JP3693893B2 - Structure construction method and construction apparatus - Google Patents

Structure construction method and construction apparatus Download PDF

Info

Publication number
JP3693893B2
JP3693893B2 JP2000218230A JP2000218230A JP3693893B2 JP 3693893 B2 JP3693893 B2 JP 3693893B2 JP 2000218230 A JP2000218230 A JP 2000218230A JP 2000218230 A JP2000218230 A JP 2000218230A JP 3693893 B2 JP3693893 B2 JP 3693893B2
Authority
JP
Japan
Prior art keywords
jack
liner
lower structure
jacks
laminated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000218230A
Other languages
Japanese (ja)
Other versions
JP2002030810A (en
Inventor
順 河野
清幸 岡部
博之 三阪
横山  稔
俊之 川添
哲郎 山下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2000218230A priority Critical patent/JP3693893B2/en
Publication of JP2002030810A publication Critical patent/JP2002030810A/en
Application granted granted Critical
Publication of JP3693893B2 publication Critical patent/JP3693893B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、例えば上弦材と下弦材を腹材を介して接合してなるトラス材を網目状に組み立ててなる大屋根構造物等の構造物の構築方法および構築装置に関し、トラス構造のみならず桁構造等にも適用可能である。
【0002】
【従来の技術】
大屋根構造物等の構造物は、通常、適宜数のブロックに分割されたものを組み立てて構築がなされるが、構造物を構成する部材数や種類が多いことからその構築時には仕分けや選出作業に多くの時間と手間を必要としていた。また、組立の際に分割されたブロックを確実に接合できないと、構造物自体の自立が成立しないことになるため、構築には仮設サポートを必要とした。
このような仮設サポートを使用した構造物の構築方法の従来例を、図3によって説明する。
【0003】
構造物の周縁となる下部構造体(躯体)23内の基礎上に立設された多数の仮設サポート22は、予め構造物21が構築される場所の地上の基礎G上に必要とされる数だけ立設される。仮設サポート22の頂部には、ジャッキ29および積層ライナー31が固定され、地上にてブロック状に分割して組み立てられた構造物は組立クレーン等を用いて仮設サポート22上に吊り上げられ、ジャッキ受部30を介してジャッキ29および積層ライナー31上に載置固定される。構造物の周縁の支承部24は下部構造体23に固定される。
仮設サポート22および下部構造体23上でのブロック状の構造物の骨組みの接合等による組立が完了した時点で、構造物21を自立させるために仮設サポート22上のジャッキ29を全て同時に緩めてジャッキダウンがなされ、最終的に構造物の全荷重は、周縁の支承部24によって下部構造体23に転嫁される。
【0004】
【発明が解決しようとする課題】
ところが、このような従来の構築方法では、構造物21の自立のためには、周縁部に比較して強度がそれほど大きくない構造物21の中間部の各部を支持する仮設サポート22上のジャッキ29を全て同時に緩めてジャッキダウンをする必要があり、全ての個所に作業員(手作業によるジャッキ調整作業)を配置するか、全てのジャッキ29・・・を自動制御で同時に動作させる必要があるが、高所での多数の作業員の配置については安全性にも問題があって実用的でなく、効率が悪化する虞れも生じた。また、完全なる自動制御については装置が複雑かつ高価となる他、監視人を置くことなく自動制御させた場合は構造物という特有の構築形態での安全上の課題を残した。とは言え、監視体制を整備すると自動制御の利点が減殺され、自動制御装置の設置分だけ余分な建設費用がかかることになって実際的でなかった。
【0005】
そこで、本発明では、前記従来の構造物の構築工法の諸課題を解決して比較的強度の大きい周縁部にて荷重を負担したジャッキ操作を行うことにより、簡素な機材と少ない人員にても安全に構築が行える構造物の構築方法および構築装置を提供することを目的とする。
【0006】
【課題を解決するための手段】
このため本発明は、構造物の周縁となる下部構造体上に載置した多数のジャッキと、下部構造体内の基礎上に立設された多数の仮設サポート上のジャッキと積層ライナーとにより構造物を支持して該構造物の骨組みを完了させた後、前記下部構造体上の全てのジャッキを押し上げ、前記構造物の全荷重を積層ライナーを介して負担した上で、前記仮設サポート上のジャッキの下降と積層ライナーを順次除去しながら無負荷の状態とした後、下部構造体上のジャッキの揺動傾斜時の積層ライナーによる全荷重の支持に次いで、ジャッキの揺動傾斜の補正とジャッキによる全荷重の支持を行った上で積層ライナーの除去を行い、以下、下部構造体上でのジャッキおよび積層ライナーの交互動作を順次繰り返すことで、積層ライナーの除去と全てのジャッキを段階的に下降させて、構造物の支承部を下部構造体上に支持固定することを特徴とするものである。
また本発明は、前記構造物の構築方法に使用される構築装置であって、基礎上に構築された構造物の周縁となる下部構造体と、該下部構造体内の基礎上に立設された多数の仮設サポートと、これら下部構造体および仮設サポート上に載置されたジャッキと積層ライナーとの組合せとから構成されたことを特徴とするもので、これらを課題解決のための手段とするものである。
【0007】
【実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。
図1および図2は本発明の構造物の構築方法および構築装置の1実施の形態を示すもので、図1(A)は構造物を構築中の半分切り欠いた平面図、図1(B)はその正面図および下部構造体への支承部の拡大図、図2は構築中の仮設サポートおよび下部構造体上のジャッキの状態を示す正面詳細図である。
本発明の構造物の構築方法について詳述すると、図1(B)に示すように、構造物1の周縁となる下部構造体(躯体)3および該下部構造体3内の基礎G上に立設された多数の仮設サポート2、2・・・上にて構造物1を構築するもので、前記下部構造体3上にジャッキ5、5、および仮設サポート2上にジャッキ9、9と積層ライナー11、11とを組み合わせて載置する(下部構造体3部については図2を参照)とともに、適宜数のブロックに分割されて基礎Gにて組み立てられた構造物1をブロック毎に図示省略の組立クレーン等の揚重機にて吊り上げる。
【0008】
次いで、前記下部構造体3上のジャッキ5、5、および仮設サポート2上のジャッキ9、9と積層ライナー11、11とにより支持させて構造物1の骨組みを完了させ、図2(A)に示すように、下部構造体3上における全てのジャッキ5、5・・・を押し上げて下部積層ライナー7、7を介して構造物1の全荷重を負担した上で、仮設サポート2、2・・・上におけるジャッキ9、9・・・を段階的に下降させ、積層ライナー11、11・・・を順次除去した後、図2(B)に示すように、下部構造体3上の全てのジャッキ5、5・・・を下降させて、下部積層ライナー7、7を順次除去しながら、構造物1の支承部4を下部構造体3上に支持固定するものである。
【0009】
前記下部構造体3上における全てのジャッキ5、5・・・を押し上げて、下部構造体3が構造物1の全荷重を下部積層ライナー7を介して負担した状態以降の工程を詳述すると、図2(A)の状態、すなわち下部構造体3上における全てのジャッキ5、5・・・を押し上げると、構造物1の中間部は各仮設サポート2、2・・・上のジャッキ受部10・・・から離間し、自重によって構造物1が僅かながらも拡開し、構造物1の外周縁は径方向外側に移動する。したがって、下部構造体3上の各ジャッキ5は底部を中心として僅か外側に揺動する。
下部構造体3上のジャッキ5の伸長によって上昇した構造物1周縁下部の下部支承部4との間の隙間に下部ライナー7を積層して追加する。これによって、ジャッキ5を下降させても下部積層ライナー7が構造物1の全荷重を負担できることになる。このとき、揺動傾斜したジャッキ5、5は、手動または自動制御あるいはレール上にジャッキを載置して構成した自動補正装置等により正常位置に復元するように構成される。
【0010】
この状態から、無負荷状態にある各仮設サポート2上における上部積層ライナー11、11をジャッキ9の伸縮動作と組み合わせて1段ずつ順次除去して行くことになる。これらの仮設サポート2上におけるジャッキ9の下降による上部積層ライナー11、11の支持に続いて、下部構造体3上のジャッキ5による支持後の下部ライナー7の除去、次いで、仮設サポート2上のジャッキ9、9の伸長後の上部積層ライナー11、11の除去およびジャッキ9、9の下降後の上部積層ライナー11、11による支持と、以下、下部構造体3上でのジャッキおよび積層ライナーによる交互動作と仮設サポート2上でのジャッキおよび積層ライナーによる交互動作を順次繰り返すことで、構造物1を徐々にジャッキダウンさせ、最終的に構造物1の支承部4を下部構造体3上に下降させて支持固定する。
【0011】
以上、本発明の各実施の形態について説明してきたが、本発明の趣旨の範囲内で、構造物の形状(円形に限らず、三角、方形、多角形等)、形式(トラス構造の他、桁構造等)、下部構造体の形状、形式、仮設サポートの形状、形式およびその設置形態、数、分割されてブロック化された構造物の揚重形態およびそれらの間の接合形態、構造物の下部構造体および仮設サポートへの支持形態、ジャッキおよび積層ライナーの形状、形式、配設形態およびそれらの間の関連構成等については適宜採用が可能である。
【0012】
【発明の効果】
以上、詳細に説明してきたように本発明によれば、仮設サポートが負担していた構造物の荷重を、比較的強度の大きい周縁部である下部構造体に転嫁させてジャッキ操作を行うことにより、構造物をジャッキダウンさせることが可能となり、簡素な機材と少ない人員にても、低コストで安全かつ短縮された工期のもとに構造物の構築ができる。
また、構造物の荷重を負担してのジャッキ作業が、強度が大きく地上にも近い足場の確実な下部構造体上にて行えるので、作業の安全性が確保できる。
さらに、従来の仮設サポート上におけるジャッキダウンに比較して、ジャッキの数を大幅に減らすことが可能となり、設備費用の低減と作業手間の軽減が図れる。
かくして、本発明によれば、比較的強度の大きい周縁部にて荷重を負担したジャッキ操作を行うことにより、簡素な機材と少ない人員にても安全に構築が行える構造物の構築方法および構築装置が提供される。
【図面の簡単な説明】
【図1】本発明の構造物の構築方法および構築装置の1実施の形態を示すもので、図1(A)は構造物を構築中の半分切り欠いた平面図、図1(B)はその正面図および下部構造体への支承部の拡大図である。
【図2】同、構築中の仮設サポートおよび下部構造体上のジャッキの状態を示す正面詳細図である。
【図3】従来の屋根構造体の構築工法を示す正面図である。
【符号の説明】
1・・・・構造物
2・・・・仮設サポート
3・・・・下部構造体(躯体)
4・・・・下部支承部
5・・・・下部ジャッキ
6・・・・下部ジャッキ受部材
7・・・・下部積層ライナー
8・・・・支承部
9・・・・ジャッキ
10・・・・ジャッキ受部
11・・・・上部積層ライナー
G・・・・基礎(地上)
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method and a construction apparatus for a structure such as a large roof structure in which a truss material obtained by joining upper chord material and lower chord material via a web material is assembled in a mesh shape, for example. It can also be applied to girder structures.
[0002]
[Prior art]
Structures such as large roof structures are usually constructed by assembling them divided into an appropriate number of blocks, but since there are many members and types that make up the structure, sorting and selection work is required at the time of construction. It took a lot of time and effort. In addition, if the blocks divided at the time of assembling cannot be reliably joined, the structure itself cannot be self-supported, so that temporary support is required for construction.
A conventional example of a structure construction method using such a temporary support will be described with reference to FIG.
[0003]
The number of temporary supports 22 erected on the foundation in the lower structure (frame) 23 that becomes the periphery of the structure is the number required on the foundation G on the ground where the structure 21 is built in advance. Only standing up. A jack 29 and a laminated liner 31 are fixed to the top of the temporary support 22, and the structure assembled by being divided into blocks on the ground is lifted on the temporary support 22 using an assembly crane or the like, and a jack receiving portion 30 is placed and fixed on the jack 29 and the laminated liner 31. The support 24 on the periphery of the structure is fixed to the lower structure 23.
When the assembly by joining the framework of the block-like structure on the temporary support 22 and the lower structure 23 is completed, the jacks 29 on the temporary support 22 are all loosened at the same time in order to make the structure 21 independent. Down, and finally the total load of the structure is transferred to the lower structure 23 by the peripheral support portion 24.
[0004]
[Problems to be solved by the invention]
However, in such a conventional construction method, in order for the structure 21 to be independent, the jack 29 on the temporary support 22 that supports each part of the intermediate part of the structure 21 that is not so strong compared to the peripheral part. It is necessary to loosen all the jacks at the same time and to jack down. It is necessary to place workers (manual jack adjustment work) at all points or to operate all jacks 29 ... simultaneously by automatic control. The arrangement of a large number of workers at high places is not practical due to safety problems, and there is a possibility that efficiency may deteriorate. In addition, for complete automatic control, the device becomes complicated and expensive, and when automatic control is performed without placing a supervisor, there remains a safety problem in a specific construction form called a structure. However, the improvement of the monitoring system diminished the advantages of automatic control, and it was not practical because it would require extra construction costs for the installation of the automatic control device.
[0005]
Therefore, in the present invention, it is possible to solve the problems of the conventional construction method of the structure and perform a jack operation in which a load is borne at a peripheral portion having a relatively high strength, so that even simple equipment and a small number of personnel can be used. An object of the present invention is to provide a construction method and construction device that can be constructed safely.
[0006]
[Means for Solving the Problems]
For this reason, the present invention provides a structure comprising a large number of jacks placed on a lower structure serving as a peripheral edge of a structure, a number of jacks on temporary supports erected on a foundation in the lower structure, and a laminated liner. After the structure of the structure is completed by supporting the structure, all jacks on the lower structure are pushed up, and the total load of the structure is borne through the laminated liner. After lowering the position and removing the laminated liner one after another to make it unloaded , then following the support of the full load by the laminated liner when the jack on the lower structure is tilted, the correction of the jack swing and the jack performs removal of the laminated liner after performing the support of full load, hereinafter, by sequentially repeating the jack and alternating operation of lamination liner on the lower structure, removing all of the laminated liner Yakki stepwise lowered, is characterized in that the supporting and fixing the bearing structure on the lower structure.
The present invention also relates to a construction apparatus used in the construction method of the structure, wherein the lower structure is a peripheral edge of the structure constructed on the foundation, and is erected on the foundation in the lower structure. It is composed of a number of temporary supports, a combination of these lower structures and jacks and laminated liners placed on the temporary supports, and these are used as means for solving the problems. It is.
[0007]
Embodiment
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
1 and FIG. 2 show an embodiment of a structure construction method and construction apparatus according to the present invention. FIG. 1 (A) is a half-cut plan view of the structure being constructed, and FIG. ) Is a front view thereof and an enlarged view of a support portion to the lower structure, and FIG. 2 is a detailed front view showing a temporary support under construction and a jack state on the lower structure.
The construction method of the structure of the present invention will be described in detail. As shown in FIG. 1 (B), the lower structure (casing) 3 which is the periphery of the structure 1 and the foundation G in the lower structure 3 are set up. A structure 1 is constructed on a number of temporary supports 2, 2... Which are provided, jacks 5 and 5 on the lower structure 3, and jacks 9 and 9 and a laminated liner on the temporary support 2. 11 and 11 are mounted in combination (see FIG. 2 for the lower structure 3 part), and the structure 1 divided into an appropriate number of blocks and assembled on the foundation G is not shown for each block. Lift with a lifting machine such as an assembly crane.
[0008]
Next, the skeleton of the structure 1 is completed by being supported by the jacks 5 and 5 on the lower structure 3 and the jacks 9 and 9 on the temporary support 2 and the laminated liners 11 and 11, as shown in FIG. As shown in the figure, all jacks 5, 5... On the lower structure 3 are pushed up to bear the full load of the structure 1 through the lower laminated liners 7, 7, and then the temporary supports 2, 2,. The upper jacks 9, 9... Are lowered stepwise and the laminated liners 11, 11... Are sequentially removed, and then all the jacks on the lower structure 3 as shown in FIG. 5, 5,... Are lowered to support and fix the support portion 4 of the structure 1 on the lower structure 3 while sequentially removing the lower laminated liners 7 and 7.
[0009]
When all the jacks 5, 5... On the lower structure 3 are pushed up and the lower structure 3 bears the total load of the structure 1 via the lower laminated liner 7 in detail, 2A, that is, when all the jacks 5, 5... On the lower structure 3 are pushed up, the intermediate portion of the structure 1 becomes a jack receiving portion 10 on each temporary support 2, 2. ..., the structure 1 is slightly expanded by its own weight, and the outer peripheral edge of the structure 1 moves radially outward. Accordingly, each jack 5 on the lower structure 3 swings slightly outward with the bottom as a center.
A lower liner 7 is stacked and added to a gap between the lower support portion 4 at the lower periphery of the structure 1 raised by extension of the jack 5 on the lower structure 3. Thereby, even if the jack 5 is lowered, the lower laminated liner 7 can bear the full load of the structure 1. At this time, the swinging and tilting jacks 5 and 5 are configured to be restored to normal positions by manual or automatic control or an automatic correction device configured by placing the jack on the rail.
[0010]
From this state, the upper laminated liners 11 and 11 on the temporary supports 2 in the no-load state are sequentially removed step by step in combination with the expansion and contraction operation of the jack 9. Following the support of the upper laminated liners 11, 11 by the lowering of the jack 9 on the temporary support 2, the removal of the lower liner 7 after the support by the jack 5 on the lower structure 3, and then the jack on the temporary support 2. Removal of the upper laminated liners 11 and 11 after the extension of 9, 9 and support by the upper laminated liners 11 and 11 after the lowering of the jacks 9 and 9 and the alternate operation by the jack and the laminated liner on the lower structure 3 hereinafter. And the alternate operation by the jack and the laminated liner on the temporary support 2 are sequentially repeated, so that the structure 1 is gradually jacked down, and finally the support portion 4 of the structure 1 is lowered onto the lower structure 3. Support and fix.
[0011]
As described above, each embodiment of the present invention has been described. Within the scope of the present invention, the shape of the structure (not limited to a circle, a triangle, a rectangle, a polygon, etc.), a form (in addition to a truss structure, Girder structure, etc.), the shape of the lower structure, the form, the shape of the temporary support, the form and its installation form, the number, the lifted form of the divided and blocked structure and the joint form between them, the structure The support form to the lower structure and the temporary support, the shape and form of the jack and the laminated liner, the arrangement form, and the related configuration between them can be appropriately adopted.
[0012]
【The invention's effect】
As described above in detail, according to the present invention, by performing the jack operation by transferring the load of the structure borne by the temporary support to the lower structure which is the peripheral portion having a relatively high strength. It is possible to jack down the structure, and even with simple equipment and a small number of personnel, the structure can be constructed at a low cost and safely and with a shortened construction period.
In addition, the jacking work while bearing the load of the structure can be performed on the secure lower structure of the scaffolding that is strong and close to the ground, so that the safety of the work can be ensured.
Furthermore, the number of jacks can be greatly reduced as compared with the conventional jackdown on the temporary support, and the equipment cost and the labor can be reduced.
Thus, according to the present invention, a construction method and a construction apparatus for a structure that can be constructed safely even with simple equipment and a small number of personnel by performing a jack operation that bears a load at a peripheral portion having a relatively high strength. Is provided.
[Brief description of the drawings]
FIG. 1 shows an embodiment of a structure construction method and construction apparatus according to the present invention. FIG. 1 (A) is a plan view in which a structure is being cut halfway, and FIG. It is the front view and the enlarged view of the support part to a lower structure.
FIG. 2 is a detailed front view showing a state of a temporary support under construction and a jack on a lower structure.
FIG. 3 is a front view showing a conventional construction method for a roof structure.
[Explanation of symbols]
1 ··· Structure 2 ··· Temporary support 3 · · · Lower structure (frame)
4... Lower support part 5... Lower jack 6... Lower jack receiving member 7 .. Lower laminated liner 8. Jack receiving part 11 ... Upper laminated liner G ... Basic (ground)

Claims (2)

構造物の周縁となる下部構造体上に載置した多数のジャッキと、下部構造体内の基礎上に立設された多数の仮設サポート上のジャッキと積層ライナーとにより構造物を支持して該構造物の骨組みを完了させた後、前記下部構造体上の全てのジャッキを押し上げ、前記構造物の全荷重を積層ライナーを介して負担した上で、前記仮設サポート上のジャッキの下降と積層ライナーを順次除去しながら無負荷の状態とした後、下部構造体上のジャッキの揺動傾斜時の積層ライナーによる全荷重の支持に次いで、ジャッキの揺動傾斜の補正とジャッキによる全荷重の支持を行った上で積層ライナーの除去を行い、以下、下部構造体上でのジャッキおよび積層ライナーの交互動作を順次繰り返すことで、積層ライナーの除去と全てのジャッキを段階的に下降させて、構造物の支承部を下部構造体上に支持固定することを特徴とする構造物の構築方法。The structure is supported by a large number of jacks placed on the lower structure serving as the peripheral edge of the structure, and a number of jacks on the temporary support and a laminated liner that are erected on the foundation in the lower structure. After completing the framework of the object, push up all the jacks on the lower structure, bear the full load of the structure through the laminated liner, lower the jack on the temporary support and laminate the liner After removing the load sequentially and removing the load, the load on the lower structure is supported by the laminated liner when the jack is tilted. Then, the tilt of the jack is corrected and the load is supported by the jack. performs removal of the laminated liner on the following, by sequentially repeating the jack and alternating operation of lamination liner on the lower structure, stepwise every jack and removal of the laminate liner Tassel so, the method for constructing a structure characterized by supporting and fixing the bearing structure on the lower structure. 前記請求項1に記載の構造物の構築方法に使用される構築装置であって、基礎上に構築された構造物の周縁となる下部構造体と、該下部構造体内の基礎上に立設された多数の仮設サポートと、これら下部構造体および仮設サポート上に載置されたジャッキと積層ライナーとの組合せとから構成されたことを特徴とする構造物の構築装置。  A construction apparatus for use in the construction method for a structure according to claim 1, wherein the lower structure is a peripheral edge of the structure constructed on the foundation, and is erected on the foundation in the lower structure. An apparatus for constructing a structure comprising a plurality of temporary supports and a combination of a lower liner and a jack and a laminated liner placed on the temporary supports.
JP2000218230A 2000-07-19 2000-07-19 Structure construction method and construction apparatus Expired - Fee Related JP3693893B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000218230A JP3693893B2 (en) 2000-07-19 2000-07-19 Structure construction method and construction apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000218230A JP3693893B2 (en) 2000-07-19 2000-07-19 Structure construction method and construction apparatus

Publications (2)

Publication Number Publication Date
JP2002030810A JP2002030810A (en) 2002-01-31
JP3693893B2 true JP3693893B2 (en) 2005-09-14

Family

ID=18713204

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000218230A Expired - Fee Related JP3693893B2 (en) 2000-07-19 2000-07-19 Structure construction method and construction apparatus

Country Status (1)

Country Link
JP (1) JP3693893B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103711322A (en) * 2014-01-19 2014-04-09 芜湖天航科技(集团)股份有限公司 Construction method for mounting large-span semispherical reticulated shell through overhanging
CN106836822B (en) * 2016-12-20 2019-04-16 安徽瑶海钢构建设有限公司 A kind of steel structure roof suspension tensioning screw rod mounting structure and installation method
CN106836498B (en) * 2016-12-28 2022-11-29 郑州工业应用技术学院 Hoisting construction method for steel truss of grand stand roof of super-large span stadium
CN113404329A (en) * 2021-06-15 2021-09-17 中建科工集团有限公司 Unloading method of temporary support structure
CN114592718A (en) * 2022-03-30 2022-06-07 浙江东南网架股份有限公司 Supporting structure for sectional hoisting of triangular pipe truss and supporting method thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3122915B2 (en) * 1992-12-15 2001-01-09 株式会社竹中工務店 Single layer truss roof push-up method
JP3204283B2 (en) * 1993-10-19 2001-09-04 前田建設工業株式会社 Large space structure construction equipment

Also Published As

Publication number Publication date
JP2002030810A (en) 2002-01-31

Similar Documents

Publication Publication Date Title
US6317957B1 (en) Method for fabricating an excavator base
JP2009132474A (en) Mounting device of climbing frame
JP2790986B2 (en) Bridge pier construction method and construction method
CN114182963A (en) Construction method for reverse-order layered lifting of plane-overlapped multi-layer large-span truss structure
JP3693893B2 (en) Structure construction method and construction apparatus
EP1677001A2 (en) System for removing the cover roof from a wind turbine
JP2001173098A (en) Mobile frame trestle for constructing dome-like roof and construction method
JP3798367B2 (en) Construction method of arch structure, dome structure and construction method thereof
JP3655161B2 (en) Bridge removal and erection methods
CN115853125A (en) Circular conical dome steel structure with upper opening and mounting method thereof
CN116290905A (en) Roof steel structure reconstruction method
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
JPH06323503A (en) Assembling method for large size suspension type boiler
JPH04161566A (en) Constructing apparatus for large space building
JP2579715B2 (en) External tower crane
JP4785013B2 (en) Tower crane and floor climbing system
JP2002235446A (en) Demolition method of building
JP2000192551A (en) Construction method for large span frame
US20190127995A1 (en) Rigging Lift and Method of Use
JPH04161565A (en) Construction of large space building
JPH0932120A (en) Method of construction of structure
JP2768237B2 (en) Assembly translation method and beam joining method of large hanging boiler, and beam joining structure
KR20140047791A (en) Installing apparatus and method of wind power generator
JPH0718743A (en) Construction method for large span domelike roof
JP3328790B2 (en) High-rise building assembly method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041005

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041116

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041208

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050621

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050622

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3693893

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080701

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110701

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120701

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120701

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130701

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130701

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140701

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees