JP2001173098A - Mobile frame trestle for constructing dome-like roof and construction method - Google Patents

Mobile frame trestle for constructing dome-like roof and construction method

Info

Publication number
JP2001173098A
JP2001173098A JP35547199A JP35547199A JP2001173098A JP 2001173098 A JP2001173098 A JP 2001173098A JP 35547199 A JP35547199 A JP 35547199A JP 35547199 A JP35547199 A JP 35547199A JP 2001173098 A JP2001173098 A JP 2001173098A
Authority
JP
Japan
Prior art keywords
wire
roof
roof frame
workbench
dome
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP35547199A
Other languages
Japanese (ja)
Other versions
JP3794465B2 (en
Inventor
Haruo Hoshino
春夫 星野
Tadao Mikami
忠雄 三上
Kenichi Miyazaki
賢一 宮崎
Hidetoshi Hayashida
英俊 林田
Hideo Oka
日出夫 岡
Daisaku So
大作 荘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP35547199A priority Critical patent/JP3794465B2/en
Publication of JP2001173098A publication Critical patent/JP2001173098A/en
Application granted granted Critical
Publication of JP3794465B2 publication Critical patent/JP3794465B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with a constructing frame trestle and timbering for supporting a steel skeleton truss top part to facilitate measurement and correction of the position of split truss units to be sequentially connected in a no- timbering construction method, and to secure safety of a high-lift work. SOLUTION: After a new split unit 46 is put in the connecting state on a working bench 1 connected to an existing part of a roof frame 45, a suspending wire 26 is connected to the existing part of the roof frame, and a lifting wire 27 is connected to the adjacent existing split unit in the circumferential direction. After the working bench is lowered to a designated height by winch driving for the suspending wire 26, the working bench is lifted by winch driving for the lifting wire 2, thereby turning the load of the working bench from the suspending wire to the lifting wire to move the working bench in the circumferential direction. A further new split unit is sequentially connected to the moved working bench to form a circumferential ring in the inner periphery of the existing part. This operation is repeated to form a dome-like roof.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はドーム状屋根の施工
に使用される移動式作業構台とこれを用いた屋根施工方
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a movable work gantry used for constructing a dome-shaped roof, and a roof construction method using the same.

【0002】[0002]

【従来の技術】ドーム状屋根を構築する場合、屋根全体
を支える仮設構台を組立て、この仮設構台の上で鉄骨ト
ラスを組み立てる方法が一般的であるが、この場合仮設
構台の費用が大きいこと、屋根工事が終了するまで内部
の工事ができないこと等の問題点がある。そこで、これ
に対処すべく特開平3−260237に示すように、屋
根の架設範囲の中央に架設構台を建てると共に、架設範
囲の一部に架設構台から遠心方向へ延びる仮設構台を仮
設し、該仮設構台と屋根を支持する下部構造とのそれぞ
れの上面にジャッキ付きローラ支承を設けておき、架設
範囲の所望の位置から架構ユニットを1ユニットまたは
数ユニットずつ架設構台および下部構造間に架設しなが
ら、架設された架構ユニットを架設構台回りに順次回転
移動させることにより、全ての架構ユニットを放射状に
配置してドーム架構を形成する架設工法が提案されてい
る。一方、比較的小規模な屋根の工事の場合には、仮設
構台を使用せずに鉄骨トラスを組み立てる無支保工工法
が行われており、これを大規模な屋根の工事にも適用す
ることが考えられている。
2. Description of the Related Art When constructing a dome-shaped roof, it is common to assemble a temporary gantry that supports the entire roof, and assemble a steel truss on the temporary gantry. In this case, however, the cost of the temporary gantry is high. There is a problem that the internal construction cannot be performed until the roof construction is completed. To cope with this, as shown in JP-A-3-260237, a erection gantry is built at the center of the erection area of the roof, and a temporary gantry extending in the centrifugal direction from the erection gantry is temporarily installed at a part of the erection area. Roller bearings with jacks are provided on the upper surfaces of the temporary gantry and the lower structure that supports the roof, and one or several frame units are erected between the erection gantry and the lower structure from a desired position in the erection range. There has been proposed a construction method in which all the frame units are radially arranged to form a dome frame by sequentially rotating the frame units constructed around the frame. On the other hand, in the case of construction of relatively small roofs, the unsupported construction method of assembling steel trusses without using temporary gantry is performed, and this can be applied to construction of large-scale roofs. It is considered.

【0003】[0003]

【発明が解決しようとする課題】上記公知例では、地上
から構築した架設構台やジャッキ付きローラ支承等の大
がかりな設備を要するという問題点がある。一方、無支
保工工法では、鉄骨トラスを下方から支持する支持点が
ないため、鉄骨トラス組立時に、分割トラスユニットの
位置測定や位置修正が困難で多大な労力を必要とすると
共に、組立を鉄骨トラス上で行うため高所作業時の安全
性等に問題がある。
In the above-mentioned known example, there is a problem that a large-scale facility such as an installation gantry constructed from the ground or a roller bearing with a jack is required. On the other hand, in the unsupported construction method, since there is no support point for supporting the steel truss from below, it is difficult to measure and correct the position of the split truss unit when assembling the steel truss, and a great deal of labor is required. Since it is performed on a truss, there is a problem in safety at the time of work at a high place.

【0004】本発明は、分割ユニットを順次連結して屋
根架構を形成することにより、屋根架構頂部を支持する
架設構台等を不要とし、また、分割ユニットの組立を移
動式構台上で行うことにより、分割ユニットの位置測定
や位置修正を容易にすると共に、高所作業の安全性も確
保する。
[0004] The present invention eliminates the need for a gantry or the like for supporting the roof frame top by sequentially connecting the division units to form a roof frame, and also assembles the division units on a movable gantry. In addition to facilitating the position measurement and position correction of the divided unit, the safety of work at height is also ensured.

【0005】[0005]

【課題を解決するための手段】第1の手段として、屋根
架構45を複数の分割ユニット46で形成するドーム状
屋根の施工に使用する構台であって、上記屋根架構45
の既設部分の下面側に連結部材16を介して一半部が連
結され、かつ、他半部は未設部分下面側に突設する作業
台1を有し、該作業台は、互いに揺動自在に枢着された
複数の台部2、3、4と、隣接する一対の台部間に配置
されて、これら一対の台部上面の相互の傾斜角度を任意
の角度に設定自在な角度調整手段10とを有し、上記作
業台1の一半部に位置する台部は、吊下ろしワイヤ26
が巻かれた複数の第1ウインチ25aと吊上げワイヤ2
7が巻かれた複数の第2ウインチ25bとを有し、上記
吊下ろしワイヤ26は屋根架構の既設部分の下面側に連
結自在な第1クランプ部材35aを有し、かつ吊上げワ
イヤ27は既設部分内端に連結された分割ユニット46
の下面側に連結自在な第2クランプ部材35bを有し、
上記作業台1の連結部材16を解除し、かつ吊下ろしワ
イヤ26用のウインチ駆動で作業台を所定高さまで吊り
下ろした後、吊上げワイヤ27用のウインチ駆動で作業
台を吊り上げることで、作業台の荷重を吊下ろしワイヤ
26から吊上げワイヤ27へ盛り替えて作業台を周方向
または内方へ移動可能に設けた。
As a first means, the present invention relates to a gantry used for constructing a dome-shaped roof in which a roof frame 45 is formed by a plurality of divided units 46.
Has a work table 1 connected to the lower surface of the existing part via a connecting member 16 and the other half has a work table 1 protruding from the lower surface of the non-installed part. Angle adjusting means which is arranged between a plurality of bases 2, 3, 4 pivotally mounted on the base and a pair of bases adjacent to each other, and which can freely set the mutual inclination angle of the upper surfaces of the pair of bases to an arbitrary angle. 10 and a platform located in one half of the work table 1 is a suspension wire 26.
Is wound around the plurality of first winches 25a and the lifting wires 2
7 is wound, a plurality of second winches 25b are wound, the hanging wire 26 has a first clamp member 35a that can be freely connected to the lower surface side of the existing portion of the roof frame, and the lifting wire 27 is connected to the existing portion. Division unit 46 connected to the inner end
Has a freely connectable second clamp member 35b on the lower surface side of
After the connecting member 16 of the work table 1 is released and the work table is suspended to a predetermined height by the winch drive for the hanging wire 26, the work table is lifted by the winch drive for the lifting wire 27, whereby the work table is lifted. The work table was provided so as to be movable in the circumferential direction or inward by changing the load from the wire 26 to the lifting wire 27.

【0006】第2の手段として、屋根架構45を複数の
分割ユニット46で形成するドーム状屋根の施工方法に
おいて、上記屋根架構45の外周部を、別に設けた仮設
構台上で組み立てた後、該仮設構台を撤去し、上記屋根
架構の既設部分の下面側に作業台1の一半部を連結し
て、他半部を未設部分下面側へ突設し、該作業台上で、
上記屋根架構の既設部分内端へあらたな分割ユニット4
6を連結し、上記作業台1にウインチを介して取り付け
た吊下ろしワイヤ26と吊上げワイヤ27とのうち、吊
下ろしワイヤ26を上記屋根架構の既設部分の下面側
に、かつ吊上げワイヤ27を周方向において隣接する既
設部分またはあらたに連結した分割ユニット46の下面
側に、それぞれ連結し、上記屋根架構に対する作業台の
連結を解除し、かつ吊下ろしワイヤ26用のウインチ駆
動で作業台を所定高さまで吊り下ろした後、吊上げワイ
ヤ27用のウインチ駆動で作業台を吊り上げることで、
作業台の荷重を吊下ろしワイヤから吊上げワイヤへ盛り
替えて作業台を周方向または内方へ移動させ、移動後の
作業台を屋根架構に連結した後、作業台上で更にあらた
な分割ユニットを順次連結することで円周状のリングま
たは径方向に伸びるアーチ形の鉄骨トラスを形成する。
As a second means, in a method of constructing a dome-shaped roof in which a roof frame 45 is formed by a plurality of divided units 46, an outer peripheral portion of the roof frame 45 is assembled on a separately provided temporary gantry. The temporary gantry is removed, one half of the work table 1 is connected to the lower surface of the existing part of the roof frame, and the other half is protruded to the lower surface of the uninstalled part, and on the work table,
A new split unit 4 at the inner end of the existing part of the roof frame
6 and the suspension wire 26 and the suspension wire 27 attached to the work table 1 via a winch, the suspension wire 26 is arranged on the lower surface side of the existing portion of the roof frame, and the suspension wire 26 is In the direction, the work table is connected to the existing portion or the lower surface side of the divided unit 46 newly connected, the connection of the work table to the roof frame is released, and the work table is driven to a predetermined height by a winch drive for the hanging wire 26. After hanging down, the work table is lifted by the winch drive for the lifting wire 27,
After lowering the load on the work platform, changing the wires from lifting wires to lifting wires, moving the work platform in the circumferential direction or inward, connecting the moved work platform to the roof frame, and then creating a new split unit on the work platform Sequential connection forms a circumferential ring or a radially extending arched steel truss.

【0007】[0007]

【発明の実施の形態】以下、本発明に係るドーム状屋根
施工用移動式構台を図面に示す実施形態を参照しながら
説明する。1は作業台で、3つの台部2、3、4から形
成され、各台部は上下に所定間隔をおいて平行状に配置
された一対の上板5及び下板6と、これら両板間にジグ
ザグ状に配列されて上下両板を互いに連結する複数の連
結斜板7とを有する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A movable gantry for dome-shaped roof construction according to the present invention will be described below with reference to an embodiment shown in the drawings. Reference numeral 1 denotes a work table, which is formed of three table parts 2, 3, and 4, each of which is a pair of upper plate 5 and lower plate 6, which are arranged in parallel at predetermined intervals vertically, and both plates. There are a plurality of connecting swash plates 7 arranged in a zigzag shape and connecting the upper and lower plates to each other.

【0008】各台部2、3、4は前後一列に並設され、
前後両端に位置する台部2、4の各上板5は、中央に位
置する台部3の上板5の前後両側にヒンジ8、8を介し
て揺動自在に枢着され、また、これら両台部2、4の各
下板6は左右一対の油圧ジャッキ10、10を介して中
央の台部3の下板6の前後両側に連結する。なお、油圧
ジャッキ10、10はヒンジを介して隣接する下板6間
に揺動自在に枢着する。また、後端の台部4と中央の台
部3とのそれぞれの上板6の前後両側から3本の支柱1
4を起立して、これら3本の支柱上端を左右方向に伸び
る横向きH形鋼15で連結する。
Each of the bases 2, 3, 4 is arranged in a line in front and rear,
The upper plates 5 of the bases 2 and 4 located at the front and rear ends are pivotally attached to the front and rear sides of the upper plate 5 of the base 3 located at the center via hinges 8 and 8 so as to be swingable. The lower plates 6 of the two base portions 2 and 4 are connected to the front and rear sides of the lower plate 6 of the central base portion 3 via a pair of left and right hydraulic jacks 10 and 10. The hydraulic jacks 10 and 10 are pivotally connected between adjacent lower plates 6 via hinges. Also, three pillars 1 from the front and rear sides of the upper plate 6 of the rear end platform 4 and the central platform 3 respectively.
4 and the upper ends of these three columns are connected by a horizontal H-shaped steel 15 extending in the left-right direction.

【0009】16は各H形鋼15の左右両部に設けられ
た連結部材で、H形鋼15に締付けボルト17を介して
固定自在な溝形状の第1クランプ18と、該クランプ上
面に設けた間隔調整部19と、該間隔調整部に自在継手
20を介して連結した溝形状の第2クランプ21とを有
し、該第2クランプは締付けボルト22を介して後述す
る鉄骨トラス45のT字状の第1取付部51の水平板に
固定可能となっている。なお、間隔調整部19は第1ク
ランプ18と第2クランプ21との間隔を調整するもの
で、本実施形態では第1クランプ18上面と自在継手2
0下面とのそれぞれから突設する雌ねじ筒19aと、こ
れら雌ねじ筒内に両端を螺合させた操作棹付きのネジ切
りロッド19bとからなり、操作棹を介してロッド19
bを回すことで間隔調整可能である。
Reference numeral 16 denotes connecting members provided on both right and left portions of each H-shaped steel 15. A first clamp 18 having a groove shape which can be fixed to the H-shaped steel 15 via a fastening bolt 17, and provided on an upper surface of the clamp. And a groove-shaped second clamp 21 connected to the gap adjusting section via a universal joint 20, and the second clamp is connected to a T-shaped truss 45 of a steel truss 45 described later via a tightening bolt 22. It can be fixed to the horizontal plate of the first mounting portion 51 in the shape of a letter. The interval adjusting section 19 adjusts the interval between the first clamp 18 and the second clamp 21. In the present embodiment, the upper surface of the first clamp 18 and the universal joint 2 are adjusted.
0 and a threaded rod 19b with an operating rod screwed into both ends of the female screw cylinder, and the rod 19 is inserted through the operating rod.
By turning b, the interval can be adjusted.

【0010】25a、25bはウインチで、中央台部3
の下板6の4隅に各一対を前後方向に並設して設置さ
れ、これらのうち後側に位置するウインチ25aには吊
下ろしワイヤ26を、かつ前側に位置するウインチ26
bには吊上げワイヤ27を巻きかけている。各ワイヤ
は、上板5に形成した透孔28を通って中央台部3上方
へ延び出し、さらに、上板5に設けたシーブ29(図1
では省略)を介して方向転換自在になっている。なお、
上記ではウインチ25a、25bを下板6の4隅に設け
ているが、これは作業台の昇降時における安定性を考慮
してのことで、従って、安定性が確保されれば3ヵ所で
もよく、或いは5ヵ所以上でもよい。
Reference numerals 25a and 25b denote winches, and
A pair of the lower plate 6 is installed at each of four corners side by side in the front-rear direction. Among them, a hanging wire 26 is attached to a winch 25a located on the rear side, and a winch 26 located on the front side.
A lifting wire 27 is wound around b. Each wire extends through the through-hole 28 formed in the upper plate 5 to extend above the central pedestal 3, and further, a sheave 29 (see FIG. 1) provided in the upper plate 5.
The direction can be freely changed via (omitted). In addition,
Although the winches 25a and 25b are provided at the four corners of the lower plate 6 in the above description, this is in consideration of the stability at the time of raising and lowering the work table. Therefore, three places may be used as long as the stability is secured. Or five or more locations.

【0011】シーブ29は、透孔28を囲む周壁30内
に、4本のローラ31を上方から見てロ字状に配置し
て、これら4本のローラで囲まれる空間を透孔28に連
通させている。該空間から延び出すワイヤはいずれかの
ローラに係合することにより円滑な方向転換が可能であ
る。
The sheave 29 has four rollers 31 arranged in a rectangular shape when viewed from above in a peripheral wall 30 surrounding the through hole 28, and a space surrounded by these four rollers communicates with the through hole 28. Let me. The wire extending from the space can be smoothly turned by engaging one of the rollers.

【0012】35a、35bはワイヤ用のクランプ部材
で、各ワイヤ26、27の先端部に金具36を介して揺
動自在に取り付けた一対の連結棹37のそれぞれの先端
部にコ字形クランプ38を枢着させている。両クランプ
の溝内に後述する鉄骨トラス45から垂下するT字状の
第2取付部52の水平板を嵌合させて締付けボルト40
で締め付けることにより各ワイヤ26、27を鉄骨トラ
スに連結する。
Reference numerals 35a and 35b denote clamp members for wires. A U-shaped clamp 38 is provided at each of the distal ends of a pair of connecting rods 37 which are swingably attached to the distal ends of the wires 26 and 27 via metal fittings 36. Has been pivoted. A horizontal plate of a T-shaped second mounting portion 52 hanging from a steel truss 45 described later is fitted into the groove of each of the clamps, and the tightening bolt 40 is inserted.
To connect the wires 26 and 27 to the steel truss.

【0013】45は屋根架構としての複数の鉄骨トラス
で、各鉄骨トラスは複数の分割トラスユニット46から
形成され、各ユニットは、上弦材47、下弦材48、こ
れらの間に配置されたラティス材49及び束材50から
なり、下弦材48下面から上述の連結部材用の第1取付
部51とワイヤ用の第2取付部52とを垂下する。
Reference numeral 45 denotes a plurality of steel trusses as a roof frame. Each steel truss is formed from a plurality of divided truss units 46. Each unit includes an upper chord 47, a lower chord 48, and a lattice material disposed therebetween. The first attachment portion 51 for the connecting member and the second attachment portion 52 for the wire are suspended from the lower surface of the lower chord material 48.

【0014】次にドーム状屋根の施工方法について説明
する。ドーム状屋根の構造には、放射状、マトリックス
状、直交格子状など種々の構造があるが、いずれの場合
も図8に示すように、円周方向のリングを外周から内周
へ一段ずつ組んでいくのが一般で、本実施形態では上記
構成に係る移動式構台を使用して次の手順により施工す
る。
Next, a method of constructing a dome-shaped roof will be described. The structure of the dome-shaped roof includes various structures such as a radial shape, a matrix shape, and an orthogonal lattice shape. In each case, as shown in FIG. 8, circumferential rings are assembled one by one from the outer periphery to the inner periphery. Generally, this embodiment uses the movable gantry according to the above-described configuration to perform the construction according to the following procedure.

【0015】(1)別途設けた図示しない仮設構台を利
用して、ドーム状屋根の外周部となるべき分割トラスユ
ニット46を円周方向に配設してリング状に組み立てる
ことにより最外周の第1のリング46aを形成した後、
該リングの内周に同様にして第2のリング46bを形成
し、さらに、該リングの内周に第3のリング46cを形
成する。
(1) Using a separately provided temporary gantry (not shown), the divided truss units 46 to be the outer peripheral portion of the dome-shaped roof are arranged in the circumferential direction and assembled in a ring shape to form the outermost outermost truss unit. After forming one ring 46a,
Similarly, a second ring 46b is formed on the inner periphery of the ring, and a third ring 46c is formed on the inner periphery of the ring.

【0016】(2)仮設構台を撤去した後、(1)の方
法で組み立てた各リングを構成する分割トラスユニット
46の径方向に並ぶ任意の一列S(図8参照)に作業台
1を次のようにして連結する。まず、油圧ジャッキ10
の伸縮で作業台1の角度を調整して列Sの曲率に略々一
致させる。次いで、間隔調整部19で第1及び第2クラ
ンプ18、21間の間隔を調整しつつ、第1クランプ1
8をH形鋼15に、かつ第2クランプ21を第1取付部
51に、それぞれ取り付けて締付けボルト17、22で
締め付ける。その際、作業台1の台部2は列Sの最内周
に位置する分割トラスユニット46よりも内方へ突設さ
せる。
(2) After removing the temporary gantry, the workbench 1 is placed next to an arbitrary row S (see FIG. 8) in the radial direction of the divided truss units 46 constituting each ring assembled by the method of (1). Connect as follows. First, the hydraulic jack 10
The angle of the work table 1 is adjusted by the expansion and contraction of the work table 1 so as to substantially match the curvature of the row S. Next, while adjusting the interval between the first and second clamps 18 and 21 by the interval adjuster 19, the first clamp 1
8 is attached to the H-shaped steel 15, and the second clamp 21 is attached to the first mounting portion 51, and tightened with the tightening bolts 17 and 22. At this time, the platform 2 of the work table 1 is protruded more inward than the divided truss unit 46 located at the innermost periphery of the row S.

【0017】(3)上記のようにして作業台1を取り付
けた列Sの内端に連結すべきあらたな分割トラスユニッ
ト46を、図6に示すように作業台1の台部2上方にク
レーン53で吊り下げ、これを作業台上の作業員が連結
する。
(3) A new split truss unit 46 to be connected to the inner end of the row S to which the work table 1 is attached as described above is placed above the base 2 of the work table 1 as shown in FIG. It is hung at 53, and this is connected by a worker on the workbench.

【0018】(4)吊下ろしワイヤ26を、列Sの中央
に位置する分割トラスユニットに連結すると共に、吊上
げワイヤ27を、図1において2点鎖線で示すように周
方向へ延出させることで、周方向において隣接し、か
つ、第3のリング46cに属する分割トラスユニットに
連結する。
(4) The suspension wire 26 is connected to the divided truss unit located at the center of the row S, and the suspension wire 27 is extended in the circumferential direction as shown by a two-dot chain line in FIG. , Adjacent to each other in the circumferential direction and connected to the divided truss units belonging to the third ring 46c.

【0019】(5)連結部材16を解除した後、吊下ろ
しワイヤ26が巻かれたウインチ25a作動により、図
7に示すようにワイヤを巻き出して作業台1を適当距離
だけ吊り下ろした後、吊上げワイヤ27が巻かれたウイ
ンチ25b作動によりワイヤを巻き取って荷重の盛り替
えを行う。このワイヤ巻き取りで作業台1は、周方向に
おいて列Sに隣接する分割トラスユニット列の下方へ移
動する。なお、作業台の吊下ろし距離は荷重の盛り替え
が可能な範囲に設定する。
(5) After the connecting member 16 is released, the wire is unwound by the operation of the winch 25a around which the hanging wire 26 is wound, as shown in FIG. The wire is wound up by the operation of the winch 25b around which the lifting wire 27 is wound to change the load. The work table 1 is moved below the row of divided truss units adjacent to the row S in the circumferential direction by the winding of the wire. The suspension distance of the work table is set in a range in which the load can be changed.

【0020】(6)ワイヤ巻き取りにより作業台1を周
方向へ移動させた後、該作業台を(2)の方法でその上
方に位置する分割トラスユニット列に連結する。
(6) After moving the work table 1 in the circumferential direction by winding the wire, the work table is connected to the row of divided truss units located above the work table by the method (2).

【0021】(7)以後、(3)〜(6)を繰り返すこ
とにより、分割トラスユニットを周方向に連結して、既
設の分割トラスユニット内周に新たなリングを形成す
る。
(7) Thereafter, by repeating (3) to (6), the split truss units are connected in the circumferential direction, and a new ring is formed on the inner circumference of the existing split truss unit.

【0022】(8)新たなリング形成後、その内周にさ
らに新たなリングを形成すべく作業台1を内方へ前進さ
せる。作業台1を前進させるには、吊下ろしワイヤ26
を、列Sを形成する分割トラスユニットのうち最内周の
ユニットに、かつ、吊上げワイヤ27を列Sの内端に連
結した新たな分割トラスユニットに、それぞれ連結す
る。
(8) After forming a new ring, the work table 1 is advanced inward to form a new ring on its inner periphery. To move the work table 1 forward, the hanging wire 26
Is connected to the innermost unit of the split truss units forming the row S, and to a new split truss unit in which the lifting wire 27 is connected to the inner end of the row S.

【0023】(9)次いで、(5)の方法により荷重の
盛り替えを行って作業台1を内方へ移動させることで、
作業台の台部2を新たに形成したリングよりも内方へ突
設させた後、(2)の方法で作業台を連結する。
(9) Next, the work table 1 is moved inward by changing the load according to the method of (5).
After the platform 2 of the workbench protrudes inward from the newly formed ring, the workbench is connected by the method (2).

【0024】(10)以後、(3)〜(6)を繰り返す
ことで新たなリングの内周にさらに新たなリングを形成
する。
(10) Thereafter, (3) to (6) are repeated to form a new ring on the inner periphery of the new ring.

【0025】なお、上記では複数の分割トラスユニット
を円周方向に配設して形成したリングを、外周から内周
へ一段ずつ組んで屋根架構を架設する工法に本発明を適
用した例について説明したが、これに限らず複数の分割
トラスユニットを径方向に順次連結して径方向に伸びる
アーチ状の鉄骨トラスを形成し、該鉄骨トラスを円周方
向に一段ずつ組んで屋根架構を形成する工法にも適用す
ることが可能である。この場合には、吊下ろしワイヤ2
6を既設の分割トラスユニットに、かつ、吊上げワイヤ
27を新たに連結した分割トラスユニットに、それぞれ
連結する。こうすることにより、荷重の盛り替えで作業
台1は周方向ではなく常に内方へ前進移動する。
In the above description, an example in which the present invention is applied to a method of constructing a roof frame by assembling a ring formed by arranging a plurality of divided truss units in the circumferential direction one by one from the outer periphery to the inner periphery. However, the present invention is not limited to this, and a plurality of split truss units are sequentially connected in the radial direction to form an arch-shaped steel truss extending in the radial direction, and the steel trusses are assembled one by one in the circumferential direction to form a roof frame. It is also possible to apply to the construction method. In this case, the hanging wire 2
6 is connected to the existing split truss unit, and the lifting wire 27 is connected to the newly connected split truss unit. In this way, the workbench 1 always moves inward, not in the circumferential direction, by changing the load.

【0026】[0026]

【発明の効果】請求項1及び2に係る発明は、未設の分
割ユニットを既設の分割ユニットに順次連結して屋根架
構を形成するため、該架構頂部を支持する架設構台が不
要であり、しかも屋根架構を昇降させる必要も、また、
回転移動させる必要もないため、屋根架構用のジャッキ
付きローラ支承等も不要となりコスト節減が可能とな
る。また、分割ユニットの組立を移動式構台上で行うた
め、分割ユニットの位置測定や位置修正が容易であり、
さらに高所作業の安全性も確保される。
According to the first and second aspects of the present invention, a roof frame is formed by sequentially connecting an undivided unit to an existing unit, so that a frame supporting the frame top is unnecessary. Moreover, it is necessary to raise and lower the roof frame,
Since there is no need to rotate and move, there is no need for a roller support with a jack for a roof frame, and the cost can be reduced. In addition, since the division unit is assembled on a movable gantry, position measurement and position correction of the division unit are easy,
In addition, the safety of working at heights is ensured.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係るドーム状屋根施工用移動式構台の
斜視図。
FIG. 1 is a perspective view of a movable gantry for dome-shaped roof construction according to the present invention.

【図2】同じく、連結部材の断面図。FIG. 2 is a cross-sectional view of the connecting member.

【図3】同じく、シーブの平面図。FIG. 3 is a plan view of a sheave.

【図4】同じく、図3の側断面図。4 is a side sectional view of FIG. 3;

【図5】同じく、ワイヤ用クランプ部材の一部断面図。FIG. 5 is a partial cross-sectional view of the wire clamp member.

【図6】同じく、屋根架構に移動式構台をセットした状
態を示す概略図。
FIG. 6 is a schematic diagram showing a state where a movable gantry is set on a roof frame.

【図7】同じく、荷重の盛り替え状態を示す説明図。FIG. 7 is an explanatory view showing the state of changing the load.

【図8】本発明に係るドーム状屋根施工方法の説明図。FIG. 8 is an explanatory view of a dome-shaped roof construction method according to the present invention.

【符号の説明】 1 作業台 2、3、4 台部 10 角度調整手段 16 連結部材 25a、25b ウインチ 26 吊下ろしワイヤ 27 吊上げワイヤ 35a、35b クランプ部材 45 屋根架構 46 分割ユニット[Description of Reference Numerals] 1 work table 2, 3, 4 base unit 10 angle adjusting means 16 connecting member 25a, 25b winch 26 hanging wire 27 lifting wire 35a, 35b clamp member 45 roof frame 46 division unit

───────────────────────────────────────────────────── フロントページの続き (72)発明者 宮崎 賢一 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 (72)発明者 林田 英俊 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 (72)発明者 岡 日出夫 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 (72)発明者 荘 大作 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 Fターム(参考) 2E174 AA01 BA05 CA03 CA12 CA16 CA35 CA38 DA11 DA24 DA58 EA03  ──────────────────────────────────────────────────続 き Continuing from the front page (72) Inventor Kenichi Miyazaki 1-5-1, Otsuka, Inzai City, Chiba Prefecture Inside the Research Institute of Takenaka Corporation (72) Inventor Hidetoshi Hayashida 1-5-1, Otsuka, Inzai City, Chiba Prefecture Takenaka Corporation Technical Research Institute, Inc. (72) Inventor Oka Hideo 1-5-1, Otsuka, Inzai City, Chiba Prefecture In-house Takenaka Corporation Technical Research Institute, (72) Inventor Daisaku Sozo, Otsuka 5-chome, Inzai City, Chiba Prefecture Address 1 F-term in Takenaka Corporation Technical Research Institute (reference) 2E174 AA01 BA05 CA03 CA12 CA16 CA35 CA38 DA11 DA24 DA58 EA03

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】屋根架構45を複数の分割ユニット46で
形成するドーム状屋根の施工に使用する構台であって、 上記屋根架構45の既設部分の下面側に連結部材16を
介して一半部が連結され、かつ、他半部は未設部分下面
側に突設する作業台1を有し、 該作業台は、互いに揺動自在に枢着された複数の台部
2、3、4と、隣接する一対の台部間に配置されて、こ
れら一対の台部上面の相互の傾斜角度を任意の角度に設
定自在な角度調整手段10とを有し、 上記作業台1の一半部に位置する台部は、吊下ろしワイ
ヤ26が巻かれた複数の第1ウインチ25aと吊上げワ
イヤ27が巻かれた複数の第2ウインチ25bとを有
し、 上記吊下ろしワイヤ26は屋根架構の既設部分の下面側
に連結自在な第1クランプ部材35aを有し、かつ吊上
げワイヤ27は既設部分内端に連結された分割ユニット
46の下面側に連結自在な第2クランプ部材35bを有
し、 上記作業台1の連結部材16を解除し、かつ吊下ろしワ
イヤ26用のウインチ駆動で作業台を所定高さまで吊り
下ろした後、吊上げワイヤ27用のウインチ駆動で作業
台を吊り上げることで、作業台の荷重を吊下ろしワイヤ
26から吊上げワイヤ27へ盛り替えて作業台を周方向
または内方へ移動可能に設けたことを特徴とするドーム
状屋根施工用の移動式作業構台。
1. A gantry used for constructing a dome-shaped roof in which a roof frame 45 is formed by a plurality of divided units 46. One half of the roof frame 45 is provided on a lower surface side of an existing portion of the roof frame 45 via a connecting member 16. The other half has a work table 1 protruding from the lower surface side of the non-installed part, and the work table has a plurality of bases 2, 3, 4 pivotally connected to each other, An angle adjusting means 10 disposed between a pair of adjacent bases and capable of setting the mutual inclination angles of the upper surfaces of the pair of bases to an arbitrary angle; The pedestal portion has a plurality of first winches 25a around which a hanging wire 26 is wound and a plurality of second winches 25b around which a lifting wire 27 is wound. The hanging wire 26 is a lower surface of an existing portion of a roof frame. Has a first clamp member 35a which can be freely connected to the side, and is lifted. The wire 27 has a freely connectable second clamp member 35b on the lower surface side of the division unit 46 connected to the inner end of the existing portion, releases the connection member 16 of the worktable 1, and winches for the hanging wire 26. After the workbench is suspended to a predetermined height by driving, the workbench is lifted by a winch drive for the lifting wire 27, so that the load on the workbench is suspended, the wire 26 is changed to the lifting wire 27, and the workbench is moved in the circumferential direction. Alternatively, a movable work gantry for dome-shaped roof construction, which is provided so as to be movable inward.
【請求項2】屋根架構45を複数の分割ユニット46で
形成するドーム状屋根の施工方法において、 上記屋根架構45の外周部を、別に設けた仮設構台上で
組み立てた後、該仮設構台を撤去し、 上記屋根架構の既設部分の下面側に作業台1の一半部を
連結して、他半部を未設部分下面側へ突設し、 該作業台上で、上記屋根架構の既設部分内端へあらたな
分割ユニット46を連結し、 上記作業台1にウインチを介して取り付けた吊下ろしワ
イヤ26と吊上げワイヤ27とのうち、吊下ろしワイヤ
26を上記屋根架構の既設部分の下面側に、かつ吊上げ
ワイヤ27を周方向において隣接する既設部分またはあ
らたに連結した分割ユニット46の下面側に、それぞれ
連結し、 上記屋根架構に対する作業台の連結を解除し、かつ吊下
ろしワイヤ26用のウインチ駆動で作業台を所定高さま
で吊り下ろした後、吊上げワイヤ27用のウインチ駆動
で作業台を吊り上げることで、作業台の荷重を吊下ろし
ワイヤから吊上げワイヤへ盛り替えて作業台を周方向ま
たは内方へ移動させ、 移動後の作業台を屋根架構に連結した後、作業台上で更
にあらたな分割ユニットを順次連結することで円周状の
リングまたは径方向に伸びるアーチ形の鉄骨トラスを形
成することを特徴とするドーム状屋根施工方法。
2. A method of constructing a dome-shaped roof in which a roof frame 45 is formed by a plurality of divided units 46. In the method for constructing a dome-shaped roof, an outer peripheral portion of the roof frame 45 is assembled on a separately provided temporary gantry, and then the temporary gantry is removed. Then, one half of the worktable 1 is connected to the lower surface side of the existing portion of the roof frame, and the other half is protruded to the lower surface side of the non-installed portion. A new split unit 46 is connected to the end, and of the hanging wire 26 and the lifting wire 27 attached to the work table 1 via a winch, the hanging wire 26 is attached to the lower surface side of the existing portion of the roof frame, In addition, the lifting wire 27 is connected to the existing portion adjacent to the circumferential direction or to the lower surface side of the newly divided unit 46 which is newly connected, and the connection of the work table to the roof frame is released. After the workbench is suspended to a predetermined height by the winch drive for lifting, the worktable is lifted by the winch drive for the lifting wire 27, so that the load on the worktable is changed from the hanging wire to the lifting wire, and the workbench is rotated. After moving the workbench to the roof frame after moving it in the direction or inward, a circular ring or an arch-shaped steel frame extending in the radial direction is obtained by sequentially connecting new division units on the workbench. A dome-shaped roof construction method characterized by forming a truss.
JP35547199A 1999-12-15 1999-12-15 Mobile gantry for dome roof construction and construction method Expired - Fee Related JP3794465B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35547199A JP3794465B2 (en) 1999-12-15 1999-12-15 Mobile gantry for dome roof construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35547199A JP3794465B2 (en) 1999-12-15 1999-12-15 Mobile gantry for dome roof construction and construction method

Publications (2)

Publication Number Publication Date
JP2001173098A true JP2001173098A (en) 2001-06-26
JP3794465B2 JP3794465B2 (en) 2006-07-05

Family

ID=18444148

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35547199A Expired - Fee Related JP3794465B2 (en) 1999-12-15 1999-12-15 Mobile gantry for dome roof construction and construction method

Country Status (1)

Country Link
JP (1) JP3794465B2 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102337785A (en) * 2011-08-19 2012-02-01 徐州中煤百甲重钢结构有限公司 Construction process of ultra-large-span net-frame arch-shaped shed type storage silo
CN102777050A (en) * 2012-08-22 2012-11-14 河北二十冶工程技术有限公司 Assembly type jig frame for longspan pipe truss roof girder
CN104032966A (en) * 2014-06-27 2014-09-10 中国十九冶集团(防城港)设备结构有限公司 Partitioning, hoisting, overhead closing and mounting method for arc-shaped double-layer net racks
CN104947942A (en) * 2015-05-06 2015-09-30 浙江东南网架股份有限公司 Computer-controlled expansion accumulative lifting method for erecting super-high arch grid structure
CN105484502A (en) * 2014-10-10 2016-04-13 五冶集团上海有限公司 Combination installation method for steel structure roofing purlins and support bars of industrial factory building
CN106988416A (en) * 2017-04-18 2017-07-28 清华大学建筑设计研究院有限公司 A kind of steel and Combined concrete space triangular ring truss structure
CN107013044A (en) * 2016-01-27 2017-08-04 万达商业规划研究院有限公司 The modularization installation method of lighting roof and the lowering or hoisting gear for installing lighting roof
CN108643357A (en) * 2018-05-21 2018-10-12 中国二十二冶集团有限公司 Across the installation on ground method of arch grid structure starting and its dedicated infrastructure
CN110778127A (en) * 2019-11-12 2020-02-11 上海宝冶集团有限公司 In-situ assembling and lifting construction aligning method for multilayer steel truss
CN111155770A (en) * 2020-01-17 2020-05-15 中国二十二冶集团有限公司 Steel roof truss assembling device and construction method for assembling steel roof truss
CN111705931A (en) * 2020-06-03 2020-09-25 中国化学工程第六建设有限公司 Construction method of large-span grid structure
CN114837440A (en) * 2022-05-24 2022-08-02 通号建设集团第一工程有限公司 Construction method of large-span arch-type steel truss roof

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102337785A (en) * 2011-08-19 2012-02-01 徐州中煤百甲重钢结构有限公司 Construction process of ultra-large-span net-frame arch-shaped shed type storage silo
CN102777050A (en) * 2012-08-22 2012-11-14 河北二十冶工程技术有限公司 Assembly type jig frame for longspan pipe truss roof girder
CN102777050B (en) * 2012-08-22 2015-03-25 河北二十冶工程技术有限公司 Assembly type jig frame for longspan pipe truss roof girder
CN104032966A (en) * 2014-06-27 2014-09-10 中国十九冶集团(防城港)设备结构有限公司 Partitioning, hoisting, overhead closing and mounting method for arc-shaped double-layer net racks
CN105484502A (en) * 2014-10-10 2016-04-13 五冶集团上海有限公司 Combination installation method for steel structure roofing purlins and support bars of industrial factory building
CN105484502B (en) * 2014-10-10 2017-11-07 五冶集团上海有限公司 A kind of industrial premises steel structural roof purlin and support bar combined installation method
CN104947942A (en) * 2015-05-06 2015-09-30 浙江东南网架股份有限公司 Computer-controlled expansion accumulative lifting method for erecting super-high arch grid structure
CN104947942B (en) * 2015-05-06 2017-03-01 浙江东南网架股份有限公司 Hypervelocity arch grid structure architecture computer controls the installation method extending out accumulation lifting
CN107013044A (en) * 2016-01-27 2017-08-04 万达商业规划研究院有限公司 The modularization installation method of lighting roof and the lowering or hoisting gear for installing lighting roof
CN106988416A (en) * 2017-04-18 2017-07-28 清华大学建筑设计研究院有限公司 A kind of steel and Combined concrete space triangular ring truss structure
CN108643357A (en) * 2018-05-21 2018-10-12 中国二十二冶集团有限公司 Across the installation on ground method of arch grid structure starting and its dedicated infrastructure
CN110778127A (en) * 2019-11-12 2020-02-11 上海宝冶集团有限公司 In-situ assembling and lifting construction aligning method for multilayer steel truss
CN111155770A (en) * 2020-01-17 2020-05-15 中国二十二冶集团有限公司 Steel roof truss assembling device and construction method for assembling steel roof truss
CN111155770B (en) * 2020-01-17 2023-11-03 中国二十二冶集团有限公司 Steel roof truss splicing device and steel roof truss splicing construction method
CN111705931A (en) * 2020-06-03 2020-09-25 中国化学工程第六建设有限公司 Construction method of large-span grid structure
CN114837440A (en) * 2022-05-24 2022-08-02 通号建设集团第一工程有限公司 Construction method of large-span arch-type steel truss roof

Also Published As

Publication number Publication date
JP3794465B2 (en) 2006-07-05

Similar Documents

Publication Publication Date Title
JP2001173098A (en) Mobile frame trestle for constructing dome-like roof and construction method
CN107816209B (en) The large-scale Roof Truss construction technology of installation is lifted across outer two sides
JP2012149393A (en) Elevating scaffold
JP3516056B2 (en) Rotary lift-up construction method for dome roof
JP2579715B2 (en) External tower crane
JPS5912827B2 (en) Demolition method for tower-like structures and scaffolding equipment for demolition
JP3693893B2 (en) Structure construction method and construction apparatus
JP3708060B2 (en) Construction method of roof structure
JPH09195497A (en) Elevatable scaffold
JPH0718743A (en) Construction method for large span domelike roof
JP3204283B2 (en) Large space structure construction equipment
JP2779258B2 (en) Roof lift-up method
JPH1088786A (en) Scaffold for columnar structure
JP3219934U (en) Roof intermediate structure and roof structure
CN211946033U (en) Utilize heavy object hoisting device of H shaped steel post shore
JP2877286B2 (en) Construction method of large roof dome truss
JP4571760B2 (en) Building construction method
JP3002054U (en) Tower crane with multiple main columns as tower mast
JP2994205B2 (en) Structural assembly method
JPH0460038A (en) Constructing method of large span dome roof
JP2903006B2 (en) Push-up method for large roof
CN111217240A (en) Gantry frame of gantry crane and mounting method thereof
KR20230012230A (en) Lift car for installing deck plate and installing method of deck plate using the same
JPH0475337B2 (en)
SU583263A1 (en) Sliding form

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040618

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060327

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060404

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060405

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090421

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100421

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100421

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110421

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110421

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120421

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120421

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130421

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130421

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140421

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees