SU1456579A1 - Method of mining sloping ore bodies - Google Patents
Method of mining sloping ore bodies Download PDFInfo
- Publication number
- SU1456579A1 SU1456579A1 SU874270723A SU4270723A SU1456579A1 SU 1456579 A1 SU1456579 A1 SU 1456579A1 SU 874270723 A SU874270723 A SU 874270723A SU 4270723 A SU4270723 A SU 4270723A SU 1456579 A1 SU1456579 A1 SU 1456579A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- stage
- zone
- mining
- width
- chambers
- Prior art date
Links
Landscapes
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Abstract
Изобретение относитс к выемке руд в услови х повышенного горного давлени . Цель - повышение безопасности выемки руд в услови х повьшен- ного горного давлени за счет ведени горных работ в зоне разгрузки. Залежь дел т на блоки, а блоки на этажи (Э) проведением подготовительно-нарезных выработок. Этажные выраг ботки проход т на рассто нии, равном ширине зоны разгрузки. Из буровьес выработок производ т бурение вееров скважин и взрывание в них зар дов ВВ. Отработки по восстанию снач.ала осуществл ют камерами первой очереди с закладкой выработанного пространства твердеющей смесью, а затем камерами второй очереди с закладкой их днищ и выемкой междуэтажных целиков. Отработку вышележащего Э ведут с опережением на ширину зоны разгрузки нижележащего Э. Горные работы в каждом блоке ведут в прилегающей по падению и простиранию рудной залежи к массиву зоне разгрузки. Размеры зоны разгрузки определ ют по формуле. Выемку камер первой очереди на каждом Э производ т после отработки крайней камеры второй очереди на границе зоны разгрузки с выработанным пространством . Выемку камер второй очереди ни- желещажего Э осуществл ют совместно с выемкой междуэтажного целика в пределах зоны разгрузки вышележащего Э. 3 ил. (Л 4аь сл Од СП СОThe invention relates to the excavation of ores under conditions of elevated rock pressure. The goal is to increase the safety of excavation of ores under conditions of increased mining pressure due to mining operations in the discharge zone. The deposit is divided into blocks, and the blocks into floors (E) by preparatory-rifled workings. Floors are moved at a distance equal to the width of the discharge zone. Drilling of fan wells and blasting explosives into them are made from the drilling workings. Workings on the uprising from the beginning were carried out by cameras of the first stage with laying of the worked-out space with a hardening mixture, and then with cameras of the second stage with laying of their bottoms and excavation of interfloor pillars. Mining of the overlying E is conducted with advance on the width of the unloading zone of the underlying E. Mining in each block is carried out in the ore deposit adjacent to the dip and strike to the massif of the discharge zone. The size of the discharge zone is determined by the formula. The removal of chambers of the first stage at each E is made after working off the extreme camera of the second stage at the border of the unloading zone with the developed space. The removal of the chambers of the second stage of the lower-phase E is carried out together with the notch of the intermediate-floor pillar in the limits of the unloading zone of the overlying E. 3 Il. (L 4a sd JV CO
Description
1one
Изобретение относитс к горной промьшшенности и может ,быть применено при разработке рудных тел пологого и наклонного залегани .The invention relates to the mining industry and can be applied in the development of flat and inclined ore bodies.
Цель изобретени - повышение безопасности выемки руды в услови х повышенного горного давлени за счет «ведени горных работ в зоне разгрузки .The purpose of the invention is to increase the safety of excavation of ore under conditions of increased mining pressure due to "mining operations in the discharge zone.
На фиг. 1 изображен отрабатываемый участок рудного тела, вид в пла- не; на фиг. 2 - разрез А-А на фиг. 1 (с эпюрой концентрации напр жений в камерах второй- очереди и массиве); на фиг. 3 - схема наложени зон разгрузочного вли ни массива.FIG. 1 shows the area of the ore body being worked out, plan view; in fig. 2 shows section A-A in FIG. 1 (with a plot of stress concentrations in chambers of the second turn and array); in fig. 3 is a diagram of the overlapping zones of the discharge effect of the array.
Способ осуществл ют следующим образом .The method is carried out as follows.
Рудную залежь дел т на эксплуатаци- oHitbie блоки с идентичными горно-геб- логическими и горно-техническими услови ми . В свою очередь, каждый блок дел т на этажи выработками 1, проведенными на рассто нии, равном ширине зоны разгрузки. Каждый вьшележащий этаж отрабатывают системой с доставкой руды силой взрыва по восстанию камерами первой 2 и второй 3 очереди Отработку камер 3 второй очереди ведут после закладки камер 2 первой очереди. Фронт работ вьшележащего этажа подвигают относительно нижележ щего с опережением на расчетную ширину зоны 4 разгрузки. При этом горные работы в каждом блоке ведут в прилегающей по падению рудной залежи к масиву зоне разгрузки. Вышележащий . этаж при опережении относительно нижележащего на ширину зоны разгрузки подвигают выемкой камеры в нетронутом массиве 5 после отработки крайней камеры 6 второй очереди, расположенной по простиранию на границе зоны разгрузки с вьфаботаннын пространством между заполненными камерами 2 первой очереди, закладочна смесь в которых набрала нормативнзпо прочность. Выемку камер 3 второй очереди нижележащего этажа осуществл ют совместно с выемкой вьппележащего междуэтажного целика 7 в пределах зоны разгрузочного вли ни массива с выпуском руды через очистное пространство камер 3 второй очереди. Днище 8 камер 3 второй очереди закладывают тведеющей смесью до отработки нижележащего междукамерного целика.The ore deposit is divided into exploitation — oHitbie blocks with identical mining-hebological and mining-technical conditions. In turn, each unit is divided into floors with openings 1, conducted at a distance equal to the width of the discharge zone. Each upper floor is worked out by the system with ore delivery by explosion force after the uprising by chambers of the first 2 and second 3 stages. Chambers 3 of the second stage are mined after cameras 2 of the first stage are laid out. The front of the works at the overlying floor is pushed relative to the lower floor, with advance on the design width of the unloading zone 4. At the same time, mining operations in each block are carried out in the ore deposit adjacent to the fall to the massif of the discharge zone. Overlying. floor ahead of the underlying width of the unloading zone move the chamber notch in the intact array 5 after working out the extreme chamber 6 of the second stage, located along the strike on the border of the discharge zone with the upper part of the filled cameras 2 of the first stage, the filling mixture gained standard strength. The recess of the chambers 3 of the second stage of the lower floor is carried out together with the recess of the imposing interfloor pillar 7 within the discharge zone of the array with the release of ore through the cleaning space of the chambers 3 of the second stage. The bottom of the 8 chambers 3 of the second stage is inserted with a leading mixture prior to the development of the underlying chamber chamber.
Ширину зоны разгрузки по восс.та нию и простиранию рудной залежи определ ют по формулеThe width of the discharge zone by recovery and strike of the ore deposit is determined by the formula
L 10L 10
Кр + 0,5Cr + 0.5
где L - ширина зоны разгрузки, м; Кр - коэффициент разгрузки.where L is the width of the discharge zone, m; Kp - the discharge factor.
Коэффициент разгрузки Кр целиков определ етс отношением действующей на целик нагрузки к полной нагрузке от всей массы пород до земной поверхности . Значени Кр по расчету изме- н ютс от 0,45 до 0,7. Конкретные значени К в этом диапазоне опреде- л ют из услови The discharge factor Kp of the pillars is determined by the ratio of the load acting on the target to the total load from the whole mass of rocks to the earth's surface. The Kp values for the calculation vary from 0.45 to 0.7. Specific K values in this range are determined from the condition
GG
a+l a + l
f f
щих пород, т/м ;breeds, t / m;
g - ускорение свободного падени , м/с ;g — free fall acceleration, m / s;
Н - глубина разработки, м.H - depth of development, m
Несутцую способность целика рассчитывают по формулеNesuttsuyu ability pillar calculated by the formula
G G с G G with
где (Jj. - прочность руды на сжатие вwhere (jj. is the compressive strength of ore in
массиве, МПа; h - высота целика, м.array, MPa; h - the height of the rear sight, m
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU874270723A SU1456579A1 (en) | 1987-05-15 | 1987-05-15 | Method of mining sloping ore bodies |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU874270723A SU1456579A1 (en) | 1987-05-15 | 1987-05-15 | Method of mining sloping ore bodies |
Publications (1)
Publication Number | Publication Date |
---|---|
SU1456579A1 true SU1456579A1 (en) | 1989-02-07 |
Family
ID=21314216
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU874270723A SU1456579A1 (en) | 1987-05-15 | 1987-05-15 | Method of mining sloping ore bodies |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU1456579A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114352283A (en) * | 2021-12-09 | 2022-04-15 | 中国恩菲工程技术有限公司 | Mining method for mine pillar in panel area through forepoling pressure relief and subsequent filling |
-
1987
- 1987-05-15 SU SU874270723A patent/SU1456579A1/en active
Non-Patent Citations (1)
Title |
---|
Авторское свидетельство СССР № 989932, кл. Е 21 С 41/06, 1981. Балах Р.В. Разработка месторождений с закладкой хвостами обогащени .- Алма-Ата, 1977, с. 204-208. * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114352283A (en) * | 2021-12-09 | 2022-04-15 | 中国恩菲工程技术有限公司 | Mining method for mine pillar in panel area through forepoling pressure relief and subsequent filling |
CN114352283B (en) * | 2021-12-09 | 2023-07-14 | 中国恩菲工程技术有限公司 | Advanced pressure relief subsequent filling mining method for ore pillar in coiled area |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110388209B (en) | Deep hole mining method for steeply inclined double-layer ore body stage | |
CN106761912B (en) | It is a kind of be suitable for unstable formation efficiently on to route slicing and filling mining methods | |
RU2306417C2 (en) | Underground mineral mining method | |
SU1456579A1 (en) | Method of mining sloping ore bodies | |
RU2757619C1 (en) | Method for developing low-powered steel ore bodies | |
RU2632615C1 (en) | Method for development of inclined ore bodies of medium width | |
RU2270338C1 (en) | Method for preparation and excavation of inclined and steep mineral bed | |
RU2184850C1 (en) | Method of underground mining of thick flat deposits of low-hardness ores | |
US1004418A (en) | Method of mining. | |
RU2453700C2 (en) | Method for selective development of upland mineral estate reserves | |
RU2790648C1 (en) | Method for underground development of steeping ore bodies in descenting order with chamber system | |
RU2762170C1 (en) | Method for developing thin and low-powered steel-falling ore bodies | |
SU825964A1 (en) | Method of working thick steeply-inclined ore bodies | |
RU2258811C1 (en) | Open-cut mineral deposit mining method | |
RU2755287C1 (en) | Method for developing thin and low-powered steel-falling ore bodies | |
RU2094612C1 (en) | Method for opening steep thin ore deposits | |
RU1776794C (en) | Method for working-up in quarry banks | |
SU1532705A1 (en) | Method of mining mineral deposits | |
SU920216A1 (en) | Method of working ore deposits | |
RU2030581C1 (en) | Method for combined mining of thick ore bodies | |
SU1083662A1 (en) | Method of mining steep-slope ore-bodies | |
RU2379513C1 (en) | Underground hard rock minerals fields development method | |
SU1104274A1 (en) | Method of working ore reserves behind controur in quarry near-edge areas | |
RU1828921C (en) | Method for working pillars in room-and-pillar mining system | |
SU1703817A1 (en) | Method of mining ore deposits |