aの、図3において上端に配設された集電部材36には端子部材40が接続され、電池スタック20cの、図3において下端に配設された集電部材36にも端子部材40が接続されている。かくして、全ての燃料電池22が電気的に直列接続され、直列接続の両端には端子部材40が存在する。
【0014】
燃料電池22について更に詳述すると、電極支持基板24は燃料ガスを燃料極層26まで透過させるためにガス透過性であること、そしてまたインターコネクタ32を介して集電するために導電性であることが要求され、かかる要求を満足する多孔質の導電性セラミック(若しくはサーメット)から形成することができる。燃料極層26及び/又は固体電解質層28との同時焼成により電極支持基板24を製造するためには、鉄属金属成分と特定希土類酸化物とから電極支持基板24を形成することが好ましい。所要ガス透過性を備えるために開気孔率が30%以上、特に35乃至50%の範囲にあるのが好適であり、そしてまたその導電率は300S/cm以上、特に440C/cm以上であるのが好ましい。燃料極層26は多孔質の導電性セラミック、例えば希土類元素が固溶しているZrO(安定化ジルコニアを称されている)とNi及び/又はNiOとから形成することができる。固体電解質層28は、電極間の電子の橋渡しをする電解質としての機能を有していると同時に、燃料ガスと酸素含有ガスとのリークを防止するためにガス遮断性を有するものであることが必要であり、通常、3〜15モル%の希土類元素が固溶したZrOから形成されている。酸素極層30は所謂ABO型のペロブスカイト型酸化物からなる導電性セラミックから形成することができる。酸素極層30はガス透過性を有していることが必要であり、開気孔率が20%以上、特に30乃至50%の範囲にあることが好ましい。インターコネクタ32は導電性セラミックから形成することができるが、水素リッチなガスでよい燃料ガス及び空気でよい酸素含有ガスと接触するため、耐還元性及び耐酸化性を有することが必要であり、このためにランタンクロマイト系のペロブスカイト型酸化物(LaCrO系酸化物)が好適に使用される。インターコネクタ32は電極支持基板24に形成された燃料通路34を通る燃料ガス及び電極支持基板24の外側を流動する酸素含有ガスのリークを防止するために緻密質でなければならず、93%以上、特に95%以上の相対密度を有していることが望まれる。集電部材36は弾性を有する金属又は合金から形成された適宜の形状の部材或いは金属繊維又は合金繊維から成るフェルトに所要表面処理を加えた部材から構成することができる。導電部材38及び端子部材40は適宜の金属又は合金から形成することができる。
【0015】
図1及び図2を参照して説明を続けると、発電システム2は 、更に、電池スタック20a、20b及び20cに燃料ガスを供給するための燃料ガス供給手段42、電池スタック20a、20b及び20cに酸素含有ガスを供給するための酸素含有ガス供給手段44、及び燃料電池組立体6のハウジング8内に区画されている発電・燃焼室16内から排ガスを排出するための排ガス排出手段46を具備している。
【0016】
燃料ガス供給手段42は、都市ガスの供給ライン或いはプロパンガスボンベでよい燃料ガス供給源48に接続された供給ライン50を含んでおり、この供給ライン50には切断弁51及び流量制御手段52が配設されている。燃料ガス供給手段42は、上記燃料電池組立体6のハウジング8内に区画されている発電・燃焼室16の上端部に配置された改質手段54及び気化手段56も含んでいる(図2においては改質手段54及び気化手段56はブロックで簡略に図示している)。改質手段54は、燃料ガスの部分改質及び水蒸気改質に必要なそれ自体は周知の触媒を収容した改質室(図示していない)を有する。上記供給ライン50は発電・燃焼室16内に延び、改質手段54の入口に接続されている。改質手段54の出口はハウジング8の側壁内に形成されている連通路58及び接続管59を介して上記燃料ガスタンク21に接続されている。上記流量制御手段52の下流側において、上記供給ライン50には切断弁60を介して送風手段62が接続されている。燃料ガス供給手段42は、更に、上水供給ラインでよい水供給源64に接続された供給ライン66を含んでおり、この供給ライン66には切断弁68、浄水手段70及び流量制御手段72が配設されている。供給ライン66も発電・燃焼室16内に延びており、上記気化手段56の入口に接続されている。気化手段56の出口は改質手段54の上流側において上記供給ライン50に接続、従って供給ライン50を介して改質手段54に接続されている。後に更に言及する如く、供給ライン50を通して改質手段54に都市ガス或いはプロパンガスでよい燃料ガスが供給され、改質手段54において水素リッチな燃料ガスに改質された後に燃料ガスタンク21に供給され、そして燃料電池22、更に詳細にはその電極支持基板24に形成されているガス通路34に供給される。送風手段62は、例えば起動時等に必要に応じて作動されて(更に詳しくは、ハウジング8内に区画されている発電・燃焼室16内の温度が充分に上昇して気化手段56が所要気化を遂行し得る状態になるまでの間に作動されて)改質手段54に空気を供給する。発電システム2の正常運転時(即ちハウジング8内に区画されている発電・燃焼室16内の温度が充分に上昇して気化手段56が所要気化を遂行し得る状態の時)には、上水でよい水が浄水手段70によって所要浄化処理を受けた後に気化手段56に供給され、気化手段56においては水蒸気が生成され、かかる水蒸気が所謂水蒸気改質のために改質手段54に供給される。
【0017】
酸素含有ガス供給手段44は、燃料電池組立体6のハウジング8の側壁を貫通して発電・燃焼室16の下部に延びる酸素含有ガス導入管72まで延在する供給ライン74を含んでいる。供給ライン74の上流端には送風手段76が配設されている。供給ライン74には、更に、流量計78及び第一の熱交換手段80が配設されている。送風手段76が作動せしめられると、空気でよい酸素含有ガスが供給ライン74を通して流動せしめられて発電・燃焼室8内に流入せしめられ、燃料電池22に供給される。
【0018】
主として図2及び図3を参照して説明を続けると、後に更に言及するとおり、例えば燃料ガスを発電・燃焼室16内で燃焼せしめることによって発電・燃焼室16内の温度が所要温度以上になると、水素リッチな燃料ガスが燃料ガスタンク21から燃料電池22における電極支持基板24のガス通路34に供給されてガス通路34を上昇し、そしてまた酸素含有ガスが酸素含有ガス導入管72を通して発電・燃焼室16内に導入せしめられることに起因して、燃料電池22の各々においては、酸素極層30で下記式(1)の電極反応が生成され、また燃料極層26では下記式(2)の電極反応が生成されて発電される。そして、生成された電力は一対の端子部材40を通して取り出される。
【0019】
酸素極: 1/2O+2e→ O2−(固体電解質) ・・・(1)
燃料極: O2−(固体電解質)+H→ HO+2e・・(2)
【0020】
燃料電池22における電極支持基板24のガス通路34を流動する燃料ガスの、電極反応に使用されなかった燃料ガスは、電極支持基板24の上端から発電・燃焼室16内に流出せしめられ、流出と同時に燃焼せしめられる。酸素含有ガス導入管72を通して発電・燃焼室16に導入された酸素含有ガス中の酸素で電極反応に使用されなかったものは燃焼に利用される。発電・燃焼室16内は、燃料電池22での発電及び燃焼ガスの燃焼に起因して例えば1000℃程度の高温になる。而して、本発明に従って構成された図示の発電・給湯コジェネレーションシステムにおいては、燃料ガス供給手段42における改質手段54及び気化手段56が発電・燃焼室16内に配設されており、発電・燃焼室16内の高温が燃料ガスの改質に効果的に利用され、そしてまた水の気化にも効果的に利用されることが留意されるべきである。
【0021】
図1及び図2を参照して説明すると、上記排ガス排出手段46は、ハウジング8の側壁の上端部を貫通して延びる排ガス導出管84及びこの排ガス導出管84から延びる排出ライン86を含んでいる。排出ライン86は上記第一の熱交換手段80を通って延び、そして更に第二の熱交換手段88を通って延びる。第一の熱交換手段80においては排ガスの熱が発電・燃焼室16に供給される酸素含有ガスに伝導される。また、第二の熱交換手段88においては、後に更に言及する如く、排ガスの熱が給湯システム4における水の加熱に利用される。かくして、高温の排ガスが保有する熱が効果的に利用され、発電・給湯コジェネレーションシステムにおける熱効率及び資源有効利用率が充分に高い値にせしめられ得る。
【0022】
図4は発電システム2に配設されている電気的構成要素を簡略に図示している。電池スタック20a、20b及び20cは、昇圧チョッパ90、インバータ92及び連係リレー94を介して、商用電源システム96と並列的に例えば家庭の電力負荷に接続されている。商用電源システム96と負荷との間には、商用電源システムス96から負荷に供給されている電力量を計測するための電流変換器95が配設されている。また、図示の実施形態においては、電池スタック20a、20b及び20cには降圧チョッパ98及び充電器100を介して蓄電器102も接続されている。この蓄電器102は昇圧チョッパ103及び上記昇圧チョッパ90を介して上記インバータ92に接続されている。発電・給湯コジェネレーションシステムには種々の交流駆動機器及び直流駆動機器が配設されているが、図4においては説明の便宜上種々の交流駆動機器を一括して番号104で示し、種々の直流駆動機器を一括して番号106で示している。直流駆動機器106には平滑回路108が付設されている。発電システム2の起動時には、交流駆動機器104には商用電源システム96から直接交流を供給し、直流駆動機器106には商用電源システム96からの交流を平滑回路108を介して供給する。電池スタック20a、20b及び20cにおいて発電が開始されると、発電された電気を昇圧チョッパ90にて昇圧し、インバータ92によって交流に変換し連係リレー94を介して負荷に供給する。負荷に対して発電量が不充分である場合には、商用電源システム96からも負荷に電力供給される。また、蓄電器102が充分に充電されていない時には、発電された電気の少なくとも一部を降圧チョッパ98にて降圧して充電器100に供給し、蓄電器102を充電する。電池スタック20a、20b及び20cが発電している時には、直流駆動機器106には発電された電気を降圧チョッパ98を介して供給し、交流駆動機器104には発電された電気を昇圧チョッパ90及びインバータ92を介して供給する。蓄電器102は非常用であり、例えば発電システム2の起動時に商用電源システム96が停電した場合には、直流駆動機器106には蓄電器102から直接的に直流を供給し、交流駆動機器104には昇圧チョッパ103、昇圧チョッパ90及びインバータ92を介して交流を供給する。
【0023】
図1を参照して説明すると、給湯システム4は貯湯槽110を含んでおり、この貯湯槽110には水流入手段112と加熱水流出手段114とが付設されている。図示の実施形態における水流入手段112は一次供給ライン116及び二次供給ライン118を含んでいる。一次供給ライン116は上記水供給源64から貯湯槽110の底部まで延在せしめられている。この一次供給ライン116には減圧弁120が配設されており、この減圧弁120は貯湯槽110内の水圧を例えば1乃至2気圧でよい所定水圧に維持する。二次供給ライン118は貯湯槽110の底部から上記第二の熱交換手段88を通って貯湯槽110の上部まで延びている。この二次供給ライン118の上流部には送水ポンプ122が配設されている。送水ポンプ122が作動せしめられると、貯湯槽110の底部に存在する低温の水が二次供給ライン118を通して流動せしめられる。二次供給ライン118を流動する水は、第二の熱交換手段88において排ガスと熱交換して加熱され、貯湯槽110の上部に流入せしめられる。本発明に従って構成された発電・給湯コジェネレーションシステムにおいては、発電・燃焼室16から排出される高温の排ガスの熱が第一の熱交換手段80において酸素含有ガスの加熱に利用され、次いで第二の熱交換手段88において給湯システム4における水の加熱に利用され、かくして排ガスの熱が充分効果的に利用される。給湯システム4における水の所望加熱温度は発電システム2における酸素含有ガスの所望加熱温度よりも低く、従って給湯システム4における水の加熱に使用される第二の熱交換手段88は排ガスの流動方向に見て酸素含有ガスの加熱に使用される第一の熱交換手段80の下流に配置されている。
【0024】
図示の実施形態においては、一次供給ライン116および二次供給ライン118を配設し、一旦貯湯槽110の底部に加熱前の水を流入せしめ、しかる後に貯湯槽10の底部から水を流出せしめて加熱し、加熱した水を貯湯槽110の上部に流入せしめているが、所望ならば、一旦貯湯槽110に流入せしめることなく、水供給源64からの水を加熱した後に貯湯槽110に流入せしめることもできる。また、第二の熱交換手段88における熱交換によって排ガス中の水蒸気が少なくとも部分的に液化される場合、第二の熱交換手段88において生成された水を気化手段56に供給することもできる。
【0025】
加熱水流出手段114は、混合手段124及び加熱手段126が配設されている流出ライン128を含んでいる。混合手段124は分岐ライン130によって上記一次供給ライン116に接続されており、従って分岐ライン130及び一次供給ライン116を介して水供給源64に接続されている。貯湯槽110から流出せしめられる加熱水の温度が所要温度を超えている場合には、混合手段124において加熱水に水供給源64から供給される水が混合されて所要温度に低下せしめられ、しかる後に使用に供される。一方、貯湯槽110から流出せしめられる加熱水が所要温度よりも低い場合には、加熱水は混合手段124において水と混合せしめられることなく混合手段124を通過し、周知のガス式或いは電気式給湯器から構成することができる加熱手段126において所要温度に加熱され、しかる後に使用に供される。
【0026】
上述したとおりの発電・給湯コジェネレーションシステムには中央制御ユニットを含む制御手段(図示していない)も装備されており、かかる制御手段による制御の下に発電・給湯コジェネレーションシステムが作動せしめられる。発電・給湯コジェネレーションシステムの作動様式を要約して説明すると、次のとおりである。
【0027】
図5は、発電・給湯コジェネレーションシステムにおける発電システムの起動時の作動手順を示すフローチャートである。例えば適宜の操作パネル(図示していない)に配設されている起動スイッチ(図示していない)が閉成されることによって発電・給湯コジェネレーションシステムが起動されると、ステップn−1において初期化チェックが遂行されて、前回の作動停止状況が確認され、必要に応じて各種機器の初期化が遂行される。次いで、ステップn−2において、異常の有無がチェックされる。例えば、燃料ガス供給源48におけるガス圧力の異常、水供給源64における水圧の異常(これらの異常は周知の検出器によって検出することができる)等がチェックされる。そして、異常が検出された場合には、ステップn−3に進行して異常警告し、作動停止する。異常警告は、例えば操作パネルに装備された警告灯の点灯或いは警告ブザーの作動でよい。更に、未だ起動していないにもかかわらず火炎を検出及び/又は出力電流を検出し(火炎、出力電流の検出については後に更に言及する)、或いはガス漏れを検出した場合も、異常検出としてステップn−3に進行する。ガス漏れ検出ついて付言すると、例えば発電・燃焼室16から排出される排出ガス中に未燃焼の燃料ガスが含有されていることを検出した場合、或いは発電・燃焼室16を規定しているハウジング8を囲繞しているケース(図示していない)内に燃料ガスが存在していることを検出した場合に、ガス漏れと判別する。上記ステップn−2において異常が検出されなかった場合にはステップn−4に進行し、酸素含有ガス供給手段44における送風手段76を始動し、供給ライン74及び酸素含有ガス導入管72を通して発電・燃焼室16内に酸素含有ガスを供給する。次いで、ステップn−5に進行して燃料ガス供給手段42における送風手段62を始動し、ステップn−6に進行して切断弁60を開き、かくして供給ライン50を介した空気の供給を開始する。しかる後にステップn−7に進行し、発電・燃焼室16の上部に配設されている着火手段(図示していない)を始動する。着火手段は例えば放電式のものでよい。次いで、ステップn−8に進行して燃料ガス供給手段42における流量制御手段52による規定流量を所定値に設定し、ステップn−9に進行して切断弁51を開き、かくして供給ライン50を介する燃料ガスの供給を開始する。供給ライン50を介して供給される空気及び燃料ガスは改質手段54に進入し、改質手段54内においては所謂部分酸化改質が遂行される。次いで、改質された燃料ガスは連通路58,接続管59及び燃料ガスタンク21を通して燃料電池22のガス通路34に供給され、少なくとも一部は燃料電池22の上端から発電・燃焼室16内に放出される。そして、燃料電池22のガス通路34を通して発電・燃焼室16内に放出された燃料ガスと酸素含有ガス導入管72を通して発電・燃焼室16に導入された酸素含有ガスが着火手段によって着火され、発電・燃焼室16内で燃焼が開始される。
【0028】
次いで、ステップn−10に進行し、発電・燃焼室16内で開始された燃焼により発生する火炎を検出する。かかる火炎の検出は、それ自体は周知の火炎検出器によって例えば図2に符号A−1で示す部位にて火炎を検出することによって好都合に遂行することができる。ステップn−10において火炎を検出できなかった時、換言すれば発電・燃焼室16内において燃焼を開始することができなかった時には、作動停止手順を遂行する。即ち、ステップn−11において切断弁51を閉じ、ステップn−12において流量制御手段52における流量設定を解除(即ち零復帰)し、ステップn−13において切断弁60を閉じ、ステップn−14において送風手段62の作動を停止する。所望ならば、切断弁52を閉じた後に若干の時間間隔をおいて切断弁60を閉じ、かくすることによって供給ライン50、改質手段54、連通路58、接続管59、燃料ガスタンク21及び燃料電池22のガス通路34に存在する燃料ガスを空気によってパージすることができる。次いで、ステップn−15に進行して発電・燃焼室16内の燃焼ガスのパージを遂行する。即ち、燃料ガスの供給を停止した後も送風手段76を所定時間作動し続け、酸素含有ガスによって発電・燃焼室16内の燃料ガスをパージする。そして、ステップn−16に進行して送風手段76の作動を停止する。ステップn−17においては上述した起動手順が例えば3回でよい所定回数繰り返し試みられたか否かが判別される。起動手順が既に所定回数試みられた時にはステップn−18に進行して異常警告し、作動停止する。起動手順が所定回数以下である場合には、上記ステップn−1に戻る。
【0029】
上記ステップn−10において火炎が適切に検出された場合には、ステップn−19に進行し、燃料電池組立体6の所定部位の温度が所定値以上に上昇したか否かが判別される。かかる温度検出は、例えば気化手段56の特定部位A−2(かかる部位の温度が所定値以上になると、水を気化手段56に供給して気化せしめることが可能になる)、電池スタック20a、20b及び20cの中央部位A−3、そして更にハウジング8の外枠体10の側面近傍A−4で遂行し、夫々の部位で夫々別個の規定温度以上に上昇したか否かを判別するのが好適である。検出温度が所定値未満である場合には上記ステップn−10に戻る。検出温度が所定以上に上昇すると、ステップn−20において流量制御手段72による規定流量を所定値に設定し、ステップn−21において切断弁68を開き、かくして気化手段56への水の供給を開始する。次いで、ステップn−22において切断弁60を閉じ、ステップn−23において送風手段62を停止し、かくして供給ライン50への空気の供給を停止する。ステップn−20乃至23は燃料ガスの改質を部分酸化改質から水蒸気改質に変更するものである。
【0030】
燃料ガスの改質が水蒸気改質に変更された後においては、図6に図示する移行手順、即ち起動から通常作動への移行手順が遂行される。ステップn−24においては、各種異常の有無、例えば発電・燃焼室16内での燃焼の停止等、が判別される。そして、異常が発生した場合にはステップn−25に進行して切断弁51を閉じ、ステップn−26に進行して流量制御手段52における流量設定を解除し、かくして燃料ガスの供給を停止する。改質手段54及び燃料電池22に対する水蒸気の供給は継続され、これによって改質手段54に収容されている触媒および燃料電池22の急激な酸化が防止される。次いで、ステップn−27において上述した部位A−2、A−3及びA−4における検出温度が夫々所定値未満に低下したか否かが判別される。検出温度が所定値未満に低下すると、ステップn−28において切断弁60を閉じ、ステップn−29において流量制御手段72における流量設定を解除する。ステップn−30においては、各種ライン等における水蒸気が温度低下によって凝縮するのを回避するために、水蒸気パージを遂行する。かかる水蒸気パージは、燃料ガス供給手段42における送風手段62を所定時間作動せしめることによって好都合に遂行され得る。しかる後にステップn−31に進行して酸素含有ガス供給手段44における送風手段76を停止し、ステップn−32に進行して異常警告し、作動停止する。
【0031】
上記ステップn−24において異常が検出されなかった場合には、ステップn−33に進行して、上記部位A−3における検出温度が所定値を超えたか否か、換言すれば燃料電池22が適切に発電することができる温度に達したか否かが判別される。検出温度が所定値以下の場合は上記ステップn−24に戻る。検出温度が所定値を超えると、ステップn―34に進行して、発電・給湯コジェネレーションシステムにおける交流駆動機器104及び直流駆動機器106に対する電力供給を、商用電源システム96(又は蓄電器102)から電池スタック20a、20b及び20cが発電する電力に変更する(図4も参照されたい)。この際には、必要に応じて、送風手段76の駆動電力並びに流量制御手段52及び72における規定流量を、電力供給の変更に適した値に変更することができる。しかる後に、図7に図示する通常作動に移行する。
【0032】
図7を参照して説明を続けると、通常作動に移行すると、ステップn−35においてインバータ92の外部出力がONされて発電・給湯コジェネレーションシステムが商用電源システム96に接続される(図4も参照されたい)。次いで、ステップn−36において通常作動状態であることが、例えば操作パネル(図示していない)に配置されている通常作動表示ランプ(図示していない)を点灯することによって表示される。ステップn−37においては、電池スタック20a、20b及び20cに接続された電流計(図示していない)によって測定される発電電流値が読み取られる。次いで、ステップn−38において、商用電力システム96から負荷に供給されている電力量、即ち商用電力使用が読み取られる。しかる後にステップn−39に進行して、電池スタック20a、20b及び20cの発電量が負荷の必要電力量以上か否かが判別される。発電量が負荷の必要電力量よりも大きい場合にはステップn−40に進行し、インバータ92の出力を必要に応じて低減せしめて負荷の必要電力量に相当した値に設定し、インバータ92から商用電源システム96に電量が流入する所謂逆潮流の発生を回避する。次いで、ステップn−41に進行し、電池スタック20a、20b及び20cの中央部位A−3における検出温度が所定範囲内か否かが判別される。検出温度が所定範囲内である場合にはステップn−42に進行して、所定演算式に従って送風手段76の適正駆動電力並びに流量制御手段52及び72における適正規定流量が演算される。かかる演算にはステップn−37において読み取られた電流値も使用される。そして、演算された値に基いて、ステップn−43において送風手段76の駆動電力、従って酸素含有ガスの供給量が適正値に設定され、ステップn−44において流量制御手段72の設定流量、従って水の供給量が適正値に設定され、ステップn−45において流量制御手段52の設定流量、従って燃料ガスの供給量が適正値に設定される。
【0033】
上記ステップn−41で読み取られる検出温度が所定範囲未満である場合には、ステップn−46に進行して、所定演算式に従って送風手段76の適正駆動電力並びに流量制御手段52及び72における適正規定流量が演算される。かかる演算は検出温度を上昇せしめるための方策、例えば発電・燃焼室16内での燃焼を増大せしめるために燃料ガスの供給量を増大せしめる等、の方策が考慮されたものである。そして、演算された値に基いて、ステップn−47において送風手段76の駆動電力、従って酸素含有ガスの供給量が適正値に設定され、ステップn−48において流量制御手段72の設定流量、従って水の供給量が適正値に設定され、ステップn−49において流量制御手段52の設定流量、従って燃料ガスの供給量が適正値に設定される。上記ステップn−41で読み取られる検出温度が所定範囲を超える場合には、ステップn−50に進行して、所定演算式に従って送風手段76の適正駆動電力並びに流量制御手段52及び72における適正規定流量が演算される。かかる演算は検出温度を下降せしめるための方策、例えば酸素含有ガスの供給量を増大せしめて燃料電池22の冷却を助長する等、の方策が考慮されたものである。そして、演算された値に基いて、ステップn−51において送風手段76の駆動電力、従って酸素含有ガスの供給量が適正値に設定され、ステップn−52において流量制御手段72の設定流量、従って水の供給量が適正値に設定され、ステップn−53において流量制御手段52の設定流量、従って燃料ガスの供給量が適正値に設定される。次いで、ステップn−54に進行して各種異常の有無が判別される。異常が発生した場合には図8に示す手順に進行する。異常がない場合にはステップn−55に進行し、例えば操作パネル(図示していない)に配設されている停止スイッチ(図示していない)が閉成されることによって停止信号が生成されているか否かが判別される。停止信号が生成されていない場合には上記ステップn−36に戻る。一方、停止信号が生成されている場合には、図9に示す手順に進行する。
【0034】
上記ステップn−39において発電量が負荷の必要電力量より小さい場合には、発電量を増大すべき、上記ステップn−41乃至n−53と同様のステップn−56乃至n−68が遂行され、しかる後にステップn−69に進行してインバータ92の出力を増大せしめる。そして、上記ステップn−54に進行する。
【0035】
図8を参照して説明を続けると、上記ステップn−54において異常が検出された場合には、ステップn−70に進行してインバータ92の外部出力をOFFにし、発電・給湯コジェネレーションシステムを負荷から切り離す。次いで、ステップn−71に進行し、異常状態の如何に応じて待機モードに移行すべきか或いは停止モードに移行すべきかを判別する。例えば、上記ステップn−54における異常が火炎を検出しないことである場合には、検出部位A−3における温度も参照して検出温度が下限界(例えば620℃)以下である場合には停止モードに移行する。検出温度が下限界よりも高い場合には自然着火する可能性がある故に待機モードに移行する。異常状態がガス漏れ検知である場合には、ガス漏れ濃度に応じて判別する。例えば燃料ガスが都市ガスである場合、爆発下限界濃度の1/4を超えると停止モードに移行し、爆発下限界濃度の1/100乃至1/4である場合には待機モードに移行する。検出部位A−1、A−2及びA−3の温度異常に関しては、例えば夫々の検出部位に関する第一下限界値以下の場合には待機モードに移行し、第一下限界値よりも低い第二下限界値以下になると停止モードに移行する。同様に、例えば夫々の検出部位に関する第一上限界値以上の場合には待機モードに移行し、第一上限界値よりも高い第二上限界値以上になると停止モードに移行する。異常状態が商用電源システム96の停電の場合には待機モードに移行し、商用電源システム96に代えて発電・給湯コジェネレーションシステムにおける発電を利用することを可能にするのが望ましい。
【0036】
待機モードに移行すべき時には、ステップn−72に進行して発電電流値を読み取る。これに先立ち、必要に応じて 送風手段76の駆動電力並びに流量制御手段52及び72における規定流量を、待機モードに適した値に変更することができる。次いで、図7に図示するステップn−41乃至n−53同様のステップn−73乃至n−85が遂行される。しかる後にステップn−86に進行し、各種異常の有無が判別される。異常がない場合には上記ステップn−25に進行して通常作動に復帰する。ステップn−86において異常がある場合にはステップn−87に進行して待機モードに進行すべきか停止モードに進行すべきかが判別される。待機モードに進行すべき場合には上記ステップn−73に戻る。
【0037】
上記ステップn−71或いは上記ステップn−87において停止モードに移行すべき場合には、上記ステップn−25乃至n−32と同様のステップn−88乃至n−95を遂行して作動停止する。
【0038】
上記ステップn−55(図7)において停止信号がある場合には、図9に図示するステップn−96に進行し、インバータ92の外部出力をOFFにして発電・給湯コジェネレーションシステムを商用電源システム96から切り離す。次いで、ステップn−97において、停止信号が待機モードへの移行を指示する信号か作動停止を指示する信号かを判別する。待機モードへ移行すべき時には、図7に図示するステップn−72乃至n−87と同様のステップn−98乃至n−113が遂行される。停止モードへ移行すべき時には、図8に図示するステップn−88乃至n−95と同様のステップn−114乃至n−120が遂行され、作動停止される。
【0039】
図10は給湯システムの作動手順を示すフローチャートである。図示の実施形態においては、給湯システム自体の作動制御は発電・給湯システムにおける発電システムの作動制御とは独立して遂行される故に、発電システムに異常が発生して発電システムが停止せしめられている場合でも、給湯システムを作動せしめて給湯を実現することが可能である。給湯システムの作動は、例えば給湯のための蛇口(図示していない)が開栓されることを検知することによって開始される。ステップm−1においては、初期化チェックが遂行されて前回の作動停止状況が確認され、必要に応じて各種機器の初期化が遂行される。次いで、ステップm−2において異常の有無がチェックされる。例えば、水供給源64における水圧の異常、加熱手段126に対する供給ガス圧力の異常、商用電源システム96における漏電乃至停電等の異常がチェックされる。異常が検出された場合には、ステップm−3に進行して異常警告し、作動停止する。異常警告は、発電システムの場合と同様に、操作パネルに装備された警告灯或いは警告ブザーの作動でよい。ステップm−2において異常がなかった場合にはステップm−4に進行し、貯湯槽110内に収容されている湯の上部の温度、即ち給湯の際に貯湯槽110から送出される湯の温度が例えば60℃でよい所定値を超えているか否かが判別される。湯の温度が所定値を超えている場合には、ステップm−5に進行して混合手段124を作動せしめ、貯湯槽110からの湯を水供給源64と混合して所要温度に冷却して給湯する。湯の温度が所定値以下の場合には、ステップm−6に進行して加熱手段126を作動せしめ、貯湯槽110からの湯を所要温度に加熱して給湯する。ステップm−7においては、給湯を継続すべきか否かが判別される。給湯を継続すべき場合には、上記ステップm−2に戻る。蛇口が閉栓され給湯を停止すべき場合には、ステップm−8に進行して作動されていた混合手段124或いは加熱手段126の作動を停止し、作動停止する。給湯システム4に配設されている送水ポンプ122は、第二の熱交換手段88の下流側における二次供給ライン118内の水の温度に基いて制御することができる。この水の温度が所定範囲、例えば80乃至95℃、よりも低い場合には送水ポンプ88による送水量を低減せしめ、所定範囲よりも高い場合には送水ポンプ88による送水量を増大せしめる。
【0040】
【発明の効果】
本発明の発電・給湯コジェネレーションシステムによれば、発電システムにおいて生成される多量の熱を可及的に有効利用して資源の利用効率を充分に向上することができる。
【図面の簡単な説明】
【図1】本発明に従って構成された発電・給湯コジェネレーションシステムの主要構成要素を簡略に示すブロック線図。
【図2】図1の発電・給湯コジェネレーションシステムにおける発電・燃焼室を一部を簡略して示す断面図。
【図3】図2の発電・燃焼室内に配設されている電池スタックを示す断面図。
【図4】図1の発電・給湯コジネレーションシステムにおける電気的構成要素を簡略に示すブロック線図。
【図5】図1の発電・給湯コジェネレーションシステムにおける発電システムの、起動時の作動手順を示すフローチャート。
【図6】図1の発電・給湯コジェネレーションシステムにおける発電システムの、起動から通常作動への移行手順を示すフローチャート。
【図7】図1の発電・給湯コジェネレーションシステムにおける発電システムの、通常作動手順を示すフローチャート。
【図8】図1の発電・給湯コジネレーションシステムにおける発電システムの、異常検出時の作動手順を示すフローチャート。
【図9】図1の発電・給湯コジェネレーションシステムにおける発電システムの停止信号生成時の作動手順を示すフローチャート。
【図10】図1の発電・給湯コジェネレーションシステムにおける給湯システムの作動手順を示すフローチャート。
【符号の説明】
2:発電システム
4:給湯システム
6:燃料電池組立体
16:発電・燃焼室
20a:電池スタック
20b:電池スタック
20c:電池スタック
22:燃料電池
42:燃料ガス供給手段
44:酸素含有ガス供給手段
46:排ガス排出手段
54:改質手段
56:気化手段
80:第一の熱交換手段
88:第二の熱交換手段
110:貯湯槽
124:混合手段
126:加熱手段
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a power generation / hot water cogeneration system in which a hot water supply system is combined with a power generation system including a solid oxide fuel cell.
[0002]
[Prior art]
Patent Document 1 below discloses a power generation / hot water cogeneration system in which a hot water supply system is combined with a power generation system including a solid oxide fuel cell. In this power generation / hot water cogeneration system, heat exchange means for exchanging heat between the high-temperature exhaust gas discharged from the power generation system and the water flowing into the hot water tank in the hot water supply system is provided. Therefore, the heat of the exhaust gas in the power generation system is used for heating water in the hot water supply system, thus improving the resource utilization efficiency.
[0003]
[Patent Document 1]
JP 2001-325882 A
[0004]
[Problems to be solved by the invention]
In the power generation / hot water cogeneration system disclosed in Patent Document 1, the heat of exhaust gas in the power generation system is used for heating water in the hot water supply system, and in this respect, effective use of resources is achieved. However, in a power generation system including a solid oxide fuel cell, the operating temperature of the solid oxide fuel cell is considerably high, for example, about 1000 ° C., so a considerable amount of heat is generated. And, if the water in the hot water supply system is only heated using the heat of the exhaust gas, only a part of the generated large amount of heat is used, and a considerable amount of heat is wasted.
[0005]
The present invention has been made in view of the above-mentioned facts, and its main technical problem is to improve a power generation / hot water cogeneration system in which a hot water supply system is combined with a power generation system including a solid oxide fuel cell. It is to further improve the utilization efficiency of resources by making effective use of the large amount of heat generated as much as possible.
[0006]
[Means for Solving the Problems]
According to the present invention, in order to achieve the main technical problem, the heat of the exhaust gas discharged from the power generation / combustion chamber in the power generation system is used for heating the oxygen-containing gas supplied to the solid electrolyte fuel cell, Thereafter, it is used for heating water in the hot water supply system, thus increasing the effective use of the heat of the exhaust gas.
[0007]
That is, according to the present invention, as a power generation / hot water cogeneration system that achieves the main technical problem,
It has a power generation system and a hot water supply system,
The power generation system includes a power generation / combustion chamber, a battery stack including a plurality of solid oxide fuel cells disposed in the power generation / combustion chamber, fuel gas supply means for supplying fuel gas to the battery stack, and the battery An oxygen-containing gas supply means for supplying an oxygen-containing gas to the stack, and an exhaust gas discharge means for discharging exhaust gas from the power generation / combustion chamber,
The hot water supply system includes a hot water storage tank and water inflow means for allowing water to flow into the hot water storage tank.
In the power generation / hot water cogeneration system,
First heat exchange means for exchanging heat between the exhaust gas discharged by the exhaust gas discharge means and the oxygen-containing gas supplied to the battery stack by the oxygen-containing gas supply means, and discharged by the exhaust gas discharge means Second heat exchanging means for exchanging heat between the exhaust gas discharged and the water flowing into the hot water storage tank by the water inflow means, and the first heat exchanging means as viewed in the flow direction of the exhaust gas Is provided upstream of the second heat exchange means, and a power generation / hot water cogeneration system is provided.
[0008]
Preferably, the fuel gas supply means includes a reforming means for reforming the hydrocarbon-based gas into a hydrogen-rich fuel gas, and the reforming means is disposed in the power generation / combustion chamber, and the power generation / combustion Indoor heat is used for reforming. Further, the fuel gas supply means includes a vaporization means for evaporating water, and the vaporization means is also disposed in the power generation / combustion chamber, and heat in the power generation / combustion chamber is utilized for water evaporation. Is preferred. The hot water supply system includes heating water outflow means for flowing out the heated water from the hot water storage tank, and the heating water outflow means mixes the heated water to be discharged with normal temperature water as needed and cools it. In addition, it is preferable to have heating means for heating the heated water to be discharged as needed.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, with reference to the accompanying drawings, a preferred embodiment of a power generation / hot water cogeneration system configured according to the present invention will be described in detail.
[0010]
FIG. 1 schematically shows the overall configuration of a preferred embodiment of a power generation / hot water cogeneration system constructed in accordance with the present invention. The power generation / hot water cogeneration system shown in the figure includes a power generation system indicated as a whole by a number 2 and a hot water supply system indicated as a whole by a number 4.
[0011]
Referring to FIG. 2 together with FIG. 1, the power generation system 2 includes a fuel cell assembly 6, and the fuel cell assembly 6 includes a housing 8 having a substantially rectangular parallelepiped shape. The housing 8 includes an outer frame body 10 formed from a heat-resistant metal plate and a heat insulating material layer 12 disposed on the inner surface of the outer frame body 10. The heat insulating material layer 12 can be formed from an appropriate ceramic. A partition wall 14 extending substantially horizontally is disposed at a lower portion of the housing 8, and the housing 8 includes a power generation / combustion chamber 16 above the partition wall 14 and an attached chamber 18 below the partition wall 14. It is airtightly partitioned. In the power generation / combustion chamber 16, three battery stacks 20a, 20b and 20c are arranged in parallel. A fuel gas tank 21 is disposed in the attached chamber 18.
[0012]
2 and FIG. 3, each of the battery stacks 20a, 20b, and 20c is a solid that extends in the vertical direction, that is, the vertical direction in FIG. 2 and the direction perpendicular to the paper surface in FIG. A plurality of (5 in the illustrated case) electrolyte fuel cells 22 are arranged in a direction perpendicular to the paper surface in FIG. 2 and in a vertical direction in FIG. As clearly shown in FIG. 3, each of the fuel cells 22 includes an electrode support substrate 24, a fuel electrode layer 26 that is an inner electrode layer, a solid electrolyte layer 28, an oxygen electrode layer 30 that is an outer electrode layer, and an interconnector 32. It is configured. As can be understood from FIG. 2, each of the fuel cells 22 is made to stand upright on the partition wall 14, and extends somewhat above the intermediate portion in the vertical direction of the power generation / combustion chamber 16. The electrode support substrate 24 is a plate-like piece that is elongated in the vertical direction, and has both flat surfaces and both sides of a semicircular shape. A plurality (four in the illustrated example) of gas passages 34 are formed in the electrode support substrate 24 so as to penetrate the electrode support substrate 24 in the vertical direction. Each of the electrode support substrates 24 is bonded onto the partition wall 14 by, for example, a ceramic adhesive having excellent heat resistance. The partition wall 14 is formed with a plurality of slits (not shown) (not shown) extending in the left-right direction at intervals in the left-right direction and the direction perpendicular to the paper surface in FIG. A gas passage 34 formed in each electrode support substrate 24 is communicated with each slit. The upper wall of the fuel gas tank 21 disposed in the attached chamber 18 defined at the lower end of the housing 8 is defined by the partition wall 14, and therefore the interior of the fuel gas tank 21 is formed in the partition wall 14. The slits communicate with gas passages 34 formed in each of the electrode support substrates 24. The interconnector 32 is disposed on one surface of the electrode support substrate 24 (the upper surface in the fuel cell stack 20a in FIG. 3). The fuel electrode layer 26 is disposed on the other surface (the lower surface in the fuel cell stack 20a of FIG. 3) and both side surfaces of the electrode support substrate 24, and both ends thereof are joined to both ends of the interconnector 32. The solid electrolyte layer 28 is disposed so as to cover the entire fuel electrode layer 26, and both ends thereof are joined to both ends of the interconnector 32. The oxygen electrode layer 30 is disposed on the main portion of the solid electrolyte layer 28, that is, on the portion covering the other surface of the electrode support substrate 24, and is positioned facing the interconnector 32 with the electrode support substrate plate 24 interposed therebetween. It has been.
[0013]
A current collecting member 36 is disposed between adjacent fuel cells 22 in each of the cell stacks 20a, 20b, and 20c. The interconnector 32 of one fuel cell 22 and the oxygen electrode layer 30 of the other fuel cell 22 are arranged. Is connected. Current collecting members 36 are also arranged on both sides of each of the battery stacks 20a, 20b and 20c, that is, on one side and the other side of the fuel cell 22 located at the upper end and the lower end in FIG. The current collecting member 36 disposed at the lower end in FIG. 3 of the battery stacks 20a and 20b is connected by the conductive member 38, and the current collecting member 36 disposed at the upper end in FIG. 3 of the battery stacks 20b and 20c. Are also connected by a conductive member 38. Further, a terminal member 40 is connected to the current collecting member 36 disposed at the upper end in FIG. 3 of the battery stack 20a, and the terminal is also connected to the current collecting member 36 disposed at the lower end in FIG. 3 of the battery stack 20c. The member 40 is connected. Thus, all the fuel cells 22 are electrically connected in series, and the terminal members 40 exist at both ends of the series connection.
[0014]
More specifically about the fuel cell 22, the electrode support substrate 24 is gas permeable to allow fuel gas to permeate to the fuel electrode layer 26, and is also conductive to collect current through the interconnector 32. It can be formed from a porous conductive ceramic (or cermet) that satisfies such a requirement. In order to manufacture the electrode support substrate 24 by simultaneous firing with the fuel electrode layer 26 and / or the solid electrolyte layer 28, it is preferable to form the electrode support substrate 24 from an iron group metal component and a specific rare earth oxide. In order to provide the required gas permeability, it is preferable that the open porosity is in the range of 30% or more, in particular 35 to 50%, and the conductivity is also 300 S / cm or more, in particular 440 C / cm or more. Is preferred. The fuel electrode layer 26 is a porous conductive ceramic, for example, ZrO in which a rare earth element is dissolved. 2 (Referred to as stabilized zirconia) and Ni and / or NiO. The solid electrolyte layer 28 has a function as an electrolyte for bridging electrons between electrodes, and at the same time has a gas barrier property to prevent leakage between the fuel gas and the oxygen-containing gas. ZrO in which 3 to 15 mol% rare earth element is usually dissolved 2 Formed from. The oxygen electrode layer 30 is so-called ABO. 3 It can be formed from a conductive ceramic made of a type perovskite oxide. The oxygen electrode layer 30 is required to have gas permeability and preferably has an open porosity of 20% or more, particularly 30 to 50%. The interconnector 32 can be formed from a conductive ceramic, but it needs to have reduction resistance and oxidation resistance because it is in contact with a fuel gas that may be a hydrogen-rich gas and an oxygen-containing gas that may be air. For this purpose, lanthanum chromite perovskite oxide (LaCrO) is used. 3 System oxides) are preferably used. The interconnector 32 must be dense in order to prevent leakage of the fuel gas passing through the fuel passage 34 formed in the electrode support substrate 24 and the oxygen-containing gas flowing outside the electrode support substrate 24, and is 93% or more In particular, it is desirable to have a relative density of 95% or more. The current collecting member 36 can be composed of a member having an appropriate shape formed from an elastic metal or alloy, or a member obtained by adding a required surface treatment to a felt made of metal fiber or alloy fiber. The conductive member 38 and the terminal member 40 can be formed from an appropriate metal or alloy.
[0015]
1 and 2, the power generation system 2 further supplies fuel gas supply means 42 for supplying fuel gas to the battery stacks 20a, 20b, and 20c, and the battery stacks 20a, 20b, and 20c. Oxygen-containing gas supply means 44 for supplying oxygen-containing gas, and exhaust gas discharge means 46 for discharging exhaust gas from the power generation / combustion chamber 16 defined in the housing 8 of the fuel cell assembly 6 are provided. ing.
[0016]
The fuel gas supply means 42 includes a supply line 50 connected to a fuel gas supply source 48, which may be a city gas supply line or a propane gas cylinder, and the supply line 50 is provided with a cutting valve 51 and a flow rate control means 52. It is installed. The fuel gas supply means 42 also includes a reforming means 54 and a vaporizing means 56 disposed at the upper end of the power generation / combustion chamber 16 defined in the housing 8 of the fuel cell assembly 6 (in FIG. 2). The reforming means 54 and the vaporizing means 56 are simply shown in blocks). The reforming means 54 has a reforming chamber (not shown) containing a catalyst known per se necessary for partial reforming and steam reforming of fuel gas. The supply line 50 extends into the power generation / combustion chamber 16 and is connected to the inlet of the reforming means 54. The outlet of the reforming means 54 is connected to the fuel gas tank 21 through a communication path 58 and a connection pipe 59 formed in the side wall of the housing 8. On the downstream side of the flow rate control means 52, a blowing means 62 is connected to the supply line 50 via a cutoff valve 60. The fuel gas supply means 42 further includes a supply line 66 connected to a water supply source 64, which may be a clean water supply line. The supply line 66 includes a cutting valve 68, a water purification means 70, and a flow rate control means 72. It is arranged. The supply line 66 also extends into the power generation / combustion chamber 16 and is connected to the inlet of the vaporizing means 56. The outlet of the vaporizing means 56 is connected to the supply line 50 on the upstream side of the reforming means 54, and is thus connected to the reforming means 54 via the supply line 50. As will be further described later, a fuel gas, which may be city gas or propane gas, is supplied to the reforming means 54 through the supply line 50, and after being reformed into hydrogen-rich fuel gas by the reforming means 54, the fuel gas is supplied to the fuel gas tank 21. The fuel cell 22 is supplied to a gas passage 34 formed in the electrode support substrate 24. The air blowing means 62 is operated as necessary, for example, at the time of start-up (more specifically, the temperature in the power generation / combustion chamber 16 partitioned in the housing 8 is sufficiently increased, and the vaporization means 56 is vaporized as required. Air is supplied to the reforming means 54). During normal operation of the power generation system 2 (that is, when the temperature in the power generation / combustion chamber 16 partitioned in the housing 8 is sufficiently increased and the vaporization means 56 can perform the required vaporization), After being subjected to the required purification process by the water purifying means 70, the water that can be obtained is supplied to the vaporizing means 56. In the vaporizing means 56, steam is generated, and the steam is supplied to the reforming means 54 for so-called steam reforming. .
[0017]
The oxygen-containing gas supply means 44 includes a supply line 74 that extends through a side wall of the housing 8 of the fuel cell assembly 6 to an oxygen-containing gas introduction pipe 72 that extends to the lower part of the power generation / combustion chamber 16. A blowing means 76 is disposed at the upstream end of the supply line 74. The supply line 74 is further provided with a flow meter 78 and first heat exchange means 80. When the air blowing means 76 is operated, an oxygen-containing gas, which may be air, is caused to flow through the supply line 74, flows into the power generation / combustion chamber 8, and is supplied to the fuel cell 22.
[0018]
The description will be continued mainly with reference to FIG. 2 and FIG. 3. As will be further described later, for example, when the temperature in the power generation / combustion chamber 16 exceeds the required temperature by burning fuel gas in the power generation / combustion chamber 16, for example. Hydrogen-rich fuel gas is supplied from the fuel gas tank 21 to the gas passage 34 of the electrode support substrate 24 in the fuel cell 22 to ascend the gas passage 34, and the oxygen-containing gas is generated and burned through the oxygen-containing gas introduction pipe 72. Due to the introduction into the chamber 16, in each of the fuel cells 22, an electrode reaction of the following formula (1) is generated in the oxygen electrode layer 30, and the following formula (2) is generated in the fuel electrode layer 26. An electrode reaction is generated and power is generated. The generated electric power is taken out through the pair of terminal members 40.
[0019]
Oxygen electrode: 1 / 2O 2 + 2e → O 2- (Solid electrolyte) (1)
Fuel electrode: O 2- (Solid electrolyte) + H 2 → H 2 O + 2e (2)
[0020]
The fuel gas that has not been used for the electrode reaction of the fuel gas flowing through the gas passage 34 of the electrode support substrate 24 in the fuel cell 22 is caused to flow out into the power generation / combustion chamber 16 from the upper end of the electrode support substrate 24. It can be burned at the same time. Oxygen in the oxygen-containing gas introduced into the power generation / combustion chamber 16 through the oxygen-containing gas introduction pipe 72 is used for combustion. The inside of the power generation / combustion chamber 16 becomes a high temperature of, for example, about 1000 ° C. due to power generation in the fuel cell 22 and combustion of combustion gas. Thus, in the illustrated power generation / hot water cogeneration system configured in accordance with the present invention, the reforming means 54 and the vaporization means 56 of the fuel gas supply means 42 are disposed in the power generation / combustion chamber 16, and It should be noted that the high temperature in the combustion chamber 16 is effectively used for fuel gas reforming and also for water vaporization.
[0021]
Referring to FIGS. 1 and 2, the exhaust gas discharge means 46 includes an exhaust gas outlet pipe 84 extending through the upper end of the side wall of the housing 8 and an exhaust line 86 extending from the exhaust gas outlet pipe 84. . The exhaust line 86 extends through the first heat exchange means 80 and further through the second heat exchange means 88. In the first heat exchange means 80, the heat of the exhaust gas is conducted to the oxygen-containing gas supplied to the power generation / combustion chamber 16. In the second heat exchanging means 88, as will be further described later, the heat of the exhaust gas is used for heating water in the hot water supply system 4. Thus, the heat of the high-temperature exhaust gas can be effectively used, and the thermal efficiency and effective resource utilization rate in the power generation / hot water supply cogeneration system can be made sufficiently high.
[0022]
FIG. 4 schematically shows the electrical components arranged in the power generation system 2. The battery stacks 20a, 20b, and 20c are connected to, for example, a household power load in parallel with the commercial power supply system 96 via the step-up chopper 90, the inverter 92, and the linkage relay 94. Between the commercial power supply system 96 and the load, a current converter 95 for measuring the amount of power supplied from the commercial power supply system 96 to the load is disposed. In the illustrated embodiment, a battery 102 is also connected to the battery stacks 20 a, 20 b and 20 c via a step-down chopper 98 and a charger 100. The battery 102 is connected to the inverter 92 via the boost chopper 103 and the boost chopper 90. Various AC drive devices and DC drive devices are arranged in the power generation / hot water supply cogeneration system. In FIG. 4, for convenience of explanation, various AC drive devices are collectively indicated by numeral 104, and various DC drive devices are provided. Devices are collectively indicated by reference numeral 106. The DC drive device 106 is provided with a smoothing circuit 108. When the power generation system 2 is activated, AC is directly supplied to the AC drive device 104 from the commercial power supply system 96, and AC from the commercial power supply system 96 is supplied to the DC drive device 106 via the smoothing circuit 108. When power generation is started in the battery stacks 20a, 20b and 20c, the generated electricity is boosted by the boost chopper 90, converted into alternating current by the inverter 92, and supplied to the load via the linkage relay 94. When the power generation amount is insufficient with respect to the load, power is also supplied from the commercial power supply system 96 to the load. When the battery 102 is not sufficiently charged, at least a part of the generated electricity is stepped down by the step-down chopper 98 and supplied to the charger 100 to charge the battery 102. When the battery stacks 20a, 20b and 20c are generating power, the DC drive device 106 is supplied with the generated electricity via the step-down chopper 98, and the AC drive device 104 is supplied with the generated electricity with the step-up chopper 90 and the inverter. 92. For example, when the commercial power supply system 96 goes out of power when the power generation system 2 is started up, the storage battery 102 is supplied with direct current from the storage battery 102 and the AC drive apparatus 104 is boosted. Alternating current is supplied through the chopper 103, the step-up chopper 90, and the inverter 92.
[0023]
Referring to FIG. 1, the hot water supply system 4 includes a hot water storage tank 110, and a water inflow means 112 and a heated water outflow means 114 are attached to the hot water storage tank 110. The water inlet means 112 in the illustrated embodiment includes a primary supply line 116 and a secondary supply line 118. The primary supply line 116 extends from the water supply source 64 to the bottom of the hot water tank 110. The primary supply line 116 is provided with a pressure reducing valve 120. The pressure reducing valve 120 maintains the water pressure in the hot water tank 110 at a predetermined water pressure that may be, for example, 1 to 2 atmospheres. The secondary supply line 118 extends from the bottom of the hot water tank 110 to the upper part of the hot water tank 110 through the second heat exchange means 88. A water supply pump 122 is disposed upstream of the secondary supply line 118. When the water pump 122 is operated, the low-temperature water present at the bottom of the hot water tank 110 is caused to flow through the secondary supply line 118. The water flowing in the secondary supply line 118 is heated by exchanging heat with the exhaust gas in the second heat exchanging means 88, and flows into the upper part of the hot water storage tank 110. In the power generation / hot water cogeneration system configured according to the present invention, the heat of the hot exhaust gas discharged from the power generation / combustion chamber 16 is used for heating the oxygen-containing gas in the first heat exchange means 80, and then the second. The heat exchanging means 88 is used for heating water in the hot water supply system 4, and thus the heat of the exhaust gas is used sufficiently effectively. The desired heating temperature of water in the hot water supply system 4 is lower than the desired heating temperature of the oxygen-containing gas in the power generation system 2, so that the second heat exchanging means 88 used for heating the water in the hot water supply system 4 is in the flow direction of the exhaust gas. As seen, it is arranged downstream of the first heat exchange means 80 used for heating the oxygen-containing gas.
[0024]
In the illustrated embodiment, a primary supply line 116 and a secondary supply line 118 are provided, and water before heating is once introduced into the bottom of the hot water tank 110, and then water is allowed to flow out from the bottom of the hot water tank 10. Although heated, the heated water is allowed to flow into the upper part of the hot water storage tank 110. If desired, the water from the water supply source 64 is heated and then flowed into the hot water storage tank 110 without being allowed to flow into the hot water storage tank 110 once. You can also Further, when the water vapor in the exhaust gas is at least partially liquefied by heat exchange in the second heat exchange means 88, the water generated in the second heat exchange means 88 can be supplied to the vaporization means 56.
[0025]
The heated water outflow means 114 includes an outflow line 128 in which the mixing means 124 and the heating means 126 are disposed. The mixing means 124 is connected to the primary supply line 116 by a branch line 130 and is therefore connected to the water supply 64 via the branch line 130 and the primary supply line 116. When the temperature of the heated water flowing out from the hot water storage tank 110 exceeds the required temperature, the water supplied from the water supply source 64 is mixed with the heated water in the mixing means 124 and is lowered to the required temperature. For later use. On the other hand, when the heated water flowing out from the hot water storage tank 110 is lower than the required temperature, the heated water passes through the mixing means 124 without being mixed with water in the mixing means 124, and is known gas or electric hot water supply. It is heated to the required temperature in the heating means 126, which can be composed of a vessel, and is thereafter used.
[0026]
The power generation / hot water cogeneration system as described above is also equipped with control means (not shown) including a central control unit, and the power generation / hot water cogeneration system is operated under the control of the control means. The operation mode of the power generation / hot water cogeneration system can be summarized as follows.
[0027]
FIG. 5 is a flowchart showing an operation procedure when starting the power generation system in the power generation / hot water supply cogeneration system. For example, when the power generation / hot water cogeneration system is started by closing a start switch (not shown) disposed on an appropriate operation panel (not shown), the initial state is set in step n-1. Checking is performed, the previous operation stop state is confirmed, and initialization of various devices is performed as necessary. Next, at step n-2, the presence or absence of abnormality is checked. For example, an abnormality in the gas pressure in the fuel gas supply source 48, an abnormality in the water pressure in the water supply source 64 (these abnormalities can be detected by a known detector), and the like are checked. And when abnormality is detected, it progresses to step n-3, an abnormality warning is carried out, and operation stops. The abnormality warning may be, for example, lighting of a warning light provided on the operation panel or activation of a warning buzzer. Further, even if the flame has not yet started, the flame is detected and / or the output current is detected (the flame and the output current will be further described later), or the gas leakage is detected as a step for detecting an abnormality. Proceed to n-3. Regarding gas leak detection, for example, when it is detected that unburned fuel gas is contained in the exhaust gas discharged from the power generation / combustion chamber 16, or the housing 8 defining the power generation / combustion chamber 16 When it is detected that fuel gas is present in a case (not shown) that surrounds, it is determined that there is a gas leak. If no abnormality is detected in step n-2, the process proceeds to step n-4, where the air blowing means 76 in the oxygen-containing gas supply means 44 is started, and power generation and power are supplied through the supply line 74 and the oxygen-containing gas introduction pipe 72. An oxygen-containing gas is supplied into the combustion chamber 16. Next, the flow proceeds to step n-5 to start the air blowing means 62 in the fuel gas supply means 42, and the flow proceeds to step n-6 to open the cutoff valve 60, thus starting the supply of air through the supply line 50. . Thereafter, the routine proceeds to step n-7, where ignition means (not shown) disposed in the upper part of the power generation / combustion chamber 16 is started. The ignition means may be, for example, a discharge type. Next, the flow proceeds to step n-8, the prescribed flow rate by the flow rate control means 52 in the fuel gas supply means 42 is set to a predetermined value, and the flow proceeds to step n-9 to open the cutoff valve 51 and thus via the supply line 50. Start supplying fuel gas. Air and fuel gas supplied through the supply line 50 enter the reforming unit 54, and so-called partial oxidation reforming is performed in the reforming unit 54. Next, the reformed fuel gas is supplied to the gas passage 34 of the fuel cell 22 through the communication passage 58, the connecting pipe 59 and the fuel gas tank 21, and at least a part is discharged into the power generation / combustion chamber 16 from the upper end of the fuel cell 22. Is done. Then, the fuel gas discharged into the power generation / combustion chamber 16 through the gas passage 34 of the fuel cell 22 and the oxygen-containing gas introduced into the power generation / combustion chamber 16 through the oxygen-containing gas introduction pipe 72 are ignited by the ignition means to generate power. Combustion is started in the combustion chamber 16.
[0028]
Next, the process proceeds to step n-10, and a flame generated by the combustion started in the power generation / combustion chamber 16 is detected. Such detection of a flame can be conveniently performed by detecting a flame at a site indicated by reference numeral A-1 in FIG. When the flame is not detected in step n-10, in other words, when the combustion cannot be started in the power generation / combustion chamber 16, the operation stop procedure is performed. That is, the cutoff valve 51 is closed in step n-11, the flow rate setting in the flow rate control means 52 is canceled (ie, reset to zero) in step n-12, the cutoff valve 60 is closed in step n-13, and in step n-14. The operation of the blowing means 62 is stopped. If desired, the shutoff valve 60 is closed at a short time interval after the shutoff valve 52 is closed, and thus the supply line 50, the reforming means 54, the communication path 58, the connecting pipe 59, the fuel gas tank 21, and the fuel. The fuel gas present in the gas passage 34 of the battery 22 can be purged with air. Next, the process proceeds to step n-15 to purge the combustion gas in the power generation / combustion chamber 16. That is, even after the supply of the fuel gas is stopped, the air blowing means 76 continues to operate for a predetermined time, and the fuel gas in the power generation / combustion chamber 16 is purged with the oxygen-containing gas. And it progresses to step n-16 and the action | operation of the ventilation means 76 is stopped. In step n-17, it is determined whether or not the above-described activation procedure has been tried a predetermined number of times, for example, three times. When the starting procedure has already been tried a predetermined number of times, the process proceeds to step n-18, where an abnormal warning is given and the operation is stopped. If the activation procedure is less than the predetermined number, the process returns to step n-1.
[0029]
If a flame is properly detected in step n-10, the process proceeds to step n-19, where it is determined whether or not the temperature of a predetermined portion of the fuel cell assembly 6 has risen to a predetermined value or more. Such temperature detection is performed by, for example, the specific part A-2 of the vaporizing unit 56 (when the temperature of the part becomes equal to or higher than a predetermined value, water can be supplied to the vaporizing unit 56 and vaporized), and the battery stacks 20a and 20b. It is preferable to perform the process at the central part A-3 of 20 and 20c, and in the vicinity of the side face A-4 of the outer frame 10 of the housing 8, and to determine whether or not the temperature has risen above a specific specified temperature at each part. It is. If the detected temperature is less than the predetermined value, the process returns to step n-10. When the detected temperature rises above a predetermined level, the specified flow rate by the flow rate control means 72 is set to a predetermined value in step n-20, and the cutoff valve 68 is opened in step n-21, thus starting the supply of water to the vaporizing means 56. To do. Next, in step n-22, the cutoff valve 60 is closed, and in step n-23, the blowing means 62 is stopped, and thus the supply of air to the supply line 50 is stopped. Steps n-20 to 23 change the reforming of the fuel gas from partial oxidation reforming to steam reforming.
[0030]
After the reforming of the fuel gas is changed to the steam reforming, the transition procedure shown in FIG. 6, that is, the transition procedure from start to normal operation is performed. In step n-24, the presence / absence of various abnormalities, for example, stoppage of combustion in the power generation / combustion chamber 16 is determined. If an abnormality occurs, the process proceeds to step n-25 to close the cutoff valve 51, and the process proceeds to step n-26 to cancel the flow rate setting in the flow rate control means 52, thus stopping the supply of fuel gas. . The supply of water vapor to the reforming unit 54 and the fuel cell 22 is continued, thereby preventing rapid oxidation of the catalyst and the fuel cell 22 accommodated in the reforming unit 54. Next, in step n-27, it is determined whether or not the detected temperatures at the above-described portions A-2, A-3, and A-4 have decreased below a predetermined value. When the detected temperature falls below a predetermined value, the cutoff valve 60 is closed in step n-28, and the flow rate setting in the flow rate control means 72 is canceled in step n-29. In step n-30, a water vapor purge is performed in order to avoid the water vapor in various lines and the like from condensing due to a temperature drop. Such a steam purge can be conveniently performed by operating the air blowing means 62 in the fuel gas supply means 42 for a predetermined time. Thereafter, the process proceeds to step n-31 to stop the air blowing means 76 in the oxygen-containing gas supply means 44, and proceeds to step n-32 to give an abnormality warning and stop the operation.
[0031]
If no abnormality is detected in step n-24, the process proceeds to step n-33 to determine whether the detected temperature at the part A-3 exceeds a predetermined value, in other words, the fuel cell 22 is appropriate. It is determined whether or not the temperature at which power can be generated has been reached. If the detected temperature is equal to or lower than the predetermined value, the process returns to step n-24. When the detected temperature exceeds a predetermined value, the process proceeds to step n-34 to supply power to the AC drive device 104 and the DC drive device 106 in the power generation / hot water supply cogeneration system from the commercial power supply system 96 (or the battery 102). The power is generated by the stacks 20a, 20b, and 20c (see also FIG. 4). At this time, if necessary, the driving power of the blowing unit 76 and the prescribed flow rates in the flow rate control units 52 and 72 can be changed to values suitable for changing the power supply. Thereafter, the normal operation shown in FIG. 7 is started.
[0032]
When the description continues with reference to FIG. 7, when the normal operation is started, the external output of the inverter 92 is turned on in step n-35, and the power generation / hot water cogeneration system is connected to the commercial power supply system 96 (also FIG. 4). See). Next, in step n-36, the normal operation state is displayed, for example, by lighting a normal operation display lamp (not shown) arranged on the operation panel (not shown). In Step n-37, the generated current value measured by an ammeter (not shown) connected to the battery stacks 20a, 20b and 20c is read. Next, in step n-38, the amount of power supplied from the commercial power system 96 to the load, that is, the commercial power usage is read. Thereafter, the routine proceeds to step n-39, where it is determined whether or not the power generation amount of the battery stacks 20a, 20b and 20c is equal to or greater than the required power amount of the load. When the power generation amount is larger than the required power amount of the load, the process proceeds to step n-40, the output of the inverter 92 is reduced as necessary, and set to a value corresponding to the required power amount of the load. The generation of a so-called reverse power flow in which electric energy flows into the commercial power supply system 96 is avoided. Next, the process proceeds to step n-41, and it is determined whether or not the detected temperature at the central portion A-3 of the battery stacks 20a, 20b and 20c is within a predetermined range. When the detected temperature is within the predetermined range, the process proceeds to step n-42, and the appropriate drive power of the blower means 76 and the appropriate specified flow rates in the flow rate control means 52 and 72 are calculated according to a predetermined calculation formula. The current value read in step n-37 is also used for such calculation. Based on the calculated value, in step n-43, the driving power of the blowing means 76, and hence the supply amount of the oxygen-containing gas, is set to an appropriate value, and in step n-44, the set flow rate of the flow rate control means 72, and accordingly. The supply amount of water is set to an appropriate value, and in step n-45, the set flow rate of the flow rate control means 52, and hence the supply amount of fuel gas, is set to an appropriate value.
[0033]
If the detected temperature read in step n-41 is less than the predetermined range, the process proceeds to step n-46, and the appropriate drive power of the blowing means 76 and the appropriate regulation in the flow rate control means 52 and 72 are determined according to a predetermined calculation formula. The flow rate is calculated. Such calculation takes into account measures for increasing the detected temperature, for example, increasing the amount of fuel gas supplied to increase combustion in the power generation / combustion chamber 16. Based on the calculated value, in step n-47, the driving power of the blowing means 76, and hence the supply amount of the oxygen-containing gas, is set to an appropriate value, and in step n-48, the set flow rate of the flow rate control means 72, and accordingly. The supply amount of water is set to an appropriate value, and in step n-49, the set flow rate of the flow rate control means 52, and hence the supply amount of fuel gas, is set to an appropriate value. When the detected temperature read in step n-41 exceeds the predetermined range, the process proceeds to step n-50, and the proper drive power of the blower means 76 and the proper specified flow rate in the flow rate control means 52 and 72 according to the predetermined arithmetic expression. Is calculated. Such calculation takes into account measures for lowering the detected temperature, for example, measures such as increasing the supply amount of the oxygen-containing gas to promote cooling of the fuel cell 22. Based on the calculated value, in step n-51, the driving power of the blowing means 76, and hence the supply amount of the oxygen-containing gas, is set to an appropriate value, and in step n-52, the set flow rate of the flow rate control means 72, and accordingly. The supply amount of water is set to an appropriate value, and in step n-53, the set flow rate of the flow control means 52, and hence the supply amount of fuel gas, is set to an appropriate value. Next, the routine proceeds to step n-54, where the presence or absence of various abnormalities is determined. If an abnormality occurs, the procedure proceeds to the procedure shown in FIG. If there is no abnormality, the process proceeds to step n-55, and a stop signal is generated by closing a stop switch (not shown) provided on the operation panel (not shown), for example. It is determined whether or not it exists. If the stop signal has not been generated, the process returns to step n-36. On the other hand, when the stop signal is generated, the process proceeds to the procedure shown in FIG.
[0034]
When the power generation amount is smaller than the required power amount of the load in step n-39, steps n-56 to n-68 similar to steps n-41 to n-53, which should increase the power generation amount, are performed. Thereafter, the routine proceeds to step n-69, where the output of the inverter 92 is increased. Then, the process proceeds to step n-54.
[0035]
Referring to FIG. 8, if an abnormality is detected in step n-54, the process proceeds to step n-70, the external output of inverter 92 is turned off, and the power generation / hot water cogeneration system is turned on. Disconnect from the load. Next, the process proceeds to step n-71, where it is determined whether to shift to the standby mode or stop mode according to the abnormal state. For example, when the abnormality in step n-54 is that no flame is detected, the stop mode is selected when the detected temperature is equal to or lower than the lower limit (eg, 620 ° C.) with reference to the temperature at the detection portion A-3. Migrate to When the detected temperature is higher than the lower limit, there is a possibility of spontaneous ignition, so the mode is shifted to the standby mode. If the abnormal state is gas leak detection, the determination is made according to the gas leak concentration. For example, when the fuel gas is city gas, the mode shifts to the stop mode when it exceeds 1/4 of the lower explosion limit concentration, and shifts to the standby mode when it is 1/100 to 1/4 of the lower explosion limit concentration. Regarding the temperature abnormalities of the detection parts A-1, A-2 and A-3, for example, in the case of the first lower limit value or less relating to the respective detection parts, the mode shifts to the standby mode and is lower than the first lower limit value. When the value falls below the two lower limit values, it shifts to the stop mode. Similarly, for example, when it is equal to or higher than the first upper limit value for each detection part, the mode is shifted to the standby mode, and when it is equal to or higher than the second upper limit value that is higher than the first upper limit value, the mode is shifted to the stop mode. When the abnormal state is a power failure of the commercial power supply system 96, it is desirable to shift to the standby mode and use the power generation in the power generation / hot water supply cogeneration system instead of the commercial power supply system 96.
[0036]
When transitioning to the standby mode, the process proceeds to step n-72 to read the generated current value. Prior to this, the driving power of the air blowing means 76 and the prescribed flow rates in the flow rate control means 52 and 72 can be changed to values suitable for the standby mode as necessary. Next, steps n-73 to n-85 similar to steps n-41 to n-53 shown in FIG. 7 are performed. Thereafter, the process proceeds to step n-86, and the presence or absence of various abnormalities is determined. If there is no abnormality, the process proceeds to step n-25 to return to normal operation. If there is an abnormality in step n-86, it is determined whether to proceed to step n-87 and proceed to the standby mode or stop mode. If it should proceed to the standby mode, the process returns to step n-73.
[0037]
In step n-71 or step n-87, if the mode should be shifted to the stop mode, steps n-88 to n-95 similar to steps n-25 to n-32 are performed to stop the operation.
[0038]
If there is a stop signal in step n-55 (FIG. 7), the process proceeds to step n-96 shown in FIG. 9, and the external output of the inverter 92 is turned off to set the power generation / hot water cogeneration system to the commercial power supply system. Separate from 96. Next, at step n-97, it is determined whether the stop signal is a signal for instructing a shift to the standby mode or a signal for instructing an operation stop. When transitioning to the standby mode, steps n-98 to n-113 similar to steps n-72 to n-87 shown in FIG. 7 are performed. When transitioning to the stop mode, steps n-114 to n-120 similar to steps n-88 to n-95 shown in FIG. 8 are performed and the operation is stopped.
[0039]
FIG. 10 is a flowchart showing an operation procedure of the hot water supply system. In the illustrated embodiment, since the operation control of the hot water supply system itself is performed independently of the operation control of the power generation system in the power generation / hot water supply system, an abnormality occurs in the power generation system and the power generation system is stopped. Even in this case, it is possible to realize hot water supply by operating the hot water supply system. The operation of the hot water supply system is started, for example, by detecting that a faucet (not shown) for hot water supply is opened. In step m-1, an initialization check is performed to confirm the previous operation stop state, and various devices are initialized as necessary. Next, whether or not there is an abnormality is checked in step m-2. For example, abnormalities such as an abnormality in water pressure at the water supply source 64, an abnormality in supply gas pressure with respect to the heating means 126, and an abnormality such as leakage or power failure in the commercial power supply system 96 are checked. If an abnormality is detected, the process proceeds to step m-3 to warn of an abnormality and stop the operation. As in the case of the power generation system, the abnormality warning may be an operation of a warning light or a warning buzzer provided on the operation panel. If there is no abnormality in step m-2, the process proceeds to step m-4 and the temperature of the hot water stored in the hot water tank 110, that is, the temperature of the hot water delivered from the hot water tank 110 when hot water is supplied. It is determined whether or not exceeds a predetermined value that may be 60 ° C., for example. If the temperature of the hot water exceeds the predetermined value, the process proceeds to step m-5 to operate the mixing means 124, mix the hot water from the hot water storage tank 110 with the water supply source 64, and cool to the required temperature. Hot water. When the temperature of the hot water is not more than a predetermined value, the process proceeds to step m-6 to operate the heating means 126, and hot water from the hot water storage tank 110 is heated to a required temperature to supply hot water. In step m-7, it is determined whether or not to continue hot water supply. When hot water supply should be continued, the process returns to step m-2. When the faucet is closed and the hot water supply is to be stopped, the operation of the mixing means 124 or the heating means 126 which has been operated by proceeding to Step m-8 is stopped and the operation is stopped. The water pump 122 provided in the hot water supply system 4 can be controlled based on the temperature of the water in the secondary supply line 118 on the downstream side of the second heat exchange means 88. When the temperature of the water is lower than a predetermined range, for example, 80 to 95 ° C., the amount of water supplied by the water supply pump 88 is reduced, and when the temperature is higher than the predetermined range, the amount of water supplied by the water supply pump 88 is increased.
[0040]
【The invention's effect】
According to the power generation / hot water supply cogeneration system of the present invention, the utilization efficiency of resources can be sufficiently improved by effectively using as much heat as possible generated in the power generation system.
[Brief description of the drawings]
FIG. 1 is a block diagram schematically showing main components of a power generation / hot water cogeneration system configured according to the present invention.
2 is a cross-sectional view schematically showing a part of a power generation / combustion chamber in the power generation / hot water cogeneration system of FIG. 1;
3 is a cross-sectional view showing a battery stack disposed in the power generation / combustion chamber of FIG. 2;
4 is a block diagram schematically showing electrical components in the power generation / hot water cogeneration system of FIG. 1. FIG.
5 is a flowchart showing an operation procedure at the start-up of the power generation system in the power generation / hot water supply cogeneration system of FIG. 1;
FIG. 6 is a flowchart showing a procedure for transition from start-up to normal operation of the power generation system in the power generation / hot water supply cogeneration system of FIG. 1;
7 is a flowchart showing a normal operation procedure of the power generation system in the power generation / hot water supply cogeneration system of FIG. 1;
8 is a flowchart showing an operation procedure when an abnormality is detected in the power generation system in the power generation / hot water cogeneration system of FIG. 1;
FIG. 9 is a flowchart showing an operation procedure when generating a stop signal of the power generation system in the power generation / hot water supply cogeneration system of FIG. 1;
10 is a flowchart showing an operation procedure of the hot water supply system in the power generation / hot water supply cogeneration system of FIG. 1;
[Explanation of symbols]
2: Power generation system
4: Hot water supply system
6: Fuel cell assembly
16: Power generation / combustion chamber
20a: Battery stack
20b: Battery stack
20c: Battery stack
22: Fuel cell
42: Fuel gas supply means
44: Oxygen-containing gas supply means
46: Exhaust gas discharge means
54: Reforming means
56: Vaporization means
80: First heat exchange means
88: Second heat exchange means
110: Hot water tank
124: Mixing means
126: Heating means

Claims (4)

発電システムと給湯システムとを備え、
該発電システムは発電・燃焼室、該発電・燃焼室内に配設された複数個の固体電解質型燃料電池を含む電池スタック、該電池スタックに燃料ガスを供給するための燃料ガス供給手段、該電池スタックに酸素含有ガスを供給するための酸素含有ガス供給手段、及び該発電・燃焼室内から排ガスを排出するための排ガス排出手段を具備し、
該給湯システムは貯湯槽及び該貯湯槽に水を流入せしめる水流入手段を具備する、
発電・給湯コジェネレーションシステムにおいて、
該排ガス排出手段によって排出される排ガスと該酸素含有ガス供給手段によって該電池スタックに供給される酸素含有ガスとの間で熱交換せしめるための第一の熱交換手段、及び該排ガス排出手段によって排出される排ガスと該水流入手段によって該貯湯槽に流入される水との間で熱交換せしめるための第二の熱交換手段を備え、排ガスの流動方向に見て、該第一の熱交換手段は該第二の熱交換手段よりも上流に配設されている、ことを特徴とする発電・給湯コジェネレーションシステム。
It has a power generation system and a hot water supply system,
The power generation system includes a power generation / combustion chamber, a battery stack including a plurality of solid oxide fuel cells disposed in the power generation / combustion chamber, fuel gas supply means for supplying fuel gas to the battery stack, and the battery An oxygen-containing gas supply means for supplying an oxygen-containing gas to the stack, and an exhaust gas discharge means for discharging exhaust gas from the power generation / combustion chamber,
The hot water supply system includes a hot water storage tank and water inflow means for allowing water to flow into the hot water storage tank.
In the power generation / hot water cogeneration system,
First heat exchange means for exchanging heat between the exhaust gas discharged by the exhaust gas discharge means and the oxygen-containing gas supplied to the battery stack by the oxygen-containing gas supply means, and discharged by the exhaust gas discharge means Second heat exchanging means for exchanging heat between the exhaust gas discharged and the water flowing into the hot water storage tank by the water inflow means, and the first heat exchanging means as viewed in the flow direction of the exhaust gas Is disposed upstream of the second heat exchanging means, and is a power generation / hot water cogeneration system.
該燃料ガス供給手段は炭化水素系ガスを水素リッチな燃料ガスに改質せしめる改質手段を含み、該改質手段は該発電・燃焼室内に配設されており、該発電・燃焼室内の熱が改質に利用される、請求項1記載の発電・給湯コジェネレーションシステム。The fuel gas supply means includes reforming means for reforming a hydrocarbon-based gas into a hydrogen-rich fuel gas, the reforming means being disposed in the power generation / combustion chamber, The power generation / hot water cogeneration system according to claim 1, wherein is used for reforming. 該燃料ガス供給手段は水を蒸発せしめるための気化手段を含み、該気化手段も該発電・燃焼室内に配設されており、該発電・燃焼室内の熱が水の蒸発に利用される、請求項2記載の発電・給湯コジェネレーションシステム。The fuel gas supply means includes vaporization means for evaporating water, the vaporization means is also disposed in the power generation / combustion chamber, and heat in the power generation / combustion chamber is utilized for water evaporation. Item 2. The power generation / hot water cogeneration system according to item 2. 該給湯システムは該貯湯槽から加熱水を流出するための加熱水流出手段を含み、該加熱水流出手段は流出せしめられる加熱水を必要に応じて常温水と混合して冷却するための混合手段、及び流出せしめられる加熱水を必要に応じて加熱するための加熱手段を有する、請求項1から3までのいずれかに記載の発電・給湯コジェネレーションシステム。The hot water supply system includes heating water outflow means for flowing out the heated water from the hot water storage tank, and the heating water outflow means mixes the heated water to be discharged with normal temperature water as needed and cools it. The power generation / hot water cogeneration system according to any one of claims 1 to 3, further comprising heating means for heating the heated water to be discharged as needed.
JP2003169694A 2003-06-13 2003-06-13 Power generation / hot water cogeneration system Expired - Fee Related JP4508557B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003169694A JP4508557B2 (en) 2003-06-13 2003-06-13 Power generation / hot water cogeneration system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003169694A JP4508557B2 (en) 2003-06-13 2003-06-13 Power generation / hot water cogeneration system

Related Child Applications (2)

Application Number Title Priority Date Filing Date
JP2009127303A Division JP5171731B2 (en) 2009-05-27 2009-05-27 Power generation system
JP2009142632A Division JP5159707B2 (en) 2009-06-15 2009-06-15 Power generation system operation method

Publications (2)

Publication Number Publication Date
JP2005005213A true JP2005005213A (en) 2005-01-06
JP4508557B2 JP4508557B2 (en) 2010-07-21

Family

ID=34094752

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003169694A Expired - Fee Related JP4508557B2 (en) 2003-06-13 2003-06-13 Power generation / hot water cogeneration system

Country Status (1)

Country Link
JP (1) JP4508557B2 (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005093430A (en) * 2003-09-11 2005-04-07 Sulzer Hexis Ag Heat exchanger for heating system with integrated fuel cells for generation of electricity
WO2007052633A1 (en) * 2005-10-31 2007-05-10 Kyocera Corporation Fuel cell system
JP2007207661A (en) * 2006-02-03 2007-08-16 Nippon Oil Corp Power supply system having fuel cell system
JP2007207446A (en) * 2006-01-31 2007-08-16 Kyocera Corp Fuel cell power generation system
JP2007294296A (en) * 2006-04-26 2007-11-08 Kyocera Corp Power generation/hot-water supply cogeneration system
JP2008152999A (en) * 2006-12-15 2008-07-03 Matsushita Electric Ind Co Ltd Fuel cell power generating system and its program
JP2009158475A (en) * 2007-12-27 2009-07-16 Antig Technology Corp Fuel cell device equipped with heat insulating structure
JP2009181941A (en) * 2008-02-01 2009-08-13 Toshiba Corp Fuel cell system
JP2009302010A (en) * 2008-06-17 2009-12-24 Showa Shell Sekiyu Kk Fuel cell cogeneration system
JP2010238597A (en) * 2009-03-31 2010-10-21 Toto Ltd Fuel cell system
JP2011003489A (en) * 2009-06-22 2011-01-06 Panasonic Corp Fuel cell system and method of operating the same
EP2306575A1 (en) 2009-09-30 2011-04-06 Toto Ltd. Solid oxide fuel cell device
JP2012209014A (en) * 2011-03-29 2012-10-25 Osaka Gas Co Ltd Solid oxide fuel cell system
US8658320B2 (en) 2009-05-08 2014-02-25 Panasonic Corporation Method of operating a fuel cell
DE112005001725B4 (en) * 2004-07-21 2018-09-06 Kyocera Corp. The fuel cell system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001065976A (en) * 1999-08-26 2001-03-16 Matsushita Electric Works Ltd Cogeneration system
JP2002151127A (en) * 2000-11-16 2002-05-24 Ngk Insulators Ltd Cogeneration power plant
JP2002246047A (en) * 2001-02-21 2002-08-30 Nissan Motor Co Ltd Fuel cell system
JP2003007325A (en) * 2001-06-20 2003-01-10 Hitachi Ltd Combustor of fuel cell anode off-gas, hydrogen production system and fuel cell power generation system
JP2003059519A (en) * 2001-08-09 2003-02-28 Mitsubishi Heavy Ind Ltd Fuel cell system and cogeneration system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001065976A (en) * 1999-08-26 2001-03-16 Matsushita Electric Works Ltd Cogeneration system
JP2002151127A (en) * 2000-11-16 2002-05-24 Ngk Insulators Ltd Cogeneration power plant
JP2002246047A (en) * 2001-02-21 2002-08-30 Nissan Motor Co Ltd Fuel cell system
JP2003007325A (en) * 2001-06-20 2003-01-10 Hitachi Ltd Combustor of fuel cell anode off-gas, hydrogen production system and fuel cell power generation system
JP2003059519A (en) * 2001-08-09 2003-02-28 Mitsubishi Heavy Ind Ltd Fuel cell system and cogeneration system

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005093430A (en) * 2003-09-11 2005-04-07 Sulzer Hexis Ag Heat exchanger for heating system with integrated fuel cells for generation of electricity
DE112005001725B4 (en) * 2004-07-21 2018-09-06 Kyocera Corp. The fuel cell system
US8470484B2 (en) 2005-10-31 2013-06-25 Kyocera Corporation Fuel cell system
WO2007052633A1 (en) * 2005-10-31 2007-05-10 Kyocera Corporation Fuel cell system
JP2007207446A (en) * 2006-01-31 2007-08-16 Kyocera Corp Fuel cell power generation system
JP2007207661A (en) * 2006-02-03 2007-08-16 Nippon Oil Corp Power supply system having fuel cell system
JP2007294296A (en) * 2006-04-26 2007-11-08 Kyocera Corp Power generation/hot-water supply cogeneration system
JP2008152999A (en) * 2006-12-15 2008-07-03 Matsushita Electric Ind Co Ltd Fuel cell power generating system and its program
JP2009158475A (en) * 2007-12-27 2009-07-16 Antig Technology Corp Fuel cell device equipped with heat insulating structure
JP2009181941A (en) * 2008-02-01 2009-08-13 Toshiba Corp Fuel cell system
JP2009302010A (en) * 2008-06-17 2009-12-24 Showa Shell Sekiyu Kk Fuel cell cogeneration system
JP2010238597A (en) * 2009-03-31 2010-10-21 Toto Ltd Fuel cell system
US8658320B2 (en) 2009-05-08 2014-02-25 Panasonic Corporation Method of operating a fuel cell
JP2011003489A (en) * 2009-06-22 2011-01-06 Panasonic Corp Fuel cell system and method of operating the same
EP2306575A1 (en) 2009-09-30 2011-04-06 Toto Ltd. Solid oxide fuel cell device
JP2011096635A (en) * 2009-09-30 2011-05-12 Toto Ltd Solid electrolyte fuel cell device
US8501358B2 (en) 2009-09-30 2013-08-06 Toto Ltd. Solid oxide fuel cell device
JP2012209014A (en) * 2011-03-29 2012-10-25 Osaka Gas Co Ltd Solid oxide fuel cell system

Also Published As

Publication number Publication date
JP4508557B2 (en) 2010-07-21

Similar Documents

Publication Publication Date Title
JP4508557B2 (en) Power generation / hot water cogeneration system
EP2352197B1 (en) Fuel cell system
JP5412960B2 (en) Fuel cell device
ES2387212T3 (en) Improved air flow of the flow hood of a fuel cell stacking using an air distribution device
JP4906242B2 (en) How to shut down the fuel cell
US8927162B2 (en) Solid oxide fuel cell system performing different restart operations depending on operation temperature
EP3121888B1 (en) Fuel battery device
JP2010086917A (en) Fuel cell system
JP2012028165A (en) Fuel cell system
JP5159707B2 (en) Power generation system operation method
JPWO2006009264A1 (en) Fuel cell system
JP2003217635A (en) Fuel cell power generation system
JP5000867B2 (en) Fuel cell power generation system
JP5171731B2 (en) Power generation system
WO2002067352A1 (en) Energy dissipater for pressurized fuel cell generators
JP2014229402A (en) Fuel cell system
JP6804232B2 (en) Power generation system and its protection control method
JP5156171B2 (en) Fuel cell system
JP2002208427A (en) Reforming device for fuel cell
JP2007188894A (en) Fuel cell power generating system
JP2012009175A (en) Fuel cell power generation system and operation method thereof
JP2007128718A (en) Fuel cell module and operation method of the same
JP2017157272A (en) Fuel battery system
JP2014011037A (en) Fuel battery system
EP3163660A1 (en) Fuel cell module having increased thermal efficiency, and heating system using same and control method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051114

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080225

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090414

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20090522

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20090522

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090612

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100330

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100427

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130514

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4508557

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140514

Year of fee payment: 4

LAPS Cancellation because of no payment of annual fees