EP3279290A1 - Method for building coke oven - Google Patents

Method for building coke oven Download PDF

Info

Publication number
EP3279290A1
EP3279290A1 EP16771759.4A EP16771759A EP3279290A1 EP 3279290 A1 EP3279290 A1 EP 3279290A1 EP 16771759 A EP16771759 A EP 16771759A EP 3279290 A1 EP3279290 A1 EP 3279290A1
Authority
EP
European Patent Office
Prior art keywords
coke oven
block
building
oven
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP16771759.4A
Other languages
German (de)
French (fr)
Other versions
EP3279290B1 (en
EP3279290A4 (en
Inventor
Shunichi Kamezaki
Seiji Enoeda
Jun Okada
Hisahiro Matsunaga
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Publication of EP3279290A1 publication Critical patent/EP3279290A1/en
Publication of EP3279290A4 publication Critical patent/EP3279290A4/en
Application granted granted Critical
Publication of EP3279290B1 publication Critical patent/EP3279290B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C10PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
    • C10BDESTRUCTIVE DISTILLATION OF CARBONACEOUS MATERIALS FOR PRODUCTION OF GAS, COKE, TAR, OR SIMILAR MATERIALS
    • C10B29/00Other details of coke ovens
    • C10B29/02Brickwork, e.g. casings, linings, walls
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/04Blast furnaces with special refractories
    • C21B7/06Linings for furnaces
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B9/00Stoves for heating the blast in blast furnaces
    • C21B9/02Brick hot-blast stoves
    • C21B9/06Linings
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/0003Linings or walls
    • F27D1/0006Linings or walls formed from bricks or layers with a particular composition or specific characteristics
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/0003Linings or walls
    • F27D1/003Linings or walls comprising porous bricks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/04Casings; Linings; Walls; Roofs characterised by the form, e.g. shape of the bricks or blocks used
    • F27D1/042Bricks shaped for use in regenerators
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/04Casings; Linings; Walls; Roofs characterised by the form, e.g. shape of the bricks or blocks used
    • F27D1/06Composite bricks or blocks, e.g. panels, modules
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/04Casings; Linings; Walls; Roofs characterised by the form, e.g. shape of the bricks or blocks used
    • F27D1/06Composite bricks or blocks, e.g. panels, modules
    • F27D1/063Individual composite bricks or blocks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/16Making or repairing linings increasing the durability of linings or breaking away linings
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/16Making or repairing linings increasing the durability of linings or breaking away linings
    • F27D1/1621Making linings by using shaped elements, e.g. bricks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D2001/0046Means to facilitate repair or replacement or prevent quick wearing
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D2001/0046Means to facilitate repair or replacement or prevent quick wearing
    • F27D2001/0053Furnace constructed in modules

Abstract

Provided is a method for building a coke oven whereby a coke oven can be built efficiently by laying shaped refractories to a high degree of precision while reducing the burden on workers, without using large module bricks. Our method for building a coke oven in order to renew or newly build a coke oven includes producing a block by laying a plurality of shaped refractories at a location other than a building site of the coke oven, transporting the block to the building site of the coke oven, applying mortar to a position for placing the block, and placing the block at the position where the mortar was applied. The length in the longitudinal direction of the block is at least 1/4 and at most 2/3 of an oven length of the coke oven, and the height of the block is less than 2 m.

Description

    TECHNICAL FIELD
  • This disclosure relates to a method for building a coke oven in order to renew or newly build an entire coke oven. In particular, this disclosure relates to a method for building a coke oven whereby a coke oven can be built efficiently by laying shaped refractories precisely while reducing the burden on workers, without the use of large module bricks.
  • BACKGROUND
  • Metallurgical coke used to manufacture steel is produced in a chamber-type coke oven by destructive distillation of coal. A chamber-type coke oven is structured by arranging carbonization chambers and combustion chambers that supply heat to the carbonization chambers alternately in the oven width direction. Heat is supplied from the combustion chambers to the carbonization chambers through refractories, such as refractory bricks, that separate the carbonization chambers and the combustion chambers. Some chamber-type coke ovens have 100 or more oven chambers. These gigantic brick structures reach a total length of 100 m or more and a height of 10 m or more.
  • The refractories that constitute the coke oven are gradually damaged due to exposure to high temperatures exceeding 1000 °C and to friction produced when coke that is obtained by destructive distillation of coal is extruded horizontally and removed. Therefore, coke ovens are used while performing simple repair with a method such as thermal spraying, or partial re-laying repair primarily on the oven port. A typical lifetime, however, is considered to be 40 to 50 years, and deteriorated coke ovens need to be renewed or newly built.
  • Coke ovens are typically built by having oven construction workers manually lay shaped refractories, such as bricks. Specifically, this operation is typically performed as follows.
  • A coke oven has a complicated structure. The contact surface between vertically-laid shaped refractories is horizontal and is designed to be aligned at the same height throughout. Layers are counted in the order of the first layer, the second layer, etc. from the bottom. During new building of a coke oven or building to renew a shaped refractory structure, a total of several hundred oven construction workers are deployed in groups of several dozen to fixed areas, and the workers lay one or two layers per day of shaped refractories in order from the bottom of the oven.
  • Each of the shaped refractories is laid during this operation as follows. First, the shaped refractories to be used are carried into the working height in advance using a crane or the like and are arranged near the position of construction. Mortar is produced using a mixer, placed in a container, and carried into the worksite by a crane or the like. The mortar is then divided into small portions and arranged near the position of construction. At the position where the shaped refractories are to be laid, the oven construction workers then apply mortar using a trowel to yield a predetermined joint thickness (method where mortar is applied to the laid refractories). Next, the workers take a shaped refractory that was placed nearby and lay it on top of the mortar, without trapping air therebetween. After adjusting the position of the laid shaped refractory using a level gauge or the like, the next shaped refractory is displaced horizontally to the laying position. By repeating the above procedure, one layer of shaped refractories is laid. Once laying of one layer of shaped refractories is complete, it is confirmed whether the required precision has been achieved. Any problematic spots are re-laid, and then the laying operation for the next layer begins.
  • The above-described type of oven building by manual laying, however, has the following problems. First, the shaped refractories that are used in the coke oven weigh approximately 5 kg to 10 kg each. Both arranging these shaped refractories in advance at the worksite and actually laying them require heavy physical labor, placing a significant burden on the workers.
  • Also, the coke oven needs to be built with a complicated combination of shaped refractories that come in a variety of shapes, such as a rectangle, trapezoid, L-shape, or the like as seen from above, unlike typical construction bricks. In addition, the shaped refractory structure of the coke oven needs to have an extremely high degree of precision. For example, the walls of the combustion chambers are required to be highly smooth, with an unevenness of 1 mm or less. Refractory bricks that are typically used as shaped refractories for coke ovens, however, are produced by firing. As a result, the error in the dimensions of each refractory brick is approximately 1 mm to 2 mm. Therefore, the required precision cannot be obtained by simply laying refractory bricks. After taking into account the variation in brick dimensions, bricks with complicated shapes need to be laid while making manual adjustments so as to achieve the final dimensional accuracy of the coke oven. Accordingly, an extremely high level of skill is required to lay the shaped refractories of a coke oven, but there is always a shortage of such experienced oven construction workers.
  • For these reasons, there is a demand for the development of a method that allows shaped refractories to be laid efficiently with little manual labor.
  • For example, JP H04-213388 A (PTL 1) proposes a technique for using integrally formed large module bricks to repair a re-laid portion of a heating chamber in a coke oven. The module bricks are prepared in advance by pouring a slurry for refractories into a mold and firing. The flue forming the combustion chamber of the coke oven and the walls of the carbonization chamber are formed integrally. This technique uses module bricks with larger dimensions than the refractory bricks used in regular manual laying. The time for repair work in the coke oven can therefore be shortened, reducing the workload.
  • JP 2011-503254 A (PTL 2) proposes a technique for attaching an outer mold and a consumable inner mold (core) to a location where the refractory brick wall of the coke oven needs to be repaired, pouring a refractory castable material into the molds, and then hardening by firing. In this technique, repair does not need to be made by laying shaped refractories, thereby reducing the workload.
  • CITATION LIST Patent Literature
    • PTL 1 : JP H04-213388 A
    • PTL 2: JP 2011-503254 A
    SUMMARY (Technical Problem)
  • In the technique in PTL 1, however, large modules that are produced by firing a slurry are used. Therefore, strain may be generated when the module is heated, leading to cracks. Also, if a crack forms for example when the module is transported to the building site, the crack grows long in accordance with the size of the module.
  • In the technique in PTL 2 as well, a larger portion than a regular-sized shaped refractory is molded integrally and fired. Therefore, cracks tend to occur upon the application of heat. Furthermore, the accuracy of the resulting repaired section depends on the accuracy of the mold. However, the mold has a complicated shape, and at the repair site, it is difficult to install the outer mold and the consumable inner mold accurately.
  • Additionally, the techniques in PTL 1 and PTL 2 are both for partially repairing a coke oven. No consideration is made of application to renewing or newly building an entire coke oven. Since repairs are typically partial and the work is hot, the speed of work is given greater importance than the accuracy of work for repairs. By contrast, a much higher degree of accuracy than for repair is required when newly building an oven, since operation of the oven over an extended period of time is assumed.
  • Therefore, it would be helpful to provide a method for building a coke oven in order to renew or newly build an entire coke oven whereby a coke oven can be built efficiently by laying shaped refractories precisely while reducing the burden on workers, without the use of large module bricks.
  • (Solution to Problem)
  • The primary features of our method are as follows.
    1. 1. A method for building a coke oven in order to renew or newly build a coke oven, the method comprising:
      • producing a block by laying a plurality of shaped refractories at a location other than a building site of the coke oven;
      • transporting the block to the building site of the coke oven;
      • applying mortar to a position for placing the block; and
      • placing the block at the position where the mortar was applied;
      • wherein a length in a longitudinal direction of the block is at least 1/4 and at most 2/3 of an oven length of the coke oven, and a height of the block is less than 2 m.
    2. 2. The method for building a coke oven of 1., wherein at least one of the blocks is for forming a regenerator of the coke oven.
    3. 3. The method for building a coke oven of 1. or 2, wherein at least one of the blocks is for forming a combustion chamber of the coke oven.
    4. 4. The method for building a coke oven of any one of 1. to 3., further comprising manually laying shaped refractories at the building site of the coke oven.
    5. 5. The method for building a coke oven of any one of 1. to 4., wherein during the producing, the block is produced using a robot.
    6. 6. The method for building a coke oven of any one of 1. to 5., wherein during the producing, the block is produced using a robot with an arm for laying shaped refractories and a robot with an arm for applying mortar.
    (Advantageous Effect)
  • According to our method for building a coke oven, an entire coke oven can be renewed or newly built by laying shaped refractories precisely while reducing the burden on workers, without the use of large module refractories.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • In the accompanying drawings:
    • FIG. 1 is a flowchart schematically illustrating a method for building a coke oven in one of the embodiments of this disclosure.
    DETAILED DESCRIPTION
  • A detailed description of our method is given below. The following is merely one embodiment of our method, and this disclosure is in no way limited to the method described below. In the following explanation, unless noted otherwise, the terms up, down, horizontal, vertical, and height are used to refer to shaped refractories, and to blocks manufactured by laying the shaped refractories, taking the orientation upon incorporation into the coke oven as a reference.
  • FIG. 1 is a flowchart schematically illustrating a method for building a coke oven in one of the embodiments of this disclosure. Our method for building a coke oven is for renewing or newly building a coke oven. As illustrated in FIG. 1, our method includes at least processes (1) to (4). Whereas (3) and (4) are performed at the coke oven building site, process (1) is performed at a location other than the coke oven building site.
    1. (1) A block production process for producing a block by laying a plurality of shaped refractories at a location other than a coke oven building site;
    2. (2) a transportation process for transporting the block to the coke oven building site;
    3. (3) a mortar application process for applying mortar to a position for placing the block; and
    4. (4) a block placement process for placing the block at the position where the mortar was applied.
  • In this disclosure, "renewing or newly building a coke oven" includes the cases of dismantling the shaped refractory structure of an existing coke oven and newly building a shaped refractory structure on the existing foundation after removal (pad-up), building a coke oven completely new, adding on an oven section adjacent to an existing coke oven, and the like.
  • The aforementioned processes (1) to (4) will be described in detail below.
  • [Block production process]
  • In the block production step, blocks are produced by laying a plurality of shaped refractories at a location other than a coke oven building site. At the coke oven building site, a coke oven can be built by placing the blocks. This approach reduces the conventional labor by oven construction workers to manually place shaped refractories one by one at a building site with poor operability, thereby significantly improving the work efficiency at the building site.
  • The aforementioned "location other than a coke oven building site" may be any location that differs from the coke oven building site and that allows production of a block by laying shaped refractories. For example, the block production process may be performed at a location adjacent to the coke oven building site, such as land adjacent to a temporary shed provided at the location for building the coke oven. If the coke oven is being built within the steelworks, the block production process may be performed at another location within the steelworks. The blocks may also be produced at a location distant from the coke oven building site. Considering the time and cost for transportation, however, the blocks are preferably produced at a location adjacent to the coke oven building site. To improve efficiency, the block production step is preferably performed intensively at one location. Blocks produced at a plurality of locations, however, may be transported and carried into one coke oven building site.
  • The blocks may be for forming any portion of the coke oven, but forming blocks from portions that have a relatively simple structure or portions that are repeatedly produced greatly increases work efficiency. Therefore, at least one of the blocks is preferably for forming either a regenerator or a combustion chamber. No upper limit is placed on the number of blocks that form the regenerators or the combustion chambers, and all (100%) of the blocks that are used may form the regenerators or the combustion chambers.
  • [[Shaped refractories]]
  • No restriction is placed on the shaped refractories for producing the blocks. Any shaped refractories may be used, such as bricks, precast blocks, and the like. Among these, typical shaped refractories used when building a coke oven by manual laying are preferably used. By using typical shaped refractories, a similar oven to conventional ovens can be designed even when building an oven with our method. As a result, performance that is at least equivalent to that of a conventional oven can be guaranteed. Also, if a crack forms when using large module bricks, the crack might spread across the entire module. By using typical shaped refractories, however, even if a crack forms in one shaped refractory, propagation of the crack can be stopped within that shaped refractory. Typical shaped refractories refer to all shaped refractories that are for manual laying and are not module bricks. The measurements thereof are generally a height of 10 cm to 15 cm and a horizontal length of 20 cm to 40 cm.
  • [[Production of blocks by manual laying]]
  • The aforementioned blocks can be produced by manual laying. In this case, unlike the case of manually laying shaped refractories at the coke oven building site, a sufficient workspace can be ensured. Hence, the burden on workers can be reduced, even for the same manual laying. Furthermore, in the case of laying shaped refractories at the coke oven building site, work needs to be performed after assembling scaffolding to match the height of the laid shaped refractories. In this disclosure, however, the operation to lay shaped refractories is performed at a location other than the coke oven building site. Therefore, there is no need to use scaffolding or the like, and work can be performed on steady ground.
  • [[Production of blocks by a robot]]
  • The aforementioned blocks may also be produced using a robot. In this case, a portion or all of the block production process can be automated, thereby reducing the number of workers involved in heavy physical labor, such as manually laying shaped refractories. Also, the use of robots allows automatization of the operation to lay shaped refractories, which requires a high level of skill.
  • Any type of robot may be used to produce blocks. A robot with a movable arm capable of handling shaped refractories or the like is preferably used. An example of the aforementioned robot with an arm is a vertically articulated robot that is a type of industrial robot. Blocks may also be produced using a robot with an arm for laying shaped refractories and a robot with an arm for applying mortar.
  • [[Block production line]]
  • There may be one or a plurality of block production lines, regardless of whether blocks are produced by manual laying or using robots. By producing blocks with multiple lines, the supply rate of blocks to the coke oven building site can be increased. Therefore, in terms of work efficiency, the number of block production lines is preferably at least two and more preferably at least three. No upper limit is placed on the number of production lines, but if more lines than necessary are provided, then the rate determining processes become the subsequent block transportation process and the processes that are performed at the coke oven building site, i.e. the mortar application process and block placement process. It thus becomes difficult to increase the speed of coke oven building any further, reducing the cost effectiveness of additional production lines. Accordingly, the number of lines is preferably determined in light of factors such as the scale of the coke oven and the operation speed in each process.
  • [[Block size]]
  • In this disclosure, it is important that the length in the longitudinal direction of the block produced in the block production process be at least 1/4 and at most 2/3 of the oven length of the coke oven to be built, and it is important that the height of the block be less than 2 m. When the block is produced by manual laying, shaped refractories are laid at a high position if the block is excessively high. Therefore, a working floor needs to be provided by some method, such as by assembling scaffolding. For example, in Japan, Article 518 of the Ordinance on Industrial Safety and Hygiene stipulates that a working floor needs to be provided if there is a danger of a fall when performing work at a height of 2 m or greater. If the height of the block is less than 2 m, there is no need to install scaffolding or the like and carry out work in high places, even when producing the block by manually laying shaped refractories. Hence, the work efficiency is high. Also, in the case of producing blocks using robots, if the height of the block is less than 2 m, then the position where shaped refractories are laid is within the range of arm mobility of a typical robot with an arm. Therefore, a block can be produced by simply moving a robot horizontally, thus yielding high work efficiency. No particular lower limit is placed on the height of the block, but the block preferably contains at least two layers of shaped refractories. Setting the length in the longitudinal direction of the block anywhere from at least 1/4 to at most 2/3 of the oven length of the coke oven to be built is acceptable. In terms of workability in the below-described block transportation process, however, the length in the longitudinal direction of the block is more preferably at least 1/4 to at most 1/2 of the oven length of the coke oven.
  • As referred to here, the "length in the longitudinal direction of the block" indicates the length in the longitudinal direction in a horizontal cross-section of the block. The "height of the block" indicates the height from the lower surface to the upper surface of the block. Any unevenness, such as dowels provided on the sides, the upper surface, and the bottom surface of the block, is not included in the aforementioned "length in the longitudinal direction of the block" and "height of the block". The "oven length of the coke oven" refers to the length in the longitudinal direction of the combustion chambers and carbonization chambers constituting the coke oven. The typical oven length of coke ovens currently in use is approximately 15 m to 17 m.
  • [Block transportation process]
  • Blocks produced by the aforementioned block production process are transported to the coke oven building site after completion of drying. Any method may be used for transporting blocks in the block transportation process. In accordance with factors such as the distance between the block production site and the coke oven building site, one or a combination of a plurality of methods may be used, such as a truck, a transporter (a self-propelled transport carriage), a crane, or the like. In this disclosure, the block is relatively small, since the length in the longitudinal direction of the block is at least 1/4 and at most 2/3 of the oven length of the coke oven, and the height of the block is less than 2 m. Therefore, a typical transportation method and means may be used, thereby reducing costs. For example, when a temporary shed is provided at the coke oven building site, the block may be transported from the block production site to the temporary shed by a transporter. Within the temporary shed, the block may be transported to the position of construction using a combination of a ceiling crane and a stage jack. In the block transportation process, the block can also be transported directly from the block production site to the position of construction at the coke oven building site. Alternatively, the block may first be transported to a block storage site and stored temporarily. In accordance with progress on oven building, the block may then be transported from the block storage site to the position of construction at the coke oven building site.
  • [Mortar application process]
  • Next, mortar is applied to a position for placing a block. Any method for applying mortar may be used. As in the case of laying shaped refractories, it suffices to apply mortar to the positions contacted by the bottom and sides of the block. In other words, it suffices to apply mortar to the upper surface and the sides of the position where the block is placed.
  • Among the surfaces where mortar is applied, a spacer may be placed on the portion that contacts the bottom of the block being installed, i.e. the portion that becomes the horizontal joint. At this portion, it might not be possible to ensure the desired joint thickness due to pressure from the load of the block. By providing a spacer and installing the block on top of the spacer, the joint thickness can easily be ensured. A spacer having the same height as the joint thickness is preferably used.
  • [Block placement process]
  • Next, a block is placed at the position where the mortar was applied in the mortar application process. Any method for placing the block may be used. For example, the block may be lifted by a crane or the like, and while adjusting the position of the block, the block may be placed on the surface where the mortar was applied. In this way, by building in units of blocks, the burden on workers is reduced as compared to when manually laying shaped refractories one by one. Hence, shaped refractories can be laid to a high degree of accuracy.
  • [Process to manually lay shaped refractories]
  • In our method for building a coke oven, a coke oven can be built by repeatedly performing the above processes. At this time, the aforementioned blocks can be used to build the entire coke oven, or a portion of the coke oven may be built using blocks, with the remaining portion being built by manual laying. In particular, forming blocks from portions that have a relatively simple structure or portions that are repeatedly produced greatly increases work efficiency. Therefore, either or both of the regenerators and the combustion chambers are preferably built using blocks, and other portions such as a corbel with a complicated structure are preferably built by manual laying.
  • INDUSTRIAL APPLICABILITY
  • According to our method for building a coke oven, a coke oven can be built efficiently by laying shaped refractories to a high degree of precision while reducing the burden on workers, without using large module bricks. Therefore, our method is extremely effective for renewing or newly building an entire coke oven.

Claims (6)

  1. A method for building a coke oven in order to renew or newly build a coke oven, the method comprising:
    producing a block by laying a plurality of shaped refractories at a location other than a building site of the coke oven;
    transporting the block to the building site of the coke oven;
    applying mortar to a position for placing the block; and
    placing the block at the position where the mortar was applied;
    wherein a length in a longitudinal direction of the block is at least 1/4 and at most 2/3 of an oven length of the coke oven, and a height of the block is less than 2 m.
  2. The method for building a coke oven of claim 1, wherein at least one of the blocks is for forming a regenerator of the coke oven.
  3. The method for building a coke oven of claim 1 or 2, wherein at least one of the blocks is for forming a combustion chamber of the coke oven.
  4. The method for building a coke oven of any one of claims 1 to 3, further comprising manually laying shaped refractories at the building site of the coke oven.
  5. The method for building a coke oven of any one of claims 1 to 4, wherein during the producing, the block is produced using a robot.
  6. The method for building a coke oven of any one of claims 1 to 5, wherein during the producing, the block is produced using a robot with an arm for laying shaped refractories and a robot with an arm for applying mortar.
EP16771759.4A 2015-03-30 2016-03-25 Method for building coke oven Active EP3279290B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2015069895 2015-03-30
PCT/JP2016/001762 WO2016157871A1 (en) 2015-03-30 2016-03-25 Method for building coke oven

Publications (3)

Publication Number Publication Date
EP3279290A1 true EP3279290A1 (en) 2018-02-07
EP3279290A4 EP3279290A4 (en) 2018-02-28
EP3279290B1 EP3279290B1 (en) 2021-07-21

Family

ID=57004113

Family Applications (1)

Application Number Title Priority Date Filing Date
EP16771759.4A Active EP3279290B1 (en) 2015-03-30 2016-03-25 Method for building coke oven

Country Status (6)

Country Link
EP (1) EP3279290B1 (en)
JP (1) JP6008071B1 (en)
KR (2) KR102122191B1 (en)
CN (1) CN107429166B (en)
TW (1) TWI609954B (en)
WO (1) WO2016157871A1 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6789753B2 (en) * 2016-10-14 2020-11-25 日鉄エンジニアリング株式会社 Coke furnace and its repair method
JP2019035024A (en) * 2017-08-16 2019-03-07 株式会社メガテック Integral molding bricks for repairing a combustion chamber of a coke oven and a method for repairing using the same
JP6502435B2 (en) * 2017-08-23 2019-04-17 株式会社メガテック Horizontal alignment method of modular block for coke oven repair
JP6970636B2 (en) * 2018-03-26 2021-11-24 日本製鉄株式会社 Coke furnace construction method and temporary shed for coke oven construction
EP3922700B1 (en) * 2019-03-26 2023-01-11 JFE Steel Corporation Inspection apparatus and inspection method for coke oven construction, and coke oven construction method
JP7136147B2 (en) * 2020-02-28 2022-09-13 Jfeスチール株式会社 Coke oven construction method and module block manufacturing method
JP7235025B2 (en) * 2020-10-27 2023-03-08 Jfeスチール株式会社 Modular block manufacturing method, furnace construction method, and measurement system
CN112574763A (en) * 2020-12-30 2021-03-30 中冶焦耐(大连)工程技术有限公司 Coke oven masonry process adopting robot to masonry coke oven masonry
JP7363841B2 (en) 2021-03-18 2023-10-18 Jfeスチール株式会社 Module block shape measurement method, module block shape measurement system, and furnace construction method
CN113773864B (en) * 2021-10-09 2022-10-04 中国一冶集团有限公司 Self-climbing robot and method for filling vertical seams at furnace mouth of coke oven carbonization chamber

Family Cites Families (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2034230C (en) 1990-02-09 2001-07-03 Robert E. Kolvek Coke oven repair
EP1067167A3 (en) * 1999-07-05 2003-02-05 Kawasaki Steel Corporation Method of repairing coke oven and apparatus for taking-in bricks for repair
JP3397724B2 (en) * 1999-07-05 2003-04-21 川崎製鉄株式会社 Brick intake device to coke oven
JP3397723B2 (en) * 1999-07-05 2003-04-21 川崎製鉄株式会社 Coke oven repair method
JP2003226878A (en) * 2002-02-05 2003-08-15 Jfe Steel Kk Oven wall-reinforcing member for coke oven combustion chamber
AU2007203730B2 (en) * 2005-12-30 2012-09-27 Fastbrick Ip Pty Ltd An automated brick laying system for constructing a building from a plurality of bricks
US20110083314A1 (en) * 2007-03-02 2011-04-14 Saturn Machine & Welding Co., Inc. Method and apparatus for replacing coke oven wall
US20080209849A1 (en) * 2007-03-02 2008-09-04 Saturn Machine & Welding Co., Inc. Method and Apparatus for Replacing Coke Oven Wall
CA2703759A1 (en) 2007-11-01 2009-05-07 Dan Drakulich Repair of heating walls in a refractory furnace
CN101265411B (en) * 2008-03-27 2012-04-25 上海交通大学 Power source and meter hanging frame automatic butting and releasing device
KR100978138B1 (en) * 2009-01-22 2010-08-25 주식회사 후상 Temperature measuring apparatus of combustionchamber in a coke oven
JP5347614B2 (en) * 2009-03-19 2013-11-20 Jfeスチール株式会社 Coke oven hot repair method
US8266853B2 (en) * 2009-05-12 2012-09-18 Vanocur Refractories Llc Corbel repairs of coke ovens
JP5223875B2 (en) * 2010-03-11 2013-06-26 Jfeスチール株式会社 Coke oven repair method
WO2012078036A2 (en) * 2010-12-09 2012-06-14 Heatteq Refractories Holding B.V. Prefabricated coke oven wall, heavy lift construction for lifting and moving such a prefabricated coke oven wall, and method for repairing an existing coke oven battery
JP5962629B2 (en) * 2013-10-23 2016-08-03 Jfeスチール株式会社 Coke oven construction method
JP6098555B2 (en) * 2014-03-19 2017-03-22 Jfeスチール株式会社 Coke oven construction method

Also Published As

Publication number Publication date
CN107429166A (en) 2017-12-01
EP3279290B1 (en) 2021-07-21
KR20190064688A (en) 2019-06-10
JP6008071B1 (en) 2016-10-19
WO2016157871A1 (en) 2016-10-06
CN107429166B (en) 2020-07-24
TW201641679A (en) 2016-12-01
KR20170130481A (en) 2017-11-28
TWI609954B (en) 2018-01-01
JPWO2016157871A1 (en) 2017-04-27
EP3279290A4 (en) 2018-02-28
KR102122191B1 (en) 2020-06-12

Similar Documents

Publication Publication Date Title
EP3279290B1 (en) Method for building coke oven
EP2251398B1 (en) Corbel and method of repairing a corbel of coke ovens
EP2203702B1 (en) Repair of heating walls in a refractory furnace
JP6280453B2 (en) Method of repairing wall and ceiling of coke oven combustion chamber and ceiling of carbonization chamber adjacent to the combustion chamber
JP2017137447A (en) Mending method of combustion chamber of coke oven
CN102373063B (en) Bricklaying loading method of coke oven
JP6844332B2 (en) Construction method of the top of the chamber-type coke oven and the structure of the top of the chamber-type coke oven
JP5991478B2 (en) Coke oven partial transshipment repair method
JP2019218421A (en) Method of constructing coke oven
JP7259810B2 (en) Furnace construction method and spacer selection method
CN110986591B (en) Method for repairing and building refractory material on back of Maerz kiln suspension cylinder
JP2020070341A (en) Dismantling and constructing method of coke oven
JP7371668B2 (en) Furnace construction method
JP7235025B2 (en) Modular block manufacturing method, furnace construction method, and measurement system
JP7136148B2 (en) Coke oven construction method, module block manufacturing method, and module block template manufacturing method
JP7073973B2 (en) Mortar joint formation method
JP6981321B2 (en) How to build a coke oven
CN114958397A (en) Construction method for heat recovery coke oven masonry
CN117433298A (en) Construction method for refractory material at special-shaped brick supporting plate of high-temperature reducing gas pipeline of hydrogen-based shaft furnace
CN110953876A (en) Method for repairing vertical kiln refractory layer
JP2020117559A (en) Construction method of coke oven, and temporary platform for coke oven construction

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20171009

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

A4 Supplementary search report drawn up and despatched

Effective date: 20180126

RIC1 Information provided on ipc code assigned before grant

Ipc: C21B 9/06 20060101ALI20180122BHEP

Ipc: F27D 1/00 20060101ALI20180122BHEP

Ipc: C21B 7/06 20060101ALI20180122BHEP

Ipc: C21B 7/00 20060101ALI20180122BHEP

Ipc: F27D 1/16 20060101ALI20180122BHEP

Ipc: F27D 1/04 20060101ALI20180122BHEP

Ipc: F27D 1/06 20060101ALI20180122BHEP

Ipc: C10B 29/02 20060101AFI20180122BHEP

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20180924

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20210224

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602016060945

Country of ref document: DE

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1412623

Country of ref document: AT

Kind code of ref document: T

Effective date: 20210815

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20210721

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 1412623

Country of ref document: AT

Kind code of ref document: T

Effective date: 20210721

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20211021

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20211021

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20211122

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20211022

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602016060945

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

26N No opposition filed

Effective date: 20220422

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210721

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20220325

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20220331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220325

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220331

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220325

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220325

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220331

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220331

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: TR

Payment date: 20230323

Year of fee payment: 8

Ref country code: DE

Payment date: 20230131

Year of fee payment: 8

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20160325