EP3633141A1 - Construction method for inner structure of single-bore double-track composite lining shield tunnel - Google Patents

Construction method for inner structure of single-bore double-track composite lining shield tunnel Download PDF

Info

Publication number
EP3633141A1
EP3633141A1 EP18806523.9A EP18806523A EP3633141A1 EP 3633141 A1 EP3633141 A1 EP 3633141A1 EP 18806523 A EP18806523 A EP 18806523A EP 3633141 A1 EP3633141 A1 EP 3633141A1
Authority
EP
European Patent Office
Prior art keywords
construction
lining
composite lining
tunnel
mid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP18806523.9A
Other languages
German (de)
French (fr)
Other versions
EP3633141A4 (en
EP3633141B1 (en
Inventor
Jian Chen
Chengzhen WAGN
Zhe Zhang
Guodong Zhao
Defu Wang
Hao Hu
Haizhen Li
Xutao SUN
Yinbin YAO
Hao Wang
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Publication of EP3633141A1 publication Critical patent/EP3633141A1/en
Publication of EP3633141A4 publication Critical patent/EP3633141A4/en
Application granted granted Critical
Publication of EP3633141B1 publication Critical patent/EP3633141B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Definitions

  • the present invention relates to the field of shield tunnel construction, and provides a construction method for an inner structure of a single-bore double-track composite lining shield tunnel.
  • the present invention is mainly intended to provide a construction method for an inner structure of a single-bore double-track composite lining shield tunnel, which can conduct composite lining on the inner structure of the tunnel synchronously during tunnel boring and thus effectively improves the efficiency.
  • a construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
  • the technical solutions of the present invention further include: the composite lining construction includes the following main steps.
  • the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component is conveyed to a shield tunneling machine frame, the prefabricated box culvert component is installed synchronously in shield boring, and upon the completion of installation, concrete filling is conducted in spaces at two sides of the prefabricated box culvert component.
  • the technical solutions of the present invention further include: the prefabricated box culvert component is a hollow square shaped box culvert, and the prefabricated box culvert component is installed on an inner lower portion of an annular pipe spliced by prefabricated segments.
  • the technical solutions of the present invention further include: the step 2) of the composite lining construction includes the following steps: the two-lining bottom arch wall is cast by using an manual erecting framework, and a casting space for the bottom arch wall is reserved in advance.
  • the technical solutions of the present invention further include: the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, a connector is pre-buried in each prefabricated segment, the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a part of reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments on the top.
  • the technical solutions of the present invention further include: the mid-partition construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition, and then a mobile trolley is used to cast wall concrete of the mid-partition from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition.
  • the technical solutions of the present invention further include: a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, and the concrete is poured into the mid-partition via the casting hole.
  • the second step includes the following main steps.
  • the technical solutions of the present invention further include: an artificial intelligence steel pipe support and a wood surface membrane cooperative structure is adopted by the evacuation platform.
  • a front section, a middle section and a rear section of the tunnel take a direction in which the shield tunneling machine bores as a front direction.
  • the present invention has the following advantages: according to the construction method for the inner structure of the single-bore double-track composite lining shield tunnel provided by the invention, with the adoption of the construction method, the construction of the inner lining structure is conducted on the middle section and/or the rear section of the tunnel synchronously during shield tunnel boring, and thus the construction efficiency is improved; moreover, the order of first lining and then splitting from bottom to top is generally adopted in the composite lining construction, and thus, the stability of the interior of the tunnel can be guaranteed, and smooth passing in a construction space is also guaranteed.
  • the construction method provided by the present invention has good practicability.
  • a construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
  • Embodiment 1 the composite lining construction includes the following main steps.
  • Embodiment 2 the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component 2 is conveyed to a shield tunneling machine frame, the prefabricated box culvert component 2 is installed synchronously in shield boring, and upon the completion of installation, concrete filling 3 is conducted in spaces at two sides of the prefabricated box culvert component 2.
  • the prefabricated box culvert component 2 is a hollow square shaped box culvert, and the prefabricated box culvert component 2 is installed on an inner lower portion of an annular pipe spliced by prefabricated segments 1.
  • the spliced installation of the prefabricated segments 1 is conducted synchronously during shield boring.
  • Embodiment 3 in view of the influence from pipelines at two sides, in the process when a shield tunneling machine is manufactured and pipelines are paved, an enough bottom arch wall casting space is reserved in advance; the two-lining bottom arch wall 4 is cast by using an manual erecting framework, a splicing template is a small arc sizing template, and its size is subject to the design condition of the tunnel, and that the template can be carried by an site operator, and should not be excessively large.
  • Embodiment 4 the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, and the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond; a connector is pre-buried in each prefabricated segment 1, the construction is conducted by the multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments 1 on the top.
  • the flue sheet and the lining arch wall below the flue sheet are cast by adopting a template trolley.
  • Embodiment 5 in the step 4) of the composite lining construction, when the arch top lining is cast in place, the arch top lining 6 is constructed after the concrete of the flue sheet is up to a design strength; and a lower trolley may also be used during strength period of the flue sheet as a support for an upper arched top in construction to perform concrete construction of the arch top. After the trolley moves and is positioned accurately, the concrete casting is implemented. A concrete delivery pump is adopted by the casting to supply the concrete at the front single side of the template trolley; the concrete is delivered from the top of the flue sheet. For concrete vibration of the side arc lining, an attached flat-plate vibrator is installed by using a rib portion of a trolley panel to vibrate artificially in combination with a vibration rod.
  • Embodiment 6 the mid-partition 7 construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition 7 construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition 7, and then a mobile trolley is used to cast wall concrete of the mid-partition 7 from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition 7.
  • a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, the concrete is poured into the mid-partition via the casting hole, and the casting hole is also served as a vibration hole.
  • Embodiment 7 the second step includes the following main steps.
  • the mid-partition of the linear section is constructed first, and after the tunnel is passed through, the curved section is constructed.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to the field of shield tunnel construction, and provides a construction method for an inner structure of a single-bore double-track composite lining shield tunnel. The method mainly include: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through. With the adoption of the construction method, the construction of the inner lining structure is conducted on the middle section and/or the rear section of the tunnel synchronously during shield tunnel boring, and thus the construction efficiency is improved; moreover, the order of first lining and then splitting from bottom to top is generally adopted in the composite lining construction, and thus, the stability of the interior of the tunnel can be guaranteed, and smooth passing in a construction space is also guaranteed. The construction method provided by the present invention has good practicability.

Description

    Technical Field
  • The present invention relates to the field of shield tunnel construction, and provides a construction method for an inner structure of a single-bore double-track composite lining shield tunnel.
  • Background
  • At present, the metro construction is upsurging in China. A great number of shield tunnels passing through complex areas and having long distances and large diameters are under construction or are to be constructed. During construction, each shield tunnel is faced with many technical problems such as complex geological condition, long construction period and large risk. Moreover, while the functional requirement on urban underground tunnel engineering is increased continuously, a composite lining structure is emerging in an urban metric shield tunnel under the requirements of fire protection, collision avoidance, explosion protection and durability. A shield tunnel of a single-bore double-track composite lining structure cannot meet the synchronous construction completely and are difficult to guarantee the construction efficiency and quality.
  • Summary
  • The present invention is mainly intended to provide a construction method for an inner structure of a single-bore double-track composite lining shield tunnel, which can conduct composite lining on the inner structure of the tunnel synchronously during tunnel boring and thus effectively improves the efficiency.
  • The technical solutions of the present invention are as follows: a construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
  • The technical solutions of the present invention further include: the composite lining construction includes the following main steps.
    1. 1) A prefabricated box culvert component is installed.
    2. 2) A two-lining bottom arch wall is cast in place.
    3. 3) A flue sheet and a lining arch wall below the flue sheet are cast in place.
    4. 4) An arch top lining is cast in place.
    5. 5) A mid-partition is constructed.
  • The technical solutions of the present invention further include: the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component is conveyed to a shield tunneling machine frame, the prefabricated box culvert component is installed synchronously in shield boring, and upon the completion of installation, concrete filling is conducted in spaces at two sides of the prefabricated box culvert component.
  • The technical solutions of the present invention further include: the prefabricated box culvert component is a hollow square shaped box culvert, and the prefabricated box culvert component is installed on an inner lower portion of an annular pipe spliced by prefabricated segments.
  • The technical solutions of the present invention further include: the step 2) of the composite lining construction includes the following steps: the two-lining bottom arch wall is cast by using an manual erecting framework, and a casting space for the bottom arch wall is reserved in advance.
  • The technical solutions of the present invention further include: the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, a connector is pre-buried in each prefabricated segment, the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a part of reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments on the top.
  • The technical solutions of the present invention further include: the mid-partition construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition, and then a mobile trolley is used to cast wall concrete of the mid-partition from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition.
  • The technical solutions of the present invention further include: a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, and the concrete is poured into the mid-partition via the casting hole.
  • The technical solutions of the present invention further include: the second step includes the following main steps.
    1. 1) A mid-partition of a curved section is cast.
    2. 2) An evacuation platform is constructed.
    3. 3) A road leveling layer is constructed.
  • The technical solutions of the present invention further include: an artificial intelligence steel pipe support and a wood surface membrane cooperative structure is adopted by the evacuation platform.
  • It is to be noted that a front section, a middle section and a rear section of the tunnel take a direction in which the shield tunneling machine bores as a front direction.
  • The present invention has the following advantages: according to the construction method for the inner structure of the single-bore double-track composite lining shield tunnel provided by the invention, with the adoption of the construction method, the construction of the inner lining structure is conducted on the middle section and/or the rear section of the tunnel synchronously during shield tunnel boring, and thus the construction efficiency is improved; moreover, the order of first lining and then splitting from bottom to top is generally adopted in the composite lining construction, and thus, the stability of the interior of the tunnel can be guaranteed, and smooth passing in a construction space is also guaranteed. The construction method provided by the present invention has good practicability.
  • Brief Description of the Drawings
  • The accompanying drawings are described here to provide further understanding of the present invention, and form a part of the present invention. The schematic embodiments and description of the present invention are adopted to explain the present invention, and do not form improper limits to the present invention. In the drawings:
    • Fig. 1 is a cross-sectional effect diagram of a shield tunnel by adopting a construction method of the present invention.
    • Fig. 2 is a process flowchart of a construction method of the present invention.
    • Fig. 3 is a schematic diagram of installation of a prefabricated box culvert component of the present invention.
    • Fig. 4 is a schematic diagram of cast-in-place construction of a two-lining bottom arch wall.
    • Fig. 5 is a schematic diagram of a reinforcing steel bar trolley of a flue sheet.
    • Fig. 6 is a schematic diagram of an arch top two-lining reinforcing steel bar trolley.
    • Fig. 7 is a schematic diagram of construction of a flue sheet and a lining arch wall below.
    • Fig. 8 is a schematic diagram of cast-in-place construction of an arch top lining.
    • Fig. 9 is a schematic diagram of a cast-in-place mid-partition.
    • Fig. 10 is a vertical section view of construction of an inner structure.
    • Fig. 11 is a sectional flowchart of construction of an inner structure.
  • In the drawings, 1. prefabricated segment; 2. prefabricated box culvert component; 3. concrete filling; 4. bottom arch wall; 5. flue sheet and lining arch wall below; 6. arch top lining; 7. mid-partition; 8. evacuation platform
  • Detailed Description of the Embodiments
  • The present invention is further described below in combination with Fig. 1 to Fig. 11 and embodiments.
  • Moreover, the followings are merely a part of embodiments; and the embodiments in the present invention and the features in the embodiments may be combined with each other if there is no conflict.
  • A construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
  • Embodiment 1: the composite lining construction includes the following main steps.
    1. 1) A prefabricated box culvert component 2 is installed.
    2. 2) A two-lining bottom arch wall 4 is cast in place.
    3. 3) A flue sheet and a lining arch wall 5 below the flue sheet are cast in place.
    4. 4) An arch top lining 6 is cast in place.
    5. 5) A mid-partition 7 is constructed.
  • Embodiment 2: the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component 2 is conveyed to a shield tunneling machine frame, the prefabricated box culvert component 2 is installed synchronously in shield boring, and upon the completion of installation, concrete filling 3 is conducted in spaces at two sides of the prefabricated box culvert component 2.
  • The prefabricated box culvert component 2 is a hollow square shaped box culvert, and the prefabricated box culvert component 2 is installed on an inner lower portion of an annular pipe spliced by prefabricated segments 1. The spliced installation of the prefabricated segments 1 is conducted synchronously during shield boring.
  • Embodiment 3: in view of the influence from pipelines at two sides, in the process when a shield tunneling machine is manufactured and pipelines are paved, an enough bottom arch wall casting space is reserved in advance; the two-lining bottom arch wall 4 is cast by using an manual erecting framework, a splicing template is a small arc sizing template, and its size is subject to the design condition of the tunnel, and that the template can be carried by an site operator, and should not be excessively large.
  • Embodiment 4: the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, and the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond; a connector is pre-buried in each prefabricated segment 1, the construction is conducted by the multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments 1 on the top. The flue sheet and the lining arch wall below the flue sheet are cast by adopting a template trolley.
  • Embodiment 5: in the step 4) of the composite lining construction, when the arch top lining is cast in place, the arch top lining 6 is constructed after the concrete of the flue sheet is up to a design strength; and a lower trolley may also be used during strength period of the flue sheet as a support for an upper arched top in construction to perform concrete construction of the arch top. After the trolley moves and is positioned accurately, the concrete casting is implemented. A concrete delivery pump is adopted by the casting to supply the concrete at the front single side of the template trolley; the concrete is delivered from the top of the flue sheet. For concrete vibration of the side arc lining, an attached flat-plate vibrator is installed by using a rib portion of a trolley panel to vibrate artificially in combination with a vibration rod.
  • Embodiment 6: the mid-partition 7 construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition 7 construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition 7, and then a mobile trolley is used to cast wall concrete of the mid-partition 7 from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition 7.
  • A construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, the concrete is poured into the mid-partition via the casting hole, and the casting hole is also served as a vibration hole.
  • Embodiment 7: the second step includes the following main steps.
    1. 1) A mid-partition 7 of a curved section is cast.
    2. 2) An evacuation platform 8 is constructed, an artificial intelligence steel pipe support and wood surface membrane cooperative structure being adopted by the evacuation platform 8.
    3. 3) A road leveling layer is constructed.
  • Since the space in the tunnel is limited, the mid-partition of the linear section is constructed first, and after the tunnel is passed through, the curved section is constructed.
  • The above are preferred embodiments of the present invention and are not intended to limit the preset invention in any form. Any modifications, equivalent replacements, improvements and the like made within the spirit and principle of the present invention should be included in a protection scope of the present invention.

Claims (10)

  1. A construction method for an inner structure of a single-bore double-track composite lining shield tunnel, mainly comprising: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
  2. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 1, wherein the composite lining construction mainly comprising:
    1) installing prefabricated box culvert component (2);
    2) casting a two-lining bottom arch wall (4) in place;
    3) casting flue sheet and a lining arch wall (5) below the flue sheet in place;
    4) casting an arch top lining (6) in place; and
    5) constructing a mid-partition (7).
  3. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein the step 1) of the composite lining construction comprising: conveying the prefabricated box culvert component (2) to a shield tunneling machine frame, installing the prefabricated box culvert component (2) synchronously in shield boring, and upon the completion of installation, conducting concrete filling in spaces at two sides of the prefabricated box culvert component (2).
  4. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 3, wherein the prefabricated box culvert component (2) is a hollow square shaped box culvert, and the prefabricated box culvert component (2) is installed on an inner lower portion of an annular pipe spliced by prefabricated segments (1).
  5. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein in the step 2) of the composite lining construction, the two-lining bottom arch wall is cast by using an manual erecting framework, and a casting space for the bottom arch wall (4) is reserved in advance.
  6. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein the step 3) of the composite lining construction comprises: binding reinforcing steel bars and casting the flue sheet and the lining arch wall (5) below the flue sheet in place, pre-burying a connector in each prefabricated segment (1), conducting the construction by multiple groups of trolleys synchronously when the reinforcing steel bars are bond, fixing arch ring reinforcing steel bars mechanically on the connector, and suspending a part of reinforcing steel bar skeleton on the flue sheet in the prefabricated segments (1) on the top.
  7. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein the mid-partition (7) construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition (7) construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition (7), and then a mobile trolley is used to cast wall concrete of the mid-partition (7) from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition (7).
  8. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 7, wherein a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, and the concrete is poured into the mid-partition via the casting hole.
  9. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in any one of claims 1 to 8, wherein the second step comprises the following main steps:
    1) casting a mid-partition of a curved section;
    2) constructing an evacuation platform; and
    3) constructing a road leveling layer.
  10. The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 9, wherein an artificial intelligence steel pipe support and a wood surface membrane cooperative structure is adopted by the evacuation platform.
EP18806523.9A 2017-05-25 2018-05-10 Construction method for inner structure of single-bore double-track composite lining shield tunnel Active EP3633141B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710381186.3A CN107435544A (en) 2017-05-25 2017-05-25 A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure
PCT/CN2018/086275 WO2018214737A1 (en) 2017-05-25 2018-05-10 Construction method for inner structure of single-bore double-track composite lining shield tunnel

Publications (3)

Publication Number Publication Date
EP3633141A1 true EP3633141A1 (en) 2020-04-08
EP3633141A4 EP3633141A4 (en) 2021-03-24
EP3633141B1 EP3633141B1 (en) 2024-01-10

Family

ID=60458589

Family Applications (1)

Application Number Title Priority Date Filing Date
EP18806523.9A Active EP3633141B1 (en) 2017-05-25 2018-05-10 Construction method for inner structure of single-bore double-track composite lining shield tunnel

Country Status (3)

Country Link
EP (1) EP3633141B1 (en)
CN (1) CN107435544A (en)
WO (1) WO2018214737A1 (en)

Families Citing this family (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435544A (en) * 2017-05-25 2017-12-05 中铁十四局集团有限公司 A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure
CN107916936A (en) * 2017-12-20 2018-04-17 北京市政建设集团有限责任公司 A kind of major diameter one-tunnel two-tracks subway tunnel and its construction method
CN108756929A (en) * 2018-05-07 2018-11-06 中铁工程设计咨询集团有限公司 Precast construction under a kind of Railway Tunnel separate type rail
CN109653768A (en) * 2018-12-29 2019-04-19 北京城建信捷轨道交通工程咨询有限公司 Adjustable support, shield duct piece and adjusting method for shield duct piece inner wall
CN109519195A (en) * 2018-12-30 2019-03-26 中铁十四局集团有限公司 Prefabricated rail flowering structure
CN109707395B (en) * 2019-01-17 2024-01-16 中铁第四勘察设计院集团有限公司 Double-layer shield tunnel with upper and lower layer discharge flues and discharge flue setting method
CN110410108A (en) * 2019-08-02 2019-11-05 中建四局贵州投资建设有限公司 A kind of tunnel cable groove construction device and construction method
CN110410103A (en) * 2019-09-03 2019-11-05 中铁十四局集团大盾构工程有限公司 A kind of novel filleting trolley
CN110486039B (en) * 2019-09-26 2024-05-07 西南交通大学 Multipurpose shield tunnel lining structure
CN110700851B (en) * 2019-10-14 2024-07-09 中铁第四勘察设计院集团有限公司 Single-hole double-line jet fan tunnel section designed based on urban D-type vehicle limit
CN110714778B (en) * 2019-10-14 2024-07-09 中铁第四勘察设计院集团有限公司 Mine tunnel section without intermediate wall for city D-type vehicle limit design single-hole double-line
CN110714779A (en) * 2019-10-14 2020-01-21 中铁第四勘察设计院集团有限公司 Shield tunnel section structure based on urban D type vehicle clearance design
CN110700852A (en) * 2019-10-14 2020-01-17 中铁第四勘察设计院集团有限公司 Single-hole double-line mine method tunnel section with mid-partition wall designed by urban D-type vehicle clearance
CN110847946A (en) * 2019-12-24 2020-02-28 山西省交通科技研发有限公司 Mounting bracket and mounting method for jet fan of long and large highway tunnel
CN112127942A (en) * 2020-08-24 2020-12-25 中铁第四勘察设计院集团有限公司 Connection structure of evacuation platform in shield zone at interconnection channel
CN112324467A (en) * 2020-12-08 2021-02-05 中铁第四勘察设计院集团有限公司 Model of shield tunnel cast-in-place internal structure and test manufacturing method thereof
CN112727482B (en) * 2021-02-05 2022-08-30 中铁工程装备集团有限公司 Large-diameter shield tunnel and complete equipment and method for construction of internal prefabricated structure of large-diameter shield tunnel
CN113153370A (en) * 2021-04-26 2021-07-23 中交二公局东萌工程有限公司 Tunnel TBM stepping precast concrete component and construction method
CN113153357B (en) * 2021-04-29 2024-06-28 重庆大学 Tunnel inverted arch half-width dismantling device and construction method
CN113356882B (en) * 2021-05-21 2023-06-20 中铁十九局集团第五工程有限公司 Large-section tunnel wall bracket and construction method
CN113323718A (en) * 2021-05-24 2021-08-31 中铁第四勘察设计院集团有限公司 Open type evacuation platform for normal-temperature normally-conductive magnetic suspension tunnel
CN113279771A (en) * 2021-06-22 2021-08-20 中建交通建设集团有限公司 Prevent prefabricated assembled structure of shield tunnel section of jurisdiction come-up under water
CN113586086B (en) * 2021-07-12 2024-02-20 山西工程技术学院 Method for reinforcing weak broken bottom plate of semi-closed large-section roadway
CN113417671B (en) * 2021-08-06 2024-07-09 中交(广州)建设有限公司 Construction method for rapid assembly of prefabricated components in shield tunnel
CN113503176B (en) * 2021-08-06 2024-07-02 中交(广州)建设有限公司 Intelligent integrated assembling trolley for prefabricated parts in tunnel
CN113622956B (en) * 2021-08-31 2022-12-06 中铁十八局集团有限公司 Construction method for high-speed railway double-track tunnel to penetrate through vertical mud gushing karst cave
CN113863949B (en) * 2021-09-13 2023-05-16 中铁十九局集团第五工程有限公司 Pool construction method for existing cavern
CN113803088B (en) * 2021-09-27 2024-05-10 中铁一局集团有限公司 Isolated double-lining shield tunnel construction structure and construction method
CN114017062B (en) * 2021-11-03 2023-11-14 北京城建设计发展集团股份有限公司 Method for monitoring cable to pass through secondary lining of large-diameter shield tunnel segment
CN114278341B (en) * 2022-02-16 2024-02-27 中铁一局集团有限公司 Two-lining template construction structure and method based on mine tunnel special-shaped section
CN114808776A (en) * 2022-04-18 2022-07-29 中交一公局集团有限公司 Prefabricated installation construction method for prefabricated box culvert pipe
CN114753861A (en) * 2022-05-17 2022-07-15 中铁第一勘察设计院集团有限公司 Drilling and blasting method double-line tunnel prefabricated lining structure and construction method thereof
CN115418983B (en) * 2022-09-27 2023-07-28 中铁十四局集团有限公司 Construction method for prefabricated box culvert in highway-railway co-construction large-section shield tunnel
CN115949427B (en) * 2023-03-08 2023-05-16 中铁第六勘察设计院集团有限公司 Double-switching shield lining structure for subway wiring section and assembling method thereof

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003206693A (en) * 2002-01-08 2003-07-25 Taisei Corp Lining method of shield tunnel
CN102061926A (en) * 2009-11-11 2011-05-18 中铁十八局集团有限公司 TBM tunneling and secondary lining synchronous construction method at mucking of continuous belt conveyor and trolley
CN102003207B (en) * 2010-12-31 2012-08-29 上海市隧道工程轨道交通设计研究院 Escape platform and security channel structure for single-hole dual-line magnetic suspension tunnel
CN202417530U (en) * 2012-01-17 2012-09-05 张新泉 Bottom-positioned traversing synchronous tunnel lining trolley for continuous conveyor construction of tunnel
CN203308471U (en) * 2012-11-20 2013-11-27 中铁十八局集团有限公司 Open type TBM cast-in-place concrete inverted arch synchronous lining trolley
CN103195440A (en) * 2013-04-03 2013-07-10 中铁隧道勘测设计院有限公司 Three-layer-structure subway double-line single-pipe circular tunnel
CN203847130U (en) * 2013-12-27 2014-09-24 中铁十八局集团有限公司 Cast-in-situ inverted arch lining trolley and concrete curing system capable of being synchronously constructed along with boring of TMB (tunnel boring machine)
CN104612711B (en) * 2015-02-09 2017-04-19 浙江省交通规划设计研究院 Lining segment structure of city subway up-down section overlapping shield tunnels
CN104747200B (en) * 2015-03-18 2017-03-01 中铁工程装备集团有限公司 Construction method with double-deck supporting and the hard rock mole of variable section of jurisdiction diameter
CN107435544A (en) * 2017-05-25 2017-12-05 中铁十四局集团有限公司 A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure
CN107916936A (en) * 2017-12-20 2018-04-17 北京市政建设集团有限责任公司 A kind of major diameter one-tunnel two-tracks subway tunnel and its construction method

Also Published As

Publication number Publication date
EP3633141A4 (en) 2021-03-24
WO2018214737A1 (en) 2018-11-29
CN107435544A (en) 2017-12-05
EP3633141B1 (en) 2024-01-10

Similar Documents

Publication Publication Date Title
EP3633141A1 (en) Construction method for inner structure of single-bore double-track composite lining shield tunnel
CN103016029B (en) Grouped second liner construction method for large cross-section tunnel
CN103075163B (en) Support change process of second liner construction of large-cross-section tunnel
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN102505708B (en) Construction method of tunnel at oversized cross section open cut area in track traffic
CN109505609B (en) Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack
CN103470272A (en) Trolley for concrete construction on multiple sections by employing mining method and construction method thereof
CN103939113A (en) Suspension rail type construction trolley
CN203499697U (en) Trolley used for concrete construction of various cross sections through mining method
CN105256836A (en) Construction method for fast restoring road traffic in construction of underground project
KR20100100193A (en) Form system for constructing rc-girder in rc top down method and the rc top down method using the same
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
KR101427812B1 (en) Open cut method for constructing an underground structure
CN110056362B (en) Shield receiving and lateral translation hoisting method in air duct of underground excavation station
CN106760486A (en) Exterior wall mould and its erection method in foundation ditch
KR20160004710A (en) Joint apparatus of upper and bottom precast segment for precast box culvert, and construction method for the same
CN116378711A (en) Shallow-buried underground excavation tunnel separated trolley device and construction method
CN103075164B (en) Double-hole and two-liner sequential isochronous propelling construction process
CN104746434A (en) Closure segment formwork system without dismantling outer formwork
KR20190066754A (en) Formwork structure supported by column unit
CN208749354U (en) Shallow buried covered excavation Urban Underground pipe gallery
CN109695347A (en) The construction techniques of curved device is held based on round steel
CN110030000B (en) One-step-distance one-turn construction method for small-section tunnel
CN219012636U (en) Shallow underground tunnel disconnect-type platform truck device that buries
CN106193112A (en) Tunnel side ditch xoncrete structure one-shot forming system and using method thereof

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20191220

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
A4 Supplementary search report drawn up and despatched

Effective date: 20210224

RIC1 Information provided on ipc code assigned before grant

Ipc: E21D 11/10 20060101ALI20210218BHEP

Ipc: E21D 11/08 20060101AFI20210218BHEP

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20221004

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20230720

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602018064039

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20240201

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20240110

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 1649044

Country of ref document: AT

Kind code of ref document: T

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240510

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20240517

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240411

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240410

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240410

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240410

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240510

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240411

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240510

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240510

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240110