JP4532337B2 - Propile pile sheet pile method capable of treating underground water - Google Patents

Propile pile sheet pile method capable of treating underground water Download PDF

Info

Publication number
JP4532337B2
JP4532337B2 JP2005143690A JP2005143690A JP4532337B2 JP 4532337 B2 JP4532337 B2 JP 4532337B2 JP 2005143690 A JP2005143690 A JP 2005143690A JP 2005143690 A JP2005143690 A JP 2005143690A JP 4532337 B2 JP4532337 B2 JP 4532337B2
Authority
JP
Japan
Prior art keywords
water
pile
sheet
underground water
sheet pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2005143690A
Other languages
Japanese (ja)
Other versions
JP2006322155A (en
Inventor
宏紀 上村
芳雄 平井
努 並河
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2005143690A priority Critical patent/JP4532337B2/en
Publication of JP2006322155A publication Critical patent/JP2006322155A/en
Application granted granted Critical
Publication of JP4532337B2 publication Critical patent/JP4532337B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

この発明は、地盤掘削時に山留め壁を構築するために実施される親杭横矢板工法の技術分野に属し、更に云うと、地盤調査等の事前調査で調べられない伏流水層等が掘削深度内に存在した場合に、事後的に伏流水等の処理が可能な親杭横矢板工法に関する。   The present invention belongs to the technical field of the main pile lateral sheet pile method for constructing a retaining wall at the time of ground excavation, and moreover, an underground water layer that cannot be examined in a preliminary survey such as a ground survey is within the excavation depth. It is related to the parent pile side sheet construction method that can be used to treat underground water afterwards.

従来の親杭横矢板工法には、地盤調査等の事前調査で調べることができる、例えば地下水位の高い地盤を止水処理しながら掘削することができるように工夫されたものがある(特許文献1〜5)。つまり、前提として地下水の処理が必要であることが当初から判明している場合に、有効な技術であり、事前調査で必要がないと判明した場合は採用されることが殆どない。   Conventional parent pile sheet pile methods can be examined by preliminary surveys such as ground surveys, for example, so that the ground with a high groundwater level can be excavated while being stopped (Patent Document) 1-5). In other words, it is an effective technique when it is known from the beginning that groundwater treatment is necessary as a premise, and it is rarely adopted when it is found that it is not necessary in a preliminary survey.

その場合は、掘削の進行とともにH形鋼から成る親杭の相互間に矢板を挿入する、通例の親杭横矢板工法が採用されるが、地盤調査等の事前調査で調べられない伏流水層等が掘削深度内に存在していた場合は、事後的に伏流水等の処理をする必要がある。当該伏流水等の処理方法としては(I)山留め壁の背面で伏流水等を汲み上げたり、又は(II)伏流水層等に薬液を注入することで遮水層を構築するのが一般的である。
特公平7−47844号公報 特開平9−71931号公報 特開平9−111754号公報 特開2001−107361号公報 特許第2818843号公報
In that case, the usual pile pile sheet pile method is adopted, in which sheet piles are inserted between the piles made of H-shaped steel as the excavation progresses, but the underground water layer that cannot be examined in the preliminary survey such as ground survey Etc. exist within the excavation depth, it is necessary to treat underground water after the fact. The treatment method for the underground water is generally (I) pumping underground water, etc. at the back of the retaining wall, or (II) constructing a water shielding layer by injecting chemicals into the underground water layer, etc. is there.
Japanese Patent Publication No. 7-47844 Japanese Patent Laid-Open No. 9-71931 Japanese Patent Laid-Open No. 9-111754 JP 2001-107361 A Japanese Patent No. 2818843

上記(I)の処理方法は、伏流水層等が深いと揚水するための設備の構築にコストが嵩む。しかも、山留め壁の背面に余裕がないと揚水するための設備が構築できない。また、設備を構築するため、山留め壁の背面の地盤が乱れるなどの問題点を有する。   In the treatment method (I), when the underground water layer or the like is deep, the construction of equipment for pumping water increases. Moreover, it is impossible to construct a facility for pumping water unless there is room on the back of the retaining wall. Moreover, since the facilities are constructed, there is a problem that the ground on the back of the retaining wall is disturbed.

上記(II)の処理方法は、薬液が高価でしかも大量に必要であるため、コストが嵩む。しかも、薬液を注入するための準備や、注入作業及び硬化待ちに時間を要するため、工期が大幅に遅れる。また、硬化するまでの間に、山留め壁の背面の砂が伏流水等に押し流され、山留め壁の背面の地盤が乱れるなどの問題点を有する。   The treatment method (II) is expensive because the chemical solution is expensive and requires a large amount. Moreover, since it takes time to prepare for injecting the chemical solution, injecting work and waiting for curing, the construction period is greatly delayed. In addition, there is a problem that the sand on the back surface of the retaining wall is swept away by underground water or the like until it hardens, and the ground on the back surface of the retaining wall is disturbed.

本発明の目的は、通例の親杭横矢板工法の流れを大きく変えることなく、事後的に伏流水等の処理が可能で、すなわち掘削が伏流水層等に到達すると、以後、掘削の進行とともに、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した集水溝に導く構成を段階的に盛り替え、同集水溝に導いた伏流水等を汲み上げながら、最終掘削底面の深さまで掘削することで、伏流水等を汲み上げるための大掛かりな設備を構築したり、又は薬液を注入する必要がなくコストの削減と工期の短縮に寄与し、しかも、山留め壁の背面に余裕がなくても実施可能な、伏流水等の処理が可能な親杭横矢板工法を提供することである。   The purpose of the present invention is to allow the treatment of underground water and the like afterwards without greatly changing the flow of the usual main pile pile sheet method, that is, when excavation reaches the underground water layer, etc. , Step by step the arrangement of guiding underground water etc. from the water-permeable sheet placed on the back of the sheet pile to the water collecting groove formed below the sheet pile, and finally pumping underground water etc. led to the water collecting groove, By drilling to the depth of the bottom of the excavation, there is no need to construct a large facility for pumping underground water, etc., or to inject chemicals, contributing to cost reduction and shortening the construction period, and the back of the retaining wall It is to provide a parent pile sheet pile method capable of processing underground water and the like, which can be carried out even if there is no room.

本発明の次の目的は、山留め壁の背面の地盤を健全な状態に維持しながら、伏流水等の処理が可能な親杭横矢板工法を提供することである。   The next object of the present invention is to provide a parent pile lateral sheet pile method capable of treating underground water and the like while maintaining the ground on the back surface of the retaining wall in a healthy state.

上記従来技術の課題を解決するための手段として、請求項1に記載した発明に係る伏流水等の処理が可能な親杭横矢板工法は、
伏流水等の処理が可能な親杭横矢板工法であって、
掘削地盤の周辺にH形鋼から成る親杭を、最終掘削底面の深さ以下まで打設する工程と、
掘削地盤を掘削し、掘削の進行とともに、親杭の相互間に矢板を挿入して山留めを行う工程と、
掘削が伏流水層等に到達すると、露出した伏流水層等の周辺の掘削底面のみを先行掘削し、伏流水層等以下の掘削側面に、水は通すが、砂は殆ど通さない繊維材料で構成した透水性シートを宛い、前記親杭の相互間に矢板を挿入して前記透水性シートを支持し、更に、同矢板の前面を止水性シートで覆い、伏流水等を矢板の背面に配置した透水性シートから、同矢板の下方に形成した集水溝に導く構成とし、同集水溝に導いた伏流水等を汲み上げる工程と、
以後、掘削の進行とともに、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した集水溝に導く構成を段階的に盛り替え、同集水溝に導いた伏流水等を汲み上げながら、最終掘削底面の深さまで掘削する工程と、
から成ることを特徴とする。
As a means for solving the above-mentioned problems of the prior art, the parent pile horizontal sheet pile method capable of processing underground water according to the invention described in claim 1 is:
It is a parent pile horizontal sheet pile method that can treat underground water,
A process of driving a parent pile made of H-shaped steel around the excavated ground to a depth below the final excavation bottom;
Excavating the excavated ground, as the excavation progresses, inserting a sheet pile between the parent piles,
When the excavation reaches the underground water layer, etc., only the bottom surface of the surrounding area such as the exposed underground water layer is pre-excavated. Address the configured water-permeable sheet, insert a sheet pile between the parent piles to support the water-permeable sheet, and further cover the front surface of the sheet pile with a water-resistant sheet, with underground water etc. on the back surface of the sheet pile From the arranged water-permeable sheet, it is configured to guide to a water collecting groove formed below the sheet pile, and a process of pumping underground water led to the water collecting groove,
Later, as excavation progressed, the underground flow water led to the drainage channel was gradually changed from the water-permeable sheet placed on the back of the sheet pile to the drainage groove formed below the sheet pile. Drilling to the depth of the final excavation bottom,
It is characterized by comprising.

請求項2記載の発明は、請求項1に記載した伏流水等の処理が可能な親杭横矢板工法において、
先行掘削は伏流水層等の下方に堆積する不透水層に到達する深さまで掘削することを特徴とする。
The invention according to claim 2 is the parent pile lateral sheet pile method capable of processing underground water and the like according to claim 1,
The preceding excavation is characterized by excavating to a depth that reaches an impermeable layer that accumulates underneath the underground water layer.

請求項3記載の発明は、請求項1又は2に記載した伏流水等の処理が可能な親杭横矢板工法において、
掘削が伏流水層等に到達した直後に形成する集水溝は、矢板の前面を止水性シートで覆った後に、先行掘削した平面領域を更に掘削して形成することを特徴とする。
The invention according to claim 3 is the parent pile horizontal sheet pile method capable of processing underground water or the like described in claim 1 or 2,
The water collecting groove formed immediately after the excavation reaches the underground water layer or the like is formed by further excavating a plane area excavated in advance after covering the front surface of the sheet pile with a water-proof sheet.

請求項4記載の発明は、請求項1又は2に記載した伏流水等の処理が可能な親杭横矢板工法において、
掘削が伏流水層等に到達した直後に形成する集水溝は、露出した伏流水層等の周辺の掘削底面を先行掘削すると共に形成することを特徴とする。
The invention according to claim 4 is the parent pile lateral sheet pile method capable of processing underground water or the like according to claim 1 or 2,
The water collecting groove formed immediately after the excavation reaches the underground water layer or the like is characterized in that the excavation bottom surface around the exposed underground water layer or the like is excavated and formed.

請求項5記載の発明は、請求項1に記載した伏流水等の処理が可能な親杭横矢板工法において、
先行掘削した平面領域に形成した集水溝を段階的に掘り下げて、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した同集水溝に導く構成を盛り替え、同集水溝に導いた伏流水等を汲み上げる工程と、集水溝に導いた伏流水等の汲み上げを続け、先行掘削した平面領域以外の平面領域を掘削する工程とを、繰り返して最終掘削底面の深さまで掘削することを特徴とする。
The invention according to claim 5 is the main pile lateral sheet pile method capable of processing underground water or the like according to claim 1,
The water collecting groove formed in the flat area that was excavated in advance is dug down step by step, and the structure that guides the underground water etc. from the water-permeable sheet arranged on the back of the sheet pile to the water collecting groove formed below the sheet pile is changed. The process of pumping underground water, etc., led to the catchment groove, and the process of continuously pumping underground water, etc., led to the catchment groove, and excavating plane areas other than the previously excavated plane area are repeated. It is characterized by drilling to a depth of.

請求項6記載の発明は、請求項1又は5に記載した伏流水等の処理が可能な親杭横矢板工法において、
集水溝に釜場を形成しており、最終工程で集水溝を形成した後に同集水溝の釜場に簡易揚水井戸を形成して同簡易揚水井戸から伏流水等の汲み上げを続け、前記集水溝に砕石を敷き詰めて最終掘削底面と略等しい高さに整え、矢板の前面を覆った止水性シートの下端部と連続するように、敷き詰めた砕石の上面を底面用止水性シートで隙間なく覆い、露出する掘削底面及び底面用止水性シートの上面に均しコンクリートを打設することを特徴とする。
The invention according to claim 6 is the parent pile lateral sheet pile method capable of processing underground water or the like according to claim 1 or 5,
A kettle is formed in the catchment ditch, and after the catchment groove is formed in the final process, a simple pumping well is formed in the catchment in the catchment ditch and pumping of underground water, etc. is continued from the simple pumping well. Place the crushed stone in the water collecting groove and adjust it to a height approximately equal to the bottom of the final excavation.The bottom surface of the crushed stone is covered with a water-proof sheet for the bottom so that it is continuous with the lower end of the water-proof sheet covering the front of the sheet pile. It is characterized in that smooth concrete is placed on the bottom surface of the excavation bottom surface and the bottom water-proof sheet that covers and exposes without gaps.

請求項7記載の発明は、請求項6に記載した伏流水等の処理が可能な親杭横矢板工法において、
集水溝を掘削地盤の平面内方まで導き、同集水溝に釜場を形成することを特徴とする。
The invention according to claim 7 is the parent pile sheet pile method capable of processing underground water or the like according to claim 6,
It is characterized by guiding the catchment groove to the inside of the excavated ground and forming a pothole in the catchment groove.

本発明に係る伏流水等の処理が可能な親杭横矢板工法は、通例の親杭横矢板工法の流れを大きく変えることなく、事後的に伏流水等の処理が可能で、すなわち掘削が伏流水層等に到達すると、以後、掘削の進行とともに、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した集水溝に導く構成を段階的に盛り替え、同集水溝に導いた伏流水等を汲み上げながら、最終掘削底面の深さまで掘削するので、伏流水等を汲み上げるための大掛かりな設備を構築したり、又は薬液を注入する必要がなくコストの削減と工期の短縮に寄与する。   The main pile horizontal sheet pile method capable of treating underground water and the like according to the present invention is capable of treating underground water and the like afterwards without greatly changing the flow of the usual parent pile horizontal sheet pile method, that is, excavation is underground After reaching the water layer, etc., as the excavation progresses, the structure that guides underground water, etc., from the water-permeable sheet placed on the back of the sheet pile to the water collecting groove formed below the sheet pile is gradually changed. While pumping underground water, etc., led to the ditches, drilling to the depth of the bottom of the final excavation, it is not necessary to build a large-scale facility for pumping underground water, etc. Contributes to shortening.

しかも、矢板の背面に透水性シートを配置できるスペースがあれば実施できるので、山留め壁の背面に余裕がなくても実施可能である。   And since it can implement if there is a space which can arrange | position a water-permeable sheet in the back surface of a sheet pile, even if there is no allowance in the back surface of a mountain retaining wall, it can implement.

また、掘削側面に水は通すが、砂は殆ど通さない繊維材料で構成した透水性シートを宛い、同透水性シートに伏流水等を通して処理するので、濾過機能が働いて伏流水等と共に砂が流出することがなく、山留め壁の背面の地盤を健全に維持しながら、伏流水等の処理をすることができる。   In addition, a water-permeable sheet made of a fiber material that allows water to pass through the excavation side, but hardly allows sand to pass, is processed through underground water, etc., through the water-permeable sheet. The underground water can be treated while maintaining the ground on the back of the retaining wall sound.

掘削地盤の周辺にH形鋼から成る親杭を、最終掘削底面の深さ以下まで打設する。掘削地盤を掘削し、掘削の進行とともに、親杭の相互間に矢板を挿入して山留めを行う。掘削が伏流水層等に到達すると、露出した伏流水層等の周辺の掘削底面のみを先行掘削し、伏流水層等以下の掘削側面に、水は通すが、砂は殆ど通さない繊維材料で構成した透水性シートを宛い、前記親杭の相互間に矢板を挿入して前記透水性シートを支持し、更に、同矢板の前面を止水性シートで覆い、伏流水等を矢板の背面に配置した透水性シートから、同矢板の下方に形成した集水溝に導く構成とし、同集水溝に導いた伏流水等を汲み上げる。以後、掘削の進行とともに、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した集水溝に導く構成を段階的に盛り替え、同集水溝に導いた伏流水等を汲み上げながら、最終掘削底面の深さまで掘削する。   A parent pile made of H-shaped steel is placed around the excavated ground to the depth of the final excavated bottom. The excavated ground is excavated, and as the excavation progresses, sheet piles are inserted between the parent piles to secure the mountain. When the excavation reaches the underground water layer, etc., only the bottom surface of the surrounding area such as the exposed underground water layer is pre-excavated. Address the configured water-permeable sheet, insert a sheet pile between the parent piles to support the water-permeable sheet, and further cover the front surface of the sheet pile with a water-resistant sheet, with underground water etc. on the back surface of the sheet pile The arrangement is such that the water permeable sheet is guided to the water collecting groove formed below the sheet pile, and the underground water or the like led to the water collecting groove is pumped up. Later, as excavation progressed, the underground flow water led to the drainage channel was gradually changed from the water-permeable sheet placed on the back of the sheet pile to the drainage groove formed below the sheet pile. Drill up to the depth of the bottom of the final excavation while pumping up etc.

請求項1〜請求項3及び請求項5、6に記載した発明に係る伏流水等(伏流水以外の地下流水などを含む。)の処理が可能な親杭横矢板工法(以下、単に親杭横矢板工法と省略する場合がある。)を、図面に基づいて説明する。   A main pile lateral sheet pile method (hereinafter simply referred to as parent pile) capable of processing underground water (including groundwater other than underground water) according to the inventions described in claims 1 to 3 and claims 5 and 6. (It may be abbreviated as a horizontal sheet pile method.) Is explained based on the drawings.

本発明の親杭横矢板工法は、地盤掘削時に山留め壁を構築するために実施され、特に、地盤調査等の事前調査で調べられない伏流水層(但し、流水層でも同様に実施可能)が掘削深度内に存在していた場合に好適に実施される。   The main pile side sheet pile method of the present invention is carried out in order to construct a retaining wall at the time of ground excavation, and in particular, there is an underground water layer that can not be examined by a preliminary survey such as ground survey (however, it can also be carried out in a flowing water layer). It is preferably implemented when it exists within the excavation depth.

先ず、通例の親杭横矢板工法と同じく、掘削地盤1の周辺に親杭として複数本のH形鋼2…を、等間隔に最終掘削底面の深さH以下まで打設する。そして、掘削地盤1を掘削し、掘削の進行とともに、H形鋼2、2の相互間に矢板3を挿入する(図1及び図2を参照)。 First, similarly to the usual parent pile side sheet pile method, a plurality of H-section steels 2 are placed around the excavated ground 1 as a parent pile at equal intervals to a depth H 1 or less of the final excavation bottom surface. And excavation ground 1 is excavated, and sheet pile 3 is inserted between H section steels 2 and 2 with progress of excavation (refer to Drawing 1 and Drawing 2).

掘削を進めていき、伏流水層4に到達すると、露出した伏流水層4の周辺の掘削底面1a(図2を参照)のみを、伏流水層4直下(但し、この限りでない。)に堆積する不透水層5(例えば、粘土層)に到達し、且つ新たな矢板3を挿入可能な深さHまで先行掘削する(請求項2記載の発明)。そして、伏流水層4が露出したH形鋼2、2の相互間における同伏流水層4以下の掘削側面1bに透水性シート6を宛い、前記H形鋼2、2の相互間に矢板3を挿入して前記透水性シート6を支持する(図3〜図5を参照)。 When excavation proceeds and reaches the underground water layer 4, only the bottom surface 1 a (see FIG. 2) around the exposed underground water layer 4 is deposited directly under the underground water layer 4 (but not limited to this). impermeable layer 5 (e.g., clay layer) reached, and a new sheet pile 3 precedes drilling to a depth H 2 can be inserted (the second aspect of the invention). And the water-permeable sheet 6 is addressed to the excavation side surface 1b below the underground flow water layer 4 between the H-section steels 2 and 2 where the underground water layer 4 is exposed, and the sheet pile is interposed between the H-section steels 2 and 2. 3 is inserted to support the water-permeable sheet 6 (see FIGS. 3 to 5).

前記透水性シート6は水を通すが、砂は殆ど通さない繊維材料(例えば、日大工業株式会社販売のヘチマロン(登録商標))で構成しており、矢板3と略同じ幅寸法、高さに形成している。この透水性シート6がH形鋼2、2の相互間に挿入した矢板3で押しつぶされないように、矢板3の背面に配置している。伏流水層4に到達すると、直ぐに不透水層5まで先行掘削し、掘削側面1bに透水性シート6を宛うので、伏流水層4内の伏流水は不透水層5に比べて透水性の高い透水性シート6に導かれる。そして、前記伏流水は透水性シート6を通って濾過されるので、伏流水と共に砂が流出することが殆どなく、矢板3の背面の地盤を健全に保つことができる。ちなみに、前記掘削側面1bは矢板3と透水性シート6との厚さ分だけ背面方向に掘削している。   The water-permeable sheet 6 is made of a fiber material that allows water to pass therethrough but hardly passes sand (for example, Hetimaron (registered trademark) sold by Nihon Daigyo Co., Ltd.), and has substantially the same width and height as the sheet pile 3. Is formed. The water permeable sheet 6 is arranged on the back surface of the sheet pile 3 so that it is not crushed by the sheet pile 3 inserted between the H-section steels 2 and 2. When the underground water layer 4 is reached, it immediately excavates to the impermeable layer 5 and the permeable sheet 6 is directed to the excavation side surface 1b, so that the underground water in the underground water layer 4 is more permeable than the impermeable layer 5. Guided to a high water permeable sheet 6. And since the underground water is filtered through the water-permeable sheet 6, sand hardly flows out together with the underground water, and the ground on the back surface of the sheet pile 3 can be kept healthy. Incidentally, the excavation side surface 1b is excavated in the back direction by the thickness of the sheet pile 3 and the water permeable sheet 6.

前記矢板3の前面を止水性シート7で覆う(図5等を参照)。具体的には、前記止水性シート7は通例の止水性シートと同様にポリフィルムで構成しており、矢板3より幅寸法、高さ共に一回り大きく形成している。この止水性シート3の両側部を両側のH形鋼2、2のフランジ2a、2aに接着剤(図示は省略、ガムテープ等でも可能。)で止着している。   The front surface of the sheet pile 3 is covered with a water-stop sheet 7 (see FIG. 5 and the like). Specifically, the water-proof sheet 7 is made of a poly film similarly to a normal water-proof sheet, and is formed to be slightly larger in both width and height than the sheet pile 3. Both side portions of the water-proof sheet 3 are fixed to the flanges 2a and 2a of the H-shaped steels 2 and 2 on both sides with an adhesive (not shown in the figure, and can be a gum tape or the like).

先行掘削した平面領域(以後、掘削底面1aと同じ符号を用いる。)1aを更に掘削して、矢板3の前方の掘削底部1cから同矢板3の下方を通って透水性シート6まで連続する集水溝8を形成する(請求項3記載の発明、図6及び図7を参照)。その結果、伏流水層4内の伏流水が矢板3の背面に配置した透水性シート6から、同矢板3の下方に形成した集水溝8に導かれる構成となる。この集水溝8に釜場9を形成し、同釜場9に集水してポンプ10で汲み上げる。ちなみに、前記集水溝8は伏流水を導いた際に溢れ出ない深さを有する。   A pre-excavated plane region (hereinafter, the same reference numeral as the excavation bottom surface 1a) 1a is further excavated, and a continuous collection from the excavation bottom 1c in front of the sheet pile 3 to the water permeable sheet 6 through the lower side of the sheet pile 3 A water groove 8 is formed (see the invention of claim 3, see FIGS. 6 and 7). As a result, the underground water in the underground water layer 4 is guided from the water-permeable sheet 6 disposed on the back surface of the sheet pile 3 to the water collecting groove 8 formed below the sheet pile 3. A pot 9 is formed in the water collecting groove 8, and water is collected in the pot 9 and pumped up by a pump 10. Incidentally, the water collecting groove 8 has a depth that does not overflow when the underground water is guided.

以後、掘削の進行とともに、伏流水を矢板3の背面に配置した透水性シート6から同矢板3の下方に形成した集水溝8に導く構成を段階的に盛り替え、同集水溝8に導いた伏流水を汲み上げながら、最終掘削底面の深さHまで掘削する。 Thereafter, as the excavation progresses, the structure in which underground water is led from the water-permeable sheet 6 disposed on the back surface of the sheet pile 3 to the water collecting groove 8 formed below the sheet pile 3 is gradually changed into the water collecting groove 8. while pumping the underflow water led, excavation of the final drilling bottom depth to H 1.

具体的には、釜場9から伏流水をポンプ10で汲み上げ続け、先行掘削した平面領域1a以外の平面領域1dを、集水溝8から伏流水が溢れ出さないように、同集水溝8の底面8a(釜場9より一段上の掘削底面)より高い位置まで掘削し、H形鋼2、2の相互間に矢板3を挿入する(以下、先行掘削した平面領域1a以外の平面領域1dの掘削工程と云う。図8及び図9を参照)。   More specifically, the underground water is continuously pumped up from the basin 9 by the pump 10, so that the underground water 1 d is not overflowed from the water collecting groove 8 in the flat area 1 d other than the previously excavated flat area 1 a. Is excavated to a position higher than the bottom surface 8a (excavated bottom surface one level above Kamaba 9), and a sheet pile 3 is inserted between the H-section steels 2 and 2 (hereinafter referred to as plane region 1d other than the previously excavated plane region 1a). (See FIGS. 8 and 9).

次に、釜場9から伏流水を汲み上げ続けることができるように、集水溝8を段階的に掘り下げて、盛り替えながら伏流水をポンプ10で汲み上げ続け、新たな矢板3を挿入した際に同矢板3の下方に集水溝8が形成される深さHまで到達すると、上段の透水性シート6と連続するように、H形鋼2、2の相互間の掘削側面1bに透水性シート6を宛い、前記H形鋼2、2の相互間に矢板3を挿入して前記透水性シート6を支持し、更に、同矢板3の前面を止水性シート7で覆う(以下、集水溝8の盛り替え工程と云う。図10を参照)。すなわち、矢板3の背面に配置した透水性シート6から同矢板3の下方に形成した集水溝8に導く構成を段階的に盛り替えていく。ちなみに、前記止水性シート7の上端部は上段の止水性シート7の下端部にラップさせて連続させている(図11を参照)。そのため、矢板3の前面から伏流水が漏れ出すおそれがない。 Next, in order to continue pumping underground water from Kamaba 9, the catchment channel 8 is dug down step by step, and the underground water is continuously pumped up by the pump 10 while changing the order, and a new sheet pile 3 is inserted. When reaching the depth H 3 where the water collecting groove 8 is formed below the sheet pile 3, the water permeability to the excavation side surface 1 b between the H-section steels 2, 2 is continuous with the upper water-permeable sheet 6. The sheet 6 is directed, the sheet pile 3 is inserted between the H-shaped steels 2, 2 to support the water-permeable sheet 6, and the front surface of the sheet pile 3 is covered with a water-proof sheet 7 (hereinafter referred to as “collection”). This is referred to as a refilling process of the water groove 8. See FIG. That is, the structure led from the water-permeable sheet 6 disposed on the back surface of the sheet pile 3 to the water collecting groove 8 formed below the sheet pile 3 is changed step by step. Incidentally, the upper end portion of the water-proof sheet 7 is continuously wrapped by being wrapped with the lower end portion of the upper water-proof sheet 7 (see FIG. 11). Therefore, there is no possibility that underground water leaks from the front surface of the sheet pile 3.

上記集水溝8の盛り替え工程と、先行掘削した平面領域1a以外の平面領域1dの掘削工程とを繰り返して、最終掘削底面の深さHまで掘削すると、山留め壁11の構築が完了する(請求項5記載の発明、図12を参照)。 Repeat the prime replacement process of the catchment groove 8, the planar region 1d Nonleading excavated plan area 1a and the excavation process, when digging to a depth H 1 of the final drilling bottom construction of earth retaining wall 11 is completed (See the invention according to claim 5, FIG. 12).

その後、本実施例では、集水溝8を段階的に掘り下げて、盛り替えながら伏流水を汲み上げ続け、新たな矢板3を挿入可能な深さまで到達すると、上段の透水性シート6と連続するように、H形鋼2、2の相互間の掘削側面1bに透水性シート6を宛い、前記H形鋼2、2の相互間に矢板3を挿入して前記透水性シート6を支持している(図13〜図15を参照)。このとき、透水性シート6と集水溝8とが矢板3で遮断されているが、同矢板3の前面に止水性シート7を設置していないので、伏流水は上段の矢板3との間や矢板3自身からしみ出てくるので、集水機能に問題がない。   Thereafter, in this embodiment, the water collecting groove 8 is dug stepwise, and the submerged water is continued to be pumped up while being refilled. When reaching a depth at which a new sheet pile 3 can be inserted, it continues with the upper water-permeable sheet 6. Further, the water-permeable sheet 6 is directed to the excavation side surface 1b between the H-shaped steels 2 and 2, and the sheet pile 3 is inserted between the H-shaped steels 2 and 2 to support the water-permeable sheet 6. (See FIGS. 13 to 15). At this time, the water-permeable sheet 6 and the water collecting groove 8 are blocked by the sheet pile 3, but since the water-stop sheet 7 is not installed on the front surface of the sheet pile 3, the underground water flows between the upper sheet pile 3. Because it oozes out from the sheet pile 3 itself, there is no problem in the water collecting function.

更に、前記集水溝8の釜場9に、複数の孔(図示は省略)を下部に備えた鋼管12を立設して簡易揚水井戸を形成し、同鋼管12の中に挿入したポンプ10で伏流水を汲み上げ続ける。そして、鋼管12の周辺に砕石13を敷き詰めて最終掘削底面と略等しい高さに整え、最下段直上の矢板3の前面を覆った止水性シート7の下端部と連続するように、前記砕石13の上面を隙間なく底面用止水性シート14で覆う。具体的には、底面用止水性シート14の側端部が、最下段直上の矢板3の前面を覆った止水性シート7の前面に凭れた状態でラップさせて連続させる(図16を参照)。最後に、露出する掘削底面1e及び底面用止水性シート14の上面に均しコンクリート15を打設する。   Furthermore, a pump 10 inserted into the steel pipe 12 by forming a simple pumping well by erecting a steel pipe 12 provided with a plurality of holes (not shown) at the bottom in the pot 9 of the water collecting groove 8. Continue pumping underground water. Then, the crushed stone 13 is spread around the steel pipe 12 and adjusted to a height substantially equal to the bottom surface of the final excavation, and the crushed stone 13 is continuous with the lower end portion of the water-stop sheet 7 that covers the front surface of the sheet pile 3 immediately above the lowest step. The upper surface is covered with the water-proof sheet 14 for the bottom surface without any gap. Specifically, the side end portion of the water-stop sheet 14 for the bottom surface is continuously wrapped and wrapped in the front surface of the water-stop sheet 7 that covers the front surface of the sheet pile 3 immediately above the lowest level (see FIG. 16). . Finally, the leveled concrete 15 is placed on the top surfaces of the exposed excavation bottom surface 1e and the bottom water-proof sheet 14.

上記した親杭横矢板工法は、通例の親杭横矢板工法の流れを大きく変えることなく、事後的に伏流水の処理が可能で、すなわち掘削が伏流水層4に到達すると、以後、掘削の進行とともに、伏流水を矢板3の背面に配置した透水性シート6から同矢板3の下方に形成した集水溝8に導く構成を段階的に盛り替え、同集水溝8に導いた伏流水を汲み上げながら、最終掘削底面の深さまで掘削するので、伏流水を汲み上げるための大掛かりな設備を構築したり、又は薬液を注入する必要がなくコストの削減と工期の短縮に寄与する。   The above-mentioned main pile horizontal sheet pile method can be treated afterwards without greatly changing the flow of the conventional parent pile horizontal sheet pile method, that is, when the excavation reaches the underground water layer 4, As the process progresses, the underground water is gradually changed from the water-permeable sheet 6 disposed on the back of the sheet pile 3 to the water collecting groove 8 formed below the sheet pile 3, and the underground water led to the water collecting groove 8. Since it excavates to the depth of the bottom of the final excavation while pumping up, it is not necessary to construct a large-scale facility for pumping underground water, or to inject chemicals, thereby contributing to cost reduction and shortening of construction period.

しかも、矢板3の背面に透水性シート6を配置できるスペースがあれば実施できるので、山留め壁11の背面に余裕がなくても実施可能である。   And since it can implement if there exists a space which can arrange the water-permeable sheet 6 in the back surface of the sheet pile 3, even if there is no allowance in the back surface of the mountain retaining wall 11, it can implement.

また、掘削側面1bに水は通すが、砂は殆ど通さない繊維材料で構成した透水性シート6を宛い、同透水性シート6に伏流水を通して処理するので、濾過機能が働いて伏流水と共に砂が流出することがなく、山留め壁11の背面の地盤を健全に維持しながら、伏流水の処理をすることができる。   Moreover, since the water permeable sheet 6 made of a fiber material that allows water to pass through the excavation side surface 1b but hardly penetrates sand is addressed, and the underground water is processed through the water permeable sheet 6, the filtration function works together with the underground water. The sand does not flow out, and the underground water can be treated while maintaining the ground on the back of the retaining wall 11 in a healthy state.

なお、上記実施例は平面領域1aと、同平面領域1a以外の平面領域1dとを別工程で掘削しているが、掘削中の平面領域1aと同平面領域1a以外の平面領域1dとの高低差が1m以上となる場合は、安全性を確保するために、平面領域1aの掘削と平行して、同平面領域1a以外の平面領域1dを掘削する。   In the above-described embodiment, the flat area 1a and the flat area 1d other than the flat area 1a are excavated in separate processes. However, the height of the flat area 1a being excavated and the flat area 1d other than the flat area 1a is high or low. When the difference is 1 m or more, in order to ensure safety, the flat area 1d other than the flat area 1a is excavated in parallel with the excavation of the flat area 1a.

上記実施例1は、伏流水層4の周辺の掘削底面1aの先行掘削と、集水溝8の形成とが別工程で行われているが、伏流水の流量が少ない場合は、同時に行っても良い。
即ち、掘削が伏流水層4に到達すると、露出した伏流水層4の周辺の掘削底面1aのみを、伏流水層4直下に堆積する不透水層5に到達し、且つ新たな矢板3を挿入した際に、同矢板3の下方に集水溝8が形成される深さまで先行掘削する(請求項4記載の発明)。すなわち、図6に示す形態となるように一気に先行掘削する。
In Example 1 described above, the preceding excavation of the excavation bottom surface 1a around the underground water layer 4 and the formation of the catchment groove 8 are performed in separate steps. Also good.
That is, when the excavation reaches the underground water layer 4, only the excavated bottom surface 1 a around the exposed underground water layer 4 reaches the impermeable layer 5 deposited immediately below the underground water layer 4, and a new sheet pile 3 is inserted. When this is done, a pre-excavation is performed to a depth where the water collecting groove 8 is formed below the sheet pile 3 (the invention according to claim 4). That is, the preceding excavation is performed at a stretch so as to obtain the form shown in FIG.

図7等に示した釜場9は掘削地盤1の側部に形成しているが、集水溝8を掘削地盤1の平面内方まで導き、同集水溝8に釜場9を形成しても良い(図17を参照、請求項7記載の発明)。   The pot place 9 shown in FIG. 7 and the like is formed on the side of the excavated ground 1, but the water collecting groove 8 is guided to the inside of the excavated ground 1 to form the pot place 9 in the water collecting groove 8. (Refer to FIG. 17, invention according to claim 7).

以上に本発明の実施例を説明したが、本発明はこうした実施例に何ら限定されるものではなく、本発明の要旨を逸脱しない範囲において、種々の形態で実施し得る。   Although the embodiments of the present invention have been described above, the present invention is not limited to these embodiments and can be implemented in various forms without departing from the gist of the present invention.

本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 図1のA−A矢視断面図であるIt is AA arrow sectional drawing of FIG. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 図3のB−B矢視断面図である。It is a BB arrow sectional view of Drawing 3. 矢板周辺の構造を示した断面図である。It is sectional drawing which showed the structure around a sheet pile. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 図6のC−C矢視断面図である。It is CC sectional view taken on the line of FIG. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 図8のD−D矢視断面図である。It is DD sectional view taken on the line of FIG. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 上段の止水性シートと下段の止水性シートとの連続構造を示した図である。It is the figure which showed the continuous structure of the upper water-proof sheet and the lower water-proof sheet. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の工程図である。It is process drawing of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 図13のE−E矢視断面図である。It is EE arrow sectional drawing of FIG. 本発明に係る伏流水等の処理が可能な親杭横矢板工法の最終形態を示した概略斜視図である。It is the schematic perspective view which showed the last form of the parent pile horizontal sheet pile method which can process underground water etc. which concern on this invention. 最下段直上の矢板の前面に設置された止水性シートと底面用止水性シートとの連続構造を示した図である。It is the figure which showed the continuous structure of the water-stop sheet | seat installed in the front surface of the sheet pile right above the lowest step, and the water-stop sheet for bottom faces. 本発明の異なる実施例を示した水平断面図である。It is the horizontal sectional view which showed the Example from which this invention differs.

符号の説明Explanation of symbols

1 掘削地盤
1a 伏流水層の周辺の掘削底面
1b 伏流水層以下の掘削側面
1d 先行掘削した領域以外の平面領域
2 H形鋼
3 矢板
4 伏流水層
5 不透水層
6 透水性シート
7 止水性シート
8 集水溝
9 釜場
13 砕石
14 底面用止水性シート
最終掘削底面の深さ
DESCRIPTION OF SYMBOLS 1 Excavation ground 1a Excavation bottom surface around underground water layer 1b Excavation side surface below underground water layer 1d Plane area other than prior excavation area 2 H-section steel 3 Sheet pile 4 Underflow water layer 5 Impervious layer 6 Permeability sheet 7 Sheet 8 Catchment groove 9 Kamaba 13 Crushed stone 14 Water-proof sheet for bottom surface H 1 Depth of bottom surface of final excavation

Claims (7)

伏流水等の処理が可能な親杭横矢板工法であって、
掘削地盤の周辺にH形鋼から成る親杭を、最終掘削底面の深さ以下まで打設する工程と、
掘削地盤を掘削し、掘削の進行とともに、親杭の相互間に矢板を挿入して山留めを行う工程と、
掘削が伏流水層等に到達すると、露出した伏流水層等の周辺の掘削底面のみを先行掘削し、伏流水層等以下の掘削側面に、水は通すが、砂は殆ど通さない繊維材料で構成した透水性シートを宛い、前記親杭の相互間に矢板を挿入して前記透水性シートを支持し、更に、同矢板の前面を止水性シートで覆い、伏流水等を矢板の背面に配置した透水性シートから、同矢板の下方に形成した集水溝に導く構成とし、同集水溝に導いた伏流水等を汲み上げる工程と、
以後、掘削の進行とともに、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した集水溝に導く構成を段階的に盛り替え、同集水溝に導いた伏流水等を汲み上げながら、最終掘削底面の深さまで掘削する工程と、
から成ることを特徴とする、伏流水等の処理が可能な親杭横矢板工法。
It is a parent pile horizontal sheet pile method that can treat underground water,
A process of driving a parent pile made of H-shaped steel around the excavated ground to a depth below the final excavation bottom;
Excavating the excavated ground, as the excavation progresses, inserting a sheet pile between the parent piles,
When the excavation reaches the underground water layer, etc., only the bottom surface of the surrounding area such as the exposed underground water layer is pre-excavated. Address the configured water-permeable sheet, insert a sheet pile between the parent piles to support the water-permeable sheet, and further cover the front surface of the sheet pile with a water-resistant sheet, with underground water etc. on the back surface of the sheet pile From the arranged water-permeable sheet, it is configured to guide to a water collecting groove formed below the sheet pile, and a process of pumping underground water led to the water collecting groove,
Later, as excavation progressed, the underground flow water led to the drainage channel was gradually changed from the water-permeable sheet placed on the back of the sheet pile to the drainage groove formed below the sheet pile. Drilling to the depth of the final excavation bottom,
A parent pile side sheet construction method capable of treating underground water and the like.
先行掘削は伏流水層等の下方に堆積する不透水層に到達する深さまで掘削することを特徴とする、請求項1に記載した伏流水等の処理が可能な親杭横矢板工法。   The pre-excavation excavates to a depth that reaches an impermeable layer that accumulates underneath the underground water layer or the like, and the pile piled sheet pile method capable of processing underground water or the like according to claim 1. 掘削が伏流水層等に到達した直後に形成する集水溝は、矢板の前面を止水性シートで覆った後に、先行掘削した平面領域を更に掘削して形成することを特徴とする、請求項1又は2に記載した伏流水等の処理が可能な親杭横矢板工法。   The water collecting groove formed immediately after the excavation reaches an underflow water layer or the like is formed by further excavating a plane area excavated in advance after covering the front surface of the sheet pile with a water-proof sheet. A parent pile sheet pile method capable of processing underground water or the like described in 1 or 2. 掘削が伏流水層等に到達した直後に形成する集水溝は、露出した伏流水層等の周辺の掘削底面を先行掘削すると共に形成することを特徴とする、請求項1又は2に記載した伏流水等の処理が可能な親杭横矢板工法。   The water collecting groove formed immediately after the excavation reaches the underground water layer or the like is formed by preceding excavation of the surrounding bottom surface of the exposed underground water layer or the like, and is formed according to claim 1 or 2. A parent pile sheet pile method that can treat underground water. 先行掘削した平面領域に形成した集水溝を段階的に掘り下げて、伏流水等を矢板の背面に配置した透水性シートから同矢板の下方に形成した同集水溝に導く構成を盛り替え、同集水溝に導いた伏流水等を汲み上げる工程と、集水溝に導いた伏流水等の汲み上げを続け、先行掘削した平面領域以外の平面領域を掘削する工程とを、繰り返して最終掘削底面の深さまで掘削することを特徴とする、請求項1に記載した伏流水等の処理が可能な親杭横矢板工法。   The water collecting groove formed in the flat area that was excavated in advance is dug down step by step, and the structure that guides the underground water etc. from the water-permeable sheet arranged on the back of the sheet pile to the water collecting groove formed below the sheet pile is changed. The process of pumping underground water, etc., led to the catchment groove, and the process of continuously pumping underground water, etc., led to the catchment groove, and excavating plane areas other than the previously excavated plane area are repeated. The main pile pile sheet pile method capable of treating underground water or the like according to claim 1, wherein the pile is excavated to a depth of 5 mm. 集水溝に釜場を形成しており、最終工程で集水溝を形成した後に同集水溝の釜場に簡易揚水井戸を形成して同簡易揚水井戸から伏流水等の汲み上げを続け、前記集水溝に砕石を敷き詰めて最終掘削底面と略等しい高さに整え、矢板の前面を覆った止水性シートの下端部と連続するように、敷き詰めた砕石の上面を底面用止水性シートで隙間なく覆い、露出する掘削底面及び底面用止水性シートの上面に均しコンクリートを打設することを特徴とする、請求項1又は5に記載した伏流水等の処理が可能な親杭横矢板工法。   A kettle is formed in the catchment ditch, and after the catchment groove is formed in the final process, a simple pumping well is formed in the catchment in the catchment ditch and pumping of underground water, etc. is continued from the simple pumping well. Place the crushed stone in the water collecting groove and adjust it to a height approximately equal to the bottom of the final excavation.The bottom surface of the crushed stone is covered with a water-proof sheet for the bottom so that it is continuous with the lower end of the water-proof sheet covering the front of the sheet pile. 6. The main pile lateral sheet pile capable of treating underground water or the like according to claim 1, wherein the concrete is placed on the bottom surface of the excavation bottom surface and the bottom water-proof sheet, which covers and exposes without a gap. Construction method. 集水溝を掘削地盤の平面内方まで導き、同集水溝に釜場を形成することを特徴とする、請求項6に記載した伏流水等の処理が可能な親杭横矢板工法。   The main pile side sheet pile method capable of treating underground water and the like according to claim 6, characterized in that the catchment groove is guided to the inside of the excavated ground and a pothole is formed in the catchment groove.
JP2005143690A 2005-05-17 2005-05-17 Propile pile sheet pile method capable of treating underground water Expired - Fee Related JP4532337B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005143690A JP4532337B2 (en) 2005-05-17 2005-05-17 Propile pile sheet pile method capable of treating underground water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005143690A JP4532337B2 (en) 2005-05-17 2005-05-17 Propile pile sheet pile method capable of treating underground water

Publications (2)

Publication Number Publication Date
JP2006322155A JP2006322155A (en) 2006-11-30
JP4532337B2 true JP4532337B2 (en) 2010-08-25

Family

ID=37542036

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005143690A Expired - Fee Related JP4532337B2 (en) 2005-05-17 2005-05-17 Propile pile sheet pile method capable of treating underground water

Country Status (1)

Country Link
JP (1) JP4532337B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5579530B2 (en) * 2010-08-09 2014-08-27 西松建設株式会社 Water leakage treatment method for earth retaining wall
JP6476450B2 (en) * 2015-01-30 2019-03-06 大成建設株式会社 Method of retaining the ceiling part of the widened part and method of widening the underground part
JP6461886B2 (en) * 2016-10-27 2019-01-30 株式会社イザキ Construction method of underground concrete structure and underground concrete structure
CN114855821B (en) * 2022-05-27 2023-10-13 广东南方建设集团有限公司 Foundation pit reinforcing system of sponge foundation and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11247195A (en) * 1998-03-05 1999-09-14 Nabco System Kk Temporary earth retaining wall structure and temporary earth retaining wall execution method
JP2000008394A (en) * 1998-06-24 2000-01-11 Nabco System Kk Construction method for underground structure such as underground pit for installation of parking lot
JP2003206539A (en) * 2002-01-11 2003-07-25 Hirose & Co Ltd Temporary closing construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11247195A (en) * 1998-03-05 1999-09-14 Nabco System Kk Temporary earth retaining wall structure and temporary earth retaining wall execution method
JP2000008394A (en) * 1998-06-24 2000-01-11 Nabco System Kk Construction method for underground structure such as underground pit for installation of parking lot
JP2003206539A (en) * 2002-01-11 2003-07-25 Hirose & Co Ltd Temporary closing construction method

Also Published As

Publication number Publication date
JP2006322155A (en) 2006-11-30

Similar Documents

Publication Publication Date Title
US7972080B2 (en) Bank-sided porosity storage reservoirs
JP5291927B2 (en) Fresh water storage and intake system
JP5430783B2 (en) Fresh water storage system
JP2006226061A (en) Underground drainage construction method
JP4532337B2 (en) Propile pile sheet pile method capable of treating underground water
JP5628014B2 (en) Impermeable wall structure
JP5016517B2 (en) Groundwater level lowering method
CN107100206A (en) A kind of prevention and controls of basement leakage
JP5070694B2 (en) Containment method for contaminated soil and groundwater
KR20120021802A (en) Method and structure for getting underground water
JP6782404B2 (en) Groundwater level lowering method, groundwater drainage channel construction method and groundwater drainage channel structure
KR102237058B1 (en) Construction method of synthetic piles for water barriers in rock layers
JP6441692B2 (en) Underground structure with flood control function and its construction method
JP2005090015A (en) Ground excavating method
JP2005344397A (en) Underground water control method for basement construction
JP2003053317A (en) Underground water drainage structure of original position confinement construction method
KR101699877B1 (en) System for salt removal of earth in the designated district of reclaimed land with desalinated water supply and method for de-salt using the system
KR101523367B1 (en) Method of dewatering for Landfill by directional drilling
CN211006700U (en) Foundation ditch flowing water lateral wall drainage protects structure
CN220868271U (en) Foundation pit dewatering structure suitable for under rich water stratum condition
KR101220898B1 (en) Method for constructing the sheet pile using foaming block
JP7074655B2 (en) How to build a retaining wall on a slope and how to build a waste disposal site on a slope
JP2000064326A (en) Caisson for underground structure construction
JP3700121B2 (en) Water blocking wall under culvert and its construction method
JP4322629B2 (en) Waste disposal site

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080326

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100428

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100525

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100610

R150 Certificate of patent or registration of utility model

Ref document number: 4532337

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130618

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees