JP2019218421A - Method of constructing coke oven - Google Patents

Method of constructing coke oven Download PDF

Info

Publication number
JP2019218421A
JP2019218421A JP2018114357A JP2018114357A JP2019218421A JP 2019218421 A JP2019218421 A JP 2019218421A JP 2018114357 A JP2018114357 A JP 2018114357A JP 2018114357 A JP2018114357 A JP 2018114357A JP 2019218421 A JP2019218421 A JP 2019218421A
Authority
JP
Japan
Prior art keywords
large block
crane
coke oven
furnace
performance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2018114357A
Other languages
Japanese (ja)
Other versions
JP7006521B2 (en
Inventor
中村 宏
Hiroshi Nakamura
宏 中村
境田 道隆
Michitaka Sakaida
道隆 境田
健一 川野
Kenichi Kawano
健一 川野
弘幸 石井
Hiroyuki Ishii
弘幸 石井
裕朗 羽田野
Hiroaki Hatano
裕朗 羽田野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP2018114357A priority Critical patent/JP7006521B2/en
Publication of JP2019218421A publication Critical patent/JP2019218421A/en
Application granted granted Critical
Publication of JP7006521B2 publication Critical patent/JP7006521B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

To provide a method of constructing a coke oven, capable of highly accurately, quickly, and safely laying refractory bricks in constructing a coke oven using refractory bricks of various shapes, without relying on a large number of highly skilled workers.SOLUTION: A tug 1a having recorded position data specifying where each of large blocks 1 is to be laid and/or configuration data on the large block 1, is attached to the large block 1 itself or to a pallet 8 on which the large block 1 is to be placed, and the large block 1 having been placed on the pallet 8 by a highly functional crane 9 provided in a shed 3 and having been transported by a conveyor 7 disposed in a supply space 6 of a lean-to roof 4 is laid on a specified place in an oven construction site 2 according to the position data or the configuration data recorded in the tug 1a.SELECTED DRAWING: Figure 1

Description

本発明は、コークス炉の築炉方法に関する。   The present invention relates to a method for building a coke oven.

製銑用コークスを製造する室炉式コークス炉においては、炭化室と燃焼室とが炉団長方向(炉幅方向)に交互に配置され、炭化室と燃焼室の上部には炉頂部、下部には蓄熱室が配列されている。燃焼室と蓄熱室との間の部分は蛇腹部ともいわれる。蓄熱室の下部にはソールフリューが配置されている。通常、炭化室の寸法は、炉高4〜7.5m余、炉幅350〜550mm、炉長13〜17m程度である。燃焼室は炉長方向に配列された燃焼室フリュー列からなる。炭化室と燃焼室との隔壁および燃焼室フリュー同士の隔壁、炉頂部、蛇腹部、蓄熱室、ソールフリューは、いずれも耐火物煉瓦の煉瓦積み構造で形成される。例えば、炭化室を64室有する室炉式コークス炉(以下単に「コークス炉」という。)においては、上記耐火物煉瓦を合計で200万個用いて構成されている。   In a coke oven furnace for producing coke for ironmaking, a coking chamber and a combustion chamber are alternately arranged in a furnace group length direction (furnace width direction). Represents a heat storage chamber. The part between the combustion chamber and the heat storage chamber is also called a bellows part. Sole flew is arranged in the lower part of the heat storage room. Usually, the dimensions of the carbonization chamber are about furnace height 4 to 7.5 m, furnace width 350 to 550 mm, and furnace length 13 to 17 m. The combustion chamber is composed of a row of combustion chamber flew arranged in the furnace length direction. The partition wall between the carbonization chamber and the combustion chamber, the partition wall between the combustion chamber flues, the furnace top, the bellows, the heat storage chamber, and the sole flue are all formed of a brick structure of refractory bricks. For example, a coke oven furnace having 64 carbonization chambers (hereinafter simply referred to as "coke oven") is configured using a total of 2 million refractory bricks.

既存のコークス炉は、現在、全国的に、20年〜30年の稼働期間を経て老朽化してきており、新たなコークス炉を建設する必要が迫ってきている。
コークス炉の建設は、従来、築炉工が耐火物煉瓦を手積みすることで行っている。手積みによる建設では、耐火物煉瓦の一つ一つにコテでモルタルを塗り、これを積み上げるという作業を繰り返し行う必要がある。さらに、コークス炉に使用される耐火物煉瓦は、一つあたり十数kgの重さがあり、これを積み上げる作業は極めて重労働といえる。
また、コークス炉は、様々な形状、大きさの多種類の耐火物煉瓦を複雑に組み合わせる必要があり、据付精度については、±2mm以内に抑える必要がある。そのためには、熟練した築炉工が大人数必要であるが、熟練した築炉工は高齢化し、大人数で確保することが難しくなってきている。
Existing coke ovens are now aging nationwide after an operation period of 20 to 30 years, and the need to construct a new coke oven is imminent.
Conventionally, coke ovens have been constructed by furnace builders manually refractory bricks. In manual construction, it is necessary to repeatedly apply mortar to each of the refractory bricks with a trowel and pile up the mortar. Furthermore, each refractory brick used in a coke oven weighs more than ten kilograms, and the work of stacking the refractory bricks is extremely hard work.
Further, the coke oven requires a complicated combination of various types of refractory bricks of various shapes and sizes, and the installation accuracy must be kept within ± 2 mm. For that purpose, a large number of skilled furnace builder is required, but the skilled furnace builder is aging and it is becoming difficult to secure a large number of skilled furnace builder.

このような事情に対し、工期短縮による必要な築炉工の人数削減を目的とし、予め、築炉現場から離れた作業しやすい広い場所で、複数の耐火物煉瓦を所定の大きさまで積み付けてモルタルにより一体化した大ブロックとし、この大ブロックを築炉現場で組み込んでコークス炉を積み付ける、プレハブ工法が公知である(特許文献1〜3)。
また、耐火物煉瓦を大ブロック化するには、粒状の耐火物組成物に水を加えて混練し、型枠に流し込んで、乾燥させることで耐火物の大ブロックを形成する、プレキャスト工法も公知である(特許文献4)。
プレハブ工法、あるいは、プレキャスト工法は、一つあたりの耐火物のブロックが大ブロックになったことにより、築炉現場で積み付けるブロック数が減少し、狭い築炉現場での作業が短縮されるため、作業効率が良く、築炉期間が短くなるとされている。特に、プレキャスト工法は、積み付けるブロック数そのものが減少するため、作業効率がよい。
In order to reduce the number of required furnace-building workers by shortening the construction period in such a situation, a plurality of refractory bricks are piled up to a predetermined size in advance in a wide area that is easy to work away from the furnace-building site. 2. Description of the Related Art A prefabricated construction method is known in which a large block is integrated with a mortar, and the large block is assembled at a furnace construction site and a coke oven is stacked (Patent Documents 1 to 3).
Also, in order to make the refractory bricks large blocks, a precast method is also known, in which water is added to a granular refractory composition, kneaded, poured into a mold, and dried to form a large block of refractories. (Patent Document 4).
In the prefabricated method or precast method, the number of blocks to be stacked at the furnace construction site is reduced due to the fact that each refractory block has become a large block, and the work at the narrow furnace construction site is shortened It is said that the work efficiency is good and the furnace construction period is shortened. In particular, the pre-casting method has good work efficiency because the number of blocks to be stacked is reduced.

一般的なコークス炉建設では、同形状のある程度の量の煉瓦を梱包(約1ton)したパレット単位で築炉現場へ移送運搬し、築炉現場で開梱(人力)→配列(人力)→築造(人力)する。取扱う煉瓦が軽量なため、現場での不具合発生時(煉瓦割れ、配列ミスなど)にも人の手で短時間での対応が可能である。
一方、プレキャスト工法では、一般的なコークス炉建設で用いられる人の手で積める軽量な煉瓦とは異なり、プレキャストした大ブロックが最大1tonあるいはそれ以上もある重量物であり、人で取扱うことが不可能であるため、人手によらないクレーン等の移送運搬や築炉専用の装置が必要となる。このプレキャストした大ブロックも、一つずつパレットと呼ばれる敷物に載せて扱われる。
In general coke oven construction, a certain amount of bricks of the same shape are transported to the furnace construction site in packed pallets (about 1 ton) and unpacked at the furnace construction site (manpower) → arrangement (manpower) → construction (Manpower). Since the bricks to be handled are lightweight, it is possible for humans to respond in a short time even when a problem occurs at the site (brick breakage, misalignment, etc.).
On the other hand, in the precast method, unlike the lightweight bricks that can be piled up by hand and used in general coke oven construction, the precast large block is a heavy object with a maximum of 1 ton or more and cannot be handled by humans. Since it is possible, a device dedicated to the transfer and transportation of a crane and the like and the furnace construction without manual operation is required. The precast large blocks are also handled one by one on a rug called a pallet.

人手によらない築炉方法としては、特許文献5においては、定型耐火物積み付けをロボットにより、積み付け位置把握システム(撮像素子と距離センサ)で行うことが記載されている。   As a furnace-building method that does not rely on humans, Patent Literature 5 describes that a fixed refractory is stacked by a robot using a stacking position grasping system (an image sensor and a distance sensor).

特開2015−081300号公報JP-A-2005-08300 特開2016−223647号公報JP-A-2006-223647 特開2016−222758号公報JP-A-2006-222758 特開2016−210643号公報JP 2016-210643 A 特開2017−14448号公報JP 2017-14448 A

プレキャスト工法では、「いかに決められた部位へ、決められたプレキャストされた大ブロックを間違いなく、早く」築造するかが重要であり、これを管理することが求められている。   In the precast method, it is important to build a "predetermined precast large block to the specified site without fail" and it is required to manage this.

特許文献5の方法は、積み付け位置を自動で測定し、測定値に基づいて、目的の位置に耐火物煉瓦を積みつけるものである。しかしながら、この方法では、自動測定などに時間がかかり、また、撮像素子や距離センサの測定精度が問題となる。また、大ブロックのための専用装置を用いれば、このような取扱いは可能であるが、専用装置の開発や運用は、時間やコスト的に問題がある。   The method of Patent Literature 5 automatically measures a stacking position and stacks refractory bricks at a target position based on the measured value. However, in this method, it takes time for automatic measurement and the like, and the measurement accuracy of the image sensor and the distance sensor becomes a problem. In addition, if a dedicated device for a large block is used, such handling is possible, but development and operation of the dedicated device have problems in terms of time and cost.

上記の事情をかんがみて、本発明は、様々な形状の耐火物煉瓦を用いるコークス炉の築炉において、それらの耐火物煉瓦を、多数の高度な技量を有する築炉技術者に頼らず、高い精度で高速かつ安全に積み付けることができるコークス炉の築炉方法を提供する。   In view of the above circumstances, the present invention is a furnace for building coke ovens using refractory bricks of various shapes, the refractory bricks, without relying on furnace construction engineers having a large number of advanced skills, high Provided is a method of building a coke oven which can be stowed with high accuracy at high speed and safely.

上記の課題を解決する本発明の要旨は以下のとおりである。
〔1〕一つあたり20kg以上の耐火物の大ブロックを積み付けるコークス炉の築炉方法であって、
前記コークス炉の築炉現場の上に仮設の上屋が設けられ、
前記上屋には、前記大ブロックを移送し、築炉現場の所定の場所に積み付ける高機能クレーンが設けられ、
前記コークス炉の築炉現場に隣接する場所に仮設の下屋が設けられ、
前記下屋には、前記大ブロックの供給スペースが設けられ、
前記供給スペースには、前記供給スペースに移送された前記大ブロックを、築炉現場方向に移送するコンベアが設けられており、
前記供給スペースの床面は、前記コンベアの高さがコークス炉の築炉後の煉瓦積みの最高高さよりも高くなるように設けられており、
前記大ブロックの築炉現場方向への移送は、前記コンベアでパレットに載置して行い、
各々の大ブロックを構築すべき位置データ、および/または、大ブロックの形状データが記録されたタグを、当該大ブロック自体、または、その大ブロックを載置する前記パレットに付与しておき、
前記タグの記録が、読み取られて前記高機能クレーンへ送られ、
前記高機能クレーンは、前記記録に基づいて、前記パレットに載せた前記大ブロックを移送し、築炉現場の所定の場所に積み付けることを特徴とする
コークス炉の築炉方法。

〔2〕前記高機能クレーンによる前記大ブロックの移送は自動で行い、前記移送された前記大ブロックの積み付けは、前記高機能クレーンにより自動で行うか、前記高機能クレーンのリモコン操作、または手添えで行うことを特徴とする〔1〕に記載のコークス炉の築炉方法。
〔3〕前記高機能クレーンがクラブトロリ式天井クレーンであり、前記クラブトロリ式天井クレーンの吊りビームの上端から、吊具と大ブロックとの合計の荷の重心までの長さL1(m)と、前記クラブトロリ式天井クレーンの吊りワイヤ保持部の中心から前記吊りビームの上端までの長さL(m)の関係が、以下の式(1)を満たしながら大ブロックを移送、積み付けることを特徴とする〔1〕または〔2〕に記載のコークス炉の築炉方法。
L1(m)≦L(m)×0.1+1.0 式(1)
The gist of the present invention for solving the above problems is as follows.
[1] A method of building a coke oven in which a large block of refractory of 20 kg or more is piled,
A temporary shed is provided on the coke oven site,
The shed is provided with a high-performance crane that transfers the large block and loads it at a predetermined location on the furnace construction site,
A temporary shed is provided at a location adjacent to the coke oven site,
The lower building is provided with a supply space for the large block,
In the supply space, a conveyor for transferring the large block transferred to the supply space in a furnace construction site direction is provided,
The floor surface of the supply space is provided so that the height of the conveyor is higher than the maximum height of brickwork after the coke oven,
Transfer of the large block toward the furnace construction site is performed by placing it on a pallet with the conveyor,
The position data at which each large block is to be constructed and / or the tag in which the shape data of the large block is recorded are given to the large block itself or the pallet on which the large block is placed,
The record of the tag is read and sent to the intelligent crane,
The high-function crane transfers the large block placed on the pallet based on the record and loads the large block at a predetermined location on a furnace-building site.

[2] The transfer of the large block by the high-performance crane is performed automatically, and the loading of the transferred large block is performed automatically by the high-performance crane, by remote control operation of the high-performance crane, or manually. The method for constructing a coke oven according to [1], wherein the method is carried out with the addition.
[3] The high-performance crane is a club trolley overhead crane, and has a length L1 (m) from the upper end of the suspension beam of the club trolley overhead crane to the center of gravity of the total load of the hanging tool and the large block. The relationship between the length L (m) from the center of the hanging wire holding portion of the club trolley type overhead traveling crane to the upper end of the hanging beam satisfies the following expression (1) is to transfer and stack large blocks. The method for constructing a coke oven according to [1] or [2].
L1 (m) ≦ L (m) × 0.1 + 1.0 Equation (1)

本発明によれば、以下のような優れた効果がある。
高機能クレーンにより積み付けを行うので、高度な技量を有する築炉高技能者の必要人数を減らし、クレーンオペレーター等の一般技能工(施工要員確保容易化)により築炉することができる。
耐火物煉瓦を大ブロックとしたことにより、積み付ける煉瓦の数が、200万個から大ブロック2〜5万個と取扱い数が大幅に減少したため、工期を短縮することができる。
大ブロックの構築すべき位置情報、および/または、大ブロックの形状情報が記録されたタグの記録を読み取って所定の位置に積み付けるので、積み付ける位置情報が早く正確に得られ、早く、精度よく積み付けることができる。
人手によらず、高機能クレーンで積み付けるために、安全性が向上する。なお、ここでいう「人手によらず」とは、完全自動クレーンを用いて、無人で積み付けすることと、基本的な移動はクレーンで行い、最後に所定の位置に積み付ける際の微調整を人手で(クレーンのリモコン操作や手添で)行うことを意味する。
According to the present invention, there are the following excellent effects.
Since the loading is performed by a high-performance crane, the required number of highly skilled furnace builders with high skills can be reduced, and the furnace can be built by general skilled workers such as crane operators (easy to secure construction personnel).
By making the refractory bricks large blocks, the number of bricks to be stacked is greatly reduced from 2 million to 2 to 50,000 large blocks, so that the construction period can be shortened.
The position information to be constructed of the large block and / or the record of the tag on which the shape information of the large block is recorded are read and stacked at a predetermined position, so that the position information to be stacked can be obtained quickly and accurately, and quickly and accurately. Can be well packed.
The safety is improved because it is loaded by a high-performance crane without manual operation. In this context, "independently of humans" refers to unmanned loading using a fully automatic crane, and fine-tuning when the basic movement is performed by a crane and finally loaded at a predetermined position. Is performed manually (by operating the remote control of the crane or by hand).

大ブロックを所定の位置に積み付ける工程において、大ブロックの流れと記録されたデータの流れを説明する概念図である。It is a conceptual diagram explaining the flow of a large block and the flow of recorded data in the process of stacking a large block at a predetermined position. 大ブロックを所定の位置に積み付ける工程を説明する斜視図である。It is a perspective view explaining the process of stacking a large block in a predetermined position. トング型の吊具を有する高機能クレーンを示した図である。(A)炉幅方向Xから見た図である。(B)炉長方向Yから見た図である。It is the figure which showed the high function crane which has a tong type | mold hanging tool. (A) It is the figure seen from furnace width direction X. (B) It is the figure seen from furnace length direction Y. ワイヤー吊りピン方式の吊具を有する高機能クレーンを示した図である。(A)炉幅方向Xから見た図である。(B)炉長方向Yから見た図である。It is the figure which showed the high function crane which has the hanging tool of the wire hanging pin system. (A) It is the figure seen from furnace width direction X. (B) It is the figure seen from furnace length direction Y. 水平出し装置を有する高機能クレーンを示した図である。(A)炉幅方向Xから見た図である。(B)炉長方向Yから見た図である。It is the figure which showed the high function crane which has a leveling device. (A) It is the figure seen from furnace width direction X. (B) It is the figure seen from furnace length direction Y.

本発明は、大ブロックを積み付ける発明であることが前提である。本発明は、今後の築炉工の施工技術力低下と築炉工人員減(建設重複による要員確保困難状況含む)を想定している。すなわち、一般的なコークス炉建設で従事する築炉高技能工を用いずとも、一般技能工(例:一般機械工、築炉一般工)でコークス炉の煉瓦積みを可能とすることを目的としている。   The present invention is based on the premise that it is an invention for stacking large blocks. The present invention envisages a decrease in the construction technology of the furnace builder and a decrease in the number of the furnace builder (including a situation where it is difficult to secure personnel due to duplication of construction). In other words, the purpose is to enable brickworking of coke ovens by general technicians (eg, general mechanics, general blast furnaces) without using high-technical furnaces for general coke oven construction. I have.

大ブロックとは、一つの単位が20kg以上にまとまった耐火物のブロックをいう。より好ましくは一つの単位が30kg以上、さらに好ましくは80kg以上の大ブロックとすることである。この大ブロックは、好ましくはプレキャスト工法により大型の耐火物の大ブロックを直接製造し、一体化したものとする。その理由は、高機能クレーンで積み付けを行う必要上、プレハブ工法のように小さい耐火物煉瓦をまとめたものであると、高機能クレーンで保持する際に耐火物煉瓦が損傷、脱落する恐れがあるためである。大ブロックは、プレキャスト工法により、熱膨張係数の小さい溶融シリカで構成することが好ましい。   The large block refers to a refractory block in which one unit weighs 20 kg or more. More preferably, one unit is a large block of 30 kg or more, more preferably 80 kg or more. The large block is preferably made by directly manufacturing a large block of a large refractory by a precast method. The reason is that small refractory bricks, such as the prefabricated construction method, need to be packed with a high-performance crane. Because there is. The large block is preferably made of fused silica having a small coefficient of thermal expansion by a precast method.

このように、一つの単位を大ブロック化することにより、一般的なコークス炉建設には約200万個の煉瓦が使用されるが、本発明では約2〜5万個の大ブロックでよく、取扱い数量としては1/40と大幅に削減が可能となる。その結果、施工要員確保確実化(一般技能工)、工事コスト安価化(施工単価減)、工期短縮化(施工取扱数大幅減)が可能となる。   In this way, by making one unit into a large block, about 2 million bricks are used for general coke oven construction, but in the present invention, about 20 to 50,000 large blocks may be used, The handling quantity can be greatly reduced to 1/40. As a result, it is possible to ensure the securing of construction personnel (general skilled workers), reduce the construction cost (reduction in construction unit price), and shorten the construction period (reduction in the number of construction handling).

本発明のコークス炉の築炉方法について、図1を参照して説明する。   A method of building a coke oven according to the present invention will be described with reference to FIG.

コークス炉の築炉現場2の上には、建設用に築炉現場2の全体を覆うような仮設の上屋3が設けられている。この上屋3の隣には、築炉現場2に隣接するように仮設の下屋4が設けられている。下屋4は、三階構造となっており、一階(1F)は大ブロック1を集積するための置き場5が設けられ、二階(2F)には、モルタル混練場、資機材置場が設けられ、三階(3F)には、大ブロック1の供給スペース6が設けられ、供給スペース6には、移送用のコンベア7が設置されている。大ブロック1をコンベア7に載置する際には、パレット8に載せたまま移送する。上屋3内には、大ブロック1を築炉現場2の所定位置に移送し、積み付ける高機能クレーン9が設けられている。また、大ブロック1またはパレット8には、その各々の大ブロック1を構築すべき位置データ、および/または、大ブロック1の形状データが記録されたタグ1aを付与する。記録は、紙への印刷、磁気記録、ICチップなど、方式は問わない。図1では、大ブロック1にタグ1aを付与した場合を例として図示している。   A temporary shed 3 that covers the whole of the coke oven site 2 is provided on the coke oven site 2 for construction. A temporary shed 4 is provided next to the shed 3 so as to be adjacent to the furnace construction site 2. The lower house 4 has a three-story structure. The first floor (1F) is provided with a storage space 5 for accumulating the large blocks 1, and the second floor (2F) is provided with a mortar kneading place and a material and equipment storage area. On the third floor (3F), a supply space 6 for the large block 1 is provided, and in the supply space 6, a conveyor 7 for transfer is installed. When placing the large block 1 on the conveyor 7, the large block 1 is transferred while being placed on the pallet 8. A high-performance crane 9 for transferring the large block 1 to a predetermined position on the furnace construction site 2 and stacking the large block 1 is provided in the shed 3. Further, the large block 1 or the pallet 8 is provided with a tag 1a in which position data for constructing each large block 1 and / or shape data of the large block 1 is recorded. Recording may be performed by any method such as printing on paper, magnetic recording, and an IC chip. FIG. 1 illustrates a case where a tag 1a is added to the large block 1 as an example.

大ブロック1、および、データ(大ブロック1を構築すべき位置データ、および/または、大ブロック1の形状データ)の流れを説明する。大ブロック1の流れ100を太い矢印で、データの流れ101を細い矢印で示した。図示しない工場で製造された大ブロック1は、トラック等で移送され、一旦保管エリア10(倉庫)に移送され、保管される。そして、必要に応じて大ブロック1を積み付ける際、準備エリア11でまとめられ、置き場5へと移送される。置き場5では、大ブロック1は、そのそれぞれの形状、大きさ等に応じ、積み付ける順序を所定のものとするため、供給スペース6に移送する順序を整える。この積み付けの順序を所定のものとするための作業は、準備エリア11で行ってもよい。その場合、その後、置き場5への移送で前後しないようにすればよい。   The flow of the large block 1 and data (position data for constructing the large block 1 and / or shape data of the large block 1) will be described. The flow 100 of the large block 1 is indicated by a thick arrow, and the data flow 101 is indicated by a thin arrow. The large block 1 manufactured in a factory (not shown) is transferred by a truck or the like, and is once transferred to a storage area 10 (warehouse) and stored. Then, when stacking the large blocks 1 as necessary, they are put together in the preparation area 11 and transferred to the storage area 5. In the storage space 5, the order in which the large blocks 1 are transferred to the supply space 6 is adjusted in accordance with the shape, size, etc. of the large blocks 1 in order to set the order in which they are stacked. The work for setting the stacking order to a predetermined order may be performed in the preparation area 11. In that case, after that, it is only necessary to prevent the transfer to the storage place 5 from moving back and forth.

置き場5から供給スペース6へは、クレーン、エレベータ等で引き上げて移送する。移送された大ブロック1は、積み付ける順序通りに移送されるよう、コンベア7上でパレット8に載置されて移送される。各々の大ブロック1の構築すべき位置データ、および/または、大ブロックの1形状データが記録されたタグ1aが当該大ブロック1自体、または、その大ブロック1を載置するパレット8に付与されている。このタグ1aに記録されたデータを、供給スペース6に設けられたデータ端末12により読み取る。そして、読み取られたデータは、高機能クレーン9に送られる。高機能クレーン9は、送られたデータに基づいて、所定の場所に当該大ブロック1を積み付ける。図1に示したように、保管エリア10に移送される前にすでに、大ブロック1自体にタグ1aが付与されている場合、データ端末12は、保管エリア10、置き場5に設けて、大ブロック1が製造されてから積み付けられるまでの流れ全体を管理してもよい。   It is lifted up from the storage place 5 to the supply space 6 by a crane, an elevator or the like and transferred. The transported large block 1 is placed on a pallet 8 on a conveyor 7 and transported so as to be transported in a stacking order. A tag 1a on which position data to be constructed of each large block 1 and / or one shape data of the large block 1 is recorded is attached to the large block 1 itself or a pallet 8 on which the large block 1 is placed. ing. The data recorded in the tag 1a is read by the data terminal 12 provided in the supply space 6. Then, the read data is sent to the high-performance crane 9. The high-performance crane 9 loads the large block 1 at a predetermined location based on the transmitted data. As shown in FIG. 1, if the tag 1 a is already attached to the large block 1 itself before being transferred to the storage area 10, the data terminal 12 is provided in the storage area 10 and the storage 5, The entire flow from production of 1 to loading may be managed.

本発明では、大ブロック1(最大1tonあるいはそれ以上)を積み付ける際、上記のように高機能クレーン9を用いて積み付ける。本発明にいう高機能クレーン9とは、炉幅方向X、炉長方向Y、炉高方向Zの三方向すべてに自在に大ブロック1を移送できるクレーンである。そして、高機能クレーン9は、絶対番地(所定の座標)での積み位置設定制御機能および水平出し機能を搭載しており、大ブロック1の積み付け精度の確保と人による積み付けレスによる安全確保も享受できる。すなわち、所定の座標x,y,zはシステムに事前登録しており、最短距離での移送が可能であり、操作者は作業実行の開始のみの操作が可能である。また、触れ止め制御機能を有しており、手介入による大ブロック1の強制触れ止め作業(手鍵棒等使用)が不要となり、積み付け(巻下げ)開始までの時間が短縮できる。   In the present invention, when the large blocks 1 (up to 1 ton or more) are stacked, they are stacked using the high-performance crane 9 as described above. The high-performance crane 9 according to the present invention is a crane that can freely transfer the large block 1 in all three directions of the furnace width direction X, the furnace length direction Y, and the furnace height direction Z. The high-function crane 9 has a loading position setting control function at an absolute address (predetermined coordinates) and a leveling function, so that the accuracy of loading the large blocks 1 is ensured and the safety is ensured without human loading. You can also enjoy. That is, the predetermined coordinates x, y, and z are pre-registered in the system, can be transferred at the shortest distance, and the operator can perform an operation only to start work execution. In addition, a touch stop control function is provided, so that a forced touch stop operation (using a hand key, etc.) of the large block 1 by hand intervention becomes unnecessary, and the time until the start of stacking (unwinding) can be shortened.

高機能クレーン9の吊具9aは、公知のものが使用でき、例えば、図3のような、トング型の吊具9aで大ブロック1を保持(把持)して移送、積み付けるものでもよいし、図4のようにワイヤー吊りピン方式の吊具9aで保持して大ブロック1を移送、積み付けるものでもよい。なお、図3、4において、水平出し機能を有する水平出し装置の記載は省略している。水平出し装置9eはたとえば、図5に示したように、吊りビーム9bと、吊具9aの間に設けることができる。図5(a)において示したように、水平出し装置9eの移動部9eaが炉長方向Yにスライド移動することにより、移動部9ecの重量の移動により吊りビーム9bの傾きを調整し、吊り荷である大ブロック1を水平にすることができる。一方、図5(b)において示したように、水平出し装置9eの移動部9eaが炉幅方向Xにスライド移動することにより、移動部9ecの重量の移動により吊りビーム9bの重心位置を調整し、吊り荷である大ブロック1を水平にすることができる。   As the hanging tool 9a of the high-function crane 9, a known one can be used. For example, as shown in FIG. 3, a large block 1 may be held (held) by a tong-shaped hanging tool 9a, transferred, and stacked. As shown in FIG. 4, the large block 1 may be transported and stacked while being held by a wire hanging pin type hanging tool 9a. 3 and 4, illustration of a leveling device having a leveling function is omitted. The leveling device 9e can be provided, for example, between the hanging beam 9b and the hanging tool 9a as shown in FIG. As shown in FIG. 5A, when the moving unit 9ea of the leveling device 9e slides in the furnace length direction Y, the weight of the moving unit 9ec adjusts the inclination of the suspension beam 9b, and the suspended load 9ec. Can be made horizontal. On the other hand, as shown in FIG. 5 (b), when the moving part 9ea of the leveling device 9e slides in the furnace width direction X, the center of gravity of the suspension beam 9b is adjusted by moving the weight of the moving part 9ec. The large block 1 as a suspended load can be made horizontal.

供給スペース6の床面は、コンベア7の高さがコークス炉の築炉後の煉瓦積みの最高高さよりも高くなるように設けてある。コークス炉の築炉では、最初に大ブロック1を積み付ける位置は低い位置であるが、築炉が進むにしたがって、大ブロック1を積み付ける位置が高くなる。築炉が進むに応じて、コンベア7の高さを上げていくことも考えられるが、それよりも、置き場5からの高さを一定とし、高機能クレーン9のZ方向への自由度により積み付け位置の上昇に対応した方が移送効率がよい。   The floor of the supply space 6 is provided so that the height of the conveyor 7 is higher than the maximum height of brickwork after the coke oven is built. In the coke oven building, the position where the large blocks 1 are initially stacked is a low position, but as the furnace construction proceeds, the position where the large blocks 1 are stacked increases. It is conceivable to raise the height of the conveyor 7 as the furnace construction progresses. However, rather than keeping the height from the storage place 5 constant, the height of the high-performance crane 9 in the Z direction is increased. Transfer efficiency is better if the mounting position is raised.

本発明では、各々の大ブロック1の構築すべき位置データ、および/または、大ブロックの1形状データが記録されたタグ1aを、当該大ブロック1自体、または、その大ブロック1を載置するパレット8に付与している。そして、このタグ1aの記録データに基づいて、高機能クレーン9が所定の位置に大ブロック1を積み付けている。   In the present invention, the tag 1a on which the position data to be constructed of each large block 1 and / or one shape data of the large block 1 is recorded is placed on the large block 1 itself or the large block 1 thereof. Pallet 8 is provided. Then, based on the recorded data of the tag 1a, the high-performance crane 9 loads the large block 1 at a predetermined position.

従来、一つの単位が小さい場合(以下、大ブロック1でないということで「小ブロック」という)は、小ブロック自体の製造誤差による、小ブロックの間の寸法誤差を吸収する目地が多いため、現場での各小ブロックの組み合わせや順序入れ替えで対応できていた。また、小ブロックは、同形状の小ブロックの数も多いため、代替する小ブロックを選択することも容易である。そのため、小ブロックを積み付ける場合は、配列管理を人手で行っていた。   Conventionally, when one unit is small (hereinafter, referred to as “small block” because it is not the large block 1), there are many joints that absorb a dimensional error between small blocks due to a manufacturing error of the small block itself. It was possible to respond by combining small blocks and changing the order. In addition, since there are many small blocks having the same shape, it is easy to select an alternative small block. For this reason, when stacking small blocks, arrangement management was performed manually.

しかしながら、本発明は大ブロック1により築炉するので、目地が相対的に少なくなった。その結果、目地の位置も大ブロック1の本体の寸法精度も要求されるようになり、各大ブロック1は、それぞれ最初の設計で決められた位置や順序以外で積み付けることが困難となった。また、一度異なる大ブロック1を現場に移送した後、それが、間違いであるとなると、大ブロック1の総数が少ないことから、代替する大ブロック1を簡単に供給することができない。さらに、大ブロック1となったことにより、現場(供給スペース6)でストックできる数も限られる。   However, in the present invention, since the furnace was built with the large block 1, the joints were relatively small. As a result, the joint position and the dimensional accuracy of the main body of the large block 1 are required, and it is difficult to stack each large block 1 in a position and order other than those determined in the initial design. . In addition, if the wrong large block 1 is transferred to the site once and is incorrect, the replacement of the large block 1 cannot be easily supplied because the total number of the large blocks 1 is small. In addition, the large block 1 limits the number that can be stocked at the site (supply space 6).

そこで、本発明では、大ブロック1をタグ1aにより管理する。具体的には、大ブロック1の構築すべき位置データ、および/または、大ブロック1の形状データをタグ1aに記録しておき、そのタグ1aに記録されたデータを読み込み、その通りに大ブロック1を積み付ける。タグ1aに記録する方法としては、記録媒体が紙なら、QRコード(登録商標)等の二次元コード、バーコード等を利用すればよい。   Therefore, in the present invention, the large block 1 is managed by the tag 1a. Specifically, the position data to be constructed of the large block 1 and / or the shape data of the large block 1 are recorded in the tag 1a, and the data recorded in the tag 1a is read. Stow one. As a method of recording on the tag 1a, if the recording medium is paper, a two-dimensional code such as QR code (registered trademark), a bar code, or the like may be used.

このタグ1aのデータに基づいて積み付ければ、正確に大ブロック1を管理することができるので、築炉する際に決められた形状、配置位置の大ブロック1を間違いなく、速く積み付けることができる。その結果、工期を短縮することができる。また、このタグ1aの情報を高機能クレーン9の作業中もフィードバックすることにより、積み付け作業中の大ブロック1のX、Y、Z位置を正確に管理、制御することができる。
このタグ1aによる大ブロック1の管理は、タグ1aの大ブロック1への付与を大ブロック1の製造後すぐに行うことが好ましい。そして、工場、保管エリア10、準備エリア11、置き場5、供給スペース6のいずれかの場所に設けたデータ端末12で読み取り、積み上げる場所と順序に誤りがないか確認する。確認は、コンピュータで自動的に照合してもよい。これにより、大ブロック1を、工場(製造)、倉庫(保管)、物流(移送)、現場(築造)の流れの中で一貫管理できるのでなお好ましい。
If the large blocks 1 are stacked based on the data of the tag 1a, the large blocks 1 can be accurately managed. it can. As a result, the construction period can be shortened. Also, by feeding back the information of the tag 1a during the operation of the high-performance crane 9, the X, Y, and Z positions of the large blocks 1 during the loading operation can be accurately managed and controlled.
It is preferable that the management of the large block 1 by the tag 1a is performed immediately after the large block 1 is manufactured. Then, the data is read by the data terminal 12 provided in any one of the factory, the storage area 10, the preparation area 11, the storage place 5, and the supply space 6, and it is checked whether there is an error in the place to be stacked and the order. The confirmation may be automatically verified by a computer. This is more preferable because the large block 1 can be integratedly controlled in the flow of a factory (manufacturing), a warehouse (storage), a physical distribution (transport), and a site (construction).

高機能クレーン9による大ブロック1の移送と積み付けは、高機能クレーン9の操作をリモコン操作によって行ってもよいが、プログラムにより自動で行うことが好ましい。また、移送までは、高機能クレーン9により自動で行い、移送された大ブロック1の積み付けは、高機能クレーン9のリモコン操作や手添えで行ってもよい。積み付けを高機能クレーン9のリモコン操作や手添えで行うと、より確実に積み付け精度を確保することができる。   The transfer and stacking of the large blocks 1 by the high-performance crane 9 may be performed by remote control operation of the high-performance crane 9, but is preferably performed automatically by a program. The transfer of the large blocks 1 may be automatically performed by the high-performance crane 9 and may be performed by remote control operation of the high-performance crane 9 or by hand. If the stacking is performed by remote control operation of the high-performance crane 9 or by hand, the stacking accuracy can be more reliably ensured.

また、大ブロック1は重量物がゆえに移送する際の取扱いが難しい。大ブロック化による最大効果である工期短縮のためには移送の高速化が好ましい。築炉は、高さ方向約15mのコークス炉を下から築造するため、積み付け位置での振れ止めや積み付けでの手添え(不安全作業)レス化が重要である。そのためには、大ブロック1の移送時や積み付け時において、大ブロック1を吊り下げた状態の高機能クレーン9の吊具と大ブロックとの合計の荷の重心9aGを制御して、大ブロック1を水平にし、積み付ける所定位置での残留振れを防止する。ここで、吊具と大ブロックとの合計の荷の重心9aGとは、大ブロック1を吊り下げた状態で、吊りビーム9bの上端から、大ブロック1の下端までの長さにおいて含まれるものを合計の荷とし、その合計の荷の重心を意味する。
残留振れを制御する(吊りビーム9b位置の残留振れを±50mm以下に収める)ためには、高機能クレーンがクラブトロリ式天井クレーンであり、クラブトロリ式天井クレーンの吊りビーム9bの上端から吊具と大ブロック1との合計の荷の重心9aGまでの長さL1(単位:m)と、高機能クレーン9のクラブ9cの吊りワイヤ保持部9caの中心から吊りビーム9bの上端までの長さL(単位:m)の関係が、以下の式(1)を満たすことが好ましい。
L1(m)≦L(m)×0.1+1.0 式(1)
Also, the large block 1 is difficult to handle when transported because of the heavy load. In order to shorten the construction period, which is the maximum effect of the large block, it is preferable to increase the transfer speed. Since a coke oven with a height of about 15 m is built from below, it is important to prevent steadying at the stacking position and to reduce the need for manual (unsafe work) in the stacking. For this purpose, when the large block 1 is transferred or loaded, the center of gravity 9aG of the total load of the hanging tool of the high-function crane 9 in a state where the large block 1 is suspended and the large block is controlled. 1 is leveled to prevent residual run-out at a predetermined position for stacking. Here, the center of gravity 9aG of the total load of the hanging tool and the large block is the one included in the length from the upper end of the hanging beam 9b to the lower end of the large block 1 in a state where the large block 1 is suspended. It is the total load and means the center of gravity of the total load.
In order to control the residual run-out (to keep the residual run-out at the position of the hanging beam 9b within ± 50 mm), a high-performance crane is a club trolley type overhead traveling crane. L1 (unit: m) up to the center of gravity 9aG of the total load of the load and the large block 1, and the length L from the center of the suspension wire holding portion 9ca of the club 9c of the high-performance crane 9 to the upper end of the suspension beam 9b. It is preferable that the relationship (unit: m) satisfies the following expression (1).
L1 (m) ≦ L (m) × 0.1 + 1.0 Equation (1)

約2万個の大ブロック1を積み付けることにより、50窯のコークス炉の築炉を行った。この50窯のコークス炉を、一チームが5窯ずつ、十チームで築炉を行った。各一チームはチームごとに、それぞれ、供給スペース6に移送された大ブロック1を、一つのコンベア7と、一つの高機能クレーン9を用いて、所定の場所に積み付けた。   By stacking about 20,000 large blocks 1, 50 coke ovens were built. The coke oven of 50 kilns was built by ten teams, ten by five. Each one team loaded the large block 1 transferred to the supply space 6 into a predetermined place using one conveyor 7 and one high-performance crane 9 for each team.

5窯を築炉する一チームが取り扱う、大ブロック1の実際の流れを図2により説明する。
供給スペース6には、コンベア操作者13と、下屋マン14が配置されている。供給スペース6に移送された大ブロック1は、コンベア7に敷いたパレット8の上に載置したまま移送される。一チームが使用する供給スペース6でストックできる大ブロック1は、この場合10個程度である。下屋マン14は、タグ1aをデータ端末12に読み取らせて、大ブロック1が所定の順序で供給されていることを確認して、大ブロック1を高機能クレーン9へ玉掛けするPB0点と移送させる。
下屋マン14は、PB0点で大ブロック1の玉掛けを行う。この時、高機能クレーン9の吊りビーム9bは、図示を省略しているが、PB0点に対応するPC0点にある。玉掛けが終わったら、高機能クレーン9の吊りビーム9bをPC0点からPC1点まで上昇することにより、大ブロック1をPB1点に吊り上げる。そして、下屋マン14は、PC1点から供給スペース6(下屋4)の縁PC2点まで高機能クレーン9を自動で移動させる。PC2点で、高機能クレーン9の操作は、下屋マン14から、築炉現場2の現場高さ(図2においては炉床盤20の高さ)にいるテレコンマン15の遠隔操作に交代する。下屋4の供給スペース6に下屋マン14を配置し、築炉現場2の現場高さにテレコンマン15を配置し、各々受け渡しつつ高機能クレーン9を操作させるのは、それぞれ近い位置で目視により動きを確認しつつ操作が可能であるからである。
The actual flow of the large block 1 handled by one team building five kilns will be described with reference to FIG.
In the supply space 6, a conveyor operator 13 and a shed man 14 are arranged. The large block 1 transferred to the supply space 6 is transferred while being placed on the pallet 8 spread on the conveyor 7. In this case, about 10 large blocks 1 can be stocked in the supply space 6 used by one team. The shed man 14 makes the data terminal 12 read the tag 1a, confirms that the large block 1 is supplied in a predetermined order, and transfers the large block 1 to the PB0 point where the large block 1 is slung on the high-performance crane 9 and transferred. Let it.
The shed man 14 slings the large block 1 at the point PB0. At this time, the suspension beam 9b of the high-performance crane 9 is at the PC0 point corresponding to the PB0 point, although not shown. When the slinging is completed, the large block 1 is lifted to the point PB1 by raising the hanging beam 9b of the high-function crane 9 from the point PC0 to the point PC1. Then, the shed man 14 automatically moves the high-function crane 9 from one point of PC to two points of edge PC of the supply space 6 (shed 4). At two PCs, the operation of the high-function crane 9 is changed from the underman 14 to the remote control of the telecon man 15 at the site height of the furnace construction site 2 (the height of the hearth 20 in FIG. 2). . It is visually observed that the man 14 is arranged in the supply space 6 of the car 4 and the tele-comman 15 is arranged at the height of the furnace construction site 2 and the high-performance crane 9 is operated while each is handed over. This is because the operation can be performed while checking the movement.

テレコンマン15は、遠隔操作により、PC2点からバックステイ21より炉内側のPC3点に移動させ、そこから高機能クレーン9の吊りビーム9bをPC4点に下ろす。このPC3点からすぐにPC4点に高機能クレーン9と吊り下げた大ブロック1を下すのは、安全のため、大ブロック1を高い場所で長距離移動させないためである。さらにテレコンマン15は、高機能クレーン9を、当該大ブロック1が積み付けられる所定の場所の上空の定位置PC5点に移動させる。PC1点からPC5点への移動は、下屋マン14やテレコンマン15が発する移動開始の命令を実行するだけの自動制御で行う。高機能クレーン9が予め大ブロック1のタグ1a内の情報に基づいたPC5点に到着したら、高機能クレーン9から積み付け完了の信号が所定の各部署に送信され、その大ブロック1の積み付け終了が確認されたとみなす。   The telecomman 15 is moved from the PC 2 point to the PC 3 point inside the furnace from the backstay 21 by remote control, and lowers the suspension beam 9b of the high-performance crane 9 from the PC 2 point to the PC 4 point. The reason why the high-function crane 9 and the large block 1 suspended from the three PCs are dropped immediately to the four PCs is to prevent the large block 1 from being moved for a long distance in a high place for safety. Further, the tele-comman 15 moves the high-functional crane 9 to five fixed positions PC above a predetermined location where the large block 1 is to be stacked. The movement from the PC 1 point to the PC 5 point is performed by automatic control that only executes a movement start command issued by the shed man 14 or the telecon man 15. When the high-functional crane 9 arrives at the five PCs based on the information in the tag 1a of the large block 1 in advance, a signal indicating the completion of the loading is transmitted from the high-functional crane 9 to predetermined sections, and the large block 1 is loaded. It is assumed that the termination has been confirmed.

PC5点からは、手動(手添え)によりPC6点、PC7点に位置を微調整し、予めモルタルが塗られた所定の場所に、大ブロック1を積み付ける。モルタルは所定の位置に機械で塗ることができる。この手動の微調整と積み付けは、テレコンマン15や、PC7点付近で待機している図示しない積み付け作業者が行う。
大ブロック1の積み付けが終了したら、手動で、高機能クレーン9をPC8点に移動させる。その後、PC8点の高機能クレーン9をテレコンマン15がPC9点を経てPC2点に戻し、高機能クレーン9の操作を下屋マン14に引き渡し、以降、同様の手順を繰り返す。PC8点からPC1点への移動は、下屋マン14やテレコンマン15が発する移動開始の命令を実行するだけの自動制御で行う。
From the five PCs, the positions are finely adjusted manually (manually) to the six PCs and the seven PCs, and the large block 1 is stacked in a predetermined place previously coated with mortar. The mortar can be machined in place. The manual fine adjustment and the stacking are performed by the tele-conman 15 or a stacking worker (not shown) waiting around seven PCs.
When the stacking of the large blocks 1 is completed, the high-function crane 9 is manually moved to eight PCs. After that, the tele-comman 15 returns the high-function crane 9 with eight PCs to the two PCs after nine points of PC, and hands over the operation of the high-function crane 9 to the lower man 14, and thereafter, the same procedure is repeated. The movement from the PC 8 point to the PC 1 point is performed by an automatic control that only executes a movement start command issued by the shelter man 14 or the telecon man 15.

このように築炉したことにより、従来、完成に6か月必要であったところが、2.5か月から3か月に工期を大幅に短縮することができた。   By constructing the furnace in this way, the construction period could be significantly reduced from 2.5 months to 3 months instead of 6 months conventionally required for completion.

本発明によれば、コークス炉の築炉において、多数の高度な築炉技術者に頼らず、高い精度で高速かつ安全に築炉することができるので、工期が短縮され、コストを低減させることができる。   ADVANTAGE OF THE INVENTION According to this invention, in the coke oven construction, since it is possible to construct the furnace with high accuracy and at high speed and safely without relying on a large number of advanced construction engineers, the construction period is shortened and the cost is reduced. Can be.

1…大ブロック
1a…タグ
2…築炉現場
3…上屋
4…下屋
5…置き場
6…供給スペース
7…コンベア
8…パレット
9…高機能クレーン
9a…吊具
9aG…吊具と大ブロックとの合計の荷の重心
9b…吊りビーム
9c…クラブ
9ca…吊りワイヤ保持部
9d…クレーンガーター
9e…水平出し装置
9ea…移動部
10…保管エリア
11…準備エリア
12…データ端末
13…コンベア操作者
14…下屋マン
15…テレコンマン
20…炉床盤
21…バックステイ
22…擁壁
23…押出機側プラットホーム
100…大ブロックの流れ
101…データの流れ
X…炉幅方向
Y…炉長方向
Z…炉高方向
DESCRIPTION OF SYMBOLS 1 ... Large block 1a ... Tag 2 ... Furnace construction site 3 ... Shed 4 ... Shed 5 ... Storage space 6 ... Supply space 7 ... Conveyor 8 ... Pallet 9 ... High-performance crane 9a ... Hanging tool 9aG ... Hanging tool and large block 9b ... hanging beam 9c ... club 9ca ... hanging wire holding part 9d ... crane garter 9e ... leveling device 9ea ... moving part 10 ... storage area 11 ... preparation area 12 ... data terminal 13 ... conveyor operator 14 ... Shitaya man 15 ... Telecon man 20 ... Heat floor 21 ... Backstay 22 ... Retaining wall 23 ... Extruder side platform 100 ... Large block flow 101 ... Data flow X ... Furnace width direction Y ... Furnace length direction Z ... Furnace height direction

Claims (3)

一つあたり20kg以上の耐火物の大ブロックを積み付けるコークス炉の築炉方法であって、
前記コークス炉の築炉現場の上に仮設の上屋が設けられ、
前記上屋には、前記大ブロックを移送し、築炉現場の所定の場所に積み付ける高機能クレーンが設けられ、
前記コークス炉の築炉現場に隣接する場所に仮設の下屋が設けられ、
前記下屋には、前記大ブロックの供給スペースが設けられ、
前記供給スペースには、前記供給スペースに移送された前記大ブロックを、築炉現場方向に移送するコンベアが設けられており、
前記供給スペースの床面は、前記コンベアの高さがコークス炉の築炉後の煉瓦積みの最高高さよりも高くなるように設けられており、
前記大ブロックの築炉現場方向への移送は、前記コンベアでパレットに載置して行い、
各々の大ブロックを構築すべき位置データ、および/または、大ブロックの形状データが記録されたタグを、当該大ブロック自体、または、その大ブロックを載置する前記パレットに付与しておき、
前記タグの記録が、読み取られて前記高機能クレーンへ送られ、
前記高機能クレーンは、前記記録に基づいて、前記パレットに載せた前記大ブロックを移送し、築炉現場の所定の場所に積み付けることを特徴とする
コークス炉の築炉方法。
A method of building a coke oven in which large blocks of refractories of 20 kg or more are stacked,
A temporary shed is provided on the coke oven site,
The shed is provided with a high-performance crane that transfers the large block and loads it at a predetermined location on the furnace construction site,
A temporary shed is provided at a location adjacent to the coke oven site,
The lower building is provided with a supply space for the large block,
In the supply space, a conveyor for transferring the large block transferred to the supply space in a furnace construction site direction is provided,
The floor surface of the supply space is provided so that the height of the conveyor is higher than the maximum height of brickwork after the coke oven,
Transfer of the large block toward the furnace construction site is performed by placing it on a pallet with the conveyor,
The position data at which each large block is to be constructed and / or the tag in which the shape data of the large block is recorded are given to the large block itself or the pallet on which the large block is placed,
The record of the tag is read and sent to the intelligent crane,
The high-function crane transfers the large block placed on the pallet based on the record and loads the large block at a predetermined location on a furnace-building site.
前記高機能クレーンによる前記大ブロックの移送は自動で行い、前記移送された前記大ブロックの積み付けは、前記高機能クレーンにより自動で行うか、前記高機能クレーンのリモコン操作、または手添えで行うことを特徴とする請求項1に記載のコークス炉の築炉方法。   The transfer of the large blocks by the high-performance crane is performed automatically, and the loading of the transferred large blocks is performed automatically by the high-performance crane, by remote control of the high-performance crane, or by hand. The method for building a coke oven according to claim 1, wherein: 前記高機能クレーンがクラブトロリ式天井クレーンであり、前記クラブトロリ式天井クレーンの吊りビームの上端から、吊具と大ブロックとの合計の荷の重心までの長さL1(m)と、前記クラブトロリ式天井クレーンの吊りワイヤ保持部の中心から前記吊りビームの上端までの長さL(m)の関係が、以下の式(1)を満たしながら大ブロックを移送、積み付けることを特徴とする請求項1または請求項2に記載のコークス炉の築炉方法。
L1(m)≦L(m)×0.1+1.0 式(1)
The high-performance crane is a club trolley type overhead traveling crane, and a length L1 (m) from an upper end of a suspension beam of the club trolley type overhead traveling crane to a center of gravity of a total load of a lifting tool and a large block; The large blocks are transferred and stacked while the relationship of the length L (m) from the center of the suspension wire holding portion of the trolley type overhead traveling crane to the upper end of the suspension beam satisfies the following expression (1). The method for building a coke oven according to claim 1 or 2.
L1 (m) ≦ L (m) × 0.1 + 1.0 Equation (1)
JP2018114357A 2018-06-15 2018-06-15 How to build a coke oven Active JP7006521B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018114357A JP7006521B2 (en) 2018-06-15 2018-06-15 How to build a coke oven

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018114357A JP7006521B2 (en) 2018-06-15 2018-06-15 How to build a coke oven

Publications (2)

Publication Number Publication Date
JP2019218421A true JP2019218421A (en) 2019-12-26
JP7006521B2 JP7006521B2 (en) 2022-01-24

Family

ID=69095667

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018114357A Active JP7006521B2 (en) 2018-06-15 2018-06-15 How to build a coke oven

Country Status (1)

Country Link
JP (1) JP7006521B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113150797A (en) * 2021-05-20 2021-07-23 中冶焦耐(大连)工程技术有限公司 Process method and system for mechanically building coke oven
JP2022012552A (en) * 2020-07-01 2022-01-17 Jfeスチール株式会社 Furnace construction method and spacer selection method
WO2024077844A1 (en) * 2022-10-13 2024-04-18 中国五冶集团有限公司 6s flat-layer building method for large coke oven body

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10212511A (en) * 1997-01-29 1998-08-11 Sumitomo Metal Ind Ltd Method for laying brick on furnace bottom of blast furnace
JP2015010128A (en) * 2013-06-27 2015-01-19 Jfeスチール株式会社 Temporary shed for construction of coke oven and method of constructing coke oven
JP2017137444A (en) * 2016-02-05 2017-08-10 株式会社メガテック Carriage on furnace carrying module block for repairing coke oven

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10212511A (en) * 1997-01-29 1998-08-11 Sumitomo Metal Ind Ltd Method for laying brick on furnace bottom of blast furnace
JP2015010128A (en) * 2013-06-27 2015-01-19 Jfeスチール株式会社 Temporary shed for construction of coke oven and method of constructing coke oven
JP2017137444A (en) * 2016-02-05 2017-08-10 株式会社メガテック Carriage on furnace carrying module block for repairing coke oven

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022012552A (en) * 2020-07-01 2022-01-17 Jfeスチール株式会社 Furnace construction method and spacer selection method
JP7259810B2 (en) 2020-07-01 2023-04-18 Jfeスチール株式会社 Furnace construction method and spacer selection method
CN113150797A (en) * 2021-05-20 2021-07-23 中冶焦耐(大连)工程技术有限公司 Process method and system for mechanically building coke oven
WO2024077844A1 (en) * 2022-10-13 2024-04-18 中国五冶集团有限公司 6s flat-layer building method for large coke oven body

Also Published As

Publication number Publication date
JP7006521B2 (en) 2022-01-24

Similar Documents

Publication Publication Date Title
KR102122191B1 (en) Method for building coke oven
JP7006521B2 (en) How to build a coke oven
US20130295511A1 (en) Mobile furnace system
JP6304182B2 (en) Standard refractory measuring method and fixed refractory measuring device
JP6844332B2 (en) Construction method of the top of the chamber-type coke oven and the structure of the top of the chamber-type coke oven
JPH05229651A (en) Device for conveying brick for construction work of hot blast stove
JP6665905B2 (en) Coke oven fixed refractory loading method and fixed refractory supply device
JP7259810B2 (en) Furnace construction method and spacer selection method
JP7235025B2 (en) Modular block manufacturing method, furnace construction method, and measurement system
JP6593420B2 (en) Standard refractory stacking method and fixed refractory stacking system
JP7371668B2 (en) Furnace construction method
JPH1046216A (en) Method for laying furnace bottom brick in blast furnace
JPH11152513A (en) Brick laying method in converter and brick-laying device for converter
JP3199439B2 (en) Batch holding device for tubular thermal storage bricks and construction method of thermal storage room
JP7322825B2 (en) Module block manufacturing method and furnace construction method
JP7363841B2 (en) Module block shape measurement method, module block shape measurement system, and furnace construction method
JP6683227B2 (en) Coke oven standard refractory loading method
CN117586795A (en) Intelligent masonry system and method for coke oven
JPH07246582A (en) Instruction method of handling robot in refractory manufacturing equipment
Johansson Bricklaying robot for installation ofrefractory material in grate-kiln systems
JPS6032100Y2 (en) Bedding material placement device
JP2022012554A (en) Furnace construction method
JPH0527467Y2 (en)
JP2019112503A (en) Method of constructing coke oven of chamber oven type, and refractory structure of coke oven of chamber oven type
CS276458B6 (en) Process of a rotary-drum furnace bricklaying

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210203

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211210

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211220