JP2002121755A - Composite waterproof method for underground structure - Google Patents

Composite waterproof method for underground structure

Info

Publication number
JP2002121755A
JP2002121755A JP2000318464A JP2000318464A JP2002121755A JP 2002121755 A JP2002121755 A JP 2002121755A JP 2000318464 A JP2000318464 A JP 2000318464A JP 2000318464 A JP2000318464 A JP 2000318464A JP 2002121755 A JP2002121755 A JP 2002121755A
Authority
JP
Japan
Prior art keywords
box
ground
waterproof
reinforced concrete
wall surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000318464A
Other languages
Japanese (ja)
Other versions
JP3530128B2 (en
Inventor
Koichi Terada
晃一 寺田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2000318464A priority Critical patent/JP3530128B2/en
Publication of JP2002121755A publication Critical patent/JP2002121755A/en
Application granted granted Critical
Publication of JP3530128B2 publication Critical patent/JP3530128B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a composite waterproof method for an underground structure which can be easily constructed at a low cost only by building the structure of reinforced concrete on the ground and settling the structure by using a special submerged caisson method, and perform repair treatment of weak elements remaining in a skeleton during the construction before submergence and waterproof treatment on an external wall surface, and completely regulate water infiltration from a bottom part after submergence. SOLUTION: In this composite waterproof method for the underground structure, a caisson having no top or bottom is constructed of reinforced concrete with waterproof material mixed therein on the predetermined ground, weak elements remaining in the skeleton during the construction are repaired, the external wall surface is primer- treated, the caisson body is submerged to a desired bearing ground by repeating excavation of an inner bottom of the bearing ground and settlement by the self weight, aggregates are filled in the inner bottom of the bearing ground, a reinforced concrete floor layer with waterproof material is formed on the filled aggregates via a waterproof film, and permeable waterproof paint is applied to and infiltrated in an internal wall surface of the caisson body including the floor layer. When submerging the caisson body constructed on the ground by the submerged caisson method, high strength correction and high waterproof are performed before and after the submergence.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、所定の地面上の作
業にて強化コンクリートにより天井、底のない函体を建
造し、該函体をその自重により所望の支持地盤まで潜函
させて地下室等の地下構造物を構築するに際し、潜函さ
せようとする函体の躯体の強度及び躯体自身の高い防水
性、防水床層の形成、土中からの浸透水の遮断など地下
構造物に係わる複合防水工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a box having no ceiling or bottom with reinforced concrete by working on a predetermined ground, and submerging the box to a desired supporting ground by its own weight, for example, in a basement. When constructing an underground structure, the composite waterproofing related to the underground structure such as the strength of the body of the box to be hidden and the high waterproofness of the body itself, the formation of a waterproof floor layer, the blocking of seepage water from the soil It concerns the construction method.

【0002】[0002]

【従来の技術】土地の狭い我が国では、地価が高いこと
から、住宅建設に際して居住部分として地下室の要望が
高い。地下室は娯楽室やオーディオルーム、ピアノ等の
楽器の練習室等、近所に遠慮なく音が出せる部屋として
理想だからである。我が国の建築基準法では以前には地
下室を居住とするときは必ず部屋の前面に“からぼり”
を設けることが必要であったが、平成10年の建設省の
通達により全く地下に潜った窓のない地下室も居住とし
て認められるようになっている。尤も、地下室は全ての
部屋数の1/4という制約はあるが、地下室には、“保
温性”“遮音性”などの特性があるため、今後、益々そ
の要望は高くなるものと思われる。
2. Description of the Related Art In Japan, where land is small, land prices are high, and there is a high demand for basements as living parts when constructing houses. This is because the basement is ideal as an entertainment room, an audio room, a practice room for musical instruments such as pianos, and a room where sounds can be freely output to the neighborhood. According to the Building Standards Law of Japan, when a basement was previously occupied, the "room" was always in front of the room.
It was necessary to establish a basement, but according to a notice of the Ministry of Construction in 1998, a basement with no windows that went underground at all was recognized as habitable. Although the basement is limited to 1/4 of the total number of rooms, the basement has characteristics such as "heat insulation" and "sound insulation", and it is expected that the demand will be further increased in the future.

【0003】一般に、地下室付き住宅建設において、地
下室部分の構築には大別して次の三つの方法が知られて
いた。即ち、は地下室となる函体の体積(高さ×面
積)を予め画定し、該画定した函体の体積に相当する空
間と該空間の周囲に作業空間が形成できるような縦穴
を、土留め壁を構築しつつ掘り下げ、該縦穴内において
前記地下室構造体を建造する方法、はと同様に土留
め壁を構築しつつ掘り下げた縦穴内に、他の場所(例え
ば工場など)で建造して運び込んできた地下室構造体を
クレーン等の機械にて吊り上げて埋設する方法、は既
製の建造物をジャッキ等の架設具にて保持し、その保持
地盤を徐々に掘り下げつつ建造物を潜函させる方法であ
る。
In general, in the construction of a basement-equipped house, the following three methods have been known for the construction of the basement. That is, the volume (height x area) of the box that will become the basement is defined in advance, and a space corresponding to the volume of the defined box and a vertical hole that can form a working space around the space are retained. A method of digging down while constructing a wall and constructing the basement structure in the vertical hole is the same as the method of constructing a retaining wall and carrying it in another place (for example, a factory) in the digging down the vertical hole. The method of lifting and burying the resulting basement structure with a machine such as a crane is a method of holding a ready-made building with a mounting tool such as a jack and digging the building while gradually digging down the holding ground. .

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記
場合には、掘り下げた縦穴内での強化コンクリートによ
る地下室構造体の建造には、建造物と土留め壁との間の
作業空間が狭く困難さが伴ったばかりでなく、土留め壁
の形成に際し、H鋼材や鉄道レールなどの打ち込み位置
を、隣接地の境界から手前側(自敷地側)に相当長入っ
た処に設定しなければならず、敷地を地下室設置のため
に広く活用することが困難であった。
However, in the above case, it is difficult to construct a basement structure with reinforced concrete in a dug down hole because the working space between the building and the retaining wall is narrow. Not only that, when forming the retaining wall, the driving position of H steel material and railway rails, etc., must be set at a place that is considerably long from the boundary of the adjacent land to the near side (own site side), It was difficult to widely use for the basement installation.

【0005】また、上記の場合には、土留め壁の構築
には上記の欠点を備えるほか、他の場所から運び込ん
できた地下室構造体はクレーン等の機械によって吊り上
げることのできる大きさに限られていたし、クレーン等
の機械自身の設置場所が確保できずに建設できないこと
もあった。
[0005] In the above case, the construction of the retaining wall has the above-mentioned disadvantages, and the basement structure carried from another place is limited to a size that can be lifted by a machine such as a crane. In some cases, construction was not possible due to the lack of a place to install machines such as cranes.

【0006】さらに、上記の場合には、潜函時に多数
のジャッキ等の架設具や多数の実働作業人員が必要であ
り、この方法で地下室構造体を潜函させるには建設コス
トが高くなるという問題があった。
Further, in the above case, a large number of jacks and other erection tools and a large number of working workers are required when submerging, and the submersion of the basement structure by this method increases the construction cost. there were.

【0007】さらにまた、上記何れの方法によるかを問
わず、地下室となる地下構造物は躯体の強度や躯体自身
の防水性が充分でないという問題もあった。
Further, regardless of which of the above methods, there is a problem that the strength of the skeleton and the waterproofness of the skeleton itself are not sufficient for the underground structure serving as the basement.

【0008】本発明は上記の種々の問題点を解決するた
めのもので、その目的とするところは、特異な潜函工法
を用い、地上にて強化コンクリートにて建造して沈下さ
せるのみで簡易にしかも低コストで構築でき、しかも、
潜函前には建造時に躯体に残る虚弱要素の修正処理と外
壁面への防水性処理、潜函後には底部及び周囲からの浸
透水の完璧なる規制ができるようにした地下構造物に係
わる複合防水工法を提供することにある。
The present invention has been made to solve the above-mentioned various problems, and an object of the present invention is to use a unique latent box construction method, simply build and reinforce reinforced concrete on the ground, and simply settle it. Moreover, it can be built at low cost, and
Before submersion, a composite waterproofing method for underground structures that corrects the weak elements remaining in the building during construction and waterproofs the outer wall surface, and after the submersion allows perfect control of seepage water from the bottom and surroundings Is to provide.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するた
め、本発明に係る地下構造物に係わる複合防水工法は、
所定の地面上で防水材を混入した強化コンクリートによ
り天井、底のない函体を建造し、該建造時に躯体に残る
虚弱要素を修正処理し、かつ、外壁面にプライマー処理
層を施した後、前記函体をその内底部の掘り下げと自重
沈下との繰り返しにより所望の支持地盤まで潜函させ、
該支持地盤の内底部に骨材を中詰し、該中詰骨材上に防
水性フィルムを介して防水材入り強化コンクリート床層
を形成し、該床層を含む函体の内壁面に浸透性防水塗料
を塗布浸透させることを特徴とし、地上作業にて建造し
た函体を潜函工法により沈めるに際し、潜函前と潜函後
に高い強度補正と高い防水性が施せるように構成した。
To achieve the above object, a composite waterproofing method for an underground structure according to the present invention comprises:
A ceiling, a bottomless box is built with reinforced concrete mixed with waterproofing material on the predetermined ground, and the weak elements remaining in the building at the time of the construction are corrected, and after applying a primer treatment layer to the outer wall surface, The box is buried down to the desired supporting ground by repetition of digging down its inner bottom and subsidence,
An aggregate is filled in the inner bottom of the supporting ground, a reinforced concrete floor layer containing a waterproof material is formed on the filled aggregate through a waterproof film, and penetrates into an inner wall surface of a box including the floor layer. It is characterized by applying and infiltrating a waterproof coating, so that when submerging a box built by ground work using the submersion method, high strength correction and high waterproofness can be applied before and after the submarine.

【0010】また、請求項2に記載の発明に係る地下構
造物に係わる複合防水工法は、前記支持地盤まで沈下さ
せた函体の外周囲を掘り下げ、該掘り下げ部に締まり性
のよい土壌を入れて填圧することを特徴とし、函体の周
囲に浸透水の遮断層が得られるように構成した。
In the composite waterproofing method for an underground structure according to the second aspect of the present invention, the outer periphery of the box submerged to the supporting ground is dug down, and soil having good tightness is put into the dug-down portion. It was constructed so that a barrier layer for permeated water could be obtained around the box.

【0011】[0011]

【発明の実施の態様】次に、本発明の実施の態様を図1
〜図6に基づいて説明する。図1は地上にて函体を建造
するに際し、型枠を組んで強化コンクリートを打設して
いる状態を示す断面図、図2は強化コンクリートの固化
養生後、型枠を外した時に残る虚弱要素を修正処理し、
外壁面にプライマー処理層を施した躯体の部分断面図、
図3は地上にて建造した函体の潜函開始時の断面図、図
4は潜函過程を示す断面図、図3は潜函終了時の断面
図、図4は床層の形成と浸透性防水塗料の作業及び函体
の外周囲の仕上げ後の状態を示す断面図である。
FIG. 1 shows an embodiment of the present invention.
This will be described with reference to FIG. FIG. 1 is a cross-sectional view showing a state in which a form is assembled and a reinforced concrete is cast when constructing a box on the ground. FIG. 2 is a weakness remaining when the form is removed after the reinforced concrete is cured and cured. Modify the element,
Partial cross-sectional view of the skeleton with a primer treatment layer applied to the outer wall surface,
FIG. 3 is a cross-sectional view of the box built on the ground at the start of the submersion, FIG. 4 is a cross-sectional view showing the submerging process, FIG. 3 is a cross-sectional view of the submarine at the end of the submersion, and FIG. FIG. 6 is a cross-sectional view showing a state after finishing the work of FIG.

【0012】1は潜函しようとする函体2を、所定の地
面G上において建造するために組んだ型枠であって、該
型枠1は函体2の内壁面を構成する内枠1aと、函体2
の外壁面を構成する外枠1bとをボルト1cにより連結
してなる。なお、前記所定の地面Gは、予め、50〜6
0cm程の深さの口掘り部Kを設ける。これは前記函体
2の潜函に際して沈下量を少なくする上に有効である。
この口掘り部Kの形成には土留め壁を形成する必要はな
い。
Reference numeral 1 denotes a mold formed by assembling a box 2 to be submerged on a predetermined ground G. The mold 1 includes an inner frame 1a forming an inner wall surface of the box 2 and , Box 2
And an outer frame 1b constituting an outer wall surface of the vehicle is connected by bolts 1c. The predetermined ground G is 50 to 6 in advance.
A digging portion K having a depth of about 0 cm is provided. This is effective in reducing the amount of settlement when the box 2 is submerged.
It is not necessary to form an earth retaining wall for forming the digging portion K.

【0013】3は前記型枠1の内外枠1aと1b間に、
コンクリートミキサー車両等の供給源(図示せず)に連
通したノズル4を通して流入させた防水材入り強化コン
クリートである。この強化コンクリートに混入した防水
材として特に限定しないが、例えば、ナルファルドC<
成瀬化学株式会社製>を使用して満足できる。
Reference numeral 3 denotes a space between the inner and outer frames 1a and 1b of the mold 1
It is a reinforced concrete containing a waterproof material which flows in through a nozzle 4 communicating with a supply source (not shown) of a concrete mixer vehicle or the like. Although there is no particular limitation on the waterproofing material mixed into the reinforced concrete, for example, Narfardo C <
Made by Naruse Chemical Co., Ltd.>

【0014】上述の如く、防水材入り強化コンクリート
3の固化、養生後、型枠1を外すことにより、図3の如
く、天井、底のない側壁のみの函体2が建造される。こ
こに使用の強化コンクリートは、繊維補強コンクリート
でも、鉄筋コンクリートでもよいが、強度は270kg
/cm2 以上であることを要する。
As described above, after the reinforced concrete 3 containing the waterproof material is solidified and cured, the mold 1 is removed to construct the box 2 having only the ceiling and the bottom side wall as shown in FIG. The reinforced concrete used here may be fiber reinforced concrete or reinforced concrete, but the strength is 270 kg.
/ Cm 2 or more.

【0015】前記函体2の躯体には、型枠1を外したと
きに虚弱要素(例えば、ボルト穴や剥げ部、或いは固
化、養生時に生じる収縮による亀裂等)が残ることか
ら、これを図2の如く修正処理(ピーコン処理、モルタ
ル埋め)5a、5bするほか、外壁面にプライマー処理
層(例えば、防水アスファルトの塗布層)6を設ける等
の複合防水化処理を施すことが重要である。
When the mold 1 is removed, weak elements (for example, bolt holes and stripped portions, or cracks due to shrinkage generated during solidification and curing) remain in the body of the box 2. It is important to carry out a composite waterproofing treatment such as providing a primer treatment layer (for example, a coating layer of waterproof asphalt) 6 on the outer wall surface in addition to the correction treatment (peacon treatment, mortar filling) 5a and 5b as in 2.

【0016】次に、建造後の函体2の内底部の地面(土
壌)をパワーショベル等の機械7を用いて(手掘りも
可)掘り下げ、排出した土砂を函体外へ搬出する。この
掘り下げにより函体2は図4の如く自重により沈下する
こととなる。
Next, the ground (soil) at the inner bottom of the box 2 after being built is dug down by using a machine 7 such as a power shovel (hand digging is also possible), and the discharged earth and sand is carried out of the box. As a result of this digging, the case 2 sinks by its own weight as shown in FIG.

【0017】前記函体2の自重沈下は、数センチ(ほぼ
5〜8cm程)づつ行われる。函体2内の地面を掘り下
げてから、函体2の側壁下面を支えている地盤を数セン
チ幅に環状に除去する。これにより、函体2はその除去
分だけ沈下する。この側壁下面の地盤の除去は、手順と
しては半周分づつ行うこととなる。即ち、水平状態にあ
る函体2の側壁下面の地盤をほぼ半周分除去すると、函
体2は支えを失い傾くように自重沈下する。そして、残
りの半周分を除去すると傾いていた函体2は水平に戻る
ように自重沈下する。これをワンサイクルとして繰り返
すことにより函体2は順次沈下する。この自重沈下の過
程で函体2の水平度はトランシット等の器具を使って適
時確認し、必要があれば微調整する。
The lowering of the weight of the box 2 is performed several centimeters (approximately 5 to 8 cm). After digging down the ground in the box 2, the ground supporting the lower surface of the side wall of the box 2 is removed in a ring having a width of several centimeters. Thereby, the box 2 sinks by the removed amount. The removal of the ground on the lower surface of the side wall is performed by half a round as a procedure. That is, when the ground on the lower surface of the side wall of the box 2 in the horizontal state is removed by almost a half turn, the box 2 loses its support and sinks under its own weight so as to tilt. When the remaining half circumference is removed, the box 2 that has been inclined sinks under its own weight so as to return to horizontal. By repeating this as one cycle, the box 2 sinks sequentially. During the process of subsidence by its own weight, the level of the box 2 is checked at appropriate times using instruments such as transit, and fine adjustment is made if necessary.

【0018】前記函体2の潜函に際し、3人程度の作業
者数で時間当たり80mm程度を沈下(潜函)させるこ
とは可能である。従って、今、例えば、2700mmの
高さを有する函体を地上で建造し、これをその上側が地
面Gに対して1000mm分だけ残るように潜函(17
00mm分を沈下)させる場合において、これに掛かる
時間は、実働8時間/1日として約2.6日間という短
時間で完了することとなる。
When the box 2 is submerged, it is possible to sink (submerge) about 80 mm per hour with about three workers. Therefore, now, for example, a box having a height of 2700 mm is built on the ground, and the sub-box (17
In the case of subsidence for 00 mm), the time required for this is completed in a short time of about 2.6 days as 8 hours / day of actual operation.

【0019】かくして、前記函体2が、自重沈下と地面
の掘り下げとの繰り返しにより、図5の如く、所望の支
持地盤G′まで到達すると、その後は内底部に玉石や砕
石等の骨材8を中詰めする。この中詰めに当たり、骨材
8に填圧を加えて平に均す。この填圧作業は地下室の基
礎(支持地盤を強化すること)となることから重要であ
り、また、床面の仕上がりを良好にするためにも重要で
ある。
Thus, when the box 2 reaches the desired supporting ground G 'as shown in FIG. 5 by repeating the sinking of its own weight and the digging of the ground, the aggregates 8 such as boulders and crushed stones are then placed on the inner bottom. To fill. At the time of this filling, a pressure is applied to the aggregate 8 to level it out. This pressurization work is important because it becomes the foundation of the basement (strengthening the supporting ground), and is also important for improving the finish of the floor surface.

【0020】前記骨材8の中詰め後、その中詰骨材8の
上面に、図6の如く、防水性フィルム9を敷き、その上
に、鉄筋(図示せず)を配して防水材を混入した強化コ
ンクリート床層10を形成する。なお、前記防水性フィ
ルム9は、函体2の底面側からの浸透水を完全に遮断す
るために有効なものである。この防水性フィルム9には
プラスチックシート(例えば、0.1mm厚のポリプロ
ピレンシート)を使用して満足できる。
After the packing of the aggregate 8, the waterproof film 9 is laid on the upper surface of the packing 8 as shown in FIG. 6, and a reinforcing steel bar (not shown) is disposed thereon. To form a reinforced concrete floor layer 10 containing The waterproof film 9 is effective for completely shutting off permeated water from the bottom surface of the box 2. It is satisfactory to use a plastic sheet (for example, a 0.1 mm thick polypropylene sheet) for the waterproof film 9.

【0021】前述の如く、函体2の底部の強化コンクリ
ート床層10が完成し、固化させ、養生させた後、該強
化コンクリート床層6を含む函体2の内壁面には吹付塗
布手段11を使用して浸透性防水塗料を吹付塗布する。
この塗料はコンクリート系の構造物の躯体中に浸透して
水分の浸透を確実に防止(シャットアウト)する機能を
備える。なお、前記塗料として無機質浸透性防水塗料
(ソロシール<エヌケー化研株式会社製>)を用いると
耐久性に優れ、より好ましい。
As described above, after the reinforced concrete floor layer 10 at the bottom of the box 2 is completed, solidified and cured, the spray coating means 11 is applied to the inner wall surface of the box 2 including the reinforced concrete floor layer 6. Spray the permeable waterproof paint using.
This paint has a function of infiltrating into the skeleton of a concrete structure to surely prevent (shut out) moisture from penetrating. In addition, it is more preferable to use an inorganic permeable waterproof paint (Solo Seal <manufactured by NK Kaken Co., Ltd.>) as the paint because of excellent durability.

【0022】前記函体2を所望の支持地盤G′まで到達
させ、更に、函体底部の強化コンクリート床層10を完
成させたならば、該函体2の外周囲を縦穴状に掘り下
げ、この掘り下げ部に締まり性のよい土壌(粒子が細か
く団粒をつくり易い土壌=例えば、赤土などの粘度質の
土)を入れ、填圧して填圧層12を形成する。この填圧
層12は地表からの雨水の浸透をなくすとともに、土中
に浸透した雨水が側面より浸透することを避けるために
有効である。なお、掘り下げ幅W及び深さFは任意に決
定できる。なお、掘り下げ幅Wについては50〜60c
m、深さFは地表から函体の2/3程度あれば充分であ
る。
After the box 2 has reached the desired supporting ground G 'and the reinforced concrete floor layer 10 at the bottom of the box 2 has been completed, the outer periphery of the box 2 is dug down into a vertical hole. Soil with good compaction (soil with fine particles and easy to form aggregates =, for example, viscous soil such as red soil) is put into the dug-down portion, and pressure is applied to form a pressure-filled layer 12. The pressurized layer 12 is effective for eliminating the penetration of rainwater from the ground surface and for preventing the rainwater that has penetrated into the soil from penetrating from the side surface. In addition, the dug width W and the depth F can be arbitrarily determined. In addition, about 50-60c about digging width W
It is sufficient that m and the depth F are about 2/3 of the box from the ground surface.

【0023】前記函体2の潜函終了後、地表より露出し
ている函体2の上部外面は必要な外装材が施されるとと
もに、上面には住宅の土台(上床)が強化コンクリート
により形成されることとなる。
After the completion of the subcasing of the case 2, the necessary outer materials are applied to the upper outer surface of the case 2 exposed from the ground surface, and the base (upper floor) of the house is formed of reinforced concrete on the upper surface. The Rukoto.

【0024】[0024]

【発明の効果】以上の如く、本発明に係る地下構造物に
係わる複合防水工法は、所定の地面上で防水材を混入し
た強化コンクリートにより天井、底のない函体を建造
し、該建造時に躯体に残る虚弱要素を修正処理し、か
つ、外壁面にプライマー処理層を施した後、前記函体を
その内底部の掘り下げと自重沈下との繰り返しにより所
望の支持地盤まで潜函させ、該支持地盤の内底部に骨材
を中詰し、該中詰骨材上に防水性フィルムを介して防水
材入り強化コンクリート床層を形成し、該床層を含む函
体の内壁面に浸透性防水塗料を塗布浸透させることを特
徴としているから、地上作業にて得た函体を、クレーン
等の機械やジャッキ等の架設具を使用せずに簡易に潜函
させることができる。しかも、H鋼材や鉄道レールなど
を打ち込んで土留め壁を構築する必要がなく、少労力、
短時間で効率よく地下構造物が構築できるとともに、地
下室構造体の大きさや設置場所を選ばず、敷地を地下室
設置のために広く活用できる上に、躯体の強度及び防水
性に優れた地下構造物を得ることができるなど、各種の
優れた効果を奏するものである。
As described above, the composite waterproofing method for an underground structure according to the present invention constructs a box without a ceiling and a bottom on a predetermined ground by using reinforced concrete mixed with a waterproof material. After correcting the weak elements remaining in the skeleton, and applying a primer treatment layer on the outer wall surface, the box is sunk to the desired support ground by repetition of digging down the inner bottom and sinking by its own weight, and The inner bottom is filled with aggregate, a reinforced concrete floor layer containing a waterproof material is formed on the filled aggregate through a waterproof film, and a permeable waterproof paint is applied to the inner wall surface of the box including the floor layer. Since it is characterized by applying and infiltrating, a box obtained by ground work can be easily hidden without using a machine such as a crane or an installation tool such as a jack. In addition, there is no need to drive H steel or railroad rails to build earth retaining walls.
In addition to being able to construct underground structures efficiently in a short period of time, the basement can be widely used for installing basements regardless of the size and location of the basement structure, and the underground structure has excellent structural strength and waterproofness And various other excellent effects can be obtained.

【0025】また、請求項2に記載の発明に係る地下構
造物に係わる複合防水工法は、前記支持地盤まで沈下さ
せた函体の外周囲を掘り下げ、該掘り下げ部に締まり性
のよい土壌を入れて填圧することを特徴としているか
ら、函体の周囲に浸透水の遮断層が得られ一層の防水効
果が得られるという優れた効果を奏するものである。
In the composite waterproofing method for an underground structure according to the second aspect of the present invention, the outer periphery of the box submerged to the supporting ground is dug down, and soil having good tightness is put into the dug-down portion. Since it is characterized by pressurizing, a barrier layer for permeated water is obtained around the box, and an excellent effect of obtaining a further waterproof effect can be obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】地上にて函体を建造するに際し、型枠を組んで
強化コンクリートを打設している状態を示す断面図であ
る。
FIG. 1 is a cross-sectional view showing a state where a reinforced concrete is cast in a formwork when constructing a box on the ground.

【図2】強化コンクリートの固化養生後、型枠を外した
ときに残る虚弱要素を修正処理し、外壁面にプライマー
処理層を施した躯体の部分断面図である。
FIG. 2 is a partial cross-sectional view of a skeleton obtained by correcting a weak element remaining when a form is removed after solidification and curing of reinforced concrete, and applying a primer treatment layer to an outer wall surface.

【図3】地上にて建造した函体の潜函開始時の断面図で
ある。
FIG. 3 is a cross-sectional view of a box built on the ground at the start of a submarine box.

【図4】函体の潜函過程を示す断面図である。FIG. 4 is a cross-sectional view showing the submerging process of the box.

【図5】函体の潜函終了時の断面図である。FIG. 5 is a cross-sectional view of the box at the end of the latent box.

【図6】函体の床部及び外周部の仕上げ後の断面図であ
る。
FIG. 6 is a sectional view after finishing the floor portion and the outer peripheral portion of the box.

【符号の説明】[Explanation of symbols]

1 型枠 1a 内枠 1b 外枠 1c ボルト 2 函体 3 防水材入り強化コンクリート 4 ノズル 5a、5b 修正処理部 6 プライマー処理層 7 パワーショベル等の機械 8 玉石や砕石等の骨材 9 防水性フィルム 10 強化コンクリート床層 11 吹付塗布手段 12 填圧層 G 地下室を建設しようとする所定の地面 G′所望する支持地盤 K 口掘り部 W 掘り下げ幅 F 掘り下げ深さ DESCRIPTION OF SYMBOLS 1 Form frame 1a Inner frame 1b Outer frame 1c Bolt 2 Box 3 Reinforced concrete with waterproofing material 4 Nozzle 5a, 5b Correction processing part 6 Primer treatment layer 7 Machine such as power shovel 8 Aggregate such as cobblestone and crushed stone 9 Waterproof film DESCRIPTION OF SYMBOLS 10 Reinforced concrete floor layer 11 Spray application means 12 Packing layer G Predetermined ground on which a basement is to be constructed G 'Desired support ground K Drilling part W Drilling width F Drilling depth

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 所定の地面上で防水材を混入した強化コ
ンクリートにより天井、底のない函体を建造し、該建造
時に躯体に残る虚弱要素を修正処理し、かつ、外壁面に
プライマー処理層を施した後、前記函体をその内底部の
掘り下げと自重沈下との繰り返しにより所望の支持地盤
まで潜函させ、該支持地盤の内底部に骨材を中詰し、該
中詰骨材上に防水性フィルムを介して防水材入り強化コ
ンクリート床層を形成し、該床層を含む函体の内壁面に
浸透性防水塗料を塗布浸透させることを特徴とする地下
構造物に係わる複合防水工法。
1. A box having no ceiling or bottom made of reinforced concrete mixed with a waterproof material on a predetermined ground, correcting weak elements remaining in the body at the time of the building, and applying a primer treatment layer on an outer wall surface. After carrying out, the box is buried to a desired supporting ground by repeating the digging of its inner bottom and the sinking of its own weight, and the inner bottom of the supporting ground is filled with aggregate, and the box is filled with aggregate. A composite waterproofing method for an underground structure, wherein a reinforced concrete floor layer containing a waterproof material is formed via a waterproof film, and a permeable waterproof paint is applied to the inner wall surface of the box including the floor layer and penetrated.
【請求項2】 前記支持地盤まで沈下させた函体の外周
囲を掘り下げ、該掘り下げ部に締まり性のよい土壌を入
れて填圧することを特徴とする請求項1に記載の地下構
造物に係わる複合防水工法。
2. The underground structure according to claim 1, wherein the outer periphery of the box submerged to the supporting ground is dug down, and soil having good tightening properties is put into the dug-down portion to pressurize. Composite waterproofing method.
JP2000318464A 2000-10-18 2000-10-18 Composite waterproofing method for underground structures Expired - Fee Related JP3530128B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000318464A JP3530128B2 (en) 2000-10-18 2000-10-18 Composite waterproofing method for underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000318464A JP3530128B2 (en) 2000-10-18 2000-10-18 Composite waterproofing method for underground structures

Publications (2)

Publication Number Publication Date
JP2002121755A true JP2002121755A (en) 2002-04-26
JP3530128B2 JP3530128B2 (en) 2004-05-24

Family

ID=18797086

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000318464A Expired - Fee Related JP3530128B2 (en) 2000-10-18 2000-10-18 Composite waterproofing method for underground structures

Country Status (1)

Country Link
JP (1) JP3530128B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020037844A (en) * 2018-03-03 2020-03-12 三和コンクリート工業株式会社 Underground shelter and installation method therefor
CN108643230B (en) * 2018-06-12 2023-08-22 五冶集团上海有限公司 Outer waterproof structure of underground comprehensive pipe rack and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020037844A (en) * 2018-03-03 2020-03-12 三和コンクリート工業株式会社 Underground shelter and installation method therefor
JP7107564B2 (en) 2018-03-03 2022-07-27 三和コンクリート工業株式会社 Underground shelter and its installation method
CN108643230B (en) * 2018-06-12 2023-08-22 五冶集团上海有限公司 Outer waterproof structure of underground comprehensive pipe rack and construction method

Also Published As

Publication number Publication date
JP3530128B2 (en) 2004-05-24

Similar Documents

Publication Publication Date Title
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
US7500807B2 (en) Method of construction using sheet piling sections
CN102444143A (en) Construction method for cancelling operation channel for facades of basement
CN108385612B (en) Construction method of concrete protective panel with good stability
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
JP3530128B2 (en) Composite waterproofing method for underground structures
CN108149707A (en) A kind of basement building structure and its construction method
CN211421139U (en) Shield constructs well crown beam bearing structure
CN210315908U (en) Immersed tube type inspection well
CN207891910U (en) A kind of basement building structure
JPH09316894A (en) Bridge pier foundation structure, and construction method thereof
JP3566644B2 (en) Submersion method
KR200291370Y1 (en) Concrete caisson structure for earth and sand guard of pier&#39;s basis
JP2015110871A (en) Caisson immersion method and underground column body group
KR200224758Y1 (en) Structure of caisson soil protection four concret caisson
JPH116164A (en) Construction method for underground structure
JP4132320B2 (en) Foundation construction method
JP2011236666A (en) Building method of protection concrete body for septic tank
KR102608696B1 (en) Reinforcing frame for repairing cracked road surface or subsidence ground and method for repairing cracked road surface or subsidence ground using the reinforcing frame
JPH09242091A (en) Construction method for underground structure
CN107964958A (en) A kind of deep foundation pit precast overlaps pile construction method
JP2796591B2 (en) Water tank bottom plate mounting structure
JPH09279609A (en) Building method of precast reinforced concrete-made underground structure
JP3656366B2 (en) Underground structure construction method
JP2001323485A (en) Method of constructing underground structure

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040127

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040226

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090305

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100305

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110305

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130305

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140305

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees