CN218665026U - Steel structure factory building roof tile hoisting combined steel carrying pole - Google Patents

Steel structure factory building roof tile hoisting combined steel carrying pole Download PDF

Info

Publication number
CN218665026U
CN218665026U CN202222179472.0U CN202222179472U CN218665026U CN 218665026 U CN218665026 U CN 218665026U CN 202222179472 U CN202222179472 U CN 202222179472U CN 218665026 U CN218665026 U CN 218665026U
Authority
CN
China
Prior art keywords
steel
plate
mounting
mounting panel
factory building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222179472.0U
Other languages
Chinese (zh)
Inventor
曾文举
刘永根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN JINHAI STEEL STRUCTURE CO Ltd
Original Assignee
HUNAN JINHAI STEEL STRUCTURE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN JINHAI STEEL STRUCTURE CO Ltd filed Critical HUNAN JINHAI STEEL STRUCTURE CO Ltd
Priority to CN202222179472.0U priority Critical patent/CN218665026U/en
Application granted granted Critical
Publication of CN218665026U publication Critical patent/CN218665026U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a steel construction factory building roofing tile hoist and mount combination steel carrying pole, including the steel pipe main part, the outer fixed surface of steel pipe main part installs first mounting panel and second mounting panel, and a plurality of through-holes have all been seted up to the upper surface of first mounting panel and second mounting panel, and the equal slidable mounting of upper surface of first mounting panel and second mounting panel has a plurality of slides, and the upper surface of a plurality of slides is fixed mounting respectively has first lifting hook and second lifting hook, and the last fixed surface of slide installs first sleeve, and first telescopic inside slidable mounting has first movable plate, the utility model discloses steel construction factory building roofing tile hoist and mount combination steel carrying pole for through the spring action of first spring, make inside the inserted bar of first sleeve insert and establish inside first mounting panel, thereby realize spacing the slide, lift by crane the transportation to the steel pipe main part through a plurality of first lifting hooks and second lifting hook convenience, make the steel pipe main part transport convenient and fast more.

Description

Steel structure factory building roof tile hoisting combined steel carrying pole
Technical Field
The utility model relates to a steel shoulder pole, in particular to steel construction factory building roofing tile hoist and mount combination steel shoulder pole.
Background
The balance beam is also called as an iron carrying pole and is used for keeping the balance of the hoisted equipment, avoiding the damage of the equipment by the sling, shortening the height of the sling, reducing the hoisting height of the movable pulley, reducing the horizontal pressure born by the equipment during hoisting, avoiding the damage of the equipment, and when a plurality of machines hoist, the balance beam can be used for reasonably distributing or balancing the load of each hoisting point.
Present steel construction factory building span all is 24m or more usually, because structural design reason, the design length of many factory building roofing coloured tiles is greater than factory building roof truss span far away, and the hoist and mount of construction installation process roofing coloured slab board must adopt the steel carrying pole to hoist, otherwise will take place the coloured tile and buckle damage or the coloured slab tile hoist and mount accident of falling, because the length of each engineering factory building roofing coloured tile is inconsistent, consequently there is following defect in steel carrying pole design and use in the past:
1, if each span factory building is designed and manufactured according to the length dimension of encaustic tiles of each factory building, the transportation of the steel carrying pole in the construction process can not be transported according to the total length dimension of the steel carrying pole, meanwhile, the steel carrying pole is generally transported by a lifting hook on the outer surface of the steel carrying pole in the transportation process, but the existing lifting hook has fixed dimension and is difficult to adjust and disassemble the position of the lifting hook for use, so that the transportation stability can not be ensured in the transportation process, the steel carrying pole is easy to damage in the transportation process,
2, the steel carrying pole is obtained in order to transport different lengths conveniently in the existing span plant, therefore, the steel carrying pole must be cut into several sections before transportation and then spliced after being transported to a construction site, the site needs to be spliced in an assembly site and found right time in construction measurement, the site needs to be welded, the labor intensity of workers is high, the welding quality of a spliced joint of the steel carrying pole is difficult to guarantee, and the potential safety hazard of a certain degree exists in the hoisting process.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steel construction factory building roofing tile hoist and mount combination steel shoulder pole to it is fixed to propose current lifting hook size in the above-mentioned background art to solve, is difficult to adjust and dismantle the use to the lifting hook position, makes when transporting, can't guarantee the stability of transportation, easily to the impaired problem of steel shoulder pole in the transportation.
In order to achieve the above object, the utility model provides a following technical scheme: steel construction factory building roofing tile hoist and mount combination steel shoulder pole, including the steel pipe main part, the fixed surface of steel pipe main part installs first mounting panel and second mounting panel, a plurality of through-holes have all been seted up to the upper surface of first mounting panel and second mounting panel, the equal slidable mounting in upper surface of first mounting panel and second mounting panel has a plurality of slides, and is a plurality of the upper surface of slide fixed mounting respectively has first lifting hook and second lifting hook, the fixed surface of slide installs first sleeve, first telescopic inside slidable mounting has first movable plate, fixed mounting has first spring between first movable plate and the first sleeve, the fixed surface of first movable plate installs the inserted bar, the inserted bar is inserted and is established the inside at the through-hole.
As a preferred technical scheme of the utility model, the external fixed surface that the inserted bar was kept away from to first movable plate is settled and is changeed there is the pull rod, the external fixed surface of pull rod installs the handle.
As an optimal technical scheme of the utility model, the cross-section of slide is the concavity, the fixed surface that the slide is close to first mounting panel installs the rubber pad.
As a preferred technical scheme of the utility model, the upper surface of slide is provided with two first sleeves, two first sleeve is central symmetry setting.
As an optimal technical scheme of the utility model, the inside fixed mounting of steel pipe main part has the fixed plate, the fixed surface of fixed plate installs the second sleeve, the telescopic inside slidable mounting of second has the second movable plate, fixed mounting has the second spring between second movable plate and the second sleeve, the fixed surface of second movable plate installs the slide bar, the free end fixed mounting of slide bar has the clamp plate, the inside fixed mounting of steel pipe main part has a plurality of limiting plates, the inside of steel pipe main part is inserted and is equipped with the connecting pipe, the fixed surface of connecting pipe installs a plurality of sliders, the one end fixed mounting that steel pipe main part was kept away from to the connecting pipe has the flange, the surface of flange is provided with a plurality of bolts.
As a preferred technical scheme of the utility model, the fixed surface that the fixed plate is close to the connecting pipe installs the guard plate, the free end of guard plate is inserted and is established inside the connecting pipe, the guard plate is close to the fixed surface of connecting pipe and installs the sealing washer.
As an optimal technical scheme of the utility model, the fixed surface of connecting pipe installs the annular plate, the diameter of annular plate is greater than the diameter of steel pipe main part.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a with the surface of a plurality of slide slidable mounting at first mounting panel and second mounting panel, then the spring action through first spring for inside inserted bar of first sleeve is inserted and is established inside first mounting panel, thereby realizes slide adjusting distance, and carry on spacingly to the slide, conveniently lift by crane the transportation to the steel pipe main part through a plurality of first lifting hooks and second lifting hook, can adjust the position of lifting by crane the rope simultaneously at any time, make the steel pipe main part transport convenient and fast more.
2. The utility model discloses an insert the inside of establishing in the steel pipe main part with the connecting pipe, then the spring action through the second spring for the clamp plate carries on spacingly to the slider of connecting pipe surface, can carry on spacingly this moment to the connecting pipe, thereby realize installing the connecting pipe, then connect the installation through the bolt with the flange of two connecting pipe surfaces, make installation and dismantlement can be more convenient between the steel pipe main part, increase the stability when steel pipe main part uses simultaneously.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of a first sleeve according to the present invention;
FIG. 3 is a schematic view of the internal structure of the steel tube main body of the present invention;
fig. 4 is a schematic view of the internal structure of the second sleeve of the present invention.
In the figure: 1. a steel pipe body; 201. a first mounting plate; 202. a through hole; 203. a slide plate; 204. a first hook; 205. a first sleeve; 206. a pull rod; 207. a first spring; 208. a first moving plate; 209. inserting a rod; 210. a second hook; 211. a second mounting plate 301, a fixing plate; 302. a second sleeve; 303. a second spring; 304. a second moving plate; 305. a slide bar; 306. pressing a plate; 307. a slider; 308. a limiting plate; 309. a protection plate; 310. a seal ring; 311. an annular plate; 312. a connecting pipe; 313. and (4) a flange.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the utility model provides a steel construction factory building roofing tile hoists combination steel shoulder pole's technical scheme:
the first embodiment is as follows:
according to fig. 1 and 2, a steel structure factory building roof tile hoisting combined steel carrying pole comprises a steel pipe body 1, a first mounting plate 201 and a second mounting plate 211 are fixedly mounted on the outer surface of the steel pipe body 1, a plurality of through holes 202 are formed in the upper surfaces of the first mounting plate 201 and the second mounting plate 211, a plurality of sliding plates 203 are slidably mounted on the upper surfaces of the first mounting plate 201 and the second mounting plate 211, a first hook 204 and a second hook 210 are fixedly mounted on the upper surfaces of the sliding plates 203 respectively, a first sleeve 205 is fixedly mounted on the upper surface of the sliding plate 203, a first moving plate 208 is slidably mounted inside the first sleeve 205, a first spring 207 is fixedly mounted between the first moving plate 208 and the first sleeve 205, an inserting rod 209 is fixedly mounted on the outer surface of the first moving plate 208, the inserting rod 209 is inserted inside the through holes 202, a pull rod 206 is fixedly mounted on the outer surface of the first moving plate 208 far away from the inserting rod 209, a handle is fixedly mounted on the outer surface of the pull rod 206, the cross section of the sliding plate 203 is concave, rubber pads are fixedly mounted on the outer surface of the first sliding plate 203, a rubber pad is capable of reducing loss generated on the first mounting plate 203, and a plurality of the sliding plates 205 is further provided with a plurality of sliding plates 205 capable of being symmetrical first sleeve 205 capable of being arranged on the surface of being provided with a plurality of friction rubber pads 205 capable of being arranged on the first sleeve 205.
When specifically using, the utility model discloses steel construction factory building roofing tile hoist and mount combination steel shoulder pole, through with a plurality of slides 203 slidable mounting on the surface of first mounting panel 201 and second mounting panel 211, and adjust the position of slide 203, make the slide 203 on first mounting panel 201 and second mounting panel 211 surface can the uniform mount, then the elastic action through first spring 207, make the inside inserted bar 209 of first sleeve 205 insert and establish inside first mounting panel 201, thereby realize spacing slide 203, conveniently lift by crane the transportation to steel pipe main part 1 through a plurality of first lifting hooks 204 and second lifting hook 210, can adjust the position of lifting by crane the rope simultaneously at any time, make steel pipe main part 1 transport convenient and fast more, and through pulling pull rod 206, pull rod 206 drives first movable plate 208 and removes, first movable plate 208 drives the inserted bar 209 and removes, make inserted bar 209 shift out first mounting panel 201, thereby the convenience is dismantled the use to slide 203.
Example two:
on the basis of the first embodiment, as shown in fig. 1, 3 and 4, a fixed plate 301 is fixedly installed inside the steel pipe main body 1, a second sleeve 302 is fixedly installed on the outer surface of the fixed plate 301, a second moving plate 304 is slidably installed inside the second sleeve 302, a second spring 303 is fixedly installed between the second moving plate 304 and the second sleeve 302, a sliding rod 305 is fixedly installed on the outer surface of the second moving plate 304, a pressing plate 306 is fixedly installed at the free end of the sliding rod 305, a plurality of limiting plates 308 are fixedly installed inside the steel pipe main body 1, a connecting pipe 312 is inserted inside the steel pipe main body 1, a plurality of sliding blocks 307 are fixedly installed on the outer surface of the connecting pipe 312, a flange 313 is fixedly installed at one end of the connecting pipe 312 far away from the steel pipe main body 1, a plurality of bolts are arranged on the outer surface of the flange 313, a protection plate 309 is fixedly installed on the outer surface of the fixed plate 301 close to the connecting pipe 312, the free end of the protection plate 309 is inserted inside the connecting pipe 312, a sealing ring 310 is fixedly installed on the outer surface of the protection plate 309 close to the connecting pipe 312, the second sleeve 302 can be protected by the protection plate 309, dust in the connecting pipe main body 1, thereby preventing the dust inside the second sleeve 302 from entering the second sleeve 302, the connecting pipe main body 303, thereby influencing the use of the second spring, the connecting pipe 303, the connecting pipe main body 303, and the connecting pipe 311 can be larger than the diameter of the connecting pipe 311.
When specifically using, the utility model discloses steel construction factory building roofing tile hoist and mount combination steel shoulder pole, when splicing the use to steel pipe main part 1, can be through inserting connecting pipe 312 in the inside of establishing at steel pipe main part 1, make the slider 307 of connecting pipe 312 surface pass limiting plate 308, rotate connecting pipe 312 again, make limiting plate 308 carry on spacingly to slider 307, then the elastic action through the inside second spring 303 of second sleeve 302, make the second remove the version remove, second movable plate 304 drives slide bar 305 and removes, slide bar 305 drives clamp plate 306 and removes, carry on spacingly to the slider 307 of connecting pipe 312 surface through getting clamp plate 306, can carry on spacingly to connecting pipe 312 this moment, thereby realize installing connecting pipe 312, then connect the installation through the bolt with the flange 313 of two connecting pipe 312 surfaces, make installation and dismantlement can be more convenient between the steel pipe main part 1, increase the stability when steel pipe main part 1 uses simultaneously.
In the description of the present invention, it should be understood that the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the indicated device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
In the present invention, unless otherwise explicitly specified or limited, for example, it may be fixedly connected, detachably connected, or integrated; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. Steel construction factory building roofing tile hoist and mount combination steel shoulder pole, including steel pipe main part (1), its characterized in that: the utility model discloses a steel pipe fitting, including steel pipe main body (1), the outer fixed surface of first mounting panel (201) and second mounting panel (211), a plurality of through-holes (202) have all been seted up to the upper surface of first mounting panel (201) and second mounting panel (211), the equal slidable mounting of upper surface of first mounting panel (201) and second mounting panel (211) has a plurality of slides (203), and is a plurality of the upper surface of slide (203) fixed mounting respectively has first lifting hook (204) and second lifting hook (210), the upper surface fixed mounting of slide (203) has first sleeve (205), the inside slidable mounting of first sleeve (205) has first movable plate (208), fixed mounting has first spring (207) between first movable plate (208) and first sleeve (205), the outer fixed surface of first movable plate (208) installs inserted bar (209), inserted bar (209) are inserted and are established the inside of through-hole (202).
2. The steel structure factory building roof tile hoist and mount combination steel shoulder pole of claim 1, characterized in that: the outer surface of the first moving plate (208) far away from the inserted link (209) is fixedly provided with a pull rod (206), and the outer surface of the pull rod (206) is fixedly provided with a handle.
3. The steel structure factory building roofing tile hoist and mount combination steel shoulder pole of claim 1, characterized in that: the cross section of the sliding plate (203) is concave, and a rubber pad is fixedly arranged on the surface, close to the first mounting plate (201), of the sliding plate (203).
4. The steel structure factory building roof tile hoist and mount combination steel shoulder pole of claim 1, characterized in that: the upper surface of slide (203) is provided with two first sleeves (205), two first sleeves (205) are central symmetry and set up.
5. The steel structure factory building roof tile hoist and mount combination steel shoulder pole of claim 1, characterized in that: the inside fixed mounting of steel pipe body (1) has fixed plate (301), the outer fixed surface of fixed plate (301) installs second sleeve (302), the inside slidable mounting of second sleeve (302) has second movable plate (304), fixed mounting has second spring (303) between second movable plate (304) and second sleeve (302), the outer fixed surface of second movable plate (304) installs slide bar (305), the free end fixed mounting of slide bar (305) has clamp plate (306), the inside fixed mounting of steel pipe body (1) has a plurality of limiting plates (308), the inside of steel pipe body (1) is inserted and is equipped with connecting pipe (312), the outer fixed surface of connecting pipe (312) installs a plurality of slider (307), the one end fixed mounting that steel pipe body (1) was kept away from in connecting pipe (312) has flange (313), the surface of flange (313) is provided with a plurality of bolts.
6. The steel structure factory building roof tile hoist and mount combination steel shoulder pole of claim 5, characterized in that: the outer fixed surface that fixed plate (301) are close to connecting pipe (312) installs guard plate (309), the free end of guard plate (309) is inserted and is established inside connecting pipe (312), the outer fixed surface that guard plate (309) are close to connecting pipe (312) installs sealing washer (310).
7. The steel structure factory building roof tile hoist and mount combination steel shoulder pole of claim 5, characterized in that: the outer surface of the connecting pipe (312) is fixedly provided with an annular plate (311), and the diameter of the annular plate (311) is larger than that of the steel pipe main body (1).
CN202222179472.0U 2022-08-18 2022-08-18 Steel structure factory building roof tile hoisting combined steel carrying pole Active CN218665026U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222179472.0U CN218665026U (en) 2022-08-18 2022-08-18 Steel structure factory building roof tile hoisting combined steel carrying pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222179472.0U CN218665026U (en) 2022-08-18 2022-08-18 Steel structure factory building roof tile hoisting combined steel carrying pole

Publications (1)

Publication Number Publication Date
CN218665026U true CN218665026U (en) 2023-03-21

Family

ID=85554980

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222179472.0U Active CN218665026U (en) 2022-08-18 2022-08-18 Steel structure factory building roof tile hoisting combined steel carrying pole

Country Status (1)

Country Link
CN (1) CN218665026U (en)

Similar Documents

Publication Publication Date Title
CN109487709B (en) One-side riding type temporary rope self-balancing pushing type suspension bridge sling replacement underpinning device
CN103470093B (en) Concrete chimney dismantling method
CN101177959A (en) Curtain wall unit hanging equipment and construction method thereof
CN112942661B (en) Construction method of stay cable with flexible cable net boundary
KR101547824B1 (en) Furnace scaffolding and hoisting system platform support system
CN218665026U (en) Steel structure factory building roof tile hoisting combined steel carrying pole
CN215367833U (en) Construction elevator short wall-attached device
CN104627849B (en) Hoisting equipment and hoisting method for hoisting inner courtyard pipeline
CN111255132A (en) Unit type glass curtain wall construction method
CN111042538A (en) Hoisting and mounting method of buckling restrained brace
CN219031472U (en) Fine-tuning lifting appliance for building curtain wall unit
CN110697564A (en) Hoisting device and hoisting method for precast concrete beam
CN210655948U (en) Hoisting device for hoisting inner ring type track single-beam crane in tall and large factory building
CN221216936U (en) Wall-riding type installation hanging bracket of high-altitude hoisting equipment
CN214780230U (en) Universal hanging bracket for prefabricated laminated slab
CN216336297U (en) Simple tool for hoisting steel column
CN109399454B (en) Hoisting device and method for pipe fitting below industrial travelling crane beam
CN210798968U (en) Shaft concrete unloading pipe installation and disassembly device
CN217758348U (en) Hang basket suspender bottom end rail anchor structure
CN210064891U (en) Linear four-point-crane universal hoisting device for precast concrete member
CN210084724U (en) A general hoisting accessory is hung to plane four points for precast concrete component
CN214935271U (en) Pipe jacking pipe joint lifting appliance
CN219792127U (en) Steel construction vestibule hoist and mount hoist
CN215048059U (en) Flange type guide pipe auxiliary lifting appliance
CN213011558U (en) H-shaped component hoisting, fixing and positioning construction device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Steel Structure Factory House Tile Hoisting Combination Steel Shoulder Pole

Granted publication date: 20230321

Pledgee: Changsha Bank Co.,Ltd. Huirong Branch

Pledgor: HUNAN JINHAI STEEL STRUCTURE CO.,LTD.

Registration number: Y2024980004008