CN214725186U - Brick laying production line with high operation efficiency - Google Patents

Brick laying production line with high operation efficiency Download PDF

Info

Publication number
CN214725186U
CN214725186U CN202120108327.6U CN202120108327U CN214725186U CN 214725186 U CN214725186 U CN 214725186U CN 202120108327 U CN202120108327 U CN 202120108327U CN 214725186 U CN214725186 U CN 214725186U
Authority
CN
China
Prior art keywords
maintenance
conveying line
brick
frame
wet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120108327.6U
Other languages
Chinese (zh)
Inventor
洪锦勋
傅国华
傅鑫源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Quangong Machinery Co Ltd
Original Assignee
Quangong Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Quangong Machinery Co Ltd filed Critical Quangong Machinery Co Ltd
Priority to CN202120108327.6U priority Critical patent/CN214725186U/en
Application granted granted Critical
Publication of CN214725186U publication Critical patent/CN214725186U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model relates to a brick production line that operating efficiency is high, including block forming machine, wet brick board transfer chain, first maintenance lift, maintenance frame transfer chain, a plurality of maintenance kilns frame, second maintenance lift, dry brick board transfer chain and lamination machine, wet brick board transfer chain one end extends to block forming machine and the first maintenance lift is connected to the other end, each maintenance kilns frame is placed on maintenance frame transfer chain, corresponding maintenance kilns frame is all connected to first maintenance lift and second maintenance lift, the trend of the wet brick board transfer chain of direction of delivery perpendicular to of maintenance frame transfer chain and dry brick board transfer chain, second maintenance lift is connected to dry brick board transfer chain, lamination machine connects keeping away from second maintenance lift one side of dry brick board transfer chain, operating efficiency is high.

Description

Brick laying production line with high operation efficiency
Technical Field
The utility model relates to a building block former technical field especially relates to a production line of laying bricks that operating efficiency is high.
Background
1. The static curing brick production line with the curing frame is a brick production line with higher automation degree for the production of baking-free press-formed bricks, static curing bricks with the curing frame and the lamination of finished products;
2. in the traditional brick production line, after a brick pressing host presses and forms a brick shape, a laminating machine directly performs laminating action on a brick plate, the brick plate is laminated by an upper plate to press down bricks, so that the laminating machine can only be laminated to 3 layers, and the bottommost wet-blank bricks are crushed due to the overhigh layer number; and after lamination, the bricks are transported to a static curing area by a manual driving forklift for static curing, and the whole process from production to finishing is carried out.
The traditional brick production line has the following defects: (1) due to the low lamination of the brick plates, the occupied area of a static curing area is large, and the utilization rate of the field area is low; (2) after the plate stacking machine stacks 3 layers at each time, the forklift needs to convey stacked bricks, the forklift can only convey 3 plates of bricks at each time, the conveying efficiency is low, the back and forth time is long, the brick pressing main machine cannot continue to work before the forklift conveys out the bricks, the forklift stops to wait for the 3 plates of bricks to convey away, bricks can continue to be manufactured, the production efficiency is low, and the yield is poor.
SUMMERY OF THE UTILITY MODEL
For overcoming the technical defect that prior art exists, the utility model provides a production line of laying bricks that operating efficiency is high, operating efficiency is high.
The utility model discloses a technical solution be:
high-operation-efficiency brick laying production line comprises a block making machine, a wet brick plate conveying line, a first maintenance lifter, a maintenance frame conveying line, a plurality of maintenance kiln frames, a second maintenance lifter, a dry brick plate conveying line and a laminating machine, wherein one end of the wet brick plate conveying line extends to the block making machine, the other end of the wet brick plate conveying line is connected with the first maintenance lifter, the maintenance kiln frames are placed on the maintenance frame conveying line, the first maintenance lifter and the second maintenance lifter are connected with the corresponding maintenance kiln frames, the conveying direction of the maintenance frame conveying line is perpendicular to the direction of the wet brick plate conveying line and the direction of the dry brick plate conveying line, the dry brick plate conveying line is connected with the second maintenance lifter, and the laminating machine is connected with one side, away from the second maintenance lifter, of the dry brick plate conveying line.
As a further improvement of the utility model, a wet brick cleaning brush is arranged on the wet brick plate conveying line.
As a further improvement of the utility model, a dry brick cleaning brush is arranged on the dry brick plate conveying line.
As a further improvement of the utility model, the maintenance frame conveyer line includes first maintenance frame conveyer and second maintenance frame conveyer, the trend of first maintenance frame conveyer is connected with wet brick board conveyer line is perpendicular, the trend of second maintenance frame conveyer is connected with dry brick board conveyer line is perpendicular.
As a further improvement of the utility model, block forming machine's the wet brick board conveyer one side of keeping away from is equipped with tray transfer chain and tray storehouse, the tray storehouse is installed on the tray transfer chain and is equipped with the board passageway between tray storehouse and the tray transfer chain.
As a further improvement of the utility model, first maintenance frame conveyer and second maintenance frame conveyer are the drag chain conveyer.
The utility model has the advantages that:
one end of a wet brick plate conveying line extends to the block forming machine, the other end of the wet brick plate conveying line is connected with a first maintenance lifter, the wet brick plate conveying line is used for conveying a supporting plate output by the block forming machine and wet bricks on the supporting plate to the position of the first maintenance lifter, each maintenance kiln frame is placed on the maintenance frame conveying line, the maintenance kiln frames move along with the maintenance frame conveying line, the first maintenance lifter and the second maintenance lifter are connected with corresponding maintenance kiln frames, when empty maintenance kiln frames are conveyed to the first maintenance lifter, the maintenance lifter vertically lifts the supporting plate on the wet brick plate conveying line and the wet bricks and horizontally conveys the wet bricks to the maintenance kiln frames, a plurality of empty maintenance kiln frames are stored before the maintenance kiln frames are lifted, the maintenance frame conveying line is started after the maintenance kiln frames are filled, the next empty maintenance kiln frame is conveyed to the position of the first maintenance lifter, the block forming machine can continuously work, and no wet bricks are carried by the maintenance kiln frames, the maintenance kiln frame is required to be temporarily conveyed by a forklift to cause production halt, the production rhythm is kept, the conveying direction of the maintenance frame conveying line is perpendicular to the direction of the wet brick plate conveying line and the direction of the dry brick plate conveying line, the maintenance kiln frame can continue to move along with the maintenance frame conveying line on the maintenance frame conveying line after being filled with wet bricks, a forklift is required to move to take the maintenance kiln frame full of wet bricks for subsequent maintenance, the dry brick plate conveying line is connected with a second maintenance lifter, after maintenance is completed, the forklift puts the dry bricks which are completed with maintenance together with the carried maintenance kiln frame on the maintenance frame conveying line again, the maintenance kiln frame conveying line conveys the maintenance kiln frame full of dry bricks to the position of the second maintenance lifter, the second maintenance lifter horizontally outputs the supporting plate together with the dry bricks on the supporting plate and lowers the supporting plate onto the dry brick plate conveying line, the laminating machine is connected with one side, away from the second maintenance lifter, of the dry brick plate conveying line, and the dried brick plate conveying line conveys the dried bricks and the supporting plates to a plate stacking machine for stacking, and the plate stacking machine stacks the dried bricks and the supporting plates to prepare for stacking in the next process.
Drawings
Fig. 1 is a schematic overall plan view of the present invention.
Fig. 2 is a schematic view of direction a in fig. 1.
Fig. 3 is a schematic view of direction B in fig. 1.
Fig. 4 is a schematic view of the first maintenance lift.
Description of reference numerals:
1. a block forming machine; 2. a wet brick plate conveying line; 3. a first maintenance lift; 31. a maintenance machine lifting mechanism; 32. a maintenance machine translation mechanism; 33. a transfer fork; 4. a maintenance rack conveying line; 41. a first curing rack conveyor; 42. a second curing rack conveyor; 5. maintaining the kiln frame; 6. a second maintenance lift; 7. a dry brick plate conveying line; 8. a plate stacking machine; 91. a dry brick cleaning brush; 92. a wet brick cleaning brush; 93. and (4) a tray bin.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings:
as shown in FIGS. 1-4, the present embodiment provides a brick laying production line with high operation efficiency, which comprises a block making machine 1, a wet brick plate conveying line 2, a first maintenance lifter 3, a maintenance frame conveying line 4, a plurality of maintenance frames 5, a second maintenance lifter 6, a dry brick plate conveying line 7 and a laminating machine 8, wherein one end of the wet brick plate conveying line 2 extends to the block making machine 1, and the other end is connected with the first maintenance lifter 3, the wet brick plate conveying line 2 is used for conveying a supporting plate output by the block making machine 1 and wet bricks on the supporting plate to the position of the first maintenance lifter 3, each maintenance frame 5 is placed on the maintenance frame conveying line 4, the maintenance frame 5 moves along with the maintenance frame conveying line 4, the first maintenance lifter 3 and the second maintenance lifter 6 are both connected with the corresponding maintenance frame 5, when the empty maintenance frame 5 is conveyed to the first maintenance lifter 3, the first maintenance lifter 3 vertically lifts the supporting plate on the wet brick plate 2 and horizontally conveys the wet brick plate to the maintenance frame 3 On the kiln frame 5, because the maintenance frame transfer chain 4 is gone up and is advanced the storage and be equipped with a plurality of empty maintenance kiln frames 5, start maintenance frame transfer chain 4 after maintenance kiln frame 5 fills with, carry next empty maintenance kiln frame 5 to first maintenance lift 3 positions, make block forming machine 1 can the continuous operation, can not be because of not having maintenance kiln frame 5 to bear wet brick of laying, need wait for fork truck to carry maintenance kiln frame 5 temporarily and cause the stop production, keep the production beat, the direction of delivery of maintenance frame transfer chain 4 is perpendicular to the trend of wet brick board transfer chain 2 and dry brick board transfer chain 7, can follow maintenance frame transfer chain 4 on maintenance frame transfer chain 4 and continue the motion after maintenance kiln frame 5 fills with wet brick of laying, wait for the fork truck fork to walk and take advantage of the maintenance kiln frame 5 of wet brick of laying and carry out afterwards.
The dry brick plate conveying line 7 is connected with the second maintenance lifter 6, after maintenance is completed, the maintenance frame conveying line 4 conveys the maintained dry bricks and the supported maintenance kiln frame 5 to the position of the second maintenance lifter 6 again through a forklift, the second maintenance lifter 6 horizontally outputs and lowers the support plate and the dry bricks on the support plate onto the dry brick plate conveying line 7, the laminator 8 is connected with one side, far away from the second maintenance lifter 6, of the dry brick plate conveying line 7, the dry brick plate conveying line 7 conveys the dry bricks and the support plate to the laminator 8 for lamination, the laminator 8 stacks the dry bricks and the support plate to prepare stacking of the next procedure, the maintenance frame conveying line 4 comprises a first maintenance frame conveyor 41 and a second maintenance frame conveyor 42, the first maintenance frame conveyor 41 is vertically connected with the wet brick plate conveying line 2, the second curing frame conveyor 42 is vertically connected to the dry brick plate conveying line 7, and both the first curing frame conveyor 41 and the second curing frame conveyor 42 are chain plate conveyors.
Wherein the first maintenance lift 3 comprises a maintenance frame, curing machine elevating system 31, curing machine translation mechanism 32, the last transportation fork 33 that has of curing machine translation mechanism 32, curing machine elevating system 31 is along curing frame elevating movement, curing machine translation mechanism 32 is installed on curing machine elevating system 31 and is along curing machine elevating system 31 elevating movement, curing machine translation mechanism 32 drives transportation fork 33 horizontal motion, transportation fork 33 is driven by curing machine elevating system 31 and is driven the brick board vertical lifting that is located wet brick board transfer chain 2 and is sent into curing kiln frame 5 by curing machine translation mechanism 32 level, first curing lift 3 and second curing lift 6 are the same in structure, second curing lift 6 is no longer repeated here, second curing kiln frame 5 transports the brick board horizontal that is located curing kiln frame 5 out and is reduced to dry brick board transfer chain 7 by curing machine elevating system 31.
The laminator 8 comprises a laminating frame installed at the tail end of the dry brick plate conveying line 7 and a laminating lifting mechanism sliding horizontally along the laminating frame, the laminating lifting mechanism slides horizontally to the tail end of the dry brick plate conveying line 7 along the laminating frame, the laminating lifting mechanism lifts and horizontally conveys out the brick plates on the dry brick plate conveying line 7 for laminating, and the laminator 8 is not repeated in detail for the prior art.
The wet brick plate conveying line 2 is provided with a wet brick cleaning brush 92 for cleaning residues on wet bricks output from the block making machine 1 and ensuring the clean surfaces of the wet bricks, and the dry brick plate conveying line 7 is provided with a dry brick cleaning brush 91 for cleaning dry bricks after maintenance is completed.
The forklift forks empty curing kilns 5 onto a first curing frame conveyor 41 in advance, the first curing frame conveyor line 4 stops when conveying the empty curing kilns 5 to the position of a first curing lifter 3, the first curing lifter 3 conveys the bricks on a wet brick plate conveyor line 2 onto the curing kilns 5, and then the first curing lifter 3 starts to convey the next empty curing kiln 5 to the first curing lifter 3; fork truck will fill in advance the maintenance kiln frame 5 fork to the second maintenance frame conveyer 42 of the dry brick of accomplishing of maintenance, second maintenance frame conveyer line 4 stops when carrying the maintenance kiln frame 5 that fills with to the second maintenance lift 6 position, second maintenance lift 6 carries the brickwork on the maintenance kiln frame 5 to wet brickwork conveyer line 2, second maintenance lift 6 starts to carry next full maintenance kiln frame 5 to second maintenance frame lift department afterwards, because can carry a plurality of full maintenance kiln frames 5 on the second maintenance frame conveyer 42 simultaneously, fork truck can fork a plurality of maintenance kiln frames 5 that fill with the dry brick simultaneously and carry to 8 boards of board folding machine by dry brickwork conveyer line 7 again on second maintenance lift 6, guarantee that the dry brick on the maintenance kiln frame 5 unloads and in time is folded the board by 8 boards of board folding machine.
One side of the block making machine 1, which is far away from the wet brick plate conveying line 2, is provided with a tray conveying line and a tray bin 93, the tray bin 93 is installed on the tray conveying line, a plate passing channel is arranged between the tray bin 93 and the tray conveying line, and the tray bin 93 is used for conveying a supporting plate to the block making machine 1 in time.
Having shown and described the fundamental principles and the principal features of the invention and its advantages, it will be understood by those skilled in the art that the present invention is not limited by the embodiments described above, which are merely illustrative of the principles of the invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the invention as defined by the appended claims and their equivalents.

Claims (6)

1. The brick laying production line is high in operation efficiency and is characterized by comprising a block making machine, a wet brick plate conveying line, a first maintenance lifter, a maintenance frame conveying line, a plurality of maintenance kilns, a second maintenance lifter, a dry brick plate conveying line and a plate stacking machine, wherein one end of the wet brick plate conveying line extends to the block making machine, the other end of the wet brick plate conveying line is connected with the first maintenance lifter, the maintenance kilns are placed on the maintenance frame conveying line, the first maintenance lifter and the second maintenance lifter are connected with the corresponding maintenance kilns, the conveying direction of the maintenance frame conveying line is perpendicular to the trend of the wet brick plate conveying line and the trend of the dry brick plate conveying line, the dry brick plate conveying line is connected with the second maintenance lifter, and the plate stacking machine is connected with one side, far away from the second maintenance lifter, of the dry brick plate conveying line.
2. The brick laying production line with high operation efficiency according to claim 1, wherein the wet brick plate conveying line is provided with a wet brick cleaning brush.
3. The brick laying production line with high operation efficiency according to claim 1, wherein a dry brick cleaning brush is arranged on the dry brick plate conveying line.
4. The brick laying production line with high operation efficiency according to claim 1, wherein the curing frame conveying line comprises a first curing frame conveyor and a second curing frame conveyor, the direction of the first curing frame conveyor is vertically connected with the wet brick plate conveying line, and the direction of the second curing frame conveyor is vertically connected with the dry brick plate conveying line.
5. The brick laying production line with high operation efficiency according to any one of claims 1 to 4, wherein a tray conveying line and a tray bin are arranged on one side of the block making machine, which is far away from the wet brick plate conveyor, the tray bin is arranged on the tray conveying line, and a plate passing channel is arranged between the tray bin and the tray conveying line.
6. The bricklaying production line with high operating efficiency according to claim 4, wherein the first curing rack conveyor and the second curing rack conveyor are both drag conveyors.
CN202120108327.6U 2021-01-15 2021-01-15 Brick laying production line with high operation efficiency Expired - Fee Related CN214725186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120108327.6U CN214725186U (en) 2021-01-15 2021-01-15 Brick laying production line with high operation efficiency

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120108327.6U CN214725186U (en) 2021-01-15 2021-01-15 Brick laying production line with high operation efficiency

Publications (1)

Publication Number Publication Date
CN214725186U true CN214725186U (en) 2021-11-16

Family

ID=78639496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120108327.6U Expired - Fee Related CN214725186U (en) 2021-01-15 2021-01-15 Brick laying production line with high operation efficiency

Country Status (1)

Country Link
CN (1) CN214725186U (en)

Similar Documents

Publication Publication Date Title
CN214819539U (en) Building block production line convenient to maintenance
CN106241397B (en) Autoclave aerated concrete building block pallet-free stacking and stacking technology
CN102730220A (en) Novel full-automatic middle-small-size tile packaging production line
CN112340450B (en) Three-dimensional conveying device and method for plate glass production line
CN103287864B (en) Plate transporter
CN103407794A (en) Fully-automatic brick packing and unloading method for sintered bricks
CN110817448A (en) Fiberboard stacking device
CN214725186U (en) Brick laying production line with high operation efficiency
CN201703902U (en) Device for stacking plates on conveying line into pile
CN111517142A (en) Single-layer paperboard stacking and conveying device
EP1243532B1 (en) An apparatus for loading and unloading tiles from roller stillages
CN214988526U (en) Feeding mechanism, receiving mechanism and uninterrupted continuous sanding production line
CN210911192U (en) Feeding device of plywood hot-pressing laminating assembly line
CN210914411U (en) Stacking lifting device for oil sprayer packaging box
CN210285979U (en) Building block stacking output device
CN207417907U (en) A kind of square tube Palletizer
CN201225833Y (en) Brick-discharging roller platform
CN218344626U (en) Fragment of brick stays hole pile up neatly equipment
CN218662577U (en) Discharge structure of barrel supply bin
CN213264243U (en) Silicon wafer lifting and conveying device
CN210884121U (en) Automatic bottle stacking machine
CN218808200U (en) Blank storage warehouse
CN220731477U (en) Silicon chip loading attachment
CN114750251B (en) High-efficiency production method of hot-pressing integrated board circulating production line
CN216736123U (en) Tray arranging system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211116

CF01 Termination of patent right due to non-payment of annual fee