Prior art keywords
supporting rod
base
suspension cable
lifter
wallboard installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121991857.6U
Other languages
Chinese (zh)
Inventor
姚娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Shunde District Jiatule Hengrong Building Decoration Co ltd
Original Assignee
Foshan Shunde District Jiatule Hengrong Building Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Shunde District Jiatule Hengrong Building Decoration Co ltd filed Critical Foshan Shunde District Jiatule Hengrong Building Decoration Co ltd
Priority to CN202121991857.6U priority Critical patent/CN215626205U/en
Application granted granted Critical
Publication of CN215626205U publication Critical patent/CN215626205U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an ALC wallboard installation auxiliary crane device, which comprises a base, wherein a lifter and a supporting rod are arranged on the base, and the supporting rod is a liftable telescopic supporting rod; a pulley is arranged at the top end of the supporting rod, the elevator is connected with a suspension cable, the suspension cable is hung down from the other side of the supporting rod after bypassing the pulley, and one end of the hanging suspension cable is connected with a clamp hanging tong; an inclination alarm is also arranged on the base; the bottom of the base is provided with trundles, the tail of the base is provided with a push handle, and an object placing space is reserved between the push handle and the lifter and/or the supporting rod. The utility model can be directly installed on site, has simple and easy manufacture, is light and flexible, and the telescopic design of the supporting rod can be telescopic along with the height of the building so as to meet the height requirement of multiple floors; the hoisting equipment adopts the clamp hanging tongs, can clamp more tightly during hoisting, ensures the safety of wallboard hoisting, improves the convenience of hoisting operation, and greatly improves the efficiency of wallboard installation operation.

Description

Auxiliary crane device for ALC wallboard installation
Technical Field
The utility model belongs to the technical field of hoisting devices, and particularly relates to a material hoisting device mainly used for wall building engineering.
Background
ALC is a short term for Autoclaved Lightweight aerated Concrete (Autoclaved Lightweight Concrete), and is a novel green environment-friendly building material which is mainly prepared by adding aluminum powder serving as an air-entraining agent into ingredients of calcareous materials (such as cement and lime) and siliceous materials (such as sand and slag), adding water, stirring, casting and molding, carrying out gas generation expansion, precuring and cutting, and carrying out high-pressure steam curing. The density of the cement is smaller than that of common cement materials, and the cement has good performances of fire resistance, fire prevention, sound insulation, heat preservation and the like.
ALC wall materials can be divided into an outer wall, an inner wall and a floor slab, an ALC strip slab is mostly used for the outer wall, reinforcing steel bars are implanted into the strip slab, the arrangement thickness and the density of the reinforcing steel bars can be customized according to building requirements, and the reinforcing steel bars are not needed for the sizing slab. The minimum specification size of ALC strip template is generally 600mm wide, high 1200mm, just can satisfy the size requirement of assembled wall board, but it is very laboursome to lift up or carry the wall to install by the manual work in the installation, and the potential safety hazard is very big. Therefore, the ALC wallboard must be installed by a lifting machine or a crane for auxiliary installation, so that the load of manual installation is reduced, and the installation efficiency is improved. However, the existing mechanical elevators, cranes and other equipment installed on the ALC wallboard are limited by site conditions, so that the advantages of the mechanical auxiliary tools cannot be exerted. Meanwhile, the structure of the existing equipment is very complex, and the operation such as moving, using and the like is not convenient enough.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects in the prior art, the utility model provides the ALC wallboard installation auxiliary crane device which is simpler in structure, more reasonable in design, stable in structure and convenient to operate.
In order to solve the technical problems, the utility model adopts the following technical scheme: the utility model provides a supplementary crane device of ALC wallboard installation which characterized in that: the lifting device comprises a base, wherein a lifter and a supporting rod are arranged on the base, and the supporting rod is a lifting telescopic supporting rod; a pulley is installed at the top end of the support rod, the elevator is connected with a suspension cable, the suspension cable bypasses the pulley and then hangs down from the other side of the support rod, and one end, which hangs down, of the suspension cable is connected with a clamp hanging tong for clamping an ALC wallboard; an inclination alarm for monitoring the inclination state of the base is also arranged on the base; the bottom of the base is provided with a caster which is convenient for the whole crane device to move, the tail part of the base is provided with a push handle for pushing the whole crane device to move, and an object placing space is reserved between the push handle and the lifter and/or the supporting rod.
Furthermore, a cross bar is fixed at the top end of the supporting rod, and the extension direction of the cross bar is parallel to a connecting line between the lifter and the supporting rod; the pulleys are directional pulleys, the left end and the right end of the cross rod are respectively provided with a directional pulley, and the suspension cable is pulled to the directional pulley close to one side of the elevator, then wound to the directional pulley at the other side and hung downwards. Therefore, the suspension cable is actually propped open through the cross rod, so that the wall plate is far away from the crane as far as possible in the hoisting process, accidents such as collision are avoided, and the safety and convenience of operation are improved.
Furthermore, an inclined strut is fixed on the periphery of the lower portion of the supporting rod and connected and fixed with the base to form a lateral supporting structure for the supporting rod, so that the supporting rod is guaranteed to have higher stability, and the safety of the hoisting process is improved.
Furthermore, inclined support rods are respectively fixed on the left side and the right side of the upper portion of each support rod, and the top ends of the two inclined support rods are respectively connected and fixed with the cross rod to form a reinforced support structure for the cross rod, so that the cross rod has stronger supporting capacity for the suspension cable.
Furthermore, a lifting hook is fixed at one suspended end of the suspension cable, and the clamp hanging tongs are hung on the lifting hook. Therefore, the clamp hanging tongs with corresponding models can be replaced according to different specifications of the wallboard, and the best matching effect is achieved.
Furthermore, the object placing space is arranged between the pushing handle and the lifter, and the supporting rod is positioned on the outer side of the lifter; the counterweight block is arranged in the storage space and is of a split modular structure, the weight of each counterweight block is 10-20 kg, and the counterweight block is fixed on the base through bolts. Can be according to the quantity of laying the balancing weight for the wallboard weight that will lift by crane like this to avoid causing extra burden, ensure simultaneously that the crane can not turn on one's side. Meanwhile, the wall boards on the site can be directly placed at the object placing space to serve as the balance weight, so that the balance weight transportation cost can be saved.
Furthermore, the four trundles are arranged at positions close to four corners of the base respectively, and at least one trundle is provided with a brake device, so that the whole crane device can be parked conveniently.
Preferably, the hoist cable is a steel wire rope.
The utility model can be directly installed on site, has simple and easy manufacture, is light and flexible, and the telescopic design of the supporting rod can be telescopic along with the height of the building so as to meet the height requirement of multiple floors; the whole locomotive equipment mass is about 60 kg, and the carrying is easy, and the power transmission is convenient. The hoisting equipment adopts the clamp hanging tongs, the heavier the hoisted wallboard or brick body is, the tighter the wallboard is, the safety of wallboard hoisting is ensured, the convenience of hoisting operation is improved, one worker can operate the crane, two workers can complete the installation operation of the wallboard, and the efficiency of wallboard installation operation is greatly improved.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
In the figure, 1 is a base, 2 is a lifter, 3 is a support rod, 4 is a cross rod, 5 is a suspension cable, 6 is a directional pulley, 7 is a lifting hook, 8 is a clamp hanging tong, 9 is an inclination alarm, 10 is an inclined strut, 11 is an inclined strut, 12 is a push handle, 13 is a balancing weight, and 14 is a caster.
Detailed Description
In this embodiment, referring to fig. 1, the ALC wall panel installation auxiliary crane apparatus includes a base 1, a lift 2 and a support rod 3 are installed on the base 1, and the support rod 3 is a telescopic support rod capable of ascending and descending; a pulley is arranged at the top end of the support rod 3, the elevator 2 is connected with a suspension cable 5, the suspension cable 5 winds around the pulley and then hangs down from the other side of the support rod 3, and one end, which hangs down, of the suspension cable 5 is connected with a clamp hanging tong 8 for clamping an ALC wallboard; an inclination alarm 9 for monitoring the inclination state of the base 1 is further arranged on the base 1, when the inclination angle of the base 1 exceeds a set value, the inclination alarm 9 gives an alarm to prompt an operator to correct or prepare for danger avoidance; the bottom of the base 1 is provided with a caster 14 which is convenient for the whole crane device to move, the tail of the base 1 is provided with a push handle 12 which is used for pushing the whole crane device to move, and an object placing space is reserved between the push handle 12 and the lifter 2 and can be used for placing a counter weight or placing a wallboard.
A cross bar 4 is fixed at the top end of the support bar 3, and the extension direction of the cross bar 4 is parallel to the connecting line between the lifter 2 and the support bar 3; the pulleys are directional pulleys 6, the left end and the right end of the cross rod 4 are respectively provided with a directional pulley 6, and the suspension cable 5 is drawn to the directional pulley 6 close to one side of the lifter 2, wound to the directional pulley 6 at the other side and hung downwards. Therefore, the hoisting cable 5 is actually propped open through the cross rod 4, so that the wall plate is far away from the crane as far as possible in the hoisting process, accidents such as collision are avoided, and the safety and convenience of operation are improved.
The lower part of the supporting rod 3 is fixed with an inclined strut 10 around, and the inclined strut 10 is connected and fixed with the base 1 to form a lateral supporting structure for the supporting rod 3, so that the supporting rod 3 is ensured to have higher stability, and the safety of the hoisting process is improved.
Inclined supporting rods 11 are respectively fixed on the left side and the right side of the upper portion of the supporting rod 3, and the top ends of the two inclined supporting rods 11 are respectively connected and fixed with the cross rod 4 to form a reinforced supporting structure for the cross rod 4, so that the supporting capacity of the cross rod 4 for the suspension cable 5 is stronger.
A lifting hook 7 is fixed at the suspended end of the suspension cable 5, and a clamp hanging tong 8 is hung on the lifting hook 7. So can come the anchor clamps tong 8 of the corresponding model of suit according to the different specifications of wallboard, realize the best matching effect. Meanwhile, the clamp hanging tongs 8 can be conveniently taken down for storage, and damage caused by collision is avoided.
The storage space is arranged between the push handle 12 and the lifter 2, and the support rod 3 is positioned at the outer side of the lifter 2 (close to the front end of the base 1); the counterweight block 13 is arranged in the storage space, the counterweight block 13 is of a split modular structure, the weight of each counterweight block is 10-20 kg, and the counterweight block 13 is fixed on the base 1 through bolts. Can be according to the quantity of laying the balancing weight for the wallboard weight that will lift by crane like this to avoid causing extra burden, ensure simultaneously that the crane can not turn on one's side. Meanwhile, the wall boards on the site can be directly placed at the object placing space to serve as the balance weight, so that the balance weight transportation cost can be saved.
The four casters 14 are disposed at positions close to four corners of the base 1, and at least one of the casters 14 is provided with a brake device, so that the whole crane apparatus can be parked.
The suspension cable 5 is a steel wire rope.
The present invention has been described in detail, and it should be understood that the detailed description and specific examples, while indicating the preferred embodiment of the utility model, are intended for purposes of illustration only and are not intended to limit the scope of the utility model.

Claims (8)

1. The utility model provides a supplementary crane device of ALC wallboard installation which characterized in that: the lifting device comprises a base, wherein a lifter and a supporting rod are arranged on the base, and the supporting rod is a lifting telescopic supporting rod; a pulley is installed at the top end of the support rod, the elevator is connected with a suspension cable, the suspension cable bypasses the pulley and then hangs down from the other side of the support rod, and one end, which hangs down, of the suspension cable is connected with a clamp hanging tong for clamping an ALC wallboard; an inclination alarm for monitoring the inclination state of the base is also arranged on the base; the bottom of the base is provided with a caster which is convenient for the whole crane device to move, the tail part of the base is provided with a push handle for pushing the whole crane device to move, and an object placing space is reserved between the push handle and the lifter and/or the supporting rod.
2. The ALC wallboard installation assist crane assembly of claim 1, wherein: a cross bar is fixed at the top end of the supporting rod, and the extension direction of the cross bar is parallel to a connecting line between the lifter and the supporting rod; the pulleys are directional pulleys, the left end and the right end of the cross rod are respectively provided with a directional pulley, and the suspension cable is pulled to the directional pulley close to one side of the elevator, then wound to the directional pulley at the other side and hung downwards.
3. The ALC wallboard installation assist crane assembly of claim 1, wherein: an inclined strut is fixed around the lower part of the supporting rod and is connected and fixed with the base to form a lateral supporting structure for the supporting rod.
4. The ALC wallboard installation assist crane assembly of claim 2, wherein: the left side and the right side of the upper part of the support rod are respectively fixed with an inclined support rod, and the top ends of the two inclined support rods are respectively connected and fixed with the cross rod to form a reinforced support structure for the cross rod.
5. The ALC wallboard installation assist crane assembly of claim 1, wherein: a lifting hook is fixed at one suspended end of the suspension cable, and a clamp hanging tong is hung on the lifting hook.
6. The ALC wallboard installation assist crane assembly of claim 1, wherein: the object placing space is arranged between the push handle and the lifter, and the supporting rod is positioned on the outer side of the lifter; the counterweight block is arranged in the storage space and is of a split modular structure, the weight of each counterweight block is 10-20 kg, and the counterweight block is fixed on the base through bolts.
7. The ALC wallboard installation assist crane assembly of claim 1, wherein: the four trundles are arranged at positions close to four corners of the base respectively, and at least one trundle is provided with a brake device.
8. The ALC wallboard installation assist crane assembly of claim 1, wherein: the suspension cable is a steel wire rope.
CN202121991857.6U 2021-08-23 2021-08-23 Auxiliary crane device for ALC wallboard installation Active CN215626205U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121991857.6U CN215626205U (en) 2021-08-23 2021-08-23 Auxiliary crane device for ALC wallboard installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121991857.6U CN215626205U (en) 2021-08-23 2021-08-23 Auxiliary crane device for ALC wallboard installation

Publications (1)

Publication Number Publication Date
CN215626205U true CN215626205U (en) 2022-01-25

Family

ID=79901033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121991857.6U Active CN215626205U (en) 2021-08-23 2021-08-23 Auxiliary crane device for ALC wallboard installation

Country Status (1)

Country Link
CN (1) CN215626205U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115028100A (en) * 2022-07-21 2022-09-09 北京城建北方集团有限公司 Electric hoisting device for building ALC (autoclaved lightweight concrete) wallboard and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115028100A (en) * 2022-07-21 2022-09-09 北京城建北方集团有限公司 Electric hoisting device for building ALC (autoclaved lightweight concrete) wallboard and construction method thereof
CN115028100B (en) * 2022-07-21 2023-12-26 北京城建北方集团有限公司 Electric hoisting device for building ALC wallboard and construction method thereof

Similar Documents

Publication Publication Date Title
CN205955236U (en) Container formula of taking pulley platform of unloading of encorbelmenting
CN101177959A (en) Curtain wall unit hanging equipment and construction method thereof
CN106241618A (en) A kind of curtain wall profiles boom hoisting
CN111188497A (en) Autoclaved aerated concrete wallboard mounting construction machine tool and using method thereof
CN215626205U (en) Auxiliary crane device for ALC wallboard installation
CN202441045U (en) Rail-type electric attached lifting scaffold
CN208039864U (en) The attached lift-type discharging platform of Guiding Support Elevating Scaffold
CN206051364U (en) A kind of curtain wall profiles boom hoisting
CN206799012U (en) A kind of concrete batten transport of small space and installation tool group
CN102677907A (en) Method for manually installing steel beam at top of silo
CN214653190U (en) Adjustable portable lifting device
CN215248971U (en) Hoisting construction device for large-scale overweight electromechanical equipment of high-rise and super high-rise building
CN108483212A (en) Cladding glass installation self-control electric hoist hanger system and its hanging method
CN214326960U (en) Indoor equipment for existing high-rise building hoisting large-scale device
CN210855091U (en) Simple movable heavy object vertical lifting equipment
CN209760761U (en) Construction platform and elevator core section of thick bamboo construction structures in a core section of thick bamboo
CN210853369U (en) Protection device for vertical transportation building blocks of tower crane
CN211396549U (en) Telescopic folding elevator shaft construction operation platform
CN217710358U (en) Transverse connection and end beam self-propelled mounting trolley between reinforced concrete composite beam boxes
CN218405975U (en) Hoist stable prefabricated superimposed sheet
CN219031629U (en) Lifting equipment for indoor plate installation
CN214885625U (en) Multi-point prefabricated part mounting platform
CN216945838U (en) Building engineering polylith superimposed sheet handling instrument simultaneously
CN213569108U (en) Precast beam template hoist and mount system
CN220815137U (en) Multifunctional suspension cage suitable for chimney construction