Platform structure and construction method Download PDF

Info

Publication number
EP1415047B1
EP1415047B1 EP02745684A EP02745684A EP1415047B1 EP 1415047 B1 EP1415047 B1 EP 1415047B1 EP 02745684 A EP02745684 A EP 02745684A EP 02745684 A EP02745684 A EP 02745684A EP 1415047 B1 EP1415047 B1 EP 1415047B1
Authority
EP
European Patent Office
Prior art keywords
platform
cross beams
beams
platform structure
units
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP02745684A
Other languages
German (de)
French (fr)
Other versions
EP1415047A1 (en
Inventor
Mark Andrew Alton
Frederick Thomas Alan Coakley
Richard Summers Shepherd Green
Andrew Keith Harmer
Ian Joseph Wells
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
M40 Trains Ltd
Mott MacDonald Ltd
Arriva Trains Holdings Ltd
Original Assignee
M40 Trains Ltd
Mott MacDonald Ltd
Laing Rail Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by M40 Trains Ltd, Mott MacDonald Ltd, Laing Rail Ltd filed Critical M40 Trains Ltd
Publication of EP1415047A1 publication Critical patent/EP1415047A1/en
Application granted granted Critical
Publication of EP1415047B1 publication Critical patent/EP1415047B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F1/00Construction of station or like platforms or refuge islands or like islands in traffic areas, e.g. intersection or filling-station islands; Kerbs specially adapted for islands in traffic areas

Definitions

  • This invention relates to the construction of platforms for railway stations.
  • DE-A-43 16 203 discloses a prefabricated platform unit for construction of a railway station platform.
  • the unit has a stepped upper surface comprising a forward portion, on which edge copers are to be mounted, and a rearward portion, with a step rising between the forward and rearward portions, the forward portion being planar.
  • the unit is 6 - 8 m wide (the dimension along the track) and 2.5 - 4 m deep (the dimension away from the track).
  • the unit includes integral cross members extending along the underside of the unit, adjacent its side edge surfaces, and integral longitudinal members extending along the underside of the unit, between the cross members and adjacent the front and rear side edge surfaces of the unit, so that the unit resembles a downwardly open box.
  • the unit is bulky and difficult to manoeuvre.
  • transverse beams are mounted on concrete foundations and the platform units are mounted on the transverse beams, each transverse beam supporting two cross beams belonging to two adjacent units.
  • the invention provides a railway station platform structure as set forth in claim 1.
  • the invention provides a method of constructing a railway station platform structure, including the following steps:
  • Each prefabricated platform unit or slab unit 1, shown in Figures 1 to 3, is a pre-cast concrete unit incorporating a reinforcing mesh 2 (not shown).
  • the slab unit 1 has a mostly planar bottom surface 3 and a stepped upper surface 4.
  • the slab unit has a nominal width of 2 metres (for example) and has a rectangular outline when viewed from above. In general, the length of the slab unit from its front edge to its rear edge is at least equal to its width. Exemplary dimensions, in millimetres, are indicated in Figure 3.
  • the slab unit has a front edge surface 6, a rear edge surface 7, and side edge surfaces 8,9, all of which are vertical surfaces.
  • the upper surface 4 has a rebated forward portion 4a which is planar and parallel to the bottom surface 3, a rearward portion 4b which is planar and slopes downwardly and rearwardly from its front edge to its rear edge, and a step 4c which rises vertically between the forward and rearward portions 4a,4b.
  • the step 4c extends across the width of the slab unit, parallel to its front edge surface 6.
  • the platform units or slab units 1 illustrated are longer from front to back than their individual width and are used in the construction of a new platform structure, which may be an extension to an existing platform structure.
  • the rearward portion 4b of the upper surface 4 has a gradual slope (1 in 50) from front to back, and there is a raised plinth 27 near the rear edge surface 7 of the slab unit 1.
  • a drainage outlet 28 is provided in the front surface of the plinth 27.
  • One side edge surface 9 has a key formation 29 for fitting in a recess or groove 31 in the opposite side edge surface 8 of an adjacent slab unit so as to prevent relative vertical movement of the adjacent slab units.
  • the bottom surface of the slab unit 1 has integrally cast projections 32 for a purpose to be explained below.
  • One slab unit 1 has a recess 33 in one edge, for receiving a lighting column (not shown).
  • a first embodiment of a platform structure incorporating the slab units 1 shown in Figure 1 will now be described with reference to Figures 2 and 3, by describing the steps involved in its method of construction.
  • steps (2), (3), (7), and (11) do not require track possession.
  • the design of the platform structure ensures that the other steps, which will normally require track possession, can be carried out quickly and in separate stages.
  • a second embodiment of the platform structure will now be described with reference to Figures 4 and 5.
  • the second embodiment differs from the first embodiment only in using piles instead of strip foundations. Accordingly, the above description, except for step (2), is applicable to the second embodiment and will not be repeated.
  • step (2) is replaced by the step of preparing the ground and inserting piles 36a into the ground at the intended locations of the supporting columns 37, which are subsequently constructed on the piles.
  • the lengths of the-cross beams 38 and the number of longitudinal beams 42 between each pair of cross beams may be varied to suit different platform widths (front to back).
  • a platform width of less than 3 metres (for example 2.5 metres) two longitudinal beams 42 may be sufficient.
  • three longitudinal beams 42 may be sufficient.
  • four longitudinal beams should be used.
  • the position of the front longitudinal beam in relation to the front end of the cross beam will be the same in each case, so that pre-cast concrete manufacture of the cross beams can to some extent be standardised.
  • the side edges of one or more of the slab units may be non-parallel, either converging or diverging away from the front edge, one or both of the side edges not being perpendicular to the front edge.
  • Cable-tray receiving grooves 47 may be provided in more than two of the longitudinal beams 42, and additional holes 41 may be provided in the cross beams 38 if one or more additional cable trays are fitted using these grooves.
  • edge copers and tactile paving elements instead of fitting the edge copers and tactile paving elements on the slab units after the installation of the slab units, it may be possible to fit them on the slab units before the slab units are mounted on the supporting structure. It may also be possible to combine the tactile paving elements with the edge copers, or to omit the tactile paving elements.
  • the edge copers and tactile paving elements may be omitted and for the upper surface of the slab unit to be provided with a suitably textured finish.
  • the rebated forward portion may be omitted or reduced in size to receive a relatively narrow edging strip (e.g. of stainless steel) set in epoxy mortar for example.
  • the platform structure can be provided at any trackside location where it may be desired to bring a train to a halt in order to allow passengers or train operating staff to board or alight from the train or to attend to the maintenance of the exterior of the train.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Road Signs Or Road Markings (AREA)
  • Footwear And Its Accessory, Manufacturing Method And Apparatuses (AREA)
  • Building Environments (AREA)
  • Platform Screen Doors And Railroad Systems (AREA)
  • Separation By Low-Temperature Treatments (AREA)

Abstract

A prefabricated platform unit (1), for construction or refurbishment of a railway station platform, has a stepped upper surface (4) with a recessed planar forward portion (4a) on which edge copers (23) are to be mounted. Refurbishment of an exiting platform may be performed by excavating a region (22) of the platform surface to the front edge, installing a prefabricated platform unit (1) in the excavated region, and installing edge copers (23). Construction of a new platform may include the steps of constructing foundations alongside the railway, constructing upstanding supporting members on the foundations, and mounting a superstructure including the prefabricated platform units on the supporting members.

Description

This invention relates to the construction of platforms for railway stations.
The increasing demand for rail travel is requiring train operating companies to create extra capacity by the use of longer trains, but many existing station platforms are too short to accommodate such trains. The construction of platform extensions is restricted by the requirement to minimise disruption to normal use of the existing platform, to accommodate the works within existing train service patterns, and to have possession of the track while much of the construction work is carried out.
DE-A-43 16 203 discloses a prefabricated platform unit for construction of a railway station platform. The unit has a stepped upper surface comprising a forward portion, on which edge copers are to be mounted, and a rearward portion, with a step rising between the forward and rearward portions, the forward portion being planar. The unit is 6 - 8 m wide (the dimension along the track) and 2.5 - 4 m deep (the dimension away from the track). The unit includes integral cross members extending along the underside of the unit, adjacent its side edge surfaces, and integral longitudinal members extending along the underside of the unit, between the cross members and adjacent the front and rear side edge surfaces of the unit, so that the unit resembles a downwardly open box. The unit is bulky and difficult to manoeuvre. To construct a platform, transverse beams are mounted on concrete foundations and the platform units are mounted on the transverse beams, each transverse beam supporting two cross beams belonging to two adjacent units.
It would therefore be desirable to be able to minimise the time for which track possession is required when constructing a railway station platform. In particular it would be desirable to be able to provide a structure which can be constructed quickly, without using time-consuming processes during possession.
In one aspect the invention provides a railway station platform structure as set forth in claim 1.
In another aspect the invention provides a method of constructing a railway station platform structure, including the following steps:
  • (a) constructing foundations alongside the railway;
  • (b) constructing upstanding supporting members on the foundations;
  • (c) mounting cross beams on the supporting members so that the cross beams have cantilevered portions extending beyond the supporting members towards the railway;
  • (d) mounting longitudinal beams on the cross beams; and
  • (e) mounting platform units on the longitudinal beams so that side edge surfaces of the units extend away from the railway and front edge surfaces of the units extend along the railway beyond the ends of the cantilevered portions of the cross beams.
  • The invention will be described further, by way of example only, with reference to the accompanying drawings, in which:
  • Figure 1A is an exploded isometric view of edge copers and tactile paving elements for use in the construction of the platform;
  • Figure 1 is an isometric view of three prefabricated platform units slab units, for use in the construction of a platform;
  • Figure 2 is a vertical section through a platform structure incorporating the slab units of Figure 1, in a first embodiment;
  • Figure 3 is an exploded isometric view of the first embodiment of the platform structure;
  • Figure 4 is a vertical section through a second embodiment of the platform structure; and
  • Figure 5 is an exploded isometric view of the second embodiment of the platform structure.
  • Each prefabricated platform unit or slab unit 1, shown in Figures 1 to 3, is a pre-cast concrete unit incorporating a reinforcing mesh 2 (not shown). The slab unit 1 has a mostly planar bottom surface 3 and a stepped upper surface 4. The slab unit has a nominal width of 2 metres (for example) and has a rectangular outline when viewed from above. In general, the length of the slab unit from its front edge to its rear edge is at least equal to its width. Exemplary dimensions, in millimetres, are indicated in Figure 3. The slab unit has a front edge surface 6, a rear edge surface 7, and side edge surfaces 8,9, all of which are vertical surfaces. The upper surface 4 has a rebated forward portion 4a which is planar and parallel to the bottom surface 3, a rearward portion 4b which is planar and slopes downwardly and rearwardly from its front edge to its rear edge, and a step 4c which rises vertically between the forward and rearward portions 4a,4b. The step 4c extends across the width of the slab unit, parallel to its front edge surface 6.
    The platform units or slab units 1 illustrated are longer from front to back than their individual width and are used in the construction of a new platform structure, which may be an extension to an existing platform structure. The rearward portion 4b of the upper surface 4 has a gradual slope (1 in 50) from front to back, and there is a raised plinth 27 near the rear edge surface 7 of the slab unit 1. A drainage outlet 28 is provided in the front surface of the plinth 27. One side edge surface 9 has a key formation 29 for fitting in a recess or groove 31 in the opposite side edge surface 8 of an adjacent slab unit so as to prevent relative vertical movement of the adjacent slab units. The bottom surface of the slab unit 1 has integrally cast projections 32 for a purpose to be explained below. One slab unit 1 has a recess 33 in one edge, for receiving a lighting column (not shown).
    A first embodiment of a platform structure incorporating the slab units 1 shown in Figure 1 will now be described with reference to Figures 2 and 3, by describing the steps involved in its method of construction.
  • (1) Simple temporary mesh fencing 34 is set up at a spacing of 2 metres from the centre line of the outermost track rail 24 to define a border between the so-called red zone (in which it would be hazardous and, in some situations, not permitted to work when not-in track possession) and the so-called green zone (in which it is safe to work under certain conditions, whether or not in track possession).
  • (2) In the green zone the ground is prepared and excavated to provide two trenches parallel to the track. Concrete is then poured into the trenches to form strip foundations 36.
  • (3) In situ concrete support columns 37 are constructed on the strip foundations 36 and incorporate vertically projecting corrosion resistant threaded tie bars of 16 mm diameter (not shown in Figure 8).
  • (4) Pre-cast concrete cross beams 38 are craned in and positioned on the support columns 37. Each cross beam 38 is supported by two columns 37 and has a cantilevered portion 38a extending beyond the support columns 37 towards the track. Each cross beam 38 has two vertical through holes 39, which are formed during the casting of the concrete cross beam and which have a minimum diameter of 50 mm. These oversize holes 39 receive the threaded bars projecting upwards from the columns 37 and are used to locate the cross beams 38 relative to the support columns 37, nuts being threaded on the tie bars to provide a mechanical connection between the cross beam 38 and the support columns 37. Resilient rubber pads (not shown) with pre-formed holes to receive the threaded bars are located on top of the columns 37. The cross beams 38 incorporate holding down-bolts (not shown) for connecting the base of the lighting column and one or more ducts 41 for the passage of electrical cables.
  • (5) Pre-cast longitudinal beams 42 are craned in and mounted on the cross beams 38. The upper edges of the cross beams 38 have recesses 43 which accommodate end portions 42a of the beams 42 resting on resilient rubber pads 44 at the bottoms of the recesses 43. Abutment surfaces 42b (recessed beneath the end portions 42a) face the respective side surfaces of the cross beams 38. The upper surfaces of the cross beams 38 are flush with the upper surfaces of the longitudinal beams 42.
  • (6) The slab units 1 are craned in and mounted on the supporting structure constituted by the cross beams 38 and longitudinal beams 42. The downward projections 32 on the slab units abut against respective side surfaces of two of the longitudinal beams 42 to locate the slab units in the direction towards and away from the track. The slab units 1 are installed one by one, engaging the key formation 29 on each slab unit with the corresponding groove 31 of the next slab unit. The joints between adjacent units are sealed by a dry rubber O-ring which, when compressed, forms a watertight seal. To assist installation, temporary lifting rings (not shown) can be fitted to anchorages (not shown) located in or near the plinth 27 and in the forward portion 4a of the upper surface of the slab unit.
  • (7) Platform fencing (not shown) is erected on the plinths 27 and electrical cabling is installed using the cable ducts 41 and cable support trays 46 mounted in facing longitudinal recesses 47 in a pair of the longitudinal beams 42.
  • (8) Platform lighting is installed, a lighting column being inserted through the recess 33 in at least one of the slab units 1 and bolted to the cross beam 38 below.
  • (9) Lightweight edge copers 23 (Fig. 1A) are installed on quick-setting epoxy adhesive mortar on the forward portions 4a of the upper surface 4 of the slab units 1. In the present example five edge copers 23 are mounted side by side across the two metre width of each slab unit. Depending on the size of the edge copers, more or fewer may be used, although there are preferably at least four. Accordingly, the edge copers 23 are small enough to be handled without undue strain, preferably weighing at most 25 kg if they are made of pre-cast concrete and being substantially lighter if they are made of less dense materials, for example plastics material. The edge copers 23 overlap the front edge of the slab unit 1 and are laid level so that their front edges are at a given horizontal and vertical spacing from the adjacent rail 24.
  • (10) Tactile paving elements 26 (which can be felt by a person's foot) are installed on quick-setting epoxy adhesive mortar, between the edge copers 23 and the step 4c, in such a manner as to compensate for any difference in level between the rear edges of the edge copers 23 and the front edge of the rearward portion 4b of the upper surface of the slab unit.
  • (11) Anti-debris netting (not shown) is installed beneath the platform, by means of stainless steel eyes received in sockets (not shown) cast in the cross beams 38.
  • (12) Finally the temporary fencing 34 is removed.
  • It will be appreciated that steps (2), (3), (7), and (11) do not require track possession. The design of the platform structure ensures that the other steps, which will normally require track possession, can be carried out quickly and in separate stages.
    A second embodiment of the platform structure will now be described with reference to Figures 4 and 5. The second embodiment differs from the first embodiment only in using piles instead of strip foundations. Accordingly, the above description, except for step (2), is applicable to the second embodiment and will not be repeated.
    In the construction of the second embodiment, step (2) is replaced by the step of preparing the ground and inserting piles 36a into the ground at the intended locations of the supporting columns 37, which are subsequently constructed on the piles.
    Various modifications may be made within the scope of the invention. In particular, the lengths of the-cross beams 38 and the number of longitudinal beams 42 between each pair of cross beams may be varied to suit different platform widths (front to back). For a platform width of less than 3 metres (for example 2.5 metres) two longitudinal beams 42 may be sufficient. For platform widths of 3 or 3.5 metres, three longitudinal beams 42 may be sufficient. For a platform width of 4 metres, four longitudinal beams should be used. The position of the front longitudinal beam in relation to the front end of the cross beam will be the same in each case, so that pre-cast concrete manufacture of the cross beams can to some extent be standardised.
    To accommodate curved track alignments the side edges of one or more of the slab units may be non-parallel, either converging or diverging away from the front edge, one or both of the side edges not being perpendicular to the front edge.
    Cable-tray receiving grooves 47 may be provided in more than two of the longitudinal beams 42, and additional holes 41 may be provided in the cross beams 38 if one or more additional cable trays are fitted using these grooves.
    Instead of fitting the edge copers and tactile paving elements on the slab units after the installation of the slab units, it may be possible to fit them on the slab units before the slab units are mounted on the supporting structure. It may also be possible to combine the tactile paving elements with the edge copers, or to omit the tactile paving elements.
    Furthermore, it may be possible for the edge copers and tactile paving elements to be omitted and for the upper surface of the slab unit to be provided with a suitably textured finish. In this case, the rebated forward portion may be omitted or reduced in size to receive a relatively narrow edging strip (e.g. of stainless steel) set in epoxy mortar for example.
    The platform structure can be provided at any trackside location where it may be desired to bring a train to a halt in order to allow passengers or train operating staff to board or alight from the train or to attend to the maintenance of the exterior of the train.

    Claims (18)

    1. A railway station platform structure comprising:
      foundations (36; 36a) alongside the railway;
      upstanding supporting members (37) rising from the foundations (36; 36a);
      cross beams (38) mounted on the supporting members (37);
      longitudinal beams (42), each longitudinal beam (42) extending between a pair of the cross beams (38), there being at least two longitudinal beams (42) between each pair of cross beams (38); and
      platform units (1) on the longitudinal beams (42), the platform units (1) having side edge surfaces (8,9) extending away from the railway and having front edge surfaces (6) extending along the railway beyond the front ends of the cross beams (38);
         characterised in that:
      the cross beams (38), the longitudinal beams (42), and the platform units (1) are separate from one another;
      the cross beams (38) have cantilevered portions (38a) extending beyond the supporting members (37) towards the railway; and
      at least one of the longitudinal beams (42) extending between a pair of the cross beams (38) is mounted on the cantilevered portions (38a) of these cross beams and at least one of these longitudinal beams (42) is mounted on these cross beams at a position remote from the cantilevered portions (38a).
    2. A platform structure as claimed in claim 1, in which the supporting members comprise columns (37).
    3. A platform structure as claimed in claim 1 or 2, in which each cross beam (38) is supported by two said supporting members (37).
    4. A platform structure as claimed in any of claims 1 to 3, in which the supporting members (37) and the cross beams (38) have complementary formations which interengage to locate the cross beams relative to the supporting members, the said formations on the supporting members preferably comprising tie bars and the said formations on the cross beams preferably comprising through-holes (39).
    5. A platform structure as claimed in any of claims 1 to 4, in which the cross beams (38) are connected to the supporting members (37) solely by mechanical connection devices.
    6. A platform structure as claimed in any of claims 1 to 5, in which the cross beams (38) have upwardly and laterally open recesses (43) which accommodate end portions (42a) of the longitudinal beams (42), resilient pads (44) preferably being interposed between the said end portions (42a) and the bottoms of the said recesses (43), the longitudinal beams (42) preferably having end abutment surfaces (42b) recessed beneath the said end portions (42a).
    7. A platform structure as claimed in any of claims 1 to 6, in which the upper surfaces of the cross beams (38) are substantially flush with the upper surfaces of the longitudinal beams (42).
    8. A platform structure as claimed in any of claims 1 to 7, in which at least one pair of adjacent longitudinal beams (42), between an adjacent pair of cross beams (38), have longitudinal recesses (47) which face each other, for receiving a cable support tray (46).
    9. A platform structure as claimed in any of claims 1 to 8, in which at least one of the cross beams (38) has at least one transverse aperture (41) for the passage of a cable.
    10. A platform structure as claimed in any of claims 1 to 9, in which each platform unit (1) has a stepped upper surface (4) comprising a forward portion (4a) and a rearward portion (4b), with a step (4c) rising between the forward and rearward portions (4a, 4b), the forward portion (4a) being planar, the rearward portion preferably sloping downwardly and rearwardly from adjacent the step (4c).
    11. A platform structure as claimed in any of claims 1 to 10, in which the length of each platform unit (1) from front to rear is at least as great as its width, each platform unit (1) preferably being elongate in the-direction away from the railway.
    12. A platform structure as claimed in any of claims 1 to 11, in which the undersides of the platform units (1) have projections (32) for locating the platform units relative to the longitudinal beams (42).
    13. A platform structure as claimed in any of claims 1 to 12, in which each longitudinal beam (42) supports at least two platform units (1).
    14. A platform structure as claimed in any of claims 1 to 13, in which the platform units (1) include raised portions (27) which are aligned to constitute a plinth to the rear of the platform structure.
    15. A platform structure as claimed in any of claims 1 to 14, further comprising edge copers (23) mounted side by side on the platform units (1).
    16. A method of constructing a railway station platform structure according to claim 1, including the following steps:
      (a) constructing foundations (36; 36a) alongside the railway;
      (b) constructing upstanding supporting members (37) on the foundations;
      (c) mounting cross beams (38) on the supporting members so that the cross beams have cantilevered portions extending beyond the supporting members towards the railway;
      (d) mounting longitudinal beams (42) on the cross beams (38); and
      (e) mounting platform units (1) on the longitudinal beams (42) so that side edge (8,9) surfaces of the units extend away from the railway and front edge surfaces of the units extend along the railway beyond the ends of the cantilevered portions (38a) of the cross beams.
    17. A method as claimed in any of claim 16, further comprising the step of mounting edge copers (23) on a rebated forward portion (4a) of the upper surface of the units (1), there being preferably at least four edge copers (23) mounted side by side per unit, the width of each edge coper (23) preferably being less than its length.
    18. A method as claimed in claim 17, further comprising the step of installing paving elements (26) between the edge copers (23) and a step (4c) in the upper surface of unit (1).
    EP02745684A 2001-08-03 2002-07-25 Platform structure and construction method Expired - Lifetime EP1415047B1 (en)

    Applications Claiming Priority (3)

    Application Number Priority Date Filing Date Title
    GB0119013 2001-08-03
    GB0119013A GB2378193A (en) 2001-08-03 2001-08-03 Railway platform construction
    PCT/GB2002/003421 WO2003014478A1 (en) 2001-08-03 2002-07-25 Platform structure and construction method

    Publications (2)

    Publication Number Publication Date
    EP1415047A1 EP1415047A1 (en) 2004-05-06
    EP1415047B1 true EP1415047B1 (en) 2005-11-23

    Family

    ID=9919791

    Family Applications (2)

    Application Number Title Priority Date Filing Date
    EP02745684A Expired - Lifetime EP1415047B1 (en) 2001-08-03 2002-07-25 Platform structure and construction method
    EP02745685A Withdrawn EP1415048A1 (en) 2001-08-03 2002-07-25 Prefabricated unit for refurbishment or construction of platforms

    Family Applications After (1)

    Application Number Title Priority Date Filing Date
    EP02745685A Withdrawn EP1415048A1 (en) 2001-08-03 2002-07-25 Prefabricated unit for refurbishment or construction of platforms

    Country Status (6)

    Country Link
    US (2) US20040231286A1 (en)
    EP (2) EP1415047B1 (en)
    AT (1) ATE310853T1 (en)
    DE (1) DE60207578D1 (en)
    GB (1) GB2378193A (en)
    WO (2) WO2003014478A1 (en)

    Families Citing this family (8)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE102006060852B4 (en) * 2006-12-22 2009-02-05 Zürcher, Harry Level superstructure over the ground as walking and driving way, in particular platform
    US8544763B2 (en) * 2010-03-15 2013-10-01 Concrete Systems Inc. Prefabricated plinth for supporting a railway track
    GB2507670B (en) * 2011-05-13 2015-09-02 Tech Coper Ltd G Edging product to resist loading
    US9506257B2 (en) 2015-02-06 2016-11-29 Radical Fencing, LLC Portable resilient floating fencing floor system
    GB2562305B (en) * 2017-05-12 2020-01-15 Geoffrey Osborne Ltd A coper unit for an edge of a platform
    GB2565417B (en) * 2017-06-14 2021-09-29 Pipex Ltd Improvements in or relating to railway platforms
    CN107378520B (en) * 2017-09-05 2023-11-10 洛阳霍鑫机电科技有限公司 Stainless steel welding type combined platform
    CN110700223A (en) * 2019-10-12 2020-01-17 上海市政工程设计研究总院(集团)有限公司 Hydrophilic platform beam slab structure and construction method thereof

    Family Cites Families (10)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE3826096A1 (en) * 1988-08-01 1990-02-15 Frenzel Otto Bauunternehmen Kit for the construction of platforms
    DE58902550D1 (en) * 1988-08-01 1992-12-03 Frenzel Otto Bauunternehmen PLATFORM.
    DE4205192C2 (en) * 1992-02-20 1995-10-12 Euka Bauelemente Verkaufsgesel platform
    DE4316203A1 (en) * 1992-05-20 1993-11-25 Stewing Beton & Fertigteilwerk Railway station platform construction kit - comprises cross-beams fixed to concrete foundation and platform plates with integral beams fixed to cross-beams
    DE4308748A1 (en) * 1992-10-15 1994-04-21 Stelcon Ag Composite railway platform for passenger trains and tramways - consists of prefab. sections and support plates with legs, corresp. to walking surface
    DE9413756U1 (en) * 1994-08-26 1994-10-27 Bilfinger + Berger Bauaktiengesellschaft, 68165 Mannheim Material for raising a platform
    DE19641800A1 (en) * 1996-10-10 1998-04-23 Hering Gmbh & Co Kg Verwaltung Modular platform kit
    DE19805273B4 (en) * 1997-02-10 2007-12-06 Staubach, Helmut, Prof. high platform
    GB2343205A (en) * 1998-10-26 2000-05-03 Vencel Resil Limited Construction of track side platforms
    DE20014951U1 (en) * 2000-08-30 2000-12-28 Kommanditgesellschaft EMS Gleisbau GmbH & Co., 21217 Seevetal platform

    Also Published As

    Publication number Publication date
    WO2003014478A1 (en) 2003-02-20
    EP1415048A1 (en) 2004-05-06
    DE60207578D1 (en) 2005-12-29
    ATE310853T1 (en) 2005-12-15
    US20040231249A1 (en) 2004-11-25
    GB0119013D0 (en) 2001-09-26
    US20040231286A1 (en) 2004-11-25
    GB2378193A (en) 2003-02-05
    EP1415047A1 (en) 2004-05-06
    WO2003014479A1 (en) 2003-02-20

    Similar Documents

    Publication Publication Date Title
    US6173653B1 (en) Modular station platform construction kit
    KR101916744B1 (en) Upper structure of bridge with improved stiffness, and Bridge construction method using it
    EP1700954A2 (en) Prefabricated modular member, permanent railway for tramways and subways including said member, and process for laying the same
    KR102105230B1 (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
    JP2009243046A (en) Block for foundation
    EP1415047B1 (en) Platform structure and construction method
    KR100757958B1 (en) Insert reclamation apparatus for construction of linear induction motor panel in linear induction motor
    KR101638093B1 (en) Rahmen using hinge type pc wall and method for constructing the same
    CN111549952A (en) Installation foundation of GIS equipment
    ES2729949T3 (en) Slab for a rail vehicle and / or a vehicle on guided tires
    WO2011120186A1 (en) Track system for magnetic suspension passenger traffic line
    WO2012128411A1 (en) Manufacturing method for prefabricated solid-bed track having solid three-dimensional shape, and construction method for concrete solid-bed track using prefabricated solid-bed track manufactured by the method
    KR100881598B1 (en) Method for construction of track for linear induction motor panel in linear induction motor
    CN218090488U (en) Bridge rubber support structure for mountain rail plate beam
    SK43494A3 (en) Railway station platform edge and its use
    US5353987A (en) Railroad track system having vertically adjustable railroad tie and method of construction therefor
    JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
    JP4136959B2 (en) "How to build underground structures and installation girder"
    KR101295496B1 (en) Built-up emergency shelter stairs block for bridge
    CN115123312A (en) Subway station prefabricated type platform structure
    GB2497274A (en) Vehicle station platform system
    KR102105229B1 (en) Temporary facility construction method for underground construction fo railroad track lower pass
    KR101883173B1 (en) Structure of Slab for Bridge
    JPH10183535A (en) Platform for railroad station
    KR101696396B1 (en) Natural stone retaining wall structure

    Legal Events

    Date Code Title Description
    PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

    Free format text: ORIGINAL CODE: 0009012

    17P Request for examination filed

    Effective date: 20040302

    AK Designated contracting states

    Kind code of ref document: A1

    Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR IE IT LI LU MC NL PT SE SK TR

    AX Request for extension of the european patent

    Extension state: AL LT LV MK RO SI

    RIN1 Information on inventor provided before grant (corrected)

    Inventor name: HARMER, ANDREW, KEITH

    Inventor name: GREEN, RICHARD SUMMERS SHEPHERD

    Inventor name: WELLS, IAN JOSEPH

    Inventor name: COAKLEY, FREDERICK THOMAS ALAN

    Inventor name: ALTON, MARK ANDREW

    GRAP Despatch of communication of intention to grant a patent

    Free format text: ORIGINAL CODE: EPIDOSNIGR1

    GRAS Grant fee paid

    Free format text: ORIGINAL CODE: EPIDOSNIGR3

    GRAA (expected) grant

    Free format text: ORIGINAL CODE: 0009210

    AK Designated contracting states

    Kind code of ref document: B1

    Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR IE IT LI LU MC NL PT SE SK TR

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: IT

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

    Effective date: 20051123

    Ref country code: FI

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: BE

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: CZ

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: AT

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: LI

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: CH

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: NL

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: SK

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    REG Reference to a national code

    Ref country code: GB

    Ref legal event code: FG4D

    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: EP

    REF Corresponds to:

    Ref document number: 60207578

    Country of ref document: DE

    Date of ref document: 20051229

    Kind code of ref document: P

    REG Reference to a national code

    Ref country code: IE

    Ref legal event code: FG4D

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: GR

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060223

    Ref country code: BG

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060223

    Ref country code: SE

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060223

    Ref country code: DK

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060223

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: DE

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060224

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: ES

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060306

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: PT

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20060424

    NLV1 Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act
    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: PL

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: MC

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20060731

    PLBE No opposition filed within time limit

    Free format text: ORIGINAL CODE: 0009261

    STAA Information on the status of an ep patent application or granted ep patent

    Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: FR

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20061020

    26N No opposition filed

    Effective date: 20060824

    EN Fr: translation not filed
    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: IE

    Payment date: 20070712

    Year of fee payment: 6

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: EE

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: TR

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: LU

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20060725

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: FR

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    Ref country code: CY

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20051123

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: GB

    Payment date: 20080922

    Year of fee payment: 7

    REG Reference to a national code

    Ref country code: IE

    Ref legal event code: MM4A

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: IE

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20080725

    GBPC Gb: european patent ceased through non-payment of renewal fee

    Effective date: 20090725

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: GB

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20090725