JPH0626297A - Tunnel drilling method - Google Patents

Tunnel drilling method

Info

Publication number
JPH0626297A
JPH0626297A JP18268292A JP18268292A JPH0626297A JP H0626297 A JPH0626297 A JP H0626297A JP 18268292 A JP18268292 A JP 18268292A JP 18268292 A JP18268292 A JP 18268292A JP H0626297 A JPH0626297 A JP H0626297A
Authority
JP
Japan
Prior art keywords
tunnel
main shaft
belt conveyor
base end
rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP18268292A
Other languages
Japanese (ja)
Inventor
Yoshikiyo Aoki
義清 青木
Hidetake Ishizaki
秀武 石崎
Masayuki Otsuka
正幸 大塚
Yuzo Koga
雄三 古賀
Toshihiko Wada
利彦 和田
Yoshiyuki Obara
由幸 小原
Masaki Imazu
雅紀 今津
Hisashi Takenaka
久 竹中
Kazuhiro Fukuda
和寛 福田
Hiroshi Kazama
広志 風間
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP18268292A priority Critical patent/JPH0626297A/en
Publication of JPH0626297A publication Critical patent/JPH0626297A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To enable a tunnel to be drilled and expanded to the required sectional area without any blasting, and enable a pilot tunnel and a main tunnel to be concurrently drilled. CONSTITUTION:A pilot tunnel 3 is drilled within the scheduled drilling section of a main tunnel 1, and the pilot tunnel 3 and the main tunnel 1 are concurrently drilled, while drilling the base end peripheral wall 4 of the pilot tunnel 3 up to the size of the main tunnel 1. As a result, a safe and continuous tunnel drilling method can be realized without any use of blasting, and a construction period can be shortened.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、トンネル掘削工法に
係り、特に、発破を用いることなく導坑と本坑を同時掘
進することができる工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel excavation method, and more particularly to a method capable of simultaneously excavating a tunnel and a main shaft without using blasting.

【0002】[0002]

【従来の技術】トンネルを掘削する場合、地質的条件を
探るためや、運搬路を目的とする作業坑のために、本坑
に先進させて導坑を掘削する場合がある。これは、導坑
先進工法と称されるもので、その一つとして、TBM
(トンネルボーリングマシン)によって導坑の全断面を
掘削して先進し、その後、該導坑の基端部を発破工法に
よって必要な断面まで切り拡げる工法がある。この工法
は、ヨーロッパ等ではよく行われているが、日本では殆
ど実施された例がないものである。
2. Description of the Related Art When excavating a tunnel, there is a case in which a tunnel is advanced to the main shaft for excavating a geological condition or for a working shaft for a transportation route. This is called an advanced tunnel construction method, one of which is TBM.
(Tunnel boring machine) is used to excavate the entire cross section of the tunnel to advance it, and then the blasting method is used to cut and spread the base end of the tunnel to the required cross section. This construction method is often used in Europe, etc., but is rarely practiced in Japan.

【0003】[0003]

【発明が解決しようとする課題】ところで、上記工法に
おいては以下に示すような問題がある。 本坑の切り拡げの発破時に、導坑への動力線、送風
管、配水管などの確実な防護ができないため、本坑の切
り拡げは導坑の掘進がすべて終了している必要があり、
導坑と本坑の切り拡げの同時進行が出来ない。このため
全体の工期が長くかかることになる。 発破時に機器類を安全な場所に退避させる必要があ
り、各作業は個別の機械を入れ替えての断続作業となる
ため、機械の大型化が難しい。また運転手が各機械毎に
必要となり、人件費がかさむ。 狭い坑内で多数の機械が稼働することによる危険性が
大きい。 発破作業の自動化は、法律による火薬の取り扱いの規
制、また安全性の確保が難しく、事実上不可能に近い。
また他の作業も発破による断続的な作業のため、全体的
なシステムの自動化が難しい。 発破の後ガス・粉塵などで坑内の環境が問題となって
いる。 火薬の取り扱い、安全性の確保が大変な作業となる。
However, the above-mentioned construction method has the following problems. At the time of blasting the cut-and-expansion of the main pit, the power line, the blower pipe, and the water pipe to the guide pit cannot be reliably protected.
It is not possible to simultaneously cut and expand the tunnel and the main shaft. Therefore, the whole construction period is long. Since it is necessary to evacuate the equipment to a safe place at the time of blasting, and each work is an intermittent work by replacing individual machines, it is difficult to increase the size of the machine. In addition, a driver is required for each machine, which increases labor costs. There is a great risk of many machines operating in a narrow mine. Automation of blasting work is practically impossible because it is difficult to regulate the handling of explosives by law and ensure safety.
Also, other work is an intermittent work due to blasting, so it is difficult to automate the entire system. After blasting, the environment inside the mine has become a problem due to gas and dust. Handling explosives and ensuring safety is a difficult task.

【0004】この発明は上記事情に鑑みてなされたもの
で、無発破により必要な断面までの切り拡げを行うこと
ができるとともに、導坑と本坑を同時掘進できるような
トンネル掘削工法を提供することを目的としている。
The present invention has been made in view of the above circumstances, and provides a tunnel excavation method capable of cutting and expanding to a required cross section without blasting and simultaneously excavating a guide shaft and a main shaft. Is intended.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、この発明の請求項1のトンネル掘削工法は、本坑の
予定掘削断面内に、円形全断面掘削機工法によって導坑
を掘削し、この導坑の基端部周壁面を割岩して該導坑の
基端部周壁面を本坑の大きさまで切り拡げつつ導坑と本
坑とを同時掘進することを特徴としている。
In order to achieve the above object, the tunnel excavation method according to claim 1 of the present invention excavates a tunnel in a planned excavation section of the main shaft by a circular full-section excavator method. The pit and the main pit are simultaneously excavated while the base end peripheral wall of the pit is split and the base end peripheral wall of the pit is cut to the size of the main pit.

【0006】請求項2のトンネル掘削工法は、請求項1
において、導坑の基端部周壁面を割岩するに際し、まず
該基端部周壁面天端付近を、上部に向かうにしたがって
漸次幅狭になるように削孔して割岩し、その後、上記基
端部周壁面を、基端部周壁面天端付近から順次周方向に
沿って基端部周壁面底部まで割岩していく工程を繰り返
して上記基端部周壁面を外側に切り拡げることを特徴と
している。
The tunnel excavation method of claim 2 is the method of claim 1.
At the time of splitting the peripheral wall surface of the base end part of the tunnel, first, near the top end of the peripheral wall surface of the base end, a hole is drilled so that the width becomes gradually narrower toward the upper part, and then the base rock is formed. Characterized by repeating the process of dividing the end peripheral wall surface from the top end of the base peripheral wall to the bottom of the base peripheral wall sequentially along the circumferential direction, and cutting the base peripheral wall to the outside. I am trying.

【0007】請求項3のトンネル掘削工法は、請求項2
において、導坑の基端部周壁面を削孔するに際し、各孔
に、割岩の際に生じさせるべき亀裂の方向に延びるスリ
ット状のノッチを形成することを特徴としている。
The tunnel excavation method of claim 3 is the method of claim 2
In the above, when drilling the peripheral wall surface of the base end portion of the tunnel, each hole is formed with a slit-shaped notch extending in the direction of the crack to be generated during the split rock.

【0008】請求項4のトンネル掘削工法は、請求項1
から3のいずれかにおいて、導坑内に、該導坑の先端部
近傍から本坑側に向けて延びる仮置きベルトコンベヤを
設けるとともに、この仮置きベルトコンベヤの基端部か
ら本坑の先端部まで延びる残土搬出ベルトコンベヤを設
け、導坑掘削の際に出る掘削残土を上記仮置きベルトコ
ンベヤに仮置きし、その後、本坑掘削の作業に支障が出
ない時期に、上記両ベルトコンベヤを起動して上記掘削
残土を上記本坑に排出することを特徴としている。
The tunnel excavation method of claim 4 is the method of claim 1.
1 to 3, the temporary placement belt conveyor extending from the vicinity of the leading end portion of the leading end to the main shaft side is provided in the guideway, and from the base end portion of the temporary placement belt conveyor to the front end portion of the main shaft. An extended residual soil unloading belt conveyor is provided, and the excavated residual soil generated during tunnel digging is temporarily placed on the temporary placement belt conveyor, and then both belt conveyors are started at a time when there is no hindrance to the main pit excavation work. The excavated soil is discharged to the main shaft.

【0009】請求項5のトンネル掘削工法は、請求項4
において、仮置きベルトコンベヤおよび残土排出ベルト
コンベヤをそれぞれ、導坑の長手方向に移動可能に設け
たことを特徴としている。
The tunnel excavation method of claim 5 is the method of claim 4
In the above, the temporary placing belt conveyor and the residual soil discharging belt conveyor are respectively provided so as to be movable in the longitudinal direction of the tunnel.

【0010】請求項6のトンネル掘削工法は、請求項1
から3のいずれかにおいて、導坑内に、該導坑の長手方
向に沿って延びかつ該長手方向に沿って移動可能な仮置
きベルトコンベヤを設け、この仮置きベルトコンベヤの
上方位置に、導坑掘削の際に出る掘削残土を導坑先端部
から仮置きベルトコンベヤまで搬送するトロッコを導坑
の長手方向に沿って移動可能に設け、本坑掘削の作業に
支障が出ない時期に、掘削残土が仮置きされた仮置きベ
ルトコンベヤを本坑まで移動させて、起動することによ
って、上記掘削残土を上記本坑に排出することを特徴と
している。
The tunnel excavation method of claim 6 is the method of claim 1.
1 to 3, a temporary placement belt conveyor that extends in the longitudinal direction of the tunnel and is movable along the longitudinal direction is provided in the tunnel, and the temporary belt conveyor is provided above the temporary belt conveyor. A trolley that conveys the excavated soil left during excavation from the tunnel tip to the temporary conveyor belt is provided so that it can be moved along the longitudinal direction of the tunnel. It is characterized in that the excavated residual soil is discharged to the main pit by moving the temporary placement belt conveyor temporarily placed to the main pit and activating it.

【0011】請求項7のトンネル掘削工法は、請求項1
から3のいずれかにおいて、本坑と導坑との取り合い部
分に、導坑基端部側から本坑先端部側に延びる防護管を
設置し、この防護管に電線、水道管、送風管等の長尺な
線状部材および残土排出ベルトコンベヤを挿通したこと
を特徴としている。
The tunnel excavation method of claim 7 is the method of claim 1.
1 to 3, a protection pipe extending from the base end side of the main shaft to the front end side of the main shaft is installed in the part where the main shaft and the main shaft are connected, and an electric wire, a water pipe, a blast pipe, etc. are installed in this protection pipe. The long linear member and the residual soil discharging belt conveyor are inserted.

【0012】請求項8のトンネル掘削工法は、請求項1
において、導坑をその頂部が本坑の頂部となるべき部位
より上方に位置するように掘削し、導坑の頂部と、本坑
の頂部となるべき部位との2つの交差部間の空間に、電
線、水道管、送風管等の長尺な線状部材を挿通したこと
を特徴としている。
The tunnel excavation method of claim 8 is the method of claim 1.
In, the tunnel was excavated so that its top was located above the site that should be the top of the main shaft, and the space between the two intersections of the top of the main shaft and the site that should be the top of the main shaft It is characterized in that a long linear member such as an electric wire, a water pipe, and a blower pipe is inserted.

【0013】請求項9のトンネル掘削工法は、請求項1
において、本坑の予定掘削断面内における上部に、円形
全断面掘削機工法によって導坑を掘削し、この導坑の基
端部周壁面を割岩して該導坑の基端部周壁面を本坑の大
きさまで切り拡げる場合において、導坑の基端部周壁面
の底部から下方を削孔して割岩した後、上記基端部周壁
面を割岩する工程を繰り返し行って、導坑の基端部周壁
面を本坑の大きさまで切り拡げることを特徴としてい
る。
The tunnel excavation method of claim 9 is the method of claim 1.
In the above, in the planned excavation cross section of the main shaft, a guide shaft is excavated by the circular full-section excavator method, and the base end peripheral wall surface of this guide shaft is split to form the base end peripheral wall surface of the guide shaft. In the case of cutting to the size of the pit, after drilling the lower part from the bottom of the peripheral wall of the base end of the guide pit and breaking the rock, the process of dividing the peripheral wall of the base end is repeated, and the base end of the guide pit. The feature is that the peripheral wall is cut to the size of the main shaft.

【0014】請求項10のトンネル掘削工法は、請求項
1において、本坑の予定掘削断面内における上部に、円
形全断面掘削機工法によって導坑を掘削し、この導坑の
基端部周壁面を割岩して該導坑の基端部周壁面を本坑の
大きさまで切り拡げる場合において、導坑の基端部周壁
面を割岩して、該基端部周壁面の底部より上方を切り拡
げつつ掘進して本坑の上半分を掘削し、その後、本坑の
下半分を縦方向に割岩することを特徴としている。
According to a tenth aspect of the present invention, in the tunnel excavation method according to the first aspect, a tunnel is excavated at an upper portion of a planned excavation section of the main shaft by a circular full-section excavator method, and a peripheral wall surface of a base end portion of the tunnel. In the case of splitting the base wall of the guide shaft to the size of the main shaft, the base wall of the guide shaft is split and cut above the bottom of the base wall. It is characterized by excavating while drilling the upper half of the main pit and then splitting the lower half of the main pit vertically.

【0015】請求項11のトンネル掘削工法は、請求項
10において、上半分が掘削された本坑と導坑との取り
合い部分に、導坑基端部側から本坑側に延びる防護管を
設置し、この防護管に電線、水道管、送風管等の長尺な
線状部材および残土排出ベルトコンベヤを挿通したこと
を特徴としている。
According to the tunnel excavation method of claim 11, a protection pipe extending from the base end side of the tunnel to the main shaft side is installed at a portion where the main shaft where the upper half has been excavated and the tunnel are connected. However, a long line-shaped member such as an electric wire, a water pipe, a blower pipe, etc. and a residual soil discharging belt conveyor are inserted through the protective pipe.

【0016】[0016]

【作用】請求項1のトンネル掘削工法にあっては、本坑
の予定掘削断面内に、導坑を掘削し、この導坑の基端部
周壁面を割岩して該導坑の基端部周壁面を本坑の大きさ
まで切り拡げつつ導坑と本坑とを同時掘進することによ
って、発破を用いることのない、安全かつ連続的なトン
ネル掘削を実現して、工期の短縮を図る。
According to the tunnel excavation method of claim 1, a tunnel is excavated within the planned excavation cross section of the main shaft, and the peripheral wall surface of the proximal end of the tunnel is split to form a base end of the tunnel. By cutting the peripheral wall to the size of the main shaft and excavating the guide shaft and the main shaft at the same time, safe and continuous tunnel excavation without blasting is realized, and the construction period is shortened.

【0017】請求項2のトンネル掘削工法にあっては、
導坑の基端部周壁面天端付近を、上部に向かうにしたが
って漸次幅狭になるように削孔して割岩することによっ
て、この割岩後、岩片を支えるものがなくなって、該岩
片が自重によって落下する。岩片が欠落した部分は自由
面となり、その後、基端部周壁面を、上記自由面から順
次周方向に沿って基端部周壁面底部まで割岩していくこ
とによって、岩片は順次落下する。これらの工程を繰り
返して行うことにより割岩による切り拡げを行う。
In the tunnel excavation method of claim 2,
By drilling a hole in the vicinity of the crown of the peripheral wall of the base end part of the tunnel and gradually narrowing it toward the upper part, there is nothing supporting the rock piece after this rock piece, and the rock piece is self-weighted. To fall by. The part where the rock piece is missing becomes a free surface, and thereafter, the rock wall is successively dropped by dividing the base end peripheral wall surface from the free surface to the base end peripheral wall surface bottom along the circumferential direction in sequence. By repeating these steps, cutting with a split rock is performed.

【0018】請求項3のトンネル掘削工法にあっては、
導坑の基端部周壁面を削孔するに際し、各孔に、割岩の
際に生じさせるべき亀裂の方向に延びるスリット状のノ
ッチを形成することによって、割岩の際にこのノッチに
応力集中が起こり、該ノッチから延びるようにして亀裂
が入り、これによって割岩を所望の方向に容易かつ確実
に行う。
In the tunnel excavation method of claim 3,
When drilling the peripheral wall of the base end part of the tunnel, by forming a slit-shaped notch in each hole that extends in the direction of the crack that should occur during split rock, stress concentration in this notch during split rock It occurs and cracks extend from the notch, which facilitates and ensures the splitting in the desired direction.

【0019】請求項4のトンネル掘削工法にあっては、
請求項1か3のいずれかの掘削を行う際に、導坑掘削の
際に出る掘削残土を仮置きベルトコンベヤに仮置きし、
その後、本坑掘削の作業に支障が出ない時期に、仮置き
ベルトコンベヤと残土搬出ベルトコンベヤとを起動して
上記掘削残土を本坑に排出することによって、導坑の掘
削作業を、本坑の掘削作業に影響されることなく行っ
て、トンネル掘進の効率化を図る。
In the tunnel excavation method of claim 4,
When the excavation according to any one of claims 1 and 3, the excavated residual soil produced during the tunnel excavation is temporarily placed on a temporary placement belt conveyor,
After that, when there is no hindrance to the main pit excavation work, the temporary placement belt conveyor and the residual soil carry-out belt conveyor are activated to discharge the excavation residual soil to the main pit, thereby completing the main pit excavation work. The efficiency of tunnel excavation will be improved without being affected by the excavation work of.

【0020】請求項5のトンネル掘削工法にあっては、
請求項4の掘削を行う際に、導坑および本坑の掘進に伴
って両ベルトコンベヤを前進させることによって、掘削
残土の排出を容易かつ連続的に行い、また、割岩作業の
際には、残土排出コンベアを仮置きベルトコンベヤ側に
移動させて退避することによって、割岩作業を支障なく
確実に行う。
In the tunnel excavation method of claim 5,
When excavating according to claim 4, by advancing both belt conveyors along with the excavation of the guide shaft and the main shaft, the excavated residual soil is easily and continuously discharged. By moving the residual soil discharge conveyor to the temporary placement belt conveyor side and retracting it, the split rock work can be performed reliably without any hindrance.

【0021】請求項6のトンネル掘削工法にあっては、
請求項1から3のいずれかの掘削を行う際に、導坑掘削
の際に出る掘削残土をトロッコによって導坑先端部から
仮置きベルトコンベヤまで搬送し、本坑掘削の作業に支
障が出ない時期に、掘削残土が仮置きされた仮置きベル
トコンベヤを本坑まで移動させて、起動することによっ
て、上記掘削残土を上記本坑に排出し、これによって、
導坑の掘削作業を、本坑の掘削作業に影響されることな
く行って、トンネル掘進の効率化を図る。
In the tunnel excavation method of claim 6,
When the excavation according to any one of claims 1 to 3 is performed, the excavated soil left during the excavation of the tunnel is conveyed by the truck to the temporary conveyor belt conveyor from the tip of the tunnel so that there is no hindrance to the excavation work of the main tunnel. At the time, the temporary excavation belt conveyor in which the excavation residual soil is temporarily placed is moved to the main pit and activated to discharge the excavation residual soil to the main pit, thereby,
The tunnel excavation work will be performed without being affected by the main shaft excavation work, and the efficiency of tunnel excavation will be improved.

【0022】請求項7のトンネル掘削工法にあっては、
請求項1から3のいずれかの掘削を行う際に、防護管に
電線、水道管、送風管等の長尺な線状部材および残土排
出ベルトコンベヤを挿通することによって、割岩されて
落下してくる岩片から線状部材を保護するとともに安全
な通行を可能にし、また、導坑掘削の際に出る掘削残土
を、割岩作業に関係なく搬出することによって、掘削作
業の効率化を図る。
In the tunnel excavation method of claim 7,
When excavating according to any one of claims 1 to 3, by inserting a long linear member such as an electric wire, a water pipe, a blower pipe, etc. and a residual soil discharging belt conveyor into the protective pipe, the rock is broken and falls. It protects the linear member from the rock fragments coming from it and enables safe passage, and the excavation residual soil generated during the tunnel excavation is carried out irrespective of the split rock work to improve the efficiency of the excavation work.

【0023】請求項8のトンネル掘削工法にあっては、
請求項1の掘削を行う際に、導坑をその頂部が本坑の頂
部となるべき部位より上方に位置するように掘削するこ
とによって、導坑の頂部と、本坑の頂部となるべき部位
との2つの交差部間にある空間は岩片が落下してこない
安全なエリアとなり、この空間に電線、水道管、送風管
等の長尺な線状部材を挿通することによって、防護管を
設置することなく線状部材を保護する。
In the tunnel excavation method of claim 8,
When the excavation according to claim 1 is performed, the top of the tunnel and the site to be the top of the main shaft are excavated so that the top of the guide shaft is located above the site to be the top of the main shaft. The space between the two intersections with and is a safe area where rock fragments do not fall, and a protective pipe is installed by inserting long linear members such as electric wires, water pipes, and air blow pipes into this space. Without protecting the linear member.

【0024】請求項9のトンネル掘削工法にあっては、
請求項1の掘削を行う際に、導坑の基端部周壁面の底部
から下方を削孔して割岩して開口部を形成した後、上記
基端部周壁面を割岩することによって、割岩された岩片
を、上記開口部から落下させて排出し、これによって本
坑予定掘削断面内の上部に導坑があり、この導坑より下
方の掘削断面が大きい場合においても、導坑の基端部周
壁面を本坑の大きさまで容易に切り拡げることができ
る。
In the tunnel excavation method of claim 9,
When the excavation according to claim 1 is carried out, the lower part of the peripheral wall surface of the base end part of the tunnel is drilled from the bottom to form an opening to form an opening, and then the peripheral wall surface of the base end part is divided to form a split rock. The resulting rock fragments are dropped from the above-mentioned opening and discharged, so that even if there is a tunnel at the upper part of the planned excavation section of the main pit and the excavation section below this tunnel is large, the base end of the tunnel The peripheral wall can be easily cut to the size of the main shaft.

【0025】請求項10のトンネル掘削工法にあって
は、請求項1の掘削を行う際に、導坑の基端部周壁面を
割岩して、該基端部周壁面の底部より上方を切り拡げつ
つ掘進して本坑の上半分を掘削し、その後、本坑の下半
分を縦方向に割岩する、すなわち割岩作業を上半分と下
半分に分割して行うことによって、本坑予定掘削断面内
の上部に導坑があり、この導坑より下方の掘削断面が大
きい場合においても、導坑の基端部周壁面を本坑の大き
さまで容易に切り拡げることができる。
In the tunnel excavation method of claim 10, when the excavation of claim 1 is performed, the peripheral wall surface of the base end portion of the tunnel is split and cut above the bottom of the peripheral wall surface of the base end portion. Excavation while expanding to excavate the upper half of the main shaft, and then split the lower half of the main shaft in the vertical direction, that is, the split rock work is divided into the upper half and the lower half to perform the planned main excavation cross section. Even if there is a tunnel in the upper part and the excavation cross section below this tunnel is large, the peripheral wall surface of the proximal end portion of the tunnel can be easily cut to the size of the main tunnel.

【0026】請求項11のトンネル掘削工法にあって
は、請求項10の掘削を行う際に、上半分が掘削された
本坑と導坑との取り合い部分に設置された防護管に、電
線、水道管、送風管等の長尺な線状部材および残土排出
ベルトコンベヤを挿通することによって、割岩されて落
下してくる岩片から線状部材を保護するとともに安全な
通行を可能にし、また、導坑掘削の際に出る掘削残土
を、割岩作業に関係なく搬出し、さらに、この掘削残土
を本坑の下半分の割岩によってでる岩片と一緒に処理す
ることによって掘削作業の効率化を図る。
In the tunnel excavation method according to claim 11, when excavating according to claim 10, an electric wire is attached to a protective pipe installed at a connecting portion between the main shaft and the tunnel where the upper half is excavated. By inserting long linear members such as water pipes and blast pipes and the belt conveyor for discharging the residual soil, the linear members are protected from the rock fragments that are broken and fall, and safe passage is also possible. Efficient excavation work will be carried out by carrying out the excavated residual soil generated during the excavation of the mine regardless of the split rock work, and treating this residual excavated soil together with the rock fragments produced by the split rock in the lower half of the main shaft.

【0027】[0027]

【実施例】以下、図面を参照してこの発明のトンネル掘
削工法の実施例を説明する。 (請求項1に相当する発明)まず、図1および図2に示
すように、本坑1の予定掘削断面内に、円形全断面掘削
機工法、すなわちTBM2によって導坑3を掘削する。
この状態で導坑3の基端部周壁面4を削孔し、発破をか
ければ導坑3が自由面になり、火薬量が少なく、効率的
な発破ができることが知られている。このように、自由
面に向けて岩が割れやすくなることを利用して、発破の
代わりに割岩によって導坑3の基端部周壁面4を本坑1
の大きさまで切り拡げる。そして、上記導坑3の掘進
と、導坑3の基端部周壁面4の切り拡げ、すなわち本坑
切り拡げとを同時進行することによって、トンネルの掘
削を行う。したがって、発破を用いることなく安全かつ
連続的にトンネルを掘削することができ、工期の短縮を
図ることができる。
Embodiments of the tunnel excavation method of the present invention will be described below with reference to the drawings. (Invention Corresponding to Claim 1) First, as shown in FIGS. 1 and 2, a guide shaft 3 is excavated in a planned excavation section of the main shaft 1 by a circular full-section excavator method, that is, a TBM 2.
It is known that, in this state, if the base end peripheral wall surface 4 of the tunnel 3 is drilled and blasted, the tunnel 3 becomes a free surface, the amount of explosive is small, and efficient blasting is possible. In this way, by utilizing the fact that the rock tends to crack toward the free surface, the base end peripheral wall surface 4 of the tunnel 3 is replaced by blast rock instead of blasting and the main shaft 1
Cut to the size of. Then, the tunnel excavation is performed by simultaneously advancing the tunnel 3 and cutting and expanding the base end peripheral wall surface 4 of the tunnel 3, that is, cutting and expanding the main shaft. Therefore, the tunnel can be excavated safely and continuously without using blasting, and the construction period can be shortened.

【0028】(請求項2に相当する発明)上記導坑3の
基端部周壁面4を割岩する場合、自由面である基端部周
壁面4がTBM2で掘削した断面円形状をなしているの
で、この回りの岩盤に等間隔に亀裂を入れたとしても、
岩片どうしがせりあい(アーチ状になり)岩片を元の岩
盤から容易に取り外すことができない。そこで、亀裂が
入った岩片をその自重で落下させるため、岩片どうしが
せりあわないように、割岩の順序、方法が重要となる。
(Invention equivalent to claim 2) When the base end peripheral wall surface 4 of the guide shaft 3 is split, the base end peripheral wall surface 4 which is a free surface has a circular cross section excavated by the TBM 2. So, even if you put cracks at equal intervals in the rock around this,
Rock pieces stick together (become arched) and cannot be easily removed from the original bedrock. Therefore, since the rock fragments with cracks are dropped by their own weight, the order and method of split rocks are important so that the rock fragments do not touch each other.

【0029】そこで、本発明では、以下のようにして割
岩を行う。すなわち、図3に示すように、まず、基端部
周壁面4の天端付近4aを、上部に向かうにしたがって
漸次幅狭になるようにして削孔して割岩する。この岩片
5aは上が狭くなった台形状をなしているので、割岩
後、この岩片5aを支えるものが無くなって、自重によ
って落下し、その岩片5aが欠落した切欠部分は自由面
となる。
Therefore, in the present invention, split rock is performed as follows. That is, as shown in FIG. 3, first, the vicinity of the top end 4a of the peripheral wall surface 4 of the base end part is drilled so that the width becomes gradually narrower toward the upper part and split rocks. Since this rock piece 5a has a trapezoidal shape with a narrow upper part, there is no support for this rock piece 5a after split rock, and the rock piece 5a falls by its own weight, and the notch portion where the rock piece 5a is missing becomes a free surface.

【0030】次いで、岩片5aと隣接していた部分を、
略三角形状になるようにして削孔・割岩すれば、この岩
片6a,6a′は岩片5aが無くなっているのでその自
重によって落下する。そして、次々に隣接する部分を、
順次周方向に沿って方形状になるようにして基端部周壁
面4の底部まで削孔・割岩すれば、それぞれの岩片7
a,7a′、8a,8a′、9a,9a′…が順次自重
によって落下して、導坑3が一周分切り拡げられる。
Next, the portion adjacent to the rock piece 5a is
When drilling and splitting rocks in a substantially triangular shape, the rock pieces 6a and 6a 'drop due to their own weight because the rock piece 5a has disappeared. And the adjacent parts one after another,
Drilling and splitting rocks to the bottom of the peripheral wall 4 at the base end in a square shape along the circumferential direction will result in each rock fragment 7
.., 7a ', 8a, 8a', 9a, 9a '... are successively dropped by their own weight, and the tunnel 3 is cut and expanded for one round.

【0031】また、岩片7a,7a′以降に割岩が進ん
だら、さらに外側の円へと拡げ、順次岩片5b、岩片6
b,6b′,7b,7b′、8b,8b′、9b,9
b′…を削孔・割岩し、さらに、岩片7b,7b′以降
に割岩が進んだら、さらに外側の円へと拡げ、同様にし
て割岩を繰り返していく。なお、新しい円の割岩作業に
入る時は、岩片5a,5bと同様に、上部に向かうにし
たがって漸次幅狭になるようにして削孔して割岩するこ
とを最初に行う。
When the split rock advances after the rock pieces 7a, 7a ', it further expands to the outer circle, and the rock pieces 5b and 6 are successively formed.
b, 6b ', 7b, 7b', 8b, 8b ', 9b, 9
When b '... is drilled and split, and the split rock progresses after the rock fragments 7b, 7b', it is further expanded to the outer circle and the split rock is repeated in the same manner. In addition, when entering a new circle breaking work, as with the rock pieces 5a and 5b, firstly, the rock is drilled so that the width becomes gradually narrower toward the upper part and the breaking rock is performed.

【0032】そして、上記導坑3の基端部周壁面4の割
岩による切り拡げが進んで、図4に示すように、掘削予
定線L近くになったら、この予定線Lに合わせて、順次
岩片5e,5e′、6e,6e′、7e,7e′、8
e,8e′、9e,9e′を削孔・割岩していき、最終
的に、上記基端部周壁面4を本坑1の大きさ(直径)ま
で切り拡げる。さらに、基端部周壁面4が切り拡げられ
て本坑1となったならば、次の基端部周壁面4を上記と
同様にして割岩して切り拡げていく工程を繰り返して、
本坑1を掘進していく。なお、本坑1の掘進と同時に導
坑3もTBM2によって掘進していく。
Then, when the base end peripheral wall surface 4 of the tunnel 3 is cut and expanded by the split rock, and as shown in FIG. Rock pieces 5e, 5e ', 6e, 6e', 7e, 7e ', 8
The holes e, 8e ′, 9e, 9e ′ are drilled and split, and finally the peripheral wall surface 4 of the base end is cut to the size (diameter) of the main shaft 1. Further, when the base end peripheral wall surface 4 is cut and expanded to become the main shaft 1, the process of splitting and expanding the next base end peripheral wall surface 4 in the same manner as above is repeated,
The main pit 1 is advanced. At the same time as the main shaft 1 is being dug, the guide shaft 3 is also dug by the TBM 2.

【0033】(請求項3に相当する発明)また、上記削
孔を行う場合、図3に示すように、多数の孔10…を主
に周方向に沿って所定間隔で形成するが、この際、各孔
10に、これと隣接する孔10に向けて延びる、すなわ
ち割岩の際に生じさせるべき亀裂の方向に延びるスリッ
ト状のノッチ10a,10aを形成すれば、このノッチ
10aに応力集中が起こり、該ノッチ10aから延びる
ようにして亀裂が入るので、割岩を所望の方向に容易か
つ確実に行うことができる。
(Invention equivalent to claim 3) When performing the above-mentioned drilling, as shown in FIG. 3, a large number of holes 10 ... Are formed mainly at predetermined intervals along the circumferential direction. By forming slit-shaped notches 10a, 10a extending in the respective holes 10 toward the holes 10 adjacent to the holes 10, that is, extending in the direction of the crack to be generated during the split rock, stress concentration occurs in the notches 10a. Since a crack is formed so as to extend from the notch 10a, the split rock can be easily and reliably performed in a desired direction.

【0034】さらに、導坑3の基端部周壁面4の天端付
近4aを最初に削孔して割岩する場合、通常のノッチな
しの削孔では、孔10cから亀裂が自由面(導坑3の内
壁面)に平行に入り易いが、孔10cにノッチ10a,
10aを割岩の際に生じさせるべき亀裂の方向に形成、
すなわち自由面に対し斜めに形成することによって、亀
裂の方向を制御でき、容易かつ確実に岩片5aを台形状
に割岩することができる。
Further, in the case where the rock near the top end 4a of the peripheral wall 4 of the base end portion of the guide shaft 3 is first drilled and the rock is split, in the case of the usual notch drilling, a crack is generated from the hole 10c on the free surface (guide shaft). It is easy to enter parallel to the inner wall surface of No. 3, but notches 10a,
10a is formed in the direction of the crack that should be generated when the rock is split,
That is, by forming it obliquely with respect to the free surface, the direction of the crack can be controlled, and the rock piece 5a can be easily and reliably split into a trapezoid.

【0035】上記ノッチ10a,10aは本出願人の所
有する特許第1253066号の「岩盤掘削穿孔方法及
び装置」を実施することによって容易かつ確実に行うこ
とができる。このようにして削孔されたノッチ付きの孔
10(10c)から亀裂を生じさせる場合、図31およ
び図32に示すように、孔10に油圧式割岩機14を挿
通して行う。この油圧式割岩機14は、互いに径方向に
接離自在に設けれて、略円筒を形成する一対の鋼製の圧
力板14a,14aと、これら圧力板14a,14aの
間に設けられたゴムチューブ14bと、このゴムチュー
ブ14bと圧力板14a,14aとの間に設けられた一
対のくさび14c,14cとを主体として構成されてい
る。
The notches 10a and 10a can be easily and surely formed by carrying out the "rock drilling and drilling method and apparatus" of the Japanese Patent No. 1253066 owned by the present applicant. When a crack is generated from the notched hole 10 (10c) drilled in this way, the hydraulic breaker 14 is inserted into the hole 10 as shown in FIGS. 31 and 32. This hydraulic type rock breaking machine 14 is provided so as to be able to come in contact with and separate from each other in the radial direction, and has a pair of steel pressure plates 14a, 14a forming a substantially cylindrical shape, and a rubber provided between these pressure plates 14a, 14a. The tube 14b is mainly composed of a tube 14b and a pair of wedges 14c, 14c provided between the rubber tube 14b and the pressure plates 14a, 14a.

【0036】そして、この油圧式割岩機14では、図3
2に示すように、ゴムチューブ14bを油圧によって膨
張させることによって、くさび14c,14cを互いに
離間する方向に移動させ、該くさび14c,14cによ
って圧力板14a,14aを拡径させて孔10に内圧を
かけることによって、ノッチ10a,10aに応力を集
中させ、これによって、ノッチ10a,10aから延び
る亀裂を生じさせるようになっている。
In this hydraulic type rock breaking machine 14, as shown in FIG.
As shown in FIG. 2, by expanding the rubber tube 14b by hydraulic pressure, the wedges 14c, 14c are moved in the direction in which they are separated from each other, and the wedges 14c, 14c expand the pressure plates 14a, 14a to cause the internal pressure in the hole 10. The stress is concentrated on the notches 10a, 10a by applying the stress, thereby causing cracks extending from the notches 10a, 10a.

【0037】なお、上記実施例では、図1および図2に
示すように、導坑3を本坑1の予定掘削断面内におい
て、比較的上部に形成する例について述べたが、導坑3
の位置としては、上記に限らず、図5および図6に示す
ように、本坑1の予定掘削断面内における最上部、図7
および図8に示すように、予定掘削断面内における中央
部、図9および図10に示すように、予定掘削断面内に
おける最下部に導坑3があってもよく、これらの場合に
おいても基本的には上述したようにして、導坑3の基端
部周壁面4の割岩作業を行う。
In the above-mentioned embodiment, as shown in FIGS. 1 and 2, an example in which the guide shaft 3 is formed relatively above in the planned excavation cross section of the main shaft 1 has been described.
The position of is not limited to the above, but as shown in FIGS. 5 and 6, the uppermost part in the planned excavation cross section of the main shaft 1, FIG.
As shown in FIG. 8 and FIG. 8, there may be a guide hole 3 at the central portion in the planned excavation cross section, and at the lowest portion in the planned excavation cross section as shown in FIGS. 9 and 10. As described above, the split rock work on the peripheral wall surface 4 of the base end portion of the tunnel 3 is performed.

【0038】(請求項4および5に相当する発明)さ
て、TBM2による導坑3と、割岩による本坑1の掘進
とを効率的に行うためには、TBM2による施工が、割
岩による切り拡げの工事に影響を与えず、かつ影響され
ないようにする必要がある。TBM2による掘進で使用
する材料の投入は、割岩による切り拡げ作業の影響のな
い時間に導坑3に搬入し、導坑3内に仮置きしておけば
よい。しかし、掘削残土は掘進作業中に常時かつ大量に
発生するため、この処理が問題となる。掘削残土の本坑
1への搬出は、本坑1の作業の時間帯に合わせて行う必
要がああるため、導坑3内に残土の仮置き場を設置す
る。これにベルトコンベヤを使用し、仮置きとともに残
土の搬出に利用する。図11および図12にその方法の
一例を示す。
(Invention equivalent to claims 4 and 5) Now, in order to efficiently excavate the tunnel 3 by the TBM 2 and the excavation of the main pit 1 by the split rock, the construction by the TBM 2 is performed by cutting and expanding by the split rock. It is necessary not to affect the construction and not to be affected. The material used in the excavation by the TBM 2 may be loaded into the tunnel 3 at a time when there is no influence of the cutting and expanding work by the split rock, and may be temporarily placed in the tunnel 3. However, this processing becomes a problem because a large amount of excavated soil is constantly generated during excavation work. Since it is necessary to carry out the excavated surplus soil to the main pit 1 in accordance with the time zone of the work of the main pit 1, a temporary storage place for the residual soil is set up in the tunnel 3. A belt conveyor is used for this, and it is used for temporary storage and removal of residual soil. 11 and 12 show an example of the method.

【0039】これらの図に示すように、導坑3内には、
該導坑3の先端部にあるTBM2から本坑1側に向けて
延びる仮置きベルトコンベヤ15と、この仮置きベルト
コンベヤ15の基端部下方から本坑1の先端部まで延び
る残土搬出ベルトコンベヤ16が設けられている。仮置
きベルトコンベヤ15は、その下部に幅方向に一対の車
輪15a,15aが導坑3の長手方向に所定間隔で取付
けられて、該長手方向に移動可能にされている。また、
仮置きベルトコンベヤ15の上部側方には、手摺15b
付きの通路15cが設置されており、この通路15cに
よって導坑3内での通行が安全にできるようになってい
る。
As shown in these figures, in the tunnel 3,
A temporary placement belt conveyor 15 extending from the TBM 2 at the tip of the tunnel 3 toward the main pit 1 side, and a residual soil unloading belt conveyor extending from below the base end of the temporary placement belt conveyor 15 to the tip of the main pit 1. 16 are provided. The temporary belt conveyor 15 has a pair of wheels 15a, 15a attached to the lower portion in the width direction at predetermined intervals in the longitudinal direction of the tunnel 3, and is movable in the longitudinal direction. Also,
Handrails 15b are provided on the upper side of the temporary placement belt conveyor 15.
An associated passage 15c is installed, and the passage 15c enables safe passage in the tunnel 3.

【0040】さらに、上記残土搬出ベルトコンベヤ16
は、その下部に幅方向に一対の車輪16a,16aが導
坑3の長手方向に所定間隔で取付けられて、該長手方向
に移動可能にされている。なお、残土搬出ベルトコンベ
ヤ16を移動させるための駆動装置は、該ベルトコンベ
ヤ16に取り付けてもよいし、仮置きベルトコンベヤ1
5など(他のものでもよい)に取り付け、ワイヤ等で操
作してもよい。また、仮置きベルトコンベヤ15を移動
させるための駆動装置は、該ベルトコンベヤ15に取り
付けてもよいし、導坑3の壁等(他のものでもよい)に
取り付け、ワイヤ等で操作してもよい。
Further, the above-mentioned remaining soil carrying-out belt conveyor 16
A pair of wheels 16a, 16a are attached to the lower portion of the guide 3 in the width direction at predetermined intervals in the longitudinal direction of the tunnel 3, and are movable in the longitudinal direction. The drive device for moving the residual soil carrying-out belt conveyor 16 may be attached to the belt conveyor 16 or the temporary placement belt conveyor 1
5 or the like (may be other), and may be operated with a wire or the like. Further, the drive device for moving the temporary-placement belt conveyor 15 may be attached to the belt conveyor 15, or may be attached to a wall or the like of the tunnel 3 (or another one) and operated by a wire or the like. Good.

【0041】そして、上記両ベルトコンベヤ15,16
を使用して掘削残土を搬出する場合、TBM2に取り付
けてある排土コンベア(ベルトコンベヤ、スクリュウコ
ンベア等)17によって掘削残土を取り出して、順次ホ
ッパ18を通して仮置きベルトコンベヤ15の上に仮置
きしていく。この場合、仮置きベルトコンベヤ15を周
回しつつ掘削残土を仮置きするが、該ベルトコンベヤ1
5上を搬送される先端の掘削残土が、ベルトコンベヤ1
5の基端部に位置したらベルトコンベヤ15の周回を停
止するとともに、排土コンベア17も停止する。
Then, the above two belt conveyors 15 and 16
When the excavation residual soil is carried out using, the excavation residual soil is taken out by the soil discharge conveyor (belt conveyor, screw conveyor, etc.) 17 attached to the TBM 2 and is temporarily placed on the temporary placement belt conveyor 15 through the hopper 18. To go. In this case, the excavated soil is temporarily placed while circling the temporary placement belt conveyor 15.
The excavated soil remaining on the top of the conveyor belt 5 is conveyed on the belt conveyor 1.
When it is located at the base end of 5, the belt conveyor 15 is stopped from rotating and the earth discharging conveyor 17 is also stopped.

【0042】その後、上記割岩による本坑掘削の作業に
支障が出ない時期に、具体的には本坑1のズリ出し時
に、残土搬出ベルトコンベヤ16を本坑側に移動させ、
該本坑1の先端部に位置させた上で、上記仮置きベルト
コンベヤ15と残土搬出ベルトコンベヤ16を周回す
る。すると、掘削残土は、仮置きベルトコンベヤ15か
ら残土搬出ベルトコンベヤ16に乗り移り、該ベルトコ
ンベヤ16によって本坑1内に排出される。なお、上記
のような両ベルトコンベヤ15,16による残土の搬出
作業の場合、導坑3と本坑1の掘進速度がほぼ一定であ
る必要があり、導坑3の掘進に伴って両ベルトコンベヤ
15,16を前進させるようにする。
After that, when there is no hindrance to the operation of the main pit excavation by the above-mentioned split rock, specifically, when the main pit 1 is unloaded, the residual soil carry-out belt conveyor 16 is moved to the main pit side,
After being positioned at the tip of the main shaft 1, the temporary placement belt conveyor 15 and the residual soil unloading belt conveyor 16 are circulated. Then, the excavated residual soil is transferred from the temporary storage belt conveyor 15 to the residual soil carrying-out belt conveyor 16 and is discharged into the main shaft 1 by the belt conveyor 16. In addition, in the case of carrying out the residual soil by the both belt conveyors 15 and 16 as described above, it is necessary that the excavation speed of the tunnel 3 and the main pit 1 be substantially constant. Make 15 and 16 move forward.

【0043】上述のようにして、導坑3の掘削の際に出
る掘削残土を排出することにより、導坑3の掘削作業
を、本坑1の掘削作業に影響されることなく行うことが
できるので、トンネル掘進の効率化を図ることができ
る。また、導坑3および本坑1の掘進に伴って容易に両
ベルトコンベヤ15,16を前進させることによって、
掘削残土の排出を容易かつ連続的に行うことができる。
さらに、上記割岩作業の際には、残土排出コンベア16
を仮置きベルトコンベヤ15側に移動させて退避するこ
とによって、割岩作業を支障なく確実に行うことができ
る。
As described above, by discharging the excavated residual soil generated during the excavation of the tunnel 3, the excavation work of the tunnel 3 can be performed without being affected by the excavation work of the main shaft 1. Therefore, the efficiency of tunnel excavation can be improved. Further, by easily advancing both belt conveyors 15 and 16 as the guide shaft 3 and the main shaft 1 advance,
The excavated soil can be easily and continuously discharged.
Furthermore, at the time of the above-mentioned split rock work, the residual soil discharge conveyor 16
It is possible to surely perform the split rock work without trouble by moving the to the temporary conveyor belt conveyor 15 side and retracting it.

【0044】(請求項6に相当する発明)図13ないし
図15は上記掘削残土の排出作業をトロッコ20と仮置
きベルトコンベヤ15とによって行うようにした例を示
す。これらの図に示すように、導坑3内には、該導坑3
の長手方向に沿って延びかつ該長手方向に沿って移動可
能な上記仮置きベルトコンベヤ15が設けられている。
この仮置きベルトコンベヤ15の上方には、導坑3を横
断する多数の枕木21…が導坑3の長手方向に沿って所
定間隔で設置されており、これら枕木21…には導坑3
の長手方向に延びる2対のレール22,22が設置され
ている。各一対のレール22,22には、トロッコ2
0,20が車輪20aによって移動自在に設けられてお
り、図13において右側トロッコ20には、トロッコ2
0,20を駆動させるバッテリーロコ23が連結されて
いる。
(Invention Corresponding to Claim 6) FIGS. 13 to 15 show an example in which the excavation residual soil is discharged by the truck 20 and the temporary placement belt conveyor 15. As shown in these figures, inside the tunnel 3,
The temporary-placement belt conveyor 15 is provided which extends along the longitudinal direction and is movable along the longitudinal direction.
A large number of sleepers 21 that cross the guide shaft 3 are installed above the temporary belt conveyor 15 along the longitudinal direction of the guide shaft 3 at predetermined intervals.
Two pairs of rails 22, 22 extending in the longitudinal direction are installed. Each pair of rails 22, 22 has a truck 2
0 and 20 are movably provided by wheels 20a. In FIG. 13, the right dolly 20 has a dolly 2
A battery locomotive 23 for driving 0, 20 is connected.

【0045】そして、上記トロッコ20と仮置きベルト
コンベヤ15を使用して掘削残土を搬出する場合、TB
M2によって掘削された掘削残土を、例えば、上記排土
コンベア17等によって、トロッコ20,20に積み込
み該トロッコ20,20によって仮置きベルトコンベヤ
15の所まで運搬し、該ベルトコンベヤ15に一時的に
降ろし、仮置きする。この場合、トロッコ20,20を
ベルトコンベヤ15に沿って移動させつつ掘削残土を降
ろしてもよいし、ベルトコンベヤ15を周回させつつ降
ろしてもよい。
When the excavated soil is carried out by using the truck 20 and the temporary placement belt conveyor 15, the TB
The excavated soil excavated by M2 is loaded on the trolleys 20, 20 by, for example, the soil discharge conveyor 17 or the like, conveyed by the trolleys 20, 20 to the temporary placement belt conveyor 15, and temporarily transferred to the belt conveyor 15. Lower it and place it temporarily. In this case, the excavated soil may be unloaded while moving the trucks 20, 20 along the belt conveyor 15, or may be unloaded while the belt conveyor 15 is rotated.

【0046】その後、上記割岩による本坑掘削が終わ
り、残土処分を行う時、すなわち本坑1のズリ出し時
に、仮置きベルトコンベヤ15を本坑側に移動させ、該
本坑1の先端部に位置させた上で、該ベルトコンベヤ1
5を周回させて掘削残土を本坑1に落として排出し、本
坑の残土処分と同時に処分する。このようにすれば、T
BM2による掘削作業は、後方の本坑1の作業に影響さ
れることなく、実施することができる。
After that, when the main pit excavation by the above-mentioned split rock is completed and the residual soil is to be disposed, that is, when the main pit 1 is slid out, the temporary-placement belt conveyor 15 is moved to the main pit side, and at the tip of the main pit 1. After being positioned, the belt conveyor 1
Circulate 5 and drop the excavated residual soil into the main pit 1 and discharge it, and dispose of it at the same time as the residual soil of the main pit. If you do this, T
The excavation work by the BM 2 can be performed without being affected by the work of the main shaft 1 at the rear.

【0047】(請求項7に相当する発明)一方、導坑3
の基端部すなわち入口付近は、上記割岩作業時に割岩さ
れた岩片が落下してくるため、その下は非常に危険であ
る。作業員、資材等は割岩作業以外の安全な時に出入り
することが可能であるが、電線、水道管、送風管などは
線状であるため、落下してくる岩片から保護する必要が
ある。
(Invention equivalent to claim 7) Meanwhile, the tunnel 3
At the base end of the rock, i.e., near the entrance, rock fragments broken during the above-mentioned rock breaking work fall down, and the area below it is extremely dangerous. Workers and materials can enter and leave at a safe time other than split rock work, but since electric wires, water pipes, blowers, etc. are linear, it is necessary to protect them from falling rock fragments.

【0048】図16および図17は導坑3を本坑1の予
定掘削断面の頂部に形成した場合を示す。本坑1と導坑
3との取り合い部分には、導坑基端部側から本坑先端部
側に延びる防護管25が設置されており、該防護管25
はガントリー式ジャンボ架台26を貫通して該架台26
の後方に突出せしめられている。このガントリー式ジャ
ンボ架台26は、割岩のための削岩機、割岩機等を装備
した装置であるが、詳細については後述することにす
る。上記防護管25には、電線27、水道管28、送風
管29等の長尺な線状部材が挿通されている。
16 and 17 show the case where the tunnel 3 is formed at the top of the planned excavation cross section of the main shaft 1. A protection pipe 25 extending from the base end side of the main shaft to the front end side of the main shaft is installed at an area where the main shaft 1 and the main shaft 3 are connected to each other.
Passes through the gantry type jumbo mount 26 and the mount 26
Is projected to the rear of. The gantry type jumbo mount 26 is a device equipped with a rock drilling machine, a rock breaking machine, etc. for rock breaking, but the details will be described later. A long linear member such as an electric wire 27, a water pipe 28, and a blower pipe 29 is inserted through the protective pipe 25.

【0049】これら線状部材は導坑3の先端部にあるT
BM2まで延びて、該TBM2に電力、水、清浄空気等
を供給するものであり、防護管25によって、割岩作業
の際に落下してくる岩片から保護されている。また、上
記防護管25には、上記線状部材の下方位置において残
土搬出ベルトコンベヤ16が導坑3の長手方向に移動自
在に挿通されており、該ベルトコンベヤ16の先端部は
導坑3内に突出せしめられ、基端部は上記ガントリー式
ジャンボ架台26の後方において本坑1内に突出せしめ
られている。さらに、上記防護管25内には、図示しな
い通路が形成されており、これによって導坑3への安全
な通行を可能にしている。
These linear members are T-shaped at the tip of the tunnel 3.
It extends to the BM2 and supplies electric power, water, clean air, etc. to the TBM2, and is protected by the protective pipe 25 from the rock fragments falling during the grooving work. In addition, a residual soil carrying-out belt conveyor 16 is movably inserted in the protective tube 25 at a position below the linear member so as to be movable in the longitudinal direction of the tunnel 3, and the tip end of the belt conveyor 16 is inside the tunnel 3. The base end portion is made to project into the main shaft 1 behind the gantry type jumbo frame 26. Further, a passage (not shown) is formed in the protection pipe 25, which enables safe passage to the tunnel 3.

【0050】上記構成においては、TBM2による掘削
残土を、例えば、上記トロッコ20等によって、残土搬
出ベルトコンベヤ16まで搬送すれば、本坑1の割岩作
業に影響されることなく、掘削残土を搬出しつつ導坑3
を掘進することができる。また、上記トロッコ20に代
えて、仮置きベルトコンベヤ15に掘削残土を仮置き
し、該仮置きベルトコンベヤ15を残土搬出ベルトコン
ベヤ16まで移動させることによって、残土排出を行っ
てもよい。この場合においても、本坑1の割岩作業に影
響されることなく残土排出を行うことができるので、仮
置きベルトコンベヤ15をかなり短くすることができ
る。
In the above structure, if the excavated residual soil by the TBM 2 is conveyed to the residual soil conveying belt conveyor 16 by the truck 20 or the like, the excavated residual soil is conveyed out without being affected by the rock breaking work of the main shaft 1. While digging 3
Can be dug. Further, in place of the truck 20, the excavated residual soil may be temporarily placed on the temporary placement belt conveyor 15 and the temporary placement belt conveyor 15 may be moved to the residual soil discharge belt conveyor 16 to discharge the residual soil. Even in this case, since the residual soil can be discharged without being affected by the rock breaking work of the main shaft 1, the temporary-placement belt conveyor 15 can be considerably shortened.

【0051】なお、上記防護管25は、導坑3の上下方
向の位置に関係なく、同様の構成にするが、防護管25
の設置高さによって岩片の落下による衝撃力が違うた
め、導坑3を下側に形成する程のその強度を高める必要
がある。
The protection tube 25 has the same structure regardless of the vertical position of the tunnel 3, but the protection tube 25
Since the impact force due to the falling of rock fragments differs depending on the installation height of the rock, it is necessary to increase the strength of the tunnel 3 so as to form it below.

【0052】(請求項8に相当する発明)図18は上記
のような防護管25を設置しなくても、上記電線27等
の線状部材を保護できる場合の例を示す。すなわち、導
坑3をその頂部が本坑1の頂部となるべき部位より上方
に位置するように掘削する。このようにすると、導坑3
の頂部と本坑1の頂部となるべき部位との2つの交差部
T1,T2間の壁面に割岩の必要がない部分ができる。
したがって、交差部T1,T2間にある空間Sは岩片が
落下してこない安全なエリアとなり、該空間Sに上記電
線27、水道管28、送風管29等の長尺な線状部材を
挿通すれば、防護管25を設置しなくても線状部材を保
護できる。
(Invention equivalent to claim 8) FIG. 18 shows an example in which the linear member such as the electric wire 27 can be protected without installing the protective tube 25 as described above. That is, the tunnel 3 is excavated so that the top of the tunnel 3 is located above the site to be the top of the main shaft 1. In this way, the tunnel 3
There is a part that does not require split rocks on the wall surface between the two intersections T1 and T2 of the top of the main shaft and the part to be the top of the main shaft 1.
Therefore, the space S between the intersections T1 and T2 is a safe area where rock fragments do not fall, and the long linear members such as the electric wire 27, the water pipe 28, and the blower pipe 29 are inserted into the space S. For example, the linear member can be protected without installing the protective tube 25.

【0053】(請求項9に相当する発明)次に、上記の
ように導坑3が本坑1の予定掘削断面内において、上部
にある場合の割岩の方法の例を説明する。すなわち、導
坑の基端部周壁面を割岩して岩片を落下させる方法で切
り拡げることができるのは、導坑3の底部までであり、
該底部より下方の部分の割岩後の岩片は、別の方法で地
山から取り外す必要がある。導坑3が上部にある場合に
は導坑3より下方の掘削断面が大きく、上記岩片の取り
外し作業が大変な作業になる。
(Invention Corresponding to Claim 9) Next, an example of a method of splitting rock when the tunnel 3 is located above in the planned excavation section of the main shaft 1 will be described. That is, it is only up to the bottom of the tunnel 3 that the rock can be spread by splitting the base wall of the tunnel at the base end and dropping the rock fragments.
The post-broken rock fragments below the bottom must be removed from the ground by another method. When the tunnel 3 is on the upper side, the excavation cross section below the tunnel 3 is large, and the work of removing the rock fragments becomes a difficult task.

【0054】したがって、これを解決するために、図1
9ないし図21に示すように、導坑3の基端部周壁面4
の底部から下方を削孔して割岩した後、該基端部周壁面
4を割岩する工程を繰り返し行って、導坑3の基端部周
壁面4を本坑1の大きさまで切り拡げるようにする。上
記基端部周壁面4の底部から下方を削孔・割岩する場
合、導坑3内に削孔用の削孔機31を設置し、この削孔
機31によって基端部周壁面4の底部から下方を削孔し
割岩する。なお、この削孔機31は本坑1の掘進のため
予め地山を補強(ロックボルトの設置や薬液注入による
地盤改良、他)するための機械と兼用することができる
ため、大きな費用増とはならない。
Therefore, in order to solve this, FIG.
As shown in FIGS. 9 to 21, the peripheral wall surface 4 of the base end portion of the tunnel 3
After drilling the lower part from the bottom of the base and splitting the rock, the process of splitting the base end peripheral wall surface 4 is repeated to cut and spread the base end peripheral wall surface 4 of the tunnel 3 to the size of the main shaft 1. To do. When drilling and splitting rocks from the bottom of the base end peripheral wall surface 4 below, a drilling machine 31 for drilling is installed in the tunnel 3 and the bottom part of the base end peripheral wall surface 4 is provided by the drilling machine 31. From below, a hole is drilled and rocks are split. Since this boring machine 31 can also be used as a machine for preliminarily strengthening the ground for excavating the main shaft 1 (installation of rock bolts, ground improvement by chemical injection, etc.), a large increase in cost will occur. Don't

【0055】ここで、上記削孔機31について図22お
よび図23を参照して説明する。該削孔機31は門型の
台車32と、この台車32に上下左右に揺動自在に連結
されたアーム33と、このアーム33の先端部に取り付
けられた削岩機34とを主体として構成されている。上
記台車32は、導坑3にこれを横断して設置された複数
の枕木35…に敷設された一対のレール36,36上
を、車輪37…を介して導坑3の長手方向に移動可能に
設けられている。台車32の上部中央には、回転軸39
がベアリング39aによって垂直軸回りに回転自在に設
けられている。この回転軸39の軸方向中央部にはギア
40が取り付けられており、このギア40にはモータ4
1aによって回転されるギア41が噛合されている。そ
して、上記回転軸39はモータ41aによってギア4
1,40を介して回転されるようになっている。
Here, the boring machine 31 will be described with reference to FIGS. 22 and 23. The boring machine 31 is mainly composed of a gantry-shaped bogie 32, an arm 33 connected to the bogie 32 so as to be vertically and horizontally swingable, and a rock drill 34 attached to a tip end of the arm 33. Has been done. The trolley 32 is movable in the longitudinal direction of the tunnel 3 via wheels 37 on a pair of rails 36, 36 laid on a plurality of sleepers 35 that are installed across the tunnel 3. It is provided in. At the center of the upper part of the dolly 32, the rotary shaft 39
Is rotatably provided around a vertical axis by a bearing 39a. A gear 40 is attached to the center of the rotary shaft 39 in the axial direction.
The gear 41 rotated by 1a is meshed. Then, the rotating shaft 39 is rotated by the motor 41a into the gear 4
It is designed to be rotated via 1, 40.

【0056】上記回転軸39の下端部には連結部42が
取り付けられており、この連結部42には、導坑3と本
坑1との取り合い部分に向けて延びるアーム33がピン
43によって上下に揺動自在に連結されている。また、
上記連結部42には、伸縮ジャッキ44が連結され、該
ジャッキ44のピストンロッド44aの先端部は上記ア
ーム33に連結されている。そして、このアーム33
は、伸縮ジャッキ44の伸縮によって、ピン43を軸と
して上下方向に揺動し、上記回転軸39の回転によって
左右方向に揺動するようになっている。
A connecting portion 42 is attached to the lower end of the rotary shaft 39, and an arm 33 extending toward the connecting portion between the guide shaft 3 and the main shaft 1 is vertically moved by a pin 43 to the connecting portion 42. Is swingably connected to. Also,
A telescopic jack 44 is connected to the connecting portion 42, and a tip end portion of a piston rod 44 a of the jack 44 is connected to the arm 33. And this arm 33
Is configured to swing vertically with the pin 43 as an axis by the extension and contraction of the extension jack 44, and to swing left and right with the rotation of the rotary shaft 39.

【0057】上記アーム33の先端部には、該アーム3
3の延長上に支持ロッド33aがスイベルジョイント3
3bを介して軸回りに回転自在に連結されており、図示
しない駆動手段によって回転されるようになっている。
この支持ロッド33aの先端部には上記削岩機34が取
り付けられている。この削岩機34は、支持ロッド33
aに固定された削岩機本体34aと、この削岩機本体3
4aに垂直に上下動可能に支持された保持ロッド34b
と、この保持ロッド34bにその下端部から突出して上
下動可能にかつ回転可能に支持された削岩ロッド34c
とを主体として構成されており、削岩ロッド34cを回
転させつつ降下させることによってその先端部に設けら
れた切刃34dで岩盤等を削孔するようになっている。
なお、符号34eは上述した構成の削孔機31を操作す
るための操作盤である。
At the tip of the arm 33, the arm 3
When the support rod 33a is extended from the swivel joint 3
It is rotatably connected about an axis via 3b and is rotated by a driving means (not shown).
The rock drill 34 is attached to the tip of the support rod 33a. This rock drill 34 has a support rod 33
The rock drill body 34a fixed to a and the rock drill body 3
A holding rod 34b which is vertically supported by 4a and is vertically movable.
And a rock drilling rod 34c which is supported by the holding rod 34b so as to project from the lower end portion thereof so as to be vertically movable and rotatable.
The rock cutting rod 34c is rotated and lowered to cut a rock or the like with a cutting edge 34d provided at the tip of the rock cutting rod 34c.
Reference numeral 34e is an operation panel for operating the hole drilling machine 31 having the above-described configuration.

【0058】さて、上記削孔機31によって導坑3の基
端部周壁面4の底部から下方を削孔・割岩するには、ま
ず台車32を導坑3の基端部近傍まで移動させて所定の
位置で停止させる。次いで、アーム33を上下左右に揺
動させて削孔の位置を決定し、その後、保持ロッド34
bを垂直に降下させて基端部周壁面4の底部より若干上
方で停止させる。次いで、削岩ロッド34cを回転させ
つつ徐々に降下させることによって基端部周壁面4の底
部から下方を本坑1の掘削底面まで削孔する。一つの孔
Kの削孔が終わったら、削岩ロッド34cを上昇させて
孔Kから引き抜き、上記と同様の工程を経て次の孔Kの
削孔を行う。そして、図21に示すように、導坑3の先
端側(奥側)の方が小さくなる台形状または三角形状に
なるように4つの孔K…の削孔が終わったら、これら孔
K…を利用して割岩を行う。このようにすると、割岩さ
れた岩片Gが本坑側に向けて広がる断面台形状の柱体に
なるので、該岩片Gは矢印方向に容易に倒れ、本坑1に
取り出される。
In order to drill and lower rocks from the bottom of the peripheral wall surface 4 of the base end portion of the tunnel 3 by the boring machine 31, first, the bogie 32 is moved to the vicinity of the base end portion of the tunnel 3. Stop it in place. Then, the arm 33 is swung vertically and horizontally to determine the position of the drilled hole, and then the holding rod 34
b is vertically lowered and stopped slightly above the bottom of the peripheral wall 4 of the base end. Next, the rock drilling rod 34c is rotated and gradually lowered to drill a hole from the bottom of the base end peripheral wall 4 to the excavated bottom surface of the main shaft 1. When the drilling of one hole K is completed, the rock drilling rod 34c is lifted and pulled out from the hole K, and the drilling of the next hole K is performed through the same steps as above. Then, as shown in FIG. 21, when the drilling of the four holes K is finished so that the tip side (back side) of the guide shaft 3 becomes smaller, the holes K ... Use it to split rocks. In this way, the broken rock fragments G become columnar bodies having a trapezoidal cross section that spreads toward the main shaft side, so that the rock fragments G easily fall in the direction of the arrow and are taken out to the main shaft 1.

【0059】岩片Gが除去されると、本坑1の中央部
に、導坑3の底部から下方に延びる開口部Aが形成され
るので、この開口部Aに岩片が落下するように、導坑3
の基端部周壁面4を割岩して、基端部周壁面4を本坑1
の大きさまで切り拡げる。具体的には、例えば、図24
に示すように、開口部Aの上端部と導坑3とが交差する
位置の壁面を割岩して、岩片G1,G1を開口部Aに落
下させ、次いで、岩片G1に対して下方および導坑3の
周方向にそれぞれ隣接する壁面を割岩して岩片G2,G
2を開口部Aに落下させ、さらに順次、下方および導坑
3の周方向に隣接する壁面を割岩して岩片を落下させる
工程を繰り返して導坑3と開口部Aを所定量切り拡げ
る。
When the rock fragments G are removed, an opening A extending downward from the bottom of the tunnel 3 is formed in the central portion of the main pit 1 so that the rock fragments fall into the opening A. Pit 3
The base end peripheral wall surface 4 of the main shaft 1
Cut to the size of. Specifically, for example, FIG.
As shown in FIG. 3, the wall surface at the position where the upper end of the opening A and the tunnel 3 intersect is split, and the rock fragments G1 and G1 are dropped into the opening A, and then below and below the rock fragment G1. Rock pieces G2, G formed by dividing the wall surfaces adjacent to each other in the circumferential direction of 3
2 is dropped into the opening portion A, and the steps of dropping the rock fragments by breaking down the wall surface adjacent to the lower side and the circumferential direction of the guiding tunnel 3 in sequence are repeated to expand the guiding hole 3 and the opening portion A by a predetermined amount.

【0060】そして、この割岩による切り拡げを順次外
側に施していくことによって、導坑3の基端部周壁面4
を本坑1の大きさまで切り拡げる。上記のようにして割
岩することによって、導坑3が上部にある場合において
も、割岩された岩片を容易に排出して、切り拡げを行う
ことができる。
Then, by sequentially cutting and spreading the slabs outward, the peripheral wall surface 4 of the base end portion of the tunnel 3 is cut.
Cut to the size of main pit 1. By splitting rocks as described above, even when the tunnel 3 is located above, the split rock fragments can be easily discharged and cut and expanded.

【0061】(請求項10に相当する発明)また、導坑
3が上部にある場合、上述した方法の他に、以下に示す
ような割岩の方法もある。すなわち、導坑3を割岩によ
って切り拡げるに際し、まず、図25に示すように、基
端部周壁面4の底部より上方の壁面を割岩して切り拡げ
つつ掘進して本坑1の上半分1aを掘削し、その後、掘
削し残した本坑1の下半分1bを、ガントリー式ジャン
ボ架台26の後方位置において、割岩掘削する。
(Invention Corresponding to Claim 10) When the tunnel 3 is located at the upper part, there is a split rock method as described below in addition to the above method. That is, when the guide shaft 3 is cut and expanded by the split rock, as shown in FIG. 25, first, as shown in FIG. 25, the wall surface above the bottom portion of the base end peripheral wall surface 4 is split and cut and expanded to advance the upper half 1a of the main shaft 1. After that, the lower half 1b of the main pit 1 left after the excavation is split rock excavated at a position behind the gantry type jumbo mount 26.

【0062】本坑1の上半分1aを掘削する場合、図2
7に示すように、上述した割岩の場合と同様にして、ま
ず、導坑3の基端部周壁面4の天端付近4aを、上部に
向かうにしたがって漸次幅狭になるようにして削孔して
割岩し、次々に隣接する部分を、順次周方向に沿って基
端部周壁面4の底部まで削孔して孔K1を形成して割岩
し、この工程を順次外側に拡げていくことによって行
う。
In case of excavating the upper half 1a of the main shaft 1, as shown in FIG.
As shown in FIG. 7, first, in the same manner as in the case of the above-mentioned split rock, first, the vicinity of the top end 4a of the peripheral wall surface 4 of the base end part of the tunnel 3 is drilled so that the width becomes gradually narrower toward the upper part. And then divide the adjacent parts one after another to the bottom of the base end peripheral wall surface 4 along the circumferential direction to form a hole K1 to divide the rock, and to sequentially expand this process to the outside. Done by.

【0063】この割岩作業の際には主に水平方向に削孔
を行うが、この削孔は上記ガントリー式ジャンボ架台2
6によって行う。ここで、このガントリー式ジャンボ架
台26の構成について説明する。すなわち図29および
図30に示すように、フレーム45の下部には車輪46
…が取り付けられており、これら車輪46…が本坑1の
上半分1aの底面に敷設されたレール47,47上を転
動することによって、フレーム45が前後に移動可能に
なっている。また、車輪46の両側にはストッパジャッ
キ48,48が設けられており、該ジャッキ48,48
のピストンロッド48a,48aを伸張してその先端部
に固定されたストッパ49,49を本坑1の上半分1a
の底面に押しつけることによってフレーム45の移動を
ロックするようになっている。
During this grooving work, a hole is mainly drilled in the horizontal direction, and this hole is made by the gantry type jumbo mount 2 described above.
6. Here, the configuration of the gantry type jumbo frame 26 will be described. That is, as shown in FIGS. 29 and 30, wheels 46 are provided on the lower portion of the frame 45.
... are mounted, and the wheels 45 roll on rails 47, 47 laid on the bottom surface of the upper half 1a of the main shaft 1, whereby the frame 45 can be moved back and forth. Further, stopper jacks 48, 48 are provided on both sides of the wheel 46, and the jacks 48, 48 are provided.
The piston rods 48a, 48a of the above are extended and stoppers 49, 49 fixed to the tip end thereof are provided on the upper half 1a of the main shaft 1.
The movement of the frame 45 is locked by pressing it on the bottom surface of the frame.

【0064】さらに、上記フレーム45には、複数の削
孔機50…が導坑3側に向けて取り付けられている。該
削孔機50…は、フレーム45の上段に3機、中段に4
機、下段に4機設けられており、各段に設けられた削孔
機50…はそれぞれ水平方向に平行に設置されている。
なお、削孔機50の台数はこれに限ることなく、トンネ
ル掘削の条件に応じて適宜設定される。上記削孔機50
について説明すると、フレーム45には支持ブロック5
1が横フレーム45aに沿って(図29において紙面と
直交する方向に)移動可能に設けられており、この支持
ブロック51には、伸縮ジャッキ52の一端部が回動自
在に連結されている。また、この伸縮ジャッキ52の中
途部にはジャッキ53の一端部が連結され、他端部は上
記支持ブロック50に連結されている。そして、伸縮ジ
ャッキ52は、ジャッキ53の伸縮によってその一端部
を支点として上下に揺動するようになっている。
Further, a plurality of boring machines 50 ... Are attached to the frame 45 toward the guide shaft 3 side. The drilling machines 50 ... are three in the upper stage of the frame 45 and four in the middle stage.
4 machines are provided in the lower stage, and the drilling machines 50 ... Provided in each stage are installed in parallel in the horizontal direction.
Note that the number of the boring machines 50 is not limited to this, and may be appropriately set according to the conditions for tunnel excavation. The boring machine 50
The support block 5 is attached to the frame 45.
1 is provided so as to be movable along the horizontal frame 45a (in the direction orthogonal to the paper surface in FIG. 29), and one end of an expansion jack 52 is rotatably connected to the support block 51. Further, one end of the jack 53 is connected to a midway portion of the telescopic jack 52, and the other end is connected to the support block 50. The expandable / contractible jack 52 swings up and down with the one end of the jack 53 as a fulcrum due to expansion and contraction of the jack 53.

【0065】上記伸縮ジャッキ52の他端部には、水平
ロッド54が取り付けられており、この水平ロッド54
の先端部には、支持部材55が回動可能に連結されてい
る。この支持部材55には、スライド部材56が図29
において左右方向にスライド自在に設けられている。こ
のスライド部材56には、削孔機本体57がスライド部
材56の長手方向に往復動可能に設けられている。削孔
機本体57の先端部には削孔ロッド58が軸回りに回転
可能に取り付けられ、該削孔ロッド58はスライド部材
56に固定された支持部59…によって摺動自在に支持
されている。
A horizontal rod 54 is attached to the other end of the telescopic jack 52.
A support member 55 is rotatably connected to the tip of the. A slide member 56 is attached to the support member 55 as shown in FIG.
Is provided so as to be slidable in the left-right direction. The slide member 56 is provided with a boring machine body 57 so as to be reciprocally movable in the longitudinal direction of the slide member 56. A boring rod 58 is rotatably attached to the tip of the boring machine body 57 about an axis, and the boring rod 58 is slidably supported by a support portion 59 fixed to a slide member 56. .

【0066】そして、上記構成のガントリー式ジャンボ
架台26では、フレーム45を前進させて所定の位置で
停止ロックした後、削孔機50…によって導坑3の基端
部周壁面4の底部より上方の壁面を削孔するようになっ
ている。この場合、支持ブロック51を移動させて水平
方向における削孔位置を決定した後、伸縮ジャッキ52
を伸張して、削孔ロッド58の先端部を壁面に近付け、
ジャッキ53によって伸縮ジャッキ52を回動させて垂
直方向における削孔位置を決定する。その後、削孔ロッ
ド58を回転させつつ削孔機本体57を前進させ、これ
によって削孔を行う。また、割岩を行い易くするため
に、壁面に垂直に削孔を施す場合、支持部材55を回転
させて、図29に二点鎖線で示すように、削孔ロッド5
8を垂直に向けて行う。
In the gantry type jumbo frame 26 having the above-mentioned structure, the frame 45 is moved forward and stopped and locked at a predetermined position, and then the hole drilling machine 50 ... It is designed to drill the wall surface of. In this case, after moving the support block 51 to determine the horizontal drilling position, the telescopic jack 52
To extend the tip of the drilling rod 58 close to the wall surface,
The telescopic jack 52 is rotated by the jack 53 to determine the drilling position in the vertical direction. After that, the boring machine main body 57 is moved forward while rotating the boring rod 58, thereby carrying out boring. Further, in order to facilitate the split rock formation, when the wall surface is drilled vertically, the support member 55 is rotated to move the drilled rod 5 as shown by the chain double-dashed line in FIG.
8 is directed vertically.

【0067】上記のようにして、本坑1の上半分1aの
掘削がある程度進行した後、図25および図28に示す
ように、ガントリー式ジャンボ架台26の後方で割岩作
業を行う。この場合、本坑1の下半分1bを縦方向(垂
直方向)に削孔して縦孔K2を形成し、割岩を行う。こ
の削孔では、例えば、上記削孔機31を使用して行えば
よく、その割岩方法も削孔機31を使用した場合と同様
にして行えば、容易に削孔・割岩を行うことができる。
なお、上半分1aの外周側には水平に横孔K1を形成し
て、割岩を行う。
After excavating the upper half 1a of the main pit 1 to some extent as described above, as shown in FIGS. 25 and 28, a split rock operation is performed behind the gantry type jumbo mount 26. In this case, the lower half 1b of the main pit 1 is drilled in the vertical direction (vertical direction) to form the vertical hole K2, and split rock is performed. In this drilling, for example, the drilling machine 31 may be used, and if the rock breaking method is the same as when the drilling machine 31 is used, drilling and rock breaking can be easily performed. .
A horizontal hole K1 is horizontally formed on the outer peripheral side of the upper half 1a to divide the rock.

【0068】(請求項11に相当する発明)また、上記
のように本坑1の上半分1aと下半分1bを分けて掘削
する場合、図25および図26に示すように、上半分が
掘削された本坑1と導坑3との取り合い部分、すなわち
上半分1aの削孔・割岩が行われる部分に、導坑基端部
側から本坑側に延びる上記防護管25を設置し、この防
護管25に電線、水道管、送風管等の長尺な線状部材を
挿通するとともに、残土搬出ベルトコンベヤ60を挿通
する。そして、このベルトコンベヤ60の先端部に上記
仮置きベルトコンベヤ16を接続して、レール22上を
移動するトロッコ(図示略)によって、TBM2による
掘削残土を仮置きベルトコンベヤ16に仮置きし、該ベ
ルトコンベヤ16から残土搬出ベルトコンベヤ60を介
して上記掘削残土をガントリー式ジャンボ架台26の後
方に搬出すれば、導坑3の掘削と本坑1の掘削を同時進
行できる。
(Invention equivalent to claim 11) When the upper half 1a and the lower half 1b of the main shaft 1 are separately excavated as described above, the upper half is excavated as shown in FIGS. 25 and 26. The protection pipe 25 extending from the base end side of the main shaft to the main shaft side is installed in the part where the main shaft 1 and the main shaft 3 are connected, that is, in the part where the upper half 1a is drilled / broken. A long linear member such as an electric wire, a water pipe, a blower pipe, or the like is inserted into the protective pipe 25, and a remaining soil unloading belt conveyor 60 is inserted. Then, the temporary placement belt conveyor 16 is connected to the tip end of the belt conveyor 60, and the excavated soil by the TBM 2 is temporarily placed on the temporary placement belt conveyor 16 by a truck (not shown) that moves on the rail 22. If the excavation residual soil is transported to the rear of the gantry type jumbo mount 26 from the belt conveyor 16 via the residual soil unloading belt conveyor 60, the excavation of the guide shaft 3 and the excavation of the main shaft 1 can proceed simultaneously.

【0069】なお、残土搬出ベルトコンベヤ60によっ
て搬出された掘削残土は、本坑1の下半分1bの掘削に
よってでる岩片と一緒にすればよい。また、上記残土搬
出ベルトコンベヤ60と仮置きベルトコンベヤ16を一
体的に形成してもよい。
The excavated residual soil carried out by the residual soil carrying-out belt conveyor 60 may be combined with the rock fragments produced by the excavation of the lower half 1b of the main pit 1. Further, the remaining soil carrying-out belt conveyor 60 and the temporary placement belt conveyor 16 may be integrally formed.

【0070】[0070]

【発明の効果】以上説明したように、この発明の請求項
1トンネルの掘削工法によれば、本坑の予定掘削断面内
に、円形全断面掘削機工法によって導坑を掘削し、この
導坑の基端部周壁面を割岩して該導坑の基端部周壁面を
本坑の大きさまで切り拡げつつ導坑と本坑とを同時掘進
するようにしたので、発破を用いることなく安全かつ連
続的にトンネルを掘削することができ、工期の短縮を図
ることができる。また発破を用いないので、機器類の退
避や入れ替えの必要がなく、よって機械を大型化するこ
とが可能になり、掘削作業の効率化を図ることができ
る。さらに、発破による後ガス、粉塵等の問題もなく、
工事の全体的なシステムの自動化を図って、トンネル掘
削に要するコストを低減することができる。
As described above, according to the method for excavating a tunnel of claim 1 of the present invention, a tunnel is excavated in the planned excavation section of the main pit by the circular full-section excavator method, and the tunnel is constructed. Since the base end peripheral wall surface of No. 1 was split and the base end peripheral wall surface of the tunnel was expanded to the size of the main shaft, the guide shaft and the main shaft were simultaneously excavated, so it was safe and without blasting. The tunnel can be continuously excavated, and the construction period can be shortened. Further, since blasting is not used, it is not necessary to evacuate or replace the equipment, so that the machine can be upsized and the excavation work can be made more efficient. Furthermore, there is no problem of post gas, dust, etc. due to blasting,
The cost of tunnel excavation can be reduced by automating the entire construction system.

【0071】請求項2のトンネル掘削工法によれば、導
坑の基端部周壁面を割岩するに際し、まず該基端部周壁
面天端付近を、上部に向かうにしたがって漸次幅狭にな
るように削孔して割岩するようにしたので、この割岩
後、岩片を支えるものがなくなって、該岩片が自重によ
って落下し、岩片が欠落した部分は自由面となり、その
後、基端部周壁面を、上記自由面から順次周方向に沿っ
て基端部周壁面底部まで割岩していくようにしたので、
岩片は順次落下することになり、よって全体を割岩によ
って容易に掘削することができる。
According to the tunnel excavation method of claim 2, when the base end peripheral wall surface of the tunnel is split, first, the vicinity of the base end peripheral wall wall top is gradually narrowed toward the upper part. Since the rock was made by drilling into the rock, there was no support for the rock fragment after this rock break, the rock fragment fell by its own weight, the part where the rock fragment was missing became a free surface, and then the peripheral wall of the base end , From the above free surface, we split the rock along the circumferential direction to the bottom of the peripheral wall surface,
The rock fragments will fall one after another, so that the whole can be easily excavated by the split rock.

【0072】請求項3のトンネル掘削工法によれば、請
求項2の掘削を行う際に、導坑の基端部周壁面を削孔す
るに際し、各孔に、割岩の際に生じさせるべき亀裂の方
向に延びるスリット状のノッチを形成するようにしたの
で、割岩の際にこのノッチに応力集中が起こり、該ノッ
チから延びるようにして亀裂が入るので、割岩を所望の
方向に容易かつ確実に行うことができる。
According to the tunnel excavation method of claim 3, when the excavation of claim 2 is performed, when the peripheral wall surface of the base end portion of the tunnel is drilled, cracks to be produced in each hole at the time of split rock Since a slit-shaped notch extending in the direction of is formed, stress concentration occurs in this notch during splitting and cracks extend from the notch, so the splitting rock can be easily and reliably placed in the desired direction. It can be carried out.

【0073】請求項4のトンネル掘削工法によれば、請
求項1から3のいずれかの掘削を行う際に、導坑内に、
該導坑の先端部近傍から本坑側に向けて延びる仮置きベ
ルトコンベヤを設けるとともに、この仮置きベルトコン
ベヤの基端部から本坑の先端部まで延びる残土搬出ベル
トコンベヤを設け、導坑を掘削した際の掘削残土を上記
仮置きベルトコンベヤに仮置きし、その後、本坑掘削の
作業に支障が出ない時期に、上記両ベルトコンベヤを周
回して上記掘削残土を上記本坑に排出するようにしたの
で、導坑の掘削作業を、本坑の掘削作業に影響されるこ
となく行うことができ、よってトンネル掘進の効率化を
図ることができる。
According to the tunnel excavation method of claim 4, when the excavation according to any one of claims 1 to 3 is carried out,
A temporary placing belt conveyor extending from the vicinity of the leading end of the tunnel to the main pit side is provided, and a residual soil unloading belt conveyor extending from the base end of the temporary placing belt conveyor to the tip of the main pit is provided. The excavated soil after excavation is temporarily placed on the temporary conveyor belt conveyor, and then, when there is no hindrance to the operation of the main shaft excavation, the belt conveyor is circulated to discharge the residual excavated soil to the main shaft. As a result, the tunnel excavation work can be performed without being affected by the main shaft excavation work, and the tunnel excavation efficiency can be improved.

【0074】請求項5のトンネル掘削工法によれば、請
求項4の掘削を行う際に、仮置きベルトコンベヤおよび
残土排出ベルトコンベヤをそれぞれ、導坑の長手方向に
移動可能に設けたので、導坑3および本坑1の掘進に伴
って容易に両ベルトコンベヤを前進させて、掘削残土の
排出を容易かつ連続的に行うことができる。また、割岩
作業の際には、残土排出コンベアを仮置きベルトコンベ
ヤ側に移動させて退避することによって、割岩作業を支
障なく確実に行うことができる。
According to the tunnel excavation method of claim 5, when the excavation of claim 4 is performed, the temporary placement belt conveyor and the residual soil discharging belt conveyor are provided so as to be movable in the longitudinal direction of the tunnel. Both belt conveyors can be easily advanced along with the digging of the mine 3 and the main pit 1, and the excavated soil can be discharged easily and continuously. Further, at the time of rock breaking work, the rock breaking work can be surely performed without trouble by moving the residual soil discharging conveyor to the temporary placing belt conveyor side and retracting it.

【0075】請求項6のトンネル掘削工法によれば、請
求項1から3のいずれかの掘削を行う際に、導坑内に、
該導坑の長手方向に沿って延びかつ該長手方向に沿って
移動可能な仮置きベルトコンベヤを設け、この仮置きベ
ルトコンベヤの上方位置に、導坑を掘削した際の掘削残
土を導坑先端部から仮置きベルトコンベヤまで搬送する
トロッコを導坑の長手方向に沿って移動可能に設け、本
坑掘削の作業に支障が出ない時期に、掘削残土が仮置き
された仮置きベルトコンベヤを本坑まで移動させて、周
回させることによって、上記掘削残土を上記本坑に排出
するようにしたので、導坑の掘削作業を、本坑の掘削作
業に影響されることなく行うことができ、よってトンネ
ル掘進の効率化を図ることができる。
According to the tunnel excavation method of claim 6, when the excavation according to any one of claims 1 to 3 is carried out,
A temporary placement belt conveyor that extends along the longitudinal direction of the tunnel and is movable along the longitudinal direction is provided, and the excavated residual soil when the tunnel is excavated is located above the temporary placement belt conveyor. A trolley that conveys from the section to the temporary placement belt conveyor is provided so that it can move along the longitudinal direction of the tunnel, and the temporary placement belt conveyor with the remaining excavated soil is temporarily placed at the time when there is no hindrance to the work of the main pit. Since the excavated residual soil is discharged to the main pit by moving to the pit and circulating, it is possible to perform the digging work of the guide shaft without being affected by the digging work of the main pit. The efficiency of tunnel excavation can be improved.

【0076】請求項7のトンネル掘削工法によれば、請
求項1から3のいずれかの掘削を行う際に、本坑と導坑
との取り合い部分に、導坑基端部側から本坑先端部側に
延びる防護管を設置し、この防護管に電線、水道管、送
風管等の長尺な線状部材および残土排出ベルトコンベヤ
を挿通したので、割岩されて落下してくる岩片から線状
部材を保護することができるとともに、防護管の内部を
通路にすることによって安全な通行が可能になる。ま
た、導坑掘削によって出る掘削残土を、割岩作業に関係
なく搬出することができるので、掘削作業の効率化を図
ることができる。
According to the tunnel excavation method of claim 7, when the excavation according to any one of claims 1 to 3 is carried out, the main shaft tip end from the main shaft end side is provided at the mating portion of the main shaft and the main shaft. Since a protective pipe extending to the side of the section was installed, and long linear members such as electric wires, water pipes, and blast pipes and a residual soil discharge belt conveyor were inserted into this protective pipe, it is linear from the rock fragments that are broken and fall. The member can be protected, and the passage inside the protective tube enables safe passage. Moreover, since the excavated soil left from the tunnel excavation can be carried out regardless of the rock breaking work, the efficiency of the excavation work can be improved.

【0077】請求項8のトンネル掘削工法によれば、請
求項1の掘削を行う際に、導坑をその頂部が本坑の頂部
となるべき部位より上方に位置するように掘削したの
で、導坑の頂部と本坑の頂部となるべき部位との2つの
交差部間にある空間は岩片が落下してこない安全なエリ
アとなる。したがって、この空間に電線、水道管、送風
管等の長尺な線状部材を挿通することによって、防護管
を設置しなくても線状部材を保護することができる。
According to the tunnel excavation method of claim 8, when the excavation of claim 1 is performed, the guide pit is excavated so that the top of the guide pit is located above the site to be the top of the main pit. The space between the two intersections of the top of the mine and the site that should be the top of the main mine is a safe area where rock fragments do not fall. Therefore, by inserting a long linear member such as an electric wire, a water pipe, or a blower pipe into this space, the linear member can be protected without installing a protective pipe.

【0078】請求項9のトンネル掘削工法によれば、請
求項1の掘削を行う際に、導坑の基端部周壁面の底部か
ら下方を削孔して割岩した後、上記基端部周壁面を割岩
する工程を繰り返し行うようにしたので、割岩された岩
片を、基端部周壁面の底部から下方を削孔・割岩して形
成された開口部から落下させて排出することができる。
したがって、本坑の予定掘削断面内における上部に導坑
を掘削した場合、すなわち導坑より下方の掘削断面が大
きい場合においても、導坑の基端部周壁面を本坑の大き
さまで容易に切り拡げることができる。
According to the tunnel excavation method of claim 9, when the excavation of claim 1 is carried out, the lower part of the peripheral wall surface of the base end portion of the tunnel is drilled downward to divide the rock, and then the base end periphery is drilled. Since the step of splitting the wall surface is repeated, the split rock fragments can be discharged by dropping from the bottom of the peripheral wall surface of the base end to the opening formed by drilling and splitting rock.
Therefore, even if the tunnel is excavated in the upper part of the planned excavation section of the main shaft, that is, even if the excavation section below the tunnel is large, the peripheral wall of the base end of the tunnel is easily cut to the size of the main shaft. Can be expanded.

【0079】請求項10のトンネル掘削工法によれば、
請求項1の掘削を行う際に、導坑の基端部周壁面を割岩
して、該基端部周壁面の底部より上方を切り拡げつつ掘
進して本坑の上半分を掘削し、その後、本坑の下半分を
縦方向に割岩する、すなわち割岩作業を分割して行うよ
うにしたので、本坑の予定掘削断面内における上部に導
坑を掘削して、導坑より下方の掘削断面が大きい場合に
おいても、導坑の基端部周壁面を本坑の大きさまで容易
に切り拡げることができる。
According to the tunnel excavation method of claim 10,
When the excavation according to claim 1 is performed, the peripheral wall surface of the base end part of the tunnel is split, and the upper half of the main shaft is excavated by cutting and expanding above the bottom part of the peripheral wall surface of the base end, and thereafter. Since the lower half of the main shaft is split in the vertical direction, that is, the split rock work is divided, the tunnel is excavated in the upper part of the planned excavation section of the main tunnel, and the excavation section below the tunnel is excavated. Even in the case of large diameter, the peripheral wall surface of the base end portion of the tunnel can be easily cut to the size of the main tunnel.

【0080】請求項11のトンネル掘削工法によれば、
請求項9の掘削を行う際に、上半分が掘削された本坑と
導坑との取り合い部分に、導坑基端部側から本坑側に延
びる防護管を設置し、この防護管に電線、水道管、送風
管等の長尺な線状部材および残土排出ベルトコンベヤを
挿通したので、本坑の上半分を割岩して落下してくる岩
片から線状部材を保護することができるとともに、防護
管の内部を通路にすることによって安全な通行が可能に
なる。また、導坑掘削によってでる掘削残土を、割岩作
業に関係なく搬出することができ、しかも、この掘削残
土を本坑の下半分の割岩によってでる岩片と一緒に処理
することができるので、掘削作業の効率化を図ることが
できる。
According to the tunnel excavation method of claim 11,
When the excavation according to claim 9 is performed, a protective pipe extending from the base end side of the main shaft to the main shaft is installed at an area where the main shaft where the upper half has been excavated and the main shaft is connected, and an electric wire is provided in this protective pipe. Since long linear members such as water pipes and blast pipes and the residual soil discharge belt conveyor are inserted, the upper members of the main shaft can be split and protected from falling rock fragments. Safe passage is possible by using the passage inside the protective tube. In addition, the excavated residual soil produced by the tunnel excavation can be carried out regardless of the split rock work, and this excavated residual soil can be processed together with the rock fragments produced by the split rock in the lower half of the main shaft. The efficiency of can be improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のトンネル掘削工法の実施例を説明する
ためのもので、導坑と本坑を示す側断面図である。
FIG. 1 is a side sectional view showing a tunnel and a main shaft for explaining an embodiment of a tunnel excavation method of the present invention.

【図2】図1におけるAーA線視断面図である。FIG. 2 is a sectional view taken along the line AA in FIG.

【図3】本発明のトンネル掘削工法における割岩方法を
示す横断面図である。
FIG. 3 is a cross-sectional view showing a split rock method in the tunnel excavation method of the present invention.

【図4】図3における割岩の最終状態の要部を示す横断
面図である。
FIG. 4 is a transverse cross-sectional view showing an essential part of the split rock in FIG. 3 in a final state.

【図5】本発明のトンネル掘削工法において、導坑の位
置が最上部にあるものを示す側断面図である。
FIG. 5 is a side sectional view showing a tunnel excavation method of the present invention in which a guide shaft is located at an uppermost position.

【図6】図5におけるBーB線視断面図である。6 is a sectional view taken along line BB in FIG.

【図7】本発明のトンネル掘削工法において、導坑の位
置が中央部にあるものを示す側断面図である。
FIG. 7 is a side sectional view showing the tunnel excavation method of the present invention in which the position of the tunnel is at the center.

【図8】図7におけるCーC線視断面図である。8 is a sectional view taken along line CC in FIG.

【図9】本発明のトンネル掘削工法において、導坑の位
置が最下部にあるものを示す側断面図である。
FIG. 9 is a side sectional view showing the tunnel excavation method of the present invention in which the position of the tunnel is at the bottom.

【図10】図9におけるDーD線視断面図である。10 is a cross-sectional view taken along the line DD in FIG.

【図11】本発明のトンネル掘削工法において、導坑の
掘削残土の排出方法を示す側断面図である。
FIG. 11 is a side sectional view showing a method for discharging the excavation residual soil in the tunnel in the tunnel excavation method of the present invention.

【図12】図11におけるEーE線視断面図である。12 is a sectional view taken along line EE in FIG.

【図13】本発明のトンネル掘削工法において、導坑の
掘削残土の排出方法の他のを示す側断面図である。
FIG. 13 is a side cross-sectional view showing another method for discharging the excavation residual soil in the tunnel in the tunnel excavation method of the present invention.

【図14】図13におけるFーF線視断面図である。FIG. 14 is a sectional view taken along line FF in FIG.

【図15】本発明のトンネル掘削工法において、導坑の
掘削残土を排出している状態を示す側断面図である。
FIG. 15 is a side cross-sectional view showing a state in which the excavated soil in the tunnel is being discharged in the tunnel excavation method of the present invention.

【図16】本発明のトンネル掘削工法において、防護管
を設置した状態を示す側断面図である。
FIG. 16 is a side sectional view showing a state in which a protective pipe is installed in the tunnel excavation method of the present invention.

【図17】図16におけるGーG線視断面図である。17 is a sectional view taken along the line GG in FIG.

【図18】本発明のトンネル掘削工法において、導坑を
その頂部が本坑の頂部より上方に位置するように掘削し
た状態を示す横断面図である。
FIG. 18 is a transverse cross-sectional view showing a state in which a tunnel has been excavated in the tunnel excavation method of the present invention such that its top is located above the top of the main shaft.

【図19】本発明のトンネル掘削工法において、導坑の
底部より下方を割岩する方法を示す側断面図である。
FIG. 19 is a side sectional view showing a method of splitting rock below the bottom of the tunnel in the tunnel excavation method of the present invention.

【図20】図19におけるHーH線視断面図である。20 is a sectional view taken along line HH in FIG.

【図21】図20におけるIーI線視断面図である。21 is a cross-sectional view taken along the line II of FIG.

【図22】本発明のトンネル掘削工法における削孔機を
示す側面図である。
FIG. 22 is a side view showing a hole drilling machine in the tunnel excavation method of the present invention.

【図23】図22におけるJーJ線視断面図である。23 is a sectional view taken along line JJ in FIG.

【図24】本発明のトンネル掘削工法において、割岩方
法を示す横断面図である。
FIG. 24 is a cross-sectional view showing a split rock method in the tunnel excavation method of the present invention.

【図25】本発明のトンネル掘削工法において、本坑を
上下2回に分割して切り拡げる方法を示す側断面図であ
る。
FIG. 25 is a side sectional view showing a method of dividing the main shaft into upper and lower parts by dividing the main shaft into two parts in the tunnel excavation method of the present invention.

【図26】図25におけるKーK線視断面図である。26 is a sectional view taken along line KK in FIG.

【図27】図25におけるLーL線視断面図である。27 is a sectional view taken along line LL in FIG. 25.

【図28】図25におけるMーM線視断面図である。28 is a sectional view taken along line MM in FIG. 25.

【図29】本発明のトンネル掘削工法において使用する
ガントリー式ジャンボ架台を示す側面図である。
FIG. 29 is a side view showing a gantry type jumbo mount used in the tunnel excavation method of the present invention.

【図30】図29におけるNーN線視断面図である。FIG. 30 is a sectional view taken along line NN in FIG. 29.

【図31】削孔された孔に油圧式割岩機を挿入した状態
を示す横断面図である。
FIG. 31 is a transverse cross-sectional view showing a state where a hydraulic rock breaking machine is inserted into the drilled hole.

【図32】削孔された孔を油圧式割岩機によって拡径し
て割岩している状態を示す横断面図である。
FIG. 32 is a transverse cross-sectional view showing a state where the drilled hole is expanded and divided by a hydraulic type rock breaking machine.

【符号の説明】[Explanation of symbols]

1 本坑 2 TBM 3 導坑 4 導坑の基端部周壁面 4a 基端部周壁面の天端付近 5a,5b,6a,6b,7a,7b,8a,8b,9
a,9b 岩片 15 仮置きベルトコンベヤ 16 残土搬出ベルトコンベヤ 20 トロッコ 25 防護管 26 ガントリー式ジャンボ架台 27 電線 28 水道管 29 送風管 T1,T2 交差部 S 空間 31 削孔機 34 削岩機 60 残土搬出ベルトコンベヤ A 開口部 G,G1,G2 岩片
1 Main pit 2 TBM 3 Guide pit 4 Base end peripheral wall of guide pit 4a Near top end of base end peripheral wall 5a, 5b, 6a, 6b, 7a, 7b, 8a, 8b, 9
a, 9b Rock piece 15 Temporary belt conveyor 16 Remaining soil conveyor belt conveyor 20 Truck 25 Protective tube 26 Gantry type jumbo stand 27 Electric wire 28 Water pipe 29 Blower pipe T1, T2 Intersection S space 31 Drilling machine 34 Rock excavator 60 Removing residual soil Belt conveyor A Opening G, G1, G2 Rock fragments

フロントページの続き (72)発明者 古賀 雄三 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 和田 利彦 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 小原 由幸 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 今津 雅紀 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 竹中 久 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 福田 和寛 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 風間 広志 東京都港区芝浦一丁目2番3号 清水建設 株式会社内Front page continued (72) Inventor Yuzo Koga 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Toshihiko Wada 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Yoshiyuki Obara 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Masaki Imazu 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Invention Hisashi Takenaka 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Kazuhiro Fukuda 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Hiroshi Kazama Tokyo Shimizuura 1-3-2, Minato-ku, Tokyo Shimizu Construction Co., Ltd.

Claims (11)

【特許請求の範囲】[Claims] 【請求項1】 本坑の予定掘削断面内に、円形全断面掘
削機工法によって導坑を掘削し、この導坑の基端部周壁
面を割岩して該導坑の基端部周壁面を本坑の大きさまで
切り拡げつつ導坑と本坑とを同時掘進することを特徴と
するトンネル掘削工法。
1. A guide shaft is excavated in a planned excavated cross section of the main shaft by a circular full-section excavator method, and a peripheral wall surface of a base end portion of the guide shaft is split to form a peripheral wall surface of the base end portion of the guide shaft. A tunnel excavation method characterized by simultaneously excavating a guide shaft and a main shaft while cutting and expanding to the size of the main shaft.
【請求項2】 導坑の基端部周壁面を割岩するに際し、
まず該基端部周壁面天端付近を、上部に向かうにしたが
って漸次幅狭になるように削孔して割岩し、その後、上
記基端部周壁面を、基端部周壁面天端付近から順次周方
向に沿って基端部周壁面底部まで削孔して割岩していく
工程を繰り返して上記基端部周壁面を外側に切り拡げる
ことを特徴とする請求項1記載のトンネル掘削工法。
2. When splitting the peripheral wall surface of the base end of the tunnel,
First, the vicinity of the base end peripheral wall top surface is drilled so that the width becomes gradually narrower toward the upper part, and the rock is divided, and then the base end peripheral wall surface from the base end peripheral wall top surface near 2. The tunnel excavation method according to claim 1, wherein the base end peripheral wall surface is cut outward by repeating a step of sequentially drilling a hole to the bottom of the base peripheral wall surface along the circumferential direction to split the rock.
【請求項3】 導坑の基端部周壁面を削孔するに際し、
各孔に、割岩の際に生じさせるべき亀裂の方向に延びる
スリット状のノッチを形成することを特徴とする請求項
2記載のトンネル掘削工法。
3. When drilling the peripheral wall surface of the base end of the tunnel,
3. The tunnel excavation method according to claim 2, wherein each hole is provided with a slit-shaped notch extending in the direction of a crack to be generated during split rock.
【請求項4】 導坑内に、該導坑の先端部近傍から本坑
側に向けて延びる仮置きベルトコンベヤを設けるととも
に、この仮置きベルトコンベヤの基端部から本坑の先端
部まで延びる残土搬出ベルトコンベヤを設け、導坑掘削
の際に出る掘削残土を上記仮置きベルトコンベヤに仮置
きし、その後、本坑掘削の作業に支障が出ない時期に、
上記両ベルトコンベヤを起動して上記掘削残土を上記本
坑に排出することを特徴とする請求項1から3のいずれ
かに記載のトンネル掘削工法。
4. A temporary placement belt conveyor extending from the vicinity of the tip of the tunnel toward the main tunnel side is provided in the tunnel, and the residual soil extending from the base end of the temporary placement belt conveyor to the tip of the main tunnel. A carry-out belt conveyor is provided, and the excavated soil that comes out during tunnel excavation is temporarily placed on the temporary placement belt conveyor, and then at a time when there is no hindrance to the main pit excavation work.
The tunnel excavation method according to any one of claims 1 to 3, wherein the both belt conveyors are activated to discharge the excavated residual soil to the main shaft.
【請求項5】 仮置きベルトコンベヤおよび残土排出ベ
ルトコンベヤをそれぞれ、導坑の長手方向に移動可能に
設けたことを特徴とする請求項4記載のトンネル掘削工
法。
5. The tunnel excavation method according to claim 4, wherein each of the temporary placement belt conveyor and the residual soil discharging belt conveyor is provided so as to be movable in the longitudinal direction of the tunnel.
【請求項6】 導坑内に、該導坑の長手方向に沿って延
びかつ該長手方向に沿って移動可能な仮置きベルトコン
ベヤを設け、この仮置きベルトコンベヤの上方位置に、
導坑掘削の際に出る掘削残土を導坑先端部から仮置きベ
ルトコンベヤまで搬送するトロッコを導坑の長手方向に
沿って移動可能に設け、本坑掘削の作業に支障が出ない
時期に、掘削残土が仮置きされた仮置きベルトコンベヤ
を本坑まで移動させて、起動することによって、上記掘
削残土を上記本坑に排出することを特徴とする請求項1
から3のいずれかに記載のトンネル掘削工法。
6. A temporary placement belt conveyor extending in the longitudinal direction of the tunnel and movable along the longitudinal direction is provided in the tunnel, and a position above the temporary placement belt conveyor is provided.
A trolley that conveys the remaining excavated soil from the tunnel excavation to the temporary belt conveyor is provided movably along the longitudinal direction of the tunnel, at a time when there is no hindrance to the main tunnel excavation work. 2. The excavated soil is discharged to the main pit by moving a temporary placement belt conveyor on which the excavated soil is temporarily placed to the main pit and activating the belt conveyor.
The tunnel excavation method according to any one of 1 to 3.
【請求項7】 本坑と導坑との取り合い部分に、導坑基
端部側から本坑先端部側に延びる防護管を設置し、この
防護管に電線、水道管、送風管等の長尺な線状部材およ
び残土排出ベルトコンベヤを挿通したことを特徴とする
請求項1から3のいずれかに記載のトンネル掘削工法。
7. A protective pipe extending from the base end side of the main shaft to the front end side of the main shaft is installed at an area where the main shaft and the main shaft are connected, and the protective pipe has a length of an electric wire, a water pipe, a blower pipe or the like. The tunnel excavation method according to any one of claims 1 to 3, wherein a long linear member and a residual soil discharging belt conveyor are inserted.
【請求項8】 導坑をその頂部が本坑の頂部となるべき
部位より上方に位置するように掘削し、導坑の頂部と、
本坑の頂部となるべき部位との2つの交差部間の空間
に、電線、水道管、送風管等の長尺な線状部材を挿通し
たことを特徴とする請求項1記載のトンネル掘削工法。
8. A tunnel is excavated so that its top is located above a site that should be the top of the main shaft, and the top of the tunnel is excavated.
The tunnel excavation method according to claim 1, characterized in that a long linear member such as an electric wire, a water pipe, a blower pipe, or the like is inserted into a space between two intersections with a site to be the top of the main shaft. .
【請求項9】 本坑の予定掘削断面内における上部に、
円形全断面掘削機工法によって導坑を掘削し、この導坑
の基端部周壁面を割岩して該導坑の基端部周壁面を本坑
の大きさまで切り拡げる場合において、導坑の基端部周
壁面の底部から下方を削孔して割岩した後、上記基端部
周壁面を割岩する工程を繰り返し行って、導坑の基端部
周壁面を本坑の大きさまで切り拡げることを特徴とする
請求項1記載のトンネルの掘削工法。
9. The upper part of the planned excavation section of the main shaft,
In the case of excavating a tunnel by the circular full-section excavator method and breaking the base wall of the tunnel at the base end to cut the base wall of the tunnel to the size of the main shaft, After drilling downward from the bottom of the end wall surface and splitting the rock, the process of splitting the base wall surface is repeated to cut the base wall surface of the tunnel to the size of the main shaft. The method for excavating a tunnel according to claim 1, characterized in that.
【請求項10】 本坑の予定掘削断面内における上部
に、円形全断面掘削機工法によって導坑を掘削し、この
導坑の基端部周壁面を割岩して該導坑の基端部周壁面を
本坑の大きさまで切り拡げる場合において、導坑の基端
部周壁面を割岩して、該基端部周壁面の底部より上方を
切り拡げつつ掘進して本坑の上半分を掘削し、その後、
本坑の下半分を縦方向に割岩することを特徴とする請求
項1記載のトンネル掘削工法。
10. A guide shaft is excavated at an upper part of a planned excavation section of the main shaft by a circular full-section excavator method, and a peripheral wall surface of a base end part of the guide shaft is split to form a base end periphery of the guide shaft. When cutting the wall to the size of the main shaft, the peripheral wall of the base of the tunnel is split, and the upper half of the main shaft is excavated by cutting and expanding above the bottom of the peripheral wall of the base. ,afterwards,
The tunnel excavation method according to claim 1, wherein the lower half of the main shaft is split in a vertical direction.
【請求項11】 上半分が掘削された本坑と導坑との取
り合い部分に、導坑基端部側から本坑側に延びる防護管
を設置し、この防護管に電線、水道管、送風管等の長尺
な線状部材および残土排出ベルトコンベヤを挿通したこ
とを特徴とする請求項10記載のトンネル掘削工法。
11. A protective pipe extending from the base end side of the main shaft to the main shaft side is installed at an area where the main shaft where the upper half has been excavated and the main shaft is connected, and an electric wire, a water pipe, and a blower are installed in the protective pipe. 11. The tunnel excavation method according to claim 10, wherein a long linear member such as a pipe and a residual soil discharging belt conveyor are inserted.
JP18268292A 1992-07-09 1992-07-09 Tunnel drilling method Withdrawn JPH0626297A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18268292A JPH0626297A (en) 1992-07-09 1992-07-09 Tunnel drilling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18268292A JPH0626297A (en) 1992-07-09 1992-07-09 Tunnel drilling method

Publications (1)

Publication Number Publication Date
JPH0626297A true JPH0626297A (en) 1994-02-01

Family

ID=16122597

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18268292A Withdrawn JPH0626297A (en) 1992-07-09 1992-07-09 Tunnel drilling method

Country Status (1)

Country Link
JP (1) JPH0626297A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62285508A (en) * 1986-06-04 1987-12-11 Sony Corp Freequency characterstic adjusting circuit
KR100537064B1 (en) * 2002-10-16 2005-12-16 서덕건설 주식회사 lower part bench excavation method of a tunnel
JP2009013603A (en) * 2007-07-02 2009-01-22 Shimizu Corp Tunnel construction method
WO2012086904A1 (en) * 2010-12-21 2012-06-28 (주)엘티엠 Method and related devices for carrying out tbm excavation and expansion blasting using a blast protector and a cart
JP2015155603A (en) * 2014-02-20 2015-08-27 川崎重工業株式会社 Rear work deck of shield machine
CN107218043A (en) * 2017-08-27 2017-09-29 中铁二十局集团第六工程有限公司 A kind of breaking surrounding rock cavern excavation method
CN112796770A (en) * 2020-12-30 2021-05-14 华能西藏雅鲁藏布江水电开发投资有限公司 Tunnel forming method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62285508A (en) * 1986-06-04 1987-12-11 Sony Corp Freequency characterstic adjusting circuit
KR100537064B1 (en) * 2002-10-16 2005-12-16 서덕건설 주식회사 lower part bench excavation method of a tunnel
JP2009013603A (en) * 2007-07-02 2009-01-22 Shimizu Corp Tunnel construction method
WO2012086904A1 (en) * 2010-12-21 2012-06-28 (주)엘티엠 Method and related devices for carrying out tbm excavation and expansion blasting using a blast protector and a cart
US9568295B2 (en) 2010-12-21 2017-02-14 Chan Woo Lee Method and related devices for carrying out TBM excavation and expansion blasting using a blast protector and a cart
JP2015155603A (en) * 2014-02-20 2015-08-27 川崎重工業株式会社 Rear work deck of shield machine
CN107218043A (en) * 2017-08-27 2017-09-29 中铁二十局集团第六工程有限公司 A kind of breaking surrounding rock cavern excavation method
CN112796770A (en) * 2020-12-30 2021-05-14 华能西藏雅鲁藏布江水电开发投资有限公司 Tunnel forming method

Similar Documents

Publication Publication Date Title
US3379264A (en) Earth boring machine
AU761775B2 (en) Three dimensional multi-phase tunneling method and equipments thereof
US6848748B2 (en) Mining system with drilling, loading, conveyor, and support
JP6751653B2 (en) How to excavate a tunnel
KR101889961B1 (en) Excavation method for rock blasting having no-vibration
JP4181980B2 (en) Tunnel construction method
JPH0626297A (en) Tunnel drilling method
JP4810475B2 (en) How to remove blast furnace residue
JP6527056B2 (en) EXPORT SYSTEM AND EXPORT METHOD OF EXCAVATOR
US20020096934A1 (en) Mining machine and method of mining
KR100351270B1 (en) 3 dimensional multi phase tunneling mathod and apparatus corresponding same
CN114635707B (en) Hydraulic fracturing-based rapid and continuous hard rock roadway or tunnel tunneling method
JP4281983B2 (en) Tunnel excavation method using advanced shaft
Okubo et al. Underground mining methods and equipment
CN114729561A (en) Projectile enhanced drilling system
JP2002303099A (en) Belt conveyor system
JP3243727B2 (en) Tunnel excavation method
JP2002021467A (en) Tunnel excavating method
US1833368A (en) Method of and apparatus for tunneling
CA2336200A1 (en) Tunnel boring machinery
CA2064625C (en) Method and apparatus for breaking a full face of rock for constructing mines and tunnels
JP3441016B2 (en) Tunnel construction equipment
RU2426881C1 (en) Development method of ore deposits with block caving system with active flexible separating covering
EA044537B1 (en) METHOD AND SYSTEM FOR CONSTRUCTION OF UNDERGROUND TUNNEL
WO2002101196A1 (en) A method of excavating a hard material body

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 19991005