SU742589A1 - Method of mining super-thin sharply assending seams - Google Patents

Method of mining super-thin sharply assending seams Download PDF

Info

Publication number
SU742589A1
SU742589A1 SU782590127A SU2590127A SU742589A1 SU 742589 A1 SU742589 A1 SU 742589A1 SU 782590127 A SU782590127 A SU 782590127A SU 2590127 A SU2590127 A SU 2590127A SU 742589 A1 SU742589 A1 SU 742589A1
Authority
SU
USSR - Soviet Union
Prior art keywords
block
ore
rock
adjacent
development
Prior art date
Application number
SU782590127A
Other languages
Russian (ru)
Inventor
Алексей Иванович Ляхов
Original Assignee
Иркутский политехнический институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Иркутский политехнический институт filed Critical Иркутский политехнический институт
Priority to SU782590127A priority Critical patent/SU742589A1/en
Application granted granted Critical
Publication of SU742589A1 publication Critical patent/SU742589A1/en

Links

Landscapes

  • Combined Means For Separation Of Solids (AREA)

Description

(54) СПОСОБ РАЗРАБОТКИ ВЕСЬМА ТОНКИХ КРУТОПАДАЮЩИХ(54) METHOD FOR DEVELOPING AN EXTREME THIN THIN FIRING

ЖИЛLIVED

Изобретение относитс  к горной пролышленности и может быть использовано при отработке весьма тонких (мощностью до 0,4-0,6 м) крутопадаю щих жил. Известен способ разработки весьма тонких крутопадающих жил, вк.таочающий шпуровую отбойку запасов бло ка сло ми снизу вверх и разделение подэтажей на короткие блоки рудоспусками , выкладываемыми из пород II. Недостаток данного способа - бол шие затраты на поддержание выработанного , пространства. Кроме того, известен способ разр ботки весьма тонких крутопадающих жил, вк.гаЬчающий шпуровую отбойку за пасов блока сло ми снизу вверх с породной )ПОдрывкой,магазинированйё руды этажа и выпуск ее 2. Недостатком данного способа  вл  етс  высокое разубоживание и потери руды и большие затраты на закладку. Цель изобретени  - повышение эффективности разработки за счет снижени  за;трат на закладку, снижени  разубоживани  и потерь руды. , Поставленна  цель достигаетс  тем, что запасы руда в этаже отраба тывают при одновременной отбойке трех блоков при разных/ стади х развити  работ в каждом блоке, при этом вначале вынимают руду нижней части первого блока и закладывают выработанное пространство ;подрываемыми породами и одновременно отбивают руду из нижней части смежного второго блока , причем выпуск замагазинированной руды из нижней части второго блока заканчивают к моменту образовани  подэтажного штрека на поверхности заложеннойнижней части первого блока , после чего отбивают верхнюю часть последнего, а отсортированную при выпуске породу подают в выработанное пространство нижней части второго блока и одновременно с этим отбивают .нижнюю часть третьего блока смежного со вторым блоком, а после выемки первого блока, при выпуске руды из верхней части второго блока и закладке нижней части третьего блока отсортированной породой начинают отработку нижней части блока смежного с третьим блоком, при этом нижнюю часть блока отбивают на высоту, при которой отсортированна  порода верхней части смежного блока полностью размещалась в нижней часи указанного блока, а шпуры по руе разбуривают на рассто нии, меньем друг от друга, чем шпуры, разбуриваемые по породе.The invention relates to the mining industry and can be used in the development of very thin (up to 0.4-0.6 m) steeply dipping veins. There is a known method of developing very thin steeply dipping veins, including the drilling of block reserves from the bottom upwards and the division of the sub-floors into short blocks by ore chords spread out from rocks II. The disadvantage of this method is the high cost of maintaining the developed space. In addition, there is a known method of developing very thin steeply dipping veins, in which the blasting of the block passes from the bottom upwards with the rock) Fragile, store ore floor and release it 2. The disadvantage of this method is the high dilution and loss of ore and high costs on the bookmark. The purpose of the invention is to increase the development efficiency by reducing the cost of laying, reducing the dilution and loss of ore. The goal is achieved by the fact that the ore reserves in the floor are mined while three blocks are being crushed at different stages of development in each block, while first removing the ore from the lower part of the first block and laying the worked out space; the lower part of the adjacent second block, and the release of the gassed ore from the lower part of the second block is completed by the time of the formation of the sublevel drift on the surface of the lower part of the first block, after they beat off the upper part of the latter, and the rock, sorted when released, is fed into the worked-out space of the lower part of the second block and at the same time beat the lower part of the third block adjacent to the second block, and after the first block is dredged, when the ore is released from the upper part of the second block and the tab is lower parts of the third block of the sorted breed begin to work out the lower part of the block adjacent to the third block, while the lower part of the block is fought off to a height at which the sorted rock of the upper part of the adjacent block and was completely located in the lower part of the block, and the holes were drilled a distance less than each other than holes drilled in the rock.

На фиг. 1 представлен обрабатываемый этаж при выемке первых двух локов, продольный разрез; на иг. 2 - отрабатываемый этаж при выемке первых трех блоков; на фиг.З трабатываемый этаж при выемке первых четырех блоков; на фиг. 4 - разез А-А на фиг. 1, 2 и 3; на фиг.5 азрез Б-Б на фиг. 2 и 3.FIG. Figure 1 shows the processed floor during the excavation of the first two locks, a longitudinal section; on ig. 2 - practiced floor with the removal of the first three blocks; in FIG. 3, the floor being tracked when the first four blocks are excavated; in fig. 4 shows A-A in FIG. 1, 2 and 3; in FIG. 5, a cut-up of BB in FIG. 2 and 3.

Подготовка этсока (выемочного частка) состоит в проведении откаточного штрека 1 и флангового восстащего 2. В процессе выемки каждого блока наращивают попутные восстающие 3| 4, 5 и т.д. Отработку этажа начинают с блока № 1, Нижнюю часть его б вынимают системой разработки с раздельной выемкой и закладкой очистного пространства вмещающими породами. После завершени  очистных работ на поверхности закладки укладывают плотный настил из досок или предварительно разровненную поверхность закладки поливают цементно-песчаным раствором дл  образовани  бетонного настила 7. В кровле нижней части блока № (над настилом) оборудуют подэтажный штрек 8, закрепл емый распорной крепью на металлических кронштейнах. В кровле прдэтажного штрека навешиваютс  съемные выпускные люки. Одновременно с блоком № 1 осуществл ют выемку нижней части смежного с Ним блока W 2 системой разработки с магазинированием руды .The preparation of the ethnoka (excavation chute) consists in carrying out the haulage road 1 and the flanking rest 2. In the process of excavating each block, the up-and-down rising 3 | 4, 5, etc. The development of the floor begins with the block number 1, the lower part of his b taken out by the development system with separate excavation and laying of the cleaning space of the enclosing rocks. After the cleaning works are completed, a dense floor of planks is laid on the surface of the bookmark or the previously smoothed surface of the bookmark is poured with a cement-sand mortar to form concrete floor 7. The roof of the lower part of the block no. (Above the floor) is equipped with a floor drift 8 fixed with spacer support on metal brackets . Removable discharge hatches are hung in the roof of the driveway. Simultaneously with block No. 1, the lower part of the W 2 block adjacent to It is excavated by a mining system with ore mining.

К моменту завершени  выемки нижней части блока № 2 и полного выпуска из нее замагазинированной руды завершают оформление подэхажного щтрека 8 в блоке 1. Над восстающим 3 блока № 1 устанавливают виброгрохот 9 с ленточным конвейером 10. После этого начинают выемку верхней части блока № 1 системой с магазинированием руды,-При этом дл  улучшени  контрастных свойств руды (увеличени  степени дроблени  жильной части забо ) шпуры по жиле располагаютс , чаще, чем по породе.By the moment of completion of the excavation of the lower part of block No. 2 and the complete release of the aerated ore from it, they complete the design of subsurface seal 8 in block 1. Above the rising 3 of block 1, the vibrating screen 9 with the belt conveyor 10 is started. By ore storage, in order to improve the contrasting properties of the ore (increasing the degree of fragmentation of the bottom part of the slab), the holes in the core are located more often than on rock.

Выдаваемую из верхней .части блока № 1 руду скрепером 11 доставл ют к виброгрохоту 9. Каделенную на виброгрохоте из руды рудную мелочь через рудовыпускные отделени  восстаюЙ1его 3 перепускают на основной горизонт„ Отсортированную пустую породу с поверхности аиброгрохота ленточным транспортером 10 подают дл  закладки отработанного пространства нижней части смежного блока 2. По мере его заполнени  ленточный транспортер наращивают.The ore delivered from the upper part of block No. 1 is delivered to the vibrating screen 9 by a scraper 11. On the vibrating screen, ore fines through ore discharge sections of the rising 3 are transferred to the main horizon. Sorted waste rock from the surface of the pneumatic screen is fed with a conveyor 10 adjacent block 2. As it is filled, the belt conveyor is enlarged.

Одновременно с отработкой верхней части блока В 1, закладкой нижней части блока М 2, осуществл ют с применением системы с магазинированием руды выемку нижней части блока 3.Simultaneously with the mining of the upper part of block B 1, laying down the lower part of block M 2, the lower part of block 3 is excavated using the system with ore storage.

После завершени  отработки верхней части блока 1 и закладки нижней части блока 2 на поверхности закладочного материала сооружают настил и в блоке № 2 оформл етс  подэтажный штрек 12 (по аналогии с сооружением подэтажного штрека 8 . блока 1). К этому моменту завершают отработку нижней части блока № 3 и над восстающим 4 устанавливают виброгрохот 9 и монтируют ленточный транспортер 10. После этого начинают отработку верхней части блока № 2 системой с магазинированием (по аналогии с отработкой верхней части блока № 1), Выдаваемую из блока РУДУ направл ют на виброгрохот. Рудна  мэлочь с виброгрохота поступает в рудовыпускное отделение восстающего 4 и по нему перепускаетс  на основной горизонт. Отсортированную на виброгрохоте пустую породу ленточным транспортером 10 доставл ют в отработанно-з пространство нижней части блока 3 дл  его закладки. Одновременно с выемкой части блока № 2 и закладкой нижней чести блока № 3, осуществл ют системой с магазинированием руды выемку нижней части блока № 4.After completion of working off the upper part of block 1 and the laying of the lower part of block 2, a flooring is constructed on the surface of the backfill material and in block 2 the sublevel drift 12 is formed (by analogy with the construction of the sublevel drift 8. Block 1). At this point, the testing of the lower part of the block No. 3 is completed, and the vibrating screen 9 is installed above the rising 4 and the belt conveyor 10 is mounted. After that, the upper part of the block No. 2 is started with the system with the store (similar to the upper part of the block No. 1), issued from the block The ore is directed to the vibrating screen. The ore maloch from the vibrating screen enters the ore mining department of Rising 4 and is transferred through it to the main horizon. The waste rock sorted out on the vibrating screen is conveyed by a belt conveyor 10 into the waste space of the lower part of the block 3 for laying it out. Simultaneously with the excavation of the part of block No. 2 and the laying down of the lower honor of block No. 3, the system with the ore mining is used to excavate the lower part of block No. 4.

В стадии полного развити  очистных работ в этаже (выемочном участке ) в одновременной работе наход тс  три смежных блока. В одном из них (с ранее вынутой и заложенной нижней частью) осуществл ют выемку верхней части. Выдаваемую из нее руду направл ют на виброгрохот, на котором из поступившей руды выдел ют рудную мелочь, поступающую через, рудовглпускное отделение восстающего на основной горизонт, а отсортированную пустую породу направл ют  а закладку отработанного пространства ранее вынутой нижней части смежного блока. Одновременно с этим идет выемка ру,цы в нижней части смежного со вторым третьего бпока. При необходимости дл  увеличени  Несущей способности закладочного массива последний может упрочн тьс  путем нагнетани  в него (или полива его.поверхности), цементно-песчаным раствором.At the stage of full development of cleaning works in the floor (excavation section), there are three adjacent blocks in simultaneous operation. In one of them (with the previously removed and laid down part), the upper part is dredged. The ore produced from it is directed to a vibrating screen on which ore fines are extracted from the ore that enters through, the ore section of the insurgent rises to the main horizon, and the sorted waste rock is directed to the spent space of the previously removed lower part of the adjacent block. At the same time, there is a notch of the ru, at the bottom of the third adjacent to the second bpock. If necessary, in order to increase the load-bearing capacity of the filling mass, the latter can be strengthened by pumping into it (or watering its surface) with a cement-sand mortar.

5five

Соотношение высот нижней и верхней частей блоков принимают с учетом полного заполнени  очистного пространства нижней части блока отсортированной пустой породой. ВозО можные излишки пустой породы, выделенной на виброгрохоте из выданной из верхней части блока руды, по породному отделению восстающего пере5 пускаютна основной горизонт.The ratio of the heights of the lower and upper parts of the blocks is taken in view of the complete filling of the cleaning space of the lower part of the block with the sorted blank rock. Possible excess waste rock, selected on the vibrating screen from the ore extracted from the upper part of the block, passes the main horizon through the breeding department of the insurgent.

Согласно проведенным расчетам отсортировка из отбитой в верхней части каждого блока рудной массы в породу лишь половины ее объема позвол ет увеличить содержание металла в выдаваемой из блока руде. Замена рудных целиков закладочным массивом позвол ет снизить потери руды в целом по блоку. Кроме того, уменьшени высоты магазинов (как при отработке нижней, так и верхней частей каждого блока) позвол ет несколько уменьшить ширину очистного пространства без изменени  трудоемкости выпуска руды (или уменьшить трудоемкость выпуска без изменени  ширины очистного пространства),According to the calculations, the separation of only half of its volume from the ore mass repulsed in the upper part of each block into the rock makes it possible to increase the metal content in the ore produced from the block. Replacing the ore pits with a backfill array allows to reduce the loss of ore in the whole block. In addition, reducing the height of the stores (both when mining the lower and upper parts of each block) allows to somewhat reduce the width of the cleaning space without changing the labor intensity of ore production (or reduce the labor intensity of production without changing the width of the cleaning space)

Claims (3)

1. Способ разработки весьма тонких крутопадающих жил, включающий шпуровую отбойку запасов блока сло ми снизу вверх с породной подрывкой магазинирование руды этажа и выпуск ее, отличающий с  тем, что, с целью повышени  эффективности разработки за счет снижени  затрат на заклалку, снижени  разубоживани  и потерь руды, запасы руды в этаже отрабатывают при одновременной отбойке трех блоков при разных стади х развити  работ в каждом блоке, при этом вначале вынимают РУДУ нижней части первого блока и закладывают выработанное пространство подрываемыми породами и одновременно отбивают руду из нижней части смежного второго блока, причем выпуск замагазинированной руды из нижней части второго блока заканчивают к моменту образовани  подэтажного штрека на поверхности заложенной нижней части первого блока, после чего отбивают верхнюю часть последнего а отсортированную при выпуске породу подают в выработанное пространство нижней части второго блока и одновременно с этим отбивают нижнюю часть третьего блока смежного со вторым блоком, а после выемки первого блока, 1. A method of developing very thin steeply dipping veins, including the blasting of block block reserves from bottom to top with rock-breaking undercuts, storing the ore on the floor and releasing it, so that, in order to increase the development efficiency by reducing the cost of insertion, reducing dilution and losses ores, ore reserves in the floor are processed while simultaneously crushing three blocks at different stages of development of work in each block, while first removing the ore of the lower part of the first block and laying the developed space along The ore from the lower part of the adjacent second block is simultaneously broken by the ore from the lower part of the second block, and the release of the aerated ore from the lower part of the second block is completed by the moment of formation of the sublevel drift on the surface of the lower lower part of the first block, then the upper part of the last block is beaten off the space of the lower part of the second block and at the same time beat off the lower part of the third block adjacent to the second block, and after the first block has been removed, 0 при выпуске руды из верхней части второго блока и закладке нижней части третьего блока отсортированной породой начинают отработку нижней части блока, смежного с третьим бло5 ком.0 when ore is released from the upper part of the second block and the lower part of the third block is sorted by rock, the lower part of the block adjacent to the third block starts mining. 2.Способ по п. 1, отлич а ющ и и с   тем, что нижнюю часть блока отбивают на высоту, при которой отсортированна  порода в верх0 ней части смежного блока полностью размещалась в нижней части указанного блока.2. The method according to claim 1, which is also distinguished by the fact that the lower part of the block is fought off to a height at which the sorted rock in the upper part of the adjacent block was completely placed in the lower part of the specified block. 3.Способ по п. 1,отлича ющ и и с   тем, что шпуры по руде 3. The method according to claim 1, which is also distinguished by the fact that the holes for ore 5 разбуривают на рассто нии меньшем друг от друга чем шпуры разбуриваемые по породе.5 are drilled at a distance shorter from each other than the holes drilled in the rock. Источники информации, Information sources, 0 прин тые во внимание при экспертизе 1, Рафиенко Д.И. Системы с магазинированием руды при разработке жильных месторождений. М., Нед1967 , с. 58-60.0 taken into account during the examination 1, Rafienko D.I. Systems with ore storage in the development of vein deposits. M., Ned 1967, p. 58-60. раra 2. АГОШКОВ М.И. и др. Системы разработки жильных месторождений.М., Госгортехиздат, i960, с. 85-87 (прототип). Y////////7// бло« v fV . .../;v f V ,- J4 X . . (,Sl .2. AGOSHKOV M.I. and others. Development systems of vein deposits. M., Gosgortekhizdat, i960, p. 85-87 (prototype). Y //////// 7 // blo «v fV. ... /; v f V, - J4 X. . (Sl.
SU782590127A 1978-03-06 1978-03-06 Method of mining super-thin sharply assending seams SU742589A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782590127A SU742589A1 (en) 1978-03-06 1978-03-06 Method of mining super-thin sharply assending seams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782590127A SU742589A1 (en) 1978-03-06 1978-03-06 Method of mining super-thin sharply assending seams

Publications (1)

Publication Number Publication Date
SU742589A1 true SU742589A1 (en) 1980-06-25

Family

ID=20753422

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782590127A SU742589A1 (en) 1978-03-06 1978-03-06 Method of mining super-thin sharply assending seams

Country Status (1)

Country Link
SU (1) SU742589A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2443864C1 (en) * 2010-06-16 2012-02-27 Георгий Михайлович Еремин Method to mine mineral deposits

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2443864C1 (en) * 2010-06-16 2012-02-27 Георгий Михайлович Еремин Method to mine mineral deposits

Similar Documents

Publication Publication Date Title
WO2019051569A1 (en) Method for underground mining of minerals
US4072352A (en) Method for mining of rock or ore according to the block caving principle in massive formations
RU2348808C2 (en) Method of preparing bottom of block
US3917348A (en) Method of developing permeable underground zones
SU742589A1 (en) Method of mining super-thin sharply assending seams
RU2039265C1 (en) Method for mining of thin gently dipping ore bodies
SU1083662A1 (en) Method of mining steep-slope ore-bodies
RU2105150C1 (en) Method for working flat and inclined deposits of minerals
SU1717821A1 (en) Method for mining mineral deposits
RU2101498C1 (en) Method of underground mineral mining
SU848643A1 (en) Method of mining ore bodies
SU1162977A1 (en) Method of mining thin steep veins
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
SU898071A1 (en) Method of working ore deposits
RU2091583C1 (en) Method of mining of mineral upper horizons
RU2083833C1 (en) Method for development of steep coal seams with backing worked-out area
SU1546639A1 (en) Method of mining mineral deposits
SU1456572A1 (en) Method of mining mineral deposits
RU2148713C1 (en) Method for opencast mining of sloping and steep deposits of minerals
SU1153062A1 (en) Method of strip mining of gently-sloping and inclined beds of mineral deposits
SU1456579A1 (en) Method of mining sloping ore bodies
SU1643717A1 (en) Method for working out contiguous seams of minerals
SU1452992A1 (en) Method of remining of mineral deposits
SU920216A1 (en) Method of working ore deposits
SU1452989A1 (en) Method of stripping with internal dumping