EP0873454B2 - Process for handling heat insulation boards for facade insulation - Google Patents

Process for handling heat insulation boards for facade insulation Download PDF

Info

Publication number
EP0873454B2
EP0873454B2 EP97901005A EP97901005A EP0873454B2 EP 0873454 B2 EP0873454 B2 EP 0873454B2 EP 97901005 A EP97901005 A EP 97901005A EP 97901005 A EP97901005 A EP 97901005A EP 0873454 B2 EP0873454 B2 EP 0873454B2
Authority
EP
European Patent Office
Prior art keywords
facade
thermal insulation
insulation boards
scaffolding
heat insulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP97901005A
Other languages
German (de)
French (fr)
Other versions
EP0873454A1 (en
EP0873454B1 (en
Inventor
Fritz Rieger
Erwin Eckert
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Knauf Marmorit GmbH
Original Assignee
Marmorit GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=26022018&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=EP0873454(B2) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Marmorit GmbH filed Critical Marmorit GmbH
Publication of EP0873454A1 publication Critical patent/EP0873454A1/en
Application granted granted Critical
Publication of EP0873454B1 publication Critical patent/EP0873454B1/en
Publication of EP0873454B2 publication Critical patent/EP0873454B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/003Devices for storing material on the scaffold

Definitions

  • the invention relates to a method for processing of thermal insulation panels for facade insulation. Such a method is e.g. in DE-U-8810244 or DE-A-2852496.
  • thermal insulation boards can be, for example, EPS insulation boards or trade mineral fiber insulation boards.
  • the invention is based on the object Process for processing thermal insulation boards for to create the facade insulation with which the Thermal insulation panels time and personnel effective at the Have the facade installed.
  • the invention a method for processing thermal insulation boards proposed for the facade insulation according to the single claim.
  • Main aspect of the new approach is the superimposed thermal insulation boards no longer on the floors of the facade scaffolding but before this, i.e. outside the floors, to store. So that the floors are of the facade scaffolding no longer due to stack of Thermal insulation boards delivered.
  • the attachment of the to processing thermal insulation panels from the outside on the Facade scaffolding also has the advantage that before the actual attachment of the thermal insulation panels on the facade, the construction column first the facade scaffolding with thermal insulation boards to be processed can only be equipped with the actual Work, namely the installation of thermal insulation boards on the facade of the building.
  • the stack of thermal insulation in storage devices accommodate that over hangers be arranged on the facade scaffolding.
  • thermal insulation boards such as EPS insulation boards
  • palletized Goods should be in special storage devices be accommodated. This applies, for example for mineral fiber insulation boards, for the purpose of better adhesion on the building facade, preferably with mortar glue are pre-coated and therefore an even larger one Have weight.
  • Light insulation boards like the ones before addressed EPS plates expediently have Packaging with integrated hangers on. About these hangers can the packaged stack of light insulation boards without any problems attach to the parapet of the building facade. One or more of these can be used for each field Packaging to be attached to the facade scaffolding. If the suspension devices on both sides of the Stack are arranged, it is possible to coat the thermal insulation panels on the outside of the facade scaffolding by contacting the construction worker Breast barrier and the top thermal insulation panel Mortar brushed over to them afterwards on the building facade to install. Should the hangers not stable enough or in the middle area of the stack, so it is useful to external stack of thermal insulation boards immediately before processing on the floor in question turn off, then with the further diagnosis Continue processing the thermal insulation panels.
  • thermal insulation panels with mortar adhesive for those located on the outside of the facade scaffolding Stack on special storage devices or special packaging can be used , it is advantageous if these storage devices or packaging towards the facade scaffolding can be opened so that the coated thermal insulation panels removed from the stack from above and can be brought to the facade.
  • the two when attaching the thermal insulation panels to be carried out on the facade Process steps, namely the supply of the facade scaffolding with thermal insulation boards to be processed and the processing of the thermal insulation boards themselves, completely separate from each other. That way it is possible to use the "auxiliary activity" of the assembly of the facade scaffolding with a stack of insulation boards completely from the actual activity of attaching separate the thermal insulation panels.
  • a facade scaffold 10 has a Variety of floors 12 on the form of Metal or wooden planks are realized. These planks lie on cross members 14, each two to each other Connect parallel vertical supports 16 to each other. Immediately above the 12 floors towering skirting boards 18 for security reasons should be present. In thigh, pelvic or chest height are like the baseboards 18 on the Facade of building opposite the front of the building Scaffolding 10 breast weirs 20 arranged with the Vertical supports 16 are connected.
  • the breast weirs 20 of the facade scaffold 10 equipped with storage devices 22 the The breast brigades 20 from above via hook elements 29 embrace.
  • the storage devices are located in the lower area 22 on the outside of the baseboards 18. This Situation as well as the removal of the individual plates of the Stack 24 is shown in FIG. 2.
  • thermal insulation material 3 is a second embodiment presented the invention. Here are also outside 10 individual stacks of thermal insulation material on the facade scaffolding, however, its weight is significant is less than that of the thermal insulation material according to FIGS. 1 and 2.
  • the thermal insulation material 3 is EPS insulation boards, each on a cardboard floor 30 with laterally standing Edges rest.
  • EPS panels 32 are arranged one above the other, with the entire stack 34 is surrounded by a packaging film 36.
  • ropes 38 are fastened by hook elements 40 are passed through, which in turn are in the breast weirs 20 can be attached. More details emerge from the representation according to FIG. 4.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention concerns a process for handling heat insulation boards for facade insulation where several stacks (24, 34) of heat insulation boards (32, 26) are arranged to lie above one another outside on facade scaffolding (10). The heat insulation boards (32, 26) are provided with mortar and are applied to the facade.

Description

Die Erfindung betrifft ein Verfahren zum Verarbeiten von Wärmedämmplatten für die Fassadendämmung. Ein solches Verfahren wirdz.B. in DE-U-8810244 oder DE-A-2852496 beschrieben. Bei diesen Wärmedämmplatten kann es sich beispielsweise um EPS-Dämmplatten oder um Mineralfaserdämmplatten handeln.The invention relates to a method for processing of thermal insulation panels for facade insulation. Such a method is e.g. in DE-U-8810244 or DE-A-2852496. With these thermal insulation boards can be, for example, EPS insulation boards or trade mineral fiber insulation boards.

Beim Anbringen von Wärmedämmplatten an Gebäudefassaden wird bisher derart verfahren, daß die Wärmedämmplatten zunächst manuell oder durch Schrägaufzüge auf die einzelnen Geschoßböden des Fassadengerüsts transportiert werden. Dort lagern sie dann im Arbeitsbereich der Bauarbeiter, was deren Bewegungsfreiheit einschränkt. Hinzu kommt, daß neben den Wärmedämmplatten zumeist auch noch Behältnisse für den Mörtelkleber auf den Geschoßböden des Fassadengerüsts ruhen oder aber über die Geschoßböden ein Förderschlauch zum maschinellen Auftragen von Mörtelkleber verläuft. Da zum einen der Transport der Wärmedämmplatten auf das Gerüst umständlich und zeit- sowie personalintensiv ist und zum anderen die auf dem Gerüst gestapelten, zu verarbeitenden Wärmedämmplatten die Bewegungsfreiheit der Bauarbeiter stark einschränken, ist die bisherige Verfahrensweise in mehrerlei Hinsicht nachteilig.When attaching thermal insulation panels Building facades has so far been operated in such a way that the Thermal insulation boards first manually or by Inclined elevators on the individual floors of the Facade scaffolding are transported. They store there then in the work area of the construction workers what their freedom of movement limits. On top of that, besides the thermal insulation panels usually also contain containers for the mortar glue on the floors of the Resting facade scaffolding or over the Floor floors a conveyor hose for mechanical Applying mortar glue runs. Because on the one hand Transporting the thermal insulation panels onto the scaffolding is cumbersome and is time and personnel intensive and for others the ones stacked on the scaffold to be processed Thermal insulation boards the freedom of movement Restricting construction workers is the previous procedure disadvantageous in several respects.

Der Erfindung liegt die Aufgabe zugrunde, ein Verfahren zum Verarbeiten von Wärmedämmplatten für die Fassadendämmung zu schaffen, mit dem sich die Wärmedämmplatten zeit- und personaleffektiv an der Fassade anbringen lassen.The invention is based on the object Process for processing thermal insulation boards for to create the facade insulation with which the Thermal insulation panels time and personnel effective at the Have the facade installed.

Zur Lösung dieser Aufgabe wird mit der Erfindung ein Verfahren zum Verarbeiten von Wärmedämmplatten für die Fassadendammung nach dem einzigen Patentanspruch vorgeschlagen.To solve this problem, the invention a method for processing thermal insulation boards proposed for the facade insulation according to the single claim.

Hauptgesichtspunkt der neuen Verfahrensweise ist es, die übereinanderliegenden Wärmedämmplatten nicht mehr auf den Geschoßböden des Fassadengerüsts sondern vor diesem, d.h. außerhalb der Geschoßböden, zu lagern. Damit sind die Geschoßböden des Fassadengerüsts nicht länger durch Stapel von Wärmedämmplatten zugestellt. Die Anbringung der zu verarbeitenden Wärmedämmplatten von außen an dem Fassadengerüst hat darüber hinaus den Vorteil, daß vor dem eigentlichen Anbringen der Wärmedämmplatten an der Fassade die Baukolonne zunächst das Fassadengerüst mit zu verarbeitenden Wärmedämmplatten bestücken kann, um erst danach mit der eigentlichen Arbeit, nämlich der Anbringung der Wärmedämmplatten an der Gebäudefassade, zu beginnen. Auf diese Weise können die beiden Arbeitsgänge, nämlich die Verbringung der zu verarbeitenden Wärmedämmplatten in die einzelnen Geschosse des Fassadengerüsts und die eigentliche Anbringung der Wärmedämmplatten an der Gebäude fassade in verfahrensökonomisch optimaler Weise voneinander getrennt werden, ohne daß durch die Lagerung der Stapel von Wärmedämmplatten Bewegungsfreiraum auf den Geschoßböden des Fassadengerüsts eingebüßt wird.Main aspect of the new approach is the superimposed thermal insulation boards no longer on the floors of the facade scaffolding but before this, i.e. outside the floors, to store. So that the floors are of the facade scaffolding no longer due to stack of Thermal insulation boards delivered. The attachment of the to processing thermal insulation panels from the outside on the Facade scaffolding also has the advantage that before the actual attachment of the thermal insulation panels on the facade, the construction column first the facade scaffolding with thermal insulation boards to be processed can only be equipped with the actual Work, namely the installation of thermal insulation boards on the facade of the building. To this The two operations, namely the Shipment of the thermal insulation boards to be processed into the individual floors of the facade scaffolding and the actual installation of the thermal insulation panels on the building facade in procedural optimally be separated from each other without that by storing the stack of thermal insulation boards Freedom of movement on the floors of the facade scaffolding is lost.

Je nach dem Gewicht, welches die zu verarbeitenden Wärmedämmplatten aufweisen, ist es von Vorteil, die Wärmedämmplattenstapel in Lagerungsvorrichtungen unterzubringen, die über Aufhängevorrichtungen an dem Fassadengerüst angeordnet werden. Bei leichteren Wärmedämmplatten, wie beispielsweise EPS-Dämmplatten ist es hingegen ausreichend, wenn die Stapel durch umlaufende Gurte o.dgl. gehalten und vor dem Fassadengerüst aufgehängt werden. Palettierte Ware hingegen sollte in speziellen Lagerungsvorrichtungen untergebracht werden. Dies gilt beispielsweise für Mineralfaserdämmplatten, die zwecks besserer Haftung an der Gebäudefassade vorzugsweise mit Mörtelkleber vorbeschichtet sind und dadurch ein noch größeres Gewicht aufweisen.Depending on the weight that the to be processed Have thermal insulation panels, it is from Advantage, the stack of thermal insulation in storage devices accommodate that over hangers be arranged on the facade scaffolding. With lighter thermal insulation boards, such as EPS insulation boards, however, are sufficient if the stacks or the like by circumferential belts. kept and be hung in front of the facade scaffolding. palletized Goods, however, should be in special storage devices be accommodated. This applies, for example for mineral fiber insulation boards, for the purpose of better adhesion on the building facade, preferably with mortar glue are pre-coated and therefore an even larger one Have weight.

Leichtdämmstoffplatten, wie die bereits zuvor angesprochenen EPS-Platten weisen zweckmäßigerweise Verpackungen mit integrierten Aufhängevorrichtungen auf. Über diese Aufhängevorrichtungen läßt sich der verpackte Stapel an Leichtdämmstoffplatten problemlos an der Brustwehr der Gebäudefassade anbringen. Pro Feld können dabei ein oder mehrere derartige Verpackungen an das Fassadengerüst angehängt werden. Sofern die Aufhängevorrichtungen beidseitig des Stapels angeordnet sind, ist es möglich, die Beschichtung der Wärmedämmplatten außen am Fassadengerüst vorzunehmen, indem sich der Bauarbeiter an die Brustwehr stellt und die oberste Wärmedämmplatte mit Mörtel bestreicht, um sie danach an die Gebäudefassade anzubringen. Sollten die Aufhängevorrichtungen nicht stabil genug ausgeführt sein oder im mittleren Bereich des Stapels verlaufen, so ist es zweckmäßig, den außen lagernden Stapel an Wärmedämmplatten unmittelbar vor der Verarbeitung auf den betreffenden Geschoßboden abzustellen, um dann mit der weiteren Beund Verarbeitung der Wärmedämmplatten fortzufahren. Bei dieser Vorgehensweise werden zwar einzelne Stapel von Wärmedämmplatten auf den Geschoßböden des Fassadengerüsts gelagert. Hierbei ist jedoch anzumerken, daß jeweils nur diejenigen Plattenstapel gelagert werden, deren Platte gerade verarbeitet werden. Die später zu verarbeitenden Wärmedämmplattenstapel verbleiben außerhalb der Geschoßböden und hängen weiterhin außen an den Brustwehren des Fassadengerüsts.Light insulation boards like the ones before addressed EPS plates expediently have Packaging with integrated hangers on. About these hangers can the packaged stack of light insulation boards without any problems attach to the parapet of the building facade. One or more of these can be used for each field Packaging to be attached to the facade scaffolding. If the suspension devices on both sides of the Stack are arranged, it is possible to coat the thermal insulation panels on the outside of the facade scaffolding by contacting the construction worker Breast barrier and the top thermal insulation panel Mortar brushed over to them afterwards on the building facade to install. Should the hangers not stable enough or in the middle area of the stack, so it is useful to external stack of thermal insulation boards immediately before processing on the floor in question turn off, then with the further diagnosis Continue processing the thermal insulation panels. With this procedure, individual stacks are created of thermal insulation boards on the floors of the facade scaffolding. However, it should be noted that only those stacks of plates are stored whose plate is being processed. The stack of thermal insulation boards to be processed later remain outside the floors and hang still outside on the breastworks of the facade scaffolding.

Sofern aus Gewichtsgründen oder aus Gründen der Beschichtung der Wärmedämmplatten mit Mörtelkleber bei von außen an dem Fassadengerüst befindlichen Stapel auf spezielle Lagerungsvorrichtungen oder spezielle Verpackungen zurückgegriffen werden muß, ist es von Vorteil, wenn diese Lagerungsvorrichtungen bzw. Verpackungen zum Fassadengerüst hin geöffnet werden können, so daß die beschichteten Wärmedämmplatten von oben vom Stapel abgenommen und an die Fassade gebracht werden können.If for reasons of weight or for reasons coating the thermal insulation panels with mortar adhesive for those located on the outside of the facade scaffolding Stack on special storage devices or special packaging can be used , it is advantageous if these storage devices or packaging towards the facade scaffolding can be opened so that the coated thermal insulation panels removed from the stack from above and can be brought to the facade.

Mit dem erfindungsgemäßen Verfahren ist es erstmals möglich, die beiden beim Anbringen der Wärmedämmplatten an die Fassade durchzuführenden Verfahrensschritte, nämlich die Versorgung des Fassadengerüsts mit zu verarbeitenden Wärmedämmplatten und die Verarbeitung der Wärmedämmplatten selbst, vollständig voneinander zu trennen. Auf diese Weise ist es möglich, die "hilfsweise Tätigkeit" der Bestückung des Fassadengerüsts mit Wärmedämmplattenstapel vollständig von der eigentlichen Tätigkeit der Anbringung der Wärmedämmplatten zu trennen. Dies ist aus verfahrensökonomischen Gründen von Vorteil, da nun die Be- und Verarbeitung der Wärmedämmplatten zur Anbringung an der Gebäudefassade nicht länger durch die Versorgung des Fassadengerüsts mit Stapel von zu verarbeitenden Wärmedämmplatten unterbrochen wird und durch die Vorab-Bestückung des Fassadengerüsts mit Wärmedämmplattenstapel keinerlei Bewegungsfreiraum auf dem Fassadengerüst eingebüßt wird, da die Wärmedämmplattenstapel außerhalb des Fassadengerüsts lagern und für die Bauarbeiter leicht zugänglich sind.It is with the method according to the invention possible for the first time, the two when attaching the thermal insulation panels to be carried out on the facade Process steps, namely the supply of the facade scaffolding with thermal insulation boards to be processed and the processing of the thermal insulation boards themselves, completely separate from each other. That way it is possible to use the "auxiliary activity" of the assembly of the facade scaffolding with a stack of insulation boards completely from the actual activity of attaching separate the thermal insulation panels. This is over procedural reasons of advantage because now the treatment and processing of the thermal insulation boards No longer attach to the building facade supplying the facade scaffolding with stacks of processing thermal insulation boards is interrupted and by pre-equipping the facade scaffolding with thermal insulation board stack no freedom of movement is lost on the facade scaffolding, because the thermal insulation panels stack outside the facade scaffolding store and easily accessible for construction workers are.

Nachfolgend wird die Erfindung anhand der Figuren näher erläutert. Im einzelnen zeigen:

Fig. 1
eine Vorderansicht eines Fassadengerüsts mit an diesem außen angehängten Lagerungsvorrichtungen zur Aufnahme von Wärmedämmplattenstapeln,
Fig. 2
eine Ansicht in Richtung des Pfeils II der Fig. 1,
Fig. 3
eine Vorderansicht eines Fassadengerüsts mit an dessen Brustwehre angehängten Leichtdämmstoffstapeln mit integrierten Aufhängungsvorrichtungen und
Fig. 4
eine Ansicht in Richtung des Pfeils IV der Fig. 3.
The invention is explained in more detail below with reference to the figures. In detail show:
Fig. 1
2 shows a front view of a facade scaffold with storage devices attached to it on the outside for receiving stacks of thermal insulation panels,
Fig. 2
2 shows a view in the direction of arrow II of FIG. 1,
Fig. 3
a front view of a facade scaffolding with attached to its breast barrier light insulation material stacks with integrated suspension devices and
Fig. 4
a view in the direction of arrow IV of FIG. 3rd

Gemäß Fig. 1 weist ein Fassadengerüst 10 eine Vielzahl von Geschoßböden 12 auf, die in Form von Metall- oder Holzbohlen realisiert sind. Diese Bohlen liegen auf Querträgern 14 auf, die jeweils zwei zueinander parallele Vertikalstützen 16 untereinander verbinden. Unmittelbar oberhalb der Geschoßböden 12 befinden sich aufragende Fußleisten 18, die aus Sicherheitsgründen vorhanden sein sollten. In Oberschenkel-, Becken- bzw. Brusthöhe sind wie die Fußleisten 18 auf der der Gebäudefassade gegenüberliegenden Vorderseite des Baugerüsts 10 Brustwehre 20 angeordnet, die mit den Vertikalstützen 16 verbunden sind.1, a facade scaffold 10 has a Variety of floors 12 on the form of Metal or wooden planks are realized. These planks lie on cross members 14, each two to each other Connect parallel vertical supports 16 to each other. Immediately above the 12 floors towering skirting boards 18 for security reasons should be present. In thigh, pelvic or chest height are like the baseboards 18 on the Facade of building opposite the front of the building Scaffolding 10 breast weirs 20 arranged with the Vertical supports 16 are connected.

Gemäß Fig. 1 sind an die Brustwehre 20 käfigähnliche Lagerungsvorrichtung 22 angehängt, die an den beiden Schmalseiten und der Oberseite eines Stapels 24 von übereinanderliegenden Mineralfaserdämmplatten 26 verlaufen und (Holz-)Paletten 27 seitlich untergreifen, auf denen die Stapel 24 ruhen. Auf den dem Fassadengerüst 10 abgewandten Außenseiten dieser Lagerungsvorrichtungen 22 befinden sich Verzurrungselemente 28. Demgegenüber sind die der Gebäudefassade zugewandten Seiten der Lagerungsvorrichtungen 22 frei, so daß die Stapel 24 von dem Fassadengerüst 10 aus frei zugänglich sind. Anstelle der Lagerungsvorrichtung 22, bei der die Auflagefläche für den Stapel 24 von einer Palette 27 gebildet ist, kann ebenso gut auch eine geschlossene (viereckige) Rahmenstruktur aufweisende Lagerungsvorrichtung mit einem oberen und einem unteren sowie diese verbindendes Rahmenelement eingesetzt werden, bei der der Stapel auf dem unteren Rahmenelement ruht. Eine solche Rahmenstruktur sowie die Lagerungsvorrichtung 22 sind insbesondere zusammenlegbar bzw. -klappbar ausgeführt.1 are 20 cage-like to the weirs Storage device 22 attached to the the two narrow sides and the top of a stack 24 of superimposed mineral fiber insulation boards 26 run and reach under (wooden) pallets 27 laterally, on which the stacks 24 rest. On the Facade scaffold 10 facing away from the outside Storage devices 22 are lashing elements 28. In contrast are those of the building facade facing sides of the storage devices 22 free, so that the stack 24 from the facade scaffold 10 are freely accessible. Instead of the storage device 22, in which the bearing surface for the stack 24th is formed by a pallet 27 may as well a closed (square) frame structure Storage device with an upper and a lower and connecting frame element be used with the stack on the bottom Frame element rests. Such a framework and the storage device 22 are in particular foldable or foldable.

Vor Beginn der Verarbeitung der Wärmedämmplatten werden die Brustwehre 20 des Fassadengerüsts 10 mit Lagerungsvorrichtungen 22 bestückt, die über Hakenelemente 29 von oben die Brustwehren 20 umgreifen. Im unteren Bereich liegen die Lagerungsvorrichtungen 22 außen an den Fußleisten 18 an. Diese Situation sowie die Entnahme der einzelnen Platten der Stapel 24 ist in Fig. 2 dargestellt.Before starting the processing of the thermal insulation boards the breast weirs 20 of the facade scaffold 10 equipped with storage devices 22, the The breast brigades 20 from above via hook elements 29 embrace. The storage devices are located in the lower area 22 on the outside of the baseboards 18. This Situation as well as the removal of the individual plates of the Stack 24 is shown in FIG. 2.

In Fig. 3 ist ein zweites Ausführungsbeispiel der Erfindung dargestellt. Auch hier befinden sich außen am Fassadengerüst 10 einzelne Stapel von Wärmedämm-Material, dessen Gewicht jedoch wesentlich geringer ist als dasjenige des Wärmedämm-Materials gemäß den Fign. 1 und 2. Bei dem Wärmedämm-Material gemäß Fig. 3 handelt es sich um EPS-Dämmplatten, die jeweils auf einem Pappboden 30 mit seitlich hochstehenden Rändern ruhen. Mehrere EPS-Platten 32 sind übereinander angeordnet, wobei der gesamte Stapel 34 von einer Verpackungsfolie 36 umgeben ist. An den hochstehenden Seitenrändern der Bodenplatte 30 sind Seile 38 befestigt, die durch Hakenelemente 40 hindurchgeführt sind, welche ihrerseits in die Brustwehre 20 einhängbar sind. Weitere Einzelheiten ergeben sich aus der Darstellung gemäß Fig. 4.3 is a second embodiment presented the invention. Here are also outside 10 individual stacks of thermal insulation material on the facade scaffolding, however, its weight is significant is less than that of the thermal insulation material according to FIGS. 1 and 2. With the thermal insulation material 3 is EPS insulation boards, each on a cardboard floor 30 with laterally standing Edges rest. Several EPS panels 32 are arranged one above the other, with the entire stack 34 is surrounded by a packaging film 36. On the upstanding side edges of the base plate 30 ropes 38 are fastened by hook elements 40 are passed through, which in turn are in the breast weirs 20 can be attached. More details emerge from the representation according to FIG. 4.

Claims (1)

  1. Process for treating heat insulation plates for facade insulation, wherein
    the heat insulation plates (32;26) placed one above the other to form a stack (24) are accommodated in storage devices (22) having suspension devices,
    the storage devices (22) are arranged on the outside of a facade scaffolding (10),
    the uppermost heat insulation plates (32;26) of the stacks (24) are provided with mortar, and
    the heat insulation plates (32;26) treated this way are removed from the storage devices (22) open towards the facade scaffolding (10) and are fixed to the facade,
    with the storage devices (22) being suspended in the bars (20) of the facade scaffolding (10) and resting, from outside, at the level of the next floor bottom (12) located below the bar (20) against the baseboard (18) of the floor bottom (12) and being supported there.
EP97901005A 1996-01-12 1997-01-11 Process for handling heat insulation boards for facade insulation Expired - Lifetime EP0873454B2 (en)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
DE19600907 1996-01-12
DE19600907 1996-01-12
DE19648459 1996-11-22
DE19648459 1996-11-22
PCT/EP1997/000115 WO1997025494A1 (en) 1996-01-12 1997-01-11 Process for handling heat insulation boards for facade insulation

Publications (3)

Publication Number Publication Date
EP0873454A1 EP0873454A1 (en) 1998-10-28
EP0873454B1 EP0873454B1 (en) 1999-09-22
EP0873454B2 true EP0873454B2 (en) 2004-01-02

Family

ID=26022018

Family Applications (1)

Application Number Title Priority Date Filing Date
EP97901005A Expired - Lifetime EP0873454B2 (en) 1996-01-12 1997-01-11 Process for handling heat insulation boards for facade insulation

Country Status (4)

Country Link
EP (1) EP0873454B2 (en)
AT (1) ATE184950T1 (en)
DE (2) DE19700787A1 (en)
WO (1) WO1997025494A1 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19751187C2 (en) * 1997-11-19 2002-10-24 Rux Guenter Gmbh Scaffolding with attachable building material collector
DE19825365C2 (en) * 1998-06-06 2003-10-30 Rockwool Mineralwolle Device for arranging and storing packaging units
DE19825366C2 (en) * 1998-06-06 2003-11-13 Rockwool Mineralwolle Packaging Unit
DE19831974C2 (en) * 1998-07-16 2001-07-05 Sto Ag Use of a device for providing insulation boards
DE20018106U1 (en) * 2000-10-23 2001-01-11 Saint Gobain Isover G & H Ag Transport unit made of insulation packages
PL375393A1 (en) 2002-08-09 2005-11-28 Deutsche Rockwool Mineralwoll Gmbh & Co.Ohg Device for vertically conveying palletless packaging units for plate-shaped construction materials
DE202012102267U1 (en) * 2012-06-19 2013-09-23 JOMA Dämmstoffwerk GmbH Insulation board packaging
DE102015016064B4 (en) 2015-12-10 2018-09-13 Rolf Adams Mounting frame with walk-in treads in different height ranges with a device for holding and temporary storage of insulation materials

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3717220A (en) * 1971-02-12 1973-02-20 W Kuiper Construction conveying system and components therefor
DE2852496A1 (en) * 1978-12-05 1980-06-19 Walter Duerr Auxiliary frame for covering building facades - comprises wire basket for foam panels hooking onto platform safety rail
DE8409221U1 (en) * 1984-03-26 1985-11-07 Schütz, Horst, 5239 Unnau Device for providing and / or carrying plates
DE8810244U1 (en) * 1988-05-05 1988-10-13 Möller, Hans, 3445 Waldkappel Device for applying masses that can be attached to building scaffolding
FR2631061B1 (en) * 1988-05-06 1991-04-12 Bouygues Sa DEVICE FOR FACILITATING THE PROVISION OF PRODUCTS ON A SCAFFOLD
DE8910626U1 (en) * 1989-09-06 1989-10-26 Humpert, Uwe, 4815 Schloß Holte-Stukenbrock Conveying device for stones or similar
US5158023A (en) * 1991-02-21 1992-10-27 Allen Tony L Scaffold table for sheet rock finishers
WO1995033105A1 (en) * 1994-05-26 1995-12-07 Koch Marmorit Gmbh Process for gluing cut sections of mineral wool panel

Also Published As

Publication number Publication date
EP0873454A1 (en) 1998-10-28
EP0873454B1 (en) 1999-09-22
WO1997025494A1 (en) 1997-07-17
DE59700467D1 (en) 1999-10-28
ATE184950T1 (en) 1999-10-15
DE19700787A1 (en) 1997-07-17

Similar Documents

Publication Publication Date Title
EP0873454B2 (en) Process for handling heat insulation boards for facade insulation
DE2255346B2 (en) System for the automatic handling of containers between transport vehicles and a warehouse
EP0873455B1 (en) Storage device for making available stackable building materials especially heat insulation boards on building or facade scaffolding
DE2833439C2 (en) Device for permanent cladding of surfaces, in particular walls or inner roof surfaces of buildings, with panels
DE2021461A1 (en) Bracket for wall cladding panels
DE3729139C1 (en) Arrangement for the automatic manufacturing of industrial products
DE580192C (en) Device for inclined conveying of piece goods, in particular bags
DE10334486B4 (en) fasteners
DE2600095A1 (en) Flat item hoisting equipment - has rope reeved over pulley on beam mounted in building top floor
DE4300672C2 (en) Transport pallet
DE19710784A1 (en) Method of fitting thermal insulation boards to outer walls
DE2109666B2 (en) Box-shaped transport container for large, bulky goods
DE8023331U1 (en) Transport pallet
DE202006016133U1 (en) Bearing lift arrangement used in a factory and warehouse extends over more than two floors of a building in which the ceilings of each floor have passages for a lift
DE4420827C2 (en) Device for storing and transporting formwork panels and formwork accessories
DE806840C (en) Transport device consisting of a conveyor belt, in particular for construction purposes
EP1211201A1 (en) Device for the automatic handling and intermediate buffering of suspended components
EP4353649A1 (en) Method for packaging elevator components of a complete elevator system
DE29906684U1 (en) Storage device for providing stackable building material, such as thermal insulation panels, on a building or facade scaffold
DE3631737A1 (en) Device for supporting articles of different shapes and dimensions on pallets
DE10238954A1 (en) Tie-bar for carrying flat, large-surfaced crates edgewise on has supporting beam, vertical claws, thrust pieces, adjusting elements and two-armed lever securing elements
DE7344898U (en) Device for loading and unloading a motor vehicle with a pallet
DE7132108U (en) Construction elevator
DD219241A1 (en) DEVICE FOR INSTALLING WINDOWS AND DOORS IN CONSTRUCTION ELEMENTS
DE29521252U1 (en) Device for sealing off the source of the fire carried by a belt conveyor

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19980708

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT CH DE GB LI

GRAG Despatch of communication of intention to grant

Free format text: ORIGINAL CODE: EPIDOS AGRA

17Q First examination report despatched

Effective date: 19981218

GRAG Despatch of communication of intention to grant

Free format text: ORIGINAL CODE: EPIDOS AGRA

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

RBV Designated contracting states (corrected)

Designated state(s): AT CH DE GB LI

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: MARMORIT GMBH

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT CH DE GB LI

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 19990922

REF Corresponds to:

Ref document number: 184950

Country of ref document: AT

Date of ref document: 19991015

Kind code of ref document: T

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: TROESCH SCHEIDEGGER WERNER AG

Ref country code: CH

Ref legal event code: EP

REF Corresponds to:

Ref document number: 59700467

Country of ref document: DE

Date of ref document: 19991028

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 19991214

PLAV Examination of admissibility of opposition

Free format text: ORIGINAL CODE: EPIDOS OPEX

PLBQ Unpublished change to opponent data

Free format text: ORIGINAL CODE: EPIDOS OPPO

PLBI Opposition filed

Free format text: ORIGINAL CODE: 0009260

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

26 Opposition filed

Opponent name: DEUTSCHE ROCKWOOL MINERALWOLL-GMBH

Effective date: 20000619

PLAV Examination of admissibility of opposition

Free format text: ORIGINAL CODE: EPIDOS OPEX

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PLAW Interlocutory decision in opposition

Free format text: ORIGINAL CODE: EPIDOS IDOP

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20021219

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20030110

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20030127

Year of fee payment: 7

PLAW Interlocutory decision in opposition

Free format text: ORIGINAL CODE: EPIDOS IDOP

PUAH Patent maintained in amended form

Free format text: ORIGINAL CODE: 0009272

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: PATENT MAINTAINED AS AMENDED

27A Patent maintained in amended form

Effective date: 20040102

AK Designated contracting states

Kind code of ref document: B2

Designated state(s): AT CH DE GB LI

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040111

REG Reference to a national code

Ref country code: CH

Ref legal event code: AEN

Free format text: AUFRECHTERHALTUNG DES PATENTES IN GEAENDERTER FORM

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040131

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040131

GBV Gb: ep patent (uk) treated as always having been void in accordance with gb section 77(7)/1977 [no translation filed]

Effective date: 19990922

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

EN Fr: translation not filed
PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20070307

Year of fee payment: 11

PLAB Opposition data, opponent's data or that of the opponent's representative modified

Free format text: ORIGINAL CODE: 0009299OPPO

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20080801