JPS5944431A - Construction of basement - Google Patents

Construction of basement

Info

Publication number
JPS5944431A
JPS5944431A JP57155607A JP15560782A JPS5944431A JP S5944431 A JPS5944431 A JP S5944431A JP 57155607 A JP57155607 A JP 57155607A JP 15560782 A JP15560782 A JP 15560782A JP S5944431 A JPS5944431 A JP S5944431A
Authority
JP
Japan
Prior art keywords
foundation
underground space
panels
basement
foundation piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57155607A
Other languages
Japanese (ja)
Inventor
Katsuzou Ochiba
落葉 勝三
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kubota Corp
Original Assignee
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kubota Corp filed Critical Kubota Corp
Priority to JP57155607A priority Critical patent/JPS5944431A/en
Publication of JPS5944431A publication Critical patent/JPS5944431A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls

Abstract

PURPOSE:To effectively construct a basement by a method in which the ground surrounded by a foundation placed along a foundation construction line is excavated to form an underground space, panels are assembled in the underground space by being supported by foundation piles, and a filling material is packed between the panels and the inner wall of the underground space. CONSTITUTION:After foundation piles 2 are driven deeper than a predetermined depth in place on the floor 4 of a basement 4 along a foundation construction line. Foundations 5 are then placed on the construction line 1, and after the constructins 5 are hardened, the ground surrounded by the foundation piles 2 is excavated to form an underground space 6. Supporting pillars 7 are attached to the foundation piles 2, plural panels 8 are assembled in parallel on the foundation piles 2 and subjected to a water-proofing treatment, and then a filling material 12 is packed between the inner wall 6A of the underground space and the panels 8. The excavating range of the underground space 6 can thus be minimized, and since the panels 8, etc., can be produced in advance in a factory, the construction work can be effetively performed.

Description

【発明の詳細な説明】 この発明は地下室の構築方法に関する。[Detailed description of the invention] This invention relates to a method of constructing a basement.

従来、地下室を構築する場合、第1図に示すように、地
下室Aの予定地に、この地下室完成予定床面A1より広
い範囲にわたって、矢板などの土留め部材Bを打ち込ん
だ後掘削し、現場打ちコンクリートなどにより地下室床
面A1、及び壁面A2を構築し、外面に防水施工Cを施
した後、土留め部材Bを除去し、壁面A2と掘削孔内面
との間を埋め戻すことが専ら行われていた。
Conventionally, when constructing a basement, as shown in Figure 1, earth retaining members B such as sheet piles are driven into the planned site of the basement A over an area wider than the planned completion floor surface A1 of the basement, and then the site is excavated. After constructing the basement floor surface A1 and wall surface A2 with poured concrete, etc., and applying waterproofing construction C to the outer surface, the earth retaining member B is removed and the space between wall surface A2 and the inner surface of the excavation hole is backfilled. I was worried.

上記において、掘削孔を設ける大きさは、地下室構築の
際の工事が行いやすくすること、及び工事中の上期れを
防止するといった目的より、一般に、地下室底より約6
0°で引き起した傾斜線りと、地表線GLとの交点とさ
れ、一般に、半地下室又は単層地下室の場合、地下室予
定床面A1に対し約1m程度の巾で掘削される。
In the above, the size of the excavation hole is generally about 6 mm from the bottom of the basement for the purpose of making it easier to perform the construction work when constructing the basement and to prevent delays in the first half of the construction process.
It is defined as the intersection of the slope line drawn at 0° and the ground line GL, and generally, in the case of a semi-basement or a single-story basement, excavation is performed to a width of about 1 m with respect to the planned floor surface A1 of the basement.

しかしながら、上記工法によれば、琴削が大工事となり
、隣地への地盤の影響、騒音等が生じ、−膜性宅地の工
事としては不向きであり、種々の制約のため、任意に施
工ができないといった欠点があった。
However, according to the above construction method, koto excavation is a major construction work, which causes the influence of the ground on neighboring land, noise, etc. - It is unsuitable for construction work on membrane-based residential land, and due to various restrictions, construction cannot be carried out arbitrarily. There were some drawbacks.

この発明は上記欠点に鑑み、特に隣地への地盤の影響を
極力なくし、かつ、容易に施工可能な地下室の構築方法
を得ることを目的としてなされたものであって、建築物
の基礎構築線に沿って適所に基礎杭を打ち込んだ後、前
記基礎構集線上に基礎土台を打設し、硬化完成後前記基
礎杭を結ぶ線で囲まれる範囲内を掘削し、地下空間を形
成し、該地下空間内に位置する前記基礎杭に支持させて
複数のパネルを前記地下空間内に組立て、そして前記パ
ネルと前記地下空間の内壁との間に充填材を充填するこ
とを特徴と゛するものである。
In view of the above-mentioned drawbacks, this invention has been made with the aim of providing a method of constructing a basement that can be easily constructed while minimizing the influence of the ground on neighboring land as much as possible. After driving foundation piles at appropriate locations along the foundation, a foundation foundation is driven on the foundation assembly line, and after hardening is completed, an area surrounded by the line connecting the foundation piles is excavated to form an underground space. A plurality of panels are assembled in the underground space by being supported by the foundation piles located in the space, and a filler is filled between the panels and the inner wall of the underground space.

以下、この発明を実施例により説明する。This invention will be explained below with reference to Examples.

第2図〜第3図はこの発明の実施例の工程を示す説明図
、第4図はこの発明の実施例に使用されるパネルの断面
図である。
2 and 3 are explanatory diagrams showing the steps of an embodiment of this invention, and FIG. 4 is a sectional view of a panel used in an embodiment of this invention.

この発明の地下室の構築方法は、まず、第2図に示すよ
うに、建築物の基礎構築線1に沿って、例えばコーナ部
IA、あるいはコーナIA間中間位置IBなどの適所に
基礎杭2,2を第3図に示すように地下室3の床面4形
成予定位置より深く打ち込み、しかる後、基礎構築線1
上に基礎土台5を打設し、硬化完成後、前記基礎杭2,
2を結ぶ線で囲まれる範囲内を第2図又は第3図に示す
ように掘削し、地下空間6を形成し、この地下空間6内
に位置する前記基礎杭2,2にそれぞれ支持柱7,7を
取付け、この支持柱7,7を介して基礎杭2,2に支持
させて、第4図に示すように内装面8A及び周囲端面8
Bに防水性スキン層9が設けられた複数の発泡コンクリ
ート製パネル8を並列状態に組立て、接合部10間に防
水性シーリング材11を圧入し、防水施工した後、前記
パネル8と前記地下空間内壁6Aとの間に、基礎土台5
に予め形成した注入口5Aより砂利又はコンクリート等
の充填材12を充填する。
As shown in FIG. 2, the method for constructing a basement according to the present invention is to first install foundation piles 2, 2 is driven deeper than the planned location for forming the floor 4 of the basement 3 as shown in Figure 3, and then the foundation construction line 1 is
A foundation foundation 5 is cast on top, and after hardening, the foundation pile 2,
As shown in FIG. 2 or 3, the area surrounded by the line connecting 2 is excavated to form an underground space 6, and support columns 7 are attached to the foundation piles 2, 2 located within this underground space 6, respectively. , 7 are attached and supported by the foundation piles 2, 2 via the support columns 7, 7, the interior surface 8A and the peripheral end surface 8 are installed as shown in FIG.
A plurality of foamed concrete panels 8 provided with a waterproof skin layer 9 are assembled in parallel on B, and a waterproof sealing material 11 is press-fitted between the joints 10 to perform waterproofing, and then the panels 8 and the underground space are sealed. Between the inner wall 6A, the foundation foundation 5
A filler material 12 such as gravel or concrete is filled through an injection port 5A formed in advance.

上記において、地下空間6の内壁6Aとパネル8との間
の間隔は100mm〜200mmで充分であわ、これ以
上の大きさとする必要はない。
In the above, it is sufficient that the distance between the inner wall 6A of the underground space 6 and the panel 8 is 100 mm to 200 mm, and there is no need to make it larger.

又、掘削された地下空間6は、その上部が枠状の基礎土
台5により、又側部が基礎杭2,2により補強されるた
め、土部れは充分に防止される。
Further, the excavated underground space 6 is reinforced at its upper part by the frame-shaped foundation foundation 5 and at its side by the foundation piles 2, 2, so that soil sagging is sufficiently prevented.

上記実施例では、パネルは発泡コンクリート製とされ、
外面部には地下水が自由に浸透するようにされているた
め、この地下水により地下室の保温が効率良く行われ、
しかも内装面のスキン層によって漏水か防止される七い
う効果を有する。
In the above embodiment, the panel is made of foamed concrete;
Because groundwater is allowed to freely permeate the exterior, this groundwater efficiently keeps the basement warm.
Moreover, the skin layer on the interior surface prevents water leakage.

この発明は以上のように構成されているから、地下室構
築のための掘削範囲が最小限ですみ、隣地への地盤沈下
、騒音等、の障害が軽減でき、又、パネルは予め工場生
産可能であり、従来工法と同程度以上の水密性を有する
地下室が、容易にかつ迅速に構築することが1きるので
、−膜性宅用の地下室の構築などに特に施工が容易に行
えるといった効果を有する。
Since this invention is configured as described above, the excavation range for constructing a basement can be minimized, and obstacles such as ground subsidence and noise to neighboring land can be reduced.Furthermore, the panels can be manufactured in advance in a factory. Since it is possible to easily and quickly construct a basement with watertightness equivalent to or higher than conventional construction methods, it has the effect of being easy to construct, especially when constructing basements for residential buildings. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来例の説明図、第2図、第3図はこの発明の
実施例の施工説明図、第4図はこの発明の実施例に使用
されるパネルの断面図である。 1・・・基礎構築線、2・・・基礎杭、5・・・基礎土
台、6・・・地下空間、7・・・支持柱、8・・・パネ
ル、8A・・・内装面、8B・・・周囲端面、9・・・
防水性スキン 5 一 層、10・・・接合部、11・・・シーリング材、12
・・・充填材。  6−
FIG. 1 is an explanatory diagram of a conventional example, FIGS. 2 and 3 are construction explanatory diagrams of an embodiment of this invention, and FIG. 4 is a sectional view of a panel used in an embodiment of this invention. 1...Foundation construction line, 2...Foundation pile, 5...Foundation foundation, 6...Underground space, 7...Support column, 8...Panel, 8A...Interior surface, 8B ... Peripheral end face, 9...
Waterproof skin 5 single layer, 10... joint, 11... sealing material, 12
...Filling material. 6-

Claims (1)

【特許請求の範囲】[Claims] (1)建築物の基礎構築線に沿って適所に基礎杭を打ち
込んだ後、前記基礎構築線上に基礎土台を打設し、硬化
完成後前記基礎杭を結ぶ線で囲まれる範囲内を掘削し、
地下空間を形成し、該地下空間内に位置する前記基礎杭
に支持させて複数のパネルを前記地下空間内に組立て、
そして前記パネルと前記地下空間の内壁との間に充填材
を充填することを特徴とする地下室の構築方法。
(1) After driving foundation piles at appropriate locations along the foundation construction line of the building, drive the foundation foundation on the foundation construction line, and after hardening, excavate within the area surrounded by the line connecting the foundation piles. ,
forming an underground space, and assembling a plurality of panels in the underground space while supporting them on the foundation piles located in the underground space;
A method for constructing a basement, characterized in that a filling material is filled between the panel and the inner wall of the underground space.
JP57155607A 1982-09-06 1982-09-06 Construction of basement Pending JPS5944431A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57155607A JPS5944431A (en) 1982-09-06 1982-09-06 Construction of basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57155607A JPS5944431A (en) 1982-09-06 1982-09-06 Construction of basement

Publications (1)

Publication Number Publication Date
JPS5944431A true JPS5944431A (en) 1984-03-12

Family

ID=15609718

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57155607A Pending JPS5944431A (en) 1982-09-06 1982-09-06 Construction of basement

Country Status (1)

Country Link
JP (1) JPS5944431A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61283587A (en) * 1985-06-10 1986-12-13 Oike Ind Co Ltd Transfer printing method
NL1018341C2 (en) * 2001-06-20 2002-12-30 B & R Beheer B V Method is for underground installation of prefabricated concrete cellar and involves cellar being fixed to support structure, particularly concrete or steel foundation beam
WO2011009219A1 (en) * 2009-07-24 2011-01-27 Sfs Structures Ltd. Shoring free excavation and basement construction apparatus and method
EP3521514A1 (en) * 2018-02-05 2019-08-07 PPZS s.r.o. Permanent prefabricated braced wall

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61283587A (en) * 1985-06-10 1986-12-13 Oike Ind Co Ltd Transfer printing method
NL1018341C2 (en) * 2001-06-20 2002-12-30 B & R Beheer B V Method is for underground installation of prefabricated concrete cellar and involves cellar being fixed to support structure, particularly concrete or steel foundation beam
WO2011009219A1 (en) * 2009-07-24 2011-01-27 Sfs Structures Ltd. Shoring free excavation and basement construction apparatus and method
EP3521514A1 (en) * 2018-02-05 2019-08-07 PPZS s.r.o. Permanent prefabricated braced wall

Similar Documents

Publication Publication Date Title
US7500807B2 (en) Method of construction using sheet piling sections
EP3521514B1 (en) Permanent prefabricated braced wall
JPS5944431A (en) Construction of basement
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
JPS6158640B2 (en)
JPS5936058B2 (en) How to construct a structure using underground continuous walls
CN111206594A (en) Foundation pit supporting construction method
JPH0613770B2 (en) Method of constructing mountain retaining wall with parent pile
RU2753301C1 (en) Method for foundation construction under conditions of year-round negative temperatures
JPH09111754A (en) Soldier pile cut-of wall construction method
JPS6018769B2 (en) Construction method of underground structure
CN110593313B (en) Open excavation construction method for additionally arranging basement and underground communication channel under existing building
JPS59429A (en) Foundation structure and its construction for building on soft ground
TW418274B (en) A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall
JP2733542B2 (en) How to build underground structures
JPH0433326B2 (en)
JPS6024249B2 (en) How to build a basement
JPH0156215B2 (en)
JP2711748B2 (en) Construction method of large-scale underground space
JP2556415B2 (en) Construction method of self-supporting retaining wall
JP3441266B2 (en) Underground space construction method
JPS6145021B2 (en)
JPS62211418A (en) Construction of continuous wall
JPH093927A (en) Basement construction method and basement structure
JPS58222219A (en) Construction of basement for housing