JP2003206539A - Temporary closing construction method - Google Patents

Temporary closing construction method

Info

Publication number
JP2003206539A
JP2003206539A JP2002005230A JP2002005230A JP2003206539A JP 2003206539 A JP2003206539 A JP 2003206539A JP 2002005230 A JP2002005230 A JP 2002005230A JP 2002005230 A JP2002005230 A JP 2002005230A JP 2003206539 A JP2003206539 A JP 2003206539A
Authority
JP
Japan
Prior art keywords
steel sheet
sheet pile
pile
ground
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002005230A
Other languages
Japanese (ja)
Other versions
JP3979466B2 (en
Inventor
Kazuhiro Yamauchi
山内一宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hirose and Co Ltd
Original Assignee
Hirose and Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hirose and Co Ltd filed Critical Hirose and Co Ltd
Priority to JP2002005230A priority Critical patent/JP3979466B2/en
Publication of JP2003206539A publication Critical patent/JP2003206539A/en
Application granted granted Critical
Publication of JP3979466B2 publication Critical patent/JP3979466B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide an economical temporary closing construction method having a short construction period for driving a steel sheet pile in hard ground. <P>SOLUTION: This temporary closing construction method to be temporarily arranged in an outer peripheral part 1 of an objective structure, is characterized in that a plurality of master piles 2 are driven at prescribed intervals in the outer peripheral part 1, a waling material 31 is extended to the outer periphery of the driven master piles 2, the steel sheet pile 4 is also driven outside, and the steel sheet pile 4 is fixed to the waling material 31. <P>COPYRIGHT: (C)2003,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、硬質地盤又は岩盤
に構築する仮締切り工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a temporary cutoff method for constructing on hard ground or rock.

【0002】[0002]

【従来の技術】従来から水中または水際に構築物を築造
する場合、一時的に工事に必要な部分から完全に水を排
除してドライワークとし、工事を行うことが多い。この
方法として、仮締切り工法が知られている。また、陸上
に築造される構造物にあっても、地下水位以下の掘削を
伴う場合の土留め工では水を締切る必要があり、この場
合にも使用される。このように仮締切り工には、外部よ
り主として水圧、土圧等の圧力が働くことになる。その
ため、仮締切り工にはそれらの圧力に耐え得る十分な強
度を備え持つと同時に、本工事内をドライな状態に保つ
ための止水機能も併せ持つことが要求される。仮締切り
工法は、一般的に鋼矢板bを地盤に打込んで連続した壁
体を築造して締切る工法であるが、現場によっては鋼矢
板bを打設する地盤が硬質地盤または岩盤(以下、硬質
地盤という。)であることがある。この場合、従来では
たとえばあらかじめケーシングcを用いてダウンザホー
ルハンマ工法等により所定の硬質地盤を先行して削孔し
た後、鋼矢板bを打設し硬質地盤に支持していた。而し
て、地盤からの受働抵抗により自立する鋼矢板bは外側
から受ける水圧等を鋼矢板bの剛性により根入れ部に伝
播し、また十分な深度を有することで鋼矢板bの下周り
からの浸水を抑える。このため、従来の硬質地盤への仮
締切り工法においては、鋼矢板bの全打設箇所にあらか
じめ削孔を行う必要があった。しかしながら、仮締切り
工はあくまで仮設工事として使用されることが多く、一
般的に本工事に比べ安全率を低く設定するなどして、施
工費を削減する動向にある。
2. Description of the Related Art Conventionally, in the case of constructing a structure underwater or at the water's edge, it is often the case that the work is temporarily performed by completely removing water from the parts required for the construction and making it a dry work. As this method, a temporary cutoff method is known. In addition, even for structures built on land, it is necessary to cut off the water in the earth retaining work when excavating below the groundwater level, and this is also used in this case. As described above, the temporary shut-off work mainly receives pressure such as water pressure and earth pressure from the outside. Therefore, the temporary shut-off work is required to have sufficient strength to withstand those pressures and also have a water stop function for keeping the inside of the construction work in a dry state. The temporary cutoff method is generally a method in which steel sheet pile b is driven into the ground to construct a continuous wall body and cut off. However, depending on the site, the ground where the steel sheet pile b is laid is hard ground or rock (hereinafter , Hard ground). In this case, conventionally, for example, a casing c is used in advance to drill a predetermined hard ground by a down-the-hole hammer method or the like, and then a steel sheet pile b is driven and supported on the hard ground. Thus, the steel sheet pile b which is self-supporting by the passive resistance from the ground propagates the water pressure received from the outside to the rooting portion due to the rigidity of the steel sheet pile b, and also has a sufficient depth so that Suppress flooding. Therefore, in the conventional temporary cutoff method for hard ground, it is necessary to drill holes in all places where the steel sheet pile b is set. However, the temporary cut-off work is often used only for temporary work, and generally, there is a trend to reduce the construction cost by setting a safety factor lower than that of this work.

【0003】[0003]

【発明が解決しようとする課題】前記した従来の硬質地
盤への仮締切り工法にあっては、次のような問題点があ
る。 <イ>硬質地盤に鋼矢板を打設するにあたり、先行して
ダウンザホールハンマ工法等による硬質地盤への削孔が
必要になる。このため、鋼矢板の全打設箇所において削
孔が必要となり、施工費用や工期がかかり不経済であ
る。 <ロ>水圧等の外部から受けた力を地盤へ伝播して抵抗
する作用は鋼矢板のみで行っている。 そのため、現場の状況変更等の理由から設計変更に伴う
各種施工の変更には、主部材である鋼矢板の種類変更お
よび鋼矢板の打設方法の変更と施工全体に及ぶため非常
に影響が大きい。
The above-mentioned conventional temporary cutoff method for the hard ground has the following problems. <a> Before placing a steel sheet pile on hard ground, it is necessary to drill a hole in the hard ground by the down-the-hole hammer method or the like. For this reason, it is necessary to drill holes in all the places where the steel sheet pile is placed, which is uneconomical because of the construction cost and construction period. <B> Only the steel sheet pile has the function of propagating the external force such as water pressure to the ground and resisting it. Therefore, changes in various constructions due to design changes due to changes in the situation at the site, etc., have a great impact because they change the type of steel sheet piles that are the main members, change the method of placing steel sheet piles, and the entire construction. .

【0004】[0004]

【発明の目的】本発明は上記したような従来の問題を解
決するためになされたもので、鋼矢板の硬質地盤への打
設にあたり、あらかじめ削孔する箇所を極力少なくし、
工期短縮および施工費を削減することができる仮締切り
工法を提供することを目的とする。このほか、当初の予
定から設計の変更を余儀なくされた場合でも、部材変更
および工期への影響を最小限に抑えると共に、経済的に
変更ができる仮締切り工法を提供することを目的として
いる。本発明は、これらの目的の少なくとも一つを達成
するものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and in setting a steel sheet pile on a hard ground, pre-drilling points are minimized.
It is an object of the present invention to provide a temporary cutoff construction method that can shorten the construction period and the construction cost. In addition, it is an object of the present invention to provide a temporary shut-off method that can be economically changed while minimizing the effect on the change of members and the construction period even if the design has to be changed from the original schedule. The present invention achieves at least one of these objectives.

【0005】[0005]

【課題を解決するための手段】上記のような目的を達成
するために、本発明の仮締切り工法は、目的構造物の外
周部に仮設する仮締切り工法において、複数の親杭を所
定の間隔をおいて前記外周部に打設し、打設した前記親
杭の外周に腹起し材を架渡し、さらに外側に鋼矢板を打
設し、該鋼矢板を前記腹起し材に固設する。
In order to achieve the above object, the temporary cutoff method of the present invention is a temporary cutoff method for temporarily installing the outer periphery of a target structure, in which a plurality of parent piles are arranged at predetermined intervals. Is placed on the outer peripheral portion of the pile, and a reinforced member is bridged over the outer periphery of the driven parent pile, and a steel sheet pile is further driven outside, and the steel sheet pile is fixed to the reinforced member. To do.

【0006】また、本発明の仮締切り工法は、前記に記
載する仮締切り工法において、前記鋼矢板の前面を築堤
して釜場を構築し、該釜場に浸透した貯水を排水するこ
とを特徴としている。
Further, the temporary cutoff method of the present invention is characterized in that, in the temporary cutoff method described above, the front surface of the steel sheet pile is erected to construct a kettle, and the stored water that has permeated into the kettle is drained. I am trying.

【0007】[0007]

【発明の実施の形態】以下図面を参照しながら本発明の
実施の形態について説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings.

【0008】<イ>親杭 親杭1は地盤に打設されて自立し、親杭1に略並行に立
設する鋼矢板4が受ける水圧等を地盤に伝播する部材で
ある。このため、地盤への自立は充分でなければなら
ず、地質および地盤への打込み深度を十分に考慮の上打
設し、土砂の受働土圧により抵抗して、転倒、滑動に対
して安全を図る。そのため、たとえば表層61の下部に
硬質地盤層62が堆積する地盤であれば硬質地盤層62
まで打設して支持する。また親杭脚部の固定はコンクリ
ート等を打設して根固めを行ってもよく、十分に支持が
得られる地盤であれば必ずしも根固めを行う必要はな
い。親杭1の打設方法は、ダウンザホールハンマ工法単
独であっても、また他の方法との併用であってもよく、
特に制約は受けない。
<B> Parent pile The parent pile 1 is a member that is driven into the ground to be self-supporting, and propagates the water pressure or the like received by the steel sheet piles 4 standing substantially parallel to the parent pile 1 to the ground. For this reason, the ground must be self-reliant, and must be installed with due consideration of the geology and the depth of driving into the ground, and resisting the passive earth pressure of earth and sand to ensure safety against falls and sliding. Try. Therefore, for example, in the case of the ground in which the hard ground layer 62 is deposited under the surface layer 61, the hard ground layer 62
Up to support. In addition, the main pile legs may be fixed by pouring concrete or the like to consolidate the soil, and it is not always necessary to consolidate the soil if the ground provides sufficient support. The method for driving the main pile 1 may be the down-the-hole hammer construction method alone, or may be a combination with another method,
There is no particular restriction.

【0009】親杭1は、目的構造物の外周に所定の間隔
をおいて打設され、この間隔は設計によって決定する。
親杭1には、たとえばH鋼杭等を使用することができ
る。この場合、材質・形状はJIS規格に規定されてお
り、幅200〜400mmのもの等を使用することがで
きる。H鋼杭は方向によって断面性能が異なるため、水
平力の作用する方向を考慮して設置する。親杭1には係
留材32を仮締切り工の外側へ向けて張り出すことがで
きる。係留材32は、親杭2に架渡す腹起し材31を載
置して固定する部材である。この係留材32は、架渡す
腹起し材31の段数に応じて取り付ける。
The main piles 1 are laid on the outer periphery of the target structure at a predetermined interval, and this interval is determined by design.
For the parent pile 1, for example, an H steel pile or the like can be used. In this case, the material and shape are specified in JIS standard, and those having a width of 200 to 400 mm can be used. Since the cross-sectional performance of H steel piles differs depending on the direction, install in consideration of the direction in which horizontal force acts. A mooring material 32 can be projected on the main pile 1 toward the outside of the temporary cofferdam. The mooring member 32 is a member for mounting and fixing the uprising member 31 that bridges the main pile 2. The mooring members 32 are attached according to the number of steps of the bridging members 31 to be bridged.

【0010】<ロ>腹起し材 腹起し材31は、水圧等を鋼矢板4が受け、地盤へ親杭
2が伝播する伝達経路の間に介在する部材である。腹起
し材31は、所定の間隔に立設する複数の親杭2の外側
に略直交して配置する。これにより、鋼矢板4が受ける
面圧を腹起し材31を介して親杭2に分散することで、
鋼矢板4の水平変位を小さくすると共に、鋼矢板4のた
わみも防止することができる。腹起し材31の固定は、
親杭2から張り出す係留材32の上に載置して固定す
る。また、さらに外側に打設する鋼矢板4を腹起し材3
1に固定して一体とする。この固定方法は、溶接等によ
って行っても良い。腹起し材31には、たとえばH形鋼
の鋼材を使用することができる。腹起し材31を親杭2
に対して一段で架渡す場合には、鋼矢板4の頭部に近い
箇所に設ける。また、腹起し材31は必要に応じて数段
に設けてもよい。
<B> Uprising material The uprising material 31 is a member interposed between the transmission paths through which the steel pile 4 receives water pressure and the like and the parent pile 2 propagates to the ground. The uprising members 31 are arranged substantially orthogonal to the outside of the plurality of parent piles 2 standing upright at predetermined intervals. As a result, the surface pressure received by the steel sheet pile 4 is dispersed to the parent pile 2 via the reaping member 31,
The horizontal displacement of the steel sheet pile 4 can be reduced and the bending of the steel sheet pile 4 can be prevented. To fix the angry material 31,
It is mounted and fixed on the mooring material 32 which projects from the main pile 2. In addition, a steel sheet pile 4 that is cast further outward is erected by the material 3
It is fixed to 1 and integrated. This fixing method may be performed by welding or the like. A steel material such as an H-shaped steel can be used for the uprising material 31. Upholstering material 31 to parent pile 2
On the other hand, when the steel sheet pile 4 is bridged in one step, the steel sheet pile 4 is provided near the head. Moreover, you may provide the uprising material 31 in several steps as needed.

【0011】<ハ>鋼矢板 鋼矢板4は、目的構造物の周囲に連続して立設し、外部
より働く水圧等の圧力を直接受ける構造材で、その圧力
に耐え得る十分な強度を有すると同時に、本工事内をド
ライな状態に保持する止水機能を有した構造とする。ま
た、場合によって鋼矢板4には静水圧以外に、流水圧、
波圧などの動的な外力を受けることもあり、これらの影
響についても十分考慮した構造でなければならない。な
お、鋼矢板4は、必ずしも目的構造物の外周全体を囲繞
する必要はなく、その一部に岸壁、護岸等を利用しても
良い。鋼矢板4には、U形、直線形、鋼管形等の形状が
あるが使用に応じて選択し、任意の断面性能を有する材
料を使用することができる。鋼矢板4の支持は、上部を
腹起し材31、下部を地盤により行う。鋼矢板4の地盤
への支持により、外部から働く水圧および土圧によって
鋼矢板4が転倒したり滑動するのを防止し、かつ止水で
きればよく、特に地盤に力を伝播しなくてもよい。その
ため、たとえば振動打込み機で打設可能な深度、つまり
打設深度が表層6のみであってもよく、硬質地盤層62
まで打込む必要はない。また、鋼矢板4の相互間におい
ても止水構造を備える必要がある。このため、たとえば
鋼矢板4継手の係合部分の遊隙内には、鋼矢板4の膨潤
止水材や止水ゴム等の弾性材を充填して止水することも
できる。
<C> Steel sheet pile The steel sheet pile 4 is a structural member that is continuously erected around the target structure and directly receives pressure such as water pressure from the outside and has sufficient strength to withstand the pressure. At the same time, a structure with a water stop function to keep the inside of the construction dry is provided. In addition to the hydrostatic pressure, the steel sheet pile 4 may have a flowing water pressure,
Since it may be subject to dynamic external forces such as wave pressure, the structure must be designed with due consideration to these effects. Note that the steel sheet pile 4 does not necessarily need to surround the entire outer periphery of the target structure, and a part of the steel sheet pile 4 may use a quay wall, a sea wall, or the like. The steel sheet pile 4 has a U shape, a linear shape, a steel pipe shape, or the like, but a material having an arbitrary cross-sectional performance can be selected depending on the use. The steel sheet pile 4 is supported by the uprising member 31 on the upper side and the ground on the lower side. By supporting the steel sheet pile 4 on the ground, it is sufficient that the steel sheet pile 4 can be prevented from tipping or sliding due to water pressure and earth pressure acting from the outside, and the water can be stopped, and in particular, the force need not be transmitted to the ground. Therefore, for example, the depth at which the vibration driving machine can be driven, that is, the driving depth may be only the surface layer 6, and the hard ground layer 62.
You don't have to type until. In addition, it is necessary to provide a water blocking structure between the steel sheet piles 4. Therefore, for example, an elastic material such as a swelling water blocking material or a water blocking rubber of the steel sheet pile 4 can be filled in the play of the engaging portion of the steel sheet pile 4 joint to stop water.

【0012】<ニ>釜場 釜場5は、掘削した井筒内の底部である鋼矢板4の前面
に築堤し、その間に溝を掘削して構築する(図1参
照)。釜場5は、鋼矢板4の近傍に構築し、これは特に
浸透流動、流速が大であり、また浸透水を掘削内部に流
入するのを未然に防止するためである。これは、鋼矢板
4に略並行に構築し、かならずしも全周に構築する必要
はない。また、釜場5は木矢板壁などで保護してもよ
い。釜場5から通じる集水場所を別途、掘削底面から深
い場所に構築してもよい。これは、浸透してきた水を釜
場5を介して集水場所へ自然流入で導き、そこから水中
ポンプあるいはヒューガルポンプなどにより外部へ排水
するためである。排出に使用するポンプとしては、集水
場所の大きさと地盤の透水によっても異なるが、たとえ
ば一般的に持ち運びの容易な吐水出口径2インチの水中
ポンプを使用してもよい。
<D> Kamaba Kamaba 5 is constructed by constructing a dike in front of the steel sheet pile 4, which is the bottom of the excavated well, and excavating a groove therebetween (see FIG. 1). The kettle 5 is constructed in the vicinity of the steel sheet pile 4, because the permeation flow and the flow velocity are particularly large, and the permeated water is prevented from flowing into the excavation interior. This is constructed substantially parallel to the steel sheet pile 4, and does not necessarily have to be constructed on the entire circumference. Further, the kettle 5 may be protected by a wood sheet pile wall or the like. A water collection place leading from the kettle 5 may be separately constructed at a deep place from the bottom of the excavation. This is because the permeated water is naturally guided to the water collecting place via the cauldron 5 and then discharged to the outside by a submersible pump or a fugal pump. The pump used for discharging may vary depending on the size of the water collecting place and the water permeability of the ground, but for example, a submersible pump having a discharge outlet diameter of 2 inches which is generally easy to carry may be used.

【0013】<ホ>その他 一般に鋼矢板4の打ち込みに際し、鋼矢板4を正しく計
画線上に打ち込むためと、施工時の安定性をはかるため
に、導材と導杭からなる導枠を設けてこれを鋼管ケーシ
ング打設時のガイドとすることができる(図示せず)。
導杭は親杭2に対して略並行に打設し、導材は導杭に架
渡して構築する。打込み始めには楔等を設けて鋼矢板4
をさらに固定することもできる。なお、この導枠は、打
込みの終わったところから順次取り外し、繰り返し使用
してもよい。
<E> Other In general, when driving the steel sheet pile 4, in order to drive the steel sheet pile 4 correctly on the planned line and to ensure stability during construction, a guide frame made of a conductive material and a conductive pile is provided. Can be used as a guide when placing the steel pipe casing (not shown).
The guide pile is laid substantially parallel to the main pile 2, and the conductive material is built on the guide pile. A steel sheet pile 4 is provided with a wedge etc. at the beginning of driving.
Can be further fixed. The guide frame may be sequentially removed from the place where the driving is finished and used repeatedly.

【0014】この他、仮締切り工の内部の掘削と共に掘
削内部の対峙する親杭2に切ばりを仮設して、周囲から
の水圧を支持することもできる(図示せず)。また、仮
締切り工の隅部には火打ち材を設けてもよく、切ばりが
長い場合には中間杭を設けて、切ばりを固定するともに
切ばりの座屈を防止することもできる。
In addition to this, along with excavation inside the temporary cut-off work, it is also possible to temporarily install a cut-off on the facing main pile 2 inside the excavation to support water pressure from the surroundings (not shown). In addition, a fire striking material may be provided at the corner of the temporary cut-off work, and if the cutting is long, an intermediate pile may be provided to fix the cutting and prevent buckling of the cutting.

【0015】[0015]

【実施例】以下図面を参照しながら、本発明の仮締切り
工法の実施例について説明する。なお、この実施例は水
中での仮締切り工法について説明するが、土留めによる
仮締切り工法やまた本工事として利用することもでき
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT An embodiment of the temporary cut-off method of the present invention will be described below with reference to the drawings. It should be noted that although this embodiment describes a temporary closing method in water, it can also be used as a temporary closing method using earth retaining or as the main work.

【0016】<イ>親杭の打設準備(図1参照) 水上もしくは水際線近くで鋼矢板4を打ち込むのに際
し、陸打ちか船打ちかまたは足場打ち等を決定して、く
い打ち機および各種作業船の手配を行う。次に、河川内
に導杭を打設する(図示せず)。導杭の貫入深度は、振
動打込み機を用いて貫入できる深度までで良い。打設し
た導杭に導材を架渡し、仮固定して導枠を設置する。
<A> Preparation for driving the main pile (see FIG. 1) When driving the steel sheet pile 4 on the water or near the waterfront, it is decided whether to land, ship, or scaffold, and Arrange for various work vessels. Next, guide piles are set in the river (not shown). The penetration depth of the guide pile may be a depth that can be penetrated using a vibration driving machine. The guide material is laid over the driven piles that have been placed, and the guide frame is installed by temporarily fixing it.

【0017】<ロ>親杭の打設 前記工程で仮設した導枠の間隙に鋼管ケーシングを打設
する。鋼管ケーシングの打設は、地盤の硬度によって打
込みの工法を使い分けて打設しても良い。たとえば、地
盤の断層が軟弱地盤の表層61とその下方に堆積する硬
質地盤層62とからなる場合、表層61部分への打設は
振動打込み機によって行い、硬質地盤層62に対しては
ダウンザホールハンマ工法等で打設してもよい。このと
き鋼管ケーシングの打込み、削孔に伴い掘削土の細粒分
がベントナイト泥水と縣濁して孔底に発生するスライム
を除去する。孔底の深度を確認した後、プランジャー等
を使用して生コンを打設する。鋼管ケーシング引き抜き
後、親杭2をクレーン等によって運搬して親杭2を建て
込む。なお、親杭2の地盤への支持構造は現場や地盤等
の諸条件に応じて、かならずしも根固めをする必要はな
い。
<B> Placing the main pile A steel pipe casing is placed in the space between the guide frames temporarily provided in the above step. The steel pipe casing may be driven by using the driving method depending on the hardness of the ground. For example, when the ground fault is composed of the surface layer 61 of soft ground and the hard ground layer 62 deposited thereunder, the driving to the surface layer 61 part is performed by a vibration driving machine, and the down ground hole hammer is applied to the hard ground layer 62. It may be placed by a construction method or the like. At this time, fine particles of excavated soil are suspended with bentonite muddy water due to the driving and drilling of the steel pipe casing, and the slime generated at the bottom of the hole is removed. After checking the depth of the bottom of the hole, use a plunger or the like to place fresh concrete. After pulling out the steel pipe casing, the parent pile 2 is transported by a crane or the like to build the parent pile 2. The support structure of the main pile 2 on the ground does not always need to be consolidated according to various conditions such as the site and the ground.

【0018】<ハ>腹起し材の固定 所定の位置に建て込んだ親杭2から係留材32を張り出
す。係留材32は親杭2の運搬時や建て込み時に支障が
なければ、先に取り付けてもよい。係留材32は打設す
る親杭2の外側側面に取り付ける。腹起し材31を係留
材32の上部に載置し、係留材32に固定する。
<C> Fixing of the upholstery member The mooring member 32 is extended from the main pile 2 built in the predetermined position. The mooring member 32 may be attached first if there is no hindrance during transportation or installation of the main pile 2. The mooring member 32 is attached to the outer side surface of the main pile 2 to be laid. The uprising member 31 is placed on the upper part of the mooring member 32 and fixed to the mooring member 32.

【0019】<ニ>鋼矢板の打設 親杭2側面の外側に腹起し材31を架渡した後、地盤に
鋼矢板4を順次打設する(図2参照)。この打設には、
たとえば振動打込み機等を用いて打設することができ、
打設深度は鋼矢板4が転倒、滑動しなければよく、たと
えば表層61部分までの深度であってもよい。また、仮
締切り工には必要に応じて内部に、火打ち材、切ばりを
設けても良い。鋼矢板4の打込み後、該鋼矢板4継手の
係合部分の遊隙内を充填して止水を行う。鋼矢板4の上
部は、腹起し材31に固定する。
<D> Placing of Steel Sheet Pile After laying up the upholstery material 31 on the outside of the side surface of the main pile 2, steel sheet pile 4 is sequentially laid in the ground (see FIG. 2). For this placement,
For example, it can be set using a vibration driving machine,
The driving depth may be such that the steel sheet pile 4 does not fall or slide, and may be the depth up to the surface layer 61, for example. Further, the temporary shut-off work may be provided with a fired material or a burial inside if necessary. After the steel sheet pile 4 is driven in, water is stopped by filling the play space of the engaging portion of the steel sheet pile 4 joint. The upper part of the steel sheet pile 4 is fixed to the uprising member 31.

【0020】<ホ>井筒内の掘削 目的構造物の外周部1に仮設した仮締切り工の井筒内部
を適当な方法で排水し、必要に応じて切ばりを仮設す
る。切ばりを仮設する場合には、あらかじめ親杭2の内
側面にブラケットを間隔をおいて配置しておく。そして
前記排水によって順次水面が下降するが、この下降によ
り水面上に出現する対向したブラケットに、夫々切ばり
を架設する。また、必要に応じて火打ち材、中間杭を設
けても良い。井筒内部を全部排水した後、掘削底部の鋼
矢板4前面には必要に応じて釜場5を築堤する(図1参
照)。これは、鋼矢板4の下部から浸入する恐れのある
浸透水の流入を留めるためである。而して、仮締切り工
内部をドライワークに保ち、目的構造物の構築が行われ
る。
<E> Excavation inside the well The inside of the well which is temporarily installed on the outer peripheral portion 1 of the structure to be excavated is drained by an appropriate method, and a cut beam is temporarily installed if necessary. In the case of temporarily installing the cut-outs, the brackets are arranged on the inner surface of the main pile 2 at intervals. Then, the water surface sequentially descends due to the drainage, and each of the facing brackets that appears on the water surface due to this drainage is provided with a cutting beam. Moreover, you may install a fired material and an intermediate pile as needed. After draining the inside of the well, the embankment 5 is constructed on the front side of the steel sheet pile 4 at the bottom of the excavation, if necessary (see FIG. 1). This is to stop the inflow of permeated water that may enter from the lower part of the steel sheet pile 4. Thus, the inside of the temporary cut-off work is maintained as a dry work, and the target structure is constructed.

【0021】[0021]

【発明の効果】本発明の仮締切り工法は以上説明したよ
うになるから次のような効果を得ることができる。 <イ>本発明の構造は、水圧等は親杭で受け、止水は鋼
矢板で行う。このため、硬質地盤への削孔箇所は親杭の
打設箇所のみで良いため、施工費の軽減および工期の短
縮に繋がり非常に経済的である。さらに、水圧等に対す
る抵抗を主に親杭にたよる工法であるため、鋼矢板に対
しては水圧等を地盤へ伝播する剛性、および地盤の変形
による剛性等を考慮する必要がなく、鋼矢板の断面性能
を従来より低く設定することができ、経済的である。 <ロ>また、水圧等の水平力を受ける働きと支持地盤に
力を伝達する働きは、夫々異なる部材により構成されて
いる。この為、設計変更を余儀なくされる場合でも全体
に及ぶことなく一部の変更のみで済むため損失が少な
い。
Since the temporary shutoff method of the present invention is as described above, the following effects can be obtained. <A> In the structure of the present invention, the main pile receives water pressure and the like, and the steel sheet pile is used to stop water. For this reason, since only the place where the parent pile is to be drilled is required for drilling the hard ground, the construction cost is reduced and the construction period is shortened, which is very economical. Furthermore, since it is a construction method that mainly relies on the main piles for resistance to water pressure, there is no need to consider the rigidity of propagating water pressure, etc. to the ground and the rigidity due to ground deformation for steel sheet piles. It is economical because the cross-sectional performance of can be set lower than before. <B> Further, the function of receiving a horizontal force such as water pressure and the function of transmitting the force to the supporting ground are constituted by different members. Therefore, even if a design change is forced, only a part of the change does not have to be applied to the whole, and thus the loss is small.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の仮締切り工法の概略説明図。FIG. 1 is a schematic explanatory view of a temporary cutoff method according to the present invention.

【図2】本発明の仮締切り工法の斜視図。FIG. 2 is a perspective view of a temporary cutoff method according to the present invention.

【図3】本発明の仮締切り工法の平面説明図。FIG. 3 is an explanatory plan view of a temporary cutoff method according to the present invention.

【図4】従来の仮締切り工法の平面説明図。FIG. 4 is an explanatory plan view of a conventional temporary cutoff method.

【符号の説明】[Explanation of symbols]

1・・・外周部 2・・・親杭 31・・腹起し材 4・・・鋼矢板 51・・釜場 1 ... Outer peripheral part 2 ... Parent pile 31 .. Uprising material 4 ... Steel sheet pile 51 ... Kamaba

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】目的構造物の外周部に仮設する仮締切り工
法において、 複数の親杭を所定の間隔をおいて前記外周部に打設し、 打設した前記親杭の外周に腹起し材を架渡し、 さらに外側に鋼矢板を打設し、該鋼矢板を前記腹起し材
に固設したことを特徴とする、 仮締切り工法。
1. A temporary cut-off method for temporarily installing an outer periphery of a target structure, wherein a plurality of parent piles are driven at the outer periphery at a predetermined interval, and the piled up parent piles are angulated. A temporary cut-off construction method, characterized in that a material is bridged, a steel sheet pile is further cast on the outer side, and the steel sheet pile is fixedly mounted on the waving material.
【請求項2】請求項1に記載する仮締切り工法におい
て、 前記鋼矢板の前面を築堤して釜場を構築し、該釜場に浸
透した貯水を排水することを特徴とする、 仮締切り工法。
2. The temporary cutoff method according to claim 1, wherein a front wall of the steel sheet pile is erected to construct a kettle, and water stored in the kettle is drained. .
JP2002005230A 2002-01-11 2002-01-11 Temporary closing method Expired - Fee Related JP3979466B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002005230A JP3979466B2 (en) 2002-01-11 2002-01-11 Temporary closing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002005230A JP3979466B2 (en) 2002-01-11 2002-01-11 Temporary closing method

Publications (2)

Publication Number Publication Date
JP2003206539A true JP2003206539A (en) 2003-07-25
JP3979466B2 JP3979466B2 (en) 2007-09-19

Family

ID=27644333

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002005230A Expired - Fee Related JP3979466B2 (en) 2002-01-11 2002-01-11 Temporary closing method

Country Status (1)

Country Link
JP (1) JP3979466B2 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006322155A (en) * 2005-05-17 2006-11-30 Takenaka Komuten Co Ltd Soldier pile lagging method capable of processing subsoil water or the like
JP2008208680A (en) * 2007-02-28 2008-09-11 Tokyo Electric Power Co Inc:The Method of constructing underwater steel pipe
CN100489200C (en) * 2006-05-19 2009-05-20 中船第九设计研究院 Large-diameter circular steel-plate cofferdam and its construction method
KR100923078B1 (en) * 2007-10-11 2009-11-02 현대건설주식회사 Cofferdam Construction Method using Sheet File and Wale and Construction Method For Underwater Structure using the Cofferdam
CN101914919A (en) * 2010-07-30 2010-12-15 中铁四局集团第六工程有限公司 Combined cofferdam under complex geological condition and construction method thereof
JP2014015809A (en) * 2012-07-11 2014-01-30 Okumura Corp Cut-off of water for joint part of steel sheet pile, and outflow prevention hardware
CN104947698A (en) * 2015-07-09 2015-09-30 中国水利水电第七工程局有限公司 Construction method for steel sheet pile cofferdam on underwater exposed bedrock
CN107700504A (en) * 2017-09-27 2018-02-16 中铁二十局集团第工程有限公司 Based on the slope rock river bed steel cofferdam for vacantly hanging pin processing structure
CN108612117A (en) * 2018-06-07 2018-10-02 深圳市市政设计研究院有限公司 A kind of seabed water-retaining structure across municipal tunnel greatly and construction method
CN110042864A (en) * 2019-05-14 2019-07-23 北京首尔工程技术有限公司 The comprehensive water sealing structure and its construction method of artesian water stratum tunneling underground station
CN110359476A (en) * 2019-07-04 2019-10-22 中铁七局集团有限公司 A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN110805046A (en) * 2019-11-18 2020-02-18 中国二十冶集团有限公司 Foundation pit support steel sheet pile driving and arranging support structure and foundation pit support steel sheet pile driving and arranging method
CN113756345A (en) * 2021-09-25 2021-12-07 聊城市交通发展有限公司 Construction method of underwater bridge foundation

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109837966B (en) * 2019-03-06 2020-10-30 中国十七冶集团有限公司 Structure for treating lateral wall waterproof curtain of foundation pit on main channel side slope by replacement and filling method and construction method
CN111350201A (en) * 2020-03-18 2020-06-30 中交第二航务工程局有限公司 Construction method of steel sheet pile cofferdam of deep-water low-pile cap of thick pebble bed riverbed

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006322155A (en) * 2005-05-17 2006-11-30 Takenaka Komuten Co Ltd Soldier pile lagging method capable of processing subsoil water or the like
JP4532337B2 (en) * 2005-05-17 2010-08-25 株式会社竹中工務店 Propile pile sheet pile method capable of treating underground water
CN100489200C (en) * 2006-05-19 2009-05-20 中船第九设计研究院 Large-diameter circular steel-plate cofferdam and its construction method
JP2008208680A (en) * 2007-02-28 2008-09-11 Tokyo Electric Power Co Inc:The Method of constructing underwater steel pipe
KR100923078B1 (en) * 2007-10-11 2009-11-02 현대건설주식회사 Cofferdam Construction Method using Sheet File and Wale and Construction Method For Underwater Structure using the Cofferdam
CN101914919A (en) * 2010-07-30 2010-12-15 中铁四局集团第六工程有限公司 Combined cofferdam under complex geological condition and construction method thereof
JP2014015809A (en) * 2012-07-11 2014-01-30 Okumura Corp Cut-off of water for joint part of steel sheet pile, and outflow prevention hardware
CN104947698A (en) * 2015-07-09 2015-09-30 中国水利水电第七工程局有限公司 Construction method for steel sheet pile cofferdam on underwater exposed bedrock
CN107700504A (en) * 2017-09-27 2018-02-16 中铁二十局集团第工程有限公司 Based on the slope rock river bed steel cofferdam for vacantly hanging pin processing structure
CN108612117A (en) * 2018-06-07 2018-10-02 深圳市市政设计研究院有限公司 A kind of seabed water-retaining structure across municipal tunnel greatly and construction method
CN110042864A (en) * 2019-05-14 2019-07-23 北京首尔工程技术有限公司 The comprehensive water sealing structure and its construction method of artesian water stratum tunneling underground station
CN110359476A (en) * 2019-07-04 2019-10-22 中铁七局集团有限公司 A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN110805046A (en) * 2019-11-18 2020-02-18 中国二十冶集团有限公司 Foundation pit support steel sheet pile driving and arranging support structure and foundation pit support steel sheet pile driving and arranging method
CN113756345A (en) * 2021-09-25 2021-12-07 聊城市交通发展有限公司 Construction method of underwater bridge foundation

Also Published As

Publication number Publication date
JP3979466B2 (en) 2007-09-19

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
JP2003206539A (en) Temporary closing construction method
CN105714833A (en) Construction method of steel plate pile open caisson support
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
CN109339079A (en) A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum
JP3603193B2 (en) How to build an underwater foundation
JP5572540B2 (en) Temporary deadline structure of the final deadline in the impermeable wall and its deadline method
JPH06146305A (en) Underwater foundation and installation method thereof
CN209260739U (en) A kind of foundation pit water-stopping system close to river permeable stratum
JP3967473B2 (en) Construction method of underground structure
CN107012792B (en) A kind of construction method of bridge substructure
CN113882431B (en) Construction method for dismantling cofferdam at end head
JP2018044337A (en) Structure and method for reinforcing embankment
KR102237058B1 (en) Construction method of synthetic piles for water barriers in rock layers
KR101649210B1 (en) Steel pipe wall temporary construction
JP2809105B2 (en) How to build an underground tank
JP2008184889A (en) Caisson construction method combined with guide hole method for constructing underground structure
JP2874906B2 (en) Shaft construction method
JP2011043047A (en) Improved/reinforced structure of existing gravity type quay
JP5468052B2 (en) Gravity structure deepening method and gravity structure
JP3877816B2 (en) Pneumatic caisson settlement method
JP2003074076A (en) Construction method of building having underground part
JP3430376B2 (en) How to build an underground skeleton
JP2000136539A (en) Ground excavating method
JP4670625B2 (en) Reinforcement method of existing gravity quay

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041214

A977 Report on retrieval

Effective date: 20061115

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20061205

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070105

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20070612

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070619

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100706

Year of fee payment: 3

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20110706

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20110706

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 5

Free format text: PAYMENT UNTIL: 20120706

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 6

Free format text: PAYMENT UNTIL: 20130706

LAPS Cancellation because of no payment of annual fees