CN206051364U - A kind of curtain wall profiles boom hoisting - Google Patents

A kind of curtain wall profiles boom hoisting Download PDF

Info

Publication number
CN206051364U
CN206051364U CN201621066694.XU CN201621066694U CN206051364U CN 206051364 U CN206051364 U CN 206051364U CN 201621066694 U CN201621066694 U CN 201621066694U CN 206051364 U CN206051364 U CN 206051364U
Authority
CN
China
Prior art keywords
support
boom hoisting
curtain wall
main outrigger
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621066694.XU
Other languages
Chinese (zh)
Inventor
李朝朋
肖仕浪
雷少华
贾竣淇
董磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201621066694.XU priority Critical patent/CN206051364U/en
Application granted granted Critical
Publication of CN206051364U publication Critical patent/CN206051364U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

This utility model provides a kind of curtain wall profiles boom hoisting, including first support and second support.Main outrigger is fixedly installed in first support and second support, stretch out second support and form vertical loading board in the end of main outrigger, the end of vertical loading board is used to hang weight, it is support bar that main outrigger is located at the part between first support and second support, length of the length of support bar more than vertical loading board, according to lever principle, with second support as fulcrum, the length of main outrigger lifting weight side can lift heavier object less than the length of opposite side.Boom hoisting is set in first support, and the fixed pulley that the steel wire penetrating lifting boom end of boom hoisting is arranged lifts weight.Hanging apparatus are placed in the floor specified, vertical loading board is reached into outside, boom hoisting is opened by operator after steel wire rope sag secured curtain wall section bar section bar is sling, be lifted into device place floor.The apparatus structure is simple, and small volume facilitates processing and manufacturing, not high to the site requirements of job site.

Description

A kind of curtain wall profiles boom hoisting
Technical field
This utility model is related to Architectural Equipment technical field, is furthermore to be related to a kind of curtain wall profiles to play lifting Put.
Background technology
Need various materials to be lifted to floor in building construction process, for later stage curtain wall construction, need ground Curtain wall exterior window be transported to designated floor upwards, traditional hanging method generally carries out vertical lifting using crane, is needing curtain The elevation of building side supporting crane of wall section bar lifting, by crane handling directly up;Or pass through a dead lift, plug-in electricity Ladder and indoor elevator vertical transport, by manual work by curtain wall profiles transport to corresponding position.
Carry out vertical lifting using crane, job site narrow field is unfavorable for supporting crane, job site personnel compared with Many, during using crane lifting, the weight of arm of crane and lifting has high potential safety hazard, and rents crane It is costly, it is unfavorable for reduces cost.The transport of a dead lift, plug-in elevator and indoor elevator is limited by elevator load bearing and space System, travelling speed are excessively slow, can affect the normal operation of other work posts, it is impossible to suitable for the engineering that the duration is nervous;And people's labour movement It is too high that defeated process takes human resourcess.
Utility model content
This utility model provides a kind of curtain wall profiles boom hoisting, and simple structure, low cost occupy little space, for hanging The curtain wall profiles of dress construction usage, reduce the occupancy of human resourcess.
A kind of curtain wall profiles boom hoisting, including first support and second support, the first support and described second Main outrigger is fixedly installed on frame, the end of the main outrigger is stretched out the second support and forms vertical loading board, and the main outrigger is located at Part between the first support and the second support is support bar, and the length of the support bar is more than the vertical loading board Length;Boom hoisting is set in the first support, and (end is arranged vertical loading board described in the steel wire penetrating of the boom hoisting Fixed pulley lifts weight.
Alternatively, the top vertical of the second support arranges stabiliser bar;The top of the stabiliser bar and the main outrigger The first junction point cylinder lever connecting rod of one end, the top of the stabiliser bar are connected drawing with the second junction point of the main outrigger other end Bar.
Alternatively, the stabiliser bar passes through steel with first junction point, the stabiliser bar and second junction point Cord connects;The top of the stabiliser bar arranges fixed pulley, connects between first junction point and second junction point The fixed pulley on stabiliser bar top described in steel wire penetrating.
Alternatively, the main outrigger includes the outer tube and inner core of mutual sheathing, on the main outrigger arrange fixing device with The length of the fixation main outrigger.
Alternatively, multiple through holes are correspondingly opened up on the outer tube and the inner core, the main outrigger is inserted to by steady pin Adjustment length in different through holes.
Alternatively, in isosceles triangle, the drift angle of the second support arranges fixed pulley, the lifting to the second support Fixed pulley at second support drift angle described in the steel wire penetrating of device.
Alternatively, the end of the first support is fixedly installed balancing weight;Vertical bar is set in the first support, it is described Balancing weight inserting is arranged in the vertical bar.
Alternatively, the boom hoisting is electrical hoist;Control is provided on the support of the first support described The control chamber of electrical hoist.
Alternatively, the first support is removable by bolt with the main outrigger with the main outrigger, the second support Unload fixation.
Alternatively, the main outrigger is in horizontally disposed or is inclined upwardly towards the vertical loading board.
This utility model provides a kind of curtain wall profiles boom hoisting, including first support and second support, first support It is positioned on ground with second support, whole device is supported.Master is fixedly installed in first support and second support to choose Beam, main outrigger play lifting, and the end of main outrigger is stretched out second support and forms vertical loading board, and the end of vertical loading board is used to hang Weight, it is support bar that main outrigger is located at the part between first support and second support, and the length of support bar is more than vertical loading board Length, according to lever principle, with second support as fulcrum, the length of main outrigger lifting weight side is less than the length of opposite side, Heavier object can be lifted.Boom hoisting is set in first support, and the steel wire penetrating lifting boom end of boom hoisting sets The fixed pulley lifting weight put.
Hanging apparatus are placed in the edge of the floor specified, vertical loading board is reached into outside, steel wire rope sag secured curtain wall Boom hoisting is opened by operator after section bar section bar is sling, be transported to device place floor.The lifting that this utility model is provided Apparatus structure is simple, and small volume facilitates processing and manufacturing, and the place space requirement to job site is not high.
Description of the drawings
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below will be to embodiment Or accompanying drawing to be used is briefly described needed for description of the prior art, it should be apparent that, drawings in the following description are only It is some embodiments of the present utility model, for those of ordinary skill in the art, in the premise for not paying creative work Under, can be with according to these other accompanying drawings of accompanying drawings acquisition.
Fig. 1 is a kind of structural representation of concrete setting form of the application curtain wall profiles boom hoisting;
Fig. 2 is construction profile;
Fig. 3 is the axonometric drawing of another angle;
Fig. 4 is the demonstration graph using process.
Wherein:
First support 1, balancing weight 11, control chamber 12, second support 2, stabiliser bar 21, main outrigger 3, vertical loading board 31, support Bar 32, the first junction point 301, the second junction point 302, boom hoisting 4.
Specific embodiment
Core of the present utility model is to provide a kind of curtain wall profiles boom hoisting, and simple structure, low cost take up room It is few, for the curtain wall profiles that lifting construction is used, reduce the occupancy of human resourcess.
In order that those skilled in the art more fully understands the technical solution of the utility model, below in conjunction with accompanying drawing and Specific embodiment, is described in detail explanation to the curtain wall profiles boom hoisting of the application.
As shown in figure 1, for a kind of structural representation of concrete setting form of the application curtain wall profiles boom hoisting;Fig. 2 is Construction profile;Fig. 3 is the axonometric drawing of another angle.The boom hoisting includes first support 1 and second support 2, first support 1 Dispose on the ground with second support 2, whole device is played a supportive role.Master is fixedly installed in first support 1 and second support 2 Outrigger 3, can be fixed on the top of first support 1 and second support 2, and 3 main body of main outrigger is extended laterally.The difference of opsition dependent, 3 points of main outrigger is two sections, respectively vertical loading board 31 and support bar 32;Stretch out second support 2 and form vertical loading board in the end of main outrigger 3 31, it is support bar 32 that main outrigger 3 is located at the part between first support 1 and second support 2, and the end of vertical loading board 31 is through lifting Steel wire rope.The length of support bar 32, is hung with second support 2 as fulcrum according to lever principle more than the length of vertical loading board 31 One side length of dress weight is less than another side length, more objects of can slinging.Curtain wall profiles are lifted by steel wire rope, first Boom hoisting 4 is set on support 1, and the fixed pulley that 31 end of steel wire penetrating vertical loading board of boom hoisting 4 is arranged lifts weight, weight Thing can be the construction materials such as curtain wall profiles.
The curtain wall profiles boom hoisting simple structure that this utility model is provided, agent structure are first support 1, second support 2 and main outrigger 3, occupy little space, low cost of manufacture, hoisting process are not take up excessive human resourcess, accelerate lifting construction progress.
On this basis, the top vertical in second support 2 arranges stabiliser bar 21, and stabiliser bar 21 is arranged on second support 2 Top, provides support force vertically upward by second support 2.When weight is lifted, main outrigger 3 is subject to larger moment of flexure, in order that The moment of flexure of main outrigger 3 is resisted, in 301 cylinder lever connecting rod of the first junction point of the top of stabiliser bar 21 and 3 one end of main outrigger, stabiliser bar Second junction point, 302 cylinder lever connecting rod of 21 top and 3 other end of main outrigger.Pull bar respectively with the first junction point 301 and second Junction point 302 is fixedly connected, and is inclined to set, and the two ends of main outrigger 3 can be provided with component upwards, main outrigger 3 is reduced and received The moment of flexure for arriving.Pull bar is provided support force upwards by the stabiliser bar 21 in second support 2, and support force is delivered to master by pull bar and chooses The two ends of beam 3.
Specifically, stabiliser bar 21 and the first junction point 301, stabiliser bar 21 and the second junction point 302 are connected by steel wire rope Connect, by steel wire rope as pull bar.Steel wire between first junction point 301 and stabiliser bar 21, the second junction point 302 and stabiliser bar 21 Rope can be complete one section, and alternatively two sections, the present embodiment here is preferably set to one section.Arrange on the top of stabiliser bar 21 Fixed pulley, the fixed pulley on 21 top of steel wire penetrating stabiliser bar connected between the first junction point 301 and the second junction point 302. The length of steel wire rope is fixed, and two ends are connected to the two ends of main outrigger 3, middle part by 21 jack-up of stabiliser bar with provide upwards Support force, can specifically adopt the steel wire rope of φ 14.Certainly, above-mentioned situation is only preferred embodiment, and pull bar also can select rigid Straight-bar.
In any of the above-described technical scheme and its on the basis of being mutually combined, main outrigger 3 includes the outer tube of mutual sheathing and interior Cylinder, arranges fixing device with the length of fixed main outrigger 3 on main outrigger 3.3 points of main outrigger for two sections of advantage is, one be can To adjust the distance between first support 1 and second support 2, two is easy disassembly connection.
Specifically, on outer tube and inner core, correspondence opens up multiple through holes, and main outrigger 3 is inserted to different through holes by steady pin Interior adjustment length.The flexible of outer tube and inner core is adjusted, the through hole of diverse location on the outer tube and inner core of main outrigger 3 is relative, insert Fill steady pin to realize the fixation of length.The main part of main outrigger 3 is rectangular steel pipe, and two ends adopt the square of 120*120*4mm , used as outer tube, the rectangular steel pipe of one 100*100*4mm of middle grafting is used as inner core, middle steel pipe and two ends outer tube for shape steel pipe One of them is welded and fixed, corresponding on outer tube of the inner core with the other end to open up through hole.
Further, second support 2 is in isosceles triangle, and fixed pulley, lifting are arranged at the drift angle of the second support 2 of triangle Fixed pulley at 2 drift angle of steel wire penetrating second support of device 2, is then passed through the fixed pulley of 31 end of vertical loading board setting.Lifting The steel wire rope of device 2 forms obtuse angle by the fixed pulley at 2 drift angle of second support, reduces the length of every section of steel wire rope, so that steel Cord is more stable when pulling.
The end of first support 1 is fixedly installed balancing weight 11, specifically, vertical bar is fixedly installed, matches somebody with somebody in first support 1 11 points of pouring weight is polylith, can insert one by one and be arranged in vertical bar.Balancing weight 11 can adopt cement block, in middle reserved insertion Hole.
Specifically, boom hoisting 4 be electrical hoist, driven by power steel wire rope pull weight.First support 1 has level Portion and vertical portion, are provided for controlling the control chamber 12 of electrical hoist on vertical support, and operator passes through control chamber 12 Control electrical hoist is rotated.Balancing weight 11 is arranged on the end of 1 horizontal part of first support, is arranged far from vertical loading board 31 as far as possible The position of end.
First support 1 is detachably fixed by bolt with main outrigger 3, second support 2 and main outrigger 3.In first support 1 Top arranges inserting frame, is also provided with inserting frame in second support 2, and main outrigger 3 can insert two inserting inframes respectively, and adopt Bolt is fixedly connected, and conveniently can dismantle.
Main outrigger 3 is in be horizontally disposed with, or is inclined upwardly towards the direction of vertical loading board 31.What this utility model was given plays lifting Put all parts all to make using rectangular steel pipe, between each steel part, 6mm full welds and be bolted fixation.Can select specified negative The electrical hoist for 2 tons is carried, the weight of balancing weight 11 is not less than 700kg.
As shown in figure 4, being the demonstration graph using process.Target is that curtain wall window is lifted into A layers, and device is placed in floor Edge, vertical loading board 31 is protruding, and curtain wall forms are transported to the first floor, the good steel wire rope of hook, by professional operation people with flat bogie Member's control electrical hoist is lifted, strict control lifting speed.To prevent hoisting process from being produced by extraneous factors such as wind-force Rock, at the floor below such as B, C, D, arrange personnel to carry out the measure for preventing forms from putting successively, it is to avoid with floor, stone material and dragon Bone produces collision.
Boom hoisting simple structure of the present utility model, flexibly can move, and easy accessibility is reusable, good economy performance, Excessive space is not take up, the man-hour of lifting is shortened.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or use that this practicality is new Type.Various modifications to these embodiments will be apparent for those skilled in the art, determined herein The General Principle of justice, can be realized in the case of without departing from spirit or scope of the present utility model in other embodiments.Cause This, this utility model is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein The most wide scope consistent with features of novelty.

Claims (10)

1. a kind of curtain wall profiles boom hoisting, it is characterised in that including first support (1) and second support (2), described first Main outrigger (3) is fixedly installed on frame (1) and the second support (2), the second support is stretched out in the end of the main outrigger (3) (2) vertical loading board (31), part of the main outrigger (3) between the first support (1) and the second support (2) are formed For support bar (32), the length of the length of the support bar (32) more than the vertical loading board (31);Set on the first support (1) Boom hoisting (4) is put, the fixed pulley lifting weight that vertical loading board (31) end described in the steel wire penetrating of the boom hoisting (4) is arranged Thing.
2. curtain wall profiles boom hoisting according to claim 1, it is characterised in that erect at the top of the second support (2) It is straight that stabiliser bar (21) is set;The top of the stabiliser bar (21) is connected with first junction point (301) of described main outrigger (3) one end Pull bar, the second junction point (302) cylinder lever connecting rod of the top of the stabiliser bar (21) and main outrigger (3) other end.
3. curtain wall profiles boom hoisting according to claim 2, it is characterised in that the stabiliser bar (21) and described first Junction point (301), the stabiliser bar (21) are connected by steel wire rope with second junction point (302);The stabiliser bar (21) top arranges fixed pulley, the steel wire rope connected between first junction point (301) and second junction point (302) Through the fixed pulley on the stabiliser bar (21) top.
4. the curtain wall profiles boom hoisting according to any one of claims 1 to 3, it is characterised in that main outrigger (3) bag The outer tube and inner core of mutual sheathing are included, fixing device is set on the main outrigger (3) with the length of the fixation main outrigger (3).
5. curtain wall profiles boom hoisting according to claim 4, it is characterised in that correspondence on the outer tube and the inner core Multiple through holes are opened up, the main outrigger (3) inserts the adjustment length in different through holes by steady pin.
6. curtain wall profiles boom hoisting according to claim 4, it is characterised in that the second support (2) is three in isosceles Angular, the drift angle of the second support (2) arranges fixed pulley, second support described in the steel wire penetrating of the boom hoisting (4) (2) fixed pulley at drift angle.
7. curtain wall profiles boom hoisting according to claim 4, it is characterised in that the end of the first support (1) is solid Balancing weight (11) is set surely;Vertical bar is set on the first support (1), and it is described vertical that balancing weight (11) inserting is arranged at On bar.
8. curtain wall profiles boom hoisting according to claim 7, it is characterised in that the boom hoisting (4) is electric rolling Raise machine;It is provided for controlling the control chamber (12) of the electrical hoist on the support of the first support (1).
9. curtain wall profiles boom hoisting according to claim 4, it is characterised in that the first support (1) and the master Outrigger (3), the second support (2) are detachably fixed by bolt with the main outrigger (3).
10. curtain wall profiles boom hoisting according to claim 4, it is characterised in that the main outrigger (3) is in horizontally disposed Or be inclined upwardly towards the vertical loading board (31).
CN201621066694.XU 2016-09-20 2016-09-20 A kind of curtain wall profiles boom hoisting Expired - Fee Related CN206051364U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621066694.XU CN206051364U (en) 2016-09-20 2016-09-20 A kind of curtain wall profiles boom hoisting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621066694.XU CN206051364U (en) 2016-09-20 2016-09-20 A kind of curtain wall profiles boom hoisting

Publications (1)

Publication Number Publication Date
CN206051364U true CN206051364U (en) 2017-03-29

Family

ID=58370755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621066694.XU Expired - Fee Related CN206051364U (en) 2016-09-20 2016-09-20 A kind of curtain wall profiles boom hoisting

Country Status (1)

Country Link
CN (1) CN206051364U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106241618A (en) * 2016-09-20 2016-12-21 中建八局第四建设有限公司 A kind of curtain wall profiles boom hoisting
CN110844796A (en) * 2019-11-08 2020-02-28 中铁二局集团有限公司 Interlayer crane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106241618A (en) * 2016-09-20 2016-12-21 中建八局第四建设有限公司 A kind of curtain wall profiles boom hoisting
CN110844796A (en) * 2019-11-08 2020-02-28 中铁二局集团有限公司 Interlayer crane

Similar Documents

Publication Publication Date Title
CN106241618A (en) A kind of curtain wall profiles boom hoisting
CN202000646U (en) Self-lifting construction platform integrating vertical transportation device and mould frame
CN103523683B (en) Construction method for dismantling tower crane by use of small hoisting equipment
CN102155089A (en) Self-jacking construction platform integrating vertical transportation equipment and mold base
CN103086279A (en) Vertical transportation construction method for building construction
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
CN206051364U (en) A kind of curtain wall profiles boom hoisting
CN206562264U (en) A kind of hanging device for transport outside high-rise building
CN214326960U (en) Indoor equipment for existing high-rise building hoisting large-scale device
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN108331335A (en) A kind of pre-splicing separation type hydraulic of steel and wood composite is from climbing support
CN215626205U (en) Auxiliary crane device for ALC wallboard installation
CN206646836U (en) A kind of exterior wall, inner partition plate movement lifting frame
CN206799012U (en) A kind of concrete batten transport of small space and installation tool group
CN214785847U (en) Be applied to hanging flower basket device of single structure concrete beam
CN211037771U (en) Hanging basket device for outer slope construction
CN111411624B (en) Hoisting method for reinforcement cage of underground continuous wall in height-limited area
CN209760761U (en) Construction platform and elevator core section of thick bamboo construction structures in a core section of thick bamboo
CN210195198U (en) Elevartor shaft moving platform
CN109516390B (en) Flat-head tower crane convenient for manual carrying and installation and field installation method
CN207633773U (en) A kind of glomeration building prefabricated construction reinforcing bar guiding tube dismounting system
CN219259304U (en) Adjustable auxiliary device for hoisting heavy objects in narrow space
CN107700854B (en) Steel plate wall sliding installation device and installation method for super high-rise core tube
CN107814318A (en) Loop wheel machine
CN216918357U (en) Hoisting device utilizing building internal structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170329

Termination date: 20210920