EP2410097A2 - Butt joints of highly stressed prefabricated columns - Google Patents
Butt joints of highly stressed prefabricated columns Download PDFInfo
- Publication number
- EP2410097A2 EP2410097A2 EP11401550A EP11401550A EP2410097A2 EP 2410097 A2 EP2410097 A2 EP 2410097A2 EP 11401550 A EP11401550 A EP 11401550A EP 11401550 A EP11401550 A EP 11401550A EP 2410097 A2 EP2410097 A2 EP 2410097A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- precast
- reinforcing bars
- prop
- reinforcing steel
- columns
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
- E04B1/21—Connections specially adapted therefor
Definitions
- the invention relates to the butt joint of highly loaded reinforced concrete prefabricated columns.
- supports In the construction of high-rise buildings, it is customary to form supports as composite supports.
- steel profiles are poured into concrete so that a common supporting effect of concrete and steel is created.
- These are heavy steel construction with welded profiles, which cause relatively high material costs.
- Another disadvantage is that the composite construction compared to the precast construction requires significantly longer construction times and thus generates a further cost disadvantage.
- reinforced reinforced concrete columns can be created.
- the reinforcement of reinforced concrete columns with high-strength steel is particularly advantageous for heavily loaded columns with predominantly normal force load - the steel is fully utilized in its carrying capacity.
- the resulting reduction of the cross-section has a positive effect: the planning of slender columns makes the usable area larger and thus provides an economic benefit.
- precast columns - these prefabricated in the factory components are characterized by a high dimensional accuracy.
- the transfer of the finished parts is done with the crane. Time-consuming set-up times for the conversion of formwork elements or long-term reinforcement work and concreting on site can be omitted.
- a disadvantage of the construction methods mentioned is that blunt shocks of the finished parts can be realized so far only at low loaded columns.
- the reinforcement of the columns must be connected to that of the columns of the previous floor or of the underlying component: in situ concrete, this can also be done by overlapping lengths after standardization, otherwise suitable reinforcement connection means are used. Commonly used are threaded sleeves or clamped connections.
- the disadvantage is the high expenditure of time that arises from the fact that every single connection of two reinforcing bars must be carried out manually; the prefabrication of reinforcement baskets is only possible to a limited extent.
- the reinforcement sleeves require a certain amount of space, since the circumference of the sleeve significantly exceeds that of the reinforcing rod. This fact alone limits the number of installable reinforcing bars in cross-section, because a sufficient embedment in the cement matrix is a prerequisite for the load-bearing behavior of the composite reinforced concrete.
- the object of the invention is to provide a system which makes it possible within a short construction time to create heavy-duty reinforced concrete columns in high quality execution - and so to optimize the economy in the production and quality, especially of high-rise buildings.
- the invention provides, preferably with high-strength steel reinforced precast columns blunt and only separated by a thin mortar bed separated from each other.
- a prerequisite for the force transfer in the butt joint is that the reinforcing bars made of steel - conventional reinforcing steel S500 or high-strength steel - are geometrically in one axis. This is inventively ensured by the fact that in the factory-made precast concrete fitting dowels are installed, which serve the adjustment and alignment of the connection.
- FIG. 1 is a vertical section through the joint area shown, as an example, the reinforcement 5, 8 is shown simplified. This must be inserted according to the requirements of the action according to the design.
- the supports of the lower floor 1 are provided and the reinforced concrete ceiling 3 is concreted on the upper edge of the finished parts 2.
- the reinforcing bars 5 protrude about 20 to 40 mm out.
- the precast columns 7 of the next floor are placed and aligned by means of the adjusting elements 6, 10.
- the reinforcement 8 of the prefabricated reinforced concrete elements 7 protrudes at its lower edge 9 approximately 10 to 25 mm, the distance between the precast lower edge 9 and upper edge 4 of the Ortbetondecke 3 is about 50 mm or more.
- the space between the support lower edge 9 and Ortbetonoberkante 4 is poured together with the joint between the reinforcing bars 5, 8 non-positively with low-shrinkage grout 11.
- the lower edge 9 of the pillar finished part 7 is inclined - this is particularly advantageous in terms of the complete filling of the mortar joint with grout 11th
- FIG. 2 is the stump stump invention to see in a plan view.
- the reinforcing bars 5, 8 and the Justierdollen 6, 10 in plan view.
- FIG. 3 shows the alternative embodiment of the precast support 7 with built-in base plate 12, which is preferably made in steel. Their arrangement creates a multi-axial bearing effect on the column foot and summarizes the transverse tensile stresses occurring there.
- This is a particularly robust construction of the stump stump joint according to the invention.
- the reinforcement of the lower support 1 projects about 40 to 55 mm beyond the upper edge 4 of the concrete ceiling 3.
- the Justiertosstoff 6, 10 provide an exact location of the reinforcing bars 5, 8 in their axial extension.
- the mortar joint is also pressed with potting mortar 11. Since this exemplary embodiment of the invention proves to be much more robust, here is a distance between the upper end of the bar steel 5 and lower edge of the Steel plate 12 of up to a quarter (1/4 d s ) of the diameter of the single rod possible.
- reinforcements at the bar end 8 serve to improve the robustness of the column connection.
- embodiments with steel ring inserts around the ends of the reinforcing rods 8 are also advantageous.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
Die Erfindung betrifft den Stumpfstoß hochbelasteter Stahlbetonfertigteilstützen.The invention relates to the butt joint of highly loaded reinforced concrete prefabricated columns.
Beim Bau von Hochhäusern ist es üblich, Stützen als Verbundstützen auszubilden. Hierbei werden Stahlprofile in Beton vergossen, so dass eine gemeinsame Tragwirkung von Beton und Stahl entsteht. Dabei handelt es sich um schweren Stahlbau mit Schweißprofilen, die relativ hohe Materialkosten verursachen. Ein weiterer Nachteil ist, dass die Verbundbauweise gegenüber der Fertigteilbauweise deutlich längere Bauzeiten erfordert und somit einen weiteren Kostennachteil generiert.In the construction of high-rise buildings, it is customary to form supports as composite supports. Here, steel profiles are poured into concrete so that a common supporting effect of concrete and steel is created. These are heavy steel construction with welded profiles, which cause relatively high material costs. Another disadvantage is that the composite construction compared to the precast construction requires significantly longer construction times and thus generates a further cost disadvantage.
Alternativ dazu können bewehrte Stahlbetonstützen erstellt werden. Dabei ist die Bewehrung von Stahlbetonstützen mit hochfestem Stahl besonders vorteilhaft bei hochbelasteten Stützen mit überwiegender Normalkraftbeanspruchung - der Stahl wird in seiner Tragfähigkeit voll ausgenutzt. Insbesondere im Zusammenhang mit der großen Anzahl von Stützen in Hochhäusern wirkt sich die dadurch mögliche Reduktion des Querschnittes positiv aus: die Planung schlankerer Stützen lässt die nutzbare Fläche größer werden und ergibt so einen wirtschaftlichen Nutzen.Alternatively, reinforced reinforced concrete columns can be created. Here, the reinforcement of reinforced concrete columns with high-strength steel is particularly advantageous for heavily loaded columns with predominantly normal force load - the steel is fully utilized in its carrying capacity. In particular, in connection with the large number of columns in high-rise buildings, the resulting reduction of the cross-section has a positive effect: the planning of slender columns makes the usable area larger and thus provides an economic benefit.
Es ist auch üblich Fertigteilstützen zu verwenden - diese im Werk vorgefertigten Bauelemente zeichnen sich durch eine hohe Maßhaltigkeit aus. Das Versetzen der Fertigteile erfolgt mit dem Kran. Zeitaufwändige Rüstzeiten für das Umsetzen von Schalungselementen oder langfristige Bewehrungsarbeiten sowie das Betonieren vorort können so entfallen.It is also common to use precast columns - these prefabricated in the factory components are characterized by a high dimensional accuracy. The transfer of the finished parts is done with the crane. Time-consuming set-up times for the conversion of formwork elements or long-term reinforcement work and concreting on site can be omitted.
Nachteilig bei den genannten Bauweisen ist, dass stumpfe Stöße der Fertigteile sich bisher nur bei gering belasteten Stützen verwirklichen lassen. In allen andern Fällen muss die Bewehrung der Stützen mit der der Stützen des vorherigen Stockwerkes oder der des darunterliegenden Bauteiles verbunden werden: in Ortbetonweise kann dies auch über Übergreifungslängen nach Normung erfolgen, andernfalls kommen geeignete Bewehrungsverbindungsmittel zum Einsatz. Häufig verwendet werden Schraubmuffen oder Klemmverbindungen. Nachteilig ist der hohe Zeitaufwand, der daraus entsteht, dass jede einzelne Verbindung zweier Bewehrungsstäbe händisch ausgeführt werden muss; die Vorfertigung von Bewehrungskörben ist nur eingeschränkt möglich. Außerdem erfordern die Bewehrungsmuffen einen gewissen Platzbedarf, da der Umfang der Muffe den des Bewehrungsstabes deutlich übersteigt. Allein diese Tatsache beschränkt die Anzahl der einbaubaren Bewehrungsstäbe im Querschnitt, denn eine ausreichende Einbettung in die Zementmatrix ist Vorraussetzung für das Tragverhalten des Verbundwerkstoffes Stahlbeton.A disadvantage of the construction methods mentioned is that blunt shocks of the finished parts can be realized so far only at low loaded columns. In all other cases, the reinforcement of the columns must be connected to that of the columns of the previous floor or of the underlying component: in situ concrete, this can also be done by overlapping lengths after standardization, otherwise suitable reinforcement connection means are used. Commonly used are threaded sleeves or clamped connections. The disadvantage is the high expenditure of time that arises from the fact that every single connection of two reinforcing bars must be carried out manually; the prefabrication of reinforcement baskets is only possible to a limited extent. In addition, the reinforcement sleeves require a certain amount of space, since the circumference of the sleeve significantly exceeds that of the reinforcing rod. This fact alone limits the number of installable reinforcing bars in cross-section, because a sufficient embedment in the cement matrix is a prerequisite for the load-bearing behavior of the composite reinforced concrete.
Bei einer Vielzahl von Stahlbetonstützen im Bauwerk liegt die Herstellung der Stützen oft auf dem kritischen Weg - d. h. die Herstellung der Stützen definiert die Dauer der Bauzeit.With a variety of reinforced concrete columns in the structure, the production of the columns is often on the critical path - d. H. The manufacture of the columns defines the duration of the construction period.
Aufgabe der Erfindung ist es ein System anzugeben, das es ermöglicht innerhalb kurzer Bauzeit hochbeanspruchbare Stahlbetonstützen in hoher Ausführungsqualität zu erstellen - und so die Wirtschaftlichkeit in der Herstellung und die Qualität besonders von Hochhäusern zu optimieren.The object of the invention is to provide a system which makes it possible within a short construction time to create heavy-duty reinforced concrete columns in high quality execution - and so to optimize the economy in the production and quality, especially of high-rise buildings.
Die Aufgabe wird durch die im Kennzeichen des Anspruchs 1 angegebenen Merkmale gelöst.The object is solved by the features specified in the characterizing part of
Hierzu sieht die Erfindung vor, mit bevorzugt hochfestem Stahl bewehrte Fertigteilstützen stumpf und nur durch ein dünnes Mörtelbett voneinander getrennt miteinander zu stoßen.For this purpose, the invention provides, preferably with high-strength steel reinforced precast columns blunt and only separated by a thin mortar bed separated from each other.
Aufgrund der sehr hohen Stahlspannungen ist die üblich Übertragung der Kräfte aus dem Bewehrungsstab über Verbund in den Beton und weiter über die Mörtelfuge nicht realisierbar. Es käme zum Betonversagen infolge der auftretenden Querzugspannungen im Lastübergangsbereich am Stützenende. Auch der Mörtel in der Fuge kann nicht allein die gesamte Stützenkraft übertragen. Die Ausbildung zweier Tragwirkungen ist notwendig: die Kraftübertragung zwischen den Stäben durch den Mörtel und die von Stab zu Stab direkt. Die Kraft im Bewehrungsstahl muss über Spitzendruck an den weiterlaufenden Bewehrungsstahl übergeben werden. Dies kann über einen Kontaktstoß gelingen, wenn die Stäbe dabei direkt übereinander stehen. Baupraktisch ist das beim Einsatz von Fertigteilstützen allerdings kaum praktikabel, die Toleranzen im Bauwesen lassen einen planmäßigen Kontaktstoß nicht zu. Überraschenderweise hat es sich gezeigt, dass der Stoß zweier hochbelasteter Fertigteilstützen in der erfindungsgemäßen Ausführung durchaus den Belastungen standhält und die auftretenden Einwirkungen mit ausreichender Sicherheit weiterleitet. Dabei kann auf einen direkten Kontakt der Stahleinlagen - für die bevorzugt hochfester Stahl verwendet wird - verzichtet werden, diese werden im Rahmen der auf der Baustelle üblichen Toleranzen mit einen planmäßigen Abstand zueinander von etwa 5 mm - maximal 1/8 des Stahldurchmesser des einzelnen Bewehrungsstabes - (+/- 2 mm Toleranz) angeordnet und justiert. Der Abstand zwischen dem Beton der Stützen-Fertigteile und dem Deckenbeton und der darüber hinausragenden Bewehrungsstäbe zueinander wird mit Vergussmörtel kraftschlüssig ausgegossen. Es zeigt sich, dass unter diesen geometrischen Randbedingungen in dem relativ dünnen Mörtelbett der Effekt aus mehrachsialem Spannungszustand in der Mörtelfuge die Tragsicherheit des Vergußmörtels steigert und das Gesamttragverhalten sehr gut ist.Due to the very high steel stresses, the usual transmission of forces from the reinforcing bar via composite in the concrete and continue on the mortar joint is not feasible. It would come to concrete failure due to the occurring transverse tensile stresses in the load transition area at the column end. Even the mortar in the joint can not transfer the entire support force alone. The formation of two load bearing effects is necessary: the power transmission between the bars through the mortar and from bar to bar directly. The force in the reinforcing steel must be transferred to the continuing reinforcing steel via peak pressure. This can be achieved via a contact impact, if the rods are directly above each other. In terms of construction, however, this is hardly practicable when using precast columns, and the tolerances in the construction industry do not permit a planned contact impact. Surprisingly, it has been found that the impact of two highly loaded precast columns in the embodiment of the invention quite well withstand the stresses and forwards the occurring effects with sufficient security. It can be on a direct contact of the steel inserts - is used for the preferred high-strength steel - are omitted, these are within the usual tolerances on the site with a scheduled distance from each other by about 5 mm - maximum 1/8 of the steel diameter of the individual reinforcing bar - (+/- 2 mm tolerance) arranged and adjusted. The distance between the concrete of the pillar prefabricated parts and the concrete ceiling and the reinforcing bars projecting beyond each other is poured out with grout with grout. It turns out that under these geometric boundary conditions in the relatively thin mortar bed, the effect of multiaxial stress state in the mortar joint increases the load-bearing safety of the grout and the overall performance is very good.
Vorraussetzung für den Kraftübergang im Stützenstoß ist, dass die Bewehrungsstäbe aus Stahl - herkömmlicher Betonstahl S500 oder hochfester Stahl - geometrisch in einer Achse liegen. Dies wird erfindungsgemäß dadurch sichergestellt, dass in den werksmäßig hergestellten Betonfertigteilen passgenau Dollen eingebaut werden, die der Justierung und Ausrichtung des Anschlusses dienen.A prerequisite for the force transfer in the butt joint is that the reinforcing bars made of steel - conventional reinforcing steel S500 or high-strength steel - are geometrically in one axis. This is inventively ensured by the fact that in the factory-made precast concrete fitting dowels are installed, which serve the adjustment and alignment of the connection.
Ausführungsbeispiele sind in den Zeichnungen dargestellt und werden im Folgenden näher beschrieben:
-
Fig. 1 : Schnitt durch den Stützenstoß im Deckenbereich -
Fig. 2 : Draufsicht auf einen Stoßquerschnitt - Prinzipskizze -
Fig. 3 : Schnitt durch den Stützenstoß im Deckenbereich mit verstärkender Stahlplatte - Ausführungsvariante
-
Fig. 1 : Section through the buttress joint in the ceiling area -
Fig. 2 : Top view on a push cross section - outline sketch -
Fig. 3 : Section through the column joint in the ceiling area with reinforcing steel plate - variant
In
Zunächst werden die Stützen des unteren Stockwerkes 1 gestellt und auf die Oberkante der Fertigteile 2 die Stahlbetondecke 3 betoniert. Über die Oberkante 4 der Ortbetondecke 3 ragen die Bewehrungsstäbe 5 ungefähr 20 bis 40 mm hinaus. Zudem ist mindestens ein - bevorzugt zwei oder mehrere - Justierdollen mit Hülse 6, 10 schon in der Fertigteilherstellung einzubauen. Bei der Herstellung der Fertigteilstützen im Werk ist auf eine hohe Maßhaltigkeit hinsichtlich der Lage der Bewehrungsstäbe 5, 8 und der Justier-Hilfsmittel 6, 10 zu achten.First, the supports of the
Die Fertigteilstützen 7 des nächsten Stockwerkes werden aufgestellt und mittels der Justierelemente 6, 10 ausgerichtet. Die Bewehrung 8 der Stahlbetonfertigteile 7 steht an deren Unterkante 9 ungefähr 10 bis 25 mm über, die Distanz zwischen Fertigteilunterkante 9 und Oberkante 4 der Ortbetondecke 3 beträgt ca. 50 mm oder mehr. Der Zwischenraum zwischen Stützenunterkante 9 und Ortbetonoberkante 4 wird gemeinsam mit der Fuge zwischen den Bewehrungsstäben 5, 8 kraftschlüssig mit schwindarmem Vergussmörtel 11 ausgegossen. In einer alternativen Ausführung ist die Unterkante 9 des Stützenfertigteiles 7 geneigt ausgeführt - dies ist besonders vorteilhaft hinsichtlich des vollständigen Ausfüllens der Mörtelfuge mit Vergussmörtel 11.The
In
Überhaupt dienen Verstärkungen am Stabstahlende 8 der Verbesserung der Robustheit des Stützenanschlusses. So sind auch alternativ zur Stahlplatte 12 Ausführungen mit Stahlringeinlagen um die Enden der Bewehrungstäbe 8 vorteilhaft.In general, reinforcements at the bar end 8 serve to improve the robustness of the column connection. As an alternative to the
- 11
- Fertigteilstützen unteres StockwerkPrefabricated columns lower floor
- 22
- Oberkante FertigteilTop edge of finished part
- 33
- StahlbetondeckeReinforced concrete floor
- 44
- Oberkante StahlbetondeckeTop edge of reinforced concrete ceiling
- 55
- Bewehrung im unteren FertigteilReinforcement in the lower finished part
- 66
- Justierhülse im oberen FertigteilAdjustment sleeve in the upper finished part
- 77
- Fertigteilstützen oberes StockwerkPrefabricated columns upper floor
- 88th
- Bewehrung im oberen FertigteilReinforcement in the upper finished part
- 99
- Unterkante oberes FertigteilLower edge of upper finished part
- 1010
- Justierdollen im unteren FertigteilAdjusting wheels in the lower finished part
- 1111
- Mörtelbettmortar bed
- 1212
- Fußplattefootplate
Claims (8)
dadurch gekennzeichnet, dass die Bewehrungsstahlstäbe (5), (8) ohne direkten Kontakt stumpf miteinander gestoßen werden.Execution of a shock of highly loaded prefabricated concrete supports (1), (7) preferably made of reinforced concrete,
characterized in that the reinforcing steel bars (5), (8) are butted together without direct contact.
dadurch gekennzeichnet, dass die Distanz zwischen den Bewehrungsstäben (5) der unteren Fertigteilstütze (1) und den Bewehrungsstäben (8) der oberen Fertigteilstütze (7) maximal 1/8 des Einzelstabdurchmessers zuzüglich des Toleranzausgleiches beträgt.Device according to claim 1,
characterized in that the distance between the reinforcing bars (5) of the lower precast prop (1) and the reinforcing bars (8) of the upper precast prop (7) is at most 1/8 of the single rod diameter plus the tolerance compensation.
dadurch gekennzeichnet, dass das Mörtelbett (11) zwischen Oberkante (4) der Ortbetondecke (3) und der Unterkante (9) der Fertigteilstütze (7) bei horizontaler Unterkante maximal 50 mm stark ist.Device according to at least one of claims 1 and 2,
characterized in that the mortar bed (11) between the upper edge (4) of the Ortbetondecke (3) and the lower edge (9) of the precast support (7) at maximum horizontal edge is a maximum of 50 mm thick.
dadurch gekennzeichnet, dass die Unterkante der Fertigteilstütze (7) gegen die Horizontale geneigt ausgeführt ist und das Mörtelbett (11) zwischen Oberkante (4) der Ortbetondecke (3) und der Unterkante (9) der Fertigteilstütze (7) einseitig dicker als 50 mm sein kann.Device according to at least one of claims 1 to 3,
characterized in that the lower edge of the precast support (7) is designed to be inclined to the horizontal and the mortar bed (11) between the upper edge (4) of the Ortbetondecke (3) and the lower edge (9) of the precast support (7) on one side thicker than 50 mm can.
dadurch gekennzeichnet, dass die obere Fertigteilstütze (7) mit einer Fußplatte (12) ausgestattet ist, auf der die Bewehrungsstäbe (8) stumpf enden.Device according to at least one of claims 1 to 4,
characterized in that the upper precast support (7) is provided with a foot plate (12) on which the reinforcing bars (8) terminate dull.
dadurch gekennzeichnet, dass die Distanz zwischen den Bewehrungsstäben (5) der unteren Fertigteilstütze (1) und der Fußplatte (12) der oberen Fertigteilstütze (7) maximal 1/4 des Einzelstabdurchmessers beträgt.Device according to claim 5,
characterized in that the distance between the reinforcing bars (5) of the lower precast prop (1) and the base plate (12) of the upper precast prop (7) is at most 1/4 of the single rod diameter.
dadurch gekennzeichnet, dass der Bewehrungsstahl (5), (8) ein hochfester Betonstahl ist.Device according to at least one of claims 1 to 6,
characterized in that the reinforcing steel (5), (8) is a high-strength reinforcing steel.
dadurch gekennzeichnet, dass in den werksmäßig hergestellten Betonfertigteilen passgenau Dollen (10) und Hülsen (6) eingebaut sind, die der Justierung und Ausrichtung des Anschlusses dienen.Device according to at least one of claims 1 to 7,
characterized in that in the factory-made precast concrete parts precisely (10) and sleeves (6) are installed, which serve the adjustment and alignment of the terminal.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE201010031511 DE102010031511A1 (en) | 2010-07-19 | 2010-07-19 | Stump stump joint of highly loaded precast columns |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2410097A2 true EP2410097A2 (en) | 2012-01-25 |
EP2410097A3 EP2410097A3 (en) | 2013-07-24 |
Family
ID=45370736
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP11401550.6A Withdrawn EP2410097A3 (en) | 2010-07-19 | 2011-07-14 | Butt joints of highly stressed prefabricated columns |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP2410097A3 (en) |
DE (1) | DE102010031511A1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CZ305679B6 (en) * | 2013-11-05 | 2016-02-03 | ÄŚeskĂ© vysokĂ© uÄŤenĂ technickĂ© v Praze, Fakulta stavebnĂ, Katedra konstrukcĂ pozemnĂch staveb | Dismountable contact joint of reinforced-concrete poles |
WO2020186857A1 (en) * | 2019-03-21 | 2020-09-24 | 巴马丹拿建筑及工程师有限公司 | Connection structure provided among precast reinforced concrete structure bodies and reinforcing steel configuration method for reinforced concrete structure bodies |
CN113818698A (en) * | 2021-10-27 | 2021-12-21 | 刘杰 | Precast concrete component butt joint system |
CZ310028B6 (en) * | 2012-07-11 | 2024-05-22 | České vysoké učení technické v Praze | A joint of prefabricated structures |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108532834B (en) * | 2018-06-22 | 2023-08-18 | 中国五冶集团有限公司 | Assembled building frame post fills structure |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
BE461851A (en) * | ||||
DD97457A1 (en) * | 1971-11-15 | 1973-05-14 | ||
BR7507955A (en) * | 1974-12-02 | 1976-08-24 | Wests Piling Construct | IMPROVEMENT IN PILE CONNECTING DEVICE |
CH688965A5 (en) * | 1993-11-11 | 1998-06-30 | Veltheim Element Ag | Load-transmission and distribution system |
DE10004768B4 (en) * | 2000-02-03 | 2004-09-23 | Gernot Wolperding | Steel core support, in particular for use in multi-storey construction, and manufacturing method |
AT413403B (en) * | 2004-04-06 | 2006-02-15 | Tech Uni Wien I Fuer Stahlbeto | PREPARED ELEMENT OF HIGH STRENGTH CONCRETE FOR SUPPORT CEILING NOTES |
JP2010065459A (en) * | 2008-09-11 | 2010-03-25 | Shimizu Corp | Joining structure and joining method of column-beam joint member and column member of precast concrete construction |
-
2010
- 2010-07-19 DE DE201010031511 patent/DE102010031511A1/en not_active Withdrawn
-
2011
- 2011-07-14 EP EP11401550.6A patent/EP2410097A3/en not_active Withdrawn
Non-Patent Citations (1)
Title |
---|
None |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CZ310028B6 (en) * | 2012-07-11 | 2024-05-22 | České vysoké učení technické v Praze | A joint of prefabricated structures |
CZ305679B6 (en) * | 2013-11-05 | 2016-02-03 | ÄŚeskĂ© vysokĂ© uÄŤenĂ technickĂ© v Praze, Fakulta stavebnĂ, Katedra konstrukcĂ pozemnĂch staveb | Dismountable contact joint of reinforced-concrete poles |
WO2020186857A1 (en) * | 2019-03-21 | 2020-09-24 | 巴马丹拿建筑及工程师有限公司 | Connection structure provided among precast reinforced concrete structure bodies and reinforcing steel configuration method for reinforced concrete structure bodies |
CN113818698A (en) * | 2021-10-27 | 2021-12-21 | 刘杰 | Precast concrete component butt joint system |
Also Published As
Publication number | Publication date |
---|---|
DE102010031511A1 (en) | 2012-01-19 |
EP2410097A3 (en) | 2013-07-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AT517958B1 (en) | Foundation for a wind turbine | |
EP2914790B1 (en) | Method for producing a tower construction from reinforced concrete | |
AT517959B1 (en) | Foundation for a wind turbine | |
DE69802193T2 (en) | COMPOUND STEEL CONCRETE PILLAR | |
EP3662122B1 (en) | Foundation for a building | |
EP3085843B1 (en) | Device and method for heat decoupling of concreted parts of buildings | |
EP3112542B1 (en) | Device and method for heat decoupling of concreted parts of buildings | |
DE102011090194B4 (en) | Tower-shaped structure | |
EP2410097A2 (en) | Butt joints of highly stressed prefabricated columns | |
EP3607147B1 (en) | Offshore foundation | |
DE10027037B4 (en) | Arrangement consisting of a prefabricated support and a foundation | |
EP1669505A1 (en) | Steel-concrete composite joist with fire-resistant support for ceiling elements | |
WO2001053623A2 (en) | Reinforced or pre-stressed concrete part which is subjected to a transverse force | |
EP1795667A2 (en) | Reinforcing member for structures made of reinforced or prestressed concrete or the same | |
EP2430245B1 (en) | Process for forming a foundation | |
EP3225758A1 (en) | Connection component for thermal isolation between a vertical and horizontal building part | |
CN210141019U (en) | Embedded profile steel type underpinning node | |
DE102012110184A1 (en) | Centrifugal concrete column for use with ceiling connector for structure of building, is made of ultra high performance concrete, where cylinder compressive strength of ultra high performance concrete is thundered mega Pascal | |
EP3492665A1 (en) | Finished concrete part with at least one load-absorbing component and connection plate for assembly in the gap between same and load-absorbing component | |
WO2011012480A1 (en) | Reinforced concrete component reinforced with z-shaped sheet metal pieces | |
AT505270B1 (en) | CONCRETE PROP | |
LU502258B1 (en) | Process for producing a tube complex | |
EP3728756B1 (en) | Column-ceiling node for a reinforced concrete ceiling and two concrete columns in storey construction | |
DE102010040332B4 (en) | foundation element | |
WO2015059008A1 (en) | Machine table foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E04B 1/21 20060101AFI20130617BHEP |
|
17P | Request for examination filed |
Effective date: 20131128 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
17Q | First examination report despatched |
Effective date: 20140508 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20141119 |