JP3566644B2 - Submersion method - Google Patents
Submersion method Download PDFInfo
- Publication number
- JP3566644B2 JP3566644B2 JP2000318463A JP2000318463A JP3566644B2 JP 3566644 B2 JP3566644 B2 JP 3566644B2 JP 2000318463 A JP2000318463 A JP 2000318463A JP 2000318463 A JP2000318463 A JP 2000318463A JP 3566644 B2 JP3566644 B2 JP 3566644B2
- Authority
- JP
- Japan
- Prior art keywords
- box
- ground
- basement
- reinforced concrete
- digging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、所定の地面上の作業にて天井、底のない函体(地下室構造物)を強化コンクリートにより建造し、その函体をジャッキ等の架設具やクレーン等の機械を使用しないで自重により所望の支持地盤まで沈下させることのできる新規な潜函工法に関するものである。
【0002】
【従来の技術】
土地の狭い我が国では、地価が高いことから、住宅建設に際して居住部分として地下室の要望が高い。地下室は娯楽室やオーディオルーム、ピアノ等の楽器の練習室等、近所に遠慮なく音が出せる部屋として理想だからである。我が国の建築基準法では以前には地下室を居住とするときは必ず部屋の前面に“からぼり”を設けることが必要であったが、平成10年の建設省の通達により全く地下に潜った窓のない地下室も居住として認められるようになっている。地下室は、全ての部屋数の1/4という制約はあるが、地下室には、“保温性”“遮音性”などの特性があるため、今後、益々その要望は高くなるものと思われる。
【0003】
一般に、地下室付き住宅建設において、地下室部分の構築には大別して次の三つの方法が知られていた。即ち、▲1▼は地下室となる函体の体積(高さ×面積)を予め画定し、該画定した函体の体積に相当する空間と該空間の周囲に作業空間が形成できるような縦穴を、土留め壁を構築しつつ掘り下げ、該縦穴内において前記地下室構造体を建造する方法、▲2▼は▲1▼と同様に土留め壁を構築しつつ掘り下げた縦穴内に、他の場所(例えば工場など)で建造して運び込んできた地下室構造体をクレーン等の機械にて吊り上げて埋設する方法、▲3▼は既製の建造物をジャッキ等の架設具にて保持し、その保持地盤を徐々に掘り下げつつ建造物を潜函させる方法である。
【0004】
【発明が解決しようとする課題】
しかしながら、上記▲1▼場合には、掘り下げた縦穴内での強化コンクリートによる地下室構造体の建造には、建造物と土留め壁との間の作業空間が狭く困難さが伴ったばかりでなく、土留め壁の形成に際し、H鋼材や鉄道レールなどの打ち込み位置を、隣接地の境界から手前側(自敷地側)に相当長入った処に設定しなければならず、敷地を地下室設置のために広く活用することが困難であった。
【0005】
また、上記▲2▼の場合には、土留め壁の構築には上記▲1▼の欠点を備えるほか、他の場所から運び込んできた地下室構造体はクレーン等の機械によって吊り上げることのできる大きさに限られていたし、クレーン等の機械自身の設置場所が確保できずに建設できないこともあった。
【0006】
さらに、上記▲3▼の場合には、潜函時に多数のジャッキ等の架設具や多数の実働作業人員が必要であり、この方法で地下室構造体を潜函させるには建設コストが高くなるという問題があった。
【0007】
本発明は上記種々の問題点を一挙に解決するためのもので、その目的とするところは、H鋼材や鉄道レールなどを打ち込んで土留め壁を構築する必要がなく少労力、短時間で効率よく地下構造物の潜函ができ、しかも、地下室構造体の大きさや設置場所を選ばず、敷地を地下室設置のために広く活用できるようにした新規な潜函工法を提供することにある。
【0008】
【課題を解決するための手段】
上記目的を達成するため、本発明に係る潜函工法は、所定の地面上で、天井、底のない函体を強化コンクリートにより建造し、該建造した函体の内底部の地面を掘り下げた後、前記函体の側壁下面を支えている地盤のほぼ半周分数センチ幅だけ除去して自重沈下させ次いで、残りのほぼ半周分を同幅だけ除去して自重沈下させて行くことを特徴とし、地上作業にて得た函体を、クレーン等の機械やジャッキ等の架設具を使用せずに簡易に潜函できるように構成している。
【0009】
また、本発明に係る潜函工法は、函体を傾きと水平とを繰り返しつつ水平度を保ちながら確実に沈下させることができるように構成している。
【0010】
【発明の実施の態様】
次に、本発明の実施の態様を図1〜図4に基づいて説明する。図1は地上にて函体を築造した状態の断面図、図2は潜函過程を示す断面図、図3は潜函終了時の断面図、図4は床部及び函体の外周囲の仕上げ後の断面図である。
【0011】
図1において、1は地下室付き住宅を建設しようとする所定の地面G上において強化コンクリートにて建造した天井、底のない側壁2のみの函体である。ここに使用の強化コンクリートとは、繊維補強コンクリート、鉄筋コンクリートを含む270kg/cm2 以上の強度を有するものである。
【0012】
前記函体1の建造には、型組、強化コンクリートの打込み、締固め、養生という手順を踏むが、これらの作業は地上にて行える点で優れている。この函体1は防水材(例えば、ナルファルドC<成瀬化学株式会社製>)が混入された強化コンクリートにて建造されているとともに、型枠を外したときに露出するボルト貫通孔が閉塞処理(ピーコン処理、モルタル埋め)され、かつ、外表面にはプライマー処理(例えば、防水アスファルトの塗布)が施されて、複合防水化されている。
【0013】
前記函体1を建造しようとする敷地内の所定の地面Gは、図1の如く、予め、50〜60cm程の深さの口掘り部Kを設ける。該口掘り部Kは浅いために土留め壁を形成する必要はない。勿論、口掘り部Kは前記函体1の潜函に際して沈下量を少なくする上に有効であるが、設計上口掘りしない場合も皆無ではない。
【0014】
前記所定の地面G上で強化コンクリートにより函体1を建造後、該函体1の内底部の地面(土壌)をパワーショベル等の機械3を用いて(手掘りも可)掘り下げ、排出した土砂を函体外へ搬出する。この掘り下げにより函体1は自重により沈下することとなる。
【0015】
前記函体1の自重沈下は、数センチ(ほぼ5〜8cm程)づつ行われる。函体1内の地面を掘り下げてから、函体1の側壁下面を支えている地盤を数センチ幅に環状に除去する。これにより、函体1はその除去分だけ沈下する。この側壁下面の地盤の除去は、手順としては半周分づつ行うこととなる。即ち、水平状態にある函体1の側壁下面の地盤をほぼ半周分除去すると、函体1は支えを失い傾くように自重沈下する。そして、残りの半周分を除去すると傾いていた函体1は水平に戻るように自重沈下する。これをワンサイクルとして繰り返すことにより函体1は順次沈下する。この自重沈下の過程で函体1の水平度はトランシット等の器具を使って適時確認し、必要があれば微調整する。
【0016】
前記函体1の潜函に際し、3人程度の作業者数で時間当たり80mm程度を沈下させることは可能である。従って、今、例えば、2700mmの高さを有する函体を建造し、これをその上側が地面Gに対して1000mm分だけ残るように潜函(1700mm分を沈下)させる場合において、これに掛かる時間は、実働8時間/1日として約2.6日間という短時間で完了することとなる。
【0017】
かくして、前記函体1が、自重沈下と地面の掘り下げとの繰り返しにより、図3の如く、所望の支持地盤G′まで到達すると、その後は内底部に玉石や砕石等の骨材4を中詰めする。この中詰めに当たり、骨材4に填圧を加えて平に均す。この填圧作業は地下室の基礎(支持地盤を強化すること)となることから重要であり、また、床面の仕上がりを良好にするためにも重要である。
【0018】
前記骨材4の中詰め後、その中詰骨材4の上面に、図4の如く、防水性フィルム5を敷き、その上に、鉄筋(図示せず)を配して防水材を混入した強化コンクリート床層6を形成する。なお、前記防水性フィルム5は、函体1の底面側からの浸透水を完全に遮断するために有効なものである。防水性フィルム5としてはプラスチックシート(例えば、0.1mm厚のポリプロピレンシート)を使用して満足できる。
【0019】
前述の如く、函体1の底部の強化コンクリート床層6が完成した後、該強化コンクリート床層6を含む函体1の内壁面を、無機質浸透性防水塗料(例えば、ソロシール<エヌケー化研株式会社製>)を吹付塗布する。この塗料はコンクリート系の構造物の躯体中に浸透して水分の浸透を確実に防止(シャットアウト)する機能を備える。
【0020】
前記函体1を所望の支持地盤G′まで到達させ、更に、函体底部の強化コンクリート層6を完成させたならば、該函体1の外周囲を縦穴状に掘り下げ、この掘り下げ部に締まり性のよい土壌(粒子が細かく団粒をつくり易い土壌=例えば、赤土などの粘度質の土)を入れ、填圧して填圧層7を形成する。この填圧層7は地表からの雨水の浸透をなくすとともに、土中に浸透した雨水が側面より浸透することを避けるために有効である。なお、掘り下げ幅W及び深さFは任意に決定できる。なお、掘り下げ幅Wについては50〜60cm、深さFは地表から函体の2/3程度あれば充分である。
【0021】
前記函体1の潜函終了後、地表より露出している函体1の上部外面は必要な外装材が施されるとともに、上面には住宅の土台(上床)が強化コンクリートにより形成されることとなる。
【0022】
【発明の効果】
以上の如く、本発明に係る潜函工法は、所定の地面上で、天井、底のない函体を強化コンクリートにより建造し、該建造した函体の内底部の地面を掘り下げた後、前記函体の側壁下面を支えている地盤のほぼ半周分数センチ幅だけ除去して自重沈下させ、次いで、残りのほぼ半周分を同幅だけ除去して自重沈下させて行くことを特徴としているから、地上作業にて得た函体を、クレーン等の機械やジャッキ等の架設具を使用せずに簡易に潜函させることができる。しかも、H鋼材や鉄道レールなどを打ち込んで土留め壁を構築する必要がなく、少労力、短時間で効率よく地下構造物が構築できるとともに、地下室構造体の大きさや設置場所を選ばず、敷地を地下室設置のために広く活用できるなど、各種の優れた効果を奏するものである。
【0023】
また、本発明に係る潜函工法は、函体を傾きと水平とを繰り返しつつ水平度を保ちながら確実に沈下させることができるという優れた効果を奏するものである。
【図面の簡単な説明】
【図1】地上にて函体を建造した状態の断面図である。
【図2】函体の潜函過程を示す断面図である。
【図3】函体の潜函終了時の断面図である。
【図4】函体の床層及び外周部の仕上げ後の断面図である。
【符号の説明】
1 函体
2 側壁
3 パワーショベル等の機械
4 玉石や砕石等の骨材
5 防水性フィルム
6 強化コンクリート層
7 填圧層
G 地下室を建設しようとする所定の地面
G′函体の所望する支持地盤
W 掘り下げ幅
F 掘り下げ深さ[0001]
TECHNICAL FIELD OF THE INVENTION
According to the present invention, a box (basement structure) without a ceiling and a bottom is constructed of reinforced concrete by work on a predetermined ground, and the box is self-weighted without using an installation tool such as a jack or a machine such as a crane. The present invention relates to a novel latent box method capable of sinking to a desired supporting ground.
[0002]
[Prior art]
In Japan where land is small, land prices are high, and there is a high demand for basements as living areas when constructing houses. This is because the basement is ideal as an entertainment room, an audio room, a practice room for musical instruments such as pianos, and a room where sounds can be freely output to the neighborhood. According to the Building Standards Law of Japan, when a basement was previously occupied, it was always necessary to provide a "floor" at the front of the room. Basements without open spaces are now recognized as habitable. The basement has a restriction of 1/4 of the total number of rooms, but since the basement has characteristics such as "heat insulation" and "sound insulation," it is expected that the demand will be further increased in the future.
[0003]
In general, in the construction of a basement-equipped house, the following three methods have been known for the construction of the basement. That is, (1) defines in advance the volume (height x area) of the box that will be the basement, and forms a space corresponding to the volume of the box defined and a vertical hole around which the working space can be formed. A method of digging down while constructing a retaining wall, and constructing the basement structure in the vertical hole. The method (2) is similar to the method (1) in that the hole is dug down while constructing the retaining wall at another location ( (E.g. factories) to lift and bury a basement structure built and carried in by a machine such as a crane, and (3) to hold an already-built building with a mounting tool such as a jack, This is a method of digging a building while gradually digging it.
[0004]
[Problems to be solved by the invention]
However, in the case of the above (1), the construction of the basement structure with the reinforced concrete in the dug down vertical hole is not only difficult due to the narrow working space between the building and the retaining wall, but also the soil. When forming the retaining wall, the driving position of the H-steel material and railway rails, etc., must be set at a place that is considerably long from the boundary of the adjacent land to the near side (own site side), and the site is installed for basement installation It was difficult to use it widely.
[0005]
In the case of the above (2), the construction of the retaining wall has the drawbacks of the above (1), and the basement structure carried from another place is large enough to be lifted by a machine such as a crane. In some cases, it was not possible to secure a place to install machines such as cranes, so construction was not possible.
[0006]
Furthermore, in the case of the above (3), a large number of jacks and other erection tools and a large number of working workers are required at the time of submerging, and there is a problem that construction costs are high to submerge the basement structure by this method. there were.
[0007]
The present invention is intended to solve the above-mentioned various problems at once, and aims at eliminating the need for driving an H steel material, a railroad rail, or the like to construct an earth retaining wall. It is an object of the present invention to provide a new method of submerging a subterranean structure that can be used frequently for setting up a basement, regardless of the size and location of the basement structure.
[0008]
[Means for Solving the Problems]
To achieve the above object, the latent box method according to the present invention, on a predetermined ground, a ceiling, a box without a bottom is built with reinforced concrete , after digging down the ground of the inner bottom of the built box , Ground work is performed by removing several centimeters in width of the ground supporting the lower surface of the side wall of the box and removing it by its own weight, and then removing the remaining half of the ground by the same width and letting it sink by its own weight. the resulting box-body at, and configured to caisson easily without the use of erection tool machines and jacks, etc. such as a crane.
[0009]
Further, caisson construction method according to the present invention is configured to be able to reliably sink while maintaining the horizontality of the box-body while repeating the slope and horizontal.
[0010]
DESCRIPTION OF THE PREFERRED EMBODIMENTS
Next, an embodiment of the present invention will be described with reference to FIGS. 1 is a cross-sectional view of a state where a box is built on the ground, FIG. 2 is a cross-sectional view showing a submerging process, FIG. 3 is a cross-sectional view at the end of the submerged box, and FIG. FIG.
[0011]
In FIG. 1,
[0012]
The construction of the
[0013]
As shown in FIG. 1, a predetermined ground G in a site where the
[0014]
After constructing the
[0015]
The sinking of the weight of the
[0016]
When the
[0017]
Thus, when the
[0018]
After the packing of the
[0019]
As described above, after the reinforced concrete floor layer 6 at the bottom of the
[0020]
When the
[0021]
After completion of the submersion of the
[0022]
【The invention's effect】
As described above, the latent box method according to the present invention comprises the steps of: constructing a box without a ceiling and a bottom with reinforced concrete on a predetermined ground, digging down the ground at the inner bottom of the built box; It is characterized by removing a few centimeters of the ground that supports the lower surface of the side wall of the side wall and submerging by its own weight, and then removing the remaining half of the ground by the same width and submerging by its own weight. Can be easily hidden without using a machine such as a crane or an installation tool such as a jack. In addition, there is no need to build H retaining materials by driving in H steel or railroad rails, so that underground structures can be constructed efficiently with little labor and in a short time, and the size and location of the basement structures can be selected. Can be widely used for setting up a basement.
[0023]
Further, the latent box construction method according to the present invention has an excellent effect that the box can be reliably settled down while maintaining the level while repeating the inclination and the horizontal .
[Brief description of the drawings]
FIG. 1 is a sectional view of a state where a box is built on the ground.
FIG. 2 is a cross-sectional view showing a submerged box process of the box.
FIG. 3 is a cross-sectional view of the box at the end of the latent box.
FIG. 4 is a sectional view after finishing a floor layer and an outer peripheral portion of the box.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000318463A JP3566644B2 (en) | 2000-10-18 | 2000-10-18 | Submersion method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000318463A JP3566644B2 (en) | 2000-10-18 | 2000-10-18 | Submersion method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002121756A JP2002121756A (en) | 2002-04-26 |
JP3566644B2 true JP3566644B2 (en) | 2004-09-15 |
Family
ID=18797085
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000318463A Expired - Fee Related JP3566644B2 (en) | 2000-10-18 | 2000-10-18 | Submersion method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3566644B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117513349B (en) * | 2023-12-20 | 2024-06-04 | 兰州交通大学 | Pit excavation method combining open caisson with slope releasing |
-
2000
- 2000-10-18 JP JP2000318463A patent/JP3566644B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2002121756A (en) | 2002-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102444142B (en) | Pile group column replacement expanded basement and construction method of same | |
KR101545307B1 (en) | Construction method of complex temporary facility with bottom grouting for weak ground | |
CN100473790C (en) | Tower crane foundation for construction and manufacturing method thereof | |
CN105464074A (en) | Manual hole digging pile high polymer grouting protection structure and construction method thereof | |
CN109706952A (en) | Large-scale well-sinking construction method | |
CN107366303A (en) | Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template | |
CN207659986U (en) | A kind of building or structures foundation stabilization underpin pier | |
CN110512594B (en) | Simple method for forming hole and pile in cavity of rotary drilling rig | |
CN110820756A (en) | Shield well and vertical shaft deep foundation pit excavation safety construction method | |
JP3566644B2 (en) | Submersion method | |
CN101597903A (en) | A kind of construction method of cylindrical slurry core pile that is used for pattern foundation pit supporting structure | |
CN211421139U (en) | Shield constructs well crown beam bearing structure | |
JP2814898B2 (en) | Underground storage facility | |
JP3530128B2 (en) | Composite waterproofing method for underground structures | |
JPH09316894A (en) | Bridge pier foundation structure, and construction method thereof | |
JPH03172412A (en) | Forming method for under surface area and liquid state-generating apparatus | |
Mangushev et al. | Practical restoration-related experience with creation of basement level and underground parking into and near architectural monuments in down-town of Saint-Petersburg | |
CN111058456A (en) | Cast-in-place pile construction method in foundation pit supporting process | |
Altuntas et al. | Secant pile wall design and construction in Manhattan, New York | |
CN216920368U (en) | Large-scale round foundation pit triaxial mixing pile supporting construction | |
CN107100216A (en) | The unilateral basic pile foundation of monolithic wall is encorbelmented underpinning construction method | |
Vanni et al. | Deep soil mixing to help the restoration of Venice San Marco Bell Tower | |
JP4031284B2 (en) | Construction method for underground structures | |
Huang | Construction Technology of Deep Foundation Pit Support in Municipal Civil Engineering Foundation Construction | |
Ibrahim | Construction project of comprehensive school in Cairo City, Egypt (Arab Republic of Egypt) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040127 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040326 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040511 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040610 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313113 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080618 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090618 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100618 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110618 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110618 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120618 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130618 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |