EP0451926B1 - Method for inserting an essentially vertical screen in the ground - Google Patents

Method for inserting an essentially vertical screen in the ground Download PDF

Info

Publication number
EP0451926B1
EP0451926B1 EP19910200886 EP91200886A EP0451926B1 EP 0451926 B1 EP0451926 B1 EP 0451926B1 EP 19910200886 EP19910200886 EP 19910200886 EP 91200886 A EP91200886 A EP 91200886A EP 0451926 B1 EP0451926 B1 EP 0451926B1
Authority
EP
European Patent Office
Prior art keywords
insertion sheet
panel
sheeting
trench
clamping bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP19910200886
Other languages
German (de)
French (fr)
Other versions
EP0451926A1 (en
Inventor
Arie Willem Van Den Berg
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hollandsche Beton Groep NV
Original Assignee
Hollandsche Beton Groep NV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hollandsche Beton Groep NV filed Critical Hollandsche Beton Groep NV
Publication of EP0451926A1 publication Critical patent/EP0451926A1/en
Application granted granted Critical
Publication of EP0451926B1 publication Critical patent/EP0451926B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material

Definitions

  • the invention relates to a method for placing an essentially vertical screen in the ground comprising:
  • Such a method is described in DE-A-3540270 and is used for the isolation of polluted ground and groundwater and for well drainage.
  • the flexible sheeting panels are, for example, 2-3 meters wide.
  • the insertion of the panels by means of an insertion sheet takes place in such a way that the locks are placed under little or no load.
  • the bentonite sheeting screen must be connected to a watertight layer, for example of a natural clay or an injected synthetic layer.
  • the screens can be of a great height, for example approximately 30 meters. Problems then occur with unrolling each panel into the vertical position from the rolled-up state and connecting one edge of the panel to the top edge of the insertion sheet.
  • each sheeting panel is fixed to the insertion sheet near the top edge thereof while said insertion sheet is in the trench, that the sheeting panel is taken into a vertically downward hanging position by pulling said insertion sheet up out of the trench thereby unrolling the sheeting panel from a rolled up state, and that before the combination of insertion sheet and sheeting panel connected to it is lowered in the trench, this combination is moved over approximately the width of the sheeting panel in the longitudinal direction of the trench.
  • the function of the insertion sheet is not only to press a panel into the ground, but also to unroll the panel from the rolled-up state into a vertical position, after which it is ready for pressing into the ground trench.
  • the method according to the invention is of great advantage.
  • a clamping bar fixed to the sheet can be used in order to fix a top edge of each panel to the insertion sheet.
  • Each sheeting panel can be pulled taut by a device being fitted between the clamping bar and the top side of the insertion sheet, by means of which a limited almost vertical displacement of the clamping bar is possible.
  • This device comprises a cable which is fixed on the clamping bar and runs over a pulley provided on the top edge of the insertion sheet to the rear side of the insertion sheet, where it is tensioned on the insertion sheet.
  • the clamping bar It is further possible for the clamping bar to be guided additionally in the vertical direction through the fact that the clamping bar with guide pins projecting through slotted holes into the clamping bar and fixed on the insertion sheet can move freely over a certain vertical distance if the tensioning device is out of action.
  • Other designs are also possible for tensioning the sheeting panel.
  • the invention also relates to an insertion sheet intended for placing a screen in the ground, in which a clamping bar is fixed near the top edge of said sheet and the fixing of the clamping bar can be such that a limited displacement of the clamping bar towards and away from the top edge of the sheet is possible as disclosed in BE-A-62742.
  • a pulley is provided on the top edge of the insertion sheet for guiding a tensioning cable fixed on the clamping bar.
  • the invention also relates to a wind clip for connecting a sheeting panel to an insertion sheet during carrying out of the above mentioned method, in which the clip has two flanges lying opposite each other which are intented for insertion through openings in transverse members in the insertion sheet, and in which at least one of the side parts of the clip is made slidable or hinged, and securing means are present for the purpose of securing said slidable or hinged side part.
  • Figure 1 shows a vertical section through a sheeting panel fitted in a ground trench, with anchor and insertion sheet projecting into it.
  • Figure 2 shows a vertical section of said ground trench during unrolling of the next sheeting panel.
  • Figure 3 shows a vertical section of the sheeting panel hanging from the top edge of the sheet above ground level and above the trench.
  • Figure 4 shows a top view of a ground trench with sheeting panels to be placed in the ground according to the invention.
  • Figure 5 shows a detail of the insertion sheet with clamping bar on a larger scale.
  • Figure 6 shows a cross-section of a screen with insertion sheet at the position of a wind clip.
  • FIGs 1 to 4 illustrate the way in which the sheeting panels of a vertical ground screen are inserted in succession in a ground trench 1 filled with a bentonite-containing mixture.
  • a sheeting panel 3 is indicated by 3a in Figure 1
  • the next sheeting panel is indicated by 3b in Figures 2 and 3.
  • Each of the panels has on the two vertical side edges a locking part, in which case a locking part 2a on a side edge of a panel can be connected, for example in the manner described in Dutch patent applications 8301918 or 8901423, to a locking part 2b on the other side edge of the next panel.
  • the panels have at their bottom edge a thickened part 4 projecting into a steel anchor 5.
  • the sheet 6 is first moved in the lengthwise direction of the trench over about the width of a panel, and only then is the panel 3b pushed into the ground trench by the sheet 6, it being ensured that the locking parts facing each other on the panels 3a and 3b engage with each other.
  • the clips 9 are also removed in succession at ground level.
  • the panel 3b assumes the position which is shown with regard to panel 3a in Figure 1, and the placing in the ground of the next panel in accordance with the cycle described above can begin. It will be clear that the wall formed from the panels can be of any desired length.
  • the clamping bar 8 can be fixed in such a way to the insertion sheet 6 that the latter can undergo a limited vertical displacement, and a tensioning cable 10 can be fixed to the clamping bar 8, which cable is guided over a pulley 11 fitted on the insertion sheet 6 to a mechanical, hydraulic or pneumatic cable tensioning device of known design (not shown). Tensioning the cable 10 pulls the panel taut.
  • the clamping bar 8 has two clamping jaws 8a, 8b between which the top edge of a panel 3 can be clamped.
  • the clamping jaws 8a, 8b can be operated by mechanical, hydraulic or pneumatic devices.
  • two or more pins 13 projecting through the vertical slotted holes 14 into the clamping bar are welded to the sheet. Heads 15 welded to the pins 13 prevent the pins from coming out of the slotted holes.
  • FIG. 6 An embodiment of the insertion sheet 6 with a wind clip 9 is shown in Figure 6.
  • the U-shaped clip has two flanges 16a, 16b which lie opposite each other and project through openings in transverse plates 17a, 17b of the insertion sheet 6.
  • parts 17a, 17b, 17c and 17d are components of the reinforcement structure 17 of insertion sheet 6.
  • the member 6 has semi-cylindrical vertical rods 18a, 18b which are fitted on it and can engage on a panel 3 and clamp it against spacers 19a, 19b welded on the wind clip 9 concerned.
  • One of the side parts of the clip 9 is hinged by means of a rotary pin 20 and can be secured in the position shown by means of a removable securing pin 21.
  • a removable securing pin 21 When the securing pin is removed the end part can be turned away to the position shown by means of a removable securing pin 21.
  • the end part When the securing pin is removed the end part can be turned away to the position shown by dotted and dashed lines in Figure 6, and the side part of the clip can be pivoted into a position in which the flange 16b projects through an opening of the transverse plate 17b.
  • a sheeting panel 3 can be taken by the insertion sheet 6 into a vertical position above ground level and that sheeting panel 3 can subsequently be pulled taut, following which insertion sheet 6 places this sheeting panel next to the previous panel 3 after being slid along over a panel width in the lengthwise direction of the trench.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Description

  • The invention relates to a method for placing an essentially vertical screen in the ground comprising:
    • digging a trench in the ground,
    • feeding a mixture into said trench, such as a bentonite-water mixture or a bentonite-cement-water mixture which can form an impenetrable layer,
    • connecting a sheeting panel to an insertion sheet,
    • lowering the insertion sheet with sheeting panel into the mixture in such a way that a vertical locking edge of said panel and a vertical locking edge of a panel already placed in the trench slide into each other,
    • breaking the connection between the insertion sheet and the sheeting panel,
    • pulling up the insertion sheet so that the next sheeting panel can be connected to said sheet,

    which actions can be repeated until a tight sheeting wall of the desired length and shape is formed from the sheeting panels in the trench.
  • Such a method is described in DE-A-3540270 and is used for the isolation of polluted ground and groundwater and for well drainage. The flexible sheeting panels are, for example, 2-3 meters wide. The insertion of the panels by means of an insertion sheet takes place in such a way that the locks are placed under little or no load. At the bottom side the bentonite sheeting screen must be connected to a watertight layer, for example of a natural clay or an injected synthetic layer. In particular, in the case of well drainage the screens can be of a great height, for example approximately 30 meters. Problems then occur with unrolling each panel into the vertical position from the rolled-up state and connecting one edge of the panel to the top edge of the insertion sheet.
  • The object of the invention is to solve these problems, and to this end the method mentioned in the preamble is characterized in that, each sheeting panel is fixed to the insertion sheet near the top edge thereof while said insertion sheet is in the trench, that the sheeting panel is taken into a vertically downward hanging position by pulling said insertion sheet up out of the trench thereby unrolling the sheeting panel from a rolled up state, and that before the combination of insertion sheet and sheeting panel connected to it is lowered in the trench, this combination is moved over approximately the width of the sheeting panel in the longitudinal direction of the trench.
  • In the application of the invention the function of the insertion sheet is not only to press a panel into the ground, but also to unroll the panel from the rolled-up state into a vertical position, after which it is ready for pressing into the ground trench. In particular in the case of sheeting panels of great height (for example, about 30 meters) the method according to the invention is of great advantage.
  • In order to prevent the panel hanging from the insertion sheet above ground level from being beaten to and fro by the wind, when each sheeting panel is being raised above ground level by means of the insertion sheet clips can be fixed a certain vertical distance apart on the sheet, which clips fall round the sheeting panel and protect it from the wind, and which are removed on by one when the panel is being placed in the ground.
  • A clamping bar fixed to the sheet can be used in order to fix a top edge of each panel to the insertion sheet.
  • Each sheeting panel can be pulled taut by a device being fitted between the clamping bar and the top side of the insertion sheet, by means of which a limited almost vertical displacement of the clamping bar is possible. This device comprises a cable which is fixed on the clamping bar and runs over a pulley provided on the top edge of the insertion sheet to the rear side of the insertion sheet, where it is tensioned on the insertion sheet. It is further possible for the clamping bar to be guided additionally in the vertical direction through the fact that the clamping bar with guide pins projecting through slotted holes into the clamping bar and fixed on the insertion sheet can move freely over a certain vertical distance if the tensioning device is out of action. Other designs are also possible for tensioning the sheeting panel.
  • The invention also relates to an insertion sheet intended for placing a screen in the ground, in which a clamping bar is fixed near the top edge of said sheet and the fixing of the clamping bar can be such that a limited displacement of the clamping bar towards and away from the top edge of the sheet is possible as disclosed in BE-A-62742.
  • According to the invention a pulley is provided on the top edge of the insertion sheet for guiding a tensioning cable fixed on the clamping bar.
  • Finally, the invention also relates to a wind clip for connecting a sheeting panel to an insertion sheet during carrying out of the above mentioned method, in which the clip has two flanges lying opposite each other which are intented for insertion through openings in transverse members in the insertion sheet, and in which at least one of the side parts of the clip is made slidable or hinged, and securing means are present for the purpose of securing said slidable or hinged side part.
  • The invention will now be explained in greater detail with reference to the figures.
  • Figure 1 shows a vertical section through a sheeting panel fitted in a ground trench, with anchor and insertion sheet projecting into it.
  • Figure 2 shows a vertical section of said ground trench during unrolling of the next sheeting panel.
  • Figure 3 shows a vertical section of the sheeting panel hanging from the top edge of the sheet above ground level and above the trench.
  • Figure 4 shows a top view of a ground trench with sheeting panels to be placed in the ground according to the invention.
  • Figure 5 shows a detail of the insertion sheet with clamping bar on a larger scale.
  • Figure 6 shows a cross-section of a screen with insertion sheet at the position of a wind clip.
  • Figures 1 to 4 illustrate the way in which the sheeting panels of a vertical ground screen are inserted in succession in a ground trench 1 filled with a bentonite-containing mixture. A sheeting panel 3 is indicated by 3a in Figure 1, and the next sheeting panel is indicated by 3b in Figures 2 and 3. Each of the panels has on the two vertical side edges a locking part, in which case a locking part 2a on a side edge of a panel can be connected, for example in the manner described in Dutch patent applications 8301918 or 8901423, to a locking part 2b on the other side edge of the next panel. The panels have at their bottom edge a thickened part 4 projecting into a steel anchor 5.
  • When a panel is being pressed into the ground use is made of a steel insertion sheet 6 which with its bottom edge also projects into the anchor 5. The anchor is provided with slanting plates 7a and 7b which centre the panel in the ground trench when it is being pressed down.
  • After a panel 3 (for example panel 3a) has been pressed fully into the ground trench (Figure 1), the insertion sheet 6 is pulled up.
  • The edge of the next panel 3b, which is in the rolled-up state, is then fixed by means of a clamping bar 8 to the top part of the insertion sheet 6, and the insertion sheet is pulled out of the ground trench by means of a hoisting structure (not shown), during which the panel 3b unrolls. In the fully raised position of the panel 3b, as shown in Figure 3, the panel 3b hangs down along the sheet 6. If there is wind of any significance, during the raising of the sheet and unrolling of the panel, clips 9 are provided spaced apart and are fixed to the sheet and clamp the panel against the insertion sheet. Details of the clips will be explained.
  • After a new anchor 5 is fitted on the bottom edge of the panel 3b and the sheet 6, the sheet 6 is first moved in the lengthwise direction of the trench over about the width of a panel, and only then is the panel 3b pushed into the ground trench by the sheet 6, it being ensured that the locking parts facing each other on the panels 3a and 3b engage with each other. The clips 9 are also removed in succession at ground level. Finally, the panel 3b assumes the position which is shown with regard to panel 3a in Figure 1, and the placing in the ground of the next panel in accordance with the cycle described above can begin. It will be clear that the wall formed from the panels can be of any desired length.
  • In order to be able to tension a panel and pull it flat and thereby, inter alia, to reduce the influence of the wind even further, the clamping bar 8 can be fixed in such a way to the insertion sheet 6 that the latter can undergo a limited vertical displacement, and a tensioning cable 10 can be fixed to the clamping bar 8, which cable is guided over a pulley 11 fitted on the insertion sheet 6 to a mechanical, hydraulic or pneumatic cable tensioning device of known design (not shown). Tensioning the cable 10 pulls the panel taut.
  • The clamping bar 8 has two clamping jaws 8a, 8b between which the top edge of a panel 3 can be clamped. The clamping jaws 8a, 8b can be operated by mechanical, hydraulic or pneumatic devices. In order to give the bar its limited vertical displacement possibilities relative to the insertion sheet, two or more pins 13 projecting through the vertical slotted holes 14 into the clamping bar are welded to the sheet. Heads 15 welded to the pins 13 prevent the pins from coming out of the slotted holes.
  • An embodiment of the insertion sheet 6 with a wind clip 9 is shown in Figure 6. The U-shaped clip has two flanges 16a, 16b which lie opposite each other and project through openings in transverse plates 17a, 17b of the insertion sheet 6. In this case parts 17a, 17b, 17c and 17d are components of the reinforcement structure 17 of insertion sheet 6. At the position of the corner pieces the member 6 has semi-cylindrical vertical rods 18a, 18b which are fitted on it and can engage on a panel 3 and clamp it against spacers 19a, 19b welded on the wind clip 9 concerned.
  • One of the side parts of the clip 9 is hinged by means of a rotary pin 20 and can be secured in the position shown by means of a removable securing pin 21. When the securing pin is removed the end part can be turned away to the position shown by means of a removable securing pin 21. When the securing pin is removed the end part can be turned away to the position shown by dotted and dashed lines in Figure 6, and the side part of the clip can be pivoted into a position in which the flange 16b projects through an opening of the transverse plate 17b.
  • For the performance of the invention it is essential that a sheeting panel 3 can be taken by the insertion sheet 6 into a vertical position above ground level and that sheeting panel 3 can subsequently be pulled taut, following which insertion sheet 6 places this sheeting panel next to the previous panel 3 after being slid along over a panel width in the lengthwise direction of the trench.

Claims (5)

  1. Method for placing an essentially vertical screen in the ground comprising:
    - digging a trench (1) in the ground,
    - feeding a mixture into said trench, such as a bentonite-water mixture or a bentonite-cement-water mixture which can form an impenetrable layer,
    - connecting a sheeting panel (3) to an insertion sheet (6),
    - lowering the insertion sheet with sheeting panel into the mixture in such a way that a vertical locking edge (2) of said panel and a vertical locking edge of a panel already placed in the trench slide into each other,
    - breaking the connection between the insertion sheet and the sheeting panel,
    - pulling up the insertion sheet so that the next sheeting panel can be connected to said insertion sheet,
    which actions can be repeated until a tight sheeting wall of the desired length and shape is formed from the sheeting panels in the trench, characterized in that each sheeting panel (3) is fixed to the insertion sheet (6) near the top edge thereof while said insertion sheet is in the trench, that the sheeting panel is taken into a vertically downward hanging position by pulling said insertion sheet up out of the trench thereby unrolling the sheeting panel from a rolled up state, and that before the combination of insertion sheet and sheeting panel connected to it is lowered in the trench, this combination is moved over approximately the width of the sheeting panel in the longitudinal direction of the trench.
  2. Method according to claim 1, characterized in that, when each sheeting panel (3) is being raised above ground level by means of the insertion sheet, clips (9) are fixed a vertical distance apart on the insertion sheet, which clips fall round the sheeting panel in order to protect it from the wind, and which clips are removed one by one when the panel is being placed in the ground.
  3. Method according to claim 1 or 2, characterized in that a clamping bar (8) fixed to the insertion sheet (6)is used for fixing an edge of each sheeting panel (3) to the insertion sheet, and that pins (13) projecting through vertical slotted holes (14) in the insertion sheet or the clamping bar extend between the clamping bar and the insertion sheet and permit a limited vertical displacement of the clamping bar relative to the insertion sheet, and that the clamping bar is pulled upwards over a limited distance by a cable (10) running over a pulley (11) provided on the top edge of the insertion sheet for pulling the sheeting panel in question taut.
  4. Insertion member (6) intended for placing a screen in the ground according to the method of claim 3, wherein at the top edge of the insertion sheet a clamping bar (8) is fixed in such a way that the limited displacement of the clamping bar towards and away from the top edge of the insertion sheet is possible, characterized in that a pulley (11) is provided on the top edge of the insertion sheet for guiding a tensioning cable (10) fixed on the clamping bar.
  5. Wind clip (9) for connecting a sheeting panel to an insertion sheet when carrying out the method according to claim 2, characterized in that the clip has two flanges (16a, 16b) lying opposite each other which are intended for insertion through openings in transverse members (17a, 17b) of the insertion sheet, and in that at least one of the side parts of the clips is made slidable or hinged, while securing means (21) are present for the purpose of securing said slidable or hinged side part.
EP19910200886 1990-04-12 1991-04-12 Method for inserting an essentially vertical screen in the ground Expired - Lifetime EP0451926B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL9000874A NL9000874A (en) 1990-04-12 1990-04-12 PROCESS FOR GROUNDING A MAIN VERTICAL SCREEN.
NL9000874 1990-04-12

Publications (2)

Publication Number Publication Date
EP0451926A1 EP0451926A1 (en) 1991-10-16
EP0451926B1 true EP0451926B1 (en) 1993-04-21

Family

ID=19856922

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19910200886 Expired - Lifetime EP0451926B1 (en) 1990-04-12 1991-04-12 Method for inserting an essentially vertical screen in the ground

Country Status (3)

Country Link
EP (1) EP0451926B1 (en)
DE (1) DE69100065T2 (en)
NL (1) NL9000874A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10354799B4 (en) * 2003-11-21 2007-04-19 Wirz, Christian H. Arrangement for a dike seal and a dike heightening
CN105507338B (en) * 2015-12-24 2018-06-05 李金良 A kind of campshed grafting rubble formula supporting water blockoff diaphragm wall is molded engineering method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE627142A (en) *
DE3540270A1 (en) * 1985-11-13 1987-05-14 Wayss & Freytag Ag Method of producing a diaphragm wall and apparatus for carrying out the method

Also Published As

Publication number Publication date
DE69100065T2 (en) 1993-11-04
NL9000874A (en) 1991-11-01
DE69100065D1 (en) 1993-05-27
EP0451926A1 (en) 1991-10-16

Similar Documents

Publication Publication Date Title
US4909674A (en) Underground continuous impervious wall and method for installing same
EP0854238A2 (en) Transportable and collapsible barrier in particular against high water
EP0451926B1 (en) Method for inserting an essentially vertical screen in the ground
GB2086456A (en) Flood barrier
CN109235445B (en) Steel sheet pile and foundation pit supporting construction method
RU179112U1 (en) GEOBOX
CN210216385U (en) Drainage board collection device and contain device's picture peg machine
EP3916167A1 (en) Method for laying channel system components in the ground
DE19739920A1 (en) Method and shoring device for pipe installation
JP3735519B2 (en) Concrete compaction method and apparatus
SU1084357A1 (en) Method of construction counter-filtration diaphragm of flexible webs and soil filler
JPH0351367Y2 (en)
DE19525590A1 (en) Building-trench formation method below water-table - removes earth along inside of one wall and forms anchroing points below table for later tightening from water-displacing box
DE4303742C1 (en) Dewatering ground with high water content
CN217400388U (en) Waterproofing membrane binding off fixing device
KR100404128B1 (en) Placementing Method of Reinforcing Strips for Constructing Precast Concrete Facing Panel and Pulling-up Device of Reinforcing Strips
CN116446336A (en) Flow blocking device for flood control of garage
EP0811723B1 (en) Support for trench shoring device
EP0026782B1 (en) Soil and water-retaining wall, composed of prefabricated plate elements
JP2872537B2 (en) Water blocking wall and method of constructing the same
JPH0626048A (en) Slope surface forming method
JPS6133072Y2 (en)
KR200235097Y1 (en) A apparatus for approach construction of lay type retaining wall
JP3395994B2 (en) Wall connection method
KR100410614B1 (en) A pulling apparatus for stainless steel wire mesh

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): BE DE GB LU NL

17P Request for examination filed

Effective date: 19911031

17Q First examination report despatched

Effective date: 19911205

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): BE DE GB LU NL

REF Corresponds to:

Ref document number: 69100065

Country of ref document: DE

Date of ref document: 19930527

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
EPTA Lu: last paid annual fee
PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20000323

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20000418

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: LU

Payment date: 20000421

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20000427

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20000428

Year of fee payment: 10

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20010412

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20010412

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20010430

BERE Be: lapsed

Owner name: HOLLANDSCHE BETON GROEP N.V.

Effective date: 20010430

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20011101

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20010412

NLV4 Nl: lapsed or anulled due to non-payment of the annual fee

Effective date: 20011101

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20020201