CN2253370Y - 烟囱电动升模施工装置 - Google Patents
烟囱电动升模施工装置 Download PDFInfo
- Publication number
- CN2253370Y CN2253370Y CN 95245190 CN95245190U CN2253370Y CN 2253370 Y CN2253370 Y CN 2253370Y CN 95245190 CN95245190 CN 95245190 CN 95245190 U CN95245190 U CN 95245190U CN 2253370 Y CN2253370 Y CN 2253370Y
- Authority
- CN
- China
- Prior art keywords
- frame
- chimney
- lifting
- electric form
- handling frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
烟囱电动升模施工装置由随升工作井架及一套电动升模机构组成。电动升模机构附着在混凝土筒壁上,包括电动提升机以及为电动提升机驱动的操作架和提升架,提升架套设于操作架内,操作架的两侧为由槽钢构成的槽钢轨道,在提升架两侧壁上装有可在操作架槽钢轨道中滚动爬升的滚轮。在操作架和提升架上还分别设有多个用于与混凝土筒壁固定的锚固挂钩装置。施工中通过电动提升机的正反转使操作架和提升架交替上升,完成整个烟囱结构的施工过程。
Description
本实用新型属于建筑施工技术领域,涉及一种高层钢筋混凝土构筑物的施工装置,特别是一种用于烟囱构筑物混凝土浇灌施工的烟囱电动升模施工装置。
目前,在钢筋混凝土烟囱的建筑施工中较普遍地采用了液压滑模工艺及装置。这种工艺及装置虽具有施工工期短等特点,但却也存在着一些难以解决的问题,其主要表现在:由于施工中采用液压千斤顶来支承模板上升,而模板的提升往往又是在烟囱筒壁前一浇灌节段混凝土强度不到1MPa的情况下进行的,这样不仅要大量耗费钢材,也易出现混凝土表面粗糙、烟囱筒壁易被拉裂以及工作平台产生中心漂移或扭转等现象,从而导致诸如施工质量难以保证、施工安全缺乏保障以及施工管理复杂等问题的发生。
本实用新型的目的在于克服现有技术的缺陷,进而提供一种结构简单、节约钢材、施工工期短、使用及管理方便、能保证烟囱施工质量及施工安全性的烟囱电动升模施工装置。
本实用新型的目的是通过下述技术解决方案实现的:
该烟囱电动升模施工装置由随升工作井架及一套电动升模机构组成。随升工作井架架设于烟囱筒壁内,其上配装有随升支模平台、内衬砌筑平台、辐射梁和升降吊篮等。电动升模机构附着在混凝土筒壁上,包括电动提升机以及为电动提升机驱动的操作架和提升架。其中提升架套设于操作架内,操作架的两侧为由槽钢构成的槽钢轨道,在提升架两侧壁上装有可在操作架槽钢轨道中滚动爬升的滚轮。另外,在操作架和提升架上还分别设有多个用于与混凝土筒壁固定的锚固挂钩装置。施工过程中,将电动升模机构的操作架通过锚固挂钩装置附着固定在建造中的钢筋混凝土烟囱筒壁上部的预留孔中,反向开启电机,使提升架滚轮沿操作架槽钢轨道上行,提升架上升;提升架到位后将其也通过锚固挂钩装置(爬升靴)附着固定在混凝土筒壁上,再松开操作架上的锚固挂钩装置,正向开启电机,使操作架上行,操作架到位后再次将其锚固在混凝土筒壁上,然后支撑安装内外模板,对半径,浇灌混凝土,砌砖;待该浇灌节段施工结束后,松开提升架上的锚固挂钩装置,反向开启电机使提升架上升,提升架就位固定后进而再使操作架上升;如此周而复始地循环操作,使提升架和操作架交替上升,最终完成整个烟囱构筑物的施工过程。
本实用新型在用于烟囱构筑物的施工时,整个装置均附着在钢筋混凝土筒壁的顶部,操作架与提升架互为轨道,通过电机的正反转相互提升,装置本身亦随着结构物的上升而上升,由此可实现筒壁、内衬、爬梯、讯号平台等的同步施工。在施工过程中,由于采用了保证安全作业的锚固挂钩装置,全部施工装置的载荷均由已硬化了的筒壁混凝土结构自身承受,这样既节省了钢材,又克服了液压滑模工艺中容易出现的混凝土表面粗糙、烟囱筒壁易被拉裂以及工作平台产生中心漂移或扭转等现象,使混凝土的质量有了工艺上的保证,烟囱的几何尺寸也易于控制。
以下将结合附图对本实用新型内容作进一步说明。
图1为本实用新型的一个具体实施例结构的原理示意图。
图2为本实用新型的另一个具体实施例结构的原理示意图。
图3为装置中电动升模机构的原理示意图。
图4为图3的B向视图。
图5为图1和图2结构中锚固挂钩装置的结构示意图。
本实用新型所述装置在具体实施中主要有两种结构形式,在此申请文本中权且将它们分称为I型装置和II型装置。I型装置的原理结构如图1所示,它由其上配装有随升支模平台2、内衬砌筑平台11、辐射梁3和升降吊篮13的随升工作井架1以及附着于烟囱混凝土筒壁12的电动升模机构组成,其中电动升模机构由分设在混凝土筒壁12内侧及外侧的内、外电动提升机8a、8b、内、外操作架4a、4b和内、外提升架7a、7b组成。内提升架7a和外提升架7b分别套设在内操作架4a和外操作架4b内(图3),在操作架的两侧设有由槽钢构成的槽钢轨道41,在提升架的两侧壁上相应装有用于在操作架槽钢轨道41中作滚动爬升的滚轮71(图4)。操作(提升)架与混凝土筒壁12的锚固形式如图5所示,它是通过设于电动升模机构中锚固挂钩装置9实现的,在电动升模机机构中所设的锚固挂钩装置9可有多个,其中每个装置中都包括一根连插在混凝土筒壁预留孔内的对销杆93、一副设于操作架4或提升架7上的挂钩92以及一副用于连接对销杆93和挂钩92的爬升靴91。本实用新型的II型装置如图2所示,它的电动升模机构由设在混凝土筒壁12外侧的电动提升机8、操作架4和提升架7组成,除此之外的其余部分结构与I型装置基本相同。
文后附图所引的其它标号分别是:5—模板;6—模板调径紧顶丝杠;10—丝杠;14-电动葫芦;94—压紧扣铁。
Claims (4)
1、一种用于烟囱构筑物混凝土浇灌施工的烟囱电动升模施工装置,由随升工作井架(1)和附着于烟囱混凝土筒壁(12)的电动升模机构组成,在随升工作井架(1)上配装有随升支模平台(2)、内衬砌筑平台(11)、辐射梁(3)和升降吊篮(13),其特征在于电动升模机构由电动提升机(8)以及为电动提升机(8)驱动的操作架(4)和提升架(7)构成,其中提升架(7)套设于操作架(4)内,操作架(4)的两侧为由槽钢构成的槽钢轨道(41),在提升架(7)两侧壁上装有可在操作架槽钢轨道(41)中滚动爬升的滚轮(71),在操作架(4)和提升架(7)上还分别设有多个用于与混凝土筒壁(12)固定的锚固挂钩装置(9)。
2、如权利要求1所述的烟囱电动升模施工装置,其特征在于电动升模机构由分设在混凝土筒壁(12)内侧及外侧的内、外电动提升机(8a、8b)、内、外操作架(4a、4b)和内、外提升架(7a、7b)组成。
3、如权利要求1所述的烟囱电动升模施工装置,其特征在于电动升模机构由设在混凝土筒壁(12)外侧的电动提升机(8)、操作架(4)和提升架(7)组成。
4、如权利要求1或2或3所述的烟囱电动升模施工装置,其特征是电动升模机构的锚固挂钩装置(9)包括一根连插在混凝土筒壁预留孔内的对销杆(93)、一副设于操作架(4)或提升架(7)上的挂钩(92)以及一副用于连接对销杆(93)和挂钩(92)的爬升靴(91)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 95245190 CN2253370Y (zh) | 1995-08-18 | 1995-08-18 | 烟囱电动升模施工装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 95245190 CN2253370Y (zh) | 1995-08-18 | 1995-08-18 | 烟囱电动升模施工装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2253370Y true CN2253370Y (zh) | 1997-04-30 |
Family
ID=33885393
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 95245190 Expired - Fee Related CN2253370Y (zh) | 1995-08-18 | 1995-08-18 | 烟囱电动升模施工装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2253370Y (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100346047C (zh) * | 2006-04-26 | 2007-10-31 | 中国建筑第二工程局 | 电动爬架倒模设备及其同步爬升控制方法和施工方法 |
CN101482372B (zh) * | 2009-01-22 | 2010-06-09 | 中冶建工有限公司 | 烧结机烟道吊运组对施工工艺 |
CN101993002A (zh) * | 2009-08-11 | 2011-03-30 | 中煤第五建设公司 | 自控升降式立井悬挂吊盘 |
CN104818882A (zh) * | 2014-11-27 | 2015-08-05 | 国网青海省电力公司西宁供电公司 | 一种防坠落的电线杆爬升装置 |
CN109262850A (zh) * | 2018-08-15 | 2019-01-25 | 江苏中南建设装饰有限公司 | 一种室内操作后置埋件打孔设备及其施工方法 |
CN114059770A (zh) * | 2021-09-02 | 2022-02-18 | 上海建工四建集团有限公司 | 一种施工人货梯基础托换的施工方法 |
CN115370130A (zh) * | 2022-08-08 | 2022-11-22 | 中建一局集团第三建筑有限公司 | 一种滑动模板系统及滑模施工方法 |
-
1995
- 1995-08-18 CN CN 95245190 patent/CN2253370Y/zh not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100346047C (zh) * | 2006-04-26 | 2007-10-31 | 中国建筑第二工程局 | 电动爬架倒模设备及其同步爬升控制方法和施工方法 |
CN101482372B (zh) * | 2009-01-22 | 2010-06-09 | 中冶建工有限公司 | 烧结机烟道吊运组对施工工艺 |
CN101993002A (zh) * | 2009-08-11 | 2011-03-30 | 中煤第五建设公司 | 自控升降式立井悬挂吊盘 |
CN101993002B (zh) * | 2009-08-11 | 2013-04-24 | 中煤第五建设公司 | 自控升降式立井悬挂吊盘 |
CN104818882A (zh) * | 2014-11-27 | 2015-08-05 | 国网青海省电力公司西宁供电公司 | 一种防坠落的电线杆爬升装置 |
CN109262850A (zh) * | 2018-08-15 | 2019-01-25 | 江苏中南建设装饰有限公司 | 一种室内操作后置埋件打孔设备及其施工方法 |
CN114059770A (zh) * | 2021-09-02 | 2022-02-18 | 上海建工四建集团有限公司 | 一种施工人货梯基础托换的施工方法 |
CN114059770B (zh) * | 2021-09-02 | 2023-08-08 | 上海建工四建集团有限公司 | 一种施工人货梯基础托换的施工方法 |
CN115370130A (zh) * | 2022-08-08 | 2022-11-22 | 中建一局集团第三建筑有限公司 | 一种滑动模板系统及滑模施工方法 |
CN115370130B (zh) * | 2022-08-08 | 2024-04-05 | 中建一局集团第三建筑有限公司 | 一种滑动模板系统及滑模施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108033367B (zh) | 一种钢柱筒架交替支撑式钢平台与塔吊同步提升装置及其提升方法 | |
CN2253370Y (zh) | 烟囱电动升模施工装置 | |
CN105540446A (zh) | 内爬式吊装平台 | |
CN106698208A (zh) | 一种用于超高层建筑外部运输的吊装设备及吊装方法 | |
CN103074871B (zh) | 一种弧形坡面混凝土滑升模板 | |
CN113090014A (zh) | 一种高层装配式建筑整体作业平台及其施工方法与应用 | |
CN200971610Y (zh) | 烟囱导轨式提升平台装置 | |
CN203878979U (zh) | 螺栓对拉式轨道滑动模板 | |
CN109252656B (zh) | 高层建筑爬升模板及组装、灌注和提升方法 | |
CN202064281U (zh) | 一种滑模模架 | |
CN209835463U (zh) | 预制桥面板吊装设备 | |
CN200968057Y (zh) | 电动挂靴式烟囱升模施工装置 | |
CN112627484A (zh) | 一种两点式三角挂架平台及施工方法 | |
CN1048065C (zh) | 混凝土筒体的建筑方法 | |
CN2703077Y (zh) | 新型电动升模施工装置 | |
CN2491552Y (zh) | 一种电动升模施工装置 | |
CN2424258Y (zh) | 烟囱电动挂靴式升模施工装置 | |
CN216810895U (zh) | 一种电梯井作业平台 | |
CN111140254A (zh) | 一种长距离隧道全圆二衬仰拱施工模板体系及模板转运方法 | |
CN211714541U (zh) | 电梯井内剪力墙模板安装专用操作架 | |
CN213171212U (zh) | 一种用于建筑工程的起重装置 | |
CN211945883U (zh) | 一种便于运输的装配式建筑结构组件 | |
CN2253371Y (zh) | 烟囱电动升模装置 | |
CN2424259Y (zh) | 烟囱电动导轨式升模施工装置 | |
CN209906186U (zh) | 建筑模板跨楼层运输设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |