JP2000170175A - Execution method of footing beam - Google Patents

Execution method of footing beam

Info

Publication number
JP2000170175A
JP2000170175A JP10345467A JP34546798A JP2000170175A JP 2000170175 A JP2000170175 A JP 2000170175A JP 10345467 A JP10345467 A JP 10345467A JP 34546798 A JP34546798 A JP 34546798A JP 2000170175 A JP2000170175 A JP 2000170175A
Authority
JP
Japan
Prior art keywords
soil
underground
underground beam
improved soil
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10345467A
Other languages
Japanese (ja)
Inventor
Misao Suzuki
操 鈴木
Nobuyuki Nakamura
信行 中村
Nobuhiro Imai
信宏 今井
Hideaki Hoshi
秀明 星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP10345467A priority Critical patent/JP2000170175A/en
Publication of JP2000170175A publication Critical patent/JP2000170175A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To enable saving, a low cost and a short construction period by backfilling a ditch by improvement soil comprising a mixture of soil, consolidation material and water after a footing beam is arranged in a ditch excavated for footing beam setting to be set on a column. SOLUTION: A pile 1 is set on ground 2, and the upper part of the pile 1 is integrated with a footing 20 having a column 5. Footing beams 7, 9 are arranged in a previously excavated ditch and joined on the column 5. Improvement soil 11 comprising a mixture of excavated soil, consolidation material and water is charged in the ditch layer the footing beams 7, 9 to be backfilled. Thereafter, a water sealing plate 13 is set, after the mixture is consolidated, the surface is ground softly and sill concrete is executed. Thereby the compaction working of soil after backfilling and the supply of good quality soil are unneeded, the execution of the underground beam of saving, a short construction period, environment good and a low cost is made possible, and the disposal amount and cost of excavation residual soil can be reduced by the use of the evacuation production soil produced during the excavation of the ditch.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地中梁を有する建
築構造物および土木構造物の地中梁の施工方法に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underground beam for an architectural structure having an underground beam and a civil structure.

【0002】[0002]

【従来の技術】地中梁の施工は、地盤に溝を掘り、梁設
置後、梁と溝の壁との空間に土を埋戻す。この際、次工
程の工種の施工性、将来の地盤の利便性を良くするた
め、あるいは埋戻し部が陥没、沈下などしないように、
比較的良質な土で十分締固める。また、発生した土は、
品質的に比較的良質でない場合、残土として処分する。
2. Description of the Related Art Underground beams are constructed by digging a groove in the ground, and after installing the beam, burying the soil in the space between the beam and the wall of the groove. At this time, in order to improve the workability of the type of work in the next process, the convenience of the ground in the future, or so that the backfill part does not sink or sink,
Compact the soil with relatively good quality soil. Also, the generated soil is
If the quality is not relatively good, dispose of it as surplus soil.

【0003】なお、地中梁が鋼製の場合には、地中での
腐食を防止するため、その回りを鉄筋コンクリートで巻
くか、あるいは鋼製梁自体を表面に特別な塗覆装をした
ものにする。また、最近では、特開平4−315620
号公報に示されるように地中梁を含む基礎全体を遮水シ
ートで覆い、周辺地盤と遮断することによって腐食を防
止するという案も提案されている。
[0003] When the underground beam is made of steel, the underground beam is wrapped around with reinforced concrete or the steel beam itself is coated with a special coating to prevent corrosion in the ground. To Recently, Japanese Patent Application Laid-Open No. 4-315620
As disclosed in Japanese Unexamined Patent Publication, there has been proposed a proposal in which the entire foundation including the underground beam is covered with a seepage control sheet to block the surrounding foundation and thereby prevent corrosion.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、従来の
地中梁の施工方法の場合には以下のような問題があっ
た。まず、地中梁の施工の際、土を十分締固める必要が
あるため、手間と工期とコストがかかる。また、埋戻し
には比較的良質な土を使う必要があるため、建築構造物
または土木構造物の建設場所の地盤を構成する土が比較
的良質でないときには、新規に埋戻し用の土を入手する
必要があると共に、入手した以上の量の残土を処分する
必要があり、環境負荷が大きいという問題がある。
However, the conventional underground beam construction method has the following problems. First, when constructing an underground beam, it is necessary to compact the soil sufficiently, which takes time, construction time and cost. In addition, since it is necessary to use relatively high quality soil for backfilling, if the soil that constitutes the ground of the construction site of the building structure or civil engineering structure is not of relatively high quality, newly obtain backfill soil. In addition to this, there is a problem that it is necessary to dispose of the surplus soil in an amount larger than that obtained, which causes a large environmental load.

【0005】さらに、地中梁が鋼製の場合において鉄筋
コンクリートを巻く方法では、型粋を組むためのスペー
スの関係で必要範囲以上に溝を掘る必要があり、コス
ト、工期がかかるほかに、新規入手土と処分残土の量が
増えるという問題もある。また、地中梁表面に塗覆装を
施す方法の場合には、鉄筋コンクリートを巻く場合に比
べて掘削土量は減るが、地中梁自体の材料のコストが著
しく上がるという問題がある。さらに、地中梁を含む基
礎全体を遮水シートで覆う方法の場合には、杭または柱
と地中梁との接合部などのように形状が複雑な部分で
は、遮水シート工事が煩雑となり、また杭と遮水シート
の接点における遮水の信頼性を高めるために、かなりの
手間、コストがかかるという問題がある。以上のよう
に、従来の方法では、手間、コスト、工期がかかり、環
境負荷も大きいという種々の問題があった。
[0005] Further, in the method of winding reinforced concrete when the underground beam is made of steel, it is necessary to dig a groove more than necessary due to the space for assembling the mold, which increases the cost and the construction period, and requires a new method. There is also a problem that the amount of soil obtained and the amount of soil left after disposal increase. Further, in the case of the method of coating and coating the underground beam surface, the amount of excavated soil is reduced as compared with the case where reinforced concrete is wound, but there is a problem that the cost of the material of the underground beam itself is significantly increased. Furthermore, in the case of the method of covering the entire foundation including the underground beam with the impermeable sheet, the construction of the impermeable sheet becomes complicated in sections with complicated shapes such as joints between piles or columns and the underground beam. In addition, there is a problem that considerable labor and cost are required to improve the reliability of the water barrier at the contact point between the pile and the water barrier sheet. As described above, the conventional method has various problems that it takes time, cost, and construction time, and that it has a large environmental load.

【0006】本発明は、かかる問題点を解決するために
なされたものであり、省力化、低コスト化、短工期化を
図ると共に環境負荷を低減することのできる地中梁の施
工方法を提供することを目的としている。
The present invention has been made in order to solve such problems, and provides a method of constructing an underground beam capable of saving labor, reducing costs, shortening the construction period, and reducing the environmental load. It is intended to be.

【0007】[0007]

【課題を解決するための手段】本発明に係る地中梁の施
工方法は、地中架設置のために掘削された溝に地中梁を
配置して柱に設置後、土と固化材と水との混合物からな
る改良土により前記溝を埋め戻すものである。
According to the present invention, there is provided a method of constructing an underground beam according to the present invention. The groove is backfilled with an improved soil made of a mixture with water.

【0008】また、土は溝の掘削の際に発生した掘削発
生土を使用することを特徴とするものである。
The soil is characterized by using excavated soil generated during excavation of the trench.

【0009】さらに、固化材はセメント系の固化材また
は石灰系の固化材であることを特徴とするものである。
Further, the solidified material is a cement-based solidified material or a lime-based solidified material.

【0010】また、地中梁が、改良土に少なくとも10
cmの厚さで覆われるようにしたことを特徴とするもの
である。
[0010] Also, the underground beam should have at least 10
It is characterized by being covered with a thickness of cm.

【0011】さらに、改良土と該改良土の上に打設する
土間コンクリートとの間に止水板を設置したことを特徴
とするものである。
[0011] Further, a waterproof plate is provided between the improved soil and the concrete between the soils to be cast on the improved soil.

【0012】また、改良土の上面に凹凸を形成して該改
良土と該改良土の上に打設する土間コンクリートとの間
の止水性を向上させるようにしたことを特徴とするもの
である。
[0012] The present invention is also characterized in that unevenness is formed on the upper surface of the improved soil to improve the water stoppage between the improved soil and the concrete between the soils cast on the improved soil. .

【0013】[0013]

【発明の実施の形態】実施の形態1.図1は本発明の一
実施の形態を説明するための斜視図、図2は正面断面
図、図3は図2における矢視A−A断面図、図4は図2
における矢視B−B断面図、図5は図2における矢視C
−C断面図である。まず、図1〜図5に基づいて本実施
の形態によって施工された完成状態について説明し、そ
の後で施工手順を説明する。図1〜図5において、1は
地盤2に設置された複数の杭、20は柱5からの応力を
杭1に伝えるフーチング、5は下端がフーチング20の
上端部に挿入設置された柱、7,9は柱5に互いに直角
方向に接合された鋼製のH形断面の地中梁である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiment 1 1 is a perspective view for explaining an embodiment of the present invention, FIG. 2 is a front sectional view, FIG. 3 is a sectional view taken along the line AA in FIG. 2, and FIG.
5 is a sectional view taken along the line BB in FIG.
It is -C sectional drawing. First, a completed state constructed according to the present embodiment will be described with reference to FIGS. 1 to 5, and then a construction procedure will be described. 1 to 5, reference numeral 1 denotes a plurality of piles installed on the ground 2, 20 denotes a footing for transmitting the stress from the column 5 to the pile 1, 5 denotes a column having a lower end inserted and installed in an upper end of the footing 20, 7. , 9 are H-shaped underground beams made of steel joined to the column 5 at right angles to each other.

【0014】11は少なくとも10cm以上の厚さで地
中梁7,9の周囲に設置された改良土である。この改良
土11は、掘削土、固化材及び水の混合物からなり、固
化材は土1m3 に対し50kg以上を混合したものであ
る。なお、固化材としては、セメント系の固化材(セメ
ントを含む)又は石灰系の固化材を用いる。13は改良
土11と後述の土間コンクリートとの境界部に設置され
た止水板であり、境界部から地下水が地中梁7,9側に
侵入するのを防止している。15は改良土11及び地盤
2上に設置された土間コンクリート、16は地中梁7,
9をセットする際に用いる梁セット治具である。
Reference numeral 11 denotes an improved soil having a thickness of at least 10 cm and installed around the underground beams 7 and 9. The improved soil 11 is composed of a mixture of excavated soil, a solidified material and water, and the solidified material is a mixture of 1 m 3 of soil and 50 kg or more. As the solidifying material, a cement-based solidifying material (including cement) or a lime-based solidifying material is used. Reference numeral 13 denotes a water stop plate provided at a boundary between the improved soil 11 and the later-described soil concrete, which prevents groundwater from entering the underground beams 7 and 9 from the boundary. Reference numeral 15 denotes the concrete between the soils installed on the improved soil 11 and the ground 2, and 16 denotes the underground beam 7,
9 is a beam setting jig used when setting 9.

【0015】次に、施工手順を説明する。地盤2に杭1
を設置し、杭上部を柱5を有するフーチング20で一体
化する。次に、柱5に地中梁7,9を予め掘削された溝
(地中梁7,9の周囲に少なくとも10cmの隙間がで
きるように掘削しておく。)に配置すると共に柱5に接
合する。そして、掘削土と固化材と水の混合物からなる
改良土11を地中梁7,9を布設した溝内に投入して埋
め戻す。そして、止水板13を設置し、混合物が固化
後、その表面を軽く削り、土間コンクリート15を施工
する。
Next, the construction procedure will be described. Pile 1 on ground 2
Is installed, and the pile upper part is integrated with the footing 20 having the pillar 5. Next, the underground beams 7 and 9 are arranged on the pillar 5 in a previously excavated groove (excavated so that a gap of at least 10 cm is formed around the underground beams 7 and 9) and joined to the pillar 5. I do. Then, the improved soil 11 made of a mixture of the excavated soil, the solidified material, and the water is put into the groove in which the underground beams 7, 9 are laid, and backfilled. Then, the water blocking plate 13 is installed, and after the mixture is solidified, the surface thereof is lightly shaved and the concrete between the earth 15 is constructed.

【0016】次に、本実施の形態の効果を、改良土の強
度及び腐食性の観点から説明する。まず、改良土の強度
については、土と固化材(土1m3 に対し50kg以
上)と水の混合物からなる改良土で鋼材の周囲を10c
mに渡って埋戻し、改良土が固化後に改良土の一軸圧縮
強さを測定した結果、初期から長期に亘って2〜3kg
f/cm2 であった。したがって、改良土を利用するこ
とで、地盤を締固める作業が不要となることが分かる。
Next, the effects of the present embodiment will be described from the viewpoint of the strength and corrosiveness of the improved soil. First, the intensity of the modified soil, the surrounding steel in the soil and the solidifying material (or 50kg to Sat 1 m 3) and a mixture of water improved soil 10c
m, and after measuring the unconfined compressive strength of the improved soil after the improved soil was solidified, 2-3 kg over the initial to long term
f / cm 2 . Therefore, it can be seen that the use of the improved soil eliminates the need to compact the ground.

【0017】次に、腐食性について述べる。図6は地盤
のpH値と鋼材の腐食速度の関係を示した図表であり、
縦軸が腐食速度を示し、横軸がpH値を示している。こ
の図表から分かるように、pH値が約11以上で腐食速
度が急激に小さくなることがわかる。これは、別途調査
した結果、鋼材の周面がpH11以上なら、鋼材の表面
に不動態皮膜が形成されるため、鋼材の腐食はほとんど
起きないためであることがわかった。したがって、鋼製
の地中梁を利用する場合には地中梁の周囲のpH値を1
1以上にすることで、腐食速度を小さくして腐食防止を
図ることができることが分かる。
Next, the corrosiveness will be described. FIG. 6 is a chart showing the relationship between the pH value of the ground and the corrosion rate of steel material,
The vertical axis indicates the corrosion rate, and the horizontal axis indicates the pH value. As can be seen from this chart, the corrosion rate sharply decreases when the pH value is about 11 or more. As a result of a separate investigation, it was found that if the peripheral surface of the steel material had a pH of 11 or more, a passive film was formed on the surface of the steel material, so that corrosion of the steel material hardly occurred. Therefore, when a steel underground beam is used, the pH value around the underground beam is set to 1
It can be seen that by setting it to 1 or more, the corrosion rate can be reduced to prevent corrosion.

【0018】また、図7は改良土のpHの追跡調査を示
すグラフであり、深度0〜40cmまでを改良土とし、
深度40cmよりも深い部分を未改良土とした場合であ
る。この図表から分かるように、深度約10cm以上の
改良土ではpH値が11〜12になっていることがわか
る。したがって、鋼製の地中梁を改良土で10cm以上
の厚みで覆うことによって、地中梁の周面ではpH値を
11〜12にすることができることがわかる。なお、改
良土の境界から10cm以上離れた位置では、pH値は
6〜7となっており、周辺地盤に影響を及ぼさないこと
が分かる。
FIG. 7 is a graph showing a follow-up survey of the pH of the improved soil.
This is a case where a portion deeper than 40 cm in depth is regarded as unimproved soil. As can be seen from this chart, the pH value of the improved soil having a depth of about 10 cm or more is 11 to 12. Therefore, it can be seen that the pH value can be adjusted to 11 to 12 on the peripheral surface of the underground beam by covering the steel underground beam with the improved soil at a thickness of 10 cm or more. At a position 10 cm or more away from the boundary of the improved soil, the pH value is 6 to 7, indicating that the pH does not affect the surrounding ground.

【0019】さらに、図8は、改良土を通過した通過水
のpH値の経時変化を示すグラフであり、縦軸がpH値
を示し、横軸が経過日数を示している。このグラフから
分かるように、pH値は長期間に亘って11〜12の間
を保持していることがわかる。
FIG. 8 is a graph showing the change over time of the pH value of the water passing through the improved soil. The vertical axis shows the pH value, and the horizontal axis shows the elapsed days. As can be seen from this graph, the pH value is maintained between 11 and 12 for a long period of time.

【0020】以上の図6〜図8の説明から分かるよう
に、本実施の形態のように地中梁7,9の周囲を10c
m以上の厚みでセメント系の固化材を用いた改良土11
によって覆うことにより、長期間に亘って地中梁7,9
の周面のをpH値を11〜12に保持することができ、
これによって地中梁7,9の周面に不動態皮膜が形成さ
れて、地中梁7,9の腐食を防止できるのである。
As can be seen from the above description of FIGS. 6 to 8, the periphery of the underground beams 7 and 9 is
improved soil using cement-based solidifying material with a thickness of at least 10 m
, The underground beams 7, 9 for a long time
The pH value of the peripheral surface can be maintained at 11 to 12,
As a result, a passivation film is formed on the peripheral surfaces of the underground beams 7 and 9 and corrosion of the underground beams 7 and 9 can be prevented.

【0021】以上のように、本実施の形態によれば、改
良土を用いることで、締め固めの作業が不要となると共
に、地中梁として鋼製のものを用いた場合にも特別な腐
食対策をすることなく腐食を防止することができる。
As described above, according to the present embodiment, the use of the improved soil eliminates the need for compaction work, and causes special corrosion even when a steel underground beam is used. Corrosion can be prevented without taking measures.

【0022】なお、上記の実施の形態1においては地盤
2と改良土11との間の止水性を高めるために止水板1
3を設置する例を示したが、改良土11の上面に凹凸を
形成することによって止水壁を形成することで止水性を
高めるようにしてもよい。
In the first embodiment, the water blocking plate 1 is used to increase the water blocking between the ground 2 and the improved soil 11.
Although the example in which 3 is installed has been shown, the water blocking property may be enhanced by forming a water blocking wall by forming irregularities on the upper surface of the improved soil 11.

【0023】また、上記の実施の形態1においてはセメ
ント系の固化材または石灰系の固化材を用いた例を示し
たが、固化材としては改良土が一定の強度を有し、一定
のpH値(11〜12)を保持するものであれば、これ
らセメント系又は石灰系の固化材に限定するものではな
い。なお、改良土が一定の強度を有しさえすれば、pH
値が一定でなくても、腐食性を考慮する必要のない地中
梁については利用できることは言うまでもない。
In the first embodiment, an example using a cement-based solidification material or a lime-based solidification material has been described. As the solidification material, the improved soil has a certain strength and a certain pH. It is not limited to these cement-based or lime-based solidified materials as long as they maintain the values (11 to 12). In addition, as long as the improved soil has a certain strength, pH
Even if the value is not constant, it goes without saying that it can be used for underground beams that do not need to consider corrosiveness.

【0024】実施の形態2.図9は本発明の他の実施の
形態を説明するための斜視図、図10は正面断面図、図
11は図10における矢視A−A断面図、図12は図1
0における矢視B−B断面図、図13は図10における
矢視C−C断面図である。以下、図9〜図13に基づい
て実施の形態2を説明する。なお、図9〜図13におい
て実施の形態1を示した図1〜図5と同一部分には同一
符号を付してある。
Embodiment 2 FIG. 9 is a perspective view for explaining another embodiment of the present invention, FIG. 10 is a front sectional view, FIG. 11 is a sectional view taken along the line AA in FIG. 10, and FIG.
10 is a sectional view taken along line BB in FIG. 10, and FIG. 13 is a sectional view taken along line CC in FIG. Hereinafter, the second embodiment will be described with reference to FIGS. 9 to 13, the same parts as those in FIGS. 1 to 5 showing the first embodiment are denoted by the same reference numerals.

【0025】実施の形態2においては床スラブとしてデ
ッキプレートを用いて、このデッキプレート上に土間コ
ンクリートを打設するようにしたものである。基本的な
構成は実施の形態1と同様であるので、以下においては
実施の形態1と異なる点についてのみ説明する。16は
地中梁7,9をセットするときに用いる梁セット用治
具、19は20cm〜30cmのピッチで地中梁7,9
に設置された取付材17を介して地中梁7,9に取り付
けられたアングル材、21は周縁部がアングル材19に
載置されてセットされたデッキプレートである。
In the second embodiment, a deck plate is used as a floor slab, and slab concrete is cast on the deck plate. Since the basic configuration is the same as that of the first embodiment, only differences from the first embodiment will be described below. 16 is a beam setting jig used for setting the underground beams 7, 9; 19 is an underground beam 7, 9 at a pitch of 20 cm to 30 cm.
An angle member 21 is attached to the underground beams 7 and 9 via an attachment member 17 installed at the bottom, and a deck plate 21 is set with its peripheral edge placed on the angle member 19.

【0026】次に、施工手順を説明する。地盤2に杭1
を設置し、杭上部を柱5を有するフーチング20で一体
化する。次に、柱5に地中梁7,9を予め掘削された溝
(地中梁7,9の周囲に少なくとも10cmの隙間がで
きるように掘削しておく。)に梁セット用治具16を用
いて配置すると共に柱5に接合する。そして、掘削土と
固化材と水の混合物からなる改良土11を地中梁7,9
を布設した溝内に投入して埋め戻す。そして、止水板1
3を設置し、混合物が固化後、その表面を軽く削り取り
ならしておく。その後、取付材19を20cm〜30c
mのピッチで地中梁7,9に設置し、さらにアングル材
19を取付材17に接合する。
Next, the construction procedure will be described. Pile 1 on ground 2
Is installed, and the pile upper part is integrated with the footing 20 having the pillar 5. Next, the beam setting jig 16 is inserted into the groove (the underground beams 7, 9 are excavated so that a gap of at least 10 cm is formed around the underground beams 7, 9) in the pillar 5 in which the underground beams 7, 9 are excavated in advance. And bonded to the pillar 5. Then, the improved soil 11 composed of the mixture of the excavated soil, the solidified material, and the water is transferred to the underground beams 7, 9
Into the groove where it was laid and backfilled. And the water stop plate 1
3 is set, and after the mixture has solidified, its surface is lightly shaved off. After that, the mounting material 19 is changed from 20 cm to 30 c.
It is installed on the underground beams 7 and 9 at a pitch of m, and the angle member 19 is joined to the mounting member 17.

【0027】次に、デッキプレート21の周縁部をアン
グル材19に載置する。その後、アングル材19で囲ま
れた地中梁7,9の周囲及びデッキプレート21上にコ
ンクリートを打設する。この地中梁7,9の周囲にコン
クリートを打設する際に、アングル材19が型枠の役割
をすることになる。
Next, the periphery of the deck plate 21 is placed on the angle member 19. Thereafter, concrete is cast around the underground beams 7 and 9 surrounded by the angle members 19 and on the deck plate 21. When casting concrete around the underground beams 7, 9, the angle members 19 serve as formwork.

【0028】実施の形態2によれば、床スラブとしてデ
ッキプレートを用いたので、土間コンクリートを打設す
る際に地盤の均し作業と締め固め作業が不要となる。
According to the second embodiment, since the deck plate is used as the floor slab, the work of leveling and compacting the ground is not required when placing the concrete between the soil.

【0029】実施の形態3.図14は本発明の他の実施
の形態を説明するための斜視図、図15は正面断面図、
図16は図15における矢視A−A断面図、図17は図
15における矢視B−B断面図、図18は図15におけ
る矢視C−C断面図である。図14〜図18において実
施の形態1と同一部分には同一の符号を付してある。
Embodiment 3 FIG. 14 is a perspective view for explaining another embodiment of the present invention, FIG. 15 is a front sectional view,
16 is a sectional view taken along line AA in FIG. 15, FIG. 17 is a sectional view taken along line BB in FIG. 15, and FIG. 18 is a sectional view taken along line CC in FIG. 14 to 18, the same parts as those in the first embodiment are denoted by the same reference numerals.

【0030】本実施の形態は基礎部の構造が実施の形態
1と異なるものに本発明を適用したものであり、基礎部
以外の構成は実施の形態1と同様である。まず、図14
〜図18に基づいて本実施の形態によって施工された完
成状態について説明し、その後で施工手順を説明する。
図14〜図18において、31は地盤32に設置されて
周囲にグラウト34(又はコンクリート)を注入すると
共に内部にコンクリート33を充填したコンクリート充
填杭、5は下端がコンクリート充填杭31の上端部に挿
入設置された柱である。
In the present embodiment, the present invention is applied to a structure different from that of the first embodiment in the structure of the basic portion, and the configuration other than the basic portion is the same as that of the first embodiment. First, FIG.
A completed state constructed according to the present embodiment will be described with reference to FIG. 18, and then the construction procedure will be described.
14 to 18, reference numeral 31 denotes a concrete-filled pile in which grout 34 (or concrete) is injected around and is filled with concrete 33 inside, and 5 denotes a lower end at the upper end of the concrete-filled pile 31. It is a pillar inserted and installed.

【0031】地中梁7,9、改良土11、止水板13、
土間コンクリート15、梁セット治具16の構成につい
ては実施の形態1と同様である。
Underground beams 7, 9, improved soil 11, water stoppage plate 13,
The configurations of the concrete between the soil 15 and the beam setting jig 16 are the same as those in the first embodiment.

【0032】次に、施工手順を説明する。地盤32にコ
ンクリート充填杭31を設置すると共に、柱5をコンク
リート充填杭31に立設する。次に、柱5に地中梁7,
9を予め掘削された溝(地中梁7,9の周囲に少なくと
も10cmの隙間ができるように掘削しておく。)に配
置すると共に柱5に接合する。そして、掘削土と固化材
と水の混合物からなる改良土11を地中梁7,9を布設
した溝内に投入して埋め戻す。そして、止水板13を設
置し、混合物が固化後、その表面を軽く削り、土間コン
クリート15を施工する。
Next, the construction procedure will be described. The concrete-filled pile 31 is installed on the ground 32, and the column 5 is erected on the concrete-filled pile 31. Next, the underground beam 7,
9 is placed in a previously excavated groove (excavated so that a gap of at least 10 cm is formed around the underground beams 7, 9) and joined to the column 5. Then, the improved soil 11 made of a mixture of the excavated soil, the solidified material, and the water is put into the groove in which the underground beams 7, 9 are laid, and backfilled. Then, the water blocking plate 13 is installed, and after the mixture is solidified, the surface thereof is lightly shaved and the concrete between the earth 15 is constructed.

【0033】実施の形態4.図19は本発明の他の実施
の形態を説明するための斜視図、図20は正面断面図、
図21は図20における矢視A−A断面図、図22は図
20における矢視B−B断面図、図23は図20におけ
る矢視C−C断面図である。本実施の形態は基礎部の構
造が実施の形態2と異なるものに本発明を適用したもの
であり、基礎部以外の構成は実施の形態2と同様であ
る。また、基礎部の構造は実施の形態3と同様である。
そこで、図19〜図23において実施の形態2,3を示
した図9〜図13、図14〜図18と同一部分には同一
符号を付して、以下施工手順について説明する。
Embodiment 4 FIG. 19 is a perspective view for explaining another embodiment of the present invention, FIG. 20 is a front sectional view,
21 is a sectional view taken along line AA in FIG. 20, FIG. 22 is a sectional view taken along line BB in FIG. 20, and FIG. 23 is a sectional view taken along line CC in FIG. In the present embodiment, the present invention is applied to a structure having a different basic structure from that of the second embodiment. The configuration other than the basic structure is the same as that of the second embodiment. The structure of the base is the same as that of the third embodiment.
Therefore, the same reference numerals are given to the same parts as in FIGS. 9 to 13 and FIGS. 14 to 18 showing the second and third embodiments in FIGS. 19 to 23, and the construction procedure will be described below.

【0034】地盤32にコンクリート充填杭31を設置
すると共に、柱5をコンクリート充填杭31に立設す
る。次に、柱5に地中梁7,9を予め掘削された溝(地
中梁7,9の周囲に少なくとも10cmの隙間ができる
ように掘削しておく。)に梁セット用治具16を用いて
配置すると共に柱5に接合する。そして、掘削土と固化
材と水の混合物からなる改良土11を地中梁7,9を布
設した溝内に投入して埋め戻す。そして、止水板13を
設置し、混合物が固化後、その表面を軽く削り取りなら
しておく。その後、取付材19を20cm〜30cmの
ピッチで地中梁7,9に設置し、さらにアングル材19
を取付材17に接合する。
The concrete-filled pile 31 is installed on the ground 32 and the column 5 is erected on the concrete-filled pile 31. Next, the beam setting jig 16 is inserted into the groove (the underground beams 7, 9 are excavated so that a gap of at least 10 cm is formed around the underground beams 7, 9) in the pillar 5 in which the underground beams 7, 9 are excavated in advance. And bonded to the pillar 5. Then, the improved soil 11 made of a mixture of the excavated soil, the solidified material, and the water is put into the groove in which the underground beams 7, 9 are laid, and backfilled. Then, the water stop plate 13 is provided, and after the mixture is solidified, the surface thereof is lightly scraped off. Thereafter, the mounting members 19 are installed on the underground beams 7, 9 at a pitch of 20 cm to 30 cm, and the angle members 19 are further mounted.
To the mounting member 17.

【0035】次に、デッキプレート21の周縁部をアン
グル材19に載置する。その後、アングル材19で囲ま
れた地中梁7,9の周囲及びデッキプレート21上にコ
ンクリートを打設する。この地中梁7,9の周囲にコン
クリートを打設する際に、アングル材19が型枠の役割
をすることになる。
Next, the periphery of the deck plate 21 is placed on the angle member 19. Thereafter, concrete is cast around the underground beams 7 and 9 surrounded by the angle members 19 and on the deck plate 21. When casting concrete around the underground beams 7, 9, the angle members 19 serve as formwork.

【0036】なお、以上の説明においては、鋼製の地中
梁を例に挙げて説明したが、本発明は鋼製の地中梁に限
定するものではなく、鉄筋コンクリート梁にも適用する
ことができるのは言うまでもない。
In the above description, the steel underground beam has been described as an example. However, the present invention is not limited to the steel underground beam, but may be applied to a reinforced concrete beam. It goes without saying that you can do it.

【0037】[0037]

【発明の効果】本発明は以上説明したように構成したの
で以下に示すような効果を奏する。
Since the present invention is constructed as described above, the following effects can be obtained.

【0038】地中梁設置のために掘削された溝に地中梁
を配置して柱に設置後、土と固化材と水との混合物から
なる改良土により前記溝を埋め戻すようにしたので、埋
戻し後に土の締固め作業や良質の土の調達が不要とな
り、省力化、短工期、環境良好、低コストの地中梁の施
工が可能となる。
After the underground beam was placed in the trench excavated for the installation of the underground beam and installed on the pillar, the trench was backfilled with the improved soil consisting of a mixture of soil, solidified material and water. The need for soil compaction work and the procurement of high quality soil after backfilling is no longer necessary, and labor saving, short construction period, good environment, and low-cost construction of underground beams are possible.

【0039】また、溝の掘削の際に発生した掘削発生土
を使用するようにしたので、掘削残土の処分量及び費用
を低減できる。
Further, since the excavated soil generated during the excavation of the trench is used, the disposal amount and the cost of the excavated soil can be reduced.

【0040】さらに、固化材としてセメント系の固化材
または石灰系の固化材を用いることにより、地中梁とし
て鋼製のものを使用しても、腐食を防止できる。
Further, by using a cement-based solidifying material or a lime-based solidifying material as the solidifying material, corrosion can be prevented even if a steel underground beam is used.

【0041】また、地中梁が、改良土に少なくとも10
cmの厚さで覆われるようにしたので、確実の腐食防止
を図ることができる。
In addition, the underground beam should have at least 10
cm, so that corrosion can be reliably prevented.

【0042】さらに、改良土と該改良土の上に打設する
土間コンクリートとの間に止水板を設置したので、地中
梁側に地下水侵入するのを防止して、地中梁の腐食等を
防止することができる。
Further, since a water stop plate is installed between the improved soil and the concrete between the soils to be cast on the improved soil, it is possible to prevent groundwater from infiltrating into the underground beam side and to corrode the underground beam. Etc. can be prevented.

【0043】また、改良土の上面に凹凸を形成して該改
良土と該改良土の上に打設する土間コンクリートとの間
の止水性を向上させるようにしたので、上記と同様に地
中梁側に地下水侵入するのを防止して、地中梁の腐食等
を防止することができる。
In addition, since unevenness is formed on the upper surface of the improved soil to improve the water stoppage between the improved soil and the concrete between the soils to be cast on the improved soil, the underground is similarly provided as described above. By preventing groundwater from entering the beam side, corrosion of the underground beam and the like can be prevented.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の一実施の形態における地中梁施工状
態の斜視図である。
FIG. 1 is a perspective view showing an underground beam construction state according to an embodiment of the present invention.

【図2】 本発明の一実施の形態における地中梁施工状
態の正面断面図である。
FIG. 2 is a front sectional view of an underground beam in an embodiment of the present invention in a construction state.

【図3】 図2における矢視A−A断面図である。FIG. 3 is a sectional view taken along line AA in FIG. 2;

【図4】 図2における矢視B−B断面図である。FIG. 4 is a sectional view taken along the line BB in FIG. 2;

【図5】 図2における矢視C−C断面図である。FIG. 5 is a sectional view taken along the line CC in FIG. 2;

【図6】 地盤のpH値と鋼材の腐食速度の関係を示し
た図表である。
FIG. 6 is a table showing the relationship between the soil pH value and the corrosion rate of steel.

【図7】 改良土のpHの追跡調査を示すグラフであ
る。
FIG. 7 is a graph showing a follow-up study of the pH of the improved soil.

【図8】 改良土を通過した通過水のpH値の経時変化
を示すグラフである。
FIG. 8 is a graph showing the change over time of the pH value of the passing water that has passed through the improved soil.

【図9】 本発明の他の実施の形態における地中梁施工
状態の斜視図である。
FIG. 9 is a perspective view of an underground beam according to another embodiment of the present invention in a construction state.

【図10】 本発明の他の実施の形態における地中梁施
工状態の正面断面図である。
FIG. 10 is a front sectional view of an underground beam according to another embodiment of the present invention.

【図11】 図10における矢視A−A断面図である。11 is a sectional view taken along the line AA in FIG.

【図12】 図10における矢視B−B断面図である。FIG. 12 is a sectional view taken along the line BB in FIG.

【図13】 図10における矢視C−C断面図である。13 is a sectional view taken along the line CC in FIG.

【図14】 本発明の他の実施の形態における地中梁施
工状態の斜視図である。
FIG. 14 is a perspective view showing an underground beam construction state according to another embodiment of the present invention.

【図15】 本発明の他の実施の形態における地中梁施
工状態の正面断面図である。
FIG. 15 is a front sectional view of another embodiment of the present invention in an underground beam construction state.

【図16】 図15における矢視A−A断面図である。16 is a sectional view taken along the line AA in FIG.

【図17】 図15における矢視B−B断面図である。17 is a sectional view taken along the line BB in FIG.

【図18】 図15における矢視C−C断面図である。18 is a sectional view taken along the line CC in FIG.

【図19】 本発明の他の実施の形態における地中梁施
工状態の斜視図である。
FIG. 19 is a perspective view showing an underground beam construction state according to another embodiment of the present invention.

【図20】 本発明の他の実施の形態における地中梁施
工状態の正面断面図である。
FIG. 20 is a front sectional view of another embodiment of the present invention in an underground beam construction state.

【図21】 図20における矢視A−A断面図である。21 is a sectional view taken along the line AA in FIG. 20.

【図22】 図20における矢視B−B断面図である。22 is a sectional view taken along the line BB in FIG.

【図23】 図20における矢視C−C断面図である。23 is a sectional view taken along the line CC in FIG. 20.

【符号の説明】[Explanation of symbols]

1 杭 5 柱 7,9 地中梁 11 改良土 13 止水板 17 取付材 19 アングル材 20 フーチング 21 デッキプレート DESCRIPTION OF SYMBOLS 1 Pile 5 Column 7 and 9 Underground beam 11 Improved soil 13 Water stop board 17 Mounting material 19 Angle material 20 Footing 21 Deck plate

───────────────────────────────────────────────────── フロントページの続き (72)発明者 今井 信宏 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 (72)発明者 星 秀明 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 Fターム(参考) 2D046 BA00  ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Nobuhiro Imai 1-2-1, Marunouchi, Chiyoda-ku, Tokyo Nihon Kokan Co., Ltd. (72) Inventor Hideaki Hoshi 1-2-1, Marunouchi, Chiyoda-ku, Tokyo Sun F-term in Honko Tube Co., Ltd. (Reference) 2D046 BA00

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 地中梁設置のために掘削された溝に地中
梁を配置して柱に設置後、土と固化材と水との混合物か
らなる改良土により前記溝を埋め戻すことを特徴とする
地中梁の施工方法。
The present invention relates to a method of arranging an underground beam in a trench excavated for installation of an underground beam and installing the underground beam on a pillar, and then backfilling the trench with an improved soil comprising a mixture of soil, a solidifying material, and water. Underground beam construction method that is characteristic.
【請求項2】 前記土は前記溝の掘削の際に発生した掘
削発生土を使用することを特徴とする請求項1記載の地
中梁の施工方法。
2. The underground beam construction method according to claim 1, wherein excavated soil generated during excavation of the trench is used as the soil.
【請求項3】 前記固化材はセメント系の固化材または
石灰系の固化材であることを特徴とする請求項1又は2
記載の地中梁の施工方法。
3. The solidifying material according to claim 1, wherein the solidifying material is a cement-based solidifying material or a lime-based solidifying material.
Construction method of underground beam described.
【請求項4】 前記地中梁が、前記改良土に少なくとも
10cmの厚さで覆われるようにしたことを特徴とする
請求項3記載の地中梁の施工方法。
4. The method according to claim 3, wherein the underground beam is covered with the improved soil with a thickness of at least 10 cm.
【請求項5】 前記改良土と該改良土の上に打設する土
間コンクリートとの間に止水板を設置したことを特徴と
する請求項1〜4のいずれかに記載の地中梁の施工方
法。
5. The underground beam according to claim 1, wherein a water stop plate is provided between the improved soil and concrete between the soil to be cast on the improved soil. Construction method.
【請求項6】 前記改良土の上面に凹凸を形成して該改
良土と該改良土の上に打設する土間コンクリートとの間
の止水性を向上させるようにしたことを特徴とする請求
項1〜5のいずれかに記載の地中梁の施工方法。
6. The water-blocking property between the improved soil and the interstitial concrete cast on the improved soil by forming irregularities on the upper surface of the improved soil. The method for constructing an underground beam according to any one of claims 1 to 5.
JP10345467A 1998-12-04 1998-12-04 Execution method of footing beam Pending JP2000170175A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10345467A JP2000170175A (en) 1998-12-04 1998-12-04 Execution method of footing beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10345467A JP2000170175A (en) 1998-12-04 1998-12-04 Execution method of footing beam

Publications (1)

Publication Number Publication Date
JP2000170175A true JP2000170175A (en) 2000-06-20

Family

ID=18376804

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10345467A Pending JP2000170175A (en) 1998-12-04 1998-12-04 Execution method of footing beam

Country Status (1)

Country Link
JP (1) JP2000170175A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016089509A (en) * 2014-11-06 2016-05-23 株式会社グランデージ Precast concrete foundation beam member, height adjustment member for precast concrete foundation beam member, foundation structure and construction method for foundation structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016089509A (en) * 2014-11-06 2016-05-23 株式会社グランデージ Precast concrete foundation beam member, height adjustment member for precast concrete foundation beam member, foundation structure and construction method for foundation structure

Similar Documents

Publication Publication Date Title
CN103958780B (en) The method for forming cementing retaining wall
CN107542115B (en) Underground engineering waterproof structure and construction method thereof
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
JP2576932B2 (en) Construction method of independent mountain retaining wall
KR101975297B1 (en) Multi-wall construction method using multi-wall construction supporting files and supporting files used for construction of harbors, rivers, dams and concrete that can prevent the inflow of soil and water
JP3107716B2 (en) Soil retaining wall
KR101267688B1 (en) The shore protection construction method using a precast finish panel
JP2000170175A (en) Execution method of footing beam
JP2000170174A (en) Execution method of footing beam
JP2005207132A (en) Caisson, and revetment for reclamation
JP2994243B2 (en) External wall construction method and external wall structure for underground structures
JP3438942B2 (en) Liquefaction countermeasures for underground linear structures
KR20090078684A (en) Composite wall using angled channel and constructing method thereof
JP2000170173A (en) Execution method of footing beam
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JP3728659B2 (en) Basement extension method
JP3030622B2 (en) How to build a tunnel
JPS5944431A (en) Construction of basement
JPH0477764B2 (en)
JPH02248527A (en) Constructing foundation structure
TW418274B (en) A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall
JP2001107361A (en) Earth retaining work structure and ground excavation method
JP2001279686A (en) Construction method for footing beam
JP2964257B2 (en) Lightweight block and embankment method
JPH0649987B2 (en) Underground continuous wall foundation construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050928

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070807

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080422

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080826