JP2004238993A - Impervious structure of revetment, and construction method for revetment - Google Patents

Impervious structure of revetment, and construction method for revetment Download PDF

Info

Publication number
JP2004238993A
JP2004238993A JP2003031079A JP2003031079A JP2004238993A JP 2004238993 A JP2004238993 A JP 2004238993A JP 2003031079 A JP2003031079 A JP 2003031079A JP 2003031079 A JP2003031079 A JP 2003031079A JP 2004238993 A JP2004238993 A JP 2004238993A
Authority
JP
Japan
Prior art keywords
seawall
steel pipe
revetment
water
precast plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003031079A
Other languages
Japanese (ja)
Other versions
JP4104467B2 (en
Inventor
Hironori Fukazawa
深沢裕紀
Atsushi Hashimoto
橋本敦史
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2003031079A priority Critical patent/JP4104467B2/en
Publication of JP2004238993A publication Critical patent/JP2004238993A/en
Application granted granted Critical
Publication of JP4104467B2 publication Critical patent/JP4104467B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide the impervious structure of a revetment and a construction method for the revetment dispensing with form removing work underwater and causing little unevenness in laying an impervious sheet. <P>SOLUTION: After improving the ground near the lower part of the revetment, a steel pipe sheet pile 3 is driven, and a precast slab 2 is installed with a prescribed space to the steel pipe sheet pile 3. A filler 4 is filled in a clearance between the steel pipe sheet pile 3 and the precast slab 2, and the impervious sheet 5 is laid in multilayer structure on the surface of the precast slab 2 to construct the impervious structure of the revetment. <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、水域を仕切って内側に埋立てをおこなう際に構築する護岸の遮水構造及び護岸の施工方法に関するものである。
【0002】
【従来の技術】
山間部のV字谷などを利用して建設が進められてきた最終処分場の建設が、近時海上での建設に移行してきている。その主な理由は、建設に適した場所の確保が困難となってきたことの他、処分場内の汚水(浸出水)の地下への漏洩に対する不安から生じた建設反対運動の激化などである。そこで、市民の生活拠点から離れて、広範な面積を有する海上での処分場建設が進められている。
上記の海上処分場の建設に際しては、まず、ケーソン設置により、あるいは水中コンクリートbの現場打ちにより処分場の外郭を構成する護岸を建設する。
護岸を水中コンクリートbの現場打ちによりおこなう場合は、例えば鋼製型枠aを設置した後に水中コンクリートbの打設をおこない、水中コンクリートbの硬化を待って鋼製型枠aの脱型をおこなっている(図8参照)。その後、コンクリート壁の護岸内側面に遮水シートを敷設して遮水構造を形成することで海上処分場が構築される。
【0003】
【発明が解決しようとする課題】
前記した従来の護岸の遮水構造及び護岸の施工方法にあっては、次のような問題点がある。
<イ>護岸の構築は、鋼製型枠等を設置後、水中コンクリートを打設し、水中コンクリートの硬化をまって型枠を脱型することによりおこなわれるが、型枠の設置や脱型が水中作業となるため作業性や工期の長期化といった問題がある。
<ロ>鋼管矢板面や水中コンクリート面に遮水シートを取り付ける場合、取り付け面が平滑でないために遮水シートにむらが生じるとともに、遮水シートの取り付けが困難となる。
【0004】
【発明の目的】
本発明は上記したような従来の問題を解決するためになされたもので、護岸の構築に要する水中作業量を低減できる護岸の遮水構造及び護岸の施工方法を提供することを目的とする。また、遮水シートの取り付けに際し、遮水シートにむらが生じ難い護岸の遮水構造及び護岸の施工方法を提供することを目的とする。また、遮水性能に優れた護岸の遮水構造及び護岸の施工方法を提供することを目的とする。
本発明は、これらの目的の少なくとも一つを達成するものである。
【0005】
【課題を解決するための手段】
上記のような目的を達成するために、水域を仕切って内側に埋立てをおこなう際に構築する本発明の護岸の遮水構造は、前記護岸下部付近の地盤を改良した改良地盤と、前記護岸の外水側に設けた鋼管矢板と、前記鋼管矢板の前記護岸の内側に設けたプレキャスト版と、前記鋼管矢板と前記プレキャスト版との間隙に打設した充填材とからなることを特徴とする護岸の遮水構造である。
また、本発明の護岸の遮水構造は、前記プレキャスト版の前記護岸の内側に遮水シートを設けることができる。なお、遮水シートは多層構造とすることもできる。
さらに、前記護岸の遮水構造を構築する本発明の護岸の施工方法は、前記護岸下部付近に改良地盤を造成する地盤改良工程と、前記鋼管矢板を設置する鋼管矢板設置工程と、前記鋼管矢板の前記護岸の内側にプレキャスト版を設置するプレキャスト版設置工程と、前記鋼管矢板と前記プレキャスト版との間隙に前記充填材を充填する充填材施工工程と、前記プレキャスト版の前記護岸の内側に前記遮水シートを設置する遮水シート設置工程とからなる施工方法である。
【0006】
【発明の実施の形態】
以下、図面を参照しながら本発明の実施の形態について説明する。
【0007】
<イ>護岸
本発明において、護岸1とは水域を仕切って内側に埋立てをおこなう際に構築する仕切り堤のことである。例えば、海に埋立地を建設する場合に構築する、埋立地を囲繞する護岸1がこれに相当する(図1参照)。護岸1を構築後、護岸内側71は一般廃棄物などの処分施設として利用することができる。
本発明は、鋼管矢板3と後述する充填材4の合成構造により護岸を構築する場合の遮水構造に関するものである(図2、図3、図4参照)。
【0008】
海面に護岸1を構築する場合、構築護岸1下の海底地盤が軟弱である場合や地耐力が確保できない場合には公知のサンドコンパクションパイル工法(SCP工法)や公知の深層混合処理工法(CDM工法)などの地盤改良を先行施工することによりおこなわれる。また、処分場の供用開始後において、所定の廃棄物投入時点における常時や地震時等の護岸1(堰堤)の安定性の検討(円弧すべり、滑動等)をおこない、供用開始後の護岸1の安定性を確保する必要が生じた場合にも前記の地盤改良をおこなうことができる。ここで、サンドコンパクションパイル工法とは、上部に振動機(バイブロハンマー)を取り付けたケーシングパイプを地中に打設し、ケーシング内部に砂を投入しながらケーシングパイプを引抜き、さらに打ち戻すことによって、パイプ径よりも太く締まった改良地盤(砂杭61)を造成していく工法のことである。一方、深層混合処理工法(CDM工法)とは、セメント系スラリーまたはモルタルと軟弱地盤を撹拌混合し、原位置で所定の強度に固化させることにより改良地盤(深層混合処理土62)を造成する工法のことである。
海底地盤に砂杭61や深層混合処理土62を造成する場合は、図5(a)に示すように、地盤改良船91などを使用することによりおこなうことができる。
なお、海底地盤の地盤改良方法は上記のSCP工法やCDM工法に拘泥するものではなく、所望の改良効果が発揮できる工法であれば、工期やコストなどを勘案しながら使用することができる。
【0009】
地盤改良施工後、本発明の護岸1の構成要素である鋼管矢板3を打設する。海底地盤に鋼管矢板3を打設する場合は、図5(b)に示すように杭打ち船92などを使用することによりおこなうことができる。なお、鋼管矢板3を一定の間隔をもって2列に並列設置し、相対する鋼管矢板3の夫々の頭部をタイロッド31にて連結させ、並列した鋼管矢板3の間に中詰材などを充填することにより構成した二重鋼管矢板式護岸とすることもできる(図6(a)参照)。
【0010】
<ロ>遮水構造
処分場における遮水構造の目的は、不透水層や難透水層などの地盤を利用したものや、表面遮水として人工材料を利用してごみの保有水や埋立地内に降った雨水(浸出水)による公共水域や地下水への汚染を防止し、ならびにこれらに起因する周辺環境への悪影響を防ぐことにある。海面処分場の場合の遮水構造は、遮水シート5などの人工材料を利用して形成することができる。表面遮水工は、埋立地底部及び法面の全表面に遮水工を施し、水を貯める容器を作るようなものである。
本発明における遮水構造は、鋼管矢板3と充填材4とプレキャスト版2および遮水シート5の多重構造にて成形するものである。ここで、遮水シート5は2重ないし3重の多層構造とするのが好ましい。
遮水シートとしては、合成ゴム系、合成樹脂系、アスファルト系、ベントナイト系、積層タイプ複合系などのシートを使用することができる。合成ゴム系シートとしては、例えば、エチレンプロピレンジエンモノマーシートやEPDM繊維複合シート、ポリオレフィン系エラストマ−シートなどが使用できる。合成樹脂系シートとしては、例えば、ポリ塩化ビニルシートや高密度ポリエチレンシート、ポリウレタンシートなどが使用できる。アスファルト系シートとしては、例えば、全層含浸タイプアスファルトシートや積層タイプアスファルトシートなどが使用できる。
【0011】
遮水シート5の敷設方法は、図7に示すように、クレーン船93などにより遮水シート5を吊り下げながら後述するプレキャスト版2の表面に敷設することによりおこなうことができる。この場合、遮水シート5の設置や遮水シート5同士の重ね部のロープ固定などを潜水士95にておこなうことができる。遮水シート5は後述のプレキャスト版2に取り付け金具8にて取り付けることができる。
【0012】
<ハ>プレキャスト版
プレキャスト版2は、鋼管矢板3の護岸1の内側に、鋼管矢板3と所定の間隔をもって設置し、鋼管矢板3及びプレキャスト版2の間隙に後述する充填材4を充填するためのものである。プレキャスト版2自体も所定の強度および不透水性を備えることにより、遮水構造の構成部材として、また護岸1の構造部材としての効果が期待できる。
従来の鋼製型枠aを仮設して水中コンクリートbを打設する方法では、型枠の設置や脱型が水中作業となるため作業性や工期の長期化といった問題が生じていたが、プレキャスト版2を設置することにより型枠の脱型作業が不要となり、上記の問題を解消することができる。また、プレキャスト版2の表面を平滑に成形することにより、遮水シート5の敷設に際してシートのむらなどが生じることもなくなり、特にシート重ね部からの浸出水の漏洩の危険が解消される。
プレキャスト版2は、例えばセメント系材料にて製作することができる。
【0013】
所定の大きさに製作したプレキャスト版2を、クレーン船93などにより、鋼管矢板3の護岸1の内側に、鋼管矢板3に取り付けられたCT鋼81に添わせて下ろし、所定の間隔をもって設置する。なお、設置に際しては潜水士95により設置精度の確保をおこなうことができる(図6(a)参照)。
【0014】
<ニ>充填材
プレキャスト版2を設置後、鋼管矢板3とプレキャスト版2の間隙に充填材4を充填することにより、鋼管矢板3とプレキャスト版2の一体化を図ることができる。充填材4としては、例えば水中コンクリートを使用することができる。
充填材4の打設は、図6(b)に示すようにミキサー船94などにより打設することができる。
充填材4の打設後、鋼管矢板3の上部に上部コンクリート41を打設することにより、鋼管矢板3上部の保護および連続する鋼管矢板3を上部で一体化させることができる。
【0015】
【実施例】
以下、図を参照しながら本発明の護岸の施工方法の実施例について説明する。
【0016】
<ホ>地盤改良工程
護岸1下部付近にサンドコンパクションパイル工法や深層混合処理工法などを施して改良地盤を造成する(図5(a)参照)。この際、護岸1の円弧すべり等(供用開始後のごみの荷重を含む)の検討結果を考慮して、砂杭61造成区域と深層混合処理土62造成区域を区分けした複数の地盤改良工法を併用することもできる。すなわち、砂杭61は砂の有するせん断抵抗摩擦力が発揮できるように、また深層混合処理土62は混合処理土の有するせん断抵抗粘着力が発揮できるように夫々の改良区域を設定するものである。
また、護岸内側71であって鋼管矢板3近傍の海底地盤面(砂杭61及び深層混合処理土62の上面)を事前混合処理土63にて置き換える置換工法を使用することもできる。本工法を使用することにより、海底地盤面(事前混合処理土63の上面)を平滑に成形し、遮水シート5の敷設に際してシートのむらなどが生じることもなくなり、護岸1と護岸内側71の底面との取り合い部の遮水性を高めることができる。なお、事前混合処理土63の流出防止対策として、図6(a)に示すように岩ずり64などで押え盛土を構築するのが好ましい。なお、上記の置換工法は、最下段のプレキャスト版2を設置した後におこなうことにより、充填材4を打設する際の底型枠の役割を果たすことができる。
【0017】
<ヘ>鋼管矢板設置工程
地盤改良工程にて護岸1下部付近にサンドコンパクションパイル工法や深層混合処理工法などを施した後、鋼管矢板3を海底地盤に打設する。鋼管矢板3の打設は杭打ち船92などによりおこなうことができる(図5(b)参照)。なお、鋼管矢板3を一定の間隔をもって2列に並列設置し、相対する鋼管矢板3の夫々の頭部をタイロッド31にて連結させ、並列した鋼管矢板3の間に中詰材などを充填することにより構成した二重鋼管矢板式護岸とすることもできる。かかる場合は、並列した鋼管矢板を打設してタイロッド31にて連結させた後に後述するプレキャスト版設置工程に移行するのが好ましい。また、上記の中詰材の充填は鋼管矢板3を打設した後であっても、後述する遮水シート設置工程の後であってもよい。
【0018】
<ト>プレキャスト版設置工程
鋼管矢板設置工程の後、所定の大きさに製作したプレキャスト版2をクレーン船93にて吊り下げながら、鋼管矢板3の護岸1の内側に鋼管矢板3と所定の間隔をもって設置していく。プレキャスト版2の設置は水中作業となることから潜水士95による所定位置へのプレキャスト版2の取り付け及び取り付けの精度確保を図ることを要する(図6(a)参照)。
【0019】
<チ>充填材施工工程
プレキャスト版設置工程の後、鋼管矢板3とプレキャスト版2の間隙に充填材4を充填する。充填材4の打設はミキサー船94などにより打設することができる(図6(b)参照)。
【0020】
<リ>遮水シート設置工程
充填材施工工程の後、クレーン船93を使用してプレキャスト版2の表面に遮水シート5の設置をおこなう。すなわち、クレーン船93にて遮水シート5を吊り下げ、潜水士95によりプレキャスト版2の表面に取り付け金具8にて取り付ける。遮水シートは2重ないし3重の多層構造とするのが好ましい。また、遮水シート5の重ね部などは潜水士95によりロープ固定を施すことができる。なお、遮水シート5は、護岸内側71の水を抜いた後に敷設することもできる。さらに、遮水シート5の重ね部は、護岸内側71の水を抜いた後に溶着により接合させることもできる。
【0021】
【発明の効果】
本発明の護岸の遮水構造及び護岸の施工方法は以上説明したようになるから次のような効果を得ることができる。
<イ>プレキャスト版を使用するため、水中における型枠脱型作業などが必要でなくなり、作業性の向上と工期の短縮を図ることができる。
<ロ>表面を平滑に製作したプレキャスト版を使用するため、遮水シートの取り付け面が平滑となり遮水シートにむらが生じ難くなることから、品質の向上を図ることができる。
【図面の簡単な説明】
【図1】本発明の遮水構造を備えた護岸を囲繞するように構築した実施例を説明した斜視図。
【図2】本発明の護岸の遮水構造を説明した断面図であって、図1のA−A矢視図。
【図3】本発明の護岸の遮水構造を説明した護岸の正面図。
【図4】(a)図3のB−B矢視図。(b)図3のC−C矢視図。
【図5】(a)本発明の護岸の施工方法のうち、地盤改良工程を説明した説明図。(b)鋼管矢板設置工程を説明した説明図。
【図6】(a)本発明の護岸の施工方法のうち、プレキャスト版設置工程を説明した説明図。(b)充填材施工工程を説明した説明図。
【図7】本発明の護岸の施工方法のうち、遮水シート設置工程を説明した説明図。
【図8】従来の護岸の施工方法において、水中にて型枠を脱型していることを説明した説明図。
【符号の説明】
1・・・護岸
2・・・プレキャスト版
3・・・鋼管矢板
4・・・充填材
5・・・遮水シート
71・・護岸内側
72・・外水側
[0001]
TECHNICAL FIELD OF THE INVENTION
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a water barrier structure for a seawall and a method for constructing a seawall to be constructed when a water area is partitioned and landfilled inside.
[0002]
[Prior art]
Construction of the final disposal site, which has been under construction using a V-shaped valley in the mountains, has recently shifted to offshore construction. The main reasons for this were the difficulty in securing a suitable place for construction, and the intensified anti-construction movement caused by concerns about leakage of sewage (leaching water) in the disposal site to the underground. Therefore, construction of a disposal site on the sea, which has a wide area, is being promoted away from the base of citizens' lives.
When constructing the above-mentioned marine disposal site, first, a seawall constituting the outer periphery of the disposal site is constructed by installing a caisson or by casting an underwater concrete b in place.
When the revetment is performed by casting the underwater concrete b in place, for example, the steel formwork a is installed, then the underwater concrete b is cast, and after the underwater concrete b hardens, the steel formwork a is released. (See FIG. 8). After that, a marine disposal site is constructed by laying a seepage control sheet on the inner side of the seawall of the concrete wall to form a seepage control structure.
[0003]
[Problems to be solved by the invention]
The above-mentioned conventional water barrier structure of the seawall and the method of construction of the seawall have the following problems.
<B> The revetment is constructed by installing steel formwork, placing underwater concrete, hardening the underwater concrete, and removing the formwork. However, there is a problem that the workability and the construction period are prolonged because of the underwater work.
<B> When attaching a water-impervious sheet to a steel pipe sheet pile surface or underwater concrete surface, the mounting surface is not smooth, so that the water-impervious sheet becomes uneven and it becomes difficult to attach the water-impervious sheet.
[0004]
[Object of the invention]
The present invention has been made in order to solve the above-described conventional problems, and an object of the present invention is to provide a seawall impermeable structure and a seawall construction method capable of reducing the amount of underwater work required for construction of a seawall. Another object of the present invention is to provide a water barrier structure for a seawall and a method for constructing a seawall where the watertight sheet is unlikely to be uneven when the watertight sheet is attached. It is another object of the present invention to provide a seawall structure and a seawall construction method that are excellent in seawater barrier performance.
The present invention achieves at least one of these objects.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, the seawall structure of the revetment of the present invention to be constructed when partitioning the water area and performing reclamation on the inside, the improved ground in which the ground near the revetment lower portion is improved, and the revetment A steel pipe sheet pile provided on the outside water side of the steel pipe sheet pile, a precast plate provided inside the seawall of the steel pipe sheet pile, and a filler poured into a gap between the steel pipe sheet pile and the precast plate. It is a water barrier structure of a seawall.
In the water barrier structure of a seawall according to the present invention, a watertight sheet can be provided inside the seawall of the precast plate. In addition, the water-blocking sheet may have a multilayer structure.
Further, the method for constructing a seawall of the present invention for constructing the watertight structure of the seawall comprises a soil improvement step of forming an improved ground near the seawall lower part, a steel pipe sheet pile installation step of installing the steel pipe sheet pile, and the steel pipe sheet pile. A precast plate installation step of installing a precast plate inside the seawall, a filler material installation step of filling the gap between the steel pipe sheet pile and the precast plate with the filler material, and the inside of the seawall of the precast plate. This is a construction method including a water-impervious sheet installation step of installing a water-impervious sheet.
[0006]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0007]
<A> Seawall In the present invention, seawall 1 is a partition embankment constructed when partitioning a water area and performing reclamation inside. For example, a revetment 1 surrounding a landfill, which is constructed when a landfill is constructed in the sea, corresponds to this (see FIG. 1). After the revetment 1 is constructed, the revetment inside 71 can be used as a disposal facility for general waste and the like.
The present invention relates to a water barrier structure when a seawall is constructed by a composite structure of a steel pipe sheet pile 3 and a filler 4 described later (see FIGS. 2, 3 and 4).
[0008]
When the revetment 1 is constructed on the sea surface, when the seabed under the constructed revetment 1 is soft or the bearing capacity cannot be secured, a known sand compaction pile method (SCP method) or a known deep mixing method (CDM method) ) Etc. are carried out by preceding construction. In addition, after the operation of the disposal site, the stability of the revetment 1 (dams) at all times at the time of the predetermined waste input or during an earthquake, etc. (arc sliding, sliding, etc.) will be examined. The above-described ground improvement can be performed even when it is necessary to ensure stability. Here, with the sand compaction pile method, a casing pipe with a vibrator (vibratory hammer) attached to the upper part is poured into the ground, the casing pipe is pulled out while sand is charged inside the casing, and further driven back, This is a method of creating an improved ground (sand pile 61) that is tightened thicker than the pipe diameter. On the other hand, the deep mixing processing method (CDM method) is a method of forming an improved ground (deep mixing processing soil 62) by stirring and mixing a cement-based slurry or mortar and soft ground to a predetermined strength in situ. That is.
When the sand pile 61 and the deep mixed treated soil 62 are formed on the seabed ground, as shown in FIG. 5A, it can be performed by using a ground improvement ship 91 or the like.
The method for improving the ground of the seabed is not limited to the above-described SCP method and CDM method, and any method capable of exhibiting a desired improvement effect can be used while taking into account the construction period and cost.
[0009]
After the ground improvement work, the steel pipe sheet pile 3 which is a component of the revetment 1 of the present invention is cast. When the steel pipe sheet pile 3 is driven into the seabed, the pile driving ship 92 can be used as shown in FIG. 5B. In addition, the steel pipe sheet piles 3 are arranged in parallel in two rows at a fixed interval, the respective heads of the opposed steel pipe sheet piles 3 are connected by tie rods 31, and a filling material or the like is filled between the parallel steel pipe sheet piles 3. Thus, a double steel pipe sheet pile type revetment can be provided (see FIG. 6A).
[0010]
<B> Water-blocking structure The purpose of the water-blocking structure at the disposal site is to use the ground, such as an impermeable layer or a poorly permeable layer, or use artificial materials as surface water-blocking, and use the water in the garbage or in the landfill. The purpose of the present invention is to prevent pollution of public waters and groundwater by rainwater (leaching water) that has fallen, and to prevent adverse effects on the surrounding environment due to these. In the case of a sea surface disposal site, the impermeable structure can be formed using an artificial material such as the impermeable sheet 5. Surface impervious works are like applying impervious works to the bottom of a landfill and the entire surface of a slope to create a container for storing water.
The impermeable structure in the present invention is formed by a multi-layered structure of the steel pipe sheet pile 3, the filler 4, the precast plate 2, and the impermeable sheet 5. Here, it is preferable that the water shielding sheet 5 has a double or triple multilayer structure.
As the water-blocking sheet, a sheet of a synthetic rubber type, a synthetic resin type, an asphalt type, a bentonite type, a laminated type composite type or the like can be used. Examples of the synthetic rubber-based sheet include an ethylene propylene diene monomer sheet, an EPDM fiber composite sheet, and a polyolefin-based elastomer sheet. Examples of the synthetic resin sheet include a polyvinyl chloride sheet, a high-density polyethylene sheet, and a polyurethane sheet. As the asphalt-based sheet, for example, an all-layer impregnated-type asphalt sheet or a laminated-type asphalt sheet can be used.
[0011]
As shown in FIG. 7, the method of laying the water-impervious sheet 5 can be performed by laying the water-impervious sheet 5 on the surface of a precast plate 2 described later while suspending the water-impervious sheet 5 by a crane ship 93 or the like. In this case, the diver 95 can perform the installation of the impermeable sheet 5 and the fixing of the rope at the overlapping portion between the impermeable sheets 5. The water-blocking sheet 5 can be attached to the precast plate 2 described later with the attachment fitting 8.
[0012]
<C> Precast plate The precast plate 2 is installed inside the revetment 1 of the steel pipe sheet pile 3 at a predetermined interval from the steel pipe sheet pile 3 and fills a gap between the steel pipe sheet pile 3 and the precast plate 2 with a filler 4 described later. belongs to. Since the precast plate 2 itself also has a predetermined strength and water impermeability, it can be expected to have an effect as a constituent member of the water barrier structure and as a structural member of the seawall 1.
In the conventional method of placing the steel formwork a temporarily and casting the underwater concrete b, the installation and demolding of the formwork are underwater work, so that problems such as workability and prolonged construction time have occurred. By disposing the plate 2, the work of removing the formwork is not required, and the above problem can be solved. In addition, by shaping the surface of the precast plate 2 into a smooth surface, unevenness of the sheet when laying the impermeable sheet 5 does not occur, and the danger of leaking out of the leachate from the sheet overlapping portion is eliminated.
The precast plate 2 can be made of, for example, a cement-based material.
[0013]
The precast plate 2 manufactured to a predetermined size is lowered by a crane ship 93 or the like along the CT steel 81 attached to the steel pipe sheet pile 3 inside the seawall 1 of the steel pipe sheet pile 3 and is installed at a predetermined interval. . At the time of installation, the diver 95 can ensure the installation accuracy (see FIG. 6A).
[0014]
<D> After the filler precast plate 2 is installed, the gap between the steel pipe sheet pile 3 and the precast plate 2 is filled with the filler material 4, whereby the steel pipe sheet pile 3 and the precast plate 2 can be integrated. As the filler 4, for example, underwater concrete can be used.
As shown in FIG. 6B, the filling material 4 can be cast by a mixer ship 94 or the like.
By placing the upper concrete 41 on the upper part of the steel pipe sheet pile 3 after placing the filler material 4, the protection of the upper part of the steel pipe sheet pile 3 and the continuous steel pipe sheet pile 3 can be integrated at the upper part.
[0015]
【Example】
Hereinafter, an embodiment of the seawall construction method of the present invention will be described with reference to the drawings.
[0016]
<E> Ground improvement process An improved ground is created near the lower part of the revetment 1 by sand compaction pile method or deep mixing method (see Fig. 5 (a)). At this time, in consideration of the results of the examination of the arc slide of the revetment 1 (including the load of the refuse after the start of operation), a plurality of ground improvement methods that divide the sand pile 61 formation area and the deep mixed treated soil 62 formation area into They can be used together. That is, the sand pile 61 sets the respective improved areas so that the shear resistance frictional force of the sand can be exhibited, and the deep mixed soil 62 can exhibit the shear resistance adhesive force of the mixed soil. .
Further, a replacement method in which the seabed ground surface (the upper surface of the sand pile 61 and the deep mixed soil 62) near the steel pipe sheet pile 3 on the seawall 71 is replaced with the premixed soil 63 may be used. By using this method, the seafloor ground surface (the upper surface of the premixed soil 63) is formed smoothly, and the laying of the impermeable sheet 5 does not cause unevenness of the sheet. And the water-shielding of the connection portion can be increased. As a countermeasure for preventing the premixed soil 63 from flowing out, it is preferable to construct the embankment with rocks 64 or the like as shown in FIG. In addition, the above-mentioned replacement method can play a role of a bottom form when the filler 4 is cast by performing after the lowermost precast plate 2 is installed.
[0017]
<F> Steel pipe sheet pile installation process In the ground improvement process, sand compaction pile method or deep mixing method is applied near the lower part of the revetment 1 and then the steel pipe sheet pile 3 is cast on the seabed ground. The driving of the steel pipe sheet pile 3 can be performed by a pile driving boat 92 or the like (see FIG. 5B). In addition, the steel pipe sheet piles 3 are arranged in parallel in two rows at a fixed interval, the respective heads of the opposed steel pipe sheet piles 3 are connected by tie rods 31, and a filling material or the like is filled between the parallel steel pipe sheet piles 3. The double-walled sheet pile type revetment constructed in this way can also be used. In such a case, it is preferable to shift to a precast plate installation step described later after driving parallel steel pipe sheet piles and connecting them with tie rods 31. The filling of the filling material may be performed after the steel sheet pile 3 is cast or after a water-impervious sheet installation step described later.
[0018]
<G> Precast plate setting process After the steel pipe sheet pile setting process, the precast plate 2 manufactured to a predetermined size is suspended by the crane ship 93 while the steel pipe sheet pile 3 is provided inside the seawall 1 at a predetermined interval. We will set up with. Since the installation of the precast plate 2 is an underwater operation, it is necessary to ensure the mounting of the precast plate 2 at a predetermined position by the diver 95 and to ensure the accuracy of the mounting (see FIG. 6A).
[0019]
<H> Filling Material Application Step After the precast plate setting step, the gap between the steel pipe sheet pile 3 and the precast plate 2 is filled with the filler 4. The filling material 4 can be cast by a mixer ship 94 or the like (see FIG. 6B).
[0020]
<I> Water Impermeable Sheet Installation Process After the filling material application process, the water impermeable sheet 5 is installed on the surface of the precast plate 2 using the crane ship 93. That is, the impermeable sheet 5 is suspended by the crane ship 93, and the diver 95 attaches the impermeable sheet 5 to the surface of the precast plate 2 with the mounting bracket 8. It is preferable that the water impermeable sheet has a double or triple multilayer structure. In addition, the diver 95 can fix the rope on the overlapping portion of the water-blocking sheet 5 and the like. The impermeable sheet 5 can also be laid after draining the water on the inner revetment wall 71. Further, the overlapping portion of the water-blocking sheet 5 can be joined by welding after draining the water on the inside of the seawall 71.
[0021]
【The invention's effect】
The water barrier structure of the revetment and the method of constructing the revetment of the present invention are as described above, and the following effects can be obtained.
<A> Since the precast plate is used, it is not necessary to remove the mold from the mold in water, and the workability can be improved and the construction period can be shortened.
<B> Since a precast plate manufactured with a smooth surface is used, the mounting surface of the water-impervious sheet becomes smoother and unevenness of the water-impervious sheet is less likely to occur, so that quality can be improved.
[Brief description of the drawings]
FIG. 1 is a perspective view illustrating an embodiment constructed so as to surround a seawall provided with a water shielding structure of the present invention.
FIG. 2 is a cross-sectional view illustrating a water barrier structure of a seawall according to the present invention, and is a view taken along the line AA in FIG.
FIG. 3 is a front view of the revetment for explaining the water barrier structure of the revetment of the present invention.
FIG. 4A is a view taken in the direction of arrows BB in FIG. (B) The CC arrow view of FIG.
FIG. 5 (a) is an explanatory view illustrating a ground improvement step in the seawall construction method of the present invention. (B) Explanatory drawing explaining the steel pipe sheet pile installation process.
FIG. 6 (a) is an explanatory view illustrating a precast plate installation step in the seawall construction method of the present invention. (B) Explanatory drawing explaining the filling material construction process.
FIG. 7 is an explanatory view illustrating a water-impervious sheet installation step in the seawall construction method of the present invention.
FIG. 8 is an explanatory view for explaining that a formwork is removed underwater in a conventional seawall construction method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Revetment 2 ... Precast plate 3 ... Steel pipe sheet pile 4 ... Filling material 5 ... Waterproof sheet 71 ... Inside of revetment 72 ... Outside water side

Claims (3)

水域を仕切って内側に埋立てをおこなう際に構築する護岸の遮水構造であって、
前記護岸下部付近の地盤を改良した改良地盤と、
前記護岸の外水側に設けた鋼管矢板と、
前記鋼管矢板の前記護岸の内側に設けたプレキャスト版と、
前記鋼管矢板と前記プレキャスト版との間隙に打設した充填材とからなることを特徴とする、
護岸の遮水構造。
It is a water barrier structure of a revetment built when partitioning the water area and reclaiming it inside.
Improved ground that improved the ground near the seawall lower part,
Steel pipe sheet piles provided on the outer water side of the seawall,
A precast plate provided inside the seawall of the steel pipe sheet pile,
It is characterized by comprising a filler poured into the gap between the steel pipe sheet pile and the precast plate,
Water barrier structure of revetment.
前記プレキャスト版の前記護岸の内側に遮水シートを設けたことを特徴とする請求項1記載の護岸の遮水構造。The water barrier structure of a seawall according to claim 1, wherein a waterproof sheet is provided inside the seawall of the precast plate. 請求項1又は2記載の護岸の遮水構造を構築する護岸の施工方法であって、
前記護岸下部付近に改良地盤を造成する地盤改良工程と、
前記鋼管矢板を設置する鋼管矢板設置工程と、
前記鋼管矢板の前記護岸の内側にプレキャスト版を設置するプレキャスト版設置工程と、
前記鋼管矢板と前記プレキャスト版との間隙に前記充填材を充填する充填材施工工程と、
前記プレキャスト版の前記護岸の内側に前記遮水シートを設置する遮水シート設置工程とからなることを特徴とする、
護岸の施工方法。
A seawall construction method for constructing a seawall impermeable structure according to claim 1 or 2,
Ground improvement process of creating an improved ground near the seawall lower part,
Steel pipe sheet pile installation step of installing the steel pipe sheet pile,
A precast plate installation step of installing a precast plate inside the seawall of the steel pipe sheet pile,
A filler application step of filling the filler in the gap between the steel pipe sheet pile and the precast plate,
A water-impervious sheet installation step of installing the water-impervious sheet inside the seawall of the precast plate,
Construction method of revetment.
JP2003031079A 2003-02-07 2003-02-07 Seawall structure and seawall construction method Expired - Lifetime JP4104467B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003031079A JP4104467B2 (en) 2003-02-07 2003-02-07 Seawall structure and seawall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003031079A JP4104467B2 (en) 2003-02-07 2003-02-07 Seawall structure and seawall construction method

Publications (2)

Publication Number Publication Date
JP2004238993A true JP2004238993A (en) 2004-08-26
JP4104467B2 JP4104467B2 (en) 2008-06-18

Family

ID=32957781

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003031079A Expired - Lifetime JP4104467B2 (en) 2003-02-07 2003-02-07 Seawall structure and seawall construction method

Country Status (1)

Country Link
JP (1) JP4104467B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103074868A (en) * 2013-01-30 2013-05-01 安徽水利开发股份有限公司 Precast fence plate dam reinforcing method
JP2014104379A (en) * 2012-11-26 2014-06-09 World Engineering Kk Upper concrete impervious structure of revetment impervious wall
KR102099932B1 (en) * 2020-01-22 2020-05-26 이희구 Construction method to prevent scouring using files and panels of offshore berthing facilities
WO2023029779A1 (en) * 2021-09-03 2023-03-09 中铁上海设计院集团有限公司 Channel revetment prefabricated capping beam

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014104379A (en) * 2012-11-26 2014-06-09 World Engineering Kk Upper concrete impervious structure of revetment impervious wall
CN103074868A (en) * 2013-01-30 2013-05-01 安徽水利开发股份有限公司 Precast fence plate dam reinforcing method
KR102099932B1 (en) * 2020-01-22 2020-05-26 이희구 Construction method to prevent scouring using files and panels of offshore berthing facilities
WO2023029779A1 (en) * 2021-09-03 2023-03-09 中铁上海设计院集团有限公司 Channel revetment prefabricated capping beam

Also Published As

Publication number Publication date
JP4104467B2 (en) 2008-06-18

Similar Documents

Publication Publication Date Title
JP4761780B2 (en) Construction method of impermeable layer
US11560686B2 (en) Membrane-lined wall
US8882397B2 (en) Methods for waterproofing depositing sites
JP4293435B2 (en) Construction method of managed revetment
CN107700521B (en) Building foundation reinforcement underpinning pier and construction method thereof
JP2004238993A (en) Impervious structure of revetment, and construction method for revetment
JP5099709B2 (en) Construction method of managed revetment
JP4315620B2 (en) Impermeable treatment method for managed waste landfill revetment
JP5728206B2 (en) Construction method of partition revetment
JP2004211533A (en) Revetment for reclamation and its construction method
JP6241167B2 (en) Seismic reinforcement method for jetty
JP2004108078A (en) Construction method for underwater shaft, underwater shaft, connection method for shaft and adit, and pit structure
JP2007247309A (en) Construction method of seepage control processing layer
JP4606454B2 (en) Construction method of managed revetment
JP3748615B2 (en) Construction method of cylindrical underground structure
JP2004197307A (en) Soil improving method
JP4139871B2 (en) Steel plate cell revetment
KR101404471B1 (en) Embankment constuction by buoyancy and water pressure on the part prevention of injury and in the force functioning bottom, a mat and execution method for filter
JP2546110B2 (en) Levee structure using excavated sludge and its construction method
JP2003278151A (en) Driving method for steel sheet-pile
JP2581602B2 (en) Waste treatment method
JPH0673739A (en) Cell and cell structure
JPH09125394A (en) Backfilling technique for burying ditch
JP2003096766A (en) Construction method of cut-off wall
JP2717589B2 (en) Construction method of underground continuous wall on water

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051128

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070712

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070718

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070830

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071127

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080122

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080304

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080325

R150 Certificate of patent or registration of utility model

Ref document number: 4104467

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110404

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110404

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120404

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120404

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130404

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140404

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term