DE2945279A1 - Transportable polygonal holiday house frame - has end linked continuous triple shanked trusses forming self supporting cage - Google Patents
Transportable polygonal holiday house frame - has end linked continuous triple shanked trusses forming self supporting cageInfo
- Publication number
- DE2945279A1 DE2945279A1 DE19792945279 DE2945279A DE2945279A1 DE 2945279 A1 DE2945279 A1 DE 2945279A1 DE 19792945279 DE19792945279 DE 19792945279 DE 2945279 A DE2945279 A DE 2945279A DE 2945279 A1 DE2945279 A1 DE 2945279A1
- Authority
- DE
- Germany
- Prior art keywords
- building according
- frame
- building
- trusses
- tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011230 binding agent Substances 0.000 claims description 13
- 210000002414 leg Anatomy 0.000 claims 5
- 210000000689 upper leg Anatomy 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 7
- 239000002023 wood Substances 0.000 abstract description 2
- 239000003292 glue Substances 0.000 description 10
- 238000005253 cladding Methods 0.000 description 2
- 238000009413 insulation Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/34—Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
- E04B1/3408—Extraordinarily-supported small buildings
- E04B1/3412—Extraordinarily-supported small buildings mainly supported by a central column or footing
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/343—Structures characterised by movable, separable, or collapsible parts, e.g. for transport
- E04B1/34336—Structures movable as a whole, e.g. mobile home structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H1/00—Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
- E04H1/02—Dwelling houses; Buildings for temporary habitation, e.g. summer houses
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B2001/0053—Buildings characterised by their shape or layout grid
- E04B2001/0084—Buildings with non right-angled horizontal layout grid, e.g. triangular or hexagonal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B2001/0053—Buildings characterised by their shape or layout grid
- E04B2001/0084—Buildings with non right-angled horizontal layout grid, e.g. triangular or hexagonal
- E04B2001/0092—Small buildings with hexagonal or similar horizontal cross-section
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/268—Connection to foundations
- E04B2001/2684—Connection to foundations with metal connectors
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
Gebäude building
Beschreibung Die Erfindung betrifft ein Gebäude gemäß dem Oberbegriff des Anspruches 1. Description The invention relates to a building according to the preamble of claim 1.
Es gibt seit langem Häuser, die aus vorgefertigten Teilen zusammengefügt werden, gewöhnlich an der 3austelle.There have long been houses that are assembled from prefabricated parts usually at the 3austelle.
Ein Beispiel für eine Sektionen-Bauweise aus Einheiten, deren Grundriß ein gleichseitiges Dreieck ist, findet sich in der US-PS 3 152 366. Sie beschreibt ein pavillonartiges Gebäude, das auf einer Anzahl verhältnismäßig dünner Stützen ruht, von denen eine zentral angeordnet ist und die übrigen über den Umfang des sechseckigen Hauses verteilt sind. Jede Einheit besteht aus einer Vielzahl von Bauelementen; dem Gebäude wird eine gewisse Minimalfestigkeit nur durch die gegenseitige Abstützung der Einheiten aneinander und durch ihre Verbindung mit einem Giebeldach verliehen, das ebenfalls aus Dreiecks-Platten zusammengesetzt ist. Diese recht aufwendige Leichtbauweise hält größeren Beanspruchungen daher nicht stand. Auch ergeben sich große Schwierigkeiten bei der Abdichtung und Isolierung.An example of a section construction from units, their floor plan is an equilateral triangle is found in U.S. Patent 3,152,366. It describes a pavilion-like building on a number of relatively thin supports rests, one of which is centrally located and the rest over the circumference of the hexagonal house. Each unit consists of a large number of components; the building is given a certain minimum strength only through the mutual support of the units given to each other and through their connection with a gable roof, which is also composed of triangular plates. This rather complex lightweight construction therefore does not withstand greater stresses. Even surrender great difficulties in sealing and insulation.
In der DE-OS 27 10 078 ist ein Gebäude vorgeschlagen worden, das - einem Turm-Restaurant nicht unähnlich - rund um eine Treppenhaussäule einen Polygonblock trägt, der insbesondere im Grundriß sechseckig und im Vertikalschnitt achteckig ist.In DE-OS 27 10 078 a building has been proposed that - Not unlike a tower restaurant - a polygonal block around a staircase column carries, which is hexagonal in plan and octagonal in vertical section is.
Die senkrechten Längsträger sind dabei als gelenkSgePolygonzüge ausgebildet, deren Gelenke nach Anbringen waagrechter Bodenträger miteinander verschraubt oder punktverschweißt werden; außen werden dann Verschalungen, Abdeckungen, Platten usw. befestigt. Eine andere Bauweise sieht jedoch zwei Betonhalbschalen vor, die in der waagrechten Mitte miteinander verbunden werden. In jedem Falle wird bei diesem Gebäude ein großer Teil des Innenraums von dem Treppenhaus eingenommen.The vertical longitudinal members are designed as articulated polygonal lines, the joints of which are screwed to one another after the horizontal shelf supports have been attached or be spot welded; on the outside, cladding, covers, panels, etc. attached. Another design, however, provides two concrete half-shells, which are in the horizontal center are connected to each other. In any case, this building will much of the interior was taken up by the stairwell.
Soweit ausgesteifte Gelenke vorhanden sind, gibt es beachtliche Festigkeitsprobleme; aber auch bei der recht schweren Betonhalbschalen-Ausführung ist die Abstützung schwierig und aufwendig. Schließlich kann das Raumgefühl der Benutzer dadurch sehr stark gestört werden, daß es nur schräge, trapezförmige Außenwände gibt. Ähnliche Nachteile haben übrigens Gebäude gemäß der DE-PS 14 59 912.As far as stiffened joints are present, there are considerable strength problems; But even with the rather heavy concrete half-shell design, the support is difficult and time-consuming. After all, this can greatly enhance the sense of space for the user are greatly disturbed that there are only sloping, trapezoidal outer walls. Similar Incidentally, buildings according to DE-PS 14 59 912 have disadvantages.
Ein Ferienhaus gemäß dem DE-GM 69 46 679 hat als formgebende Stützen Fünfeck-Rahmenbinder mit einem Bodenteil, zwei schräg nach innen verlaufenden niedrigen Seitenteilen und zwei hohen Giebelschenkeln. Mindestens vier solcher Rahmenbinder stützen den Fußboden, die Seitenwände, gegebenenfalls einen Zwischenboden und das Giebeldach ab. Auch hier ist die Eckverbindung der Rahmenbinderteile kritisch. Es kommt hinzu, daß das Gebäude nicht besonders stabil und schon wegen der schrägen Außenwände für allgemeine Wohnzwecke nicht geeignet ist; Türe(n) und Fenster sind nur stirnseitig vorgesehen.A holiday home according to DE-GM 69 46 679 has as shaping supports Pentagonal frame truss with a bottom part, two low slanting inwards Side parts and two high gable legs. At least four such frame trusses support the floor, the side walls, if necessary an intermediate floor and that Gable roof off. Here, too, the corner connection of the frame truss parts is critical. It In addition, the building is not particularly stable and because of the sloping Exterior walls are unsuitable for general residential use; Door (s) and window are only provided on the front.
Es ist ein wichtiges Ziel der Erfindung, unter Uberwindung dieser und weiterer Nachteile des Standes der Technik ein verbessertes Gebäude der eingangs genannten Art zu schaffen, das eine einfache, übersichtliche Konstruktion besitzt, sich schnell und stabil aus verhältnismäßig wenig Bauteilen errichten läßt, vor allem aber auch als Ganzes transportabel ist und fertig auf ein vorbereitetes Fundament gesetzt werden kann.It is an important object of the invention to overcome this and further disadvantages of the prior art, an improved building of the initially mentioned to create the type mentioned, which has a simple, clear construction, can be erected quickly and stably from relatively few components But above all, it is also transportable as a whole and ready on a prepared foundation can be set.
In Anspruch 1 sind kennzeichnende Merkmale der Erfindung angegeben. Sie hat den großen Vorteil, daß die Rahmenbinder-Struktur als Skelett oder zusammen mit weiteren Bauteilen, z.B. Ringbalken, oder auch komplett mit allen sonstigen Bauteilen zusammen werksseitig aufgebaut und befördert werden kann. Da die einzelnen Rahmenbinder gelenkfreie Bügel sind, entfallen alle Schwierigkeiten, die den herkömmlichen Eckverbindungen von Rahmenbinder-Teilen anhaften. Zugleich wird Gewicht gespart, ohne daß die Konstruktion an Festigkeit einbüßt.In claim 1 characterizing features of the invention are given. It has the great advantage that the frame truss structure as a skeleton or together with other components, e.g. ring bars, or completely with all others Components can be assembled and transported together at the factory. Because the individual Frame trusses are hinge-free brackets, eliminating all the difficulties that the conventional ones Adhere corner connections of frame truss parts. At the same time, weight is saved, without the construction losing strength.
Ausgestaltungen der Erfindung sind in den Unteransprüchen gekennzeichnet. Die wichtigen Merkmale des Anspruchs 2 tragen dazu bei, den Transport des Gebäudes wesentlich zu erleichtern.Refinements of the invention are characterized in the subclaims. The important features of claim 2 help to transport the building make it much easier.
Die vorgesehenen Rohre unterstützen aber auch den Aufbau, zumal durch sie eine zentrale Last-Abfangung gemäß Anspruch 3 möglich ist. Ein laut Anspruch 4 vorgesehenes Mittelrohr kann als Transportträger dienen, jedoch auch als zentrale Stütze des verankerten Gebäudes beibehalten werden. In diesem Falle ist es auch möglich und erfindungsgemäß vorgesehen, ein einziges, durchgehendes Rohr zwischen den oberen und den unteren Enden der Rahmenbinder anzuordnen.The pipes provided also support the construction, especially through it is a central load interception according to claim 3 is possible. A loud claim 4 provided central tube can serve as a transport carrier, but also as a central one Support of the anchored building. In this case it is too possible and provided according to the invention, a single, continuous tube between arrange the top and bottom ends of the frame trusses.
Die Maßnahme des Anspruches 5 hat sich als besonders wirtschaftlich erwiesen; im allgemeinen sind nämlich Metallprofile zu schwer und/oder zu teuer. Vorgefertigte Holzbinder lassen sich hingegen als Leichtbauträger hoher Festigkeit überaus rationell herstellen. Wenn erforderlich, ist es aber auch möglich und erfindungsgemäß vorgesehen, aus Verbundwerkstoffen aufgebaute Rahmenbinder zu verwenden.The measure of claim 5 has proven to be particularly economical proven; in general, metal profiles are too heavy and / or too expensive. Let pre-made wood ties on the other hand as a lightweight carrier produce high strength extremely efficiently. If necessary, it is possible and provided according to the invention, frame trusses constructed from composite materials to use.
Zur Versteifung des Gebäudes insbesondere in horizontaler Richtung dienen die Merkmale der Ansprüche 6 bis 9. Aber auch in vertikaler Richtung wird die Festigkeit erhöht, weil ein Auseinanderfedern der verbundenen Rahmenbinder-Enden dadurch weitestgehend unterbunden wird. Andererseits bleibt eine gewisse Elastizität insbesondere dank der Maßnahmen des Anspruches 8 erhalten, so daß z.B. thermisch bedingte Spannungen mühelos aufgefangen werden. Dazu tragen auch die Merkmale der Ansprüche 10 und 11 bei.To stiffen the building, especially in the horizontal direction serve the features of claims 6 to 9. But also in the vertical direction the strength is increased, because a springing apart of the connected frame truss ends is thereby largely prevented. On the other hand, a certain elasticity remains obtained in particular thanks to the measures of claim 8, so that e.g. thermally conditional tensions can be absorbed effortlessly. The characteristics of the Claims 10 and 11 at.
Besonders günstig sind die Ausgestaltungen gemäß Anspruch 12 für den Transport und gemäß Anspruch 13 für das Gebäudeklima.The embodiments according to claim 12 are particularly favorable for the Transport and according to claim 13 for the building climate.
Unterschiedliche Bauformen ergeben sich gemäß den Ansprüchen 14 und 15.Different designs result from claims 14 and 15th
Sehr vorteilhaft ist die Verankerung nach Anspruch 16, wobei Ver- und Entsorgungsleitungen gemäß Anspruch 17 seitlich ein-bzw. ausgeführt sein können.The anchoring according to claim 16 is very advantageous, whereby and disposal lines according to claim 17 laterally in or. can be executed.
Noch andere Weiterbildungen der Erfindung gemäß den Ansprüchen 18 bis 20 ermöglichen die baulich besonders einfache Verbindung von Teil-Gebäuden zu an sich bekannten Baugruppen mit einer Anzahl von Räumen, deren Tragsäulen durch Querverbindungen nicht nur eine hochstabile Gesamtanordnung ergeben, sondern auch Ver- und Entsorgung maßgeblich verbessern können.Still other further developments of the invention according to claims 18 up to 20 enable the structurally particularly simple connection of partial buildings known assemblies with a number of rooms, the support columns through Cross connections not only result in a highly stable overall arrangement, but also Can significantly improve supply and disposal.
Weitere Merkmale, Einzelheiten und Vorteile der Erfindung ergeben sich aus der folgenden Beschreibung von Ausführungsbeispielen anhand der Zeichnung. Darin zeigen: Fig. 1 eine Schnittansicht eines erfindungsgemäßen Gebäudes in senkrechter Schnittebene, Fig. 2 eine Schnittansicht entsprechend der Linie II-II in Fig. 1, Fig. 3 eine First-Schnittansicht entsprechend dem Kreis III in Fig. 1, Fig. 4 eine Druntersicht auf ein oberes Rohr mit Leimbinder-Anschlüssen gemäß Fig. 3, Fig. 5 eine Schnittansicht eines Fußes entsprechend dem Oval V in Fig. 1, Fig. 6 eine Seitenansicht einer Giebelanordnung, Fig. 7a eine Seiten- bzw. Schnittansicht eines Gelenks und entsprechend dem Kreis VII in Fig. 6, Fig. 7b Fig. 8 eine schematisierte Seitenansicht einer erfindungsgemäßen Gebäude gruppe und Fig. 9 eine Draufsicht auf die Anordnung von Fig. 8.Further features, details and advantages of the invention result from the following description of exemplary embodiments with reference to the drawing. 1 shows a vertical sectional view of a building according to the invention Section plane, Fig. 2 is a sectional view along the line II-II in Fig. 1, 3 shows a ridge sectional view corresponding to circle III in FIG. 1, FIG. 4 a Underneath view of an upper tube with glue binder connections according to FIGS. 3, 5 a sectional view of a foot corresponding to the oval V in Fig. 1, Fig. 6 is a side view a gable arrangement, Fig. 7a a side or sectional view of a joint and corresponding to circle VII in FIG. 6, FIG. 7b, FIG. 8, a schematic side view a building group according to the invention and FIG. 9 is a plan view of the arrangement of Fig. 8.
Das in der Schnittansicht von Fig. 1 vereinfacht veranschaulichte Gebäude ist in seiner Gesamtheit mit 10 bezeichnet. Es ruht auf einer Tragsäule 12, die aus einem Sockel 52 mit Ankerkorb 54 in einem Fundament 50 bestehen kann. Leimbinder 14 sind mit ihren unteren bzw. oberen Enden mittels einer Befestigung 15 mit einem unteren Rohr 16 bzw. einem oberen Rohr 18 verbunden. Ein Mittelrohr 20 kann die Rohre 16, 18 miteinanderverbinden, zumindest während des Transportes.That illustrated in simplified form in the sectional view of FIG. 1 Building is denoted by 10 in its entirety. It rests on a support column 12, which can consist of a base 52 with an anchor cage 54 in a foundation 50. Glued binders 14 are fastened with their lower and upper ends 15 is connected to a lower tube 16 and an upper tube 18, respectively. A central tube 20 can connect the tubes 16, 18 to one another, at least during transport.
Jeder Leimbinder 14 besteht aus einem unteren Schenkel 22, einem seitlichen - insbesondere senkrechten - Wand schenkel und einem oberen Schenkel 26. An den Außenecken 36, 38, d.h.Each glue binder 14 consists of a lower leg 22, a lateral one - Especially vertical - wall leg and an upper leg 26. To the Outside corners 36, 38, i.
an den unteren und oberen Enden der Wandschenkel 24, können Riegel bzw. Ringbalken 28 vorgesehen sein (vgl. Fig. 2), die dem von den Leimbindern 14 gebildeten Korb insbesondere in Umfangsrichtung hohe Festigkeit verleihen. Außerdem sind Zugbalken 30 vorhanden, die zumindest vom unteren Rohr 16 aus mit den unteren Außenecken 36 mittels Verschraubung 34 waagrecht verbunden sind. An den Zugbalken 30 sind Fußbodenbalken 29 parallel zu den jeweiligen Riegeln bzw. Ringbalken 28 angebracht, was in Fig. 2 der Ubersicht halber jedoch nur in einem von sechs Feldern dargestellt ist.at the lower and upper ends of the wall legs 24, latches can or ring bars 28 may be provided (cf. FIG. 2), which correspond to that of the glue binders 14 give high strength especially in the circumferential direction formed basket. aside from that are drawbars 30 are present, which at least from the lower tube 16 are connected horizontally to the lower outer corners 36 by means of screw 34. Floor beams 29 are attached to the tension beams 30 parallel to the respective transoms or Ring beam 28 attached, which in Fig. 2 for the sake of clarity, however, only in one is represented by six fields.
Einzelheiten der Anschlüsse und Verbindungen gehen insbesondere aus den Fig. 3 bis 7 hervor. Man erkennt insbesondere anhand der Fig. 3 und 5, daß die Verbindung der Leimbinder 14 am unteren Rohr 16 einerseits und am oberen Rohr 18 andererseits durch die Verschraubung 15 an Knotenblechen 32 erfolgt, die mit den Rohren 16, 18 einstückig oder verschweißt sind. Die Knotenbleche 32 bilden Schuhe 35, welche die Enden der Leimbinder 14 teils mit, teils ohne die Endender Zugbalken 30 fassen. Zumindest am Fuß (Fig. 5) können die Enden jedes oder jedes zweiten Leimbinders 14 bzw. 14' mittels einer Gelenkverbindung 33 an den Knotenblechen 32 angebracht sein. Bevorzugt ist die Anordnung so getroffen (vgl. Fig. 2 und 4), daß z.B. ein Stern aus drei Leimbindern 14 mit starrer Befestigung 15 an dem unteren Rohr 16 bzw. oberen Rohr 18 befestigt ist, während dazwischen liegende Leimbinder 14' an den Gelenken 33 gehaltert sind.Details of the connections and connections go out in particular FIGS. 3 to 7 emerge. It can be seen in particular with reference to FIGS. 3 and 5 that the Connection of the glue binders 14 to the lower tube 16 on the one hand and to the upper tube 18 on the other hand, through the screw connection 15 on gusset plates 32, which with the Pipes 16, 18 are integral or welded. The gusset plates 32 form shoes 35, which the ends of the glue binders 14 partly with, partly without the ends of the tie bars 30 hold. At least at the foot (Fig. 5) the ends of each or every second glue binder 14 or 14 'attached to the gusset plates 32 by means of an articulated connection 33 be. Preferably, the arrangement is such (see Figs. 2 and 4) that, for example, a Star made of three glue binders 14 with rigid fastening 15 on the lower tube 16 or upper tube 18 is attached, while intermediate glue binders 14 'to the joints 33 are supported.
Die untere Ebene (Fig. 2) kann eine Versteifungs-Scheibe tragen oder bilden. Der von den Balken 29 getragene Fußboden kann in üblicher Weise mehrschichtig aufgebaut und isoliert sein und z.B. auch eine Fußbodenheizung unter dem Bodenbelag aufnehmen.The lower level (Fig. 2) can carry a stiffening disc or form. The floor carried by the beams 29 can be multilayered in the usual way be constructed and insulated and, for example, underfloor heating under the floor covering take up.
Wie vor allem aus Fig. 5 hervorgeht, kann das untere Rohr 16 über eine Flanschverbindung 86 mit dem Zwischenrohr 52 verbunden sein, durch das Ver- und Entsorgungsleitungen 64 in Form eines Kabel- bzw. Rohrstranges seitlich ein- und ausgeführt werden.As is particularly evident from FIG. 5, the lower tube 16 can over a flange connection 86 can be connected to the intermediate pipe 52, through which and disposal lines 64 in the form of a cable or pipe run laterally and run.
Der obere Flansch 86 des Zwischenrohres 52 ist mit Knotenblechen 90 daran abgestützt. Entsprechende Knotenbleche 88 stützen den unteren Flansch 84, der zur Befestigung an einer Ankerplatte 92 durch den Ankerkorb 54 dient, welcher von Moniereisen 94 im Fundament 50 gehalten ist.The upper flange 86 of the intermediate tube 52 is provided with gusset plates 90 supported on it. Corresponding gusset plates 88 support the lower flange 84, for attachment to a Anchor plate 92 through the anchor cage 54 is used, which is held in the foundation 50 by reinforcement bars 94.
Zur Querverbindung mit einer anderen (in Fig. 5 nicht ersichtlichen, jedoch in Fig. 8 angedeuteten) Tragsäule 12 kann eine Traverse bzw. ein Querrohr 98 am Zwischenrohr 52 befestigt und mit gegebenenfalls isolierten Durchlässen versehen sein.For cross-connection with another (not shown in Fig. 5, However, in Fig. 8 indicated) support column 12 can be a cross member or a cross tube 98 attached to the intermediate pipe 52 and optionally provided with insulated passages be.
Die Wandschenkel 24 der Leimbinder 14 und/oder die Leimbinder 14, 14' können Wandelemente 46 mit Fenstern und Türen tragen, wie in Fig. 1 schematisch angedeutet. Die oberen Schenkel 26 tragen ein Giebeldach 48, das bevorzugt mit einer Leichtbedachung oder Dachhaut 78 versehen ist, wie am besten aus Fig. 3 erkennbar. Auf Sparren 70 sitzen Dachplatten 72, die mit einer Holzverschalung 74 und Teerbahnen 76 abgedeckt sind. Unter den Dachplatten 72 ist ein Lüftungs-Zwischenraum 79 oberhalb einer Dämmschicht 80. Die Decke des überdachten Raumes kann von Gipskarton oder einem Holzprofil 82 gebildet sein.The wall legs 24 of the glued beams 14 and / or the glued beams 14, 14 'can carry wall elements 46 with windows and doors, as shown schematically in FIG. 1 indicated. The upper legs 26 carry a gable roof 48, which is preferably with a Light roofing or roof skin 78 is provided, as can best be seen from FIG. 3. Roof panels 72 are seated on rafters 70, with wooden cladding 74 and tar sheets 76 are covered. Under the roof panels 72 there is a ventilation gap 79 above an insulation layer 80. The ceiling of the covered space can be made of plasterboard or a wooden profile 82 be formed.
Das obere Rohr 18 kann raumseitig bzw. unten eine Flansch-Abstützung 40 aufweisen, die in Fig. 3 gestrichelt angedeutet ist. Nach außen bzw. oben sind am Rohr 18 Aufnahmen oder Ösen 42 vorgesehen, die zum Angriff eines Hebezeugs dienen, beispielsweise des Hakens eines Krans oder Hubschraubers. Eine Abdeckung 44 in Form einer Haube (Fig. 1 und 3) oder einer Platte (Fig. 6) verhindert das Eindringen von Nässe, Staub o.dgl., ohne den Abzug aus dem Rauminneren zu behindern.The upper tube 18 can be a flange support on the room side or below 40, which is indicated by dashed lines in FIG. 3. Are outwards or upwards on the tube 18 receptacles or eyelets 42 are provided, which are used to attack a hoist, for example the hook of a crane or helicopter. A cover 44 in the form a hood (Fig. 1 and 3) or a plate (Fig. 6) prevents penetration from moisture, dust or the like. Without hindering the extraction from the interior of the room.
Die Ausbildung des Giebels ist in Fig. 5 schematisch angedeutet.The formation of the gable is indicated schematically in FIG.
Die Leimbinder 14 mit Zugbalken 30 sind einerseits am oberen Rohr 18, andererseits an Gelenken (VII) mit den Riegeln bzw.The glue binders 14 with tie bars 30 are on the one hand on the upper tube 18, on the other hand on the joints (VII) with the bolts or
Ringbalken 28 verbunden. Einzelheiten der Eckverbindung 66 veranschaulichen die Fig. 7a und 7b. Sie besitzt innere und äußere Winkelplatten 67, die durch Haltebolzen 68 an den Riegeln 28 angeschlagen sind. Langlöcher 96 übernehmen dabei eine gewisse Anlenkung, d.h. einen Bewegungsausgleich. Zur Verbindung der beiden Winkelplatten 67 jedes Eckverbinders 66 dient eine Spannverschraubung 69. Solche (Gelenk-)Verbindungen können entsprechend auch für die Elemente 15, 33, 34 Verwendung finden.Ring beam 28 connected. Details of the corner joint 66 illustrate Figures 7a and 7b. It has inner and outer angle plates 67, which are held by retaining bolts 68 are posted on the bolts 28. Long holes 96 take on a certain amount Linkage, i.e. a movement compensation. To the Connection of the two Angle plates 67 of each corner connector 66 are used for a clamping screw 69. Such (Articulated) connections can accordingly also be used for the elements 15, 33, 34 Find.
In den Rahmen der Erfindung fällt auch der Aufbau von Gebäude gruppen gemäß Fig. 8 und 9. Man erkennt, daß eine Anzahl von Teil-Gebäuden 10 zu einer Baugruppe 100 vereinigt sein kann, vorzugsweise durch direkten Anschluß an Polygonseiten-Ebenen 102 (Fig. 9). Zusätzlich zu der dadurch bewirkten Verfestigung der gesamten Struktur können die einzelnen Tragsäulen 12 bzw.The structure of building groups also falls within the scope of the invention 8 and 9. It can be seen that a number of sub-buildings 10 form an assembly 100 can be combined, preferably by direct connection to polygon side planes 102 (Figure 9). In addition to the solidification of the entire structure that this brings about the individual support pillars 12 resp.
Zwischenrohre 52 durch die beschriebenen Traversen bzw. Querrohre 98 (Fig. 5) untereinander verbunden sein. Soweit ein Teil-Gebäude 10 zwischen benachbarten Gebäuden zurückspringt, können Fülleinsätze bzw. Vorbauten 104 (Fig. 9) vorgesehen werden, die beispielsweise als Veranda, Halle o.dgl. ausgeführt sein können.Intermediate tubes 52 through the crossbars or cross tubes described 98 (Fig. 5) be connected to one another. So much for a part of the building 10 between neighboring buildings Buildings jumps back, filling inserts or stems 104 (FIG. 9) can be provided are, for example, as a veranda, hall or the like. can be executed.
Die dargestellten Ausführungsbeispiele sind Gebäude 10 von sechseckigem Grundriß. Die Erfindung ist jedoch hierauf keineswegs beschränkt; zwar eignen sich regelmäßige Vieleck-Grundrisse besonders, vor allem auch Achtecke, doch ist ein erfindungsgemäßes Gebäude grundsätzlich z.B. auch mit vier- oder fünfeckigem Grundriß realisierbar. Ferner ist anzumerken, daß im Bedarfsfalle auch unsymmetrische Strukturen möglich sind, beispielsweise mit außermittiger Anordnung der Rohre 16, 18 sowie der Tragsäule 12 bei Verwendung ungleicher Leimbinder 14.The illustrated embodiments are buildings 10 of hexagonal Layout. However, the invention is by no means restricted to this; although are suitable regular polygon floor plans especially, especially octagons, but is a building according to the invention in principle, e.g. also with a square or pentagonal ground plan realizable. It should also be noted that, if necessary, asymmetrical structures can also be used are possible, for example with an eccentric arrangement of the tubes 16, 18 and of the support column 12 when using unequal glue binders 14.
Sämtliche aus den Ansprüchen, der Beschreibung und der Zeichnung hervorgehenden Merkmale und Vorteile der Erfindung, einschließlich konstruktiver Einzelheiten, räumlicher Anordnungen und Verfahrensschritten, können sowohl für sich als auch in den verschiedensten Kombinationen erfindungswesentlich sein.All from the claims, the description and the drawing Features and advantages of the invention, including construction details, spatial arrangements and procedural steps, can both for themselves and be essential to the invention in a wide variety of combinations.
Claims (20)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19792945279 DE2945279C2 (en) | 1979-11-09 | 1979-11-09 | building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19792945279 DE2945279C2 (en) | 1979-11-09 | 1979-11-09 | building |
Publications (2)
Publication Number | Publication Date |
---|---|
DE2945279A1 true DE2945279A1 (en) | 1981-05-21 |
DE2945279C2 DE2945279C2 (en) | 1982-03-25 |
Family
ID=6085575
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19792945279 Expired DE2945279C2 (en) | 1979-11-09 | 1979-11-09 | building |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE2945279C2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0183541A2 (en) * | 1984-11-28 | 1986-06-04 | Hiroyuki Ishikawa | House construction |
DE3537306A1 (en) * | 1985-10-19 | 1987-04-23 | Thomas Dipl Ing Sewing | Mobile structure in the form of a house |
DE3938231A1 (en) * | 1989-11-17 | 1990-06-13 | Bernhard Backs | Loft space conversion - uses sandwiched slabs resting on edges of building walls and assembled by unit parts |
FR2711383A1 (en) * | 1993-10-20 | 1995-04-28 | Georges Marcel Paul | Construction with wooden framework erected around a central structure |
DE29716674U1 (en) * | 1997-09-17 | 1997-10-30 | Weihmann Andreas | building |
WO1997044542A1 (en) * | 1996-05-20 | 1997-11-27 | Deladriere Jean Marc | Wooden building system |
FR2925093A1 (en) * | 2007-12-13 | 2009-06-19 | Regis Rodriguez | Tent type shelter device for being installed in stump of tree, has board holes arranged at center between horizontal beams to house, directly or indirectly and end of stump of tree containing beams |
CN105386614A (en) * | 2015-10-25 | 2016-03-09 | 张若玮 | Elevated forest house |
US10801223B1 (en) * | 2019-08-16 | 2020-10-13 | Johnny Angel Zailian | Modular building |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ES2088348B1 (en) * | 1993-08-12 | 1999-01-01 | Ferreiro Rumbo Josefina | PERMANENT STRUCTURES FOR THE CONSTRUCTION OF BUILDINGS OF TWO OR MORE PLANTS, OF VARIOUS USES, WITH WOODEN ROLLS. |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3152366A (en) * | 1960-12-27 | 1964-10-13 | Thomas L Mccrory | Prefabricated building unit |
DE6946679U (en) * | 1969-12-02 | 1970-05-14 | Klein Werner | MADE OF PREFABRICATED PARTS ASSEMBLY TRANSPORTABLE HOUSE, IN PARTICULAR HOLIDAY HOME. |
DE1459912C (en) * | 1971-11-18 | Camoletti, Bruno, Genf (Schweiz), Hausermann, Pascal, Chateau de Mmzier par Frangy (Frankreich), Hoechel, Eric, Genf (Schweiz) | Building made of prefabricated components with upper and lower shells assembled in pairs | |
DE2710078A1 (en) * | 1977-03-08 | 1978-09-14 | Wolfgang Brall | Polyhedral room unit resting on central column - has octagonal vertical plane cross=section and column with helical stairs |
-
1979
- 1979-11-09 DE DE19792945279 patent/DE2945279C2/en not_active Expired
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1459912C (en) * | 1971-11-18 | Camoletti, Bruno, Genf (Schweiz), Hausermann, Pascal, Chateau de Mmzier par Frangy (Frankreich), Hoechel, Eric, Genf (Schweiz) | Building made of prefabricated components with upper and lower shells assembled in pairs | |
US3152366A (en) * | 1960-12-27 | 1964-10-13 | Thomas L Mccrory | Prefabricated building unit |
DE6946679U (en) * | 1969-12-02 | 1970-05-14 | Klein Werner | MADE OF PREFABRICATED PARTS ASSEMBLY TRANSPORTABLE HOUSE, IN PARTICULAR HOLIDAY HOME. |
DE2710078A1 (en) * | 1977-03-08 | 1978-09-14 | Wolfgang Brall | Polyhedral room unit resting on central column - has octagonal vertical plane cross=section and column with helical stairs |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0183541A2 (en) * | 1984-11-28 | 1986-06-04 | Hiroyuki Ishikawa | House construction |
EP0183541A3 (en) * | 1984-11-28 | 1987-08-05 | Hiroyuki Ishikawa | House construction |
DE3537306A1 (en) * | 1985-10-19 | 1987-04-23 | Thomas Dipl Ing Sewing | Mobile structure in the form of a house |
DE3938231A1 (en) * | 1989-11-17 | 1990-06-13 | Bernhard Backs | Loft space conversion - uses sandwiched slabs resting on edges of building walls and assembled by unit parts |
FR2711383A1 (en) * | 1993-10-20 | 1995-04-28 | Georges Marcel Paul | Construction with wooden framework erected around a central structure |
WO1997044542A1 (en) * | 1996-05-20 | 1997-11-27 | Deladriere Jean Marc | Wooden building system |
DE29716674U1 (en) * | 1997-09-17 | 1997-10-30 | Weihmann Andreas | building |
FR2925093A1 (en) * | 2007-12-13 | 2009-06-19 | Regis Rodriguez | Tent type shelter device for being installed in stump of tree, has board holes arranged at center between horizontal beams to house, directly or indirectly and end of stump of tree containing beams |
CN105386614A (en) * | 2015-10-25 | 2016-03-09 | 张若玮 | Elevated forest house |
US10801223B1 (en) * | 2019-08-16 | 2020-10-13 | Johnny Angel Zailian | Modular building |
Also Published As
Publication number | Publication date |
---|---|
DE2945279C2 (en) | 1982-03-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE1559410A1 (en) | Prefabricated building construction | |
DE2945279A1 (en) | Transportable polygonal holiday house frame - has end linked continuous triple shanked trusses forming self supporting cage | |
DE2215011A1 (en) | KIT FOR ERECTING PRE-FABRICATED HOUSES | |
DE8008815U1 (en) | SUPPORT FOR THE BUILDING OF BUILDINGS | |
DE3532846C2 (en) | Building element for building, also for building models | |
DE2031168A1 (en) | Roofing for construction sites | |
DE2301782A1 (en) | PREFABRICATED BUILDING CONSTRUCTION | |
AT302598B (en) | Roofing for construction sites | |
DE2710078A1 (en) | Polyhedral room unit resting on central column - has octagonal vertical plane cross=section and column with helical stairs | |
DE938874C (en) | Building consisting of a metal skeleton and panel cladding | |
EP0513949A2 (en) | Framework consisting of two elements by four rectangular trihedrons each for the load bearing structure of a uniform measured building | |
EP3051039A1 (en) | Building system, in particular for residential and professional purposes | |
DE3905927C1 (en) | Dismantleable wooden building comprising pre-assembled wall and roof units | |
DE2652783C3 (en) | Wooden skeleton for a multi-storey building | |
DE4211929A1 (en) | Min. cost easily moved prefabricated house - has two longitudinal walls, floor, ceiling and roof made of one-piece un-jointed sheets of chipboard, plasterboard and outer layer of GRP | |
DD213255A1 (en) | SPACE CELL UNIT | |
DE4423423A1 (en) | Transportable living unit with half-timbered structure | |
EP0665341A1 (en) | Accomodation unit and method for manufacturing as well as floor frame therefore | |
DE2658410A1 (en) | Rapidly assembled temporary stable - comprises wall panels and roof sheets on structure of tubular posts and trusses | |
AT235531B (en) | Process for the production of beam ceilings | |
DE4237325A1 (en) | Room cell arrangement, especially a mobile building with a multi-storey construction | |
DE2750931C2 (en) | ||
EP1584762B1 (en) | building structure | |
AT513705B1 (en) | radio station | |
DE3320566A1 (en) | Roof structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OP8 | Request for examination as to paragraph 44 patent law | ||
D2 | Grant after examination | ||
8339 | Ceased/non-payment of the annual fee |