JP2004245035A - Underground beam construction frame and underground beam construction method using the same - Google Patents
Underground beam construction frame and underground beam construction method using the same Download PDFInfo
- Publication number
- JP2004245035A JP2004245035A JP2004002476A JP2004002476A JP2004245035A JP 2004245035 A JP2004245035 A JP 2004245035A JP 2004002476 A JP2004002476 A JP 2004002476A JP 2004002476 A JP2004002476 A JP 2004002476A JP 2004245035 A JP2004245035 A JP 2004245035A
- Authority
- JP
- Japan
- Prior art keywords
- underground beam
- beam construction
- frame
- fixed
- construction frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
本発明は地中梁施工枠及びこれを用いた地中梁施工法に関するものである。 The present invention relates to an underground beam construction frame and an underground beam construction method using the same.
従来の地中梁の施工法は、次の通りである。まず、図7に示すように掘削部分100を掘削して掘削工事を行う。次に、図8に示すように掘削部分100の底盤に栗石101等を敷き詰め、突き固める割栗工事行う。次に、図9に示すように捨てコンクリート102を薄く打設し墨で地中梁等の位置を記す、捨てコンクリート工事と墨出しを行う。
次に、図10に示すように配筋工事を行う。これは多数の鉄筋103,103・・を組んで、所定の高さと幅に形成して行う。なお、104,104は鉄筋103,103・・の下に敷いたコンクリートブロック等の台である。
次に、図11に示すように型枠工事を行う。これは配筋を囲むように板材からなる型枠105を組み立てるものである。次に、図示はしないが該型枠105内に生コンクリートを打設し、そして生コンクリートが硬化した後、この型枠105を解体し、その後埋め戻しを行うものである。
The conventional construction method of underground beams is as follows. First, as shown in FIG. 7, the excavated
Next, as shown in FIG. This is performed by forming a large number of reinforcing
Next, formwork is performed as shown in FIG. This is to assemble a
しかし、この従来の施工法では、上記の如く現場において人手によって鉄筋と型枠を組み立てるものであるから、作業に多大な労力と時間を要することになる。また、従来の型枠は解体しなければならないため、打設した生コンクリートが硬化するまでの間、通常は丸1〜2日間工事を休まなければならず作業能率が悪い。そして埋め戻す前に型枠を解体しなければならないため、余分な労力と時間を要することになる。これらのことから、従来の施工法では多大な労力と時間を浪費すると共に作業能率も悪い。そのため工期が長引くと共にコストも高くつくという問題点があった。 However, in this conventional construction method, since the reinforcing bar and the formwork are assembled manually at the site as described above, a large amount of labor and time are required for the work. Further, since the conventional formwork has to be dismantled, the work has to be usually rested for one to two days until the poured ready-mixed concrete hardens, and the work efficiency is poor. The mold must be dismantled before backfilling, which requires extra effort and time. For these reasons, the conventional construction method wastes a great deal of labor and time, and also has a low work efficiency. Therefore, there is a problem that the construction period is prolonged and the cost is high.
本発明は上記の点に鑑みなされたものであって、地中梁の施工において従来よりも大幅に工期を短縮することができると共にコストの大幅な軽減を図ることができるようにした地中梁施工枠及びこれを用いた地中梁施工法を提供するものである。 The present invention has been made in view of the above points, and has an underground beam capable of significantly reducing the construction period and the cost significantly in the construction of an underground beam as compared with the related art. A construction frame and an underground beam construction method using the same are provided.
本発明の要旨とするところは、2枚の断面コ字形の鋼板を一定間隔をおいて平行に配置し、この鋼板の両端部に、連結ボルトの挿通孔を設けた方形のアングルを嵌めて枠本体を構成し、この枠本体内に適宜の配筋を施した地中梁施工枠である。 The gist of the present invention resides in that two steel plates having a U-shaped cross section are arranged in parallel at a predetermined interval, and a rectangular angle provided with through holes for connecting bolts is fitted to both ends of the steel plates. This is an underground beam construction frame that constitutes a main body, and has an appropriate arrangement of reinforcing bars inside the frame main body.
また、本発明の要旨とするところは、上記地中梁施工枠の中間部を曲折し、この中間部の内部にアンカーボルトを固定した連結板を取り付けると共に、上記中間部の上部に、表面に柱を立設したベースプレートを配置し、このベースプレートと上記連結板をアンカーボルトで枠本体に固定したの地中梁施工枠である。 In addition, the gist of the present invention is to bend the middle part of the underground beam construction frame, attach a connecting plate to which an anchor bolt is fixed inside the middle part, and, on the surface of the upper part of the middle part, This is an underground beam construction frame in which a base plate on which columns are erected is arranged, and the base plate and the connection plate are fixed to the frame body with anchor bolts.
また、本発明の要旨とするところは、上記地中梁施工枠の中間部を曲折し、この中間部の上部には柱の上部支持板を固定すると共に、下部には下部支持板を固定し、柱を上記上部支持板と下部支持板に固定することにより枠本体に固定した地中梁施工枠である。 In addition, the gist of the present invention is to bend the middle part of the underground beam construction frame, fix the upper support plate of the pillar on the upper part of the middle part, and fix the lower support plate on the lower part. An underground beam construction frame fixed to the frame body by fixing columns to the upper support plate and the lower support plate.
また、本発明の要旨とするところは、上記地中梁施工枠の中間部に、一端のアングルを取り外した地中梁施工枠を取り付け、上記中間部の内部にアンカーボルトを固定した連結板を取り付けると共に、上記中間部の上部に、表面に柱を立設したベースプレートを配置し、このベースプレートと上記連結板をアンカーボルトで枠本体に固定した地中梁施工枠である。 Further, the gist of the present invention is that an underground beam construction frame with an angle removed at one end is attached to an intermediate portion of the underground beam construction frame, and a connecting plate in which anchor bolts are fixed inside the intermediate portion. An underground beam construction frame in which a base plate on which a pillar is erected on the surface is arranged, and the base plate and the connection plate are fixed to a frame body with anchor bolts, while being attached.
また、本発明の要旨とするところは、上記地中梁施工枠の中間部に、一端のアングルを取り外した地中梁施工枠を取り付け、上記中間部の上部には柱の上部支持板を固定すると共に、下部には下部支持板を固定し、柱を上記上部支持板と下部支持板に固定することにより枠本体に固定した地中梁施工枠である。 Further, the gist of the present invention is that an underground beam construction frame from which an angle is removed at one end is attached to an intermediate portion of the underground beam construction frame, and an upper support plate of a pillar is fixed to an upper portion of the intermediate portion. At the same time, the underground beam construction frame is fixed to the frame body by fixing a lower support plate to a lower portion and fixing columns to the upper support plate and the lower support plate.
また、本発明の要旨とするところは、2枚の断面コ字形の鋼板を構成し、この鋼板を対向させて一定間隔を保って平行に配置した後、上記鋼板の両端部に連結ボルトの挿通孔を設けた方形のアングルを嵌めて枠本体を構成し、その後この枠本体内に適宜の配筋を施してからコンクリート上に設置し、次いで枠本体内に生コンクリートを打設して硬化させる地中梁施工法である。 The gist of the present invention is that two steel plates having a U-shaped cross section are formed, and the steel plates are opposed to each other and arranged in parallel at a constant interval. A rectangular body with a hole is fitted to form a frame body, after which appropriate reinforcement is provided in the frame body, and then placed on concrete, and then ready-mixed concrete is poured into the frame body and hardened. Underground beam construction method.
請求項1乃至請求項5に記載した地中梁施工枠及び請求項6に記載した地中梁施工法によれば、上記した従来工法のように、現場において鉄筋を組む作業、型枠を組む作業並びに型枠を解体する作業を省略することができる。さらに一定間隔に配した鋼板製の枠内にコンクリートを打設して硬化させた状態で地中梁施工枠が完成する。そのためこの完成した状態で直ちに高速道路や橋脚等に永久構築物として使用することができる。
また型枠内に生コンクリートを打設した直後、あるいは生コンクリートの打設前であっても埋め戻しを行うことができる。
したがって、従来の如く多大な労力と時間を浪費することがなく、地中梁施工工事において工期を大幅に短縮することができると共に、コストの大幅な軽減を図ることができる。また、特に請求項2乃至請求項5に記載の地中梁施工枠によれば、本発明の地中梁施工枠と柱との固定を現場において迅速に行うことができるのである。
According to the underground beam construction frame described in
Also, the backfill can be performed immediately after placing the ready-mixed concrete in the formwork or even before placing the ready-mixed concrete.
Therefore, a great deal of labor and time are not wasted as in the related art, and the construction period can be greatly reduced in the underground beam construction work, and the cost can be significantly reduced. According to the underground beam construction frame of the second to fifth aspects, the underground beam construction frame and the column of the present invention can be quickly fixed on the site.
本発明に係る地中梁施工枠を実施するための最良の形態は、軸断面コ字形の一対の鋼板を一定間隔を保って開放側を向き合わせて、同一の高さで平行に配置し、この鋼板の長さ方向の両端部に、所要箇所に連結ボルトの挿通孔を設けた方形のアングルを嵌めて枠本体を構成し、この枠本体内に適宜の配筋を施すものである。 The best mode for carrying out the underground beam construction frame according to the present invention is to arrange a pair of steel plates having a U-shape in cross section, facing the open side at a constant interval, and arranging them in parallel at the same height, The frame body is formed by fitting a rectangular angle having connection bolt insertion holes at required locations at both ends in the length direction of the steel plate to form a frame main body, and providing appropriate reinforcing bars inside the frame main body.
また、本発明に係る地中梁施工法を実施するための最良の形態は、軸断面コ字形の一対の鋼板を構成し、この鋼板を一定間隔を保って開放側を向き合わせて、同一の高さで平行に配置した後、この鋼板の長さ方向の両端部に、所要箇所に連結ボルトの挿通孔を設けた方形のアングルを嵌めて枠本体を構成し、その後この枠本体内に適宜の配筋を施してからコンクリート上に配置し、次いで生コンクリートを打設して硬化させることにある。 In addition, the best mode for carrying out the underground beam construction method according to the present invention is to form a pair of steel plates having a U-shape in axial section, face the open sides of the steel plates at a constant interval, and After arranging in parallel at the height, the frame body is constructed by fitting a square angle with connecting bolt insertion holes at required locations at both ends in the length direction of this steel sheet, and then appropriately inside this frame body And then placing it on concrete and then pouring and hardening fresh concrete.
以下、本発明の実施例について説明する。
図1は本発明に係る地中梁施工枠の斜視図、図2は図1に示した地中梁施工枠を用いた地中梁施工法の説明図、図3は柱を固定する部分に用いる地中梁施工枠の斜視図、図4は柱を固定する部分に用いる地中梁施工枠の斜視図、図5はアンカーボルトを用いた地中梁施工枠と柱の固定構造の説明図及び図6は溶接による地中梁施工枠と柱の固定構造の説明図である。
Hereinafter, examples of the present invention will be described.
FIG. 1 is a perspective view of an underground beam construction frame according to the present invention, FIG. 2 is an explanatory view of an underground beam construction method using the underground beam construction frame shown in FIG. 1, and FIG. FIG. 4 is a perspective view of an underground beam construction frame used for a part for fixing a column, and FIG. 5 is an explanatory view of an underground beam construction frame and a column fixing structure using anchor bolts. 6 is an explanatory view of a structure for fixing an underground beam construction frame and a column by welding.
図中、1は地中梁施工枠である。この地中梁施工枠1は、後記枠本体と配筋とからなる。2,2は同一の大きさ、同一の形状の一対の鋼板であり、いずれも所定長さを有していて、上端及び下端を同方向に折曲しているため軸断面はコ字形をしている。この鋼板2,2は一定間隔Lをおいて開放側を対向させて平行に配されていており、両鋼板2の上端が水平になるように設置されている。
In the figure,
3,3は鋼板からなる方形のアングルであり、前記一対の鋼板2,2の長さ方向の両端部に夫々嵌め込んで溶接されている。このアングル3,3は、全体的な強度を出すためと固定強度の点から、本実施例では軸断面をL字形としている。そして、該アングル3,3には、隣接する地中梁施工枠1と連結させるための連結ボルト4を挿通する孔5,5・・を所要箇所に設けている。6は該連結ボルト4に螺合する締付ナットである。
上記一対の鋼板2,2と方形のアングル3,3とによって枠本体7を構成するのである。また、該枠本体7の高さと幅は、これを用いて施工する地中梁に応じて適宜決定される。
The
8は前記枠本体7内に施した配筋であり、枠本体7の長さ方向に沿った鉄筋8a,8a・・と、枠本体7の長さ方向と直交し垂直に配した鉄筋8b,8b・・と、枠本体7の長さ方向と直交し水平に配した鉄筋8c,8c・・等を適宜に組み合わせて組みつけられる。
次に、上記地中梁施工枠1を用いた地中梁施工法について、図2を参照しつつ説明する。
掘削工事、割栗工事並びに捨てコンクリート工事及び墨出しを行うことは、従来の施工法と同様である。本施工法は、予め工場において製作した上記地中梁施工枠1を捨てコンクリート上に設置し、その後この枠本体7内に生コンクリート(図示せず)を打設して硬化させるのである。
これにより、従来行われていた現場における鉄筋の組み立て作業や、型枠の組み立て作業が省略でき、無駄な労力と時間を節約し、併せて作業能率をアップさせることができるのである。
そして地中梁施工枠1はそのままで地中梁を構成するから、従来の如く解体する必要がない。そのため、従来の如く生コンクリートが硬化するまで待つ必要がなく、生コンクリートを打設した直後、あるいは生コンクリートの打設前であっても埋め戻すことができるのである。
これらのことから、型枠の解体に要する手間と時間も節約でき、かつ工期を大幅に短縮することができると共にコストの大幅な軽減を図ることもできる。
なお、9,9は地中梁施工枠1を捨てコンクリート上に設置する際に用いる部材であり、本実施形態では枠本体7の側面下部に固定した軸断面L字形の鋼板10,10と捨てコンクリートに固定したレベル調整ボルト11,11とからなるものを用いている。
Next, an underground beam construction method using the underground
Excavation work, split chestnut work, abandoned concrete work, and blackout are the same as in the conventional construction method. According to this construction method, the underground
As a result, the work of assembling the reinforcing bar and the work of assembling the formwork at the site, which has been conventionally performed, can be omitted, and unnecessary labor and time can be saved, and the work efficiency can be improved.
Since the underground
From these facts, the labor and time required for dismantling the form can be saved, the construction period can be greatly reduced, and the cost can be significantly reduced.
次に、本発明に係る地中梁施工枠を用いて地中梁の施工を行う場合には、角の部分や梁が交差する部分等において柱の固定が行われるが、この場合には次の地中梁施工枠を用いることが望ましく、これにより固定を迅速に行うことができる。 Next, when the underground beam is constructed using the underground beam construction frame according to the present invention, the pillars are fixed at corners, intersections of beams, and the like. It is desirable to use the underground beam construction frame, whereby the fixing can be performed quickly.
図3は角の部分、すなわち地中梁施工枠1を直角に曲折した中間部1aにおいて柱の固定を行う場合、図4は梁が交差する部分である中間部1bにおいて柱の固定を行う場合である。
これらの場合において、図3に示す中間部1aにおいて柱の固定を行う場合には、地中梁施工枠1を平面L字形に構成する。また図4に示す如く梁の交差する中間部1bにおいて柱の固定を行う場合には、地中梁施工枠1を平面T字形に構成し、1個の地中梁施工枠2nは一端のアングルを取り外して他の地中梁施工枠に取り付けられる。
FIG. 3 shows the case where the column is fixed at the corner portion, that is, the
In these cases, when fixing the column in the
そして、図5に示す如く、枠本体7の上部側の所定箇所にアンカーボルト12,12・・を固定した連結板13を固定し、表面に柱14を立設したベースプレート15に設けたアンカーボルト挿通孔16,16・・に上記アンカーボルト12,12・・を挿通し、ナット17,17・・によって締め付けて固定するのである。
また、図4の7a,7a・・は枠本体7に設けたボルト挿通孔、13a,13a・・は連結板13に設けたアンカーボルト挿通孔であり、アンカーボルト12,12・・は該アンカーボルト挿通孔13a,13aに挿通した状態で予め工場において連結板13に溶接しておく。また、13bは連結板13の中央部に設けた生コンクリート充填孔である。
なお、その他の構成は上記地中梁施工枠1と同様であるから、同一の部分には同一の符号を付して詳細な説明は省略する。
Then, as shown in FIG. 5, a connecting
4 are bolt insertion holes provided in the
Since other configurations are the same as those of the underground
次に、図6を参照しつつ図3に示す中間部1a及び図4に示す中間部1bに柱を固定する場合について説明する。
本実施例の場合には、柱18の下端部に上部支持板19と下部支持板20を溶接により固定し、該柱18を枠本体7における柱の固定箇所に垂直に配置すると共にこの2枚の支持板19,20を枠本体7の上部と下部に溶接して固定する。また、該柱18には、その上部に柱本体18Aを溶接によって固定するのである。
なお、その他の構成は上記地中梁施工枠1と同様であるから、同一の部分には同一の符号を付して詳細な説明は省略する。
Next, a case where the pillar is fixed to the
In the case of the present embodiment, the
Since other configurations are the same as those of the underground
1 地中梁施工枠
1a 地中梁施工枠の中間部
1b 地中梁施工枠の交差部
2n 地中梁施工枠
2 鋼板
3 アングル
4 連結ボルト
5 ボルト挿通孔
6 ナット
7 枠本体
8 配筋
12 アンカーボルト
13 連結板
13a アンカーボルト挿通孔
14 柱
15 ベースプレート
16 アンカーボルト挿通孔
17 ナット
18 柱
19 上部支持板
20 下部支持板
DESCRIPTION OF
Claims (6)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004002476A JP3763575B2 (en) | 2004-01-07 | 2004-01-07 | Underground beam construction frame and underground beam construction method using the same |
CNB2004101011334A CN1329589C (en) | 2004-01-07 | 2004-12-13 | Underground beam construction frame and underground beam construction method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004002476A JP3763575B2 (en) | 2004-01-07 | 2004-01-07 | Underground beam construction frame and underground beam construction method using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004245035A true JP2004245035A (en) | 2004-09-02 |
JP3763575B2 JP3763575B2 (en) | 2006-04-05 |
Family
ID=33028481
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004002476A Expired - Fee Related JP3763575B2 (en) | 2004-01-07 | 2004-01-07 | Underground beam construction frame and underground beam construction method using the same |
Country Status (2)
Country | Link |
---|---|
JP (1) | JP3763575B2 (en) |
CN (1) | CN1329589C (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105332389A (en) * | 2015-11-13 | 2016-02-17 | 燕山大学 | Underground pipe rack erector |
JP2017172308A (en) * | 2016-03-27 | 2017-09-28 | 株式会社南条製作所 | Integrated foundation and integrated foundation construction method |
CN115492376A (en) * | 2022-08-31 | 2022-12-20 | 上海宝冶集团有限公司 | Template supporting method for lattice beams and lattice columns of ultra-large slope broken stone slope |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103112766A (en) * | 2013-02-06 | 2013-05-22 | 山河建设集团有限公司 | Construction elevator suspending over basement roof of building and construction method thereof |
CN105625454B (en) * | 2016-03-01 | 2017-06-20 | 沈阳建筑大学 | The separate house cross concrete foundation that a kind of concrete segment is poured |
CN105625458B (en) * | 2016-03-01 | 2018-01-30 | 沈阳建筑大学 | A kind of concrete slab pours separate house cross basis |
CN105625452B (en) * | 2016-03-01 | 2017-11-10 | 沈阳建筑大学 | A kind of separate house in-line concrete foundation poured with concrete segment |
CN108894430B (en) * | 2017-01-03 | 2020-06-16 | 河北中郸建设有限公司 | Construction method for reinforcing steel structure beam or column |
CN112832455A (en) * | 2019-11-25 | 2021-05-25 | 怀化市恒裕实业有限公司 | Steel structure beam |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2105517U (en) * | 1991-10-17 | 1992-05-27 | 钱久军 | Composite foundation beam |
JPH09256383A (en) * | 1996-03-22 | 1997-09-30 | Fujita Corp | Erection method of steel framed column |
CN1189561A (en) * | 1997-01-27 | 1998-08-05 | 环境建筑技术有限公司 | Building construction method |
JP3169887B2 (en) * | 1998-04-02 | 2001-05-28 | 大和ハウス工業株式会社 | Column base structure of steel pipe column and its construction method |
-
2004
- 2004-01-07 JP JP2004002476A patent/JP3763575B2/en not_active Expired - Fee Related
- 2004-12-13 CN CNB2004101011334A patent/CN1329589C/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105332389A (en) * | 2015-11-13 | 2016-02-17 | 燕山大学 | Underground pipe rack erector |
JP2017172308A (en) * | 2016-03-27 | 2017-09-28 | 株式会社南条製作所 | Integrated foundation and integrated foundation construction method |
CN115492376A (en) * | 2022-08-31 | 2022-12-20 | 上海宝冶集团有限公司 | Template supporting method for lattice beams and lattice columns of ultra-large slope broken stone slope |
Also Published As
Publication number | Publication date |
---|---|
CN1329589C (en) | 2007-08-01 |
CN1637210A (en) | 2005-07-13 |
JP3763575B2 (en) | 2006-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4877654B2 (en) | Rigid structure of corner | |
JP2004245035A (en) | Underground beam construction frame and underground beam construction method using the same | |
JP2535722B2 (en) | Reinforcement concrete column and steel beam connection structure and building construction method | |
JP2011089390A (en) | Rigid connection structure of corner section | |
JP3133615U (en) | Exterior wall concrete formwork panel | |
JP2000073381A (en) | Exposed type fixed column base in steel steel-structured building, installation structure thereof, and its construction method | |
JP2004263507A (en) | Building foundation construction method and building foundation structure | |
JPH06264453A (en) | Precast concrete-made permanent form for foundation, and foundation practice using its form | |
JP2737099B2 (en) | Construction method of underground beam reinforcing bars and underground beams | |
JP2004360411A (en) | Form construction method and accessory plate | |
JP2813605B2 (en) | Construction foundation and construction method | |
JPH09264029A (en) | Foundation for construction, foundation structure using it and execution of works thereof | |
JP4460357B2 (en) | Construction method of underground concrete structure | |
JP7288390B2 (en) | Foundation construction method and foundation | |
JPH10219708A (en) | Precast concrete block for continuous footing and continuous footing method by use thereof | |
JP3729890B2 (en) | Single-sided precast concrete underground beam and its components | |
JPH0376929A (en) | Steel-framed foundation | |
JP2004027647A (en) | Steel structure of house, and its construction method | |
JPH06341167A (en) | Working method for concrete structure | |
KR20030085264A (en) | soil sheathing method of rahmaen frame using prestress support and bracket and bracket thereof | |
JP2520364B2 (en) | Construction method of underground structure | |
JPH07286332A (en) | Execution method of precast concrete foundation and installation spacer used therefor | |
JP2021105272A (en) | Precast floor slab construction method | |
JPH11140883A (en) | Positioning support device for anchor bolt for construction of foundation | |
JPH11172689A (en) | Anchoring method of leg section of steel-framed column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20040705 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20040730 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20050729 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20050804 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050906 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051020 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060111 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060116 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090127 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100127 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110127 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120127 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120127 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130127 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140127 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |