CS230923B1 - The method of clearing the face using sliding reinforcement sections - Google Patents

The method of clearing the face using sliding reinforcement sections Download PDF

Info

Publication number
CS230923B1
CS230923B1 CS8210006A CS1000682A CS230923B1 CS 230923 B1 CS230923 B1 CS 230923B1 CS 8210006 A CS8210006 A CS 8210006A CS 1000682 A CS1000682 A CS 1000682A CS 230923 B1 CS230923 B1 CS 230923B1
Authority
CS
Czechoslovakia
Prior art keywords
reinforcement
face
sliding
sections
individual hydraulic
Prior art date
Application number
CS8210006A
Other languages
Czech (cs)
Other versions
CS1000682A1 (en
Inventor
Arnost Felkl
Miloslav Sochacky
Original Assignee
Arnost Felkl
Miloslav Sochacky
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Arnost Felkl, Miloslav Sochacky filed Critical Arnost Felkl
Priority to CS8210006A priority Critical patent/CS230923B1/en
Publication of CS1000682A1 publication Critical patent/CS1000682A1/en
Publication of CS230923B1 publication Critical patent/CS230923B1/en

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

Vynález řeší způsob likvidace porubu vybaveného individuální hydraulickou výztuží pomocí sekcí posuvná výztuže a týká se oboru hlubinného dobývání. Podstata způsobu likvidace porubu pomocí sekcí posuvné výztuže spočívá v tom, že se po likvidaci strojního a elektrovybavení porubu nahradí úvodní tahy individuální hydraulické výztuže od výdušné třídy alespoň dvěma sekcemi posuvné výztuže, načež se provádí plenění dalších tahů individuální hydraulické výztuže včetně stropnic ze zajištěného prostoru porubu sekcemi posuvné výztuže, přičemž vypleněná individuální hydraulická výztuž a stropnice se dopravují pontonem pomocí vrátků na těžní třídu a plenění dalšího tahu se provádí vždy po přeloženi sekcí posuvné výztuže ve směru podél uhelného pilíře, což se dále opakuje pro každý tah a odkliz vypleněné individuální hydraulické včetně stropnic se opět provádí pontonem pomocí vrátků do úplné likvidace výztuže porubu, kde větrání se zajištuje sacím separátním větráním z těžní třídy, která se rovněž postupně vyklízí s postupem likvidace.The invention solves a method of liquidating a face equipped with individual hydraulic reinforcement using sliding reinforcement sections and relates to the field of deep mining. The essence of the method of liquidating the face using sliding reinforcement sections is that after liquidating the mechanical and electrical equipment of the face, the initial strokes of individual hydraulic reinforcement from the ventilation class are replaced with at least two sections of sliding reinforcement, after which the subsequent strokes of individual hydraulic reinforcement, including the ceiling beams, are removed from the secured area of the face using sliding reinforcement sections, while the removed individual hydraulic reinforcement and ceiling beams are transported by pontoon using winches to the mining class and the subsequent stroke is always removed after the sliding reinforcement sections have been transferred in the direction along the coal pillar, which is then repeated for each stroke and the removal of the removed individual hydraulic reinforcement, including the ceiling beams, is again carried out by pontoon using winches until the face reinforcement is completely liquidated, where ventilation is ensured by suction separate ventilation from the mining class, which is also gradually cleared with the liquidation process.

Description

Vynález řeší způsob likvidace porubu vybaveného individuální hydraulickou výztuží pomocí sekcí posuvná výztuže a týká se oboru hlubinného dobývání.The invention solves a method of disposal of a face equipped with individual hydraulic reinforcement by means of sliding reinforcement sections and relates to the field of underground mining.

Podstata způsobu likvidace porubu pomocí sekcí posuvné výztuže spočívá v tom, že se po likvidaci strojního a elektrovybavení porubu nahradí úvodní tahy individuální hydraulické výztuže od výdušné třídy alespoň dvěma sekcemi posuvné výztuže, načež se provádí plenění dalších tahů individuální hydraulické výztuže včetně stropnic ze zajištěného prostoru porubu sekcemi posuvné výztuže, přičemž vypleněná individuální hydraulická výztuž a stropnice se dopravují pontonem pomocí vrátků na těžní třídu a plenění dalšího tahu se provádí vždy po přeloženi sekcí posuvné výztuže ve směru podél uhelného pilíře, což se dále opakuje pro každý tah a odkliz vypleněné individuální hydraulické včetně stropnic se opět provádí pontonem pomocí vrátků do úplné likvidace výztuže porubu, kde větrání se zajištuje sacím separátním větráním z těžní třídy, která se rovněž postupně vyklízí s postupem likvidace.The principle of the method of disposing of the face by means of sliding reinforcement sections consists in that after the disposal of machinery and electrical equipment of the face the initial strokes of individual hydraulic reinforcement from the discharge class are replaced by at least two sliding reinforcement sections. sliding reinforcement sections, where the plundered individual hydraulic reinforcement and joist are transported by a pontoon through the winch to the mining class and the plundering of the next tension is performed after the sliding reinforcement sections are folded in the direction along the coal pillar. The joist is again carried out by a pontoon through the winches until complete lining reinforcement is disposed of, where ventilation is ensured by separate exhaust ventilation from the mining class, which is also gradually cleared out with the liquidation procedure.

Vynález řeší způsob likvidace porubu vybaveného individuální hydraulickou výztuží pomoci sekci posuvné výztuže z oboru hlubinného dobýváni.The invention solves a method of disposal of a face equipped with an individual hydraulic reinforcement by means of a sliding reinforcement section in the field of underground mining.

Dosud se poruby vybavené individuální hydraulickou výztuží po jejich vyrubání likvidují tak, že se přebudují dřevěnou výztuží, to je tři metry dlouhou kulatinou na podchycení stropu porubu od závalu až k pilíři a dřevěnými stojkami, což je rovněž kulatina, jejíž délka je dána mocností sloje. Poté se postupně provádí demontáž a výkliz strojního a elektro vybavení porubu, jakož i plenění a výkliz individuální hydraulické výztuže včetně stropnic.Up to now, coats equipped with individual hydraulic reinforcement have been disposed of by rebuilding them by rebuilding the wood reinforcement, a three-meter long log to hold the ceiling from a cave to a pillar and wooden props, a log whose length is determined by the thickness of the seam. Then the dismantling and evacuation of the machine and electrical equipment of the face, as well as plundering and evacuation of the individual hydraulic reinforcement, including the joists, are gradually carried out.

Nevýhodou tohoto způsobu je značná pracnost při přebudovávání porubu dřevěnou výztuži, což představuje spotřebu sto až stopsdesáti směn ne jeden porub, jakož i velká spotřeba dřeva, která činí dvanáct až patnáct metrů kubických, včetně nákladů na jeho dopravu z povrchu až do porubu.The disadvantage of this method is the considerable effort involved in rebuilding the lining of the wood reinforcement, which involves the consumption of one hundred to fifty shifts per one lining, as well as a large consumption of wood of twelve to fifteen cubic meters, including the cost of transportation from surface to lining.

VýSe uvedené nevýhody jsou na minimum sníženy způsobem likvidace porubu pomocí sekcí posuvné výztuže podle vynálezu, jehož podstata spočívá v tom, že se po likvidaci strojního a elektro vybavení porubu nahradí úvodními tahy individuální hydraulické výztuže od výdušné třídy dvěmi sekcemi posuvné výztuže.The aforementioned disadvantages are minimized by the method of disposing of the lining by means of the sliding reinforcement sections according to the invention, which consists in replacing two sliding reinforcement sections with initial strokes of the individual hydraulic reinforcement from the outlet class after the lining of the lining machinery and electrical equipment.

Ze zajištěného prostoru porubu těmito sekcemi posuvné výztuže se pak provádí plenění dalších tahů individuální hydraulické výztuže, to je stojek a stropnic. Tato vypleněná výztuž se nakládá do pontonu a pomocí vrátků je tento ponton dopravován na těžní třídu. Poté se sekce posuvné výztuže přeloží ve směru podél uhelného pilíře a celá činnost se opakuje až do úplného vyklizení výztuže z porubu. Vzhledem k tomu, že nezajištěný prostor* za sekcemi posuvné výztuže po jejich přeložení se zavaluje, je porub větrán sacím separátním větráním z těžní třídy.From the secured area of the lining with these sections of the sliding reinforcement, we then plunder further strokes of the individual hydraulic reinforcement, i.e. the upright and the joist. This plundered reinforcement is loaded into the pontoon and by the winches the pontoon is transported to the mining class. Then the sliding reinforcement section is folded in the direction along the coal pillar and the whole operation is repeated until the reinforcement is completely cleared from the face. Since the unsecured area * behind the sliding reinforcement sections is overloaded after folding, the coalface is ventilated by separate exhaust ventilation from the mining class.

Výhodou způsobu likvidace porubu pomocí sekcí posuvné výztuže podle vynálezu je její urychlení o 40 až 60 % oproti stávajícímu způsobu, což dále představuje úsporu směn na tuto činnost, snížení fyzicky namáhavé práce horníků a v neposlední řadě úsporu dřeva včetně nákladů na jeho dopravu.The advantage of the method of disposal of the lining by means of the sliding reinforcement sections according to the invention is its acceleration by 40 to 60% compared to the existing method, which further saves savings on this activity, reduces physical labor of miners and last but not least wood savings including transport costs.

Na přiloženém výkresu je schematicky znázorněno příkladné provedení způsobu likvidace porubu pomocí eekcí posuvné výztuže podle vynálezu.The accompanying drawing shows schematically an exemplary embodiment of a method for the disposal of a face by means of the sliding reinforcement solutions according to the invention.

V likvidovaném porubu vybaveném individuální hydraulickou výztuží 2 jsou nasazeny dvě sekce posuvné výztuže 1 tak, že jsou těsně vedle sebe a současně souběžně s porubní frontou. Tímto umístěním plní funkci bezpečnostní hraně pro pracovníky, kteří vlastní likvidaci provádějí.In the liquidated face equipped with the individual hydraulic reinforcement 2, two sections of the sliding reinforcement 1 are fitted so that they are close to each other and at the same time parallel to the face front. This location serves as a safety edge for workers who carry out their own disposal.

Déle je v porubu umístěn vrátek J, pomocí něhož je zajištována doprava pontonu g do porubu lanem 6 přes kladky 2, které jsou ukotveny jednak na sekci posuvné výztuže i a na výztuži těžní třídy 8. Zpětná doprava pontonu g z porubu je pak zajištována vrátkem 4i umístěným na těžní třídě g, Větrání porubu je zajištováno separátním větráním 22, z těžní třídy g.In the longitudinal direction, there is a gate J, which is used to transport the pontoon g to the notch by means of a rope 6 via pulleys 2, which are anchored on the sliding reinforcement section i and on the mining class 8 reinforcement. Mining class g, Coating ventilation is provided by separate ventilation 22, from mining class g.

Vlastní postup likvidace porubu je pak takový, že se nejdříve vrátkem g zatáhne ponton g až k sekci posuvná výztuže i, Ze zajištěného prostoru porubu sekcemi posuvné výztuže 2 od výdušné třídy g, se provede vypleněni jednoho tahu individuální hydraulické výztuže 2 včetně stropnic a současně se demontuje příslušná část separátního větrání '10, které se pak naloží do pontonu g. Obě sekce posuvné výztuže 2 se přeloží ve směru £ a ponton g se stáhne vrátkem 2 na těžní třídu g, kde se vyloží. Poté následuje stažení prázdného pontonu g opět až k sekcím posuvné výztuže £ 8 celá činnost se opakuje až do úplného vykli zení porubu.The actual procedure of the face strip disposal is such that the g is pulled to the sliding reinforcement section i to the sliding reinforcement section i. it removes the respective part of the separate ventilation 10, which is then loaded into the pontoon g. Then, the empty pontoon g is pulled back up to the sliding reinforcement sections 8 and the entire operation is repeated until the lining is completely cleared.

Claims (1)

PŘEDMĚT VYNÁLEZUSUBJECT OF THE INVENTION Způsob likvidace porubu pomocí sekcí posuvné výztuže, vyznačující se tím, že se po likvidaci strojního a elektrovybavení porubu nahradí úvodní tahy individuální hydraulické výztuže od výdušné třídy alespoň dvěma sekcemi posuvné výztuže, načež se provádí plenění dalších tahů individuální hydraulické výztuže včetně stropnic ze zajištěného prostoru porubu sekcemi posuvné výztuže, přičemž vypleněné individuální hydraulická výztuž a strop nice se dopravuje pontonem pomocí vrátků ná těžní třídu a plenění delšího tahu se provádí vždy po přeložení sekcí posuvná výztuže ve směru podél uhelného pilíře, což se déle opaku je pro každý tah a odkliz vypleněné inflividuélní hydraulické výztuže věetnš stropnic se opět provádí pontonem pomocí vrátků do úplné likvidace výztuže porubu, kde větrání se zajištuje sacím separátním větráním z těžní třídy, které se rovněž postupně vyklízí s postupem likvidace.A method of disposing of a face by means of sliding reinforcement sections, characterized in that after the disposal of machinery and electrical equipment of the face, the initial strokes of the individual hydraulic reinforcement from the expendable class are replaced by at least two sliding reinforcement sections. sliding reinforcement sections, where the plundered individual hydraulic reinforcement and ceiling are transported by a pontoon through the door of the loading class and the longer thrust is plundered after the sliding reinforcement sections are folded in the direction along the coal pillar. The hydraulic reinforcement including the joists is again carried out by a pontoon through the winches until the complete reinforcement of the lining reinforcement, where ventilation is provided by suction separate ventilation from the mining class, which is also gradually vacating the process of liquidation.
CS8210006A 1982-12-30 1982-12-30 The method of clearing the face using sliding reinforcement sections CS230923B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CS8210006A CS230923B1 (en) 1982-12-30 1982-12-30 The method of clearing the face using sliding reinforcement sections

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CS8210006A CS230923B1 (en) 1982-12-30 1982-12-30 The method of clearing the face using sliding reinforcement sections

Publications (2)

Publication Number Publication Date
CS1000682A1 CS1000682A1 (en) 1984-01-16
CS230923B1 true CS230923B1 (en) 1984-08-13

Family

ID=5447550

Family Applications (1)

Application Number Title Priority Date Filing Date
CS8210006A CS230923B1 (en) 1982-12-30 1982-12-30 The method of clearing the face using sliding reinforcement sections

Country Status (1)

Country Link
CS (1) CS230923B1 (en)

Also Published As

Publication number Publication date
CS1000682A1 (en) 1984-01-16

Similar Documents

Publication Publication Date Title
BG112575A (en) METHOD FOR UNDERGROUND MINING
CN112196616B (en) End mining and rapid withdrawal method for fully mechanized mining face of underground coal mine
Krauze et al. The mechanized supporting system in tunnelling operations
Shvaher et al. Annual production enhancement at deep mining
RU2657557C1 (en) Extraction of mineral resources by large blocks from vein type deposits by cutting all longitudinal and cross-second wheels with hydroabrazing jets of water of super-high pressure in the surface mountain massive of vein
RU2327038C1 (en) Excavation method of heavy-pitching thick and average thick ore deposits with complicated structure
CS230923B1 (en) The method of clearing the face using sliding reinforcement sections
RU2101501C1 (en) Method of preservation of mine working
RU2064045C1 (en) Method for mining steeply dipping ore bodies and methods for mining, processing and concentration of copper and/or copper-zinc and/or zinc and/or sulfur ores with possible content of gold, silver and other precious and rare-earth elements from steeply dipping ore bodies
RU2065053C1 (en) Method for exploitation of steeply dipping ore bodies and methods for mining, processing and beneficiation of copper and/or copper/zinc, and/or zinc, and/or sulfur ores possibly containing gold, silver and other precious and rare-earth elements of steeply dipping ore bodies
JPH0626297A (en) Tunnel drilling method
Mazurek et al. Development of technology for withdrawal of the powered roof support from a row and its relocation from the liquidated longwall system
SU1089260A1 (en) Method of depreservation of temporary side walls of open mines
RU2555997C1 (en) Method of open-underground development of thick single steeply inclined coal seam
RU2520228C1 (en) Development method of thick gently sloping formation in large slabs
RU2063512C1 (en) Method for mining steeply dipping ore bodies
SU569714A1 (en) Method of ore mining
RU2148715C1 (en) System of heading machines
SU1765408A1 (en) Method at mining steep medium-thickness mineral deposit seams
SU1518520A1 (en) Method of working ore lodes
SU798303A1 (en) Method of mining thick ore deposits
RU2067177C1 (en) Shield unit
SU742589A1 (en) Method of mining super-thin sharply assending seams
Oldham et al. Void fill techniques for stabilizing roof conditions during longwall recovery
PL243434B1 (en) Device for construction of a longwall section of powered support