JP2001336164A - Working platform for constructing underground structure and constructing method thereof - Google Patents

Working platform for constructing underground structure and constructing method thereof

Info

Publication number
JP2001336164A
JP2001336164A JP2000158768A JP2000158768A JP2001336164A JP 2001336164 A JP2001336164 A JP 2001336164A JP 2000158768 A JP2000158768 A JP 2000158768A JP 2000158768 A JP2000158768 A JP 2000158768A JP 2001336164 A JP2001336164 A JP 2001336164A
Authority
JP
Japan
Prior art keywords
underground structure
work gantry
ground
constructing
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000158768A
Other languages
Japanese (ja)
Other versions
JP4267175B2 (en
Inventor
Kiyoshi Hina
潔 比名
Kenichi Hamazaki
憲一 濱崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2000158768A priority Critical patent/JP4267175B2/en
Publication of JP2001336164A publication Critical patent/JP2001336164A/en
Application granted granted Critical
Publication of JP4267175B2 publication Critical patent/JP4267175B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a working platform and the constructing method thereof which facilitates ingress and egress of haulage vehicles for carrying out excavated soil of a ground surrounded by earth retaining walls and by which an underground structure can be efficiently constructed and hence, the construction period can be reduced when the underground structure of a building is constructed in a narrow building site. SOLUTION: After a building site surrounded by earth retaining walls is primarily excavated relatively shallowly, working platforms are continuously connected to each other so that one end edge facing a road side is almost flush with the road and the primarily excavated excavation recess is opened between other end edge and the earth retaining wall. Haulage vehicles are allowed to come in and out on the working platform from the road side and soil secondarily excavated by excavating machine on the working platform is carried out and after the secondary excavation, the working platform is used as a part of slabs above the ground to construct the underground structure.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、市街地などの狭小
地に建築物の地下構造物を築造する際に、地盤を掘削す
る掘削機械の作業空間部や掘削土砂等の運搬通路として
用いられる地下構造物構築用作業構台とその構築方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underground used as a work space of an excavating machine for excavating the ground and a transport passage for excavated earth and sand when building an underground structure of a building in a narrow land such as an urban area. The present invention relates to a work gantry for building a structure and a method of building the work gantry.

【0002】[0002]

【従来の技術】従来から、比較的浅い地下構造を有する
建物を構築する場合、まず、図9に示すように、構築す
べき建物の地下一階を構成する地下構造物11の周辺地盤
に山留め壁12を施工したのち、この山留め壁12で囲まれ
た地盤を地下構造物11の高さに相当する深さまで掘削
し、その掘削凹部13の底面に基礎部14を築造したのち、
該基礎部14から上方に向かって柱や壁15及び地上1階の
スラブ16を順次施工することによって地下構造物11を構
築し、しかるのち、地上階層を建築している。
2. Description of the Related Art Conventionally, when a building having a relatively shallow underground structure is constructed, first, as shown in FIG. 9, a ground is attached to the ground around an underground structure 11 constituting the first basement floor of the building to be constructed. After constructing the wall 12, the ground surrounded by the retaining wall 12 is excavated to a depth corresponding to the height of the underground structure 11, and the foundation 14 is built on the bottom surface of the excavation recess 13,
The underground structure 11 is constructed by sequentially constructing the pillars and walls 15 and the slab 16 on the first floor from the base 14 upward, and then the ground floor is constructed.

【0003】このような建物における上記地下構造物11
を構築する際に、建設すべき建物の周辺部に既設の建物
が存在していて上記山留め壁12で囲まれた地盤を掘削す
るための作業空間が殆どない場合には、まず、建物の敷
地内に仮設の作業構台17を敷設し、この作業構台17の下
方の地盤を構築すべき地下構造物11の高さに相当する深
さまで掘削すると共に掘削土砂を作業構台17上に待機し
ている運搬車18に搭載して搬出し、所定深さまで掘削し
たのちに上記のように地下構造物11の構築作業を行って
いるのが現状である。
[0003] The underground structure 11 in such a building
When constructing a building, if there is an existing building around the building to be constructed and there is almost no work space for excavating the ground surrounded by the retaining wall 12, first, A temporary work gantry 17 is laid inside, and the ground below the work gantry 17 is excavated to a depth corresponding to the height of the underground structure 11 to be constructed, and the excavated soil is waiting on the work gantry 17 At present, the underground structure 11 is constructed as described above after being mounted on the transport vehicle 18 and carried out and excavated to a predetermined depth.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、通常、
地下構造物11はその上端の上記地上部のスラブ16を地表
面の高さに一致するように構築されるために、上記仮設
の作業構台17を予め、このスラブ16よりも50cm程度、高
位置に設置しておかなければならず、従って、建物周辺
の道路19からこの作業構台17上に運搬車等の車両を乗り
入れするには、道路に面した作業構台17の端部を図9に
示すように、道路側に向かって下向きに傾斜した通路部
17a に形成しておく必要があると共に、築造すべき地下
構造物11が該道路19との境界線ぎりぎりの位置まで近接
しているため、この通路部17a が急勾配となって車両の
出入りに支障をきたすばかりでなく、通路部17a の下面
が築造すべき地下構造物11の上記スラブ16の角部に近接
して該スラブ16の端部の施工が困難になる。通路部17a
を緩勾配にすればスラブ16の施工が容易となるが、そう
すると通路部17a が長くなって道路19上にはみ出ること
になり、通路部17a の配設ができなくなる。
However, usually,
Since the underground structure 11 is constructed so that the above-mentioned slab 16 at the upper end of the underground structure 11 matches the height of the ground surface, the temporary work gantry 17 is previously set at about 50 cm higher than the slab 16, Therefore, in order to get a vehicle such as a truck on the work gantry 17 from the road 19 around the building, the end of the work gantry 17 facing the road is shown in FIG. Passageway inclined downward toward the road side
17a, and because the underground structure 11 to be built is very close to the position just below the boundary with the road 19, this passage 17a becomes steep and the vehicle enters and exits. Not only does this cause a problem, but also the lower surface of the passage 17a is close to the corner of the slab 16 of the underground structure 11 to be built, making it difficult to construct the end of the slab 16. Passage 17a
If the slope is made gentler, the construction of the slab 16 becomes easier. However, if this is done, the passage 17a becomes longer and protrudes onto the road 19, so that the passage 17a cannot be arranged.

【0005】また、構築すべき建物の敷地内に、予め、
上記仮設の作業構台17を配設しておくものであるから、
作業構台自体の費用と共にその敷設費用、敷設作業を必
要とし、さらに、地下構造物11の構築後における撤去作
業も行わなければならないために、工期が長くなると共
にコスト高になるという問題点があった。
[0005] In the site of the building to be constructed,
Since the temporary work gantry 17 is provided,
In addition to the cost of the work gantry itself, the laying cost and the laying work are required, and furthermore, the removal work after the construction of the underground structure 11 has to be carried out. Was.

【0006】本発明はこのような問題点に鑑みてなされ
たもので、その目的とするところは、仮設の作業構台を
採用することなく、地上階スラブの一部を作業構台とし
て兼用して車両の出入りを円滑に行えるようにすると共
に作業能率を向上させ、且つ地下構造物を経済的に構築
し得るようにした地下構造物用作業構台とその構築方法
を提供するにある。
SUMMARY OF THE INVENTION The present invention has been made in view of such problems, and an object of the present invention is to use a part of a ground floor slab as a work gantry without employing a temporary work gantry. It is an object of the present invention to provide a work gantry for underground structures and a method of constructing the underground structures capable of smoothly entering and exiting the building, improving work efficiency, and economically constructing underground structures.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、本発明の地下構造物構築用作業構台は、請求項1に
記載したように、山留め壁により囲まれた地中に地下構
造物を構築する際の作業構台であって、構築すべき地下
構造物の底部よりも深部にまで打設した複数本の杭体上
にこれらの杭体により支持された地上階スラブの一部を
施工してこの地上階スラブの一部により作業構台を形成
し、この作業構台の外周端部の一部を地表面に略同一水
平面上で面一状態に連続させてなる構造としている。
In order to achieve the above-mentioned object, a work gantry for constructing an underground structure according to the present invention is provided in an underground structure surrounded by a retaining wall. A part of the ground floor slab supported by these piles is installed on a plurality of piles that are cast deeper than the bottom of the underground structure to be constructed Then, a work gantry is formed by a part of the ground floor slab, and a part of the outer peripheral end of the work gantry is formed to be continuous with the ground surface in substantially the same horizontal plane.

【0008】上記地下構造物構築用作業構台において、
請求項2に係る発明は、作業構台における地表面に略同
一水平面上で面一状態に連続させている上記一端部以外
の外周端部の端面と山留め壁の上端部とを切梁部材によ
り連結していることを特徴とし、請求項3に係る発明
は、作業構台の下面に一体に設けている梁部を上記杭体
の上端に支持させたことを特徴としている。さらに、請
求項4に係る発明は、作業構台を複数枚のプレキャスト
コンクリート板によって形成していることを特徴として
いる。
In the work gantry for constructing an underground structure,
According to a second aspect of the present invention, an end surface of the outer peripheral end other than the one end and the upper end of the retaining wall connected to the ground surface of the work gantry on the substantially same horizontal plane are connected by a cutting beam member. The invention according to claim 3 is characterized in that a beam part integrally provided on the lower surface of the work gantry is supported on an upper end of the pile body. Further, the invention according to claim 4 is characterized in that the work gantry is formed by a plurality of precast concrete plates.

【0009】また、請求項5に係る発明は、上記地下構
造物構築用作業構台の構築方法であって、建設すべき地
下構造物の周辺地盤に山留め壁を施工すると共にこの山
留め壁で囲まれた地盤に地下構造物の底部よりも深部に
まで複数本の杭体を打設する工程と、山留め壁で囲まれ
た地盤を一次掘削したのち上記杭体の上端に支持され且
つその外周端部の一部が地表面に略同一水平面上で面一
状態に連続するように地上階スラブの一部を施工してこ
の地上階スラブの一部によって作業構台を形成する工程
とからなることを特徴としている。
According to a fifth aspect of the present invention, there is provided a method of constructing a work gantry for constructing an underground structure, wherein a mountain retaining wall is constructed on a ground around an underground structure to be constructed and is surrounded by the mountain retaining wall. Placing a plurality of piles deeper than the bottom of the underground structure on the ground, and after first excavating the ground surrounded by the retaining wall, the pile is supported at the upper end of the pile and the outer peripheral end thereof A part of the ground floor slab is constructed so that a part of the ground floor is continuous with the ground surface in substantially the same horizontal plane, and a work gantry is formed by a part of the ground floor slab. And

【0010】上記地下構造物構築用作業構台の構築方法
において、請求項6に係る発明は、作業構台の形成後、
この作業構台における上記外周端部の一部以外の部分の
外周端面と上記山留め壁の上端部とを切梁部材により連
結することを特徴とし、請求項7に係る発明は、上記作
業構台の形成後に該作業構台の下方及び周辺の地盤を構
築すべき地下構造物の高さに相当する深さまで二次掘削
し、掘削凹部の底面に地下構造物の基礎部を構築すると
共に地下構造物の柱及び壁と上記作業構台を一部に用い
た地上階スラブを構築することを特徴とするものであ
る。
In the method for constructing a work gantry for constructing an underground structure, the invention according to claim 6 is characterized in that after forming the work gantry,
The invention according to claim 7, wherein an outer peripheral end surface of a portion other than a part of the outer peripheral end portion of the work gantry and an upper end portion of the retaining wall are connected by a cutting beam member. Afterwards, secondary excavation is performed to a depth corresponding to the height of the underground structure to be constructed below and around the work gantry, a foundation of the underground structure is constructed on the bottom surface of the excavation recess, and columns of the underground structure are formed. And a ground-floor slab using a part of the wall and the work gantry.

【0011】さらに、請求項7に係る発明は、地上階ス
ラブの一部によって形成している上記作業構台の高さが
構築すべき地上階スラブの高さに対してずれている場合
には、そのずれを補正することを特徴としている。
Further, according to the present invention, when the height of the work gantry formed by a part of the ground floor slab is shifted from the height of the ground floor slab to be constructed, It is characterized in that the deviation is corrected.

【0012】[0012]

【作用及び効果】請求項1に係る発明によれば、構築す
べき地下構造物の底部よりも深部にまで打設した複数本
の杭体上にこれらの杭体により支持された地上階スラブ
の一部を施工してこの地上階スラブの一部により作業構
台を形成しているので、作業構台は杭体により強固に且
つ安定した状態で支持されているから、作業構台上での
作業が安全に且つ能率よく行えるのは勿論、この作業構
台の外周端部の一部を地表面に略同一水平面上で面一状
態に連続させているので、構築すべき地下構造物が建物
周辺の道路に近接していても該道路に同一水平面上で連
続した外周端部の一部を通じて作業構台上への運搬車等
の乗り入れや作業構台上からの道路への進入が容易とな
るものである。
According to the first aspect of the present invention, the ground floor slab supported by the piles on a plurality of piles cast deeper than the bottom of the underground structure to be constructed. Since the work gantry is formed by part of this ground floor slab by constructing a part, the work gantry is firmly and stably supported by the piles, so the work on the work gantry is safe. Of course, a part of the outer edge of this work gantry is continuous with the ground surface on almost the same horizontal plane, so that the underground structure to be built is located on the road around the building. Even if it is close to the road, it becomes easy for a transport vehicle or the like to enter the work gantry or to enter the road from the work gantry through a part of the outer peripheral end that is continuous on the same horizontal plane with the road.

【0013】さらに、作業構台は構築すべき地下構造物
の天井スラブ、即ち、地上1階の床スラブの一部から構
成しているので、従来のような仮設の作業構台の敷設作
業を不要にして経済的であるばかりでなく、作業能率が
向上して地下構造物の構築期間を短縮することができ、
その上、この作業構台の上記地表面に連続した部分以外
の外周端部は、築造すべき地下構造物の周辺地盤に施工
した山留め壁に対して敷地内に離間した位置にあり、作
業構台上から掘削機械によって山留め壁で囲まれた地盤
を円滑に一次掘削することができる。
Further, since the work gantry is composed of a ceiling slab of an underground structure to be constructed, that is, a part of the floor slab on the first floor above the ground, the work of laying a temporary work gantry as in the prior art is unnecessary. Not only is it economical, but also the work efficiency is improved and the construction period of underground structures can be shortened.
In addition, the outer peripheral end of the work gantry other than the portion continuous to the ground surface is located at a position separated from the ground retaining wall constructed on the ground around the underground structure to be built within the site, and The primary excavation can be performed smoothly on the ground surrounded by the retaining wall by the excavating machine.

【0014】この一次掘削時において、請求項2に記載
したように通路側以外の作業構台の外周端部の端面と上
記山留め壁の上端部とを切梁部材により連結しているの
で、上記山留め壁がその周囲の土圧により内方に傾動す
るのを作業構台を介して確実に防止することができ、掘
削作業等の作業の安全性を確保することができると共に
上記作業構台も切梁部材の一部として利用しているの
で、切梁部材の施工本数を減少させることができ、工期
の短縮を図ることができる。
At the time of the primary excavation, since the end face of the outer peripheral end of the work gantry other than the passage side and the upper end of the retaining wall are connected by a cutting beam member as described in claim 2, the retaining It is possible to reliably prevent the wall from tilting inward due to the surrounding earth pressure through the work gantry, to ensure the safety of work such as excavation work, and to make the work gantry a cutting beam member. Since it is used as a part of the construction, it is possible to reduce the number of constructions of the cutting beam member and shorten the construction period.

【0015】また、請求項3に係る発明によれば、上記
作業構台の下面に一体に設けている梁部を杭体の上端に
支持させているので、杭体による作業構台の支持構造が
一層強固になるばかりでなく、杭体を構築すべき地下構
造物の柱として使用して梁部と一体化させた柱の建設が
能率よく行えるものである。
According to the third aspect of the present invention, since the beam portion integrally provided on the lower surface of the work gantry is supported at the upper end of the pile, the structure for supporting the work gantry by the pile is further enhanced. Not only will it be strong, but it will also be possible to efficiently construct pillars that will be used as pillars for underground structures to be built and integrated with beams.

【0016】さらにまた、請求項4に係る発明によれ
ば、上記作業構台を複数枚のプレキャストコンクリート
板により形成しているので、作業構台の構築が一層能率
よく行えると共にこの作業構台をスラブの一部とした地
下構造物の地上階スラブの施工性も向上し、工期の短縮
を図ることができる。
According to the fourth aspect of the present invention, since the work gantry is formed of a plurality of precast concrete plates, the work gantry can be constructed more efficiently and the work gantry can be mounted on a slab. The workability of the ground floor slab of the underground structure as a part is also improved, and the construction period can be shortened.

【0017】上記作業構台の構築方法は、請求項5に記
載したように、建設すべき地下構造物の周辺地盤に山留
め壁を施工すると共にこの山留め壁で囲まれた地盤に地
下構造物の底部よりも深部にまで複数本の杭体を打設す
る工程と、山留め壁で囲まれた地盤を一次掘削したのち
上記杭体の上端に支持され且つその外周端部の一部が地
表面に略同一水平面上で面一状態に連続するように地上
階スラブの一部を施工してこの地上階スラブの一部によ
って作業構台を形成する工程とからなるものであるか
ら、山留め壁で囲まれた地盤の一次掘削は作業構台が施
工可能な比較的浅い深さまで掘削すればよいので、仮設
の作業構台を設けることなく掘削作業及び運搬車による
掘削土砂の搬出が可能となり、一次掘削が能率よく行え
る。
According to a fifth aspect of the present invention, there is provided a method of constructing a work gantry, comprising: constructing a mountain retaining wall on the ground surrounding an underground structure to be constructed, and constructing a bottom portion of the underground structure on the ground surrounded by the mountain retaining wall. A step of placing a plurality of piles deeper than deeper, and after first excavating the ground surrounded by the retaining wall, the pile is supported by the upper end of the pile and a part of the outer peripheral end thereof is substantially on the ground surface. A part of the ground floor slab is constructed so as to be continuous on the same horizontal plane and a work gantry is formed by a part of the ground floor slab. Since the primary excavation of the ground only needs to be excavated to a relatively shallow depth where the work gantry can be constructed, the excavation work and the removal of the excavated soil by the transport vehicle can be performed without providing a temporary work gantry, and the primary excavation can be efficiently performed. .

【0018】この一次掘削後、構築すべき地下構造物の
敷地内に打設している複数本の杭体上に予め、地上階ス
ラブの一部を施工して作業構台を形成するものであるか
ら、一次掘削した掘削底面を足場に使用して作業構台を
容易に施工することができると共に上記複数本の杭体は
構築すべき地下構造物の底部よりも深部にまで打設され
ているから、これらの杭体によって強固に支持された安
定した作業構台を形成することができる。
After the primary excavation, a part of the ground floor slab is previously constructed on a plurality of piles cast in the site of the underground structure to be constructed to form a work gantry. From this, the work gantry can be easily constructed using the excavated bottom surface that has been primarily excavated as a scaffold, and the plurality of piles are cast deeper than the bottom of the underground structure to be constructed. Thus, a stable work gantry firmly supported by these piles can be formed.

【0019】さらに、この作業構台の外周端部の一部を
道路等の地表面に対して直接、水平状に連続させるの
で、構築すべき地下構造物と道路との境界線が近接して
いてもその一部を運搬車等の車両が容易に出入り可能な
通路部として用いることができ、その上、作業構台は構
築すべき地下構造物の地上階スラブ全体の広さに施工さ
れるのではなく、該地上階フラズの一部として施工され
るので、該作業構台の上記道路に面した上記一部以外の
外周端部と上記山留め壁との間に一次掘削された地盤が
露呈した所望広さの開口部を形成することができ、この
開口部を通じて作業構台上の掘削機械により構築すべき
地下構造物の高さに相当する深さまでの地盤の二次掘削
及び作業構台上に待機している運搬車への掘削土砂の投
入作業を行うことができる。また、作業構台の下方地盤
の二次掘削は、その地盤上で移動する掘削機械により行
えばよい。
Further, since a part of the outer peripheral end of the work gantry is directly and horizontally continuous with the ground surface such as a road, the boundary between the underground structure to be constructed and the road is close to each other. Some of these can be used as passages that allow vehicles such as transport vehicles to easily enter and exit, and the work gantry is constructed over the entire ground floor slab of the underground structure to be constructed. The ground is constructed as a part of the ground floor fuzz, so that the first excavated ground is exposed between the outer peripheral end of the work gantry other than the part facing the road and the retaining wall. Through which the secondary excavation of the ground to a depth corresponding to the height of the underground structure to be built by the excavating machine on the work gantry and waiting on the work gantry Of excavated earth and sand into a truck Kill. Secondary excavation of the ground below the work gantry may be performed by an excavating machine moving on the ground.

【0020】また、請求項6に係る発明によれば、上記
作業構台における地表面に連続させた一部分以外の外周
端面と山留め壁とを切梁部材により連結させるので、安
定した強固な地下構造物構築用作業構台を形成すること
ができると共に作業構台も切梁として利用しているの
で、切梁部材の使用本数を減少させることができ、切梁
部材の施工が効率よく行えると共に爾後における撤去作
業も容易に行えるものである。
According to the sixth aspect of the present invention, since the outer peripheral end surface of the work gantry other than a part continuous to the ground surface and the retaining wall are connected by the cutting beam member, a stable and strong underground structure is provided. Since the work gantry for construction can be formed and the work gantry is also used as a cutting beam, it is possible to reduce the number of the cutting beam members to be used, to efficiently perform the cutting beam members, and to remove the work afterwards. Can also be easily performed.

【0021】このような地下構造物構築作業構台の築造
方法において、請求項7に係る発明は、上記作業構台の
形成後に該作業構台の下方及び周辺の地盤を構築すべき
地下構造物の高さに相当する深さまで二次掘削し、掘削
凹部の底面に地下構造物の基礎部を構築すると共に地下
構造物の柱及び壁と上記作業構台を一部に用いた地上階
スラブを構築することを特徴とするものであるから、作
業構台を撤去することなくこの作業構台を地上階スラブ
の一部に使用した地上階スラブを経済的に且つ能率よく
施工することができ、また、作業構台を支持した上記杭
体を撤去することなく地下構造物の柱や壁として利用す
ることにより、経済的にして且つ工期の一層の短縮を図
ることができる。
In the method of constructing a work gantry for constructing an underground structure according to the present invention, the height of the underground structure on which the ground below and around the work gantry should be constructed after the work gantry is formed. Secondary excavation to a depth equivalent to the above, constructing the foundation of the underground structure on the bottom of the excavation recess and constructing the ground floor slab partially using the columns and walls of the underground structure and the above work gantry This feature makes it possible to economically and efficiently construct a ground floor slab that uses this work gantry as part of a ground floor slab without removing the work gantry, and supports the work gantry. By using the pile body as a pillar or a wall of an underground structure without removing the pile body, it is economical and the construction period can be further shortened.

【0022】また、請求項7に係る発明によれば、地下
構造物の基礎部の構築後において、地上階スラブの一部
によって形成している上記作業構台の高さが構築すべき
地上階スラブの高さに対してずれている場合にそのずれ
を補正することを特徴とするものであるから、精度のよ
い地下構造物を構築することができる。
According to the seventh aspect of the present invention, after the foundation of the underground structure is constructed, the height of the work gantry formed by a part of the ground floor slab is to be constructed. The feature is that when there is a shift with respect to the height of the ground, the shift is corrected, so that an accurate underground structure can be constructed.

【0023】[0023]

【発明の実施の形態】次に、本発明の具体的な実施の形
態を図面について説明すると、図1、図2において、1
は構築すべき地下構造物Aの敷地内に施工された平面矩
形状の作業構台で、その下面は構築すべき地下構造物A
の高さよりも深部にまで打設している複数本のH形鋼か
らなる杭体2によって支持されている。この作業構台1
は地下構造物Aの天井スラブ、即ち、該地下構造物Aを
地下一階とする建物の地上一階の床スラブの一部からな
り、その下面には梁部1aが長さ方向(前後方向)に所定
間隔毎に一体に形成されている。一方、上記杭体2は作
業構台1の上記梁1aと同一間隔毎にこれらの梁部1aに対
応して打設されてあり、各梁部1aの両側端部の下部にそ
の上端部を埋設、固着させた状態にして作業構台1を支
持している。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a block diagram showing a first embodiment of the present invention; FIG.
Is a flat rectangular work gantry constructed on the site of the underground structure A to be constructed, and the lower surface thereof is the underground structure A to be constructed.
Is supported by a pile 2 made of a plurality of H-shaped steels which are cast to a depth deeper than the height of the pile. This work gantry 1
Is a part of the ceiling slab of the underground structure A, that is, a part of the floor slab on the first floor above the building where the underground structure A is the first basement. ) Are integrally formed at predetermined intervals. On the other hand, the pile body 2 is cast at the same intervals as the beams 1a of the work gantry 1 in correspondence with these beams 1a, and the upper ends thereof are buried under the lower ends of both sides of each beam 1a. The work gantry 1 is supported in a fixed state.

【0024】また、上記敷地内における構築すべき地下
構造物Aの周辺地盤には地表面から該地下構造物Aの高
さよりも深い地中にまで山留め壁3が平面矩形枠状に施
工されてあり、上記地上階スラブの一部からなる作業構
台1は、この山留め壁3で囲まれた地盤Bを比較的浅く
一次掘削したのち、後述するようにこの掘削凹部4を足
場にして上記隣接する杭体2の上端部間に型枠8を組立
て、該型枠8内にコンクリートを打設することによって
地上階スラブの一部を先行して築造し、この地上階スラ
ブの一部によって形成しているものである。
On the ground near the underground structure A to be constructed in the site, a mountain retaining wall 3 is constructed in a plane rectangular frame shape from the ground surface to the ground deeper than the height of the underground structure A. The work gantry 1 composed of a part of the above-mentioned ground floor slab is configured to firstly excavate the ground B surrounded by the retaining wall 3 relatively shallowly, and then to use the excavated concave portion 4 as a scaffold, as described later, to adjoin the adjacent work gantry. A formwork 8 is assembled between the upper ends of the piles 2 and a part of the ground floor slab is built in advance by casting concrete into the formwork 8 and formed by a part of the ground floor slab. Is what it is.

【0025】この作業構台1の面積(広さ)は、上記山
留め壁3によって囲まれた地盤Bの面積よりも小さく、
且つその上面が地表面と略同一水平面上になるように施
工されてあり、さらに、作業構台1の四方外周端部にお
いて、道路C側に面した外周端部の一部、即ち、一端縁
辺部は、道路Cと面一状態に連続するように道路との境
界線Gに近傍した上記山留め壁3における道路C側壁体
部の上方部地表面に連設している。一方、作業構台1の
四方外周端部において、上記一端縁辺部以外のその他の
部分、即ち、他端縁辺部と両側縁辺部とは、これらの縁
辺部と平行に対向した山留め壁3の他端側壁体部と両側
端側壁体部との上端部に対して所定の間隔を存して離間
してあり、その離間した部分においては、一次掘削した
掘削凹部4が地表面に向かって開口5している。
The area (area) of the work gantry 1 is smaller than the area of the ground B surrounded by the retaining wall 3.
And the upper surface is constructed so as to be substantially on the same horizontal plane as the ground surface, and further, at the four outer peripheral ends of the work gantry 1, a part of the outer peripheral end facing the road C side, that is, one end edge part Is connected to the ground surface above the side wall of the road C in the retaining wall 3 near the boundary G with the road so as to be continuous with the road C. On the other hand, at the four outer peripheral ends of the work gantry 1, other portions other than the above-mentioned one end edge, that is, the other end edge and both side edges are the other ends of the mountain retaining wall 3 facing in parallel with these edges. The upper end portion of the side wall body portion and both side end wall body portions is separated from each other at a predetermined interval, and in the separated portion, the first excavation recess 4 is opened 5 toward the ground surface. ing.

【0026】さらに、山留め壁3の上端部四方内周面に
H形鋼よりなる腹起し部材6を取付けてあり、この腹起
し部材6と上記開口部5に面している作業構台1の他端
面と両側端面とを複数本の切梁部材7によって連結して
山留め壁3の周囲の土圧により山留め壁3が内方に傾動
するのを防止している。この場合、作業構台1も切梁部
材としての役目を果しているので、上記切梁部材7の施
工本数が少なくてすみ、例えば、図2に示すように、作
業構台1の他端面中央部と腹起し部材7間、及び、作業
構台1の両側端面における長さ方向の両端部と腹起し部
材7間を連結した構造としておけばよい。なお、山留め
壁3を打設した地盤Bの支持力が大きい場合には、切梁
部材7は必ずしも設けておく必要はない。
Further, an erection member 6 made of H-shaped steel is attached to the inner peripheral surface on the four sides of the upper end of the retaining wall 3, and the gantry 1 facing this erection member 6 and the opening 5. Are connected to each other by a plurality of cutting members 7 to prevent the retaining wall 3 from tilting inward due to earth pressure around the retaining wall 3. In this case, since the work gantry 1 also serves as a girder member, the number of the girder members 7 to be constructed can be reduced. For example, as shown in FIG. What is necessary is just to make it the structure which connected between the member 7 and the both ends of the longitudinal direction in the both end surfaces of the work gantry 1 and the protruding member 7. In the case where the ground B on which the retaining wall 3 is cast has a large supporting force, it is not always necessary to provide the cutting beams 7.

【0027】このように構成した地下構造物構築用作業
構台は、その作業構台1を利用して地下構造物Aを構築
するための地盤の二次掘削やその他の作業を行うと共に
道路Cと略同一水平面にして該道路C側に連設している
水平な一端部を介して土砂搬出運搬車等の車両の出入り
を行わせ、地下構造物Aの天井スラブ、即ち、地上1階
の床スラブ(地上階スラブ)を築造する際にはこの作業
構台1を該スラブの一部として使用し、上記開口部5に
作業構台1の外周端面に連続するスラブを施工して地上
階スラブを築造するものである。なお、この作業構台1
は場所打ちコンクリートによって造成したが、一定形状
を有する複数枚のプレキャストコンクリート板を杭体2
上に設置、敷設することによって形成してもよい。この
場合、この作業構台1を一部とした上記地上階スラブ全
体がプレキャストコンクリート板によって形成される。
The work gantry for constructing an underground structure constructed as described above uses the work gantry 1 to perform secondary excavation of the ground for constructing the underground structure A and other operations, and is substantially similar to the road C. A vehicle such as a sediment carry-out vehicle is allowed to enter and exit through a horizontal end connected to the road C side on the same horizontal plane, and the ceiling slab of the underground structure A, that is, the floor slab on the first floor above the ground. When constructing a (ground floor slab), this work gantry 1 is used as a part of the slab, and a slab continuous to the outer peripheral end surface of the work gantry 1 is constructed in the opening 5 to build a ground floor slab. Things. This work gantry 1
Was formed by cast-in-place concrete, but a plurality of precast concrete
It may be formed by installing and laying on top. In this case, the entire ground floor slab including the work gantry 1 as a part is formed of a precast concrete plate.

【0028】次に、上記地下構造物構築用作業構台の構
築方法を図8に示す施工フロー図に基づいて説明する。
構築すべき地下構造物Aの敷地は図4に示すように、三
方が既設の建物Dで囲まれてあり、残りの一方側のみが
歩道C1を有する道路C側に面している。このような狭小
地に高層ビルの地下一階となる地下構造物Aを構築する
には、まず、敷地内に構築すべき地下構造物Aの周辺地
盤に該地下構造物Aの高さよりも深部にまで山留め壁3
を打設、施工したのち、道路C側に連続するように作業
構台1を施工すべき位置に該作業構台1の下面における
両端両側部と中央両側部とを支持するための複数本の杭
体2を図3図4に示すように、構築すべき地下構造物A
の底部よりも深部にまで打設する。
Next, a method of constructing the work gantry for constructing the underground structure will be described with reference to a construction flowchart shown in FIG.
As shown in FIG. 4, the site of the underground structure A to be constructed is surrounded by an existing building D on three sides, and only the other side faces the side of the road C having the sidewalk C1. In order to construct the underground structure A that is the first basement floor of a high-rise building in such a narrow land, first, a deeper part of the ground around the underground structure A to be constructed in the site than the height of the underground structure A Mountain retaining wall 3
And a plurality of piles for supporting both sides of the lower surface of the work gantry 1 and both sides of the center at a position where the work gantry 1 is to be constructed so as to be continuous with the road C side. 2 is an underground structure A to be constructed as shown in FIGS.
Drill deeper than the bottom.

【0029】この杭体2は地盤改良などの補助工法を実
施することなく単に地盤Bに打ち込むものとしてコスト
ダウンを図る。なお、地盤が超軟弱地盤である場合に
は、簡易根巻き等の処置を施せばよい。
The pile body 2 is simply driven into the ground B without performing an auxiliary construction method such as ground improvement or the like, thereby reducing the cost. When the ground is an extremely soft ground, a treatment such as simple root winding may be performed.

【0030】杭体2の打設後、上記山留め壁3で囲まれ
た地盤Bをバックホー等の掘削機械Eによって作業構台
1が施工可能な比較的浅い深さまで一次掘削し、掘削土
砂はダンプカー等の運搬車Fに搭載して搬出する。この
場合、道路C側に面した地盤部B1を図3に示すように、
道路Cに向かって上方に傾斜した傾斜面に形成してお
き、この傾斜面を利用して運搬車Fを出入りさせ、最後
にこの地盤B1を掘削、排除することによって山留め壁3
で囲まれた部分に一次掘削により形成した掘削凹部4を
設ける。
After the pile body 2 has been driven, the ground B surrounded by the retaining wall 3 is primarily excavated by a drilling machine E such as a backhoe to a relatively shallow depth at which the work gantry 1 can be constructed. Mounted on a transport vehicle F and carried out. In this case, the ground portion B1 facing the road C side is, as shown in FIG.
It is formed on an inclined surface that is inclined upward toward the road C, and the transport vehicle F enters and exits using the inclined surface. Finally, the ground B1 is excavated and removed, thereby removing the retaining wall 3.
An excavation recess 4 formed by primary excavation is provided in a portion surrounded by.

【0031】一次掘削が終了すると、図5に示すように
作業構台1を施工する。この作業構台1の施工手順は、
まず、上記掘削凹部4を足場にして作業構台1を構築す
べき位置、即ち、通路C側に面した山留め壁3の壁体部
3Aの中央から、通路Cと反対側の山留め壁3の壁体部3B
に対して内方に所定間隔を存した位置に至る部分に型枠
8を組み立てる。この際、上記杭体2の上端部において
は、作業構台1の梁部1aを形成するための型枠部8Aを型
枠8の全幅に亘って組立てておく。この型枠8は掘削凹
部4の底面に立設した多数本のサポートジャッキ9によ
り支持されている。型枠8の組立後、型枠8内にコンク
リートを打設することによって図5、図6に示すよう
に、上面が地表面と略同一水平面上に位置し、且つその
一端縁辺部が通路Cと面一状に連続していると共にその
他の三方外周縁辺部とこれらの三方外周縁辺部に対向し
た山留め壁3の壁体部との間が開口5している地上階ス
ラブの一部からなる作業構台1を築造するものである。
When the primary excavation is completed, the work gantry 1 is constructed as shown in FIG. The construction procedure of this work gantry 1
First, the position where the work gantry 1 is to be constructed using the excavation recess 4 as a scaffold, that is, the wall portion of the retaining wall 3 facing the passage C side.
From the center of 3A, the wall 3B of the retaining wall 3 opposite the passage C
Then, the mold 8 is assembled at a portion reaching a position at a predetermined interval inward. At this time, at the upper end of the pile 2, a form 8 A for forming the beam 1 a of the work gantry 1 is assembled over the entire width of the form 8. The formwork 8 is supported by a large number of support jacks 9 erected on the bottom surface of the excavation recess 4. After assembling the formwork 8, concrete is poured into the formwork 8 so that the upper surface is located substantially on the same horizontal plane as the ground surface as shown in FIGS. And a part of the ground floor slab which has an opening 5 between the other three-side outer peripheral edge portion and the wall portion of the retaining wall 3 facing the three-side outer peripheral edge portion. The work gantry 1 is built.

【0032】この作業構台1の築造後、上記サポートジ
ャッキ9を撤去すると共に型枠8を解体、撤去する一
方、上記図1、図2に示すように、山留め壁3の上端部
四方内周面にH形鋼よりなる腹起し部材6を装着すると
共にこの腹起し部材6と上記開口部5に面している作業
構台1の他端面と両側端面とを山留支保工として複数本
の切梁部材7により連結する。なお、山留め壁3を打設
した地盤Bの支持力が大きい場合には、腹起し部材6や
切梁部材7は必ずしも設ける必要はない。
After the work gantry 1 is built, the support jack 9 is removed, and the form 8 is dismantled and removed. On the other hand, as shown in FIGS. And the other end surface and both side end surfaces of the work gantry 1 facing the opening member 5 and the flared member 6 are formed as a plurality of piers. They are connected by a cutting beam member 7. When the ground B on which the retaining wall 3 is cast has a large supporting force, the bulging member 6 and the cutting beam member 7 do not always need to be provided.

【0033】しかるのち、図7に示すように、この作業
構台1上にバックホー等の掘削機械Eを乗り入れて上記
開口部5を通じて一次掘削された上記掘削凹部4をさら
に深く二次掘削する。この時、作業構台1の下方の地盤
は上記作業構台1上の掘削機械Eでは掘削が困難である
ので、その下方の掘削凹部4内に小型の掘削機械E1を搬
入し、上記掘削機械Eと共に掘削凹部4を地下構造物A
が構築可能な深さまで二次掘削する。
Thereafter, as shown in FIG. 7, an excavating machine E such as a backhoe is put on the work gantry 1 to excavate the excavated recess 4 primarily excavated through the opening 5 further deeper. At this time, it is difficult to excavate the ground below the work gantry 1 with the excavating machine E on the work gantry 1. Excavation recess 4 is inserted into underground structure A
Secondary drilling to a depth that can be constructed.

【0034】二次掘削後、構築すべき地下構造物Aの基
礎部A1を造成し、次いで、切梁部材7を撤去する。この
基礎部A1を造成するまでは、作業構台1を支持している
複数本の杭体2は多少、沈下する可能性があるが、基礎
部A1の造成後には該基礎部A1に固定、支持されて沈下が
生じることはないので、基礎部A1の打設時に、予め、作
業構台1の高さをチエックし、沈下していればその高さ
を補正する。しかるのち、山留め壁3で囲まれた基礎部
A1上に地下構造物Aを構築する。なお、築造すべき地下
構造物Aは図2、図4、図6において、二点鎖線で示し
ている。
After the secondary excavation, the foundation A1 of the underground structure A to be constructed is formed, and then the girder member 7 is removed. Until the foundation A1 is constructed, the plurality of piles 2 supporting the work gantry 1 may sink slightly, but after the foundation A1 is constructed, the piles 2 are fixed to and supported by the foundation A1. Since the sinking does not occur, the height of the work gantry 1 is checked in advance when the foundation A1 is cast, and if the sinking occurs, the height is corrected. After a while, the foundation surrounded by the retaining wall 3
An underground structure A is constructed on A1. The underground structure A to be constructed is indicated by a two-dot chain line in FIGS.

【0035】この地下構造物Aの構築時において、作業
構台1を支持している杭体2は撤去してもよいが、地下
構造物Aの柱や壁の一部としてそのまま使用してもよ
い。一方、作業構台1は上述したように、地下構造物A
の天井スラブ、即ち、地上1階の床スラブ(地上階スラ
ブ)の一部としてスラブ全体の構築に先行して築造され
ているものであり、従って、この作業構台1を水平方向
に延長するようにスラブを造成して地上階スラブとする
ものである。
At the time of constructing the underground structure A, the pile body 2 supporting the work gantry 1 may be removed, but may be used as it is as a part of the column or wall of the underground structure A. . On the other hand, the work gantry 1 has the underground structure A as described above.
Ceiling slab, that is, a part of the floor slab of the first floor above the ground (ground floor slab), which is constructed prior to the construction of the entire slab. Therefore, the work gantry 1 is extended in the horizontal direction. A slab is formed in the ground floor slab.

【0036】なお、作業構台1をその一部とした地上階
スラブは、上記のように場所打ちコンクリートの打設に
よって造成しているが、作業構台1と共に多数枚のプレ
キャストコンクリート板を敷設、連結することによって
施工してもよく、このように地上階スラブをプレキャト
スコンクリート板によって形成すれば、場所打ちコンク
リートの打設による場合に比較して、工期の短縮を図る
ことができる。地下構造物Aの構築後、地上階層の施工
を行って高層建物を建築するものである。
The ground floor slab, which includes the work gantry 1 as a part, is formed by casting cast-in-place concrete as described above. However, a large number of precast concrete plates are laid together with the work gantry 1 and connected. If the ground floor slab is formed of a precast concrete plate in this way, the construction period can be shortened as compared with the case where cast-in-place concrete is cast. After the construction of the underground structure A, a high-rise building is constructed by constructing the ground floor.

【図面の簡単な説明】[Brief description of the drawings]

【図1】地下構造物構築用作業構台の簡略縦断側面図、FIG. 1 is a simplified longitudinal side view of a working gantry for underground structure construction,

【図2】その平面図、FIG. 2 is a plan view thereof,

【図3】一次掘削を行っている状態の簡略縦断側面図、FIG. 3 is a simplified longitudinal side view of a state where primary excavation is being performed;

【図4】その平面図、FIG. 4 is a plan view thereof,

【図5】作業構台を造成している状態の簡略縦断側面
図、
FIG. 5 is a simplified longitudinal side view of a state where a work gantry is being created;

【図6】造成した作業構台の平面図、FIG. 6 is a plan view of the created work gantry,

【図7】二次掘削を行っている状態の簡略縦断側面図、FIG. 7 is a simplified longitudinal side view of a state where secondary excavation is being performed;

【図8】施工フロー図、FIG. 8 is a construction flow diagram,

【図9】従来例を説明するための縦断側面図。FIG. 9 is a longitudinal sectional side view for explaining a conventional example.

【符号の説明】[Explanation of symbols]

A 地下構造物 B 地盤 C 道路 1 作業構台 1a 梁部 2 杭体 3 山留め壁 4 掘削凹部 5 開口部 7 切梁部材 A Underground structure B Ground C Road 1 Work gantry 1a Beam 2 Pile 3 Mountain retaining wall 4 Excavation recess 5 Opening 7 Cut beam member

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 山留め壁により囲まれた地中に地下構造
物を構築する際の作業構台であって、構築すべき地下構
造物の底部よりも深部にまで打設した複数本の杭体上に
これらの杭体により支持された地上階スラブの一部を施
工してこの地上階スラブの一部により作業構台を形成
し、この作業構台の外周端部の一部を地表面に略同一水
平面上で面一状態に連続させていることを特徴とする地
下構造物構築用作業構台。
1. A work gantry for constructing an underground structure in the ground surrounded by a retaining wall, wherein a plurality of piles are cast deeper than the bottom of the underground structure to be constructed. A part of the ground floor slab supported by these piles is constructed to form a work gantry with a part of the ground floor slab, and a part of the outer peripheral end of the work gantry is substantially flush with the ground surface. A working gantry for constructing an underground structure, wherein the working gantry is continuously flush with the above.
【請求項2】 作業構台における地表面に略同一水平面
上で面一状態に連続させている一端部以外の外周端部の
端面と山留め壁の上端部とを切梁部材により連結してい
ることを特徴とする請求項1に記載の地下構造物構築用
作業構台。
2. An end face of an outer peripheral end other than one end continuous with the ground surface of the work gantry on a substantially same horizontal plane and an upper end of the retaining wall are connected by a cutting beam member. The working gantry for constructing an underground structure according to claim 1, wherein:
【請求項3】 作業構台の下面に一体に設けている梁部
を杭体の上端に支持させていることを特徴とする請求項
1または請求項2に記載の地下構造物構築用作業構台。
3. The work gantry for constructing an underground structure according to claim 1, wherein a beam portion integrally provided on a lower surface of the work gantry is supported on an upper end of the pile body.
【請求項4】 作業構台は複数枚のプレキャストコンク
リート板を設置することによって形成されていることを
特徴とする請求項1、請求項2又は請求項3に記載の地
下構造物構築用作業構台。
4. The work gantry according to claim 1, wherein the work gantry is formed by installing a plurality of precast concrete plates.
【請求項5】 建設すべき地下構造物の周辺地盤に山留
め壁を施工すると共にこの山留め壁で囲まれた地盤に地
下構造物の底部よりも深部にまで複数本の杭体を打設す
る工程と、山留め壁で囲まれた地盤を一次掘削したのち
上記杭体の上端に支持され且つその外周端部の一部が地
表面に略同一水平面上で面一状態に連続するように地上
階スラブの一部を施工してこの地上階スラブの一部によ
って作業構台を形成する工程とからなることを特徴とす
る地下構造物構築用作業構台の構築方法。
5. A step of constructing a mountain retaining wall around the underground structure to be constructed and driving a plurality of piles deeper than the bottom of the underground structure in the ground surrounded by the retaining wall. And a ground floor slab supported by the upper end of the pile body after primary excavation of the ground surrounded by the retaining wall, and such that a part of the outer peripheral end thereof is substantially flush with the ground surface and substantially flush with the ground surface. And constructing a work gantry with a part of the ground floor slab by constructing a part of the work gantry.
【請求項6】 作業構台の形成後、この作業構台におけ
る上記外周端部の一部以外の部分の外周端面と上記山留
め壁の上端部とを切梁部材により連結することを特徴と
する請求項5に記載の地下構造物構築用作業構台の構築
方法。
6. After forming the work gantry, an outer peripheral end surface of the work gantry other than a part of the outer peripheral end and an upper end of the retaining wall are connected by a cutting beam member. 6. The method for constructing a work gantry for constructing an underground structure according to 5.
【請求項7】 作業構台の形成後に該作業構台の下方及
び周辺の地盤を構築すべき地下構造物の高さに相当する
深さまで二次掘削し、掘削凹部の底面に地下構造物の基
礎部を構築すると共に地下構造物の柱及び壁と上記作業
構台を一部に用いた地上階スラブを構築することを特徴
とする請求項5又は請求項6に記載の地下構造物構築用
作業構台の構築方法。
7. After the work gantry is formed, secondary excavation is performed to a depth corresponding to the height of an underground structure to be constructed below and around the work gantry. The work gantry for underground structure construction according to claim 5 or 6, wherein a ground floor slab using at least a part of the work gantry and pillars and walls of the underground structure is constructed. How to build.
【請求項8】 地下構造物の基礎部の構築後において、
地上階スラブの一部によって形成している作業構台の高
さが構築すべき地上階スラブの高さに対してずれている
場合にそのずれを補正することを特徴とする請求項5、
請求項6又は請求項7に記載の地下構造物構築用作業構
台の構築方法。
8. After the foundation of the underground structure is constructed,
6. When the height of the work gantry formed by a part of the ground floor slab is shifted from the height of the ground floor slab to be constructed, the shift is corrected.
A method for constructing a work gantry for constructing an underground structure according to claim 6 or 7.
JP2000158768A 2000-05-29 2000-05-29 Construction method of underground structure Expired - Lifetime JP4267175B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000158768A JP4267175B2 (en) 2000-05-29 2000-05-29 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000158768A JP4267175B2 (en) 2000-05-29 2000-05-29 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JP2001336164A true JP2001336164A (en) 2001-12-07
JP4267175B2 JP4267175B2 (en) 2009-05-27

Family

ID=18663193

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000158768A Expired - Lifetime JP4267175B2 (en) 2000-05-29 2000-05-29 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JP4267175B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014114941A3 (en) * 2013-01-25 2015-04-09 James Crawford Thomson Method and apparatus for forming tunnels and tunnels formed thereby
JP2021188433A (en) * 2020-06-03 2021-12-13 株式会社豊田中央研究所 Road structure and road structure manufacturing method
CN114032910A (en) * 2021-07-28 2022-02-11 中国建筑一局(集团)有限公司 Narrow foundation pit ramp structure and unearthing method using same

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014114941A3 (en) * 2013-01-25 2015-04-09 James Crawford Thomson Method and apparatus for forming tunnels and tunnels formed thereby
US9702094B2 (en) 2013-01-25 2017-07-11 James Crawford Thomson Method and apparatus for forming tunnels and tunnels formed thereby
JP2021188433A (en) * 2020-06-03 2021-12-13 株式会社豊田中央研究所 Road structure and road structure manufacturing method
JP7269197B2 (en) 2020-06-03 2023-05-08 株式会社豊田中央研究所 ROAD STRUCTURE AND METHOD FOR MANUFACTURING ROAD STRUCTURE
CN114032910A (en) * 2021-07-28 2022-02-11 中国建筑一局(集团)有限公司 Narrow foundation pit ramp structure and unearthing method using same
CN114032910B (en) * 2021-07-28 2023-10-03 中建一局集团华南建设有限公司 Narrow foundation pit ramp structure and soil discharging method using same

Also Published As

Publication number Publication date
JP4267175B2 (en) 2009-05-27

Similar Documents

Publication Publication Date Title
JP2008013926A (en) Existing building foundation reinforcing method
JP2001241053A (en) Method for constructing underground structure
JP4881555B2 (en) Construction method of underground structure
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
JP4226954B2 (en) Underpinning method and viaduct
KR0179708B1 (en) Working method for underground structure of a building
CN114351761B (en) Construction method of pre-buried frame column at middle partition wall of underground structure
JPH1136338A (en) Construction method of underground structure
JP2003193495A (en) Underground structure constructing method
JP2001336164A (en) Working platform for constructing underground structure and constructing method thereof
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JP3930954B2 (en) Construction method of structure
JP2003003420A (en) Supporting member for prefabricated bridge
JP2845060B2 (en) Construction method of underground construction by fully automatic building construction system
JPH0754364A (en) Construction method of basement floor
KR200428941Y1 (en) Strut system of temporary retaining wall
JP2656892B2 (en) Underground structure construction method and continuous underground wall construction method
KR102500013B1 (en) Method for constructing underground structure
JPH07138972A (en) Construction method for underground skeleton
KR100663108B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JPH0654016B2 (en) Underground space construction method
JP7204228B2 (en) Underground beam construction method
JP7384755B2 (en) Core material and upper core material removal method
JP2915746B2 (en) Foundation formwork

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060908

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080711

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080729

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080926

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090120

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090218

R150 Certificate of patent or registration of utility model

Ref document number: 4267175

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150227

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term