DE4231980C2 - Groundwater basin made of plastic geomembranes without solid construction - Google Patents

Groundwater basin made of plastic geomembranes without solid construction

Info

Publication number
DE4231980C2
DE4231980C2 DE4231980A DE4231980A DE4231980C2 DE 4231980 C2 DE4231980 C2 DE 4231980C2 DE 4231980 A DE4231980 A DE 4231980A DE 4231980 A DE4231980 A DE 4231980A DE 4231980 C2 DE4231980 C2 DE 4231980C2
Authority
DE
Germany
Prior art keywords
groundwater
plastic
groundwater basin
tub
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
DE4231980A
Other languages
German (de)
Other versions
DE4231980A1 (en
Inventor
Manfred Goebel
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE4231980A priority Critical patent/DE4231980C2/en
Publication of DE4231980A1 publication Critical patent/DE4231980A1/en
Application granted granted Critical
Publication of DE4231980C2 publication Critical patent/DE4231980C2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/06Methods or arrangements for protecting foundations from destructive influences of moisture, frost or vibration
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Description

Die Erfindung betrifft eine Grundwasserwanne nach dem Oberbegriff des Anspruches 1.The invention relates to a groundwater basin according to the preamble of claim 1.

Beim Bau von Verkehrswegen, wie Straßen, Radwegen, Fußgän­ gerwegen, Schienensträngen von Eisenbahnen, S-Bahnen, Stra­ ßenbahnen usw. sowie bei sonstigen Flächen wie z. B. Park­ plätzen ist es aus vielfältigen Gründen oft notwendig, die Oberfläche dieser Bauten unterhalb eines vorhandenen Grund­ wasserspiegels zu legen. Dies würde dann ohne das Ergreifen weiterer Maßnahmen dazu führen, dass die Fahr- oder Gehflä­ che bzw. der Schienenstrang ständig von Wasser überstanden wäre.When building traffic routes such as roads, bike paths, pedestrian walkways straight, railroad tracks of railways, S-Bahn, Stra ßenbahnen etc. as well as other areas such. B. Park It is often necessary for various reasons that Surface of these buildings below an existing ground to lay water level. This would then happen without the grasp further measures cause the driving or walking area surface of the rail or the track is constantly exposed to water would.

Eine Möglichkeit, das Problem zu lösen, besteht in einer Ab­ senkung des Grundwasserspiegels bis unterhalb der Höhe der betreffenden Fläche.One way to solve the problem is to start with lowering the water table to below the level of the affected area.

Von Seiten der Wasserwirtschaftsverwaltungen wird dies aus Umweltschutzgründen jedoch kaum noch genehmigt. Um trotzdem den ursprünglichen Verlauf des Verkehrsweges beizubehalten, ergibt sich als Möglichkeit der Bau einer Grundwasserwanne.This will be avoided on the part of the water management administrations Environmental protection reasons hardly approved. To anyway to maintain the original course of the traffic route, arises as a possibility of building a groundwater basin.

Grundwasserwannen sind bekannte Bauwerke, die in Massivbau­ weise erstellt werden. Baustoff sowohl für den Wannenboden als auch für die Seitenwände ist dabei insbesondere Stahl­ beton, der als wasserdichter Beton hergestellt wird bzw. durch zusätzliche Maßnahmen an der Oberfläche wie Beschich­ tung oder Anstrich oder das Anbringen von Dichtungspappe wasserdicht gemacht wird. Für die seitliche Abdichtung kann bei geringem Wasser- und Erddruck auch Mauerwerk, das durch Verputz sowie Anstrich, Beschichtung oder Dichtungs­ pappe wasserundurchlässig wird, Verwendung finden.Groundwater tanks are well-known structures that are used in solid construction be created wisely. Building material for both the tub floor as well as steel for the side walls concrete that is produced as waterproof concrete or through additional measures on the surface such as coating coating or painting or the application of sealing cardboard is made waterproof. For side sealing can also masonry with low water and earth pressure through plastering as well as painting, coating or sealing cardboard becomes impermeable to water.

In Verbindung mit den oben genannten massiven Bauweisen sind auch Kunststoff-Dichtungsbahnen als ergänzende Dichtungsmaß­ nahme bekannt. Sie werden außen aufgebracht als Schutz gegen drängendes Grundwasser. Are in connection with the massive construction mentioned above also plastic sealing sheets as a supplementary sealing measure known. They are applied outside as protection against urgent groundwater.  

Auch als Dachabdichtung finden sie Verwendung.They are also used as roof waterproofing.

Weiterhin sind sie als innere Abdichtung von Flüssigkeitsbe­ hältern oder -becken bekannt.Furthermore, they are used as an internal seal of liquid known tanks or basins.

Kunststoffabdichtungen sind auch ohne Verbindung mit einem massiven Bauwerk als Abdichtungsmaterial bekannt. Insbeson­ dere künstliche Teiche werden häufig mit Kunststoffen ausge­ kleidet, um eine Versickerung des Teichinhaltes zu verhin­ dern. Bei Mülldeponien beugen Kunststoffabdichtungen einem Eindringen der Deponie-Sickerwässer in den Untergrund vor.Plastic seals are also without connection to one massive structure known as waterproofing material. Insbeson their artificial ponds are often covered with plastics dresses to prevent the contents of the pond from seeping away countries. At landfills, plastic seals bend you Penetration of the landfill leachate into the subsurface.

Weiterhin ist der Einsatz von Kunststoff-Dichtungsbahnen beim Bau von Grundwasserwannen auch unabhängig von den oben genannten massiven Bauwerken aus der Patentanmeldung DD 127 403 bekannt. Die Dichtungsbahn wird dabei als Sperrschicht eingesetzt, die auf einer Bettungsschicht verlegt wird. Die Sperrschicht ist allerdings wasserdurchlässig. Bauwerkseitig wird eine Deckschicht angeordnet, die neben dem Schutz der Dichtungsbahnen und der Sicherung gegen Auftrieb auch als Filterschicht dient für das Wasser, das durch die Sperr­ schicht dringt. Dieses wird dann durch Drainagen aufgefangen und abgeführt.Furthermore, the use of plastic sealing sheets in the construction of groundwater wells, regardless of the above mentioned massive structures from the patent application DD 127 403 known. The waterproofing membrane is used as a barrier layer used, which is laid on a bedding layer. The However, the barrier layer is permeable to water. building side a cover layer is arranged, in addition to protecting the Geomembranes and protection against buoyancy also as Filter layer serves for the water passing through the barrier layer penetrates. This is then collected through drainage and dissipated.

In allen Fällen werden dabei die Kunststoff-Dichtungsbahnen werkseitig angeliefert und danach verlegt.In all cases, the plastic sealing membrane delivered at the factory and then installed.

Die oben beschriebenen Verfahren zur Herstellung einer Grundwasserwanne in Massivbauweise verursachen beträchtliche Baukosten. Darüberhinaus zieht sich die Bauzeit über einen längeren Zeitraum hin und ist auf Grund der Beton- oder Mau­ rerarbeiten stark witterungsabhängig.The methods described above for making a Groundwater tanks in solid construction cause considerable Building-costs. In addition, the construction period extends over one longer period and is due to the concrete or Mau work strongly dependent on the weather.

Bei einem Verzicht auf massive Bauwerke unter Einsatz von Dichtungsbahnen als Sperrschicht ist dagegen nach bisherigem Stand der Technik gemäß der Patentanmeldung DD 127 403 die Dichtheit der Wanne nicht gegeben, so dass ständig eindrin­ gendes Wasser abgeführt werden muss.If massive structures are dispensed with using Sealing membranes as a barrier layer, however, is the previous one State of the art according to patent application DD 127 403  Tightness of the tub is not given, so that it constantly penetrates water must be removed.

Die Aufgabe der Erfindung besteht darin, die Baukosten ex­ trem zu reduzieren, die Bauzeit ganz wesentlich zu verkürzen und von der jeweiligen Jahreszeit praktisch unabhängig zu sein; jedoch gleichzeitig eine wasserdichte Konstruktion herzustellen, so dass kein eindringendes Grundwasser gesam­ melt und abgeleitet werden muss wie bei der Patentanmeldung DD 127 403. Die Grundwasserwanne ist somit einer Konstruk­ tion in Massivbauweise völlig gleichwertig.The object of the invention is to ex construction costs to reduce tremendously, shorten the construction time considerably and practically independent of the season his; but at the same time a waterproof construction to produce so that no total groundwater penetration melt and must be derived as in the patent application DD 127 403. The groundwater basin is thus a construct solid construction is completely equivalent.

Die Aufgabe wird durch eine Wannenkonstruktion gelöst, bei der sowohl die Sohle der Grundwasserwanne als auch die Wände aus wasserdicht verschweißten oder verklebten Kunststoff- Dichtungsbahnen bestehen. Massive Bauteile sind nicht mehr erforderlich.The task is solved by a tub construction, at of both the bottom of the groundwater basin and the walls made of waterproof welded or glued plastic Sealing membranes exist. Solid components are no longer required.

Dabei ist beim Herstellen weitestgehend horizontaler Flächen der anstehende Baugrund so weit als möglich zu glätten. Auf diesen geglätteten Baugrund wird dann eine Schutzschicht aufgebracht, die sowohl aus steinfreiem, sandigem Material, gemahlener Schlacke und dergleichem, als auch aus einem Vlies, Glaswolle, aufgeschäumtem Kunststoff, einer zusätzli­ chen Kunststoffbahn oder ähnlichem Material bestehen kann. Entsprechende Schutzmaßnahmen werden auch für den oberseiti­ gen Schutz der Dichtungshaut durchgeführt. Es sind auch Kom­ binationen möglich.It is largely horizontal surfaces when manufacturing smooth out the existing ground as far as possible. On this smoothed subsoil then becomes a protective layer applied, both from stone-free, sandy material, ground slag and the like, as well as from one Fleece, glass wool, foamed plastic, an additional Chen plastic sheet or similar material may exist. Appropriate protective measures are also applied to the upper side protection of the sealing skin. It is also com combinations possible.

Für die Herstellung geneigter Flächen, insbesondere der seitlichen Wände, die in der Regel als Böschung ausgebildet sind, gilt das Gleiche wie für horizontale Flächen der Grundwasserwanne. Bei starker Neigung kann jedoch wegen der Rutschgefahr steinfreier Sand, gemahlene Schlacke oder ähnliches als Schutzmaterial gegebenenfalls nicht ver­ wandt werden. Durch eine geriffelte oder genoppte Folien­ oberfläche kann dem allerdings zumindest für die oberseitige Schutzschicht der Folie entgegen gewirkt werden.For the production of inclined surfaces, especially the side walls, usually formed as an embankment are the same as for horizontal surfaces of the Groundwater basin. With a strong inclination, however, can the danger of slipping stone-free sand, ground slag or the like may not be used as protective material be turned. Through a corrugated or nubbed film The surface can, however, at least for the top Protective layer of the film can be counteracted.

Bei ausreichend standfestem Baugrund, insbesondere Fels oder stark bindigem Boden können die seitlichen Wände der Grund­ wasserwanne stark geneigt, eventuell auch senkrecht ausge­ bildet werden. Bindiger Boden ist dabei mechanisch zu glät­ ten, Fels durch Abklopfen von Spitzen und Kanten und Bear­ beiten mit Mörtel oder Spritzbeton einzuebnen. Gegebenen falls können Spundwände als Hilfskonstruktion gerammt wer­ den. Steinfreier Sand, gemahlene Schlacke oder vergleichba­ res Material scheiden wegen der starken Neigung auch hier als Schutzschicht aus.With a sufficiently stable foundation, in particular rock or  strong cohesive soil can be the side walls of the bottom water tub strongly inclined, possibly also vertically out be formed. Cohesive soil is mechanically smooth ten, rock by tapping tips and edges and bear level with mortar or shotcrete. given if possible, sheet pile walls can be rammed as an auxiliary structure the. Stone-free sand, ground slag or similar Res material also divide here because of the strong inclination as a protective layer.

Bei entsprechenden Voraussetzungen kann auf Maßnahmen zum Schutz der Folie völlig verzichtet werden. Dies gilt dann, wenn die Flächen, auf denen die Dichtungsbahnen zum Auflie­ gen kommen, weitestgehend geglättet und steinfrei sind bzw. das Verfüllmaterial steinfrei ist, so dass eine mechanische Beschädigung der Dichtungsbahnen vermieden wird.If the conditions are right, measures can be taken Protection of the film can be completely dispensed with. This applies if the surfaces on which the geomembranes are laid come, largely smoothed and stone-free or the backfill material is stone-free, so that a mechanical Damage to the sealing membrane is avoided.

Neben der Dichtheit ist auch die Auftriebssicherheit zu gewährleisten. Da die Wannenaußenhaut allein aus geschützter Folie besteht, ist sie nicht starr und kann keine Biegemo­ mente aufnehmen. Deshalb muss in jedem Punkt der Wanne durch entsprechende Auflast die Sicherheit gegen Auftrieb gewähr­ leistet sein, damit nicht Teilflächen der Wannensohle bzw. auch der Böschungen sich vom Untergrund abheben können.In addition to the tightness, the safety against buoyancy is also increased guarantee. Because the tub skin is protected only Film, it is not rigid and cannot bend record moments. The tub must therefore pass through at every point guarantee the appropriate load the security against buoyancy to ensure that parts of the base of the tub or the embankments can also stand out from the ground.

Auf Grund der Folienkonstruktion ist die Wanne beliebig ver­ formbar. Neben der vertikalen oder geneigten Ausbildung der seitlichen Wände kann somit auch die Sohle der Wanne, die unterhalb der Fahrfläche, Gehwegfläche, Parkfläche usw. liegt, problemlos mit dieser steigend oder fallend bis ober­ halb des Grundwasserspiegels geführt werden. Weiterhin kön­ nen auch Ein- oder Ausbuchtungen der Wanne, die z. B. durch bestehende Bauwerke verursacht werden, ohne Schwierigkeiten hergestellt werden. Das Bauwerk dient dann als Widerlager für die Folie. Due to the film construction, the tub is ver malleable. In addition to the vertical or inclined formation of the Lateral walls can also be the sole of the tub below the driving surface, sidewalk surface, parking space etc. lies, easily with this rising or falling to the top half of the groundwater table. Furthermore, Nen also indentations or bulges of the tub, the z. B. by existing structures can be created without difficulty getting produced. The building then serves as an abutment for the slide.  

Die Dichtungshaut und die dazugehörigen Dichtungsvliese, Kunststoffschutzbahnen, Bahnen aus Glaswolle usw. werden an den oberen Rändern der Wanne fixiert. Dies kann wahlweise durch eine Verankerung in einem Aufhängegraben, durch Erdnä­ gel oder andere Konstruktionen geschehen.The sealing skin and the associated sealing fleece, Plastic protective sheets, sheets of glass wool, etc. are on the upper edges of the tub fixed. This can be optional by anchoring in a suspension trench, by ground sewing gel or other constructions happen.

Bei massiven Bauwerken, die sich im Bereich der Wanne befin­ den, erfolgt ein Befestigen durch Ankleben, Anschweißen, An dübeln und ähnliches, je nach örtlichen Gegebenheiten und nach Wirtschaftlichkeit.For massive structures that are located in the area of the tub is attached by gluing, welding, to dowels and the like, depending on local conditions and for economy.

Claims (3)

1. Grundwasserwanne zur Plazierung von Verkehrswegen aller Art, des weiteren von Parkplätzen und Freiflächen unter dem ständigen oder zeitweiligen Grundwasserstand, wobei die ge­ samte Dichtungsfläche der Wanne unter Verzicht auf massive Bauteile aus Kunststoff-Dichtungsbahnen besteht, die mitein­ ander verschweißt oder verklebt sind, dadurch gekennzeichnet, dass die aus den Kunststoff-Dichtungsbahnen bestehende Grund­ wasserwanne wasserdicht ist.1.Groundwater trough for the placement of traffic routes of all kinds, furthermore of parking lots and open spaces under the constant or temporary groundwater level, whereby the entire sealing surface of the trough consists of plastic components, without solid components, which are welded or glued to each other, thereby characterized in that the basic water tank consisting of the plastic sealing membrane is watertight. 2. Grundwasserwanne nach Anspruch 1, dadurch gekennzeichnet, dass die verschweißten oder verklebten Kunststoffbahnen der Grundwasserwanne einseitig oder beidseitig geschützt sind gegen mechanische Beanspruchung oder Beschädigung durch eine Schutzlage oder mehrere Schutzlagen aus Vliesen oder Glaswol­ le oder aufgeschäumten Kunststoffen oder weiteren Kunststoff­ bahnen oder steinfreiem Feinsand oder feingemahlener Schlacke oder vergleichbaren Materialien.2. groundwater basin according to claim 1, characterized in that the welded or glued plastic sheets of the Groundwater basin are protected on one or both sides against mechanical stress or damage from a Protective layer or several protective layers made of fleece or glass wool le or foamed plastics or other plastic tracks or stone-free fine sand or finely ground slag or comparable materials. 3. Grundwasserwanne nach Anspruch 1 oder 2, dadurch gekennzeich­ net, dass die Sicherheit gegen Auftrieb in jedem Punkt der Wanne vorhanden ist.3. groundwater basin according to claim 1 or 2, characterized that security against buoyancy in every point of the Tub is present.
DE4231980A 1992-09-24 1992-09-24 Groundwater basin made of plastic geomembranes without solid construction Expired - Fee Related DE4231980C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE4231980A DE4231980C2 (en) 1992-09-24 1992-09-24 Groundwater basin made of plastic geomembranes without solid construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE4231980A DE4231980C2 (en) 1992-09-24 1992-09-24 Groundwater basin made of plastic geomembranes without solid construction

Publications (2)

Publication Number Publication Date
DE4231980A1 DE4231980A1 (en) 1994-03-31
DE4231980C2 true DE4231980C2 (en) 2002-10-10

Family

ID=6468717

Family Applications (1)

Application Number Title Priority Date Filing Date
DE4231980A Expired - Fee Related DE4231980C2 (en) 1992-09-24 1992-09-24 Groundwater basin made of plastic geomembranes without solid construction

Country Status (1)

Country Link
DE (1) DE4231980C2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4340787A1 (en) * 1993-11-23 1995-05-24 Frenzel Otto Bauunternehmen Pollutant-collection equipment from rails

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD127403A1 (en) * 1976-09-13 1977-09-21

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD127403A1 (en) * 1976-09-13 1977-09-21

Also Published As

Publication number Publication date
DE4231980A1 (en) 1994-03-31

Similar Documents

Publication Publication Date Title
DE69926791T2 (en) STAUDAMM AND SEALING METHOD
CN108678000B (en) U-shaped retaining structure for roadbed underpass highway and construction method thereof
CN105735354B (en) A kind of city underground engineering lid digs full-reverse construction method
EP1067241B1 (en) Basin construction for catchment of a traffic road
Bell et al. Expansive clays and construction, especially of low-rise structures: a viewpoint from Natal, South Africa
CN107386298A (en) A kind of depth hole composite supporting construction and its construction method with water-proof function
CN105544463B (en) A kind of construction method of geomembrane face dam composite panel
DE3716496C1 (en) Sealing system for refuse landfills with sloping landfill delimitations
CN116607617A (en) Municipal road roadbed drainage structure and construction method thereof
DE4231980C2 (en) Groundwater basin made of plastic geomembranes without solid construction
CN112900181B (en) Construction method for widening thin layer of asphalt pavement
DE2321647A1 (en) PROCESS AND FINISHED PART FOR THE PRODUCTION OF A CORE OR SURFACE SEAL
CN112302678B (en) Deformation control construction process for shallow tunnel of underpass building
DE4440787A1 (en) Prefabricated support for use on weak or unstable ground
Langdon Spon's Civil Engineering and Highway Works Price Book 2009
CN206986904U (en) A kind of depth hole composite supporting construction with water-proof function
DE102020109990A1 (en) Bridge structure
EP1067243B1 (en) Catchment basin for above ground water and construction method thereof
DE3802671C2 (en)
RU2778149C1 (en) Method for creating an anti-filtration sand-sapropel curtain
DE4321730C2 (en) Combination waterproofing for landfills with steep walls to vertical walls and / or embankments as landfill restrictions
CN109487819B (en) Comprehensive pipe gallery and construction method thereof
JPS60123609A (en) Artificial reservior and construction thereof
DE2032574C3 (en) Sealing of stone dams, embankments or natural embankments
Keily et al. SMM7 Explained and Illustrated

Legal Events

Date Code Title Description
8110 Request for examination paragraph 44
8125 Change of the main classification

Ipc: E02D 19/06

D2 Grant after examination
8364 No opposition during term of opposition
8339 Ceased/non-payment of the annual fee