EP2829467B1 - Vessel for transporting compressed gas - Google Patents

Vessel for transporting compressed gas Download PDF

Info

Publication number
EP2829467B1
EP2829467B1 EP12872093.5A EP12872093A EP2829467B1 EP 2829467 B1 EP2829467 B1 EP 2829467B1 EP 12872093 A EP12872093 A EP 12872093A EP 2829467 B1 EP2829467 B1 EP 2829467B1
Authority
EP
European Patent Office
Prior art keywords
gas
containers
pipeline
cells
vessel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP12872093.5A
Other languages
German (de)
English (en)
French (fr)
Other versions
EP2829467A4 (en
EP2829467A1 (en
Inventor
El-Said Khassan AKHMED MIAVAD
Abdul Karim HAMDO
Valeriy MOROZOV
Oleksiy SHUSTYK
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of EP2829467A1 publication Critical patent/EP2829467A1/en
Publication of EP2829467A4 publication Critical patent/EP2829467A4/en
Application granted granted Critical
Publication of EP2829467B1 publication Critical patent/EP2829467B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B11/00Interior subdivision of hulls
    • B63B11/02Arrangement of bulkheads, e.g. defining cargo spaces
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B17/00Vessels parts, details, or accessories, not otherwise provided for
    • B63B17/0027Tanks for fuel or the like ; Accessories therefor, e.g. tank filler caps
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B25/00Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
    • B63B25/02Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods
    • B63B25/08Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods fluid
    • B63B25/12Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods fluid closed
    • B63B25/14Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods fluid closed pressurised
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C13/00Details of vessels or of the filling or discharging of vessels
    • F17C13/08Mounting arrangements for vessels
    • F17C13/082Mounting arrangements for vessels for large sea-borne storage vessels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B25/00Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
    • B63B25/02Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods
    • B63B25/08Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods fluid
    • B63B2025/087Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods fluid comprising self-contained tanks installed in the ship structure as separate units
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/01Shape
    • F17C2201/0104Shape cylindrical
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/03Orientation
    • F17C2201/035Orientation with substantially horizontal main axis
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/05Size
    • F17C2201/054Size medium (>1 m3)
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2203/00Vessel construction, in particular walls or details thereof
    • F17C2203/06Materials for walls or layers thereof; Properties or structures of walls or their materials
    • F17C2203/0602Wall structures; Special features thereof
    • F17C2203/0612Wall structures
    • F17C2203/0614Single wall
    • F17C2203/0617Single wall with one layer
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/01Mounting arrangements
    • F17C2205/0123Mounting arrangements characterised by number of vessels
    • F17C2205/013Two or more vessels
    • F17C2205/0134Two or more vessels characterised by the presence of fluid connection between vessels
    • F17C2205/0142Two or more vessels characterised by the presence of fluid connection between vessels bundled in parallel
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/01Mounting arrangements
    • F17C2205/0123Mounting arrangements characterised by number of vessels
    • F17C2205/013Two or more vessels
    • F17C2205/0134Two or more vessels characterised by the presence of fluid connection between vessels
    • F17C2205/0146Two or more vessels characterised by the presence of fluid connection between vessels with details of the manifold
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/03Fluid connections, filters, valves, closure means or other attachments
    • F17C2205/0302Fittings, valves, filters, or components in connection with the gas storage device
    • F17C2205/0323Valves
    • F17C2205/0326Valves electrically actuated
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/03Fluid connections, filters, valves, closure means or other attachments
    • F17C2205/0302Fittings, valves, filters, or components in connection with the gas storage device
    • F17C2205/0323Valves
    • F17C2205/0332Safety valves or pressure relief valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/03Fluid connections, filters, valves, closure means or other attachments
    • F17C2205/0302Fittings, valves, filters, or components in connection with the gas storage device
    • F17C2205/0323Valves
    • F17C2205/0335Check-valves or non-return valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2221/00Handled fluid, in particular type of fluid
    • F17C2221/03Mixtures
    • F17C2221/032Hydrocarbons
    • F17C2221/033Methane, e.g. natural gas, CNG, LNG, GNL, GNC, PLNG
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/01Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the phase
    • F17C2223/0107Single phase
    • F17C2223/0123Single phase gaseous, e.g. CNG, GNC
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/03Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the pressure level
    • F17C2223/035High pressure (>10 bar)
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2270/00Applications
    • F17C2270/01Applications for fluid transport or storage
    • F17C2270/0102Applications for fluid transport or storage on or in the water
    • F17C2270/0105Ships

Definitions

  • This invention relates to the design of vessels and their equipment and systems for compressed gas transportation from production fields to the specified place.
  • the cylinders are equipped with the pipeline with the valve system for interconnection of cylinders' chambers of the indicated compartment separated by the elastic partition between each other and with the shipboard gas pipeline.
  • the cylinders are equipped with the pipeline with the valve system for interconnection of cylinders' chambers of the other compartment separated by the elastic partition and with the pressure source, which is made in the form of a source of compressed air.
  • the chambers of shipboard hermetic compartments for storage of high pressure cylinders with compressed gas are interconnected with the pipeline through the valve system and with the shipboard gas pipeline.
  • the vessel for transportation of compressed gas which is equipped with the source of cold, connected to the pipeline through the valve system, and the heat exchanger with the chambers of the shipboard hermetic compartments.
  • the design drawback of the known vessel is a large size of the containers for compressed gas, which does not allow to unload containers at the ports and to deliver them to the consumer, so only a gas loading through the pipeline to the port external storage facilities is possible. Either the use of onshore main pipelines to the specified place or pumping compressed or liquid gas into the containers for transportation by other types of transport are required for further gas transfer to the customers.
  • the fact, that containers have a large size does not allow to transport gas under pressure more than 100 kg/sq cm, which limits the amount of gas transported by the vessel and needs constant cooling of the containers for maintaining gas parameters close to the gas critical state.
  • Compartments are also equipped with tanks for condensate accumulation.
  • Chambers of shipboard hermetic compartments are connected with pipelines through a system of valves, a compressor and a heat exchanger are connected with a source of cold, which the ship is equipped with.
  • the same manifolds of gas reservoirs and shipboard hermetic compartments are interconnected respectively with each other through a system of valves by corresponding pipelines, providing that pipelines of hermetic compartments and pipelines of compressed gas uploading and offloading manifolds are connected to the main shipboard gas pipeline through a system of valves.
  • the pipeline of condensate accumulation manifolds is configured with the ability to be connected to the condensate accumulation tank.
  • the vessel is equipped with a pump for transmission of condensate accumulated in the manifolds into the condensate accumulation tank.
  • the condensate accumulation tank can be located both on board of the ship and on the onshore or sea terminals.
  • the vessel for transportation of compressed gas is equipped with the main shipboard gas pipeline comprising means of connection with onshore or sea terminals, hermetic compartments for compressed gas storage, each of which has a gas tank designed in the form of a stack of pipes with different diameter, which are arranged at an angle to the horizon and connected by means of common manifolds at both ends.
  • uploading and offloading manifolds for compressed gas are arranged on ascending end of the pipelines and manifolds for condensate accumulation, which is produced in the pipes during the compressed gas transportation, are arranged on descending end of the pipelines.
  • Compartments are also provided with tanks for condensate accumulation.
  • the pipelines of smaller diameter in stacks are arranged in the spaces, which were created between pipelines of the bigger diameter, as well as between the pipelines of the bigger diameter and the walls of hermetic compartment.
  • the cavities shipboard hermetic compartments are connected through a system of valves, a compressor and a heat exchanger are connected with a source of cold, which ship is equipped with.
  • the same manifolds of gas reservoirs and shipboard hermetic compartments are interconnected respectively with each other through a system of valves by corresponding pipelines and, providing that pipelines of hermetic compartments and pipelines of compressed gas uploading and offloading manifolds are connected to the main shipboard gas pipeline through a system of valves.
  • the pipeline of condensate accumulation manifolds is configured with the ability to be connected to the condensate accumulation tank.
  • the vessel is equipped with a pump for transmission of condensate accumulated in the manifolds into the condensate accumulation tank.
  • the condensate accumulation tank can be located both on board of the ship and on the onshore or sea terminals.
  • the design drawback of the known vessel is a large size the of the cylinders for compressed gas and the fact that they are made of steel and constructed for assembly inside the hold of the vessel, that does not allow to unload containers at the ports and to deliver them to the consumer, so only a gas loading through the pipeline to the port external storage facilities is possible.
  • Either the use of onshore main pipelines to the specified place or pumping compressed or liquid gas into the containers for transportation by other types of transport are required for further gas transfer to the customers.
  • the fact, that containers have a non-optimal form and a large size does not allow to transport gas under pressure more than 100 kg/sq cm, which limits the amount of gas transported by the vessel.
  • a system for compressed gas transportation comprises a vessel, compartments for compressed gas storage, which design and arrangement ensure ship transportation and each of which is equipped with interconnected gas tanks, high and low pressure pipelines, both including means for connection with onshore terminals, means of circulating connection of each compartment for compressed gas storage with every pipeline of high and low pressure, and valves for selective control of compressed gas flow between every, compartment for compressed gas storage and every pipelines of high and low pressure.
  • each compartment for compressed gas storage is configured with the ability of selective flow connection to every pipeline of high and low pressure.
  • the vessel has cargo holds, which are equipped with vertical gas tanks.
  • the system includes a hermetic hatch cover for each cargo hold and means for inert gas supply into each cargo hold and each cargo hold is arranged so that it can be filled with the inert media from the said inert gas.
  • cargo holds and actually hermetic hatch covers are thermally insulated.
  • the system may comprise additional equipment for detection of gas leaks and means of compressed gas release into the atmosphere from the leaking gas storage compartment.
  • the system may comprise a flare device in addition to the means of compressed gas release into the atmosphere from the leaking gas storage compartment.
  • the system comprises onshore equipment, which contains a compressor.
  • system may comprise the onshore terminal for exporting compressed gas from the ship, which contains a cryogenic unit for conversion of a compressed gas part exported from the ship into the liquefied gas.
  • the system may comprise the onshore terminal for compressed gas export from ship by high and low pressure pipelines and for supply of the said compressed gas into the gas transit pipeline.
  • the onshore terminal includes a discharging compressor for gas compressing, which is produced from the low pressure pipeline before its supply from the low pressure pipe into the gas transfer pipeline.
  • the high pressure pipeline, the low pressure pipeline and the discharging compressor are designed and arranged with providing a substantially complete discharge of the ship for about 8 hours.
  • each gas tank may contain compressed gas at pressure from about 70.3 kg/sq cm (1000 pound / square inch) to about 351.6 kg/sq cm (5000 pound / square inch).
  • each compartment for compressed gas storage comprises at least three and no more than thirty gas tanks.
  • gas tanks are made of welded pipes of mild steel with welded dome-shaped lids at both ends.
  • the system in which the said gas is natural gas.
  • this ensures the adiabatic expansion of compressed gas during ship offloading, when the adiabatic expansion of compressed gas is used to cool the gas tank and keep these tanks in a refrigerated state until they are filled with compressed gas next time.
  • An additional compressor for conversion of a compressed gas part into liquefied natural gas and means of liquefied natural gas storage are also used in the onshore equipment, as well as a part of compressed gas from the high pressure pipeline is supplied to activate the additional compressor. Natural gas is used as compressed gas and liquefied natural gas is used as liquefied gas.
  • the vessel for transportation of compressed gas includes cargo holds with tanks for storing gas during transportation located in said cargo holds equipped with pipelines, signaling sensors, shutoff fittings and a connecting fittings, and compressors.
  • the design drawback of the said vessel is a large size of cylinders for compressed gas, designed for vertical storage, that does not allow to unload containers at the ports and to deliver them to the consumer, so only a gas loading through the pipeline to the port external storage facilities is possible.
  • the aim of the invention is to create a design of a vessel for transporting compressed gas, which allows not only to receive, control, charge and discharge gas through the vessel's pipeline systems, but also to charge and discharge gas at the container terminals, ensuring gas container transportation to the specified places by shallow-draft vessels on the rivers and also by road or railway transport, without additional process steps and extra energy costs at the ambient temperature; to simplify repair or replacement of gas tanks; to ensure quick and technologically simple conversion of cellular container vessels for transporting compressed gas.
  • Essential distinguishing characteristic are that the hull of the vessel is divided into cells with vertical guides, at least one bulkhead is impermeable to water and gas, standard containers are stacked in cell guides one on one with compressed gas tanks horizontally placed in them and connected to the shipboard compressed gas loading system.
  • the hull of the vessel is divided into cells so, that in the zone of at least one bulkhead delimiting the cell a distance from 0.8 to 2 metres is ensured and there are compressed gas distribution manifolds, pipelines with shut-off valves, a compressor, an emergency monitoring and control equipment in this space.
  • Each double-jointed sell is locked by one jointed hatch cover which is impermeable to water and gas and separated by water- and airtight bulkheads from other pairs of cells.
  • At least one container with empty dump tank is placed in each double-jointed compartment, with the ability to drain condensate or gas excess in the cargo containers into it, providing that dump tanks are connected through the safety valves and pipelines are brought out to the upper deck to the excess gas burner.
  • Each tank is connected through a shut-off valve to the collector with a flexible pipeline or an expansion bellows and the manifold is arranged between the ends of containers of the parts of double-jointed cells and connected by the pipeline through a shut-off valve and through the emergency equipment with the compressor.
  • the pipeline is brought out into the upper deck from each double-jointed cells manifold and has the connecting fittings adjustable to external gas storage and pipeline fittings connected to other double-jointed cells.
  • the compressor connection system provides the bypass by the pipeline with shut-off valves enabling to transmit gas under pressure by gravity.
  • the containers are connected between each other by traversing container locks or centering cones and ties.
  • Cylindrical tanks made of composite materials are placed in the containers in horizontal position, each one having at least one connection pipe, shut-off and safety valves, pressure and temperature sensors, as well as a condensate detection sensor and a condensate drain pipe connection.
  • Outlet connection pipe is arranged on both ends of each tank.
  • Containers are standard 40 feet shipboard containers with external dimensions: length of 12192 mm, width of 2438 mm and height of 2591 mm.
  • Each individual cell or group of cells is closed on top by a hatch cover that is impermeable to water.
  • Each individual cell or group of cells is closed on top by a removable deckhead cladding.
  • the ship hull is divided into cells with vertical cell guides, at least one bulkhead is impermeable to water and gas, standard containers are stacked in cell guides one on one with compressed gas tanks horizontally placed in them and connected to the shipboard compressed gas loading system.
  • the hull of the vessel is divided into cells in such a way, that in the zone of at least one bulkhead delimiting the cell a distance from 0.8 to 2 metres is ensured, and there are compressed gas distribution manifolds, pipelines with shut-off valves, a compressor, emergency monitoring and control equipment in this space.
  • At least one container with empty dump tank is arranged at each double-jointed cell, with the ability to reset condensate in it or gas excess in the cargo tanks and the dump tank are connected through the safety valves and brought out to the upper deck piping to the gas combustion device.
  • Each tank is connected through a shut-off valve to the manifold by a flexible pipeline or by an expansion bellows and the manifold is arranged between the ends of container double-jointed cells and connected with pipeline through a shut-off valve and pressure relief equipment to the compressor and pipeline is arranged into the upper deck from the manifold of each double-jointed cell and has the connecting fitting with to the external gas storage pipeline and connecting fittings with another double-jointed cell.
  • the compressor connection system provides the bypass of the pipeline with shut-off valves enabling to transmit gas under pressure by gravity.
  • the containers are connected between each other by traversing container locks or centering cones and ties.
  • Cylindrical tanks made of composite materials are arranged in the containers horizontally, each one having at least one connection pipe, shut-off and safety valves, pressure and temperature sensors, as well as a condensate detection sensor and a condensate drain connection.
  • Outlet connection pipe is arranged on both ends of each tank.
  • Containers are standard 40 feet shipboard containers with external dimensions: length of 12192 mm, width of 2438 mm and height of 2591 mm.
  • Each individual cell or group of cells is closed on top by a hatch cover impermeable to water.
  • Each individual cell or group of cells is closed on top by a removable deckhead cladding.
  • containers are connected to the compressed gas loading shipboard system and that the hull of the vessel is divided into cells, so that there is at least one cell bulkhead between them, with ensured distance from 0.8 to 2 metres, and there are compressed gas distribution manifolds between them, pipelines with shut-off valves, a compressor, emergency monitoring and control equipment, allowed to reduce the length of the pipeline and to increase work safety.
  • the vessel for transporting compressed gas comprises of a hull of the vessel 1, divided into double-jointed cells 2 with vertical cell guides 3, longitudinal 4 and transverse bulkheads 5 and also containers partitions arranged between the tiers inside the cells 2, of double-jointed type, not closed, of truss type structure or closed ones which are impermeable to water and gas 6, the distance between them is 1.8 meters.
  • Double transverse bulkheads which are impermeable to water and gas 7 with intermediate size of 0.8 meters are separating forage compartments 2 from the engine room 8 and the lower tiers of the deckhouse 9 and double-jointed transverse bulkheads which are impermeable to water and gas 10 are arranged between the compartment 11 and cells 2, which are the closest to the shipboard bow.
  • Compressed gas distribution manifolds 12 of compressed gas overload shipboard system are located between double-jointed bulkheads 6.
  • Each double-jointed cell 2 is closed by one jointed hatch cover 13 and is separated from other cells by bulkheads 4 and 5, which are impermeable to water and gas.
  • Containers 15 are installed in vertical cell guides 3 and connected between each other with quick-turning container stoppers 14, where cylindrical tanks 16 made of composite materials with spherical end parts are arranged horizontally.
  • Containers 15 are located in three vertical cell guides 3 of their cell with the ends towards containers 15 of the other part of the double-jointed cell 2, and a common manifold 12 is placed between them at the bulkhead 6.
  • the connection pipes 17 are arranged on each tank on the ends providing the described arrangement of the containers, a set cap 18 is located on one of them and a shut-off valve 19 is connected to another.
  • the safety valve 20, the pressure sensor 21, the temperature sensor 22 and the condensate detection sensor 23 are also placed on tanks 16 and condensate pipe connections 24 are mounted in the bottom of tanks 16, where shut-off valves 25 are located.
  • containers 15 are standard shipboard 40 feet containers having external dimensions as follows: length of 12 192 mm, width of 2438 mm and height of 2591 mm. Such containers are suitable for further transportation by shallow-draft vessels on the rivers as well as by road and railway transport, but one may use other standard containers of new sizes.
  • Tanks 16 of containers 15 are connected through their shut-off valve 19 by the flexible pipeline 26 with the manifold 12, which consists of vertically oriented pipes 27 with shut-off valves 28. Pipes 27 are interconnected by a locking pipeline 29 with shut-off valves 30.
  • the manifold which is placed between the tiers in the cells, allows reducing the length of pipes and simplifying maintenance and management of gas loading system.
  • the manifold system 12 also includes the pipeline 31, which is connected through the shut-off valve 32 to manifold pipes 12 and through the shut-off valve 33 to the compressor and, as a result, through the connecting device 44 to external storage facilities.
  • Manifold pipes 12 are connected through shut-off valves 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, to the connection unit 44 and to the pipeline of external gas storage.
  • the shut-off valve 45 and the gas meter 46 are also installed.
  • the manifold pipe system of each cells pair 2 is connected to the connecting pipeline 47 laid on the upper deck with shut-off valves 48.
  • Each double-jointed cell 2 mentioned in the described manifold system 12, has the compressor 49, which is connected to the pipe 31 through the shut-off valve 36 and the pipe 27 through the shut-off valve 35 and the safety valve 50.
  • the compressor 49 is bypassed by the pipeline with shut-off valves 38, 37, 34, 39, 40, 49, and by shut-off valves 36 and 35 at its inlet and outlet.
  • connection unit 44 and the compressor 49 are installed in the hermetic stowed position and in the intensively ventilated area 51, which is established at the level of the upper deck in the area of the manifolds 12 location, in each double-jointed cell 2 along the length of the ship.
  • Cells 11 are not connected to the general compressed gas loading system and are used for other gases that are by-products, such as helium, while the main gas for transportation is methane.
  • Each double-jointed cell 2 has two containers 52 with the empty dump tank 53, with the ability to drain condensate or gas excess in the cargo tanks 16 into it, providing that dump tanks 53 are connected through their safety valves 54 and pipelines are brought out to the upper deck to the gas combustion device 55.
  • the condensate collector and drain system includes shut-off valves 25, mounted in the lower part of containers 16, which are connected through flexible pipelines 56 and shut-off valves 57 with vertical pipes 58, interconnected by switchers 59 with each other and connected to the separate pump 60.
  • the hatch cover availability makes possible to use the vessel according to the invention, both in gas uploading and offloading mode through the gas loading shipboard system or to load it with containers filled with gas tanks or offload filled containers at the container terminal and deliver gas by other means of transport.
  • deckhead cladding panels can be provided at the deckhouse 61 that are installed at the coaming, welded and contain constructive elements that can be cut in case of repair and access to some cell.
  • shut-off valves and manifold outlet pipelines 12 are covered with heat-carrying medium.
  • the system is not shown herein, as it is known to the experts and is not the subject of the invention.
  • Rotatable container locks allow loading spreader at the container terminal to install automatically or unload containers from the ship.
  • Fixing container 15 by centering cones and ties are more suitable for gas uploading and offloading through the shipboard system.
  • Gas uploading and offloading is produced both by gravity and by compressor gas supply according to the differential pressure.
  • Receiving devices 44 are connected to the gas storage outer pipeline at the production field, and as empty tanks 16 are under residual pressure of 1 kg/cm 2 gas is taken from the external gas storage under pressure above 100 kg/cm 2 through the open shut-off valves 41, 38, 37, 34 and manifolds 12 of each cell 2, and gas enters from manifolds 12 through the open shut-off valves 28 and 19 to tanks 16 of containers 15. In this case shut-off valves 48, 42, 43, 40, 36, 35, 33, 32 are closed.
  • shut-off valves 42 and 48 are opened additionally and gas is supplied into other double-jointed cell 2, in which the shut-off valve 38 is closed and gas enters the tank 16 through the shut-off valve 42 and other ones above mentioned for the first cell (see Fig. 5 , which shows a part of the loading system of another double-jointed cell 2).
  • shut-off valves 42, 38 and 37 are closing in the cells loading system, which is connected to the external pipeline by the unit 44, and shut-off valves 39, 40, 36, 35 are opening and gas is supplied by the compressor 49 and continues to flow until reaching the specified pressure in tanks 16.
  • the compressor 49 is off
  • shut-off valves 40, 36 are closing
  • shut-off valves 39, 43 are opening and gas is supplied to tanks of the double-jointed cell on the left, and if it is required to supply gas to the right (see Figure 5 ), then the shut-off valve 48 is opening.
  • shut-off valves 43, 40, 36, compressor 49 of this cell and shut-off valves 35 and 34 which are described above, manifold valves 12 are similar to the Figure .5 .
  • junction points with the pipes of the manifold 12 are denoted with letters A and B.
  • shut-off valve 45 is opening and gas counter 46 starts to work, but pressure control enables to estimate gas quantity without the counter.
  • the system allows redistributing gas between tanks in case of incomplete vessel loading and tanks being in emergency state in any of the cells.
  • Condensate can be removed from the tanks by using the gas pressure in tanks both before gas uploading and on the beginning of uploading or by the additional pump 60.
  • shut-off valves in order to explain the vessel's design and schemes of the loading, control and storage system for transportation of compressed gas, without specifying the type and the drive, but the latter is a well known electrical, hydraulic and pneumatic remote control of all types of valves in engineering, which is not described in the claim, as it is not the subject of invention.
  • Specialists and engineers of automation control are able to develop remote control systems of shut-off valves and compressors using programmable controllers connected to sensors of pressure, temperature and by switching on the operation modes for specified programs.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
EP12872093.5A 2012-03-19 2012-12-14 Vessel for transporting compressed gas Active EP2829467B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
UAA201203198A UA101584C2 (ru) 2012-03-19 2012-03-19 Судно для транспортировки сжатого газа
PCT/UA2012/000112 WO2013141828A1 (ru) 2012-03-19 2012-12-14 Судно для транспортировки сжатого газа

Publications (3)

Publication Number Publication Date
EP2829467A1 EP2829467A1 (en) 2015-01-28
EP2829467A4 EP2829467A4 (en) 2016-01-13
EP2829467B1 true EP2829467B1 (en) 2016-06-22

Family

ID=56404841

Family Applications (1)

Application Number Title Priority Date Filing Date
EP12872093.5A Active EP2829467B1 (en) 2012-03-19 2012-12-14 Vessel for transporting compressed gas

Country Status (5)

Country Link
EP (1) EP2829467B1 (zh)
CN (1) CN104379440B (zh)
RU (1) RU2589811C2 (zh)
UA (1) UA101584C2 (zh)
WO (1) WO2013141828A1 (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105953068B (zh) * 2016-05-20 2019-04-09 蓬莱中柏京鲁船业有限公司 一种压缩天然气运输船及其改装方法
CN109398602B (zh) * 2017-08-15 2021-09-10 上海船厂船舶有限公司 用于钻井船的高压空气瓶组件的安装方法
CN110642217A (zh) * 2019-07-01 2020-01-03 Amg能源新加坡私人有限公司 Lng运输和配送的系统和方法
CN110878909B (zh) * 2019-11-25 2024-02-20 江苏国富氢能技术装备股份有限公司 一种高压氢气瓶组集装结构
JP7499147B2 (ja) * 2020-10-27 2024-06-13 住友重機械マリンエンジニアリング株式会社 船舶
EP4259518A1 (en) * 2020-12-11 2023-10-18 Global Hydrogen Ventures Pty Ltd Apparatus for gas storage and transport
GB2613374B (en) 2021-12-01 2024-06-26 Subsea 7 Norway As Subsea hydrogen storage system
CN114493323A (zh) * 2022-02-11 2022-05-13 内蒙古中科装备有限公司 储氢容器的紧急吹扫方法、系统及介质

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2135575B1 (zh) * 1971-05-05 1973-07-13 Liquid Gas Anlagen Union
DE2253023C3 (de) * 1972-10-28 1979-06-07 Liquid Gas International Gmbh, 5480 Remagen Batterietank für drucklose oder unter Druck stehende Flüssigkeiten, vornehmlich verflüssigte Gase, insbesondere für den Transport von Flüssiggas auf Schiffen
DE2337673A1 (de) * 1973-07-25 1975-02-06 Dieter Fischer Schwimmfaehige transporteinrichtung fuer unter druck stehendes erdgas
US5839383A (en) * 1995-10-30 1998-11-24 Enron Lng Development Corp. Ship based gas transport system
BR9607554A (pt) * 1995-10-30 1998-07-07 Enron Lng Dev Corp Sistema baseado em navio para transporte de gás natural comprimido
TW396253B (en) * 1997-06-20 2000-07-01 Exxon Production Research Co Improved system for processing, storing, and transporting liquefied natural gas
RU2299151C1 (ru) 2005-09-22 2007-05-20 Общество с ограниченной ответственностью "Инжиниринг, технический анализ, разработки и исследования" Судно для транспортировки сжатого газа
RU2300480C1 (ru) * 2005-09-22 2007-06-10 Общество с ограниченной ответственностью "Инжиниринг, технический анализ, разработки и исследования" Судно для транспортировки сжатого газа (варианты)
CN201395358Y (zh) * 2009-04-10 2010-02-03 荆门宏图特种飞行器制造有限公司 一种压缩天然气集装箱
CN201462388U (zh) * 2009-05-28 2010-05-12 荆门宏图特种飞行器制造有限公司 油田伴生气或压缩天然气罐式集装箱

Also Published As

Publication number Publication date
CN104379440B (zh) 2017-02-22
RU2589811C2 (ru) 2016-07-10
EP2829467A4 (en) 2016-01-13
CN104379440A (zh) 2015-02-25
UA101584C2 (ru) 2013-04-10
WO2013141828A1 (ru) 2013-09-26
RU2014141807A (ru) 2016-05-10
EP2829467A1 (en) 2015-01-28

Similar Documents

Publication Publication Date Title
EP2829467B1 (en) Vessel for transporting compressed gas
KR100458142B1 (ko) 압축천연가스운반용선박기초시스템
EP0946387B1 (en) Ship based gas transport system
EP1322518B1 (en) Methods and apparatus for compressed gas
ES2952648T3 (es) Sistema y método para carga, almacenamiento y descarga de gas natural de buques
MXPA97002712A (en) System based on boat for transport of natural gas comprim
EP2228294A1 (en) Vessel for transport of liquefied natural gas
CN110505977B (zh) 压缩天然气存储和运输系统
KR20140111668A (ko) 압축 천연 가스를 모듈 내에 조합된 검사가능 원통형 컨테이너 내에 격납하고 수송하기 위한 시스템
WO2014086413A1 (en) Integrated and improved system for sea transportation of compressed natural gas in vessels, including multiple treatment steps for lowering the temperature of the combined cooling and chilling type
AU6658000A (en) Natural gas composition transport system and method
SK50562016U1 (sk) Komplexný prepravný a skladovací systém dodávok LNG v logistickom reťazci LNG riečnej prepravy
SK50232016A3 (sk) Komplexný prepravný a skladovací systém dodávok LNG v logistickom reťazci LNG riečnej prepravy

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20141013

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

DAX Request for extension of the european patent (deleted)
RA4 Supplementary search report drawn up and despatched (corrected)

Effective date: 20151216

RIC1 Information provided on ipc code assigned before grant

Ipc: B63B 27/25 20060101ALI20151210BHEP

Ipc: B63B 25/14 20060101AFI20151210BHEP

Ipc: B63B 25/08 20060101ALI20151210BHEP

Ipc: B63B 17/00 20060101ALI20151210BHEP

Ipc: B67D 9/00 20100101ALI20151210BHEP

Ipc: F17C 1/00 20060101ALI20151210BHEP

Ipc: B63B 3/56 20060101ALI20151210BHEP

Ipc: F17C 13/08 20060101ALI20151210BHEP

Ipc: B63B 11/02 20060101ALI20151210BHEP

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

INTG Intention to grant announced

Effective date: 20160418

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 807494

Country of ref document: AT

Kind code of ref document: T

Effective date: 20160715

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602012019867

Country of ref document: DE

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20160622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160922

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160923

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 5

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161022

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161024

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602012019867

Country of ref document: DE

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20170323

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 6

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20121214

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161214

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160622

REG Reference to a national code

Ref country code: AT

Ref legal event code: UEP

Ref document number: 807494

Country of ref document: AT

Kind code of ref document: T

Effective date: 20160622

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: LU

Payment date: 20181121

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20181121

Year of fee payment: 7

Ref country code: MC

Payment date: 20181122

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: IE

Payment date: 20190520

Year of fee payment: 11

Ref country code: FR

Payment date: 20181120

Year of fee payment: 7

Ref country code: GB

Payment date: 20181121

Year of fee payment: 7

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602012019867

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200102

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20191214

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191214

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191214

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200701

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191231

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191214

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191214

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20201217

Year of fee payment: 9

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20220701

Year of fee payment: 10

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211231

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211231

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: TR

Payment date: 20221212

Year of fee payment: 11

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 807494

Country of ref document: AT

Kind code of ref document: T

Effective date: 20221214

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20221214