JP2004211422A - Impervious-wall construction method - Google Patents

Impervious-wall construction method Download PDF

Info

Publication number
JP2004211422A
JP2004211422A JP2003000029A JP2003000029A JP2004211422A JP 2004211422 A JP2004211422 A JP 2004211422A JP 2003000029 A JP2003000029 A JP 2003000029A JP 2003000029 A JP2003000029 A JP 2003000029A JP 2004211422 A JP2004211422 A JP 2004211422A
Authority
JP
Japan
Prior art keywords
vertical hole
impermeable wall
adjacent
hole
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003000029A
Other languages
Japanese (ja)
Inventor
Yoshihito Sugizaki
吉仁 杉崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUGIZAKI KISO KK
Original Assignee
SUGIZAKI KISO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUGIZAKI KISO KK filed Critical SUGIZAKI KISO KK
Priority to JP2003000029A priority Critical patent/JP2004211422A/en
Publication of JP2004211422A publication Critical patent/JP2004211422A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide an impervious-wall construction method easily soil-improving the place of an imperfect contact by using a simple device when the imperfect contact is expected for constructing an impervious wall. <P>SOLUTION: In the impervious-wall construction method in which piles (1) are excavated, impervious wall elements (1a) are formed by injecting impervious wall materials (C) into the pits (1) and the impervious walls (10) are built by contacting/continuing the elements (1a). outer pipes (20) for a double packer are inserted previously in side end sections, which are adjoined or may be adjoined to single piles or the elements (1a) in a specified width in the pits (1). The impervious wall materials (C) are injected into the pits (1), injection pipes (30) are inserted into the outer pipes (20) and a soil-improvement agent (C1) is force-fed towards a ground in the vicinity of the contacting sections of the single piles or the elements (1a) in the specified width, which are adjoined or may be adjoined, from the outer pipes (20). <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、遮水壁構築工法に関するもので、さらに詳しくは、従来、代表的に施工されている、縦孔を掘削して、この縦孔内に遮水壁材を注入して単杭又は所定幅の遮水壁エレメントを形成し、この単杭又は遮水壁エレメントを横方向に接触・連続させて遮水壁を構築する遮水壁構築工法に関するものである。
【0002】
【従来の技術】
従来、この種の遮水壁構築工法は、施工例も多く確立された技術として信頼を得ている。しかし、最近はこの遮水壁の要求深度が深くなり、地上で施工するわずかな寸法誤差が、深い部位では誤差が拡大して、大きな誤差となって、遮水壁の連続性が確保できない施工ミスも報告されるようになってきている。
【0003】
すなわち、図1に示す左側の既設遮水壁エレメント1aに、右側の縦孔1を掘削したところ、その鉛直性の精度に多少の誤差があると、深い部位で縦孔1が既設遮水壁エレメント1aより離れてしまう。また、図4及び図9例では、鉛直性の誤差に加えて、幅の広い縦孔1が多少捻られた場合で、同図破線で示す位置が正規の設計上の掘削位置であるが、縦孔1を掘削中、該縦孔1が深くなるにしたがって何らかの事情で鉛直性に誤差が生じ、図左側が図の上方に向くように捻られてしまった場合で、縦孔1を既設遮水壁エレメント1aに一部重なるように掘削しようとしたところ、深い部位では、縦孔1が既設遮水壁エレメント1aより離れてしまった場合である。従って、この様に単杭又は遮水壁エレメント1aが離れてしまうと、この部位での遮水性が全く確保できなくなり、また、土留め機能も期待できなくなるものである。
【0004】
上記のような施工ミスは、無論放置できるものではなく、施工中、又は縦孔を掘削して検尺した結果、誤差が発見されると、縦孔を埋め戻して再度縦孔の掘削を行うか、単杭又は遮水壁エレメント完成後に、別途地上からこの施工不良場所近くまで薬液注入孔を掘削して、地上から地盤改良剤を注入する改良工事を行っている。
【0005】
従来、上記の地盤改良剤を注入する改良工事には、ダブルパッカー工法が汎用されており、その一例は特許文献1にも記載されている。この特許文献1のダブルパッカー工法は、その特許請求の範囲に、所謂、「於いて書」として、「外管としてのスリーブつきパイプと内管としてのインジェクションパイプを組み合わせた2重管を注入管とし、インジェクションパイプにはダブルパッカーを設ける2重管ダブルパッカー工法において、」と記載し、ダブルパッカー工法が公知技術であることが開示されている。なお、本発明との関連において、この特許文献1の段落番号「0006」にはスリーブが、注入ノズルを覆うゴム(ラバー)スリーブであることも開示されている。
【0006】
また、特許文献2には、目的は相違するも、遮水壁の下部の地盤を改良する方法として、「鉄筋籠3の中にパイプ5を所定の配列間隔で、例えば千鳥状に配列する。鉄筋籠3を掘削溝2に建込んでコンクリートを打設した後、前記各パイプ5をガイドとしてジェットボルト6を掘削溝2の溝底部よりさらに深い地層にまで削孔し被圧滞水地層E1に到達させる。次いでジェットボルト6の先端より被圧滞水地層E1の箇所に薬液7を注入し、これを固化させて地質改良を行う」ことが開示されている。
【0007】
そして、上記特許文献1及び特許文献2の技術を応用することで、前記施工不良場所近くの地盤を改良し、遮水性を確保し、土留め機能を確保することができるが、特許文献1のダブルパッカー工法を使用するには、「図9」に示すように、ダブルパッカー用の縦孔H1(ボーリング孔)を別途掘削し、この縦孔H1にダブルパッカー装置を差し込んで薬液を注入して改良地盤部C1aを形成しなくてはならず、工費がかさむという問題点と、ダブルパッカー工法用の縦孔H1を掘削するための余分な工事用スペースが要求され、必ずしもどこの工事現場でも実現できるものではないという問題点を有していた。
【0008】
また、上記特許文献2の工法は、遮水壁の下方の地盤を改良するには問題がないが、図1、図4例のように、縦孔1の側方の地盤改良には適さないもので、特に、径が小さい縦孔1の場合は、該縦孔1内には、特許文献2に記載された長いジェットボルトを、横方向に収納しておくスペースがないという問題点を有している。
【0009】
【特許文献1】特開平8−311855号公報 (特許請求の範囲、図1及び段落番号「0006」)
【特許文献2】特開平6−146270号公報 (図3)
【0010】
【発明が解決しようとする課題】
そこで本発明は上記問題点に鑑みなされたもので、遮水壁の構築に接触不良(連続性不良)が予想される場合、簡易な装置を使用することで、容易に該接触不良箇所の地盤改良を適宜に行え、連続止水性が保証できる遮水壁構築工法を提供することを課題としたものである。
【0011】
【課題を解決するための手段】
本発明は、上記課題を達成するため、縦孔1を掘削して、この縦孔1内に遮水壁材Cを注入して単杭又は所定幅の遮水壁エレメント1aを形成し、この単杭又は遮水壁エレメント1a,1a,1a・・・を横方向に接触・連続させて遮水壁10を構築する遮水壁構築工法において、上記縦孔1内の、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に、ダブルパッカー用の外管20を挿入しておき、上記縦孔1内に遮水壁材Cを注入した後、上記外管20内にインジェクション管30を差し込んで、該外管20より地盤改良剤C1を隣接する又は隣接を予定する単杭又は所定幅の遮水壁エレメント1aの接触部位付近の地盤に向けて圧送するようになしたことを特徴とする技術的手段を講じたものである。
【0012】
それ故、本発明遮水壁構築工法は、遮水壁10を形成するための縦孔1を、ダブルパッカー用の外管20を差し込む孔に兼用しているので、別途ダブルパッカー工法用の縦孔H1(図9参照)を掘削する必要性がなく、縦孔1内に遮水壁材Cを注入した後に地盤改良剤C1を圧送するようになしているので、該地盤改良剤C1を確実に地盤中に圧送・注入できる作用を呈するものである。
【0013】
なお、上記ダブルパッカー用の外管20を利用して地盤改良剤C1を圧送する作用は、従来のダブルパッカー工法と同じ作用で、所望の深さの圧送口(通孔21)より適宜、地盤改良剤C1を圧送できる作用と、地盤改良剤C1の種類を変えて、複数回同じ場所に地盤改良剤C1を圧送することもできる作用を呈するものである。また、この外管20は遮水壁材C内に埋入し、この遮水壁材Cはやがて固化するが、噴射圧送圧を調整することでこの、固化した、又は固化途中の遮水壁材Cを割裂して、地盤改良剤C1を外方に噴出させる作用を呈するものである。
【0014】
次に、請求項2の発明は、縦孔1を掘削して、この縦孔1内に遮水壁材Cを注入して単杭又は所定幅の遮水壁エレメント1aを形成し、この単杭又は遮水壁エレメント1a,1a,1a・・・を横方向に接触・連続させて遮水壁10を構築する遮水壁構築工法において、上記縦孔1内の、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管20を挿入しておき、この外管20には上下方向に所定の間隔で外管圧送口となる通孔21,21,21・・・を該縦孔1の外側に向けて設けると共に、この各通孔21部位は、ゴム状のスリーブ体23で夫々覆い、このスリーブ体23は締着バンド22,22で外管20に締着すると共に、通孔21に適合する位置には、外方先端側が順次縮径される嘴状凸部24を膨出成形し、さらにこの嘴状凸部24の先端部にはスリット状の開口部24aを設け、上記外管20内には、下部に圧送口31を有したインジェクション管30を抜き差し可能に差し込み、このインジェクション管30の圧送口31の上方と下方とには、該インジェクション管30外周面と外管20の内周面との間隙を密閉する一対のパッキン32,32を装着し、上記縦孔1内に遮水壁材Cを注入した後、インジェクション管30を昇降させて、所望の通孔21より、地盤改良剤C1を隣接する又は隣接を予定する単杭又は所定幅の遮水壁エレメント1aの接触部位付近の地盤に向けて圧送するようになしたことを特徴とする技術的手段を講じたものである。
【0015】
それ故、本発明遮水壁構築工法は、請求項1の作用に加えて、外管圧送口となる通孔21をスリーブ体23で覆ってなるので、外管20を建て込んだ縦孔1内に遮水壁材Cを注入しても、あるいは、遮水壁材Cを注入した縦孔1内に外管20を建て込んでも、通孔21,21,21・・・の密閉性は保たれ、外管20内に遮水壁材Cが侵入することを防止する作用を呈するものである。なお、上記スリーブ体23は、締着バンド22,22で外管20に締着してあるので、大きな外力が加わってもずれることが無く、通孔21側より外側に向けて地盤改良材C1の高圧圧送があると、該ゴム帯体23にはスリット状の開口部24aを設けてあるので、この開口部24aが押し開かれて、通孔21よりの地盤改良材C1の圧送を容易に許容し、外管20外方より通孔21の中に向かっての流体の逆流は抑止する作用を呈するものである。
【0016】
そして、スリーブ体23には通孔21の適合部位に予め嘴状突出部24を膨出成型してあるので、この嘴状突出部24を縦孔1の側端部において外方に向けることで、該嘴状突出部24の先端では遮水壁材Cがその分薄くなっていることと、通孔21より圧送される地盤改良材C1の内圧は、先に向かって縮径される嘴状突出部24の先端側に向かって順次高まり、該遮水壁材Cが固化して所定の強度となっていても、この内側よりの大きな圧力で、容易に該遮水壁材Cが破断し、地盤改良材C1の流出を許容する作用を呈するものである。
【0017】
次ぎに、請求項3の発明は、縦孔1を掘削して、この縦孔1内に遮水壁材Cを注入して単杭又は所定幅の遮水壁エレメント1aを形成し、この単杭又は遮水壁エレメント1a,1a,1a・・・を横方向に接触・連続させて遮水壁10を構築する遮水壁構築工法において、上記縦孔1内に建て込む鉄筋籠又は芯材Sの、単杭又は所定幅の遮水壁エレメント1aに隣接する又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管20を固定して取り付け、この外管30を芯材Sと共に縦孔1内に建て込み、上記縦孔1内の、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管20を挿入しておき、この外管20には上下方向に所定の間隔で外管圧送口となる通孔21,21,21・・・を該縦孔1の外側に向けて設けると共に、この各通孔21部位は、ゴム状のスリーブ体23で夫々覆い、このスリーブ体23は締着バンド22,22で外管20に締着すると共に、通孔21に適合する位置には、外方先端側が順次縮径される嘴状凸部24を膨出成形し、さらにこの嘴状凸部24の先端部にはスリット状の開口部24aを設け、上記外管20内には、下部に圧送口31を有したインジェクション管30を抜き差し可能に差し込み、このインジェクション管30の圧送口31の上方と下方とには、該インジェクション管30外周面と外管20の内周面との間隙を密閉する一対のパッキン32,32を装着し、上記縦孔1内に遮水壁材Cを注入した後、インジェクション管30を昇降させて、所望の通孔21より、地盤改良剤C1を隣接した又は隣接を予定する単杭又は所定幅の遮水壁エレメント1aの接触部位付近の地盤に向けて圧送するようになしたことを特徴とする技術的手段を講じたものである。
【0018】
それ故、本発明遮水壁構築工法は、請求項2の作用にさらに加え、縦孔1内に建て込む鉄筋籠又は芯材Hに、ダブルパッカー用の外管20を固定して取り付けたので、該芯材Hの建て込みで、外管20を所望の位置に建て込み、固定できる作用を呈するものである。
【0019】
【実施例】
次に本発明の実施例を、添付図面を参照して詳細に説明する。先ず、本発明遮水壁構築工法は、縦孔1を掘削して、この縦孔1内に遮水壁材Cを注入して単杭又は所定幅の遮水壁エレメント1aを形成し、この単杭又は遮水壁エレメント1a,1a,1a・・・を横方向に接触・連続させて遮水壁10を構築するのは従来と同じである。該縦孔1の掘削は、無論、従来法で行えばよく、素堀りしても無論差し支えはないが、遮水壁が必要な場所は、地下水位が高いことが前提とされるため、通常、素堀は不可能である。
【0020】
そこで、通常、縦孔1の掘削は、ベノト工法、リバース工法、ケーシングチューブを使用するアースドリル工法等で行われ、特に、施工例の多いリバース工法での、従来法遮水壁構築工法を図7及び図8によって説明すると、図7(a)が縦孔1の縦孔掘削行程で、掘削機本体100の掘削ロッド101を回転させ、この掘削ロッド101の下端のビット102(図示例は、三軸ビットで、中心のビットが回転すると、その駆動力で両側のビットも回転するようになしてある。)で縦孔1を掘削する。そして、掘削中の縦孔1内には孔壁崩壊を防止する安定液W1が充填されており、この安定液W1は掘削ロッド101の上端から掘削土と共に吸い上げられ、排泥装置103で掘削土を除去した後、縦孔1に戻され、掘削ロッド101は順次継ぎ足されて、所望の深さまで縦孔1を掘削するようになしてある。
【0021】
縦孔1の掘削が終了したら、該縦孔1内には図7(b)で、遮水壁材Cが注入される。この遮水壁材Cは、コンクリートミルク供送装置104等から供送チューブ105を、縦孔1内に差し込み、該縦孔1の底から、供送チューブ105を引き上げつつ注入される。なお、この遮水壁材Cは、縦孔1内に残留する安定液の一部を利用して固化するものと、遮水壁材Cの注入にともなって安定液W1はオーバーフローした分を順次回収して、縦孔1内の安定液W1は全量を遮水壁材Cと交換されるものがある。
【0022】
次いで、通常は、縦孔1内に図7(c)に示すように、芯材Hを建て込み、遮水壁材Cが固化すると遮水壁エレメント1aが完成する。なお、この芯材Hは、図示例ではH型鋼が使用され、クレーン106で縦孔1内に建て込むようになしてあるが、この芯材Hは省略されることもあり、また、遮水壁材Cの注入前に芯材Hを建て込むことも可能である。
【0023】
上記遮水壁エレメント1aは、先ず、図8aに示すように、所定の間隔を設けて設けられる。図示例では、この遮水壁エレメント1aは三軸ビットで縦孔1を掘削し芯材Hに二本の形鋼を使用しているが、該遮水壁エレメント1aは断面円形の単杭であっても、断面が所定巾の長方形又は長円形のものであっても無論差し支えなく、また、芯材Hは図示例とは異なり、鉄筋籠を使用してもよいのは無論である。
【0024】
次ぎに、上記によって構築された遮水壁エレメント1aと遮水壁エレメント1aとの間に両者を連結する図8(b)に破線で示す遮水壁エレメント1a,1a,1a・・・が、前記と同様にして構築され、図8(c)に示す遮水壁10が完成するものである。なお、この先行施工した遮水壁エレメント1aと後に施工される遮水壁エレメント1aとは、一部を重ねることで多少の寸法誤差があっても遮水壁10は連続して遮水性、土留め機能が損なわれないようになしてある。
【0025】
そして、本発明は、上記縦孔1内の、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に、ダブルパッカー用の外管20を挿入する(建て込む)。この外管20は、従来公知な鋼管・合成樹脂管等が使用でき(本実施例では、この外管20は埋め殺されるため、安価に入手できる塩化ビニール樹脂製のパイプを使用した。)、この外管20には圧送口となる通孔21が上下方向に所望の間隔を有して取り付けられてなり、この通孔21をゴム状体で構成したスリーブやOリングで塞いでおく。
【0026】
なお、従来例では、上記通孔21は、外管20の周方向にも複数箇所に渡って設けられるが、本発明では、後記する地盤改良剤C1の圧送方向を特定する要望から、上下一直線上に設けるか、あるいは数状の上下直線状に並置してある。また、この通孔21は通常円形とするが、横長通孔等の非円形となして、地盤改良剤C1の噴出する方向を調整してもよいものである。
【0027】
上記外管20を挿入するのは、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に挿入され、言い換えると、縦孔1の、先行施工した単杭又は所定幅の遮水壁エレメント1a側(図4参照)でも、先行施工する縦孔1内で、後に構築する単杭又は所定幅の遮水壁エレメント1a側であってもよい。また、この外管20は全ての縦孔1,1,1・・・に必ず挿入する必要性はなく、縦孔1の掘削中の作業者の経験則で、又は、縦孔掘削後の測量で掘削寸法誤差が判明した場合、又はその疑いがあると判断された場合のみでよい。また、図示例ではこの外管20は縦孔1の図左右の一方側にのみ挿入するようになしてあるが、左右双方に一対挿入するようになしても差し支えないものである。
【0028】
そして、縦孔1内に遮水壁材Cを注入した後、上記外管20内にインジェクション管30を差し込んで、該外管20より地盤改良剤C1を隣接する又は隣接を予定する単杭又は所定幅の遮水壁エレメント1aの接触部位付近の地盤に向けて圧送する。この遮水壁材Cとしては、前記もしたように従来公知なものが使用され、安定液W1の一部を利用してこれを固化するものと、安定液W1と入れ替えるものといずれでもよい。
【0029】
また、地盤改良剤C1も従来公知なものを、従来法(従来公知なダブルパッカー工法)で圧送すればよく、遮水壁材Cが固化する前、固化した直後、固化して所定の強度となってからのいずれでもよいが、外管20を被包している遮水壁材Cを割裂して地盤改良剤C1が噴出するためには、該遮水壁材Cが固化を開始して最終的な強度に達する前の状態の間が最も望ましいものであった。
【0030】
なお、この外管20内に差し込むインジェクション管30も、無論、従来公知なものが使用でき、インジェクション管30は、その下端を密閉し、下部(周壁)に圧送口31を設け、この圧送口31の上方と下方とには、該インジェクション管30外周面と外管20の内周面との間隙を密閉する一対のパッキン32,32(図3参照)を装着し、上端側より図示しない圧送装置より圧送される地盤改良剤C1は、該圧送口31より図3の矢印A1,A1,A1・・・に示すように上下パッキン32,32の間に流出し、さらに、同図矢印A2に示すように外管20の通孔21より外方に流出するようになしてある。なお、このインジェクション管30は抜き差し可能となしてあるので、該インジェクション管30を昇降することで、外管20のどの高さの通孔21より地盤改良剤C1を送り出すのかを選択できるものである。
【0031】
次に、請求項2の発明は、縦孔1を掘削して、この縦孔1内に遮水壁材Cを注入して単杭又は所定幅の遮水壁エレメント1aを形成し、この単杭又は遮水壁エレメント1a,1a,1a・・・を横方向に接触・連続させて遮水壁10を構築する遮水壁構築工法において、上記縦孔1内の、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管20を挿入するのは、上記請求項1と同じ構成である。
【0032】
そして、本発明は、この外管20には上下方向に所定の間隔で外管圧送口となる通孔21,21,21・・・を該縦孔1の外側に向けて設けると共に、この各通孔21部位は、ゴム状のスリーブ体23で夫々覆い、このスリーブ体23は締着バンド22,22で外管20に締着すると共に、通孔21に適合する位置には、外方先端側が順次縮径される嘴状凸部24を膨出成形し、さらにこの嘴状凸部24の先端部にはスリット状の開口部24aを設けてある。
【0033】
すなわち、外管20の通孔21,21,21・・・を、スリーブ体23で覆って該外管20内に異物が混入してインジェクション管30の昇降が阻害されることを防止することは従来公知であるが、本発明では、この外管20を遮水壁材C中に埋入させるため、粘度の大きい遮水壁材C中にインジェクション管30を差し込むか、予め差し込んだインジェクション管30の周りに遮水壁材Cを注入すると、該スリーブ体23の肉厚部による段部には大きな外力が加わり、該スリーブ体23が捲れ上がって密閉性を保証できないため、本発明では、段部となる部位を締着バンド22,22でしっかりと緊締して、スリーブ体23がずれたり、捲れ上がるのを防止してある。
【0034】
なお、この両ゴム状スリーブ体23は、通孔21に適合する位置に、外方先端側が順次縮径される嘴状凸部24を膨出成形し、さらにこの嘴状凸部24の先端部にはスリット状の開口部24aを設けてあり、このような形状を一体成型しても無論よいが、一体成型するのには意外と複雑な形状であるので、本発明では展開して図5及び図6に示すように一部が突出した帯状本体23aを形成し、この帯状本体23aの長さ(図左右方向の長さ)を、外管20の外周の長さに一致させ、この帯状本体23aを外管20に巻き付けることでスリーブ体23として使用できるようになしてある。
【0035】
また、上記帯状本体23aの一端部には上記嘴状突出部24の縦半分側24’を膨出形成して、他端部には該嘴状突出部24の残りの縦半分側24’を膨出形成して、該帯状本体23aを外管20に巻き付ける際に、両端部の接合部位が通孔21の柱状に位置することで、この一対の縦半分側24’,24’で構成される嘴状突出部24が通孔21の位置に適合されるようになしてある。なお、この帯状本体23aの両端辺23b、23cを接合することで、該接合部が前記したスリット状の開口部24aとなるようになしてある。
【0036】
次に、請求項3の発明は、縦孔1を掘削して、この縦孔1内に遮水壁材Cを注入して単杭又は所定幅の遮水壁エレメント1aを形成し、この単杭又は遮水壁エレメント1a,1a,1a・・・を横方向に接触・連続させて遮水壁10を構築する遮水壁構築工法において、上記縦孔1内に建て込む鉄筋籠又は芯材Sの、単杭又は所定幅の遮水壁エレメント1aに隣接する又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管20を固定して取り付け、この外管30を芯材Sと共に縦孔1内に建て込み、上記縦孔1内の、単杭又は所定幅の遮水壁エレメント1aに隣接又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管20を挿入しておき、この外管20には上下方向に所定の間隔で外管圧送口となる通孔21,21,21・・・を該縦孔1の外側に向けて設けると共に、この各通孔21部位は、ゴム状のスリーブ体23で夫々覆い、このスリーブ体23は締着バンド22,22で外管20に締着すると共に、通孔21に適合する位置には、外方先端側が順次縮径される嘴状凸部24を膨出成形し、さらにこの嘴状凸部24の先端部にはスリット状の開口部24aを設け、上記外管20内には、下部に圧送口31を有したインジェクション管30を抜き差し可能に差し込み、このインジェクション管30の圧送口31の上方と下方とには、該インジェクション管30外周面と外管20の内周面との間隙を密閉する一対のパッキン32,32を装着し、上記縦孔1内に遮水壁材Cを注入した後、インジェクション管30を昇降させて、所望の通孔21より、地盤改良剤C1を隣接した又は隣接を予定する単杭又は所定幅の遮水壁エレメント1aの接触部位付近の地盤に向けて圧送するようになしたものである。
【0037】
すなわち、本発明は、前記請求項2の外管20を、縦孔1内に建て込む鉄筋籠又は芯材Hに固定して、該芯材Hと共に縦孔1内に建て込めるようになしたものである。この外管20の芯材Hへの固定は、針金による緊締でもよく、あるいは、図示はしていないが、芯材Hに一例としては樋支承体のような、従来公知な筒体ホルダーを予め取り付けておき、この筒体ホルダーで保持させるようになしてもよいものである。
【0038】
【発明の効果】
請求項1乃至3の発明によれば、万が一、縦孔1の掘削施工において誤差が生じた場合でも、特に、新たな掘削を行うことなく、遮水壁の不連続部位を地盤改良して、遮水性と土留め機能とを保証できる遮水壁構築工法を提供できるものである。
【0039】
特に、請求項2及び請求項3の発明によると、スリーブ体23には通孔21の適合部位に予め嘴状突出部24を膨出成型してあるので、この嘴状突出部24を縦孔1の側端部において外方に向けることで、該嘴状突出部24の先端では遮水壁材Cがその分薄くなっていることと、通孔21より圧送される地盤改良材C1の内圧は、先に向かって縮径される嘴状突出部24の先端側に向かって順次高まり、該遮水壁材Cが固化して所定の強度の遮水壁エレメント1aとなっていても、この内側よりの大きな圧力で、容易に該遮水壁材Cが破断し、地盤改良材C1の流出を許容することができ、地盤改良材C1を目的の方向に確実に圧送できる水壁構築工法を提供できるものである。
【図面の簡単な説明】
【図1】本発明遮水壁構築工法の工程を示す、縦断面図である。
【図2】本発明遮水壁構築工法での、外管を挿入した状態での部分断面図である。
【図3】本発明に使用されるダブルパッカーの一実施例装置縦断面図である。
【図4】本発明水壁構築工法で地盤改良された部位の横断面図である。
【図5】本発明に使用されるスリーブ体の一実施例展開正面図である。
【図6】上記スリーブ体の右側面図である。
【図7】遮水壁エレメントの構築手順を説明する一部断面正面図である。
【図8】遮水壁エレメントの構築手順を説明する平面図である。
【図9】従来例で地盤改良された部位の横断面図である。
【符号の説明】
1 縦孔
C 遮水壁材
1a 遮水壁エレメント
10 遮水壁
S 芯材
20 外管
30 インジェクション管
21 通孔
22 締着バンド
23 スリーブ体
24 嘴状突部
24a 開口部
31 圧送口
32 パッキン
C1 地盤改良剤
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a seepage control wall construction method, and more specifically, conventionally, a well-constructed, excavating a vertical hole, injecting a seepage control wall material into the vertical hole, or a single pile or The present invention relates to an impermeable wall construction method for forming an impermeable wall element having a predetermined width and contacting and continuing the single pile or impermeable wall element laterally to construct an impermeable wall.
[0002]
[Prior art]
Conventionally, this type of impermeable wall construction method has gained trust as an established technique with many construction examples. However, recently, the required depth of the impermeable wall has become deeper, and slight dimensional errors on the ground to be installed on the ground will increase in deeper parts, resulting in large errors, and the continuity of the impermeable wall cannot be ensured. Mistakes are being reported.
[0003]
That is, when the right vertical hole 1 is excavated in the left existing impermeable wall element 1a shown in FIG. 1, if there is some error in the accuracy of the verticality, the vertical hole 1 is deeply formed in the existing impermeable wall element. It is separated from the element 1a. In addition, in the example of FIG. 4 and FIG. 9, in addition to the verticality error, in the case where the wide vertical hole 1 is slightly twisted, the position indicated by the broken line in FIG. When the vertical hole 1 is excavated, an error occurs in the verticality for some reason as the vertical hole 1 becomes deeper, and the vertical hole 1 is twisted so as to face upward in the figure. When the excavation was attempted to partially overlap the water wall element 1a, the vertical hole 1 was separated from the existing impermeable wall element 1a in a deep part. Therefore, if the single pile or the impermeable wall element 1a is separated in this way, it is impossible to secure water impermeability at this portion at all, and the soil retaining function cannot be expected.
[0004]
Of course, the above construction error is not something that can be left unattended, during construction, or as a result of excavating the vertical hole and measuring it, if an error is found, refill the vertical hole and re-excavate the vertical hole Alternatively, after the completion of a single pile or impermeable wall element, a chemical liquid injection hole is separately excavated from the ground to the vicinity of this poor construction site, and improvement work is performed to inject a ground improvement agent from the ground.
[0005]
Conventionally, a double packer method has been widely used for the improvement work for injecting the ground improvement agent, and one example thereof is described in Patent Document 1. According to the double packer method of Patent Document 1, a double pipe combining a pipe with a sleeve as an outer pipe and an injection pipe as an inner pipe is used as a so-called "injection pipe". In the double pipe double packer method for providing a double packer on the injection pipe, the description is made to state that the double packer method is a known technique. In connection with the present invention, paragraph [0006] of Patent Document 1 also discloses that the sleeve is a rubber (rubber) sleeve that covers the injection nozzle.
[0006]
Patent Document 2 discloses a method for improving the ground below the impermeable wall, which has a different purpose, for example, "Pipes 5 are arranged in the reinforcing cage 3 at predetermined arrangement intervals, for example, in a staggered manner. After the reinforced cage 3 is built in the excavation groove 2 and concrete is poured, the jet bolt 6 is drilled to a formation deeper than the groove bottom of the excavation groove 2 by using the pipes 5 as guides to form a pressurized water-bearing formation E1. Then, the chemical solution 7 is injected from the tip of the jet bolt 6 to the location of the pressurized aquifer E1 and solidified to improve the geology ”.
[0007]
Then, by applying the techniques of Patent Documents 1 and 2 described above, it is possible to improve the ground near the poor construction site, secure water shielding, and secure the earth retaining function. In order to use the double packer method, as shown in FIG. 9, a vertical hole H1 (boring hole) for the double packer is separately excavated, a double packer device is inserted into the vertical hole H1, and a chemical solution is injected. It is necessary to form the improved ground part C1a, and the construction cost is increased, and an extra construction space for excavating the vertical hole H1 for the double packer method is required, and it is not necessarily realized at any construction site. There was a problem that it could not be done.
[0008]
The method of Patent Document 2 has no problem in improving the ground below the impermeable wall, but is not suitable for improving the ground beside the vertical hole 1 as shown in FIGS. 1 and 4. In particular, in the case of the vertical hole 1 having a small diameter, there is a problem that there is no space in the vertical hole 1 for accommodating the long jet bolt described in Patent Document 2 in the lateral direction. are doing.
[0009]
[Patent Document 1] Japanese Patent Application Laid-Open No. 8-31855 (Claims, FIG. 1 and paragraph number “0006”)
[Patent Document 2] JP-A-6-146270 (FIG. 3)
[0010]
[Problems to be solved by the invention]
Therefore, the present invention has been made in view of the above problems, and when poor contact (continuity) is expected in the construction of the impermeable wall, the use of a simple device makes it easy to construct the ground at the poor contact point. It is an object of the present invention to provide a method for constructing a seepage control wall that can be improved appropriately and can guarantee continuous water stoppage.
[0011]
[Means for Solving the Problems]
In order to achieve the above object, the present invention excavates the vertical hole 1 and injects the water-blocking wall material C into the vertical hole 1 to form a single pile or a water-blocking wall element 1a having a predetermined width. In the seepage control wall construction method of constructing the seepage control wall 10 by making the single pile or the seepage control wall elements 1a, 1a, 1a... The outer pipe 20 for a double packer is inserted into a side end adjacent to or planned to be adjacent to the water impervious wall element 1a, and the water impervious wall material C is injected into the vertical hole 1, and then the outer pipe The injection pipe 30 is inserted into the inner pipe 20, and the soil improving agent C1 is pumped from the outer pipe 20 to the adjacent ground or a single pile or a ground near the contact area of the impermeable wall element 1a having a predetermined width. Technical measures characterized by the following are taken.
[0012]
Therefore, in the present invention, since the vertical hole 1 for forming the water-impervious wall 10 is also used as the hole into which the outer pipe 20 for the double-packer is inserted, the vertical hole 1 for the double-packer method is separately provided. There is no need to excavate the hole H1 (see FIG. 9), and since the impermeable wall material C is injected into the vertical hole 1, the ground improving agent C1 is pumped, so that the ground improving agent C1 is surely supplied. In addition, it has the function of being able to be pumped and injected into the ground.
[0013]
The operation of pumping the ground improving agent C1 using the outer pipe 20 for the double packer is the same as the operation of the conventional double packer method, and the ground is appropriately fed from the pumping hole (through hole 21) having a desired depth. The present invention has an effect of pumping the improving agent C1 and an effect of pumping the soil improving agent C1 to the same place a plurality of times by changing the type of the soil improving agent C1. The outer pipe 20 is embedded in the impermeable wall material C, and the impermeable wall material C eventually solidifies. However, by adjusting the injection pressure, the impermeable wall material that has solidified or is in the process of being solidified is adjusted. It has the function of splitting the material C and ejecting the ground improvement agent C1 outward.
[0014]
Next, according to the invention of claim 2, the vertical hole 1 is excavated, and the water impermeable wall material C is injected into the vertical hole 1 to form a single pile or a water impermeable wall element 1a having a predetermined width. In the impermeable wall construction method of constructing the impermeable wall 10 by laterally contacting and continuing the piles or impermeable wall elements 1a, 1a, 1a,. An outer pipe 20 for a double packer whose bottom is sealed is inserted into a side end adjacent to or planned to be adjacent to the impermeable wall element 1a, and the outer pipe 20 is vertically pumped to the outer pipe 20 at predetermined intervals. .. Serving as mouths are provided toward the outside of the vertical hole 1, and each of the through holes 21 is covered with a rubber-like sleeve member 23, respectively. The outer band 20 is fastened to the outer tube 20 with the attachment bands 22, 22, and the outer tip side is located at a position matching the through hole 21. The beak-shaped convex portion 24 to be reduced in diameter is formed by bulging. Further, a slit-shaped opening 24a is provided at the tip of the beak-shaped convex portion 24. A pair of injection pipes 30 each of which is capable of inserting and removing the injection pipe 30 and having a pair of seals between the outer peripheral surface of the injection pipe 30 and the inner peripheral surface of the outer pipe 20 above and below the pressure feed port 31 of the injection pipe 30. After installing the packings 32 and 32 and injecting the impermeable wall material C into the vertical hole 1, the injection pipe 30 is moved up and down, and the ground improvement agent C <b> 1 is adjacent or is scheduled to be adjacent to the desired through hole 21. A technical measure characterized in that a single pile or a predetermined width of the impermeable wall element 1a is pressure-fed toward the ground near the contact portion.
[0015]
Therefore, according to the construction method of the present invention, since the through hole 21 serving as the outer tube pressure feed port is covered with the sleeve body 23 in addition to the function of claim 1, the vertical hole 1 in which the outer tube 20 is built is provided. Even if the impermeable wall material C is injected into the inside, or the outer pipe 20 is built in the vertical hole 1 into which the impermeable wall material C is injected, the sealing performance of the through holes 21, 21, 21. It is maintained and exhibits an action of preventing the water-blocking wall material C from entering the outer tube 20. Since the sleeve body 23 is fastened to the outer tube 20 by the fastening bands 22, 22, the sleeve body 23 does not shift even when a large external force is applied, and the ground improvement material C1 is moved outward from the through hole 21 side. When the rubber band 23 is provided with a slit-shaped opening 24a, the opening 24a is pushed open to facilitate the pressure feeding of the ground improvement material C1 through the through hole 21. This allows the backflow of the fluid from the outside of the outer tube 20 toward the inside of the through-hole 21 to be suppressed.
[0016]
Since the beak-shaped protrusion 24 is formed in the sleeve body 23 in advance at a portion corresponding to the through hole 21, the beak-shaped protrusion 24 is directed outward at the side end of the vertical hole 1. At the tip of the beak-shaped protruding portion 24, the water-impervious wall material C is thinner by that amount, and the internal pressure of the ground improvement material C1 fed from the through-hole 21 is reduced to a beak-like shape whose diameter is reduced. Even if the water-impervious wall material C is solidified to have a predetermined strength, the water-impervious wall material C is easily broken by a pressure higher than the inner side even if the water-impervious wall material C is solidified to a predetermined strength. And an effect of allowing outflow of the ground improvement material C1.
[0017]
Next, a third aspect of the present invention is to excavate the vertical hole 1 and inject the water impervious wall material C into the vertical hole 1 to form a single pile or a water impervious wall element 1a having a predetermined width. In the impermeable wall construction method for constructing the impermeable wall 10 by laterally contacting and continuing the piles or impermeable wall elements 1a, 1a, 1a,... A fixed outer pipe 20 for a double packer having a closed bottom is fixedly attached to a single pile or a side end adjacent to or expected to be adjacent to the impermeable wall element 1a having a predetermined width. It is built into the vertical hole 1 together with the material S, and inside the vertical hole 1 is a single pile or a side end portion adjacent to or planned to be adjacent to the impermeable wall element 1a having a predetermined width. A pipe 20 is inserted into the outer pipe 20, and a through hole serving as an outer pipe pressure feeding port is provided at a predetermined interval in the vertical direction. Are provided outside the vertical hole 1, and the through holes 21 are covered with rubber-like sleeves 23, respectively. A beak-shaped convex portion 24 whose outer distal end side is sequentially reduced in diameter is bulged at a position adapted to the through hole 21 while being fastened to the outer tube 20. Is provided with a slit-shaped opening 24a, and an injection pipe 30 having a pressure feed port 31 at a lower portion is removably inserted into the outer pipe 20, and is inserted above and below the pressure feed port 31 of the injection pipe 30. Is mounted with a pair of packings 32, 32 for sealing the gap between the outer peripheral surface of the injection pipe 30 and the inner peripheral surface of the outer pipe 20, and after injecting the water-blocking wall material C into the vertical hole 1, the injection pipe 30 is moved up and down to obtain the desired through hole 2. Further, a technical measure characterized in that the ground improvement agent C1 is pumped toward the ground near the contact portion of the adjacent or planned single pile or the impermeable wall element 1a having a predetermined width is taken. It is a thing.
[0018]
Therefore, according to the method of the present invention, the outer pipe 20 for the double packer is fixed and attached to the reinforcing bar or the core H to be built in the vertical hole 1 in addition to the function of claim 2. With the core material H, the outer tube 20 can be erected at a desired position and fixed.
[0019]
【Example】
Next, embodiments of the present invention will be described in detail with reference to the accompanying drawings. First, in the method of constructing a water impermeable wall according to the present invention, a vertical hole 1 is excavated, and a water impermeable wall material C is injected into the vertical hole 1 to form a single pile or a water impermeable wall element 1a having a predetermined width. Establishing the impermeable wall 10 by making the single pile or impermeable wall elements 1a, 1a, 1a... Of course, the excavation of the vertical hole 1 may be performed by a conventional method, and it is of course possible to perform the excavation without any difficulty. However, since the place where the impermeable wall is required is assumed to have a high groundwater level, Usually, moat is impossible.
[0020]
Therefore, excavation of the vertical hole 1 is usually performed by the Venoto method, the reverse method, the earth drill method using a casing tube, and the like. 7 and FIG. 8, FIG. 7A is a vertical hole excavation process of the vertical hole 1, in which a drill rod 101 of an excavator body 100 is rotated, and a bit 102 at a lower end of the drill rod 101 (in the illustrated example, With the triaxial bit, when the center bit is rotated, the bits on both sides are also rotated by the driving force.), And the vertical hole 1 is excavated. The vertical hole 1 during excavation is filled with a stabilizing solution W1 for preventing collapse of the hole wall. The stable solution W1 is sucked up together with the excavated soil from the upper end of the excavating rod 101, and excavated soil is discharged by the sludge discharging device 103. Is removed, the hole is returned to the vertical hole 1, and the drilling rod 101 is successively added to excavate the vertical hole 1 to a desired depth.
[0021]
When the excavation of the vertical hole 1 is completed, the impermeable wall material C is injected into the vertical hole 1 as shown in FIG. The water impervious wall material C is injected from the concrete milk supply device 104 or the like into the vertical hole 1 by inserting the supply tube 105 into the vertical hole 1 and pulling up the supply tube 105 from the bottom of the vertical hole 1. The impermeable wall material C is solidified by using a part of the stabilizing liquid remaining in the vertical hole 1, and the portion of the stable liquid W1 that has overflowed due to the injection of the impermeable wall material C is sequentially determined. Some of the recovered liquid W1 in the vertical hole 1 is collected and exchanged for the impermeable wall material C.
[0022]
Next, usually, as shown in FIG. 7 (c), a core material H is erected in the vertical hole 1 and the impermeable wall material C is solidified to complete the impermeable wall element 1a. The core H is made of H-shaped steel in the illustrated example, and is built into the vertical hole 1 by the crane 106. However, the core H may be omitted. It is also possible to build the core material H before the wall material C is injected.
[0023]
First, the water impermeable wall elements 1a are provided at predetermined intervals as shown in FIG. 8A. In the illustrated example, the water-blocking wall element 1a is formed by excavating the vertical hole 1 with a triaxial bit and using two shaped steels for the core material H. The water-blocking wall element 1a is a single pile having a circular cross section. Even if the cross section is rectangular or oval with a predetermined width, it is of course possible to use the core material H different from the illustrated example.
[0024]
Next, the impervious wall elements 1a, 1a, 1a,... Indicated by broken lines in FIG. It is constructed in the same manner as described above, and the impermeable wall 10 shown in FIG. 8C is completed. It should be noted that the impervious wall element 1a which is pre-installed and the impervious wall element 1a which is to be installed later are partially overlapped so that even if there is some dimensional error, the impervious wall 10 can be continuously impervious to water and soil. The fastening function is not impaired.
[0025]
In the present invention, the outer pipe 20 for the double packer is inserted (built) into the single hole or the side end to be adjacent to the impermeable wall element 1a having the predetermined width in the vertical hole 1. . As the outer tube 20, a conventionally known steel tube, synthetic resin tube, or the like can be used (in the present embodiment, a pipe made of vinyl chloride resin, which is available at a low cost because the outer tube 20 is buried, is used). A through hole 21 serving as a pressure feed port is attached to the outer tube 20 at a desired interval in the vertical direction, and the through hole 21 is closed with a sleeve or O-ring made of a rubber-like body.
[0026]
In the conventional example, the through holes 21 are provided at a plurality of locations in the circumferential direction of the outer tube 20. However, in the present invention, in order to specify the direction of feeding the ground improvement agent C1 described later, the through holes 21 are vertically aligned. It is provided on a line or is juxtaposed in a number of vertical straight lines. The through holes 21 are usually circular, but may be non-circular such as horizontally long through holes to adjust the direction in which the ground improving agent C1 is ejected.
[0027]
The outer pipe 20 is inserted into a single pile or a side end that is adjacent to or planned to be adjacent to the impermeable wall element 1a having a predetermined width. The side of the impermeable wall element 1a having a width (see FIG. 4) may be a single pile to be constructed later or the side of the impermeable wall element 1a having a predetermined width in the pre-constructed vertical hole 1. It is not necessary to always insert the outer pipe 20 into all the vertical holes 1, 1, 1... It is sufficient only when the excavation dimensional error is found or when it is determined to be suspected. In the illustrated example, the outer tube 20 is inserted into only one of the left and right sides of the vertical hole 1 in the figure, but a pair may be inserted into both the left and right sides.
[0028]
Then, after injecting the impermeable wall material C into the vertical hole 1, the injection pipe 30 is inserted into the outer pipe 20, and the ground improvement agent C <b> 1 is adjacent to or is scheduled to be adjacent to the outer pipe 20 from the single pile or It is pumped toward the ground near the contact area of the impermeable wall element 1a having a predetermined width. As the water impervious wall material C, a conventionally known material is used as described above, and either a material that solidifies the stabilizer using part of the stabilizer W1 or a material that replaces the stabilizer W1 may be used.
[0029]
Also, the ground improving agent C1 may be pumped by a conventional method (a conventionally known double packer method) by a conventional method (prior known double packing method). Although it may be any after that, in order for the impermeable wall material C enclosing the outer pipe 20 to be split and the ground improving agent C1 is jetted, the impermeable wall material C starts to solidify. The state before reaching the final strength was most desirable.
[0030]
The injection pipe 30 inserted into the outer pipe 20 can be of course a conventionally known one. The injection pipe 30 has a lower end hermetically sealed and a pressure feed port 31 provided at a lower portion (peripheral wall). A pair of packings 32, 32 (see FIG. 3) for sealing a gap between the outer peripheral surface of the injection pipe 30 and the inner peripheral surface of the outer pipe 20 are mounted above and below the pumping apparatus. The soil improving agent C1 which is further pumped out flows out between the upper and lower packings 32, 32 as shown by arrows A1, A1, A1,... In the pumping port 31 and further shown by arrow A2 in FIG. As described above, it flows out from the through hole 21 of the outer tube 20. Since the injection pipe 30 can be inserted and removed, it is possible to select the height of the through-hole 21 of the outer pipe 20 from which the ground improving agent C1 is to be sent out by moving the injection pipe 30 up and down. .
[0031]
Next, according to the invention of claim 2, the vertical hole 1 is excavated, and the water impermeable wall material C is injected into the vertical hole 1 to form a single pile or a water impermeable wall element 1a having a predetermined width. In the impermeable wall construction method of constructing the impermeable wall 10 by laterally contacting and continuing the piles or impermeable wall elements 1a, 1a, 1a,. Inserting the outer tube 20 for a double packer with a closed bottom into the side end portion adjacent to or planned to be adjacent to the impermeable wall element 1a is the same configuration as in the first aspect.
[0032]
In the present invention, the outer tube 20 is provided with through holes 21, 21, 21... Serving as outer tube pressure feed ports at predetermined intervals in the vertical direction toward the outside of the vertical hole 1. The portions of the through holes 21 are covered with rubber-like sleeve members 23, respectively. The sleeve members 23 are fastened to the outer tube 20 by fastening bands 22, 22, and the outer end is located at a position suitable for the through holes 21. The beak-shaped protrusion 24 whose side is sequentially reduced in diameter is formed by bulging, and further, a slit-shaped opening 24a is provided at the tip of the beak-shaped protrusion 24.
[0033]
That is, it is possible to prevent the through holes 21, 21, 21,... Of the outer tube 20 from being covered with the sleeve body 23, and to prevent foreign matters from being mixed into the outer tube 20 and hindering the elevation of the injection tube 30. Although conventionally known, in the present invention, in order to embed the outer pipe 20 in the impermeable wall material C, the injection pipe 30 is inserted into the highly viscous impermeable wall material C, or the injection pipe 30 inserted in advance is used. When the water-impervious wall material C is injected around the periphery, a large external force is applied to the step portion due to the thick portion of the sleeve body 23, and the sleeve body 23 is rolled up and the sealing property cannot be ensured. The part to be a part is firmly tightened by the fastening bands 22, 22 to prevent the sleeve body 23 from shifting or rolling up.
[0034]
The two rubber-like sleeves 23 are formed by bulging a beak-shaped convex portion 24 whose outer distal end is sequentially reduced in diameter at a position suitable for the through-hole 21. Is provided with a slit-shaped opening 24a, and it is of course possible to integrally mold such a shape. However, since the shape is unexpectedly complicated to integrally mold, it is developed in the present invention and FIG. As shown in FIG. 6, a belt-shaped main body 23 a partly protruding is formed, and the length (length in the left-right direction in the figure) of the band-shaped main body 23 a is made to match the outer peripheral length of the outer tube 20. The sleeve 23 a is wound around the outer tube 20 so that it can be used as the sleeve body 23.
[0035]
Further, a longitudinal half side 24 'of the beak-shaped protrusion 24 is formed at one end of the band-shaped main body 23a by bulging, and the remaining longitudinal half 24' of the beak-shaped protrusion 24 is formed at the other end. When the band-shaped main body 23a is swelled and wound around the outer tube 20, the joining portions at both ends are located in a columnar shape of the through-hole 21, so that the pair of vertical half sides 24 ', 24' is formed. The beak-shaped protrusion 24 is adapted to the position of the through hole 21. In addition, by joining both side edges 23b and 23c of the band-shaped main body 23a, the joining portion becomes the slit-shaped opening 24a described above.
[0036]
Next, according to the invention of claim 3, a vertical hole 1 is excavated, and a water impervious wall material C is injected into the vertical hole 1 to form a single pile or a water impervious wall element 1a having a predetermined width. In the impermeable wall construction method for constructing the impermeable wall 10 by laterally contacting and continuing the piles or impermeable wall elements 1a, 1a, 1a,... A fixed outer pipe 20 for a double packer having a closed bottom is fixedly attached to a single pile or a side end adjacent to or expected to be adjacent to the impermeable wall element 1a having a predetermined width. It is built into the vertical hole 1 together with the material S, and inside the vertical hole 1 is a single pile or a side end portion adjacent to or planned to be adjacent to the impermeable wall element 1a having a predetermined width. A pipe 20 is inserted into the outer pipe 20, and a through hole 2 serving as an outer pipe pressure feed port is provided at a predetermined interval in the vertical direction. , 21, 21... Are provided toward the outside of the vertical hole 1, and the respective through holes 21 are covered with rubber-like sleeve members 23, respectively. A beak-shaped convex portion 24 whose outer distal end is sequentially reduced in diameter is bulged at a position adapted to the through-hole 21 while being fastened to the outer tube 20. Is provided with a slit-shaped opening 24a, and an injection pipe 30 having a pressure supply port 31 at a lower portion is removably inserted into the outer pipe 20, and an upper portion and a lower portion of the injection port 30 of the injection pipe 30 are provided. A pair of packings 32, 32 for sealing the gap between the outer peripheral surface of the injection pipe 30 and the inner peripheral surface of the outer pipe 20 are mounted, and after the water blocking wall material C is injected into the vertical hole 1, the injection pipe 30 Is moved up and down to obtain the desired through-hole 21. Ri, in which none to pump toward the ground improvement agent C1 to ground in the vicinity of the contact portion of impervious wall element 1a of the single pile or a predetermined width to schedule adjacent or neighboring.
[0037]
That is, according to the present invention, the outer tube 20 of the second aspect is fixed to a reinforcing bar or a core H to be built in the vertical hole 1 so that the outer tube 20 can be built in the vertical hole 1 together with the core H. Things. The fixing of the outer tube 20 to the core material H may be performed by tightening with a wire, or, although not shown, a conventionally known cylindrical holder such as a gutter support is used as the core material H in advance. It may be attached and held by this cylindrical holder.
[0038]
【The invention's effect】
According to the invention of claims 1 to 3, even if an error occurs in the excavation work of the vertical hole 1, in particular, without performing new excavation, the ground portion of the discontinuous portion of the impermeable wall is improved, It is an object of the present invention to provide a method for constructing a water-impervious wall that can guarantee the water-impermeability and earth retaining function.
[0039]
In particular, according to the second and third aspects of the present invention, the beak-shaped protrusion 24 is formed in advance in the sleeve body 23 at a position corresponding to the through-hole 21 by bulging. 1 at the side end, the water-impervious wall material C is thinner at the tip of the beak-shaped protrusion 24, and the internal pressure of the ground improvement material C1 pumped through the through hole 21. Is gradually increased toward the distal end side of the beak-shaped protrusion 24 whose diameter is reduced toward the front, and even if the impermeable wall material C is solidified to form the impermeable wall element 1a having a predetermined strength, A water wall construction method capable of easily breaking the impermeable wall material C with a greater pressure than the inside, allowing the ground improvement material C1 to flow out, and reliably pumping the ground improvement material C1 in the desired direction. It can be provided.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view showing steps of a method for constructing a seepage control wall of the present invention.
FIG. 2 is a partial cross-sectional view of an impermeable wall construction method according to the present invention with an outer pipe inserted.
FIG. 3 is a longitudinal sectional view of an embodiment of the double packer used in the present invention.
FIG. 4 is a cross-sectional view of a part where the ground has been improved by the water wall construction method of the present invention.
FIG. 5 is an exploded front view of one embodiment of a sleeve used in the present invention.
FIG. 6 is a right side view of the sleeve body.
FIG. 7 is a partial cross-sectional front view for explaining a construction procedure of the impermeable wall element.
FIG. 8 is a plan view for explaining a construction procedure of a water-blocking wall element.
FIG. 9 is a cross-sectional view of a portion where the ground has been improved in the conventional example.
[Explanation of symbols]
1 vertical hole
C impermeable wall material
1a Impermeable wall element
10 impermeable wall
S core material
20 outer tube
30 Injection tube
21 through hole
22 Fastening band
23 Sleeve body
24 beak-shaped protrusion
24a opening
31 Pressure port
32 Packing
C1 ground improvement agent

Claims (3)

縦孔(1)を掘削して、この縦孔(1)内に遮水壁材(C)を注入して単杭又は所定幅の遮水壁エレメント(1a)を形成し、この単杭又は遮水壁エレメント(1a,1a,1a・・・)を横方向に接触・連続させて遮水壁(10)を構築する遮水壁構築工法において、
上記縦孔(1)内の、単杭又は所定幅の遮水壁エレメント(1a)に隣接又は隣接を予定する側端部内に、ダブルパッカー用の外管(20)を挿入しておき、
上記縦孔(1)内に遮水壁材(C)を注入した後、上記外管(20)内にインジェクション管(30)を差し込んで、該外管(20)より地盤改良剤(C1)を隣接する又は隣接を予定する単杭又は所定幅の遮水壁エレメント(1a)の接触部位付近の地盤に向けて圧送するようになしたことを特徴とする遮水壁構築工法。
A vertical hole (1) is excavated, and a water impervious wall material (C) is injected into the vertical hole (1) to form a single pile or a water impervious wall element (1a) having a predetermined width. In the impermeable wall construction method of constructing the impermeable wall (10) by contacting and continuing the impermeable wall elements (1a, 1a, 1a ...) in the lateral direction,
In the vertical hole (1), an outer pipe (20) for a double packer is inserted in a single pile or a side end that is adjacent or planned to be adjacent to the impermeable wall element (1a) having a predetermined width,
After injecting the impermeable wall material (C) into the vertical hole (1), an injection pipe (30) is inserted into the outer pipe (20), and the ground improving agent (C1) is inserted through the outer pipe (20). Characterized by the fact that pressure is fed toward the ground near the contact area of a single pile or a predetermined width of the impermeable wall element (1a) adjacent or scheduled to be adjacent.
縦孔(1)を掘削して、この縦孔(1)内に遮水壁材(C)を注入して単杭又は所定幅の遮水壁エレメント(1a)を形成し、この単杭又は遮水壁エレメント(1a,1a,1a・・・)を横方向に接触・連続させて遮水壁(10)を構築する遮水壁構築工法において、
上記縦孔(1)内の、単杭又は所定幅の遮水壁エレメント(1a)に隣接又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管(20)を挿入しておき、この外管(20)には上下方向に所定の間隔で外管圧送口となる通孔(21,21,21・・・)を該縦孔(1)の外側に向けて設けると共に、この各通孔(21)部位は、ゴム状のスリーブ体(23)で夫々覆い、このスリーブ体(23)は締着バンド(22,22)で外管(20)に締着すると共に、通孔(21)に適合する位置には、外方先端側が順次縮径される嘴状凸部(24)を膨出成形し、さらにこの嘴状凸部(24)の先端部にはスリット状の開口部(24a)を設け、
上記外管(20)内には、下部に圧送口(31)を有したインジェクション管(30)を抜き差し可能に差し込み、このインジェクション管(30)の圧送口(31)の上方と下方とには、該インジェクション管(30)外周面と外管(20)の内周面との間隙を密閉する一対のパッキン(32,32)を装着し、
上記縦孔(1)内に遮水壁材(C)を注入した後、インジェクション管(30)を昇降させて、所望の通孔(21)より、地盤改良剤(C1)を隣接する又は隣接を予定する単杭又は所定幅の遮水壁エレメント(1a)の接触部位付近の地盤に向けて圧送するようになしたことを特徴とする遮水壁構築工法。
A vertical hole (1) is excavated, and a water impervious wall material (C) is injected into the vertical hole (1) to form a single pile or a water impervious wall element (1a) having a predetermined width. In the impermeable wall construction method of constructing the impermeable wall (10) by contacting and continuing the impermeable wall elements (1a, 1a, 1a ...) in the lateral direction,
An outer tube (20) for a double packer with a closed bottom is inserted into a side end of the vertical hole (1) adjacent or expected to be adjacent to the single pile or the impermeable wall element (1a) having a predetermined width. The outer tube (20) is provided with through holes (21, 21, 21...) Serving as outer tube pressure feed ports at predetermined intervals in the vertical direction toward the outside of the vertical hole (1). Each of the through holes (21) is covered with a rubber-like sleeve (23), and the sleeve (23) is fastened to the outer tube (20) by fastening bands (22, 22). A beak-shaped convex portion (24) whose outer distal end side is sequentially reduced in diameter is bulged at a position suitable for the through hole (21), and a slit-shaped convex portion is formed at the distal end of the beak-shaped convex portion (24). Opening (24a) is provided,
Into the outer pipe (20), an injection pipe (30) having a pressure feed port (31) at its lower part is removably inserted, and above and below the pressure feed port (31) of the injection pipe (30). A pair of packings (32, 32) for sealing a gap between an outer peripheral surface of the injection pipe (30) and an inner peripheral face of the outer pipe (20) are attached;
After injecting the impermeable wall material (C) into the vertical hole (1), the injection pipe (30) is raised and lowered, and the ground improvement agent (C1) is adjacent or adjacent to the desired through hole (21). A method for constructing a seepage control wall, characterized in that the pumping is carried out toward a ground near a contact portion of a single pile or a seepage control wall element (1a) having a predetermined width.
縦孔(1)を掘削して、この縦孔(1)内に遮水壁材(C)を注入して単杭又は所定幅の遮水壁エレメント(1a)を形成し、この単杭又は遮水壁エレメント(1a,1a,1a・・・)を横方向に接触・連続させて遮水壁(10)を構築する遮水壁構築工法において、
上記縦孔(1)内に建て込む鉄筋籠又は芯材(S)の、単杭又は所定幅の遮水壁エレメント(1a)に隣接する又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管(20)を固定して取り付け、この外管(30)を芯材(S)共に縦孔(1)内に建て込み、
上記縦孔(1)内の、単杭又は所定幅の遮水壁エレメント(1a)に隣接又は隣接を予定する側端部内に、底を密閉したダブルパッカー用の外管(20)を挿入しておき、この外管(20)には上下方向に所定の間隔で外管圧送口となる通孔(21,21,21・・・)を該縦孔(1)の外側に向けて設けると共に、この各通孔(21)部位は、ゴム状のスリーブ体(23)で夫々覆い、このスリーブ体(23)は締着バンド(22,22)で外管(20)に締着すると共に、通孔(21)に適合する位置には、外方先端側が順次縮径される嘴状凸部(24)を膨出成形し、さらにこの嘴状凸部(24)の先端部にはスリット状の開口部(24a)を設け、
上記外管(20)内には、下部に圧送口(31)を有したインジェクション管(30)を抜き差し可能に差し込み、このインジェクション管(30)の圧送口(31)の上方と下方とには、該インジェクション管(30)外周面と外管(20)の内周面との間隙を密閉する一対のパッキン(32,32)を装着し、
上記縦孔(1)内に遮水壁材(C)を注入した後、インジェクション管(30)を昇降させて、所望の通孔(21)より、地盤改良剤(C1)を隣接した又は隣接を予定する単杭又は所定幅の遮水壁エレメント(1a)の接触部位付近の地盤に向けて圧送するようになしたことを特徴とする遮水壁構築工法。
A vertical hole (1) is excavated, and a water impervious wall material (C) is injected into the vertical hole (1) to form a single pile or a water impervious wall element (1a) having a predetermined width. In the impermeable wall construction method of constructing the impermeable wall (10) by contacting and continuing the impermeable wall elements (1a, 1a, 1a ...) in the lateral direction,
The bottom was sealed in a side end portion of the reinforcing rod cage or the core material (S) to be built in the vertical hole (1) adjacent to or planned to be adjacent to the single pile or the impermeable wall element (1a) having a predetermined width. An outer tube (20) for a double packer is fixed and attached, and the outer tube (30) is built together with the core material (S) into the vertical hole (1),
An outer tube (20) for a double packer with a closed bottom is inserted into a side end of the vertical hole (1) adjacent or expected to be adjacent to the single pile or the impermeable wall element (1a) having a predetermined width. The outer tube (20) is provided with through holes (21, 21, 21...) Serving as outer tube pressure feed ports at predetermined intervals in the vertical direction toward the outside of the vertical hole (1). Each of the through holes (21) is covered with a rubber-like sleeve (23), and the sleeve (23) is fastened to the outer tube (20) by fastening bands (22, 22). A beak-shaped convex portion (24) whose outer distal end side is sequentially reduced in diameter is bulged at a position suitable for the through hole (21), and a slit-shaped convex portion is formed at the distal end of the beak-shaped convex portion (24). Opening (24a) is provided,
Into the outer pipe (20), an injection pipe (30) having a pressure feed port (31) at its lower part is removably inserted, and above and below the pressure feed port (31) of the injection pipe (30). A pair of packings (32, 32) for sealing a gap between an outer peripheral surface of the injection pipe (30) and an inner peripheral face of the outer pipe (20) are attached;
After injecting the impermeable wall material (C) into the vertical hole (1), the injection pipe (30) is raised and lowered, and the ground improvement agent (C1) is adjacent or adjacent to the desired through hole (21). A method for constructing a seepage control wall, characterized in that the pumping is carried out toward a ground near a contact portion of a single pile or a seepage control wall element (1a) having a predetermined width.
JP2003000029A 2003-01-06 2003-01-06 Impervious-wall construction method Pending JP2004211422A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003000029A JP2004211422A (en) 2003-01-06 2003-01-06 Impervious-wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003000029A JP2004211422A (en) 2003-01-06 2003-01-06 Impervious-wall construction method

Publications (1)

Publication Number Publication Date
JP2004211422A true JP2004211422A (en) 2004-07-29

Family

ID=32818483

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003000029A Pending JP2004211422A (en) 2003-01-06 2003-01-06 Impervious-wall construction method

Country Status (1)

Country Link
JP (1) JP2004211422A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015063888A (en) * 2013-08-27 2015-04-09 学校法人早稲田大学 Construction method for soil cement underground continuous wall
CN104695456A (en) * 2015-03-27 2015-06-10 济南轨道交通集团有限公司 Construction method novel vertical shaft horizontal rotation jet grouting pile foundation pit lateral wall water stopping curtain
JP2015110894A (en) * 2013-11-07 2015-06-18 ライト工業株式会社 Reinforcement material and development method thereof
JP2016164331A (en) * 2015-03-06 2016-09-08 ケミカルグラウト株式会社 Ground improvement method
JP7435970B2 (en) 2019-12-27 2024-02-21 ジェコス株式会社 Countermeasures for soil defects in soil-cement column walls

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015063888A (en) * 2013-08-27 2015-04-09 学校法人早稲田大学 Construction method for soil cement underground continuous wall
JP2015110894A (en) * 2013-11-07 2015-06-18 ライト工業株式会社 Reinforcement material and development method thereof
JP2016164331A (en) * 2015-03-06 2016-09-08 ケミカルグラウト株式会社 Ground improvement method
CN104695456A (en) * 2015-03-27 2015-06-10 济南轨道交通集团有限公司 Construction method novel vertical shaft horizontal rotation jet grouting pile foundation pit lateral wall water stopping curtain
JP7435970B2 (en) 2019-12-27 2024-02-21 ジェコス株式会社 Countermeasures for soil defects in soil-cement column walls

Similar Documents

Publication Publication Date Title
JP2006226061A (en) Underground drainage construction method
KR100415809B1 (en) precast pile for braced wall and the method using the same
JP4451553B2 (en) Buoyancy prevention structure and construction method thereof
JP4074313B2 (en) Structure of steel sheet pile for water flow and water retaining wall, and its construction method.
JP2004211422A (en) Impervious-wall construction method
JP3834571B2 (en) Construction method for underground structures
JP6730121B2 (en) Underground wall construction method
JP2007162323A (en) Wall body forming method and wall body
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
JP2842236B2 (en) Grout injection method into back of underground continuous wall and its injection device
JP4274898B2 (en) Groundwater flow conservation method
JP4600897B2 (en) Chemical injection method
JPH089862B2 (en) Chemical injection method
JP2000328560A (en) Method of creating steel pipe column row earth retaining wall
KR20030091836A (en) A Continuous and Cut Off wall And Foundation Method By Overlap Casing
JP2000328561A (en) Underground water flowing construction method in soil cement column row earth retaining wall
JP2010126998A (en) Method and structure for preventing deformation of ground
JP2007162265A (en) Tunnel construction method
JPS6358975B2 (en)
JP2005330769A (en) Structure and construction method of water passing earth retaining wall
JP2024037500A (en) Chemical injection method
JP2002021063A (en) Method for constructing earth retaining wall
JP3552925B2 (en) Opening method of groundwater holes in steel pipe column retaining wall
JP3944005B2 (en) Chemical injection method to press-fit shaft and its excavation ground
JP6628360B2 (en) Ground reinforcement method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050215

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050222

A02 Decision of refusal

Effective date: 20050628

Free format text: JAPANESE INTERMEDIATE CODE: A02