EP3633141A1 - Construction method for inner structure of single-bore double-track composite lining shield tunnel - Google Patents
Construction method for inner structure of single-bore double-track composite lining shield tunnel Download PDFInfo
- Publication number
- EP3633141A1 EP3633141A1 EP18806523.9A EP18806523A EP3633141A1 EP 3633141 A1 EP3633141 A1 EP 3633141A1 EP 18806523 A EP18806523 A EP 18806523A EP 3633141 A1 EP3633141 A1 EP 3633141A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- construction
- lining
- composite lining
- tunnel
- mid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 92
- 239000002131 composite material Substances 0.000 title claims abstract description 45
- 238000005192 partition Methods 0.000 claims description 30
- 238000005266 casting Methods 0.000 claims description 17
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 15
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 5
- 230000005641 tunneling Effects 0.000 claims description 5
- 238000004513 sizing Methods 0.000 claims description 4
- 238000013473 artificial intelligence Methods 0.000 claims description 3
- 239000012528 membrane Substances 0.000 claims description 3
- 238000005086 pumping Methods 0.000 claims description 3
- 239000000758 substrate Substances 0.000 claims description 3
- 239000002023 wood Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 8
- 230000000694 effects Effects 0.000 description 1
- 238000004880 explosion Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/107—Reinforcing elements therefor; Holders for the reinforcing elements
Definitions
- the present invention relates to the field of shield tunnel construction, and provides a construction method for an inner structure of a single-bore double-track composite lining shield tunnel.
- the present invention is mainly intended to provide a construction method for an inner structure of a single-bore double-track composite lining shield tunnel, which can conduct composite lining on the inner structure of the tunnel synchronously during tunnel boring and thus effectively improves the efficiency.
- a construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
- the technical solutions of the present invention further include: the composite lining construction includes the following main steps.
- the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component is conveyed to a shield tunneling machine frame, the prefabricated box culvert component is installed synchronously in shield boring, and upon the completion of installation, concrete filling is conducted in spaces at two sides of the prefabricated box culvert component.
- the technical solutions of the present invention further include: the prefabricated box culvert component is a hollow square shaped box culvert, and the prefabricated box culvert component is installed on an inner lower portion of an annular pipe spliced by prefabricated segments.
- the technical solutions of the present invention further include: the step 2) of the composite lining construction includes the following steps: the two-lining bottom arch wall is cast by using an manual erecting framework, and a casting space for the bottom arch wall is reserved in advance.
- the technical solutions of the present invention further include: the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, a connector is pre-buried in each prefabricated segment, the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a part of reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments on the top.
- the technical solutions of the present invention further include: the mid-partition construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition, and then a mobile trolley is used to cast wall concrete of the mid-partition from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition.
- the technical solutions of the present invention further include: a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, and the concrete is poured into the mid-partition via the casting hole.
- the second step includes the following main steps.
- the technical solutions of the present invention further include: an artificial intelligence steel pipe support and a wood surface membrane cooperative structure is adopted by the evacuation platform.
- a front section, a middle section and a rear section of the tunnel take a direction in which the shield tunneling machine bores as a front direction.
- the present invention has the following advantages: according to the construction method for the inner structure of the single-bore double-track composite lining shield tunnel provided by the invention, with the adoption of the construction method, the construction of the inner lining structure is conducted on the middle section and/or the rear section of the tunnel synchronously during shield tunnel boring, and thus the construction efficiency is improved; moreover, the order of first lining and then splitting from bottom to top is generally adopted in the composite lining construction, and thus, the stability of the interior of the tunnel can be guaranteed, and smooth passing in a construction space is also guaranteed.
- the construction method provided by the present invention has good practicability.
- a construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
- Embodiment 1 the composite lining construction includes the following main steps.
- Embodiment 2 the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component 2 is conveyed to a shield tunneling machine frame, the prefabricated box culvert component 2 is installed synchronously in shield boring, and upon the completion of installation, concrete filling 3 is conducted in spaces at two sides of the prefabricated box culvert component 2.
- the prefabricated box culvert component 2 is a hollow square shaped box culvert, and the prefabricated box culvert component 2 is installed on an inner lower portion of an annular pipe spliced by prefabricated segments 1.
- the spliced installation of the prefabricated segments 1 is conducted synchronously during shield boring.
- Embodiment 3 in view of the influence from pipelines at two sides, in the process when a shield tunneling machine is manufactured and pipelines are paved, an enough bottom arch wall casting space is reserved in advance; the two-lining bottom arch wall 4 is cast by using an manual erecting framework, a splicing template is a small arc sizing template, and its size is subject to the design condition of the tunnel, and that the template can be carried by an site operator, and should not be excessively large.
- Embodiment 4 the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, and the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond; a connector is pre-buried in each prefabricated segment 1, the construction is conducted by the multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments 1 on the top.
- the flue sheet and the lining arch wall below the flue sheet are cast by adopting a template trolley.
- Embodiment 5 in the step 4) of the composite lining construction, when the arch top lining is cast in place, the arch top lining 6 is constructed after the concrete of the flue sheet is up to a design strength; and a lower trolley may also be used during strength period of the flue sheet as a support for an upper arched top in construction to perform concrete construction of the arch top. After the trolley moves and is positioned accurately, the concrete casting is implemented. A concrete delivery pump is adopted by the casting to supply the concrete at the front single side of the template trolley; the concrete is delivered from the top of the flue sheet. For concrete vibration of the side arc lining, an attached flat-plate vibrator is installed by using a rib portion of a trolley panel to vibrate artificially in combination with a vibration rod.
- Embodiment 6 the mid-partition 7 construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition 7 construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition 7, and then a mobile trolley is used to cast wall concrete of the mid-partition 7 from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition 7.
- a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, the concrete is poured into the mid-partition via the casting hole, and the casting hole is also served as a vibration hole.
- Embodiment 7 the second step includes the following main steps.
- the mid-partition of the linear section is constructed first, and after the tunnel is passed through, the curved section is constructed.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
- The present invention relates to the field of shield tunnel construction, and provides a construction method for an inner structure of a single-bore double-track composite lining shield tunnel.
- At present, the metro construction is upsurging in China. A great number of shield tunnels passing through complex areas and having long distances and large diameters are under construction or are to be constructed. During construction, each shield tunnel is faced with many technical problems such as complex geological condition, long construction period and large risk. Moreover, while the functional requirement on urban underground tunnel engineering is increased continuously, a composite lining structure is emerging in an urban metric shield tunnel under the requirements of fire protection, collision avoidance, explosion protection and durability. A shield tunnel of a single-bore double-track composite lining structure cannot meet the synchronous construction completely and are difficult to guarantee the construction efficiency and quality.
- The present invention is mainly intended to provide a construction method for an inner structure of a single-bore double-track composite lining shield tunnel, which can conduct composite lining on the inner structure of the tunnel synchronously during tunnel boring and thus effectively improves the efficiency.
- The technical solutions of the present invention are as follows: a construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
- The technical solutions of the present invention further include: the composite lining construction includes the following main steps.
- 1) A prefabricated box culvert component is installed.
- 2) A two-lining bottom arch wall is cast in place.
- 3) A flue sheet and a lining arch wall below the flue sheet are cast in place.
- 4) An arch top lining is cast in place.
- 5) A mid-partition is constructed.
- The technical solutions of the present invention further include: the step 1) of the composite lining construction includes the following steps: the prefabricated box culvert component is conveyed to a shield tunneling machine frame, the prefabricated box culvert component is installed synchronously in shield boring, and upon the completion of installation, concrete filling is conducted in spaces at two sides of the prefabricated box culvert component.
- The technical solutions of the present invention further include: the prefabricated box culvert component is a hollow square shaped box culvert, and the prefabricated box culvert component is installed on an inner lower portion of an annular pipe spliced by prefabricated segments.
- The technical solutions of the present invention further include: the step 2) of the composite lining construction includes the following steps: the two-lining bottom arch wall is cast by using an manual erecting framework, and a casting space for the bottom arch wall is reserved in advance.
- The technical solutions of the present invention further include: the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, a connector is pre-buried in each prefabricated segment, the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a part of reinforcing steel bar skeleton on the flue sheet is suspended in the prefabricated segments on the top.
- The technical solutions of the present invention further include: the mid-partition construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition, and then a mobile trolley is used to cast wall concrete of the mid-partition from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition.
- The technical solutions of the present invention further include: a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, and the concrete is poured into the mid-partition via the casting hole.
- The technical solutions of the present invention further include: the second step includes the following main steps.
- 1) A mid-partition of a curved section is cast.
- 2) An evacuation platform is constructed.
- 3) A road leveling layer is constructed.
- The technical solutions of the present invention further include: an artificial intelligence steel pipe support and a wood surface membrane cooperative structure is adopted by the evacuation platform.
- It is to be noted that a front section, a middle section and a rear section of the tunnel take a direction in which the shield tunneling machine bores as a front direction.
- The present invention has the following advantages: according to the construction method for the inner structure of the single-bore double-track composite lining shield tunnel provided by the invention, with the adoption of the construction method, the construction of the inner lining structure is conducted on the middle section and/or the rear section of the tunnel synchronously during shield tunnel boring, and thus the construction efficiency is improved; moreover, the order of first lining and then splitting from bottom to top is generally adopted in the composite lining construction, and thus, the stability of the interior of the tunnel can be guaranteed, and smooth passing in a construction space is also guaranteed. The construction method provided by the present invention has good practicability.
- The accompanying drawings are described here to provide further understanding of the present invention, and form a part of the present invention. The schematic embodiments and description of the present invention are adopted to explain the present invention, and do not form improper limits to the present invention. In the drawings:
-
Fig. 1 is a cross-sectional effect diagram of a shield tunnel by adopting a construction method of the present invention. -
Fig. 2 is a process flowchart of a construction method of the present invention. -
Fig. 3 is a schematic diagram of installation of a prefabricated box culvert component of the present invention. -
Fig. 4 is a schematic diagram of cast-in-place construction of a two-lining bottom arch wall. -
Fig. 5 is a schematic diagram of a reinforcing steel bar trolley of a flue sheet. -
Fig. 6 is a schematic diagram of an arch top two-lining reinforcing steel bar trolley. -
Fig. 7 is a schematic diagram of construction of a flue sheet and a lining arch wall below. -
Fig. 8 is a schematic diagram of cast-in-place construction of an arch top lining. -
Fig. 9 is a schematic diagram of a cast-in-place mid-partition. -
Fig. 10 is a vertical section view of construction of an inner structure. -
Fig. 11 is a sectional flowchart of construction of an inner structure. - In the drawings, 1. prefabricated segment; 2. prefabricated box culvert component; 3. concrete filling; 4. bottom arch wall; 5. flue sheet and lining arch wall below; 6. arch top lining; 7. mid-partition; 8. evacuation platform
- The present invention is further described below in combination with
Fig. 1 to Fig. 11 and embodiments. - Moreover, the followings are merely a part of embodiments; and the embodiments in the present invention and the features in the embodiments may be combined with each other if there is no conflict.
- A construction method for an inner structure of a single-bore double-track composite lining shield tunnel mainly includes: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
- Embodiment 1: the composite lining construction includes the following main steps.
- 1) A prefabricated
box culvert component 2 is installed. - 2) A two-lining
bottom arch wall 4 is cast in place. - 3) A flue sheet and a
lining arch wall 5 below the flue sheet are cast in place. - 4) An arch top lining 6 is cast in place.
- 5) A mid-partition 7 is constructed.
- Embodiment 2: the step 1) of the composite lining construction includes the following steps: the prefabricated
box culvert component 2 is conveyed to a shield tunneling machine frame, the prefabricatedbox culvert component 2 is installed synchronously in shield boring, and upon the completion of installation, concrete filling 3 is conducted in spaces at two sides of the prefabricatedbox culvert component 2. - The prefabricated
box culvert component 2 is a hollow square shaped box culvert, and the prefabricatedbox culvert component 2 is installed on an inner lower portion of an annular pipe spliced byprefabricated segments 1. The spliced installation of theprefabricated segments 1 is conducted synchronously during shield boring. - Embodiment 3: in view of the influence from pipelines at two sides, in the process when a shield tunneling machine is manufactured and pipelines are paved, an enough bottom arch wall casting space is reserved in advance; the two-lining bottom
arch wall 4 is cast by using an manual erecting framework, a splicing template is a small arc sizing template, and its size is subject to the design condition of the tunnel, and that the template can be carried by an site operator, and should not be excessively large. - Embodiment 4: the step 3) of the composite lining construction includes the following steps: reinforcing steel bars are bond and the flue sheet and the lining arch wall below the flue sheet are cast in place, and the construction is conducted by multiple groups of trolleys synchronously when the reinforcing steel bars are bond; a connector is pre-buried in each
prefabricated segment 1, the construction is conducted by the multiple groups of trolleys synchronously when the reinforcing steel bars are bond, arch ring reinforcing steel bars are mechanically fixed on the connector, and a reinforcing steel bar skeleton on the flue sheet is suspended in theprefabricated segments 1 on the top. The flue sheet and the lining arch wall below the flue sheet are cast by adopting a template trolley. - Embodiment 5: in the step 4) of the composite lining construction, when the arch top lining is cast in place, the arch top lining 6 is constructed after the concrete of the flue sheet is up to a design strength; and a lower trolley may also be used during strength period of the flue sheet as a support for an upper arched top in construction to perform concrete construction of the arch top. After the trolley moves and is positioned accurately, the concrete casting is implemented. A concrete delivery pump is adopted by the casting to supply the concrete at the front single side of the template trolley; the concrete is delivered from the top of the flue sheet. For concrete vibration of the side arc lining, an attached flat-plate vibrator is installed by using a rib portion of a trolley panel to vibrate artificially in combination with a vibration rod.
- Embodiment 6: the
mid-partition 7 construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during themid-partition 7 construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of themid-partition 7, and then a mobile trolley is used to cast wall concrete of themid-partition 7 from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of themid-partition 7. - A construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, the concrete is poured into the mid-partition via the casting hole, and the casting hole is also served as a vibration hole.
- Embodiment 7: the second step includes the following main steps.
- 1) A
mid-partition 7 of a curved section is cast. - 2) An evacuation platform 8 is constructed, an artificial intelligence steel pipe support and wood surface membrane cooperative structure being adopted by the evacuation platform 8.
- 3) A road leveling layer is constructed.
- Since the space in the tunnel is limited, the mid-partition of the linear section is constructed first, and after the tunnel is passed through, the curved section is constructed.
- The above are preferred embodiments of the present invention and are not intended to limit the preset invention in any form. Any modifications, equivalent replacements, improvements and the like made within the spirit and principle of the present invention should be included in a protection scope of the present invention.
Claims (10)
- A construction method for an inner structure of a single-bore double-track composite lining shield tunnel, mainly comprising: a first stage and a second stage; in the first stage, composite lining construction is conducted on a middle section and/or a rear section of the tunnel synchronously during tunnel boring, and lining is conducted on the tunnel by adopting an order of first lining and then splitting from bottom to top in the composite lining construction; and the second stage is a construction stage after the tunnel is bored through.
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 1, wherein the composite lining construction mainly comprising:1) installing prefabricated box culvert component (2);2) casting a two-lining bottom arch wall (4) in place;3) casting flue sheet and a lining arch wall (5) below the flue sheet in place;4) casting an arch top lining (6) in place; and5) constructing a mid-partition (7).
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein the step 1) of the composite lining construction comprising: conveying the prefabricated box culvert component (2) to a shield tunneling machine frame, installing the prefabricated box culvert component (2) synchronously in shield boring, and upon the completion of installation, conducting concrete filling in spaces at two sides of the prefabricated box culvert component (2).
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 3, wherein the prefabricated box culvert component (2) is a hollow square shaped box culvert, and the prefabricated box culvert component (2) is installed on an inner lower portion of an annular pipe spliced by prefabricated segments (1).
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein in the step 2) of the composite lining construction, the two-lining bottom arch wall is cast by using an manual erecting framework, and a casting space for the bottom arch wall (4) is reserved in advance.
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein the step 3) of the composite lining construction comprises: binding reinforcing steel bars and casting the flue sheet and the lining arch wall (5) below the flue sheet in place, pre-burying a connector in each prefabricated segment (1), conducting the construction by multiple groups of trolleys synchronously when the reinforcing steel bars are bond, fixing arch ring reinforcing steel bars mechanically on the connector, and suspending a part of reinforcing steel bar skeleton on the flue sheet in the prefabricated segments (1) on the top.
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 2, wherein the mid-partition (7) construction in the step 5) of the composite lining construction is mid-partition construction on a linear section; and during the mid-partition (7) construction, a small steel sizing template is used first to construct a wall below an evacuation platform to serve as a substrate of the mid-partition (7), and then a mobile trolley is used to cast wall concrete of the mid-partition (7) from an upper portion of the flue sheet to a bottom portion of the flue sheet to serve as an upper portion of the mid-partition (7).
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 7, wherein a construction hole is reserved on the flue sheet, a concrete pumping pipe is connected to an area above the flue sheet via the construction hole, an air duct sheet is further provided in the flue sheet, a casting hole is reserved in the middle of the air duct sheet, and the concrete is poured into the mid-partition via the casting hole.
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in any one of claims 1 to 8, wherein the second step comprises the following main steps:1) casting a mid-partition of a curved section;2) constructing an evacuation platform; and3) constructing a road leveling layer.
- The construction method for the inner structure of the single-bore double-track composite lining shield tunnel as claimed in claim 9, wherein an artificial intelligence steel pipe support and a wood surface membrane cooperative structure is adopted by the evacuation platform.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710381186.3A CN107435544A (en) | 2017-05-25 | 2017-05-25 | A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure |
PCT/CN2018/086275 WO2018214737A1 (en) | 2017-05-25 | 2018-05-10 | Construction method for inner structure of single-bore double-track composite lining shield tunnel |
Publications (3)
Publication Number | Publication Date |
---|---|
EP3633141A1 true EP3633141A1 (en) | 2020-04-08 |
EP3633141A4 EP3633141A4 (en) | 2021-03-24 |
EP3633141B1 EP3633141B1 (en) | 2024-01-10 |
Family
ID=60458589
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP18806523.9A Active EP3633141B1 (en) | 2017-05-25 | 2018-05-10 | Construction method for inner structure of single-bore double-track composite lining shield tunnel |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP3633141B1 (en) |
CN (1) | CN107435544A (en) |
WO (1) | WO2018214737A1 (en) |
Families Citing this family (34)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107435544A (en) * | 2017-05-25 | 2017-12-05 | 中铁十四局集团有限公司 | A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure |
CN107916936A (en) * | 2017-12-20 | 2018-04-17 | 北京市政建设集团有限责任公司 | A kind of major diameter one-tunnel two-tracks subway tunnel and its construction method |
CN108756929A (en) * | 2018-05-07 | 2018-11-06 | 中铁工程设计咨询集团有限公司 | Precast construction under a kind of Railway Tunnel separate type rail |
CN109653768A (en) * | 2018-12-29 | 2019-04-19 | 北京城建信捷轨道交通工程咨询有限公司 | Adjustable support, shield duct piece and adjusting method for shield duct piece inner wall |
CN109519195A (en) * | 2018-12-30 | 2019-03-26 | 中铁十四局集团有限公司 | Prefabricated rail flowering structure |
CN109707395B (en) * | 2019-01-17 | 2024-01-16 | 中铁第四勘察设计院集团有限公司 | Double-layer shield tunnel with upper and lower layer discharge flues and discharge flue setting method |
CN110410108A (en) * | 2019-08-02 | 2019-11-05 | 中建四局贵州投资建设有限公司 | A kind of tunnel cable groove construction device and construction method |
CN110410103A (en) * | 2019-09-03 | 2019-11-05 | 中铁十四局集团大盾构工程有限公司 | A kind of novel filleting trolley |
CN110486039B (en) * | 2019-09-26 | 2024-05-07 | 西南交通大学 | Multipurpose shield tunnel lining structure |
CN110700851B (en) * | 2019-10-14 | 2024-07-09 | 中铁第四勘察设计院集团有限公司 | Single-hole double-line jet fan tunnel section designed based on urban D-type vehicle limit |
CN110714778B (en) * | 2019-10-14 | 2024-07-09 | 中铁第四勘察设计院集团有限公司 | Mine tunnel section without intermediate wall for city D-type vehicle limit design single-hole double-line |
CN110714779A (en) * | 2019-10-14 | 2020-01-21 | 中铁第四勘察设计院集团有限公司 | Shield tunnel section structure based on urban D type vehicle clearance design |
CN110700852A (en) * | 2019-10-14 | 2020-01-17 | 中铁第四勘察设计院集团有限公司 | Single-hole double-line mine method tunnel section with mid-partition wall designed by urban D-type vehicle clearance |
CN110847946A (en) * | 2019-12-24 | 2020-02-28 | 山西省交通科技研发有限公司 | Mounting bracket and mounting method for jet fan of long and large highway tunnel |
CN112127942A (en) * | 2020-08-24 | 2020-12-25 | 中铁第四勘察设计院集团有限公司 | Connection structure of evacuation platform in shield zone at interconnection channel |
CN112324467A (en) * | 2020-12-08 | 2021-02-05 | 中铁第四勘察设计院集团有限公司 | Model of shield tunnel cast-in-place internal structure and test manufacturing method thereof |
CN112727482B (en) * | 2021-02-05 | 2022-08-30 | 中铁工程装备集团有限公司 | Large-diameter shield tunnel and complete equipment and method for construction of internal prefabricated structure of large-diameter shield tunnel |
CN113153370A (en) * | 2021-04-26 | 2021-07-23 | 中交二公局东萌工程有限公司 | Tunnel TBM stepping precast concrete component and construction method |
CN113153357B (en) * | 2021-04-29 | 2024-06-28 | 重庆大学 | Tunnel inverted arch half-width dismantling device and construction method |
CN113356882B (en) * | 2021-05-21 | 2023-06-20 | 中铁十九局集团第五工程有限公司 | Large-section tunnel wall bracket and construction method |
CN113323718A (en) * | 2021-05-24 | 2021-08-31 | 中铁第四勘察设计院集团有限公司 | Open type evacuation platform for normal-temperature normally-conductive magnetic suspension tunnel |
CN113279771A (en) * | 2021-06-22 | 2021-08-20 | 中建交通建设集团有限公司 | Prevent prefabricated assembled structure of shield tunnel section of jurisdiction come-up under water |
CN113586086B (en) * | 2021-07-12 | 2024-02-20 | 山西工程技术学院 | Method for reinforcing weak broken bottom plate of semi-closed large-section roadway |
CN113417671B (en) * | 2021-08-06 | 2024-07-09 | 中交(广州)建设有限公司 | Construction method for rapid assembly of prefabricated components in shield tunnel |
CN113503176B (en) * | 2021-08-06 | 2024-07-02 | 中交(广州)建设有限公司 | Intelligent integrated assembling trolley for prefabricated parts in tunnel |
CN113622956B (en) * | 2021-08-31 | 2022-12-06 | 中铁十八局集团有限公司 | Construction method for high-speed railway double-track tunnel to penetrate through vertical mud gushing karst cave |
CN113863949B (en) * | 2021-09-13 | 2023-05-16 | 中铁十九局集团第五工程有限公司 | Pool construction method for existing cavern |
CN113803088B (en) * | 2021-09-27 | 2024-05-10 | 中铁一局集团有限公司 | Isolated double-lining shield tunnel construction structure and construction method |
CN114017062B (en) * | 2021-11-03 | 2023-11-14 | 北京城建设计发展集团股份有限公司 | Method for monitoring cable to pass through secondary lining of large-diameter shield tunnel segment |
CN114278341B (en) * | 2022-02-16 | 2024-02-27 | 中铁一局集团有限公司 | Two-lining template construction structure and method based on mine tunnel special-shaped section |
CN114808776A (en) * | 2022-04-18 | 2022-07-29 | 中交一公局集团有限公司 | Prefabricated installation construction method for prefabricated box culvert pipe |
CN114753861A (en) * | 2022-05-17 | 2022-07-15 | 中铁第一勘察设计院集团有限公司 | Drilling and blasting method double-line tunnel prefabricated lining structure and construction method thereof |
CN115418983B (en) * | 2022-09-27 | 2023-07-28 | 中铁十四局集团有限公司 | Construction method for prefabricated box culvert in highway-railway co-construction large-section shield tunnel |
CN115949427B (en) * | 2023-03-08 | 2023-05-16 | 中铁第六勘察设计院集团有限公司 | Double-switching shield lining structure for subway wiring section and assembling method thereof |
Family Cites Families (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003206693A (en) * | 2002-01-08 | 2003-07-25 | Taisei Corp | Lining method of shield tunnel |
CN102061926A (en) * | 2009-11-11 | 2011-05-18 | 中铁十八局集团有限公司 | TBM tunneling and secondary lining synchronous construction method at mucking of continuous belt conveyor and trolley |
CN102003207B (en) * | 2010-12-31 | 2012-08-29 | 上海市隧道工程轨道交通设计研究院 | Escape platform and security channel structure for single-hole dual-line magnetic suspension tunnel |
CN202417530U (en) * | 2012-01-17 | 2012-09-05 | 张新泉 | Bottom-positioned traversing synchronous tunnel lining trolley for continuous conveyor construction of tunnel |
CN203308471U (en) * | 2012-11-20 | 2013-11-27 | 中铁十八局集团有限公司 | Open type TBM cast-in-place concrete inverted arch synchronous lining trolley |
CN103195440A (en) * | 2013-04-03 | 2013-07-10 | 中铁隧道勘测设计院有限公司 | Three-layer-structure subway double-line single-pipe circular tunnel |
CN203847130U (en) * | 2013-12-27 | 2014-09-24 | 中铁十八局集团有限公司 | Cast-in-situ inverted arch lining trolley and concrete curing system capable of being synchronously constructed along with boring of TMB (tunnel boring machine) |
CN104612711B (en) * | 2015-02-09 | 2017-04-19 | 浙江省交通规划设计研究院 | Lining segment structure of city subway up-down section overlapping shield tunnels |
CN104747200B (en) * | 2015-03-18 | 2017-03-01 | 中铁工程装备集团有限公司 | Construction method with double-deck supporting and the hard rock mole of variable section of jurisdiction diameter |
CN107435544A (en) * | 2017-05-25 | 2017-12-05 | 中铁十四局集团有限公司 | A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure |
CN107916936A (en) * | 2017-12-20 | 2018-04-17 | 北京市政建设集团有限责任公司 | A kind of major diameter one-tunnel two-tracks subway tunnel and its construction method |
-
2017
- 2017-05-25 CN CN201710381186.3A patent/CN107435544A/en active Pending
-
2018
- 2018-05-10 WO PCT/CN2018/086275 patent/WO2018214737A1/en unknown
- 2018-05-10 EP EP18806523.9A patent/EP3633141B1/en active Active
Also Published As
Publication number | Publication date |
---|---|
EP3633141A4 (en) | 2021-03-24 |
WO2018214737A1 (en) | 2018-11-29 |
CN107435544A (en) | 2017-12-05 |
EP3633141B1 (en) | 2024-01-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3633141A1 (en) | Construction method for inner structure of single-bore double-track composite lining shield tunnel | |
CN103016029B (en) | Grouped second liner construction method for large cross-section tunnel | |
CN103075163B (en) | Support change process of second liner construction of large-cross-section tunnel | |
CN103939114B (en) | A kind of outstanding rail chassis lining construction method | |
CN102505708B (en) | Construction method of tunnel at oversized cross section open cut area in track traffic | |
CN109505609B (en) | Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack | |
CN103470272A (en) | Trolley for concrete construction on multiple sections by employing mining method and construction method thereof | |
CN103939113A (en) | Suspension rail type construction trolley | |
CN203499697U (en) | Trolley used for concrete construction of various cross sections through mining method | |
CN105256836A (en) | Construction method for fast restoring road traffic in construction of underground project | |
KR20100100193A (en) | Form system for constructing rc-girder in rc top down method and the rc top down method using the same | |
CN109869153A (en) | The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method | |
KR101427812B1 (en) | Open cut method for constructing an underground structure | |
CN110056362B (en) | Shield receiving and lateral translation hoisting method in air duct of underground excavation station | |
CN106760486A (en) | Exterior wall mould and its erection method in foundation ditch | |
KR20160004710A (en) | Joint apparatus of upper and bottom precast segment for precast box culvert, and construction method for the same | |
CN116378711A (en) | Shallow-buried underground excavation tunnel separated trolley device and construction method | |
CN103075164B (en) | Double-hole and two-liner sequential isochronous propelling construction process | |
CN104746434A (en) | Closure segment formwork system without dismantling outer formwork | |
KR20190066754A (en) | Formwork structure supported by column unit | |
CN208749354U (en) | Shallow buried covered excavation Urban Underground pipe gallery | |
CN109695347A (en) | The construction techniques of curved device is held based on round steel | |
CN110030000B (en) | One-step-distance one-turn construction method for small-section tunnel | |
CN219012636U (en) | Shallow underground tunnel disconnect-type platform truck device that buries | |
CN106193112A (en) | Tunnel side ditch xoncrete structure one-shot forming system and using method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20191220 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
DAV | Request for validation of the european patent (deleted) | ||
DAX | Request for extension of the european patent (deleted) | ||
A4 | Supplementary search report drawn up and despatched |
Effective date: 20210224 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E21D 11/10 20060101ALI20210218BHEP Ipc: E21D 11/08 20060101AFI20210218BHEP |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20221004 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20230720 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602018064039 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
P01 | Opt-out of the competence of the unified patent court (upc) registered |
Effective date: 20240201 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20240110 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 1649044 Country of ref document: AT Kind code of ref document: T Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240510 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20240517 Year of fee payment: 7 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240411 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240410 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240410 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240410 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240510 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240411 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240510 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240510 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20240110 |