JP2004190241A - Foundation structure of main column erected on ground - Google Patents

Foundation structure of main column erected on ground Download PDF

Info

Publication number
JP2004190241A
JP2004190241A JP2002356356A JP2002356356A JP2004190241A JP 2004190241 A JP2004190241 A JP 2004190241A JP 2002356356 A JP2002356356 A JP 2002356356A JP 2002356356 A JP2002356356 A JP 2002356356A JP 2004190241 A JP2004190241 A JP 2004190241A
Authority
JP
Japan
Prior art keywords
pipe pile
concrete
pipe
vertical hole
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002356356A
Other languages
Japanese (ja)
Other versions
JP3622963B2 (en
Inventor
Takashi Koyama
隆資 小山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sankei Co Ltd
Original Assignee
Sankei Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sankei Co Ltd filed Critical Sankei Co Ltd
Priority to JP2002356356A priority Critical patent/JP3622963B2/en
Publication of JP2004190241A publication Critical patent/JP2004190241A/en
Application granted granted Critical
Publication of JP3622963B2 publication Critical patent/JP3622963B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To ensure a reliability on the burying strength of a pipe pile and the perpendicularity of the pipe pile as much as possible regardless of a ground structure in the foundation structure of a main column erected on the ground. <P>SOLUTION: In the foundation structure of the ground-surface in which main columns 13 are erected and pits 3 are excavated, the pipe piles 6 are buried into the pits 3, the insides of the pipe piles 6 are filled with filling crushed stones 11 or filling concrete to form in-pipe foundations 12, the lower end sections of the main columns 13 are inserted movably into the pipe piles 6 and supported to the in-pipe foundations 12 and sections among the lower end sections of the main columns 13 and the inner peripheral surfaces of the pipe piles 6 are filled with filling concrete 16, the pipe piles 6 are buried into the pits 3 at annular spaces, the insides of the annular spaces 7 are filled with hydraulic-filling sand 8 and the pipe piles 6 are supported, encased concrete 17 foot-protecting the main columns 13 is placed into shallow wide-mouthed holes 1 at the upper ends of the pits 3 and the upper-end opening surfaces of the pipe piles 6 and the upper-end opening surfaces of the annular spaces 7 are concealed by foot protection concrete 17. <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は交通標識や看板を掲示するための主柱、或いはゴルフ練習場等のネットを張るための主柱等、地面に立設する主柱の基礎構造に関する。
【0002】
【従来の技術】
特許文献1においては地面に縦穴を掘削し、該縦穴内に管杭を埋入し、該管杭内に中込め砕石又は中込めコンクリートを充填して管内基礎を形成し、該管杭内に主柱の下端部を遊挿して上記管内基礎に支持せしめ、更に該主柱の下端部と管杭内周面間に中込めコンクリートを充填して成る地面立設主柱の基礎構造を開示している。
【0003】
【特許文献1】
特公平3−28540号公報
【0004】
【発明が解決しようとする課題】
然るに上記特許文献1に示す地面立設主柱の基礎構造においては、主柱を縦穴の内周面で直接拘束する構造を採っているが、縦穴が傾斜して掘削されると、これに応じて管杭も傾いて立設され、主柱の直立に支障を来す恐れを有している。
【0005】
又縦穴を画成する地盤強度は現場に応じて様々であり、地盤による管杭並びに主柱支持強度に信頼性を欠き、縦穴内周面が部分的に崩れ落ちて巣を生成する問題を有している。
【0006】
又主柱の立設強度は中込めコンクリートと根巻きコンクリート(嵩上げモルタル)にのみ依存しており、コンクリートの経年劣化、或いはコンクリート打設後に主柱とコンクリートの界面に間隙が生成され、主柱立設強度を損なう問題点を有している。
【0007】
【課題を解決するための手段】
本発明は上記問題点を適切に解決する地面立設主柱の基礎構造を提供する。
【0008】
この地面立設主柱の基礎構造は地面に縦穴を掘削し、該縦穴内に管杭を埋入し、該管杭内に中込め砕石又は中込めコンクリートを充填して管内基礎を形成し、該管杭内に主柱の下端部を遊挿して上記管内基礎に支持せしめ、更に該主柱の下端部と管杭内周面間に中込めコンクリートを充填して成る地面立設主柱の基礎構造であって、上記管杭外周面と縦穴内周面間に環状間隔を形成し、該環状間隔内に水締め砂を充填して管杭を確固に支持し、ひいては支柱を安定に支持する。
【0009】
更に上記縦穴上端の浅い拡口穴内に上記主柱を根固めする根巻きコンクリートを打設し、該根巻きコンクリートにて上記管杭の上端開口面と上記環状間隔の上端開口面を隠蔽する構造を採る。
【0010】
上記地面立設主柱の基礎構造は上記水締め砂により地盤構造に拘わらず管杭の埋設強度の信頼性を確保し、且つ管杭の垂直性を可及的に保証する。
【0011】
又他例として上記管杭外周面と縦穴内周面間の環状間隔内に水締め砂を充填して管杭を支持する構造を採りながら、上記管杭開口面を横断し且つ両端を管杭上端面に溶接又は螺子止めした両持ち支持バーを設け、該両持ち支持バーの上記横断部を上記主柱の側面に溶接又は螺子止めして主柱を管杭に強固に支持する。
【0012】
更に上記縦穴上端の浅い拡口穴内に上記主柱を根固めする根巻きコンクリートを打設し、該根巻きコンクリートにて上記両持ち支持バーを埋設すると共に上記管杭の上端開口面と上記環状間隔の上端開口面を隠蔽する構造を採る。
【0013】
上記地面立設主柱の基礎構造は前記例示と同様、上記水締め砂により地盤構造に拘わらず管杭の埋設強度の信頼性を確保し、且つ管杭の垂直性を可及的に保証すると同時に、上記両持ち支持バーにより、中込めコンクリートや根巻きコンクリートと協働して主柱の立設強度と垂直性を確保する。
【0014】
【発明の実施の形態】
以下本発明に係る地面立設主柱の基礎構造を図1乃至図10に示した工程(工法)に基づいて詳述する。
【0015】
図1に示すように、地面に拡口穴1を根切りし、所謂根切り穴を掘削する。地盤がコンクリートやアスファルトで舗装されている場合には、この舗装を方形等にカッティングして除去して上記拡口穴1を形成し、該拡口穴1内に地盤を露出せしめる。更地である場合には地盤表層部を方形等に掘削し、上記拡口穴1を形成する。
【0016】
次に図2に示すように、シャフトの周面に螺旋掘削フィンを備えた掘削装置、所謂オーガー2を用い、上記拡口穴1の略中心部に縦穴3を所要の深さに掘削する。
【0017】
次に図3に示すように、上記縦穴3の内底部に底込め砕石4を投入して底基礎5を形成する。
【0018】
次に図4に示すように、上記縦穴3内に管杭6を遊埋入してその下端面を上記底基礎5上に支持せしめ、上記管杭6の外周面と縦穴3の内周面間に環状間隔7を形成する。即ち上記縦穴3内に管杭6を環状間隔7を存して埋入する。
【0019】
上記管杭6は両端が開放された貫通管腔を有する管杭であり、コンクリート管杭又は鋼管杭から成る。
【0020】
上記管杭6は図4に示すように、その下端面を底基礎5上に支持しつつ、その上端部を縦穴3の開口面から拡口穴1内へ突出せしめる。又は管杭6の下端面を底基礎5上に支持しつつ、その上端面を縦穴3の開口面と略同一レベルに埋設する。
【0021】
次に図5に示すように、上記管杭6の外周面と縦穴3の内周面間の環状間隔7に砂を水締めしつつ充填する。8はこの水締め砂を示す。
【0022】
上記水締め時に縦穴3の内周面の崩壊を防止し且つ管杭6内に水が注入されないようにすることが肝要であり、その手段として例えば、上記管杭6の上端開口面を蓋9で覆い、該蓋9上に砂、好ましくは山砂を盛り上げ、該盛り上げ砂8′を水道に接続したホース10から放出した水22で崩しつつ、管杭6の外周面に沿って上記環状間隔7内への砂8を流し込み充填する。
【0023】
上記水締め砂8はその水分が底基礎5内へ浸透しつつ逃がされ、固く砂締め、所謂水締めされる。この水締め砂はその下端が底基礎5上に支持され、同上端面が縦穴3の開口面と略同一レベルになるまで充填する。
【0024】
次に図6に示すように、上記蓋9を取り除き、管杭6内の途中まで中込め砕石11を充填して上記底基礎5上に積層し、管内基礎12を形成する。
【0025】
上記管内基礎12は中込め砕石11に代え、中込めコンクリートを管杭6内へ充填して形成できる。
【0026】
次に図7に示すように、上記管内基礎12を形成した管杭6内に角柱又は円柱から成る主柱13の下端部を遊挿して、その下端面を上記管内基礎12の上面に支持させて直立し、主柱13の下端部外周面と管杭6の上端内周間に環状間隔15を形成する。
【0027】
上記主柱13は鋼管主柱又はコンクリート主柱であり、何れも既存のものであり、用途に応じ使い分ける。コンクリート主柱はその上端面にリング形の鋼製カバー23を被嵌し、補強した構造を有する。
【0028】
次に図8Aに示すように、上記管杭6の上端開口面から主柱13と管杭6間の環状間隔15内へ楔14を打ち込み、主柱13の直立を保持する。該楔14は主柱13の周囲に略等間隔に複数打ち込み、主柱13を管杭6の略中心部に支持する。
【0029】
次に図9Aに示すように、上記楔14間を通して上記環状間隔15内へ中込めコンクリート16を充填し、主柱13を支持する。この中込めコンクリート16はその下端が上記管内基礎12に達し、その上端面が管杭6の開口面と略同一レベル、又は同開口面直下に達するまで充填する。
【0030】
次に図10Aに示すように、上記楔14を取り除き、又は楔14を残存し、上記拡口穴1内へ上記主柱13を根固めする根巻きコンクリート17を打設し、該根巻きコンクリート17にて上記管杭6の上端面及び上端開口面と上記水締め砂8が充填された環状間隔7の上端開口面を隠蔽し、管杭6と一体化し且つ中込めコンクリートと一体化する。
【0031】
前記の通り管杭6の上端を拡口穴1内へ突出する場合には、該管杭6の突出部18の外周面と拡口穴1の内周面間に根巻きコンクリート17を充填し、同突出部18を該根巻きコンクリート17内へ一体に埋設する。
【0032】
次に図8B,Cと図9Bと図10Bに基づき上記楔14を用いない地面立設主柱の基礎構造について説明する。
【0033】
図1乃至図7の工程は前記と同様であり、前記説明を援用する。即ち図7に基づき説明したように、主柱13を管杭6内の基礎12上に支持しつつ直立し、次に図8B,図8Cに示すように、上記管杭6の開口面を横断し且つ両端を管杭6の上端面に溶接19又は螺子止めした両持ち支持バー20を設け、該両持ち支持バー20の上記横断部を上記主柱13の側面に溶接21して又は螺子止めして主柱13を管杭6に強固に支持する。螺子止めとは何れもアンカー止めを包含する。以下同様である。
【0034】
上記両持ち支持バー20は、例えば角柱又は円柱から成る主柱13の対向する側面に添えて二本並設し、上記各溶接19,21を施すか螺子止めする。
【0035】
上記両持ち支持バー20は鋼材から成るL形チャンネル(アングル鋼材)、又は鋼棒、鋼パイプ等を用いることができる。又上記管杭6が鋼管から成る場合には上記両持ち支持バー20の溶接が可能であるが、コンクリート杭の場合には前記した通りの管杭上端面にリング形の鋼製カバーを被嵌したものを用い、該鋼製カバーに上記両持ち支持バー20を溶接又は螺子止めする。又は鋼製カバーを有しないコンクリート杭の場合には螺子止めにて対処する。
【0036】
よって上記管杭6の外周面と縦穴3の内周面間の環状間隔7内に水締め砂8を固く充填して管杭6を支持する構造と協働して、管杭6並びに主柱13の支持強度と垂直性を確保する。
【0037】
次に図9Bに示すように、上記両持ち支持バー20間を通して上記環状間隔15内へ中込めコンクリート16を充填し、主柱13を支持する。この中込めコンクリート16はその下端が上記管内基礎12へ達し、その上端面が管杭6の開口面と略同一レベル、又は同開口面直下に達するまで充填する。
【0038】
次に図10Bに示すように、上記縦穴3の上端の浅い拡口穴1内に上記主柱13を根固めする根巻きコンクリート17を打設し、該根巻きコンクリート17内に上記両持ち支持バー20を一体に埋設すると共に、同コンクリート17にて上記管杭6の上記中込めコンクリート16が充填された上端開口面と、上記水締め砂8が充填された環状間隔7の上端開口面を隠蔽し、管杭6と一体化し且つ中込めコンクリートと一体化する。
【0039】
前記の通り管杭6の上端を拡口穴1内へ突出する場合には、該管杭6の突出部18の外周面と拡口穴1の内周面間に根巻きコンクリート17を充填し、同突出部18を該根巻きコンクリート17内へ一体に埋設する。上記拡口穴1内には鉄筋を組み筋し、鉄筋コンクリート構造としても良い。
【0040】
上記コンクリートとはセメントと砂と砂利を混練したもの、或いは砂利を混入せずにセメントと砂を混練したモルタルを含む。
【0041】
又上記中込めコンクリート16と根巻きコンクリート17は別々に打設するか、又は同時に打設する。
【0042】
【発明の効果】
上記地面立設主柱の基礎構造によれば、上記水締め砂により地盤構造に拘わらず管杭の埋設強度の信頼性と、管杭の垂直性を可及的に確保できる。
【0043】
又上記両持ち支持バーが上記水締め砂並びに中込めコンクリートや根巻きコンクリートと協働して、主柱の立設強度と垂直性を確保できる。
【図面の簡単な説明】
【図1】拡口穴の根切り工程を示す断面図。
【図2】縦穴の掘削工程を示す断面図。
【図3】上記縦穴内の底基礎の形成工程を示す断面図。
【図4】上記底基礎上に立設する管杭の縦穴内への埋入工程を示す断面図。
【図5】上記管杭周面の環状間隔内への水締め砂の充填工程を示す断面図。
【図6】上記管杭内に管内基礎を形成する工程を示す断面図。
【図7】上記管内基礎上に主柱を立設する工程を示す断面図。
【図8】Aは上記主柱を楔にて支持する工程を示す断面図、Bは該楔を用いずに両持ち支持バーにて主柱を支持する工程を示す断面図、Cは該両持ち支持バーの平面図。
【図9】Aは図8Aにおける楔を通して管杭内へ中込めコンクリートを充填する工程を示す断面図、Bは図8Bにおける両持ち支持バーを通して管杭内へ中込めコンクリートを充填する工程を示す断面図。
【図10】Aは上記楔を用いた図9Aにおける拡口穴内へ根巻きコンクリートを打設する工程を示す断面図、Bは上記両持ち支持バー用いた図9Bにおける拡口穴内へ根巻きコンクリートを打設する工程を示す断面図
【符号の説明】
1…拡口穴、2…オーガー、3…縦穴、4…底込め砕石、5…底基礎、6…管杭、7…環状間隔、8…水締め砂、8′…盛り上げ砂、9…蓋、10…ホース、11…中込め砕石、12…管内基礎、13…主柱、14…楔、15…環状間隔、16…中込めコンクリート、17…根巻きコンクリート、18…突出部、19…溶接、20…両持ち支持バー、21…溶接、22…水、23…鋼製カバー
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a basic structure of a main pillar standing on the ground, such as a main pillar for posting a traffic sign or a signboard, or a main pillar for extending a net such as a driving range.
[0002]
[Prior art]
In Patent Document 1, a vertical hole is excavated in the ground, and a pipe pile is embedded in the vertical hole, and the inside of the pipe pile is filled with crushed crushed stone or medium-filled concrete to form a pipe foundation. Disclose the main structure of the main pillar standing on the ground by inserting the lower end of the main pillar into the pipe foundation and supporting it on the above-mentioned pipe foundation, and filling in the concrete between the lower end of the main pillar and the inner peripheral surface of the pipe pile. ing.
[0003]
[Patent Document 1]
Japanese Examined Patent Publication No. 3-28540 [0004]
[Problems to be solved by the invention]
However, in the basic structure of the ground standing main pillar shown in the above-mentioned Patent Document 1, a structure in which the main pillar is directly restrained by the inner peripheral surface of the vertical hole is adopted. The pipe piles are also tilted, and there is a risk of hindering the upright of the main pillar.
[0005]
In addition, the strength of the ground that defines the vertical hole varies depending on the site, and the pipe pile and main column support strength by the ground is unreliable, and the inner peripheral surface of the vertical hole partially collapses and generates a nest. ing.
[0006]
In addition, the standing strength of the main pillar depends only on the embedded concrete and the root-wrapped concrete (raised mortar). The concrete deteriorates over time, or a gap is generated at the interface between the main pillar and concrete after the concrete is cast. It has the problem of impairing the standing strength.
[0007]
[Means for Solving the Problems]
The present invention provides a foundation structure of a ground standing main pillar that appropriately solves the above problems.
[0008]
The foundation structure of this ground standing main pillar excavates a vertical hole in the ground, embeds a pipe pile in the vertical hole, fills the pipe pile with crushed stone or medium concrete, and forms a pipe foundation, The lower end of the main pillar is loosely inserted into the pipe pile and supported by the pipe foundation, and the ground standing main pillar is formed by filling in the concrete between the lower end of the main pillar and the inner peripheral surface of the pipe pile. It is a basic structure, and an annular interval is formed between the outer peripheral surface of the pipe pile and the inner peripheral surface of the vertical hole, and the ring pile is filled with water-tight sand to firmly support the pipe pile, and thus support the column stably. To do.
[0009]
Further, a structure in which a root-wrapped concrete that solidifies the main pillar is placed in a shallow widened hole at the upper end of the vertical hole, and the upper-end opening surface of the pipe pile and the upper-end opening surface of the annular interval are concealed by the root-wrapped concrete. Take.
[0010]
The foundation structure of the ground standing main pillar ensures the reliability of pipe pile burying strength as much as possible with the water-tight sand regardless of the ground structure.
[0011]
As another example, while adopting a structure in which watertight sand is filled in an annular interval between the outer peripheral surface of the pipe pile and the inner peripheral surface of the vertical hole to support the pipe pile, the pipe pile crossing the pipe pile opening surface and both ends of the pipe pile are taken. A both-end support bar welded or screwed to the upper end surface is provided, and the transverse portion of the both-end support bar is welded or screwed to the side surface of the main column to firmly support the main column to the pipe pile.
[0012]
Further, a root-rolling concrete that solidifies the main pillar is placed in the shallow widening hole at the upper end of the vertical hole, the both-end support bar is embedded in the root-wrapping concrete, and the upper end opening surface of the pipe pile and the annular shape A structure that conceals the upper end opening surface of the interval is adopted.
[0013]
As in the above example, the foundation structure of the ground standing main pillar is to ensure the reliability of pipe pile burying strength regardless of the ground structure, and to guarantee the verticality of the pipe pile as much as possible. At the same time, the above-mentioned doubly-supported support bar ensures the standing strength and verticality of the main column in cooperation with the embedded concrete and the cored concrete.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the basic structure of the main standing column according to the present invention will be described in detail based on the steps (construction methods) shown in FIGS.
[0015]
As shown in FIG. 1, the widening hole 1 is rooted in the ground, and a so-called root cutting hole is excavated. In the case where the ground is paved with concrete or asphalt, the pavement is cut and removed into a square or the like to form the widened hole 1, and the ground is exposed in the widened hole 1. In the case of clear land, the ground surface layer is excavated into a square or the like to form the above-mentioned widened hole 1.
[0016]
Next, as shown in FIG. 2, a vertical hole 3 is excavated to a required depth at a substantially central portion of the expanded hole 1 by using a so-called auger 2 having a spiral excavation fin on the peripheral surface of the shaft.
[0017]
Next, as shown in FIG. 3, the bottom foundation 5 is formed by introducing the bottomed crushed stone 4 into the inner bottom of the vertical hole 3.
[0018]
Next, as shown in FIG. 4, the pipe pile 6 is loosely embedded in the vertical hole 3 and the lower end surface thereof is supported on the bottom foundation 5, and the outer peripheral surface of the pipe pile 6 and the inner peripheral surface of the vertical hole 3. An annular interval 7 is formed between them. That is, the pipe pile 6 is embedded in the vertical hole 3 with an annular interval 7.
[0019]
The said pipe pile 6 is a pipe pile which has the penetration lumen | bore open | released at both ends, and consists of a concrete pipe pile or a steel pipe pile.
[0020]
As shown in FIG. 4, the pipe pile 6 protrudes from the opening surface of the vertical hole 3 into the enlarged hole 1 while supporting the lower end surface on the bottom foundation 5. Alternatively, while supporting the lower end surface of the pipe pile 6 on the bottom foundation 5, the upper end surface is embedded at substantially the same level as the opening surface of the vertical hole 3.
[0021]
Next, as shown in FIG. 5, sand is filled in the annular interval 7 between the outer peripheral surface of the pipe pile 6 and the inner peripheral surface of the vertical hole 3 while water-tightening. 8 shows this watertight sand.
[0022]
It is important to prevent the inner peripheral surface of the vertical hole 3 from collapsing when the water is tightened and to prevent water from being injected into the pipe pile 6. For example, the upper end opening surface of the pipe pile 6 is covered with a lid 9. And crushing sand, preferably mountain sand, on the lid 9, and crushing the raised sand 8 ′ with water 22 discharged from the hose 10 connected to the water supply, and the annular spacing along the outer circumferential surface of the pipe pile 6. Pour sand 8 into 7 and fill.
[0023]
The water-tightening sand 8 is released while its moisture penetrates into the bottom foundation 5, and is tightly sanded, so-called watertight. The lower end of the water-tightening sand is supported on the bottom foundation 5 and is filled until the upper end surface is substantially at the same level as the opening surface of the vertical hole 3.
[0024]
Next, as shown in FIG. 6, the lid 9 is removed, and a medium-filled crushed stone 11 is filled in the pipe pile 6 and laminated on the bottom foundation 5 to form the pipe foundation 12.
[0025]
The in-pipe foundation 12 can be formed by filling the inside of the pipe pile 6 with the inside concrete instead of the inside crushed stone 11.
[0026]
Next, as shown in FIG. 7, the lower end portion of the main pillar 13 made of a prism or a cylinder is loosely inserted into the pipe pile 6 in which the inner pipe foundation 12 is formed, and the lower end surface is supported on the upper surface of the inner pipe foundation 12. The annular interval 15 is formed between the outer peripheral surface of the lower end portion of the main column 13 and the inner periphery of the upper end of the pipe pile 6.
[0027]
The main pillar 13 is a steel pipe main pillar or a concrete main pillar, both of which are existing, and are selectively used according to the application. The concrete main column has a structure in which a ring-shaped steel cover 23 is fitted on the upper end surface of the column and reinforced.
[0028]
Next, as shown in FIG. 8A, the wedge 14 is driven into the annular space 15 between the main pillar 13 and the pipe pile 6 from the upper end opening surface of the pipe pile 6 to keep the main pillar 13 upright. A plurality of wedges 14 are driven around the main pillar 13 at substantially equal intervals, and the main pillar 13 is supported at a substantially central portion of the pipe pile 6.
[0029]
Next, as shown in FIG. 9A, the embedded concrete 16 is filled into the annular interval 15 through the wedges 14 to support the main pillar 13. The inside concrete 16 is filled until the lower end reaches the pipe foundation 12 and the upper end surface reaches substantially the same level as or directly below the opening surface of the pipe pile 6.
[0030]
Next, as shown in FIG. 10A, the wedge 14 is removed or the wedge 14 is left, and a root-rolling concrete 17 that solidifies the main pillar 13 is placed in the widened hole 1. In 17, the upper end surface and upper end opening surface of the pipe pile 6 and the upper end opening surface of the annular interval 7 filled with the water-tightening sand 8 are concealed, and are integrated with the pipe pile 6 and integrated concrete.
[0031]
When the upper end of the pipe pile 6 protrudes into the enlarged hole 1 as described above, the root-wrapped concrete 17 is filled between the outer peripheral surface of the protruding portion 18 of the pipe pile 6 and the inner peripheral surface of the enlarged hole 1. The projecting portion 18 is integrally embedded in the root-wrapped concrete 17.
[0032]
Next, the basic structure of the main standing column which does not use the wedge 14 will be described with reference to FIGS. 8B and 8C, FIG. 9B and FIG. 10B.
[0033]
The steps in FIGS. 1 to 7 are the same as those described above, and the above description is incorporated. That is, as explained based on FIG. 7, the main pillar 13 is supported upright on the foundation 12 in the pipe pile 6, and then, as shown in FIGS. 8B and 8C, crosses the opening surface of the pipe pile 6. Further, a both-end support bar 20 having both ends welded or screwed to the upper end surface of the pipe pile 6 is provided, and the transverse portion of the both-end support bar 20 is welded 21 to the side surface of the main column 13 or screwed. Thus, the main column 13 is firmly supported by the pipe pile 6. All screw stops include anchor stops. The same applies hereinafter.
[0034]
The two end support bars 20 are provided side by side along the opposite side surfaces of the main pillar 13 made of, for example, a prism or a cylinder, and each of the welds 19 and 21 is applied or screwed.
[0035]
The double-supported bar 20 can be an L-shaped channel (angle steel material) made of steel, or a steel rod, steel pipe, or the like. When the pipe pile 6 is made of a steel pipe, it is possible to weld the doubly supported bar 20, but in the case of a concrete pile, a ring-shaped steel cover is fitted on the upper end surface of the pipe pile as described above. The above-mentioned doubly-supported support bar 20 is welded or screwed to the steel cover. Or, in the case of a concrete pile without a steel cover, it is dealt with by screwing.
[0036]
Therefore, the pipe pile 6 and the main column are cooperated with the structure in which the water-tight sand 8 is firmly filled in the annular space 7 between the outer peripheral surface of the pipe pile 6 and the inner peripheral surface of the vertical hole 3 to support the pipe pile 6. 13 support strength and perpendicularity are ensured.
[0037]
Next, as shown in FIG. 9B, the interstitial concrete 16 is filled into the annular interval 15 through the support rods 20 and the main pillar 13 is supported. The inside concrete 16 is filled until the lower end reaches the pipe foundation 12 and the upper end surface reaches substantially the same level as or directly below the opening surface of the pipe pile 6.
[0038]
Next, as shown in FIG. 10B, a wrapping concrete 17 for solidifying the main pillar 13 is placed in the shallow widening hole 1 at the upper end of the vertical hole 3, and the both-end support is supported in the wrapping concrete 17. The bar 20 is embedded integrally, and the upper end opening surface of the pipe pile 6 filled with the embedded concrete 16 and the upper end opening surface of the annular interval 7 filled with the water-tightening sand 8 are filled with the concrete 17. It is concealed, integrated with the pipe pile 6 and integrated with the embedded concrete.
[0039]
When the upper end of the pipe pile 6 protrudes into the enlarged hole 1 as described above, the root-wrapped concrete 17 is filled between the outer peripheral surface of the protruding portion 18 of the pipe pile 6 and the inner peripheral surface of the enlarged hole 1. The projecting portion 18 is integrally embedded in the root-wrapped concrete 17. Reinforcing bars may be combined in the enlarged hole 1 to form a reinforced concrete structure.
[0040]
The concrete includes a mixture of cement, sand and gravel, or a mortar in which cement and sand are mixed without mixing gravel.
[0041]
The intermediate concrete 16 and the root-wrapped concrete 17 are cast separately or simultaneously.
[0042]
【The invention's effect】
According to the foundation structure of the ground standing main pillar, the reliability of the embedding strength of the pipe pile and the verticality of the pipe pile can be ensured as much as possible regardless of the ground structure by the watertight sand.
[0043]
Also, the both-end support bar cooperates with the water-tightening sand, the embedded concrete and the root-wrapped concrete to ensure the standing strength and verticality of the main pillar.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing a root cutting process of an enlarged hole.
FIG. 2 is a cross-sectional view showing a vertical hole excavation process.
FIG. 3 is a cross-sectional view showing a process of forming a bottom foundation in the vertical hole.
FIG. 4 is a cross-sectional view showing a step of embedding a pipe pile standing on the bottom foundation into a vertical hole.
FIG. 5 is a cross-sectional view showing a filling process of water-tight sand into the annular interval of the pipe pile peripheral surface.
FIG. 6 is a cross-sectional view showing a process of forming a pipe foundation in the pipe pile.
FIG. 7 is a cross-sectional view showing a process of erecting a main pillar on the pipe foundation.
8A is a cross-sectional view showing a process of supporting the main column with a wedge, B is a cross-sectional view showing a process of supporting the main column with a double-supported bar without using the wedge, and C is a cross-sectional view of the process. The top view of a supporting bar.
9A is a cross-sectional view showing the process of filling the concrete pile into the pipe pile through the wedge in FIG. 8A, and FIG. 9B is the process of filling the concrete pile into the pipe pile through the doubly supported bar in FIG. 8B. Sectional drawing.
FIG. 10A is a cross-sectional view showing a step of placing the root-wrapped concrete into the widened hole in FIG. 9A using the wedge, and B is the root-wrapped concrete into the widened hole in FIG. 9B using the above-mentioned double-supported bar. Sectional drawing showing the process of placing
DESCRIPTION OF SYMBOLS 1 ... Mouth opening hole, 2 ... Auger, 3 ... Vertical hole, 4 ... Bottom crushed stone, 5 ... Bottom foundation, 6 ... Pipe pile, 7 ... Ring interval, 8 ... Water-tight sand, 8 '... Raised sand, 9 ... Lid DESCRIPTION OF SYMBOLS 10 ... Hose, 11 ... Medium-filled crushed stone, 12 ... In-pipe foundation, 13 ... Main pillar, 14 ... Wedge, 15 ... Annular spacing, 16 ... Medium-filled concrete, 17 ... Necked concrete, 18 ... Projection, 19 ... Welding 20 ... Both-end support bar, 21 ... Welding, 22 ... Water, 23 ... Steel cover

Claims (2)

地面に縦穴を掘削し、該縦穴内に管杭を埋入し、該管杭内に中込め砕石又は中込めコンクリートを充填して管内基礎を形成し、該管杭内に主柱の下端部を遊挿して上記管内基礎に支持せしめ、更に該主柱の下端部と管杭内周面間に中込コンクリートを充填して成る地面立設主柱の基礎構造において、上記縦穴内に管杭を環状間隔を存して埋入し、該環状間隔内に水締め砂を充填して管杭を支持し、更に上記縦穴上端の浅い拡口穴内に上記主柱を根固めする根巻きコンクリートを打設し、該根巻コンクリートにて上記管杭の上端開口面と上記環状間隔の上端開口面を隠蔽する構成としたことを特徴とする地面立設主柱の基礎構造。Drill a vertical hole in the ground, embed a pipe pile in the vertical hole, fill the pipe pile with crushed crushed stone or medium concrete, form a pipe foundation, and the lower end of the main column in the pipe pile In the foundation structure of the main standing column which is filled with interstitial concrete between the lower end of the main pillar and the inner peripheral surface of the pipe pile, and the pipe pile is inserted into the vertical hole. Placed in the annular interval, filled with water-tight sand in the annular interval to support the pipe piles, and then cast the wound concrete that solidifies the main column in the shallow widened hole at the upper end of the vertical hole. A foundation structure of a main pillar standing on the ground, wherein the root pile concrete is configured to conceal the upper end opening surface of the pipe pile and the upper end opening surface of the annular interval. 地面に縦穴を掘削し、該縦穴内に管杭を埋入し、該管杭内に中込め砕石又は中込めコンクリートを充填して管内基礎を形成し、該管杭内に主柱の下端部を遊挿して上記管内基礎に支持せしめ、更に該主柱の下端部と管杭内周面間に中込めコンクリートを充填して成る地面立設主柱の基礎構造において、上記縦穴内に管杭を環状間隔を存して埋入し、該環状間隔内に水締め砂を充填して管杭を支持し、更に上記管杭開口面を横断し且つ両端を管杭上端面に溶接又は螺子止めした両持ち支持バーを設け、該両持ち支持バーの上記横断部を上記主柱の側面に溶接又は螺子止めし、更に上記縦穴上端の浅い拡口穴内に上記主柱を根固めする根巻きコンクリートを打設し、該根巻きコンクリートにて上記両持ち支持バーを埋設すると共に上記管杭の上端開口面と上記環状間隔の上端開口面を隠蔽する構成としたことを特徴とする地面立設主柱の基礎構造。Drill a vertical hole in the ground, embed a pipe pile in the vertical hole, fill the pipe pile with crushed crushed stone or medium concrete, form a pipe foundation, and the lower end of the main column in the pipe pile In the foundation structure of the main standing column which is filled with interstitial concrete between the lower end of the main pillar and the inner peripheral surface of the pipe pile, and the pipe pile is inserted into the vertical hole. Is inserted in an annular interval, filled with water-tight sand in the annular interval to support the pipe pile, and further, the pipe pile opening surface is crossed and both ends are welded or screwed to the pipe pile upper end surface. A wrap-around concrete that includes the above-mentioned double-supported support bar, welds or screws the transverse portion of the double-supported support bar to the side surface of the main column, and further solidifies the main column in a shallow widened hole at the upper end of the vertical hole And burying the above-mentioned doubly supported bar with the root-wrapped concrete and the upper end of the above-mentioned pipe pile Basic structure of the ground elevation 設主 pillar, characterized in that it has a configuration to conceal the mouth surface and the upper end open surface of said annular spacing.
JP2002356356A 2002-12-09 2002-12-09 Foundation structure of main pillar standing on the ground Expired - Fee Related JP3622963B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002356356A JP3622963B2 (en) 2002-12-09 2002-12-09 Foundation structure of main pillar standing on the ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002356356A JP3622963B2 (en) 2002-12-09 2002-12-09 Foundation structure of main pillar standing on the ground

Publications (2)

Publication Number Publication Date
JP2004190241A true JP2004190241A (en) 2004-07-08
JP3622963B2 JP3622963B2 (en) 2005-02-23

Family

ID=32756719

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002356356A Expired - Fee Related JP3622963B2 (en) 2002-12-09 2002-12-09 Foundation structure of main pillar standing on the ground

Country Status (1)

Country Link
JP (1) JP3622963B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009097244A (en) * 2007-10-17 2009-05-07 Ibigawa Concrete Kogyo Kk Concrete block and locking member for erecting pole
US7993079B2 (en) * 2004-08-12 2011-08-09 Societe Centrale D'etudes Et De Realisations Routieres Scetauroute Device and method for a tower reinforcing foundation
JP2012052383A (en) * 2010-09-02 2012-03-15 Jfe Civil Engineering & Construction Corp Construction method of steel pipe support
JP2013057204A (en) * 2011-09-08 2013-03-28 Toshiba Plant Systems & Services Corp Foundation pile construction method, foundation pile, and solar cell array
CN107437374A (en) * 2016-12-31 2017-12-05 广州迪然安全检测技术有限公司 A kind of alarming device for forest fire protection
CN107437373A (en) * 2016-12-31 2017-12-05 广州迪然安全检测技术有限公司 A kind of alarming device of forest fire protection
CN107437386A (en) * 2016-12-31 2017-12-05 广州曙迅自动化设备有限公司 A kind of indication plate that changes its course of road construction
JP2020094421A (en) * 2018-12-13 2020-06-18 Jfeシビル株式会社 Joint structure for pile and superstructure, construction method for joint structure, and structural body
JP2020117902A (en) * 2019-01-22 2020-08-06 東日本旅客鉄道株式会社 Assembly foundation of column and construction method thereof
JP7333955B2 (en) 2019-12-10 2023-08-28 有限会社大竹重機建設 Method of erecting a columnar work

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6867664B1 (en) * 2020-12-22 2021-05-12 株式会社トラバース Foundation structure of structure, foundation construction method, and support pipe material used for foundation

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7993079B2 (en) * 2004-08-12 2011-08-09 Societe Centrale D'etudes Et De Realisations Routieres Scetauroute Device and method for a tower reinforcing foundation
JP2009097244A (en) * 2007-10-17 2009-05-07 Ibigawa Concrete Kogyo Kk Concrete block and locking member for erecting pole
JP2012052383A (en) * 2010-09-02 2012-03-15 Jfe Civil Engineering & Construction Corp Construction method of steel pipe support
JP2013057204A (en) * 2011-09-08 2013-03-28 Toshiba Plant Systems & Services Corp Foundation pile construction method, foundation pile, and solar cell array
CN107437374B (en) * 2016-12-31 2019-08-30 浙江黄岩德威塑料制品厂 A kind of alarming device for forest fire protection
CN107437373A (en) * 2016-12-31 2017-12-05 广州迪然安全检测技术有限公司 A kind of alarming device of forest fire protection
CN107437386A (en) * 2016-12-31 2017-12-05 广州曙迅自动化设备有限公司 A kind of indication plate that changes its course of road construction
CN107437386B (en) * 2016-12-31 2019-08-27 台州市绿鑫交通设施有限公司 A kind of indication plate that changes its course of road construction
CN107437374A (en) * 2016-12-31 2017-12-05 广州迪然安全检测技术有限公司 A kind of alarming device for forest fire protection
CN107437373B (en) * 2016-12-31 2019-10-18 南安松茂贸易有限公司 A kind of alarming device of forest fire protection
JP2020094421A (en) * 2018-12-13 2020-06-18 Jfeシビル株式会社 Joint structure for pile and superstructure, construction method for joint structure, and structural body
JP7146607B2 (en) 2018-12-13 2022-10-04 Jfeシビル株式会社 Joint structure between pile and superstructure, construction method for joint structure, and structure
JP2022171931A (en) * 2018-12-13 2022-11-11 Jfeシビル株式会社 Joint structure for pile and superstructure, and structural body
JP7345614B2 (en) 2018-12-13 2023-09-15 Jfeシビル株式会社 Joint structure and structure between pile and superstructure
JP2020117902A (en) * 2019-01-22 2020-08-06 東日本旅客鉄道株式会社 Assembly foundation of column and construction method thereof
JP7333955B2 (en) 2019-12-10 2023-08-28 有限会社大竹重機建設 Method of erecting a columnar work

Also Published As

Publication number Publication date
JP3622963B2 (en) 2005-02-23

Similar Documents

Publication Publication Date Title
JP3622963B2 (en) Foundation structure of main pillar standing on the ground
KR20110041391A (en) Pile structure
JP2005180079A (en) Aseismatic reinforcement structure of construction
JPS5985028A (en) Steel pipe pile and laying work thereof
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JP3895363B1 (en) New foundation structure
JP2011163009A (en) Subsidence prevention structure of foundation steel pipe
JP3486602B2 (en) Pier foundation method and pier foundation structure
JP3481508B2 (en) Stone masonry retaining wall reinforcement method
JP4485006B2 (en) Construction method for underground structures
JPS59126821A (en) Erection work of foundation pile
JP2005240426A (en) Erection structure for steel-pipe column
JP2018044337A (en) Structure and method for reinforcing embankment
JP5300163B1 (en) Steel pile rooting method
JP2004150070A (en) Treatment method for removed soil, and removed soil-treated construction method for foundation pile
JP3772915B2 (en) Foundation pile construction method and foundation pile
JP2014109190A (en) Foot protection method for steel pile
JPS6250516A (en) Formation work of composite pile
JP3612524B2 (en) Septic tank installation and construction method
CN220486515U (en) Anti-sedimentation structure of silt soil layer overpass pile foundation
JP2006037491A (en) Expanded head pile and construction method of expanded head pile
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
JP4344733B2 (en) Seismic reinforcement structure for existing pile foundation structures
JP2006037413A (en) Method for improving ground under railway and ground improving rod
JP2005290870A (en) Foundation structure

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20041116

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041119

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3622963

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071203

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081203

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081203

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091203

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091203

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101203

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111203

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111203

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121203

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121203

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131203

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees