JP5572540B2 - Temporary deadline structure of the final deadline in the impermeable wall and its deadline method - Google Patents

Temporary deadline structure of the final deadline in the impermeable wall and its deadline method Download PDF

Info

Publication number
JP5572540B2
JP5572540B2 JP2010289838A JP2010289838A JP5572540B2 JP 5572540 B2 JP5572540 B2 JP 5572540B2 JP 2010289838 A JP2010289838 A JP 2010289838A JP 2010289838 A JP2010289838 A JP 2010289838A JP 5572540 B2 JP5572540 B2 JP 5572540B2
Authority
JP
Japan
Prior art keywords
water
wall
final
sheet pile
impermeable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010289838A
Other languages
Japanese (ja)
Other versions
JP2011089392A (en
Inventor
博信 福山
道生 田崎
亮行 鵜飼
隆太郎 園田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Development Co Ltd
Penta Ocean Construction Co Ltd
Original Assignee
Electric Power Development Co Ltd
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Development Co Ltd, Penta Ocean Construction Co Ltd filed Critical Electric Power Development Co Ltd
Priority to JP2010289838A priority Critical patent/JP5572540B2/en
Publication of JP2011089392A publication Critical patent/JP2011089392A/en
Application granted granted Critical
Publication of JP5572540B2 publication Critical patent/JP5572540B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

本発明は、海面廃棄物処分場などであって、海や河川に漏出しないように措置しなければならない廃棄物や保有水(以下、これらを保有水等という)を締め切る遮水壁における最終締切部の仮締切構造と、その締切方法に関するものである。   The present invention is a sea surface waste disposal site and the like, and the final deadline at the impermeable wall that cuts off waste and retained water (hereinafter referred to as retained water) that must be taken so as not to leak into the sea or river. The provisional deadline structure of the part and the deadline method.

従来、大規模となることが多い海面廃棄物処分場において、廃棄物の埋立場所となる処分場内の空間は、外海と処分場内水面とを鋼矢板等での遮水工を有する遮水護岸によって、その境界を締め切ることにより構築される。前記保有水等用遮水工の建設時においては、前記遮水工に開口部を設けることで、該開口部の通水により内外水位を同じにし、潮汐による内外水位差を生じさせないことで、施工中の遮水工に水圧を作用させず、作業の安全性,施工性,品質を確保している。   Conventionally, in sea surface waste disposal sites, which are often large-scale, the space in the disposal site that serves as a landfill site for waste is separated by a water-impervious revetment that has a water-impervious structure such as steel sheet piles between the open sea and the water surface in the disposal site Built by closing its boundaries. At the time of construction of the impervious work for retained water, etc., by providing an opening in the impervious work, making the water level inside and outside the same by passing water through the opening, and not causing a difference in water level between inside and outside due to tides, Water safety is not applied to the impervious work under construction, ensuring work safety, workability and quality.

前記保有水等における遮水鋼矢板による遮水工の締切作業は、前記保有水等が外部に流出しないように、図7(A)に示すように、クローラクレーン10等で鋼矢板1aを台船等から揚重してワイヤーで吊り下げ、図7(A)に示すように、既設の鋼矢板1aに隣接させて高い遮水性を確保しながら、前記鋼矢板1aをバイブロハンマー等で順次不透水層の海底に打設して遮水壁を構築しなければならない。   As shown in FIG. 7 (A), the shut-off work of the impervious construction with the water-impervious steel sheet pile in the retained water is performed by mounting the steel sheet pile 1a with a crawler crane 10 or the like as shown in FIG. As shown in FIG. 7 (A), the steel sheet pile 1a is lifted from a ship or the like and suspended by a wire hammer, etc. while being adjacent to the existing steel sheet pile 1a to ensure high water shielding. Impermeable walls must be constructed by placing them on the bottom of the permeable layer.

このような遮水護岸における開口部の締切においては、従来例1として、開口部に鋼管製の門柱を所定間隔に打設し、各門柱間にフラップゲートを海底に沈めて寝かせ、小潮期間の干潮時に前記フラップゲートを起立させて、開口部の閉塞を行うようにしたもの(特許文献1参照)や、従来例2として、締切箇所にシートセルを係止して位置決めするための支持杭を、その上端面を水面上に突出延長させた状態で打設し、シートセルを吊り上げて支持杭の上方から当該支持杭を内部に挿通させるようにして締切箇所に設置した後に、前記シートセルの内部に中詰用の土砂を投入充填して中詰めセルを形成し、この中詰めセルを締切箇所に沿って連接することで締切箇所を締め切る方法(特許文献2参照)が知られている。   In the deadline of the opening in such a water-impounded revetment, as a conventional example 1, steel pipe gate pillars are placed at predetermined intervals in the openings, and the flap gates are sunk on the sea floor between the gate pillars. A support pile for locking and positioning the sheet cell at the cut-off location as one in which the flap gate is erected at low tide and the opening is closed (see Patent Document 1) or as a conventional example 2. The upper end surface of the sheet cell is placed in a projecting and extended state, and the seat cell is lifted and inserted into the support pile from above the support pile. There is known a method (see Patent Document 2) in which a filling cell is formed by filling and filling the inside with a filling cell to form a filling cell and connecting the filling cell along the cutting point.

特開平06−49821号公報Japanese Patent Laid-Open No. 06-49821 特開平11−222850号公報Japanese Patent Laid-Open No. 11-222850

しかし、上記従来例1,2の保有水等の締切方法においては、水位の深い箇所で更に大規模な保有水等には適用することが困難であり、シートセルに土砂等を中詰めする作業は開口部の流速が速くなると作業性が低下する。   However, it is difficult to apply to the retained water etc. in the deep water level in the deadline method of the retained water etc. of the conventional examples 1 and 2 above, and the work of filling the sheet cell with earth and sand etc. As the flow rate at the opening increases, workability decreases.

このように、遮水壁の開口部の幅が縮小するにつれ、潮位の変動に伴う内外潮位差及び速い開口部流速の発生により、固定が不十分な打設中の矢板に流体力が作用して、想定外の挙動が生じて事故が発生することが懸念される。   In this way, as the width of the opening of the impermeable wall decreases, fluid force acts on the sheet pile that is not fixed enough due to the difference between the inner and outer tide levels accompanying the fluctuation of the tide level and the rapid flow velocity of the opening. Therefore, there is concern that accidents may occur due to unexpected behavior.

また、捨石の移動が生じるくらいに流速が速くなると、基礎捨石の崩落につながり、安全性が低下する。更に、打設中の矢板が不安定になって施工性が低下し、流体力に耐えることができるよう仮設工を増強する必要があると、作業手間が増し、作業性が低下する。   Moreover, if the flow velocity becomes fast enough to cause movement of the rubble, it will lead to the collapse of the basic rubble, which will reduce the safety. Furthermore, if the sheet pile being placed becomes unstable and the workability is lowered, and it is necessary to increase the temporary work so as to be able to withstand the fluid force, the labor is increased and the workability is lowered.

また、鋼矢板の継手部においても、遮水材に流体力によって変形や流出など正常な状態が保持できない可能性があり品質の低下につながる。そのほか、開口部の流速が速くならないように潮止まりの限られた時間内に作業しなければならず、最終締切作業が困難となることがある。本発明に係る遮水壁における最終締切部の仮締切構造とその締切方法は、このような課題を解決するために提案されたものである。   Further, even in the joint portion of the steel sheet pile, there is a possibility that a normal state such as deformation or outflow may not be maintained due to fluid force on the water shielding material, leading to deterioration in quality. In addition, it is necessary to work within a limited time of the tide so that the flow velocity of the opening does not increase, and the final closing work may be difficult. The temporary closing structure and the closing method of the final closing part in the impermeable wall according to the present invention have been proposed in order to solve such problems.

本発明に係る遮水壁における最終締切部の仮締切構造の上記課題を解決して目的を達成するための要旨は、廃棄物又は保有水を外海から遮水する遮水壁を遮水矢板で構築する際の、該遮水壁における最終締切部の仮締切構造であって、前記最終締切部の外側に、前記遮水壁に直交する対向配置の短辺壁と前記遮水壁に平行な長辺壁とでなる平面視略コ字形の仮遮水壁を構築し、前記対向配置の短辺壁に、水が出入りできる通水部が設けられ、前記通水部の通水面積が調節可能にしてあることである。   The gist for achieving the object by solving the above-described problem of the temporary closing structure of the final closing portion in the water blocking wall according to the present invention is to use a water blocking sheet pile for the water blocking wall for blocking waste or retained water from the outside sea. A temporary cutoff structure of the final cutoff portion in the water-blocking wall at the time of construction, which is parallel to the water-blocking wall and the short side wall opposed to the water-blocking wall on the outside of the final cutoff portion. A temporary water-impervious wall having a substantially U-shape in plan view composed of a long side wall is constructed, and a water passing part through which water can enter and exit is provided on the opposed short side wall, and the water passing area of the water passing part is adjusted. It is possible.

また、前記通水部の通水面積の調節は、通水部の縦方向の長さに合わせた通水面積調節用の矢板である雇い杭を打設したり、通水部に打設した雇い杭を引き抜いたりして、調節されるものであることであり、;
また、前記通水部は、櫛の歯状に打設された矢板にによって形成されていることを含むものである。
In addition, the adjustment of the water flow area of the water flow section was performed by placing a hiring pile that is a sheet pile for adjusting the water flow area according to the length of the water flow section in the vertical direction, or driving the water flow section. Pulling out hired stakes and adjusting it;
Moreover, the said water flow part contains that it is formed by the sheet pile laid in the comb-tooth shape.

本発明に係る遮水壁における最終締切部の締切方法の上記課題を解決して目的を達成するための要旨は、廃棄物又は保有水を外海から遮水する遮水壁を遮水矢板で構築する際の、前記遮水壁の最終締切部を締切する方法において、前記遮水壁の最終締切部の外側に、該最終締切部に直交する対向配置で通水部を有する短辺壁を構築し、次に、前記遮水壁の最終締切部に平行な長辺壁を構築することで平面視略コ字形の仮遮水壁を構築し、前記短辺壁における一方の通水部を閉塞させ、その後、前記短辺壁における他方の通水部を適宜な潮位の時に閉塞させ、前記遮水壁の最終締切部を矢板を打設して閉塞し、その後、前記仮遮水壁を撤去することである。   The gist for achieving the object by solving the above-described problem of the method for closing the final deadline in the water-impervious wall according to the present invention is to construct a water-impervious wall that shields waste or retained water from the open sea with a water-impregnated sheet pile. In the method of closing the final cut-off portion of the water-impervious wall, a short side wall having a water-permeable portion is arranged outside the final cut-off portion of the water-impervious wall and opposed to the final cut-off portion. Next, by constructing a long side wall parallel to the final cut-off portion of the water shielding wall, a temporary water shielding wall having a substantially U shape in plan view is constructed, and one water passage portion in the short side wall is closed. After that, the other water flow portion in the short side wall is closed at an appropriate tide level, the final cut-off portion of the water shielding wall is closed by placing a sheet pile, and then the temporary water shielding wall is removed. It is to be.

前記通水部は、櫛の歯状に打設された矢板によって形成されていることであり、;
更に、前記通水部を閉塞するには、通水部における櫛の歯状開口部の縦方向の長さに合わせた通水面積調節用の矢板である雇い杭を前記櫛の歯状の開口部に打設して閉塞すること、若しくは、雇い杭の下部を櫛の歯状の開口部で水面下に沈んでいる矢板上部に連結して当該矢板を前記雇い杭を介して水面上に引き上げて閉塞することを含むものである。
The water flow portion is formed by a sheet pile placed in the shape of a comb tooth;
Furthermore, in order to close the water flow portion, a hiring pile, which is a sheet pile for adjusting the water flow area in accordance with the length of the comb tooth opening in the water flow portion, is used as the comb tooth opening. Or by closing the lower part of the hiring pile to the upper part of the sheet pile sinking under the water surface with a comb-shaped opening and pulling the sheet pile up to the water surface via the hiring pile. Obstruction.

本発明の遮水壁における最終締切部の仮締切構造とその締切方法によれば、仮遮水壁を設けることで潮汐による内外水位差や開口部流速の発生の影響を受けることなく、本設の遮水壁における最終締切部の締切作業を行うことができる。前記最終締切部の品質を、廃棄物処分場等の保有水等の規模や潮汐の大きさに関係なく、確保することができる。
仮遮水壁の通水部を、コ字形又は略コ字形の短辺部に設けたので、流速の発生方向が本設の遮水壁の法線と平行になり、隅角部もあることから発生流速に対する仮設遮水用の矢板の安定性を高めることができる。前記仮遮水壁の通水部を、対向する短辺壁の2カ所に設けたので、1カ所あたりの開口部の大きさを小規模にすることができ、仮締切作業を容易にすることができる。
前記仮遮水壁の通水部を矢板によって櫛の歯状に形成するので、開口部の流速が非常に速くなる最後の数枚の遮水矢板の締切作業においても、発生流速の影響を受け難く、作業を行うことができる。
仮遮水壁の通水部を、仮設の遮水用矢板と同型の雇い杭を用いることで、仮設の遮水用矢板を一般部の矢板と同様な所定深さにする打設で、通水部を容易に確保することができる。更に、前記仮遮水壁の通水部を、櫛の歯状に設けることができて、発生流速に影響されにくくして仮締切を短時間で施工できる。また、前記開口部を締め切るタイミングに余裕ができて、保有水等の内水位を管理水位となるように確認しながら、閉塞することができるなど、数々の優れた効果を奏するものである。
According to the temporary closing structure and the closing method of the final cutoff portion of the impermeable wall according to the present invention, the provisional impermeable wall can be installed without being affected by the difference in internal and external water levels due to tides and the occurrence of the flow velocity of the opening. It is possible to perform the final cut-off work of the final cut-off portion in the water-impervious wall. The quality of the final deadline can be ensured regardless of the scale of the retained water and the tide of the waste disposal site.
Since the water-permeable part of the temporary impermeable wall is provided on the short side of the U-shaped or substantially U-shaped, the direction of the flow velocity is parallel to the normal line of the main impermeable wall, and there is also a corner. Therefore, the stability of the sheet pile for temporary water shielding against the generated flow velocity can be increased. Since the water-permeable portion of the temporary impermeable wall is provided at two locations on the opposing short side wall, the size of the opening per location can be made small, and the temporary closing work is facilitated. Can do.
Since the water flow portion of the temporary impermeable wall is formed in a comb-like shape by a sheet pile, the final few sheets of the water shield sheet pile whose flow velocity at the opening becomes very fast is also affected by the generated flow velocity. It is difficult and work can be done.
By using the hiring pile of the same type as the temporary water-impervious sheet pile, the temporary water-impervious wall's water-passing part is driven to a predetermined depth similar to that of the general part. The water part can be easily secured. Further, the water-permeable portion of the temporary impermeable wall can be provided in a comb-like shape, so that it is difficult to be affected by the generated flow velocity, and the temporary closing can be performed in a short time. In addition, there are many excellent effects such as a margin for closing the opening and the ability to block the water while confirming that the internal water level of retained water is the control water level.

本発明に係る遮水壁における最終締切部の仮締切構造の概略を示す斜視図である。It is a perspective view which shows the outline of the temporary cutoff structure of the final cutoff part in the impermeable wall which concerns on this invention. 本発明に係る遮水壁における最終締切部の仮締切構造において、短辺壁に設けた通水部を櫛の歯状にする様子を示す斜視図(A)と、片側の短辺壁の通水部を閉塞して、他方の櫛の歯状通水部を閉塞していく様子を示す斜視図(B)とである。In the temporary cutoff structure of the final cutoff part in the impermeable wall according to the present invention, a perspective view (A) showing a state in which the water passing part provided on the short side wall is formed in a comb tooth shape, and the passage of the short side wall on one side. It is a perspective view (B) which shows a mode that the water part is obstruct | occluded and the tooth-like water-permeable part of the other comb is obstruct | occluded. 同本発明の遮水壁における最終締切部の外側に仮遮水壁3を構築する手順を示す説明用斜視図(A),(B),(C)図である。It is an explanatory perspective view (A), (B), (C) which shows the procedure of constructing the temporary impermeable wall 3 outside the final cutoff part in the impermeable wall of the present invention. 同本発明の遮水壁における最終締切部の外側の仮遮水壁3において通水部を閉塞する手順を示す説明用斜視図(A),(B),(C)図である。It is explanatory perspective view (A), (B), (C) figure which shows the procedure which obstruct | occludes a water flow part in the temporary water-impervious wall 3 outside the last cutoff part in the water-impervious wall of this invention. 同本発明の遮水壁における最終締切部の外側に仮遮水壁3を構築した後に、本設の遮水壁の開口部を閉塞して、仮遮水壁3を撤去する手順を示す説明用斜視図(A),(B),(C)図である。The description which shows the procedure which obstruct | occludes the opening part of the main water-blocking wall, and removes the temporary water-blocking wall 3 after constructing the temporary water-blocking wall 3 outside the final cutoff part in the water-blocking wall of the present invention. It is a perspective view for use (A), (B), (C). クローラクレーン10により鋼矢板1aを台船から揚重し、ワイヤーで吊り下げた鋼矢板1aをバイブロハンマー8で海底地盤9に打設する作業を示す説明図である。It is explanatory drawing which shows the operation | work which lifts the steel sheet pile 1a from the carrier with the crawler crane 10, and drives the steel sheet pile 1a suspended with the wire to the submarine ground 9 with the vibro hammer 8. FIG. 鋼矢板1aを雇い杭7で水面下に打ち込む様子を説明する説明図(A)と、雇い杭7で鋼矢板1aを引き上げる様子を示す説明図(B)である。It is explanatory drawing (A) explaining a mode that the steel sheet pile 1a is driven below the surface of the water with the hiring pile 7, and explanatory drawing (B) which shows a mode that the hiring pile 7 pulls up the steel sheet pile 1a. 同本発明の遮水壁における最終締切部の外側に仮遮水壁3を構築する手順を示す概略の作業フロー図である。It is a general | schematic work flow figure which shows the procedure which builds the temporary impermeable wall 3 in the outer side of the final cutoff part in the impermeable wall of the same invention. 従来例に係る遮水壁を構築する施工の様子を示す説明断面図(A)と、鋼矢板1aを連接して打設する様子を示す説明図(B)とである。It is explanatory sectional drawing (A) which shows the mode of construction which builds the impermeable wall concerning a prior art example, and explanatory drawing (B) which shows a mode that the steel sheet pile 1a is connected and driven.

本発明に係る遮水壁1における最終締切部2の仮締切構造とその締切方法は、図1−Aに示すように、前記最終締切部2である開口部の外海側に矩形状の仮遮水壁3を構築し、最終締切部2を囲うことによってその開口部の流速を穏やかにして当該最終締切部2の締切を行うものである。前記遮水壁1で締め切られた廃棄物用埋立処分域に、一般廃棄物または管理型産業廃棄物を埋め立て処分するものである。   As shown in FIG. 1A, the temporary cutoff structure of the final cutoff part 2 in the water-impervious wall 1 according to the present invention and its cutoff method are rectangular temporary shields on the open sea side of the opening which is the final cutoff part 2. By constructing the water wall 3 and enclosing the final cutoff part 2, the flow rate of the opening is made gentle, and the final cutoff part 2 is closed. In the landfill disposal area for waste closed by the water shielding wall 1, general waste or managed industrial waste is landfilled.

図1−Aと図1−Bとに示すように、保有水等6の遮水壁1を本設の遮水矢板(以下、鋼矢板)1aで構築する際に、遮水壁1の一部を構成する遮水壁1bに設けられる最終締切部2である開口部の外側を囲う仮締切構造であって、前記最終締切部2の外側、即ち外海側5に、前記遮水壁1bの法線に直交する対向配置の短辺壁3a,3aと前記遮水壁1bの法線に平行な長辺壁3dとでなる平面視略コ字形の仮遮水壁3を構築する。前記最終締切部2における開口部を仮遮水壁3で囲って、開口部の流速を穏やかにするものである。   As shown in FIG. 1-A and FIG. 1-B, when constructing the impermeable wall 1 for the retained water 6 or the like with a main impermeable sheet pile (hereinafter referred to as a steel sheet pile) 1a, A temporary cutoff structure that surrounds the outside of the opening that is the final cutoff portion 2 provided in the water-impervious wall 1b that constitutes the portion, and the outer side of the final cutoff portion 2, that is, the outside sea side 5, A temporary impermeable wall 3 having a substantially U shape in a plan view is constructed by the short-side walls 3a, 3a arranged opposite to each other perpendicular to the normal and the long-side wall 3d parallel to the normal of the impermeable wall 1b. The opening in the final cutoff part 2 is surrounded by a temporary impermeable wall 3 so as to make the flow rate of the opening gentle.

前記対向配置の短辺壁3aは、例えば鋼矢板1aを海底に打ち込んで形成されるものであり、その一部に内外に水が出入りできる通水部3b,3cが設けられている。また、前記通水部3b,3cの通水面積が調節可能にされている。この通水部3b,3cを短辺壁3aに設けたのは、直接、波が短辺壁3aに打ち付けないことと、最終締切部2における開口部に対して波が平行になるよう調整されて仮遮水壁3内側に入り込むので、最終締切部2の内外水位差による海水の流速が緩和されるからである。   The opposed short side wall 3a is formed, for example, by driving a steel sheet pile 1a into the seabed, and water passage portions 3b and 3c through which water can enter and exit are provided in a part of the short side wall 3a. Moreover, the water flow area of the water flow parts 3b and 3c is adjustable. The reason why the water flow portions 3b and 3c are provided on the short side wall 3a is that the wave does not directly hit the short side wall 3a and that the wave is parallel to the opening in the final cutoff portion 2. This is because the flow rate of the seawater due to the difference between the inner and outer water levels of the final cutoff part 2 is relieved because the water enters the temporary impermeable wall 3.

前記通水部3b,3cの通水面積は、図1−B(B)に示すように、通水部3b,3cの縦方向の長さに合わせた通水面積調節用の矢板である雇い杭(幅0.6m程度)7を打設することで、調整される。または、通水部3b,3cに打設した雇い杭7を水面下に打ち込んだ鋼矢板の頭部に連結して、該鋼矢板を所要の位置まで引き上げたりして、前記通水部3b,3cの通水面積を調節する。この方法については、詳細に後述する。このようにして、最終締切部2における開口部に直接的に波が入らないように仮遮水壁3を構築して、波の方向が前記最終締切部2に平行になるようにするものである。   As shown in FIG. 1-B (B), the water flow area of the water flow parts 3b and 3c is a sheet pile for adjusting the water flow area adjusted to the length of the water flow parts 3b and 3c. It is adjusted by driving a pile (width of about 0.6 m) 7. Alternatively, the hiring pile 7 placed in the water flow sections 3b and 3c is connected to the head of the steel sheet pile driven into the water surface, and the steel sheet pile is pulled up to a required position, and the water flow section 3b, Adjust the water flow area of 3c. This method will be described later in detail. In this way, the temporary impermeable wall 3 is constructed so that the wave does not directly enter the opening in the final cutoff part 2 so that the direction of the wave is parallel to the final cutoff part 2. is there.

本発明に係る遮水壁1における最終締切部2の締切方法について、図2〜図6を参照して一例を説明する。保有水等用の遮水壁1を矢板(鋼矢板)1aで構築する際の、遮水壁1の一部である本設の遮水壁(500m〜800m程度)1bに設けられる最終締切部2(開口部が約20m程度)を締切する方法である。図2(A)に示すように、前記本設の遮水壁1bの最終締切部2である開口部の外側に、即ち外海側5に、前記本設の遮水壁1bの法線に直交する対向配置で通水部3bを有する短辺壁3aと、通水部3cを有する短辺壁3aをそれぞれ構築する。   An example of the closing method of the final closing part 2 in the impermeable wall 1 according to the present invention will be described with reference to FIGS. The final cut-off part provided in the main impermeable wall (about 500 m to 800 m) 1b which is a part of the impermeable wall 1 when the impermeable wall 1 for retained water is constructed with a sheet pile (steel sheet pile) 1a 2 (opening is about 20 m). As shown in FIG. 2 (A), perpendicular to the normal line of the main water-impervious wall 1b, outside the opening that is the final cut-off portion 2 of the main water-impervious wall 1b, that is, on the outer sea side 5. A short side wall 3a having a water passage 3b and a short side wall 3a having a water passage 3c are respectively constructed.

前記本設の遮水壁1bは、不透水層を有する海底地盤9に鋼矢板1aを打設して更に裏込石を投入して、構築するものである。前記鋼矢板1aによる遮水壁1の構築には、図5−Aに示すように、マウント11の上にケーソン12を敷設して、その上に作業架台12aを構築して、該作業架台12aに乗せたクローラクレーン10によって台船から揚重した鋼矢板1aをワイヤーで吊り下げて、打設位置にてバイブロハンマー8で前記鋼矢板1aを所定の高さに打ち込むものである。これが、図6に示すステップ1である。   The permanently installed impermeable wall 1b is constructed by placing a steel sheet pile 1a on a seabed ground 9 having an impermeable layer and further introducing a backstone. As shown in FIG. 5A, the construction of the impermeable wall 1 using the steel sheet pile 1a is performed by laying a caisson 12 on the mount 11, constructing a work platform 12a thereon, and then constructing the work platform 12a. The steel sheet pile 1a lifted from the carriage by the crawler crane 10 placed on is hung with a wire, and the steel sheet pile 1a is driven to a predetermined height with a vibro hammer 8 at the placing position. This is step 1 shown in FIG.

次に、図2(A),(B)に示すように、短辺壁3a,3aを構築する。この短辺壁3aにおける通水部3b,3cは、鋼矢板1aを海面下の所定の深さまで打ち込むことで形成される。そのとき、バイブロハンマー8を海中に入れることができないので、ヤットコとしての所要長さにした雇い杭(鋼矢板1aと同じもの)7を使用する。   Next, as shown in FIGS. 2A and 2B, the short side walls 3a and 3a are constructed. The water flow portions 3b and 3c in the short side wall 3a are formed by driving the steel sheet pile 1a to a predetermined depth below the sea surface. At that time, since the vibro hammer 8 cannot be put into the sea, an employment pile (same as the steel sheet pile 1a) 7 having a required length as a Yatco is used.

図5−B(A)に示すように、鋼矢板1aの頭部に連結板7aを介して雇い杭7を取り付けて、前記鋼矢板1aを海面下に打ち込む。所定の位置に達したら、潜水夫により前記連結板7aの下側のボルト等を外して、連結板7aと鋼矢板1aとの連結状態を解除し、バイブロハンマー8とともに雇い杭7を引き上げる。このようにして、通水部3b,3cを形成する。図6のステップ2である。   As shown in FIG. 5-B (A), the hiring pile 7 is attached to the head of the steel sheet pile 1a via the connecting plate 7a, and the steel sheet pile 1a is driven below the sea level. When a predetermined position is reached, the lower bolt or the like of the connecting plate 7a is removed by a diver, the connecting state of the connecting plate 7a and the steel sheet pile 1a is released, and the hiring pile 7 is pulled up together with the vibro hammer 8. Thus, the water flow parts 3b and 3c are formed. This is step 2 in FIG.

開口部2の片側に鋼矢板1aを打設して開口部2の長さを約20mにする。そして、裏込め石を投入する。図6のステップ3,4である。その後、図2(C)に示すように、前記本設の遮水壁1bの法線に平行な長辺壁3dを構築することで、平面視略コ字形の仮遮水壁3を構築する。図6のステップ5である。仮遮水壁3に裏込め石を投入する。図6のステップ6である。   A steel sheet pile 1a is driven on one side of the opening 2 so that the length of the opening 2 is about 20 m. Then throw back stones. These are steps 3 and 4 in FIG. Thereafter, as shown in FIG. 2 (C), by constructing a long side wall 3d parallel to the normal line of the main impermeable wall 1b, a temporary impermeable wall 3 having a substantially U shape in plan view is constructed. . This is step 5 in FIG. A backfill stone is put into the temporary impermeable wall 3. This is step 6 in FIG.

図3(A)に示すように、前記短辺壁3aにおける一方の通水部3cを雇い杭7で閉塞させる。この作業においては、通水部3bや最終締切部2である開口部の流速が早まらないように、潮止まり時間,作業時間,発生流速等を確認して行うものである。   As shown in FIG. 3 (A), one water passing portion 3 c in the short side wall 3 a is closed by the hiring pile 7. In this operation, the tidal time, the operation time, the generated flow velocity, etc. are confirmed so that the flow velocity of the water passage portion 3b and the opening that is the final cutoff portion 2 does not increase.

更に、保有水等6内の水位調整のため、他方の短辺壁3aの通水部3bは、櫛の歯状にする。それには、図3(B)に示すように、雇い杭7を櫛歯状に挿入する。この状態になると、速い流速が生じても、安全に施工できる。   Furthermore, in order to adjust the water level in the retained water 6 or the like, the water passing portion 3b of the other short side wall 3a is shaped like a comb. For this purpose, as shown in FIG. 3 (B), the hiring pile 7 is inserted in a comb shape. If it will be in this state, even if a quick flow velocity arises, it can construct safely.

次に、他方の短辺壁3aにおける通水部3bを、保有水等6の内水位が管理水位に近いことを確認しながら、図4(A)に示すように、適宜な潮位の時に締切する。これには、図3(C)に示すように、雇い杭7を櫛の歯状の通水部3bに差し込んで閉塞する。または、図5−B(B)に示すように、海面下に打設した鋼矢板1aを、雇い杭7を前記鋼矢板1aの頭部に連結して、バイブロハンマー8で前記雇い杭7を介して振動を与えて徐々に水面上に引き上げていき、鋼矢板1aによって閉塞させるようにしても良い。これが図6のステップ7である。   Next, the water flow section 3b in the other short side wall 3a is cut off at an appropriate tide level as shown in FIG. 4 (A) while confirming that the internal water level of the retained water 6 is close to the control water level. To do. For this, as shown in FIG. 3 (C), the hiring pile 7 is inserted into the comb-shaped water passage 3b and closed. Alternatively, as shown in FIG. 5-B (B), a steel sheet pile 1a placed under the sea surface is connected to the head of the steel sheet pile 1a with the hiring pile 7 and the hiring pile 7 is connected with a vibro hammer 8. It is also possible to apply vibrations to the surface of the water and gradually close it with the steel sheet pile 1a. This is step 7 in FIG.

そして、図4(B)に示すように、前記本設の遮水壁1bの最終締切部2である開口部を、鋼矢板1aを打設して全部締切る。これで遮水壁1の本締切が完了する。そして、開口部2の周辺に裏込石を投入する。これが図6のステップ8,9である。その後、図4(C)に示すように、前記仮遮水壁3をクローラクレーン10によってバイブロハンマー8で引き抜いて撤去する。図6のステップ10である。   And as shown in FIG.4 (B), the steel sheet pile 1a is driven and the opening part which is the final cutoff part 2 of the said water-impervious wall 1b is permanently closed. This completes the final closing of the impermeable wall 1. Then, a back stone is put around the opening 2. This is steps 8 and 9 in FIG. Thereafter, as shown in FIG. 4C, the temporary impermeable wall 3 is pulled out by the crawler crane 10 with the vibro hammer 8 and removed. This is step 10 in FIG.

本発明に係る遮水壁の最終締切部における仮締切構造とその締切方法は、最終締切部である開口部の流速が速くなるおそれのある潮位差の大きい海岸部や河川堤等において適用できるものである。   The temporary closing structure and the closing method for the final cutoff part of the impermeable wall according to the present invention can be applied to a coastal part or a river bank with a large tide level difference that may increase the flow velocity of the opening which is the final cutoff part. It is.

1 遮水壁、 1a 遮水矢板(鋼矢板)、
1b 本設の遮水壁、
2 最終締切部(開口部)、
3 仮遮水壁、 3a 短辺壁、
3b 通水部、 3c 通水部、
3d 長辺壁、
4 通水部、
5 外海側、
6 保有水等、
7 雇い杭、 7a 連結板、
8 バイブロハンマー、
9 海底地盤、
10 クローラクレーン、
11 マウント、
12 ケーソン、 12a 作業架台。
1 impermeable wall, 1a impermeable sheet pile (steel sheet pile),
1b Impermeable wall,
2 Final deadline (opening),
3 Temporary impermeable wall, 3a Short side wall,
3b water passage, 3c water passage,
3d long side wall,
4 water flow section,
5 Open sea side,
6 Retained water, etc.
7 Hiring pile, 7a Connecting plate,
8 Vibro hammer,
9 Undersea ground,
10 crawler crane,
11 Mount,
12 Caisson, 12a Work platform.

Claims (6)

廃棄物又は保有水を外海から遮水する遮水壁を遮水矢板で構築する際の、該遮水壁における最終締切部の仮締切構造であって、
前記最終締切部の外側に、前記遮水壁に直交する対向配置の短辺壁と前記遮水壁に平行な長辺壁とでなる平面視略コ字形の仮遮水壁を構築し、
前記対向配置の短辺壁に、水が出入りできる通水部が設けられ、
前記通水部の通水面積が調節可能にしてあること、
を特徴とする遮水壁における最終締切部の仮締切構造。
When the impermeable wall that shields waste or retained water from the open sea is constructed with a impermeable sheet pile, a temporary closing structure of the final closing portion in the impermeable wall,
On the outside of the final cut-off part, a temporary water shielding wall having a substantially U-shape in plan view composed of a short side wall oppositely arranged perpendicular to the water shielding wall and a long side wall parallel to the water shielding wall is constructed,
On the short side wall of the opposed arrangement, a water passage portion through which water can enter and exit is provided,
The water flow area of the water flow section is adjustable.
A temporary cutoff structure of the final cutoff part in the impermeable wall characterized by
通水部の通水面積の調節は、通水部の縦方向の長さに合わせた通水面積調節用の矢板である雇い杭を打設したり、通水部に打設した雇い杭を引き抜いたりして、調節されるものであること、
を特徴とする請求項1に記載の遮水壁における最終締切部の仮締切構造。
Adjustment of the water flow area of the water flow section can be done by placing a hiring pile that is a sheet pile for adjusting the water flow area according to the vertical length of the water flow section, or To be pulled out and adjusted,
The temporary cutoff structure of the final cutoff part in the impermeable wall of Claim 1 characterized by these.
通水部は、櫛の歯状に打設された矢板によって形成されていること、
を特徴とする請求項1または2に記載の遮水壁における最終締切部の仮締切構造。
The water flow part is formed by a sheet pile placed in the shape of a comb tooth,
The temporary cutoff structure of the final cutoff part in the impermeable wall of Claim 1 or 2 characterized by these.
廃棄物又は保有水を外海から遮水する遮水壁を遮水矢板で構築する際の、前記遮水壁の最終締切部を締切する方法において、
前記遮水壁の最終締切部の外側に、該最終締切部に直交する対向配置で通水部を有する短辺壁を構築し、
次に、前記遮水壁の最終締切部に平行な長辺壁を構築することで平面視略コ字形の仮遮水壁を構築し、
前記短辺壁における一方の通水部を閉塞させ、
その後、前記短辺壁における他方の通水部を適宜な潮位の時に閉塞させ、
前記遮水壁の最終締切部を矢板を打設して閉塞し、
その後、前記仮遮水壁を撤去すること、
を特徴とする遮水壁における最終締切部の締切方法。
In the method of closing the final cut-off part of the impermeable wall when constructing the impermeable wall that shields waste or retained water from the open sea with the impermeable sheet pile,
On the outside of the final cutoff part of the water-impervious wall, construct a short side wall having a water passage part in an opposing arrangement perpendicular to the final cutoff part,
Next, by constructing a long side wall parallel to the final cut-off portion of the water shielding wall, a temporary water shielding wall having a substantially U shape in plan view is constructed,
Block one water passing portion in the short side wall,
After that, the other water flow portion in the short side wall is closed at an appropriate tide level,
The final shut-off part of the impermeable wall is closed by placing a sheet pile,
Then, removing the temporary impermeable wall,
A method for closing the final cut-off portion in the impermeable wall characterized by the above.
通水部は、櫛の歯状に打設された矢板によって形成されていること、
を特徴とする請求項4に記載の遮水壁における最終締切部の締切方法。
The water flow part is formed by a sheet pile placed in the shape of a comb tooth,
The method for closing a final cut-off portion in the impermeable wall according to claim 4.
通水部を閉塞するには、通水部における櫛の歯状開口部の縦方向の長さに合わせた通水面積調節用の矢板である雇い杭を前記櫛の歯状の開口部に打設して閉塞すること、若しくは、雇い杭の下部を櫛の歯状の開口部で水面下に沈んでいる矢板上部に連結して当該矢板を前記雇い杭を介して水面上に引き上げて閉塞すること、
を特徴とする請求項5に記載の遮水壁における最終締切部の締切方法。
In order to close the water flow portion, a hiring pile, which is a sheet pile for adjusting the water flow area adjusted to the longitudinal length of the comb tooth opening in the water flow portion, is applied to the tooth opening of the comb. Install and block, or connect the lower part of the hiring pile to the upper part of the sheet pile sinking under the water surface with a comb-like opening and pull the sheet pile up to the water surface through the hiring pile and close it about,
The method for closing the final cut-off portion in the impermeable wall according to claim 5.
JP2010289838A 2010-12-27 2010-12-27 Temporary deadline structure of the final deadline in the impermeable wall and its deadline method Active JP5572540B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010289838A JP5572540B2 (en) 2010-12-27 2010-12-27 Temporary deadline structure of the final deadline in the impermeable wall and its deadline method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010289838A JP5572540B2 (en) 2010-12-27 2010-12-27 Temporary deadline structure of the final deadline in the impermeable wall and its deadline method

Publications (2)

Publication Number Publication Date
JP2011089392A JP2011089392A (en) 2011-05-06
JP5572540B2 true JP5572540B2 (en) 2014-08-13

Family

ID=44107867

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010289838A Active JP5572540B2 (en) 2010-12-27 2010-12-27 Temporary deadline structure of the final deadline in the impermeable wall and its deadline method

Country Status (1)

Country Link
JP (1) JP5572540B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113737829A (en) * 2021-07-30 2021-12-03 中铁十九局集团第五工程有限公司 Steel sheet pile and concrete wall combined cofferdam structure and construction method
CN113737830A (en) * 2021-09-07 2021-12-03 江苏兴宇建设集团有限公司 One-way occupation method steel pipe pile cofferdam construction method
CN114753390B (en) * 2022-05-05 2024-02-09 蒙城县水利局建筑工程队 Water conservancy cofferdam with adjustable
CN115324085A (en) * 2022-07-25 2022-11-11 中交一公局厦门工程有限公司 Basement rock skirting protection device for bottom-sealing-free rock-socketed steel sheet pile cofferdam

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0258617A (en) * 1988-08-23 1990-02-27 Mizota Kogyo Kk Temporary coffering method for river
JP2000144677A (en) * 1998-11-05 2000-05-26 Taisei Corp Temporary cofferdam construction method
JP5132435B2 (en) * 2008-06-18 2013-01-30 株式会社アイ・エイチ・アイ・アムテック Installation method of water stop box and water stop box

Also Published As

Publication number Publication date
JP2011089392A (en) 2011-05-06

Similar Documents

Publication Publication Date Title
JP5445351B2 (en) Filling reinforcement structure
CN113330164A (en) Method for constructing underwater concrete block structure
JP4761780B2 (en) Construction method of impermeable layer
JP2011518268A (en) Flood, coastal or puddle protection device and method
JP5572540B2 (en) Temporary deadline structure of the final deadline in the impermeable wall and its deadline method
JP5846150B2 (en) Construction method of river revetment structure
JP5782734B2 (en) Wall sheet with liquefaction measures and steel sheet pile with liquefaction suppression function
JP2003206539A (en) Temporary closing construction method
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
JP6854479B2 (en) Liquefaction countermeasure structure for underground structures
JP4819835B2 (en) Offshore structure and construction method of offshore structure
JP2008019561A (en) Construction method of countermeasure against liquefaction under breakwater caused by creation of underground wall
KR20140092217A (en) Construction method of the pier with the working bardge
CN104612106B (en) A kind of permeable geotechnique soft raft structure
KR101983964B1 (en) Cofferdam structure and cofferdam method using the same
JP2726611B2 (en) How to set up an open caisson
JP2003113608A (en) Impervious wall structure and impervious bank protection structure using the same
JP5306885B2 (en) Construction method for underwater structures
JP6018804B2 (en) Cell body water-blocking structure
JP6283086B1 (en) Construction method of partition revetment
JP4982632B2 (en) Liquefaction countermeasure method under breakwater
JP4104467B2 (en) Seawall structure and seawall construction method
JPH0645943B2 (en) Liquefaction countermeasure construction method for buried structures
KR102702783B1 (en) Waterproofing method of steel temporary facilities
JPH05132913A (en) Method of installing protective device to big wave

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20131022

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140425

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140603

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140630

R150 Certificate of patent or registration of utility model

Ref document number: 5572540

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250