CN216888872U CN202123322874.3U CN202123322874U CN216888872U CN 216888872 U CN216888872 U CN 216888872U CN 202123322874 U CN202123322874 U CN 202123322874U CN 216888872 U CN216888872 U CN 216888872U
Authority
CN
China
Prior art keywords
galvanized pipe
baffle
pipe processing
conveying device
lifting platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123322874.3U
Other languages
Chinese (zh)
Inventor
王利琨
李学进
兰光辉
宿立华
张立杰
王少杰
周连宇
申宝华
王利森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shahe Jinhai Special Steel Co ltd
Original Assignee
Shahe Jinhai Special Steel Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shahe Jinhai Special Steel Co ltd filed Critical Shahe Jinhai Special Steel Co ltd
Priority to CN202123322874.3U priority Critical patent/CN216888872U/en
Application granted granted Critical
Publication of CN216888872U publication Critical patent/CN216888872U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a galvanized pipe processing and conveying device. Galvanized pipe processing conveyor includes: the base, the fixed station that is used for fixed processingequipment is installed at the top of base, and one side of fixed station is equipped with first elevating platform, be equipped with the second elevating platform on the first elevating platform, install two track boards on the first elevating platform, install by first electronic jar driven install bin on the track board, install by motor drive's runner, two in the install bin the bracket is installed to one side of install bin. The galvanized pipe processing and conveying device provided by the utility model can play an auxiliary supporting role during conveying of the galvanized pipe through the arrangement of the bracket, the labor intensity is reduced, the galvanized pipe is prevented from being damaged due to falling, the baffle plate with a smaller height difference with the galvanized pipe is arranged, the deformation possibility of the baffle plate is reduced, the baffle plate can be protected by using the base plate which is easy to disassemble, and the abrasion of the baffle plate can be reduced.

Description

Galvanized pipe processing conveyor
Technical Field
The utility model relates to the technical field of galvanized pipe processing, in particular to a galvanized pipe processing and conveying device.
Background
The galvanized pipe is a corrosion-resistant pipe and is widely applied to the fields of buildings, machinery and the like. When the galvanized pipe is processed, the galvanized pipe needs to be conveyed into a processing machine, the existing conveying device can only convey the galvanized pipe with one specification, the conveying is inconvenient when pipes with different specifications exist, and the conveying length is measured every time when the pipes are conveyed into the processing machine, so that the galvanized pipe can be processed.
The patent document of current grant publication No. CN 214568961U discloses a galvanized pipe processing conveyor, belongs to galvanized pipe processing technical field. A galvanized pipe processing and conveying device comprises a base, wherein a first electric push rod is fixedly installed on one side inside the base, a lifting table is fixedly installed at the top of the first electric push rod, and a first supporting plate is fixedly installed inside the lifting table; when the galvanized pipe processing machine is used, the first electric push rod is firstly used for pushing the lifting platform to ascend, so that the rotating wheels are parallel to the processing machine, the galvanized pipe is taken to the middle parts of the two rotating wheels, the third electric push rod is started, the mounting box is pushed to be close to the galvanized pipe, the rotating wheels on the two sides are moved to the two sides of the galvanized pipe, the second electric push rod is used for pushing the bottom plate to move to the bottom of the galvanized pipe, the bottom of the galvanized pipe is supported, the galvanized pipe is prevented from falling off, during production, the first motor is started to drive the rotating wheels to rotate through the rotating shafts, the rotating wheels on the two sides of the galvanized pipe rotate in opposite directions, and the galvanized pipe is conveyed into the processing machine for processing.
But this scheme still has not enough, at first draw the baffle through the stay cord vertical, carry out the bottom sprag to the baffle through bracing piece and lead screw slide table, and the baffle must just can obtain more accurate galvanized pipe length with galvanized pipe tip in close contact with, the baffle is long-term atress easily makes the baffle wearing and tearing too fast or take place deformation, it is great to lead to galvanized pipe processing length error, secondly send into the galvanized pipe before blocking between two runners, lack the auxiliary stay to the galvanized pipe, handheld time is easy tired for a long time, make the galvanized pipe drop, cause galvanized pipe surface damage, lose rust-proof effect.
Therefore, it is necessary to provide a galvanized pipe processing and conveying device to solve the above technical problems.
SUMMERY OF THE UTILITY MODEL
The utility model solves the technical problem of providing a galvanized pipe processing and conveying device which can reduce the labor intensity, prevent the galvanized pipe from falling to cause damage, reduce the abrasion of a baffle and reduce the deformation possibility of the baffle.
In order to solve the technical problem, the utility model provides a galvanized pipe processing and conveying device, which comprises: the base, the fixed station that is used for fixed processingequipment is installed at the top of base, and one side of fixed station is equipped with first elevating platform, be equipped with the second elevating platform on the first elevating platform, install two track boards on the first elevating platform, install by first electronic jar driven install bin on the track board, install by motor drive's runner, two in the install bin the bracket is installed to one side of install bin, the both sides of bracket are respectively through two connecting plates and two the install bin rotates to be connected, one side of fixed station is equipped with the baffle, a side-mounting electric putter of baffle, a plurality of backing plates are installed to the joint on the baffle.
Preferably, the baffle is connected with a sliding plate, the sliding plate slides on two guide rods, and springs are mounted on the guide rods.
Preferably, the bracket includes the mount, the both sides of mount all through two connecting plates and two the install bin is connected, install the alignment jig on the mount, install first bearing wheel and accommodate the lead screw on the alignment jig.
Preferably, the base plate is provided with a convex block, the base plate is provided with a clamping groove matched with the convex block, and the clamping groove is matched with the baffle.
Preferably, one side of the base plate is provided with a limiting groove, and one side of the lug is provided with a limiting rod matched with the limiting groove.
Preferably, a second bearing wheel is installed on the second lifting platform.
Preferably, a second electric cylinder is installed at the bottom of the first lifting platform, and a third electric cylinder is installed at the bottom of the second lifting platform.
Compared with the prior art, the galvanized pipe processing and conveying device provided by the utility model has the following beneficial effects:
(1) through setting up the bracket, can play the auxiliary stay effect when carrying galvanized pipe, reduce intensity of labour, prevent that galvanized pipe from dropping and causing the damage, set up and the less baffle of galvanized pipe difference in height, reduce the deformation possibility of baffle, use quick detachable backing plate can play the guard action to the baffle, can reduce its wearing and tearing.
(2) Through setting up sliding plate, guide bar and spring, play the guide effect to the removal of baffle, can make galvanized pipe more stable when supporting the baffle simultaneously, galvanized pipe process length more accurate.
(3) But install height-adjusting's first bearing wheel through setting up, when can play the support to the galvanized pipe, adjust according to the specification of different galvanized pipes, make things convenient for runner and galvanized pipe adaptation.
(4) Through setting up lug and draw-in groove, make things convenient for the quick installation each other of backing plate and baffle and backing plate.
(5) The limiting rod and the limiting groove are arranged, so that the limiting and supporting effects on the base plate are achieved.
(6) Through setting up the second bearing wheel, can conveniently reduce the frictional force between second elevating platform and the galvanized pipe to the support and the removal of galvanized pipe, reduce the wearing and tearing on galvanized pipe surface.
(7) Through setting up electronic jar of second and the electronic jar of third, can provide power to first elevating platform and second elevating platform, make things convenient for the lift of first elevating platform and second elevating platform.
Drawings
FIG. 1 is a schematic structural diagram of a view angle of a galvanized pipe processing and conveying device provided by the utility model;
FIG. 2 is a schematic structural diagram of a view angle of the galvanized pipe processing and conveying device provided by the utility model;
FIG. 3 is a schematic structural diagram of a bracket in the galvanized pipe processing and conveying device shown in FIG. 1;
FIG. 4 is a schematic structural diagram of a backing plate in the galvanized pipe processing and conveying device shown in FIG. 1;
FIG. 5 is a schematic structural view of a second load-bearing wheel in the galvanized pipe processing and conveying device shown in FIG. 1;
fig. 6 is an assembly schematic diagram of the first lifting table and the second lifting table in the galvanized pipe processing and conveying device shown in fig. 1.
Reference numbers in the figures: 1. the base, 2, the fixed station, 3, first elevating platform, 4, the second elevating platform, 5, the bracket, 6, the connecting plate, 7, the install bin, 8, the track board, 9, the runner, 10, electric putter, 11, the baffle, 12, the sliding plate, 13, the guide bar, 14, the backing plate, 15, the spring, 16, first electronic jar, 17, the mount, 18, the alignment jig, 19, first bearing wheel, 20, accommodate the lead screw, 21, the lug, 22, the draw-in groove, 23, the gag lever post, 24, the spacing groove, 25, the second bearing wheel, 26, the electronic jar of second, 27, the electronic jar of third, 28, the motor.
Detailed Description
The utility model is further described with reference to the following figures and embodiments.
Example 1:
referring to fig. 1-6, in an embodiment of the present invention, a galvanized pipe processing and conveying apparatus includes: the galvanized pipe fixing device comprises a base 1, wherein a fixed platform 2 used for fixing a processing device is installed at the top of the base 1, a first lifting platform 3 is arranged on one side of the fixed platform 2, a second lifting platform 4 is arranged on the first lifting platform 3, two rail plates 8 are installed on the first lifting platform 3, an installation box 7 driven by a first electric cylinder 16 is installed on each rail plate 8, a rotating wheel 9 driven by a motor 28 is installed in each installation box 7, brackets 5 are installed on one sides of the two installation boxes 7, two sides of each bracket 5 are respectively in rotary connection with the two installation boxes 7 through two connecting plates 6, a baffle 11 is arranged on one side of the fixed platform 2, an electric push rod 10 is installed on one side of the baffle 11, a plurality of backing plates 14 are installed on the baffle 11 in a clamping mode, the number of the backing plates 14 is selected according to actual needs, when the galvanized pipe is used, the galvanized pipe penetrates through the brackets 5, the bottom of the pipe is supported and made to be flat through the rising of the second lifting platform 4, start two first electronic jars 16 and make two install bins 7 remove to the centre, block the galvanized pipe until two runner 5, adjust the height of first elevating platform 3, make the galvanized pipe highly suitable, starting motor 28 drive runner 5 rotates and drives the removal of plated venturi tube, carry the galvanized pipe, start electric putter 10 and make baffle 11 remove the tip position that makes backing plate 14 directly support the galvanized pipe, the moment of the power that baffle 11 received is less, non-deformable, the backing plate 14 of joint is convenient to be changed.
Through setting up bracket 5, can play the auxiliary stay effect when carrying galvanized pipe, reduce intensity of labour, improve and carry stability, prevent that galvanized pipe from dropping and causing the damage, set up with the less baffle 11 of galvanized pipe difference in height, reduce baffle 11's deformation possibility, use quick detachable backing plate 14 can play the guard action to baffle 11, can reduce its wearing and tearing.
Example 2:
as shown in fig. 1-2, the baffle plate 11 is connected with a sliding plate 12, the sliding plate 12 slides on two guide rods 13, and springs 15 are installed on the guide rods 13, when in use, the baffle plate 11 moves to drive the sliding plate 12 to move on the guide rods 13 and compress the springs 15, and the springs 15 and the electric push rod 10 fix the baffle plate 11 from two directions, so that the baffle plate 11 is prevented from shaking, and the galvanized pipe is more stable when abutting against the baffle plate 11.
Through setting up sliding plate 12, guide bar 13 and spring 15, play the guide effect to the removal of baffle 11, can make galvanized pipe more stable when supporting baffle 11 simultaneously, galvanized pipe processing length is more accurate.
Example 3:
as shown in fig. 1-3, the bracket 5 includes a fixing frame 17, both sides of the fixing frame 17 are connected to the two mounting boxes 7 through two connecting plates 6, an adjusting frame 18 is mounted on the fixing frame 17, a first bearing wheel 19 and an adjusting screw 20 are mounted on the adjusting frame 18, when in use, a galvanized pipe passes through the fixing frame 17 and is placed on the first bearing wheel 19, the adjusting screw 20 is rotated to enable the fixing frame 17 to ascend, the fixing frame 17 ascends to enable the first bearing wheel 19 to ascend so as to adjust the height of the galvanized pipe to be level with the rotating wheel 5, and when the two mounting boxes 7 approach, the connecting plates 6 rotate to enable the bracket 5 to be far away from the base 1.
But install height-adjusting's first bearing wheel 19 through the setting, when can playing the support to the galvanized pipe, adjust according to the specification of different galvanized pipes, make things convenient for runner 5 and galvanized pipe adaptation.
Example 4:
as shown in fig. 4, be equipped with lug 21 on the backing plate 14, set up on the backing plate 14 with the draw-in groove 22 of lug 21 adaptation, draw-in groove 22 with baffle 11 adaptation, during the use, the draw-in groove 22 of backing plate 14 aims at baffle 11 and puts down, with backing plate 14 joint on baffle 11, and similarly, the accurate lug 21 of draw-in groove 22 of more backing plates 14 puts down, can be with backing plate 14 and backing plate 14 joint.
The projection 21 and the slot 22 facilitate the rapid installation of the backing plate 14 and the baffle 11 and the backing plate 14 to each other.
Example 5:
as shown in fig. 4, a limiting groove 24 is formed in one side of the backing plate 14, a limiting rod 23 adapted to the limiting groove 24 is arranged on one side of the projection 21, and when the backing plates 14 are clamped with each other, the limiting rod 23 is clamped in the limiting groove 24 to limit the backing plate 24.
The limiting rod 23 and the limiting groove 24 are arranged to limit and support the backing plate 24.
Example 6:
as shown in fig. 5, a second bearing wheel 25 is installed on the second lifting platform 4, and when in use, the second bearing wheel 25 supports the bottom of the galvanized pipe, and the second bearing wheel 25 rotates along with the movement of the galvanized pipe.
Through setting up second bearing wheel 25, can conveniently reduce the frictional force between second elevating platform 4 and the galvanized pipe to the support and the removal of galvanized pipe, reduce the wearing and tearing on galvanized pipe surface.
Example 7:
as shown in fig. 6, a second electric cylinder 26 is mounted at the bottom of the first lifting platform 3, a third electric cylinder 27 is mounted at the bottom of the second lifting platform 4, and when in use, the second electric cylinder 26 is started to lift the first lifting platform, and the third electric cylinder 27 is started to lift the second lifting platform 4.
Through setting up second electronic jar 26 and third electronic jar 27, can provide power to first elevating platform 3 and second elevating platform 4, make things convenient for the lift of first elevating platform 3 and second elevating platform 4.
The working principle of the galvanized pipe processing and conveying device provided by the utility model is as follows:
firstly, a galvanized pipe passes through a fixed frame 17 and is placed on a first bearing wheel 19, an adjusting screw rod 20 is rotated to enable the fixed frame 17 to ascend, the fixed frame 17 ascends to enable the first bearing wheel 19 to ascend so as to adjust the height of the galvanized pipe to be flush with the rotating wheel 5, a third electric cylinder 27 is started to ascend a second lifting platform 4, a second bearing wheel 25 is enabled to support the bottom of the galvanized pipe and enable the bottom to be flat, two first electric cylinders 16 are started to enable two installation boxes 7 to move towards the middle, at the moment, a connecting plate 6 rotates to enable a bracket 5 to be far away from a base 1 until two rotating wheels 5 clamp the galvanized pipe, a second electric cylinder 26 is started to enable the height of a first lifting platform 3 to enable the galvanized pipe to be proper (consistent with the processing height of a processing device), a motor 28 is started to drive the rotating wheels 5 to rotate to drive a galvanized pipe to move to convey the galvanized pipe, an electric push rod 10 is started to enable a baffle plate 11 to move to enable a backing plate 14 to move to reach the processing length of the galvanized pipe, galvanized pipe removes and directly supports baffle 11, and the moment of force that baffle 11 received is less, non-deformable, and the backing plate 14 of joint is convenient to be changed, uses first bearing wheel 19 and second bearing wheel 25 to support galvanized pipe, has reduced intensity of labour, improves galvanized pipe and carries stability.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the utility model, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (7)

1. A galvanized pipe processing conveyor, its characterized in that includes:
the processing device comprises a base (1), a fixed platform (2) used for fixing a processing device is installed at the top of the base (1), a first lifting platform (3) is arranged on one side of the fixed platform (2), a second lifting platform (4) is arranged on the first lifting platform (3), two track plates (8) are installed on the first lifting platform (3), an installation box (7) driven by a first electric cylinder (16) is installed on each track plate (8), a rotating wheel (9) driven by a motor (28) is installed in each installation box (7), a bracket (5) is installed on one side of each installation box (7), two sides of each bracket (5) are rotatably connected with the two installation boxes (7) through two connecting plates (6) respectively, a baffle (11) is arranged on one side of the fixed platform (2), an electric push rod (10) is installed on one side of the baffle (11), and a plurality of backing plates (14) are clamped on the baffle (11).
2. The galvanized pipe processing and conveying device according to claim 1, characterized in that the baffle plate (11) is connected with a sliding plate (12), the sliding plate (12) slides on two guide rods (13), and springs (15) are mounted on the guide rods (13).
3. The galvanized pipe processing and conveying device according to claim 1, characterized in that the bracket (5) comprises a fixed frame (17), both sides of the fixed frame (17) are connected with the two mounting boxes (7) through two connecting plates (6), an adjusting frame (18) is mounted on the fixed frame (17), and a first bearing wheel (19) and an adjusting screw rod (20) are mounted on the adjusting frame (18).
4. The galvanized pipe processing and conveying device according to claim 1, characterized in that a bump (21) is arranged on the backing plate (14), a clamping groove (22) matched with the bump (21) is formed in the backing plate (14), and the clamping groove (22) is matched with the baffle (11).
5. The galvanized pipe processing and conveying device according to claim 4, characterized in that one side of the backing plate (14) is provided with a limiting groove (24), and one side of the projection (21) is provided with a limiting rod (23) matched with the limiting groove (24).
6. The galvanized pipe processing and conveying device according to claim 1, characterized in that a second bearing wheel (25) is mounted on the second lifting platform (4).
7. The galvanized pipe processing and conveying device according to claim 1, characterized in that a second electric cylinder (26) is installed at the bottom of the first lifting platform (3), and a third electric cylinder (27) is installed at the bottom of the second lifting platform (4).
CN202123322874.3U 2021-12-28 2021-12-28 Galvanized pipe processing conveyor Active CN216888872U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123322874.3U CN216888872U (en) 2021-12-28 2021-12-28 Galvanized pipe processing conveyor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123322874.3U CN216888872U (en) 2021-12-28 2021-12-28 Galvanized pipe processing conveyor

Publications (1)

Publication Number Publication Date
CN216888872U true CN216888872U (en) 2022-07-05

Family

ID=82209357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123322874.3U Active CN216888872U (en) 2021-12-28 2021-12-28 Galvanized pipe processing conveyor

Country Status (1)

Country Link
CN (1) CN216888872U (en)

Similar Documents

Publication Publication Date Title
CN106315207A (en) Conveying and lifting mechanism for laser-cut steel plates
CN216888872U (en) Galvanized pipe processing conveyor
CN111476051A (en) Optical module production bar code reading device
CN109607209B (en) Steel pipe receiving mechanism
CN211966780U (en) Discharging equipment for aluminum alloy section
CN202861252U (en) Automatic material receiving and distributing device of long-U-shaped copper pipe bending machine
CN215438371U (en) Drift diameter gauge conveying device for cleaning oil pipe
CN215984419U (en) Bar straightness detection device
CN202861253U (en) Automatic material collecting device of long-U-shaped copper pipe bending machine
CN103769493B (en) Long U-shaped Copper pipe bender automatic material connection dispenser
CN210392443U (en) Full-automatic plate conveying and feeding device
CN214003494U (en) Automatic equipment of rolling up of cloth
CN103769494B (en) The automatic material-gathering device of long U-shaped Copper pipe bender
CN211140718U (en) Continuous conveying device for electroplating of automobile ornaments
CN211103720U (en) Copper bar mounting tool for high-low voltage power distribution cabinet
CN209777393U (en) directional circulation material rack of material box
CN208483897U (en) A kind of electrothermal tube cutter device
CN219584657U (en) Lifting centering mechanism
CN214568961U (en) Galvanized pipe processing conveyor
CN110775610A (en) Balancing piece storage feeding device
CN111392423A (en) Glass plate blanking conveying table
CN217295885U (en) Synchronous type conveying device for electronic product detection
CN219991054U (en) Coating transportation lifting platform for coating production
CN210914369U (en) Glass conveying and positioning device
CN216303905U (en) Heat treatment device with heat dissipation function for high-strength stainless steel processing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant