CN218346792U - Wooden formwork fixing device - Google Patents
Wooden formwork fixing device Download PDFInfo
- Publication number
- CN218346792U CN218346792U CN202222038327.0U CN202222038327U CN218346792U CN 218346792 U CN218346792 U CN 218346792U CN 202222038327 U CN202222038327 U CN 202222038327U CN 218346792 U CN218346792 U CN 218346792U
- Authority
- CN
- China
- Prior art keywords
- embedded sleeve
- bolt
- plate
- embedded
- pressing plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a wood formwork fixing device, which comprises a pre-buried sleeve, a bolt and a pressing piece; the embedded sleeves are horizontally arranged; the pressing piece of the L-shaped structure comprises a pressing plate which is vertically arranged and a propping plate which is connected with the lower end of the pressing plate; the bolt penetrates through the through hole in the pressing plate and extends into the embedded sleeve, and the bolt is connected with the embedded sleeve through a threaded structure; the abutting plate is located on one side, adjacent to the embedded sleeve, of the pressing plate. The concrete pouring wooden template positioned on the side A of the outer vertical surface of the building is convenient to disassemble and assemble. The safety of the concrete pouring wooden template construction process located on the side A of the outer vertical face of the building is improved, the reliability is high, and the working efficiency and the construction quality are improved. Part component repeatedly usable practices thrift manpower, material resources for construction progress, effectively reduce construction cost.
Description
Technical Field
The utility model belongs to the technical field of the construction, concretely relates to plank sheathing fixing device.
Background
In the construction process of constructional engineering, the forming of a concrete structure is mainly formed by erecting a wood formwork, the concrete structure is usually designed into multiple layers according to needs, and pouring construction is carried out from bottom to top, so that an interlayer construction joint L exists between an upper layer and a lower layer. In the construction process of concrete structure walls, columns and other members outside the building, wooden templates are also required to be erected for supporting. And after the lower-layer concrete reaches the form removal strength, removing the lower-layer concrete pouring wood formwork, and then erecting the upper-layer concrete pouring wood formwork. The upper concrete pouring wood formwork located on the outer vertical surface side of the building needs to shield the interlayer construction joint L, the upper concrete pouring wood formwork is firmly fixed at the interlayer construction joint L, and the upper concrete pouring wood formwork needs to be tightly lapped with the outer side surface of the lower concrete structure to meet the requirement of erecting the wood formwork in engineering construction and ensure the forming quality of the concrete member.
In the current common practice of construction site, as shown in fig. 1-2, a lower layer concrete pouring wood formwork 1 is erected and encloses a pouring space 101. Drilling holes at the upper part of the lower layer concrete pouring wood formwork 1 positioned on the outer vertical surface side A of the building for installing the horizontally arranged embedded screw rods 3, wherein one end of each embedded screw rod 3 is positioned in the pouring cavity 101, and the other end of each embedded screw rod 3 is positioned on the outer vertical surface side A of the building. And pouring concrete into the pouring space 101, and removing the lower-layer concrete pouring wood formwork 1 after the lower-layer concrete structure 102 reaches the demolding strength. And after demolding, the embedded screw rod 3 is used for supporting and fixing the lower end position of the upper concrete pouring wood template 2. Because the wood template is provided with the back edge, the wood template and the back edge are generally connected into a whole by nails, the thickness of the wood template is about 100mm, a phi 48 steel pipe is used as a main edge during fixing, and then the wood template is fixed by a wood template tie screw rod. Therefore, the length of the embedded screw rod 3 is about 200mm.
In order to remove the lower concrete pouring wooden form 1 positioned on the building outer vertical surface side a by using the embedded screw rods 3, the lower concrete pouring wooden form 1 needs to be withdrawn about 300mm from the building outer vertical surface side a to be smoothly taken out. On the other hand, in the scaffold installed on the building facade side a, since the specification of the distance from the inside of the scaffold to the building facade side a is required to be about 250mm, the lower concrete-poured wooden form 1 is attached and detached by interference of the scaffold, and therefore, it is necessary to adjust the steel pipe interfering with the inside of the scaffold and then attach and detach the lower concrete-poured wooden form 1. Therefore, the concrete pouring wooden formwork located on the building outer vertical face side a is inconvenient to erect and construct, and particularly, the concrete pouring wooden formwork located on a gable part is large in area, difficult to construct and high in potential safety hazard.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that a plank sheathing fixing device is provided, make the concrete placement plank sheathing easy dismounting who is located facade side A outside the building.
The utility model provides a technical scheme that its technical problem adopted is: the wood template fixing device comprises a pre-buried sleeve, a bolt and a pressing piece;
the embedded sleeves are horizontally arranged;
the pressing piece of the L-shaped structure comprises a pressing plate which is vertically arranged and a propping plate which is connected with the lower end of the pressing plate;
the bolt penetrates through the through hole in the pressing plate and extends into the embedded sleeve, and the bolt is connected with the embedded sleeve through a threaded structure; the abutting plate is located on one side, adjacent to the embedded sleeve, of the compression plate.
Furthermore, one end of the embedded sleeve adjacent to the compression plate is connected with a nut, and the bolt is connected with the nut.
Furthermore, the outer side wall of the nut is connected with the inner wall of the embedded sleeve in a welding mode.
Furthermore, the embedded sleeve type seal head anchor plate further comprises a vertically arranged seal head anchor plate, and the seal head anchor plate is connected with one end, far away from the nut, of the embedded sleeve.
Furthermore, the embedded sleeve, the nut, the bolt, the pressing piece and the seal head anchor plate are all made of steel.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model provides a plank sheathing fixing device makes the concrete placement plank sheathing easy dismounting who is located facade side A outside the building. The construction process of the concrete pouring wooden template positioned on the side A of the outer vertical face of the building is improved, the reliability is high, and the working efficiency and the construction quality are improved. Part component repeatedly usable practices thrift manpower, material resources for construction progress, effectively reduce construction cost.
Drawings
FIG. 1 is a schematic structural diagram of a prior art in which a lower concrete pouring wooden template is erected and an embedded screw rod is installed;
FIG. 2 is a schematic structural diagram of a prior art upper concrete pouring wooden formwork supported and fixed by embedded screws;
FIG. 3 is a schematic structural diagram of the construction of a lower concrete pouring wooden form and the installation of the utility model;
fig. 4 is a schematic structural view of the upper concrete pouring wood formwork supported and fixed by the utility model;
fig. 5 is a schematic cross-sectional structural view of the embedded sleeve, the nut and the anchor plate;
fig. 6 is a schematic side view of the pre-buried sleeve, the nut and the anchor plate;
reference numerals are as follows: 1-pouring lower-layer concrete into a wood template; 101-pouring a cavity; 102-an underlying concrete structure; 2-upper concrete pouring wood formwork; 3, pre-embedding a screw rod; 4-embedding a sleeve; 5-a nut; 6-bolt; 7, a pressing piece; 701-a compression plate; 702-a backup plate; 8-end enclosure anchor plate.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and examples.
As shown in fig. 3 to 6, the wood formwork fixing device includes an embedded sleeve 4, a bolt 6 and a pressing member 7; the embedded sleeves 4 are horizontally arranged; the pressing piece 7 with an L-shaped structure comprises a pressing plate 701 which is vertically arranged, and an abutting plate 702 which is connected with the lower end of the pressing plate 701; the bolt 6 penetrates through a through hole in the pressing plate 701 and extends into the embedded sleeve 4, and the bolt 6 is connected with the embedded sleeve 4 through a threaded structure; the abutting plate 702 is located on one side of the pressing plate 701 adjacent to the embedded sleeve 4.
And (3) erecting a lower-layer concrete pouring wood formwork 1 and enclosing a pouring space 101. The embedded sleeve 4 is horizontally arranged in the pouring cavity 101, and one end of the embedded sleeve 4 is arranged adjacent to the lower-layer concrete pouring wood formwork 1 located on the outer facade side A of the building. The bolt 6 penetrates through a through hole in the lower concrete pouring wood formwork 1 positioned on the outer facade side A of the building and is detachably connected with the embedded sleeve 4 through a threaded structure. And pouring concrete into the pouring chamber 101, removing the bolts 6 after the concrete reaches the form removal strength, removing the lower-layer concrete pouring wood formwork 1, and positioning the embedded sleeve 4 in the lower-layer concrete structure 102. And then, installing the pressing piece 7 and the bolt 6, and reserving an installation gap between the pressing plate 701 and the outer side surface of the lower-layer concrete structure 102. And (3) erecting an upper concrete pouring wood formwork 2, wherein the upper concrete pouring wood formwork 2 positioned on the building outer facade side A shields the interlayer construction joint L, placing the construction joint L into the installation gap, screwing the bolt 6, enabling the pressing plate 701 to abut against the upper concrete pouring wood formwork 2 positioned on the building outer facade side A, and placing the upper concrete pouring wood formwork 2 on the bolt 6. The abutting plate 702 abuts against the outer side face of the lower-layer concrete structure 102 to provide a transverse support for the pressing plate 701, so that the pressing plate 701 is enabled to be tightly attached to the upper-layer concrete pouring wood formwork 2 located on the outer vertical face side A of the building. The wood formwork fixing devices are arranged in the horizontal direction at intervals, and the wood formwork fixing devices jointly provide stable vertical supports for the upper concrete pouring wood formwork 2 located on the outer vertical face side A of the building. The method has the advantage of convenient disassembly and assembly, and can meet the disassembly and assembly requirements of the upper concrete pouring wood formwork 2 positioned on the outer vertical surface A of the concrete structure.
The pressing plate 701 and the abutting plate 702 may be welded together or may be an integrally formed integral structure.
The inner wall of the embedded sleeve 4 can be provided with a thread matched with the bolt 6 in a thread manner, preferably, one end of the embedded sleeve 4 adjacent to the pressing plate 701 is connected with a nut 5, and the bolt 6 is connected with the nut 5. The nuts 5 are cast in the lower concrete structure 102 adjacent to the outer side of the lower concrete structure 102.
One end face of the embedded sleeve 4 can be connected with one end face of the nut 5 in a welding mode, and when the upper concrete pouring wood template 2 is placed on the bolt 6, the nut 5 is prone to being separated from the embedded sleeve 4. In order to solve the above technical problem, it is preferable that an outer side wall of the nut 5 is welded to an inner wall of the embedded sleeve 4. The nut 5 may be partially or entirely disposed in the embedment sleeve 4. When the upper concrete pouring wood formwork 2 is arranged on the bolt 6, the pipe wall of the embedded sleeve 4 provides stress support for the nut 5, the nut 5 is prevented from being separated from the embedded sleeve 4, and the reliability of the device is improved.
Preferably, the anchor plate device further comprises a head anchor plate 8 which is vertically arranged, and the head anchor plate 8 is connected with one end, far away from the nut 5, of the embedded sleeve 4. The end socket anchor plate 8 has the functions of anchoring and plugging the embedded sleeve 4, and avoids that the poured concrete flows into the embedded sleeve 4 to influence the dismounting and mounting of the bolt 6. The seal head anchor plate 8 is connected with the embedded sleeve 4 in a welding mode.
Preferably, the embedded sleeve 4, the nut 5, the bolt 6, the pressing piece 7 and the seal head anchor plate 8 are all made of steel.
The utility model discloses an above do the concrete embodiment, can find out from the implementation, the utility model provides a plank sheathing fixing device makes the concrete placement plank sheathing easy dismounting who is located building facade side A. The construction process of the concrete pouring wooden template positioned on the side A of the outer vertical face of the building is improved, the reliability is high, and the working efficiency and the construction quality are improved. Part component repeatedly usable practices thrift manpower, material resources, when accelerating the construction progress, effectively reduces construction cost.
Claims (5)
1. Plank sheathing fixing device, its characterized in that: comprises an embedded sleeve (4), a bolt (6) and a pressing piece (7);
the embedded sleeves (4) are horizontally arranged;
the pressing piece (7) of the L-shaped structure comprises a pressing plate (701) which is vertically arranged and an abutting plate (702) which is connected with the lower end of the pressing plate (701);
the bolt (6) penetrates through a through hole in the pressing plate (701) and extends into the embedded sleeve (4), and the bolt (6) is connected with the embedded sleeve (4) through a threaded structure; the abutting plate (702) is located on one side, adjacent to the embedded sleeve (4), of the pressing plate (701).
2. The plank sheathing apparatus of claim 1, wherein: one end of the embedded sleeve (4) adjacent to the compression plate (701) is connected with a nut (5), and the bolt (6) is connected with the nut (5).
3. The plank sheathing apparatus of claim 2, wherein: the outer side wall of the nut (5) is connected with the inner wall of the embedded sleeve (4) in a welding mode.
4. The plank sheathing apparatus of claim 2, wherein: the sealing head anchor plate is characterized by further comprising a sealing head anchor plate (8) which is vertically arranged, wherein the sealing head anchor plate (8) is connected with one end, far away from the nut (5), of the embedded sleeve (4).
5. The plank sheathing apparatus of claim 4, wherein: the embedded sleeve (4), the nut (5), the bolt (6), the pressing piece (7) and the seal head anchor plate (8) are all made of steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222038327.0U CN218346792U (en) | 2022-08-03 | 2022-08-03 | Wooden formwork fixing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222038327.0U CN218346792U (en) | 2022-08-03 | 2022-08-03 | Wooden formwork fixing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218346792U true CN218346792U (en) | 2023-01-20 |
Family
ID=84913529
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222038327.0U Active CN218346792U (en) | 2022-08-03 | 2022-08-03 | Wooden formwork fixing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218346792U (en) |
-
2022
- 2022-08-03 CN CN202222038327.0U patent/CN218346792U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206616862U (en) | Formwork root bracing means | |
CN105544979A (en) | Formwork supporting device for wall corner portion construction and construction method | |
CN104746862A (en) | Temporary installation operating platform on overhead equipment foundation and erecting method thereof | |
CN103161313B (en) | Connection method of main reinforcement of constructional column of infilled wall and framed girder | |
CN113585652B (en) | Same-layer construction method for pipeline decoration integrated pre-assembled wallboard and main body structure | |
CN210396134U (en) | Reinforcing tool for controlling horizontal joint quality of shear wall | |
CN210685444U (en) | Quick leveling, mounting and supporting device for prefabricated external wall panel | |
CN218346792U (en) | Wooden formwork fixing device | |
CN207177286U (en) | Add region mould after fabricated shear wall is reserved | |
KR101131079B1 (en) | Multi U-head Support Apparatus For Bridge Construction | |
CN213062888U (en) | Built-in type scaffold is wall spare and scaffold even | |
CN110424601B (en) | Concrete pouring anti-floating device for composite floor slab with fabricated structure and implementation method | |
CN201901941U (en) | Building system combining precast concrete member and cast-in-place concrete template | |
JP5749620B2 (en) | Seismic isolation method for existing buildings | |
CN209907936U (en) | Integrated template system of cast-in-situ overhanging window board with secondary structure | |
CN110905185B (en) | Overhanging I-shaped steel fixing method | |
CN114517585A (en) | Accurate installation method for building shock insulation support | |
CN204983647U (en) | Design instrument formula aluminum alloy template | |
KR100865133B1 (en) | A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof | |
CN110118014B (en) | Exterior wall template system free of exterior scaffold and construction method thereof | |
CN209907886U (en) | Adjustable assembled stair construction platform | |
CN111851997A (en) | Construction method for post-cast section template of laminated slab | |
CN112323811A (en) | Adjustable-length inner supporting structure of fabricated foundation pit and construction method of adjustable-length inner supporting structure | |
CN205330172U (en) | A formwork support device that is used for wall body corner position to be under construction | |
KR101415867B1 (en) | Precast concrete structure construction method for downward construction of underground structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |