JP2000345546A - Improvement method for soft ground containing hard stratum - Google Patents
Improvement method for soft ground containing hard stratumInfo
- Publication number
- JP2000345546A JP2000345546A JP11159243A JP15924399A JP2000345546A JP 2000345546 A JP2000345546 A JP 2000345546A JP 11159243 A JP11159243 A JP 11159243A JP 15924399 A JP15924399 A JP 15924399A JP 2000345546 A JP2000345546 A JP 2000345546A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- sand
- wall
- piles
- forming
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Piles And Underground Anchors (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地盤の表層部又は
比較的表層部に近い中間層に存在する硬質層を、予めオ
ーガ削孔機で先行削孔を行った後に締固め砂杭又は砕石
杭等を造成する際、締固め砂杭又は砕石杭造成前の削孔
壁の崩落を防止する高効率施工が可能な硬質層を有する
軟質地盤の改良工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for compacting sand piles or crushed stones after preliminarily drilling a hard layer existing in the surface portion of the ground or an intermediate layer relatively close to the surface portion with an auger drill. The present invention relates to a method for improving soft ground having a hard layer capable of highly efficient construction for preventing collapse of a drilled wall before forming compacted sand piles or crushed stone piles when forming a pile or the like.
【0002】[0002]
【従来の技術】従来、地盤の表層部又は比較的表層部に
近い中間層に存在する硬質層を有する軟質地盤を改良す
る工法として、例えば、硬質層を貫通して軟質地盤中に
多数の砂杭や固結杭を造成する締固め砂杭工法や固結杭
造成工法等がある。この硬質層を有する軟質地盤を改良
する工法においては、先ず、後工程の砂杭等の形成を容
易にするため、硬質層をオーガ削孔機で先行削孔した
後、その後、当該先行削孔部分に締固め砂杭や固結杭を
多数造成する方法を採る場合がある。2. Description of the Related Art Conventionally, as a method of improving a soft ground having a hard layer existing in a surface layer portion of the ground or an intermediate layer relatively close to the surface layer, for example, a method of penetrating a hard layer into a soft ground and forming a large amount of sand in the soft ground. There is a compacted sand pile construction method and a consolidated pile construction method for creating piles and consolidated piles. In the method of improving the soft ground having this hard layer, first, in order to facilitate the formation of sand piles and the like in the subsequent process, the hard layer is pre-drilled by an auger drill, and then the pre-drilling is performed. In some cases, a method of creating a large number of compacted sand piles and consolidated piles may be adopted.
【0003】[0003]
【発明が解決しようとする課題】この場合、先ず、硬質
層中に多数の先行削孔が形成されるが、先行削孔後、1
〜数日後に施工される後工程の砂杭や固結杭造成の際に
は、隣接する先行削孔の削孔時に発生する振動又はその
他の振動などの影響により削孔壁が崩れ、先行削孔が閉
塞される場合がある。これでは、先行削孔を設けた意味
がなく、また、再度の削孔により施工効率が著しく低下
するという問題がある。In this case, first, a large number of pre-drilled holes are formed in the hard layer.
When creating sand piles and consolidated piles in the post-process, which will be performed a few days later, the drilling wall collapses due to the vibration generated during drilling of the adjacent preceding drilling or other vibrations, and the preceding drilling Holes may be blocked. In this case, there is no point in providing the pre-drilling, and there is a problem that the re-drilling significantly reduces the construction efficiency.
【0004】従って、本発明の目的は、先行削孔の削孔
壁の崩落を回避する高効率の施工が可能な硬質層を有す
る軟質地盤の改良工法を提供することにある。[0004] Accordingly, an object of the present invention is to provide an improved method of soft ground having a hard layer capable of performing construction with high efficiency while avoiding collapse of the drilling wall of the preceding drilling.
【0005】[0005]
【課題を解決するための手段】かかる実情において、本
発明者らは鋭意検討を行った結果、予め、硬質層中の下
端深度に緩い削孔壁保持材料杭を多数造成しておき、次
いで、かかる杭部に砂杭や固結杭などの杭状又は壁状物
を構築すれば、先行削孔の削孔壁の崩落の問題を回避で
き高効率施工が可能であることなどを見出し、本発明を
完成するに至った。Under such circumstances, the present inventors have conducted intensive studies, and as a result, previously prepared a large number of loose drilling wall holding material piles at the lower end depth in the hard layer, When pile-like or wall-like materials such as sand piles and consolidated piles are constructed on such piles, the problem of collapse of the drilling wall of the pre-drilling can be avoided and high-efficiency construction is possible. The invention has been completed.
【0006】すなわち、本発明は、硬質層中に削孔壁保
持材料杭を多数造成して硬質層の一部を前記削孔壁保持
材料で置き換える第1行程と、当該削孔壁保持材料杭に
杭状物又は壁状物を設計深度から構築する第2工程を有
することを特徴とする硬質層を有する軟質地盤の改良工
法を提供するものである。かかる構成を採ることによ
り、第1工程は、単にオーガ削孔機で地盤を削孔する代
わりに、例えば、公知の砂杭造成工法により削孔と緩い
砂杭などの削孔壁保持材料杭の造成を同時に行うことか
ら、削孔壁の崩落を防止すると共に、後工程の該削孔部
分への挿入管などの貫入が行い易くなる。第2工程にお
いては、第1工程で形成された当該削孔壁保持材料杭に
挿入管、既製杭、シート状壁などを容易に貫入できるた
め、所望の砂杭、砕石杭、既製杭又は固結杭等の杭状物
又は壁状物の高効率施工が可能となる。That is, the present invention provides a first step in which a number of drilled wall holding material piles are formed in a hard layer and a part of the hard layer is replaced with the drilled wall holding material. And a second step of constructing a pile or wall from a design depth. By adopting such a configuration, the first step is, instead of simply drilling the ground with an auger drilling machine, for example, drilling by a known sand pile formation method and drilling of a drilled wall holding material pile such as a loose sand pile. Since the formation is performed at the same time, it is possible to prevent the drilling wall from collapsing and to easily insert an insertion pipe or the like into the drilling portion in a later step. In the second step, an insertion pipe, a ready-made pile, a sheet-like wall, or the like can easily penetrate into the drilled wall holding material pile formed in the first step, so that a desired sand pile, crushed stone pile, ready-made pile or solid pile can be obtained. High-efficiency construction of piles or wall-like objects such as knots is possible.
【0007】[0007]
【発明の実施の形態】本発明の硬質層を有する軟質地盤
の改良工法の第1工程は、硬質層中に削孔壁保持材料杭
を多数造成して硬質層の一部を前記削孔壁保持材料で置
き換える工程である。削孔壁保持材料杭は、第2工程で
行われる当該削孔壁保持材料杭への挿入管、既製杭、シ
ート状壁などの貫入が行い易いように形成されるもので
ある。従って、削孔壁保持材料杭としては、例えば、
砂、砕石、現地残土などが充填される砂杭、砕石杭など
が挙げられる。このうち、密度が小さい、緩い砂杭が削
孔壁の崩落を防止すると共に、後工程の該削孔部分への
挿入管などの貫入が行い易くなる点で好ましい。この削
孔壁保持材料杭は硬質層の深さ全長に亘り形成してもよ
く、また、その途中(一部)まで形成するものであって
もよい。BEST MODE FOR CARRYING OUT THE INVENTION The first step of the method for improving soft ground having a hard layer according to the present invention is to form a large number of drilling wall holding material piles in the hard layer and to make a part of the hard layer into the drilling wall. This is a step of replacing with a holding material. The drilled wall holding material pile is formed such that an insertion tube, a ready-made pile, a sheet-like wall, or the like, which penetrates into the drilled wall holding material pile performed in the second step, is easily performed. Therefore, as a drilled wall holding material pile, for example,
Sand pile, crushed stone pile, etc. filled with sand, crushed stone, on-site remaining soil, and the like. Of these, a loose sand pile having a low density is preferable in that it prevents collapse of the drilled wall and facilitates penetration of an insertion tube or the like into the drilled portion in a later step. The drilled wall holding material pile may be formed over the entire depth of the hard layer, or may be formed halfway (partly).
【0008】砂杭及び砕石杭の造成方法としては、特公
昭62−25808号公報などに開示されているよう
に、中空管を硬質層の下端深度まで貫入した後、地表ま
で引き抜く過程で、前記中空管の一定深さ引き抜き管内
に投入された砂、砕石等を排出する方法が挙げられる。
従来の所謂、締固め砂杭造成工法は、この中空管を引き
抜く工程に引き続いて、前記中空管を再び貫入して排出
砂等を締固める再貫入工程を繰り返して行うことによ
り、所定の強度に締固めた砂杭を造成するものである
が、本発明の第1工程の砂杭及び砕石杭の造成方法にお
いては、この再貫入工程を省略するか、又は再貫入の貫
入幅を小さくすることが緩い砂杭などが形成できる点で
好ましい。また、硬質層の下端深度まで中空管を貫入す
る施工機としては、硬質層を有すること、また、削孔壁
保持材料で置き換えた保持状況を維持し易くする点で回
転式貫入装置を備える施工機が好適である。As a method for forming a sand pile and a crushed stone pile, as disclosed in Japanese Patent Publication No. 25808/1987, the hollow pipe is penetrated to the lower end depth of the hard layer and then pulled out to the surface of the ground. A method of discharging sand, crushed stones, and the like that have been introduced into the hollow pipe having a constant depth is drawn.
A conventional so-called compaction sand pile forming method is a method of repeatedly performing a re-penetration step of re-penetrating the hollow pipe and compacting discharged sand, etc., following the step of pulling out the hollow pipe, thereby performing a predetermined process. A method for forming a sand pile compacted to a high strength. In the method for forming a sand pile and a crushed stone pile in the first step of the present invention, the re-penetration step is omitted or the penetration width of the re-penetration is reduced. This is preferable because a loose sand pile or the like can be formed. Also, as a construction machine that penetrates the hollow pipe to the lower end depth of the hard layer, it has a hard layer, and also includes a rotary penetration device in that it easily maintains a holding state replaced with a drilled wall holding material. Construction machines are preferred.
【0009】本発明の硬質層を有する軟質地盤の改良工
法の第2工程は、第1工程で形成された削孔壁保持材料
杭に杭状物又は壁状物を設計深度から構築する工程であ
る。杭状物又は壁状物としては、砂杭、砕石杭、既製杭
及び固結杭などが挙げられる。砂杭及び砕石杭の形成方
法としては、第1工程で実施する砂杭及び砕石杭の形成
方法と同様の方法が挙げられるが、この第2工程では、
第1工程の方法とは異なり、再貫入工程を繰り返し実施
することにより、所定の強度に締固めた砂杭を造成する
ことが硬質層の下又は硬質層の上下に存在する軟質地盤
を締固めて地盤の強化が図れる点で好ましい。The second step of the method for improving soft ground having a hard layer according to the present invention is a step of constructing a pile or a wall from the drilled wall holding material pile formed in the first step from a design depth. is there. Examples of the pile or wall include sand piles, crushed stone piles, ready-made piles, and consolidated piles. Examples of the method for forming the sand pile and the crushed stone pile include a method similar to the method for forming the sand pile and the crushed stone pile performed in the first step, but in the second step,
Unlike the method of the first step, by repeatedly performing the re-penetration step, it is possible to form a sand pile compacted to a predetermined strength by compacting the soft ground existing below the hard layer or above and below the hard layer. This is preferable in that the ground can be strengthened.
【0010】既製杭の形成方法は、コンクリート柱、鋼
管など別途に製造された杭体の打ち込みによる造成であ
り、固結杭の形成方法としては、例えば、機械式攪拌装
置の先端を、施工する柱体の芯に合わせてロッドを回転
させ、装置先端から軽量固化材を吐出しながら攪拌羽根
を回転し、掘削土と混合攪拌しながら掘進を行い、設計
深度に達したところで吐出を停止し、ロッドを逆転し
て、更に混合攪拌しながら地盤上に引き上げて柱状体を
造成する方法が挙げられる。また、壁状物の形成方法と
しては、上記固結杭の形成方法で造成された柱状体を多
数連ねて壁状物を形成する方法が挙げられる。壁状物の
造成により、廃棄物による地下汚染の拡大防止、調整池
や河川堤防の封じ込めができる。[0010] The method of forming a ready-made pile is a method of driving a separately manufactured pile body such as a concrete pillar or a steel pipe, and the method of forming a consolidated pile is, for example, using a tip of a mechanical stirring device. Rotate the rod according to the core of the column, rotate the stirring blade while discharging the lightweight solidified material from the tip of the device, perform excavation while mixing and stirring with excavated soil, stop discharging when the design depth is reached, A method of reversing the rod and pulling it up on the ground while further mixing and stirring to form a columnar body may be used. In addition, as a method of forming a wall-like object, a method of forming a wall-like object by connecting a large number of columnar bodies formed by the above-described method of forming a consolidated pile is used. The creation of walls can prevent the spread of underground pollution caused by waste and containment ponds and river embankments.
【0011】本発明の実施の形態における硬質層を有す
る軟質地盤の改良工法について、図1を参照して説明す
る。図1は硬質層を有する軟質地盤の改良工法の工程を
示す模式図である。図1中、地盤は硬質層1の下に軟質
地盤2が存在する硬質/軟質積層地盤である。また、
(I)、(II)及び(III )は第1工程の緩い砂杭造成
工程を示し、(IV)及び(V)は第2工程の固結杭造成
工程を示す。An improvement method for a soft ground having a hard layer according to an embodiment of the present invention will be described with reference to FIG. FIG. 1 is a schematic view showing the steps of an improvement method for a soft ground having a hard layer. In FIG. 1, the ground is a hard / soft laminated ground in which a soft ground 2 exists below a hard layer 1. Also,
(I), (II) and (III) show the loose sand pile forming step of the first step, and (IV) and (V) show the consolidated pile forming step of the second step.
【0012】第1工程において使用する砂杭造成装置1
0はスパイラル13を外周に装備したケーシング管12
と、ケーシング管12を回転させるモーター14と、ケ
ーシング管12内に砂を投入する砂投入口11を有す
る。先ず、ケーシング管12をモーター14で回転させ
硬質層1の底部16まで挿入し(図1中、(I)及び
(II) )、砂投入口11から砂を投入してケーシング管
12内に砂を入れた後、ケーシング管12を逆回転させ
引き抜き、その削孔部に砂を残置し、地盤中に直径40
〜50cmの砂杭15を形成する(図1中、(III))。こ
れにより、予め、オーガ削孔機を使用して先行削孔を形
成することがないため、削孔壁の崩落の問題が生じない
と共に、硬質層1中に緩い砂杭15が形成できるため、
第2工程の貫入管28の貫入が容易となる。Sand pile forming apparatus 1 used in the first step
0 is a casing tube 12 equipped with a spiral 13 on the outer periphery.
And a motor 14 for rotating the casing tube 12 and a sand inlet 11 for introducing sand into the casing tube 12. First, the casing tube 12 is rotated by the motor 14 and inserted up to the bottom 16 of the hard layer 1 ((I) and (II) in FIG. 1). After that, the casing tube 12 is rotated in the reverse direction and pulled out, sand is left in the drilled portion, and a diameter of 40 mm is placed in the ground.
A sand pile 15 of about 50 cm is formed ((III) in FIG. 1). Thereby, since the advance drilling is not formed in advance using the auger drilling machine, the problem of the collapse of the drilling wall does not occur, and the loose sand pile 15 can be formed in the hard layer 1.
The penetration of the penetration pipe 28 in the second step is facilitated.
【0013】第2工程において使用する機械式攪拌装置
30は、クローラークレーン21と、クローラークレー
ン21に一端が固定された昇降装置22を支持又はガイ
ドするリーダ27と、昇降装置22に連結する挿入管2
3と、外周形状が角状の挿入管23の下方部で角軸に嵌
合する鍔(不図示)に接続して挿入管23を回転させる
下部駆動モーター24とを有する一軸機である。先ず、
機械式攪拌装置30の先端を施工する柱体の芯に合わせ
て挿入管23を回転させ、挿入管23の先端から低強度
固化材を吐出させながら攪拌羽根を回転し、掘削土と混
合攪拌しながら掘進を行い、設計深度29に達したとこ
ろで吐出を停止し、挿入管23を逆転して、更に混合攪
拌しながら地盤上に引き上げて軟質地盤2と硬質層1に
亘る柱状体25を造成する(図1中、(IV)及び
(V))。第2工程は、第1工程で形成された砂杭15
が緩い強度のものであるため、砂杭15への挿入管23
の貫入が容易となり、施工効率が高くなる。The mechanical stirring device 30 used in the second step includes a crawler crane 21, a leader 27 that supports or guides an elevating device 22 having one end fixed to the crawler crane 21, and an insertion pipe connected to the elevating device 22. 2
3 is a single-axis machine having a lower drive motor 24 connected to a flange (not shown) fitted to a square shaft at a lower portion of the insertion tube 23 having a square outer periphery to rotate the insertion tube 23. First,
The tip of the mechanical stirring device 30 is rotated in accordance with the core of the column to be installed, and the insertion pipe 23 is rotated. The stirring blade is rotated while discharging the low-strength solidified material from the tip of the insertion pipe 23 to mix and stir the excavated soil. When the depth reaches the design depth 29, the discharge is stopped, the insertion tube 23 is reversed, and the column is pulled up onto the ground while further mixing and stirring to form the columnar body 25 extending over the soft ground 2 and the hard layer 1. ((IV) and (V) in FIG. 1). The second step is to use the sand pile 15 formed in the first step.
Is of low strength, the insertion pipe 23 into the sand pile 15
Penetration becomes easy, and construction efficiency increases.
【0014】[0014]
【発明の効果】本発明によれば、第1工程は、単にオー
ガ削孔機で地盤を削孔する代わりに、例えば、公知の砂
杭造成工法により削孔と緩い砂杭などの削孔壁保持材料
杭の造成を同時に行うことから、削孔壁の崩落を防止す
ると共に、後工程の該削孔部分への挿入管などの貫入が
行い易くなる。第2工程において、当該削孔壁保持材料
杭に挿入管、既製杭、シート状壁などが容易に貫入でき
るため、所望の砂杭、砕石杭、既製杭又は固結杭等の杭
状物又は壁状物の高効率施工が可能となる。According to the present invention, in the first step, instead of simply drilling the ground with an auger drilling machine, for example, drilling is performed by a known sand pile forming method and a drilled wall such as a loose sand pile is formed. Since the formation of the holding material piles is performed at the same time, it is possible to prevent the drilling wall from collapsing and to easily insert an insertion tube or the like into the drilling portion in a later step. In the second step, since an insertion pipe, a ready-made pile, a sheet-like wall and the like can easily penetrate into the drilled wall holding material pile, a desired sand pile, a crushed stone pile, a ready-made pile or a consolidated pile or the like, Highly efficient construction of wall-like objects becomes possible.
【図1】本発明の硬質層を有する軟質地盤の改良工法の
工程を示す模式図である。FIG. 1 is a schematic view showing steps of a method for improving soft ground having a hard layer according to the present invention.
1 硬質層 2 軟質地盤 10 砂杭造成装置 11 砂投入口 12 ケーシング管 13 スパイラル 14 モーター 15 砂杭 16 硬質層の下端深度 21 クローラークレーン 22 昇降装置 23 挿入管 24 下部駆動モーター 25 柱状体 27 リーダ 29 設計深度 30 機械式攪拌装置 DESCRIPTION OF SYMBOLS 1 Hard layer 2 Soft ground 10 Sand pile forming apparatus 11 Sand inlet 12 Casing pipe 13 Spiral 14 Motor 15 Sand pile 16 Lower end depth of hard layer 21 Crawler crane 22 Elevating device 23 Insertion pipe 24 Lower drive motor 25 Column 27 Leader 29 Design depth 30 Mechanical stirrer
───────────────────────────────────────────────────── フロントページの続き Fターム(参考) 2D040 AB05 AB14 AC05 BA08 BD03 BD05 CA09 2D041 AA01 AA02 BA31 CA01 CB01 DA12 DB02 DB03 EA01 FA01 2D043 CA01 CA02 CA06 CA12 DB01 EA01 EA02 ──────────────────────────────────────────────────続 き Continued on the front page F term (reference) 2D040 AB05 AB14 AC05 BA08 BD03 BD05 CA09 2D041 AA01 AA02 BA31 CA01 CB01 DA12 DB02 DB03 EA01 FA01 2D043 CA01 CA02 CA06 CA12 DB01 EA01 EA02
Claims (2)
して硬質層の一部を前記削孔壁保持材料で置き換える第
1行程と、当該削孔壁保持材料杭に杭状物又は壁状物を
設計深度から構築する第2工程を有することを特徴とす
る硬質層を有する軟質地盤の改良工法。1. A first step in which a plurality of drilled wall holding material piles are formed in a hard layer, and a part of the hard layer is replaced with the drilled wall holding material. Or a method of improving soft ground having a hard layer, comprising a second step of constructing a wall-shaped object from a design depth.
杭、既製杭又は固結杭であることを特徴とする請求項1
記載の硬質層を有する軟質地盤の改良工法。2. The pile-shaped material or the wall-shaped material is a sand pile, a crushed stone pile, a ready-made pile or a consolidated pile.
An improved method for soft ground having a hard layer as described above.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15924399A JP3524433B2 (en) | 1999-06-07 | 1999-06-07 | Improvement method of soft ground with hard layer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15924399A JP3524433B2 (en) | 1999-06-07 | 1999-06-07 | Improvement method of soft ground with hard layer |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2000345546A true JP2000345546A (en) | 2000-12-12 |
JP3524433B2 JP3524433B2 (en) | 2004-05-10 |
Family
ID=15689483
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15924399A Expired - Fee Related JP3524433B2 (en) | 1999-06-07 | 1999-06-07 | Improvement method of soft ground with hard layer |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3524433B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103850242A (en) * | 2014-03-12 | 2014-06-11 | 朱武卫 | Method for treating collapsible loess foundation by non-compaction method |
CN112726565A (en) * | 2020-12-25 | 2021-04-30 | 中建八局第三建设有限公司 | Construction method for rotary digging pile penetrating through construction waste |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306278B (en) * | 2013-05-31 | 2015-06-10 | 武汉广益交通科技股份有限公司 | Method for processing soft soil foundation with environment-friendly light pile |
-
1999
- 1999-06-07 JP JP15924399A patent/JP3524433B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103850242A (en) * | 2014-03-12 | 2014-06-11 | 朱武卫 | Method for treating collapsible loess foundation by non-compaction method |
CN112726565A (en) * | 2020-12-25 | 2021-04-30 | 中建八局第三建设有限公司 | Construction method for rotary digging pile penetrating through construction waste |
Also Published As
Publication number | Publication date |
---|---|
JP3524433B2 (en) | 2004-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH10204876A (en) | Soil improvement method by using pile | |
JP3524433B2 (en) | Improvement method of soft ground with hard layer | |
JP2700781B2 (en) | Construction method of soil cement pile | |
JP2832508B2 (en) | Retaining wall structure and retaining method | |
JPH09268554A (en) | Construction method of basic pile and device thereof | |
GB2137678A (en) | Method and apparatus for pile construction | |
JPH0280710A (en) | Preparing cast-in-place concrete pile | |
JP4360745B2 (en) | Construction method of ready-made piles | |
JP2004218378A (en) | Removing method for existing pile | |
JP2004270260A (en) | Non-removed earth foundation post construction apparatus and non-removed earth foundation pole construction method | |
JP2000154532A (en) | Ground improving construction method and excavating device therefor | |
JP3706354B2 (en) | Construction method of soil cement pile | |
KR102260596B1 (en) | Site Construction Method Of Base Top Pile For Ground Reinforcement | |
JPS62178620A (en) | Formation of improved angular ground | |
JP2899671B2 (en) | Continuous drilling soil cement wall method and construction excavator | |
JP2886365B2 (en) | Construction method of pile | |
JP7160297B1 (en) | Pile foundation with soil improvement and its construction method | |
JP3005741B2 (en) | Ground improvement method | |
JP3182674B2 (en) | Construction method of agitated mixing reinforcement | |
JP2001164550A (en) | Improvement method of construction ground for underground structure | |
JP3727017B2 (en) | Construction method of soil cement pile | |
JPH0442493B2 (en) | ||
JPH0629509B2 (en) | Construction method of field construction pile | |
JPS63197718A (en) | Construction work of in-situ pile | |
JP2021169749A (en) | Ground improvement method of pile drawing hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20031202 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040206 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040212 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3524433 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100220 Year of fee payment: 6 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100220 Year of fee payment: 6 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110220 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110220 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120220 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120220 Year of fee payment: 8 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120220 Year of fee payment: 8 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130220 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130220 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |