CN214462460U - Novel construction of building external scaffolding even wall spare device - Google Patents

Novel construction of building external scaffolding even wall spare device Download PDF

Info

Publication number
CN214462460U
CN214462460U CN202022800795.8U CN202022800795U CN214462460U CN 214462460 U CN214462460 U CN 214462460U CN 202022800795 U CN202022800795 U CN 202022800795U CN 214462460 U CN214462460 U CN 214462460U
Authority
CN
China
Prior art keywords
steel pipe
anchor
screw rod
template
novel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022800795.8U
Other languages
Chinese (zh)
Inventor
蔡昇烨
冯雁波
黄河
简廷新
杨鹏
缪俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN202022800795.8U priority Critical patent/CN214462460U/en
Application granted granted Critical
Publication of CN214462460U publication Critical patent/CN214462460U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a novel construction device for wall connecting pieces of external scaffolds for buildings, which comprises a prefabricated anchor piece, a positioning screw rod, a bolt, an anchor plate, a fixed steel pipe, a baffle, a wall body and a template, wherein the template is provided with a through hole, one end of the positioning screw rod passes through the through hole and is arranged inside the prefabricated anchor piece, the positioning screw rod and the prefabricated anchor piece are arranged on the template through nuts, the prefabricated anchor piece is arranged inside the template, one end of the anchor plate is provided with the through hole, the top and the bottom of the fixed steel pipe are symmetrically provided with sliding grooves, the inside of the fixed steel pipe is movably provided with an adjusting screw rod through a rotating shaft, the baffle is movably arranged on the fixed steel pipe through a sliding block and a connecting plate, the novel construction device for wall connecting pieces of external scaffolds for buildings can reduce waste and save resources, has simple structure and convenient use, and can be simultaneously suitable for used items, the construction efficiency can be improved.

Description

Novel construction of building external scaffolding even wall spare device
Technical Field
The utility model relates to a construction technical field specifically is a novel construction of outer scaffold frame of building even wall spare construction device.
Background
Even wall spare indicates to be connected construction scaffold frame and building engineering major structure, prevents the component that the outrigger topples, and tradition is even wall spare construction process and is: the steel pipe is embedded into the beam or the wall in advance before concrete pouring, the steel pipe is hinged with the other steel pipe through the rotary fastener, the steel pipe is connected with an external scaffold together, the steel pipe embedded in the traditional process is finally remained in the concrete, after the rotary fastener is loosened when the wall connecting piece is detached in the later stage, other steel pipes are detached, the steel pipe embedded into the beam or the inner protrusion of the wall needs to be cut off through a grinding machine, the hole is filled with mortar, the steel pipe embedded into the inner side is wasted, the cut steel pipe is shortened, the application is reduced, resource waste is caused, time and labor are wasted, and when the external scaffold is fixed, the rotary fastener slides easily, safety accidents are caused.
Therefore, the utility model provides a novel building outer scaffolding is wall spare construction even device.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a novel building outer scaffolding is wall spare construction even device to solve the problem that proposes in the above-mentioned background art, the utility model discloses need not pre-buried steel pipe inside the concrete, solve the steel pipe cutting, mend the extravagant scheduling problem of hole, as long as pre-buried prefabricated anchor piece, can realize the installation of even wall spare, external scaffold frame is fixed, and other components are whole can have enough to meet the need the use many times, and the environmental protection is practiced thrift.
In order to achieve the above purpose, the present invention is realized by the following technical solution: the utility model provides a novel construction of outer scaffold of building even wall spare device, includes prefabricated anchor, positioning screw, bolt, anchor slab, fixed steel pipe, baffle, wall body and template, the through-hole has been seted up on the template, positioning screw's one end is passed the through-hole and is installed the inside at prefabricated anchor, positioning screw and prefabricated anchor pass through the nut and install on the template, prefabricated anchor sets up the inside at the template, the through-hole has been seted up to anchor slab's one end, the spout has been seted up to the top and the bottom symmetry of fixed steel pipe, there is adjusting screw in the inside of fixed steel pipe through axis of rotation movable mounting, the baffle passes through slider and connecting plate movable mounting on fixed steel pipe.
As a preferred embodiment of the present invention, the anchor plate is installed on one side of the wall body by a bolt, and one end of the bolt is installed inside the prefabricated anchor.
As a preferred embodiment of the present invention, one end of the prefabricated anchor is provided with a fixing nut, one side of the fixing nut is provided with a stopper, and the prefabricated anchor is disposed inside the wall.
As an optimal implementation manner of the utility model, adjusting screw's one end is provided with the hand wheel, one side of hand wheel is provided with the limiting plate.
As an optimal implementation mode of the utility model, there is the slider inboard of baffle through connecting plate fixed mounting, the screw has been seted up to the central point department of putting of slider, slider movable mounting is on adjusting screw, the connecting plate slides and sets up the inside at the spout.
As a preferred embodiment of the present invention, the one end of the fixed steel pipe is welded to the bottom of one side of the anchor plate.
The utility model has the advantages that: the utility model relates to a novel construction of building external scaffolding even wall spare device includes prefabricated anchor piece, positioning screw, nut, fixation nut, dog, bolt, anchor slab, fixed steel pipe, adjusting screw, baffle, connecting plate, slider, screw, spout, wall body, template.
1. The device does not need pre-buried steel pipe, can save the manual work of cutting the steel pipe, saves steel, can improve the efficiency of construction, and the pre-buried prefabricated anchor of the device leaves the hole on wall body or roof beam body very little, and together handle during later stage fitment can, need not to spend manual work and material specially and go to repair labour saving and time saving.
2. All components of the device are produced in a factory in a standardized manner, can be used in all projects in a circulating manner, can be used for multiple times in one-time production, and is simple in structure, convenient to use and low in production cost.
3. The adjustment of baffle can be according to the fixed position of fixed steel pipe and outer scaffold frame, the stability of outer scaffold frame is improved.
Drawings
FIG. 1 is a schematic structural view of the novel construction device for the external scaffold wall connecting piece of the building;
FIG. 2 is a schematic cross-sectional view of the novel construction device for the wall connecting piece of the external scaffold for building of the present invention;
fig. 3 is a left side view of the novel construction external scaffold wall connecting piece construction device of the utility model;
fig. 4 is a left side view of the novel construction external scaffold wall connecting piece construction device of the utility model;
in the figure: 1. prefabricating an anchor; 2. positioning a screw rod; 3. a nut; 4. fixing a nut; 5. a stopper; 6. a bolt; 7. an anchor plate; 8. fixing the steel pipe; 9. adjusting the screw rod; 10. a baffle plate; 11. a connecting plate; 12. a slider; 13. a screw hole; 14. a chute; 15. a wall body; 16. and (5) template.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
Referring to fig. 1 to 4, the present invention provides a technical solution: the utility model provides a novel building external scaffolding is wall spare construction device even, includes prefabricated anchor 1, positioning screw 2, bolt 6, anchor slab 7, fixed steel pipe 8, baffle 10, wall body 15 and template 16, the through-hole has been seted up on the template 16, positioning screw 2's one end is passed the through-hole and is installed in the inside of prefabricated anchor slab 1, positioning screw 2 and prefabricated anchor slab 1 pass through nut 3 and install on template 16, prefabricated anchor slab 1 sets up the inside at template 16, the through-hole has been seted up to anchor slab 7's one end, spout 14 has been seted up to the top and the bottom symmetry of fixed steel pipe 8, there is adjusting screw 9 in the inside of fixed steel pipe 8 through axis of rotation movable mounting, baffle 10 passes through slider 12 and connecting plate 11 movable mounting on fixed steel pipe 8, simple to operate, easy operation.
As a preferred embodiment of the present invention, the anchor plate 7 is installed on one side of the wall 15 through the bolt 6, one end of the bolt 6 is installed inside the prefabricated anchor 1, and the anchor plate 7 is conveniently installed and disassembled.
As a preferred embodiment of the present invention, one end of the prefabricated anchor 1 is provided with a fixing nut 4, one side of the fixing nut 4 is provided with a stopper 5, and the prefabricated anchor 1 is disposed inside the wall 15, so as to prevent the concrete from entering the prefabricated anchor 1.
As an optimal implementation mode of the utility model, adjusting screw 9's one end is provided with the hand wheel, one side of hand wheel is provided with the limiting plate, carries on spacingly to adjusting screw 9, makes things convenient for adjusting screw 9 to rotate.
As an optimal implementation manner of the present invention, the inner side of the baffle 10 is fixedly provided with a slider 12 through a connecting plate 11, the central position of the slider 12 is provided with a screw hole 13, the slider 12 is movably mounted on the adjusting screw rod 9, the connecting plate 11 is slidably arranged inside the sliding groove 14, so that the baffle 10 can slide on the fixed steel pipe 8, and the position of the baffle 10 can be adjusted.
As a preferred embodiment of the utility model, the one end welding of fixed steel pipe 8 is in the bottom of one side of anchor slab 7, fixes fixed steel pipe 8 through the fixed convenience to anchor slab 7, improves its stability.
When the novel construction device for the wall connecting piece of the external scaffold for the building is used, one end of a positioning screw rod 2 is arranged inside a prefabricated anchor piece 1, the other end of the positioning screw rod 2 penetrates through a through hole on a formwork 16 and is fixed to the positioning screw rod 2 through a nut 3, the prefabricated anchor piece 1 is arranged inside the formwork 16, a proper amount of prefabricated anchor piece 1 is arranged on the formwork 16, concrete is poured inside the formwork 16, a concrete wall is completely formed, the nut 3 is unscrewed, the positioning screw rod 2 and the formwork 16 are disassembled together, an adjusting screw 9 is rotated through a hand wheel, the adjusting screw 9 drives a sliding block 12 to slide inside a fixing steel pipe 8 through a screw hole 13, the sliding block 12 drives a baffle plate 10 to slide on the fixing steel pipe 8 through a connecting plate 11, the baffle plate 10 is moved to one end far away from an anchor plate 7, one end of a bolt 6 penetrates through the through hole on the anchor plate 7 and is inserted into the prefabricated anchor piece 1, through rotating fixed steel pipe 8, adjust the position of anchor slab 7 and fixed steel pipe 8, make the one end of fixed steel pipe 8 be close to next outer scaffold, will fix steel pipe 8 and outer scaffold through the fastener and fix, the reverse rotation hand wheel, the hand wheel passes through adjusting screw 9 and drives slider 12 and slide, slider 12 drives baffle 10 through connecting plate 11 and slides, make one side of baffle 10 support the fastener, this novel outer scaffold of building even wall spare construction equipment can be according to the position of fixed steel pipe 8 and outer scaffold to the adjustment of baffle 10, improve the stability of outer scaffold, reduce the waste, resources are saved, the steam generator is simple in structure, high durability and convenient use, can be applicable to the project of using simultaneously, construction efficiency can be improved.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (6)

1. A novel construction device for wall connecting pieces of external scaffolds of buildings comprises a prefabricated anchor piece (1), a positioning screw rod (2), a bolt (6), an anchor plate (7), a fixed steel pipe (8), a baffle plate (10), a wall body (15) and a template (16), it is characterized in that the template (16) is provided with a through hole, one end of the positioning screw rod (2) passes through the through hole and is arranged inside the prefabricated anchor (1), the positioning screw rod (2) and the prefabricated anchor (1) are arranged on the template (16) through a nut (3), the prefabricated anchor (1) is arranged inside the template (16), one end of the anchor plate (7) is provided with a through hole, the top and the bottom of the fixed steel pipe (8) are symmetrically provided with sliding chutes (14), an adjusting screw rod (9) is movably arranged in the fixed steel pipe (8) through a rotating shaft, the baffle (10) is movably arranged on the fixed steel pipe (8) through a sliding block (12) and a connecting plate (11).
2. The novel construction device for the wall connecting piece of the external scaffold of the building as claimed in claim 1, wherein: the anchor plate (7) is installed on one side of a wall body (15) through a bolt (6), and one end of the bolt (6) is installed inside the prefabricated anchor (1).
3. The novel construction device for the wall connecting piece of the external scaffold of the building as claimed in claim 1, wherein: one end of the prefabricated anchor (1) is provided with a fixing nut (4), one side of the fixing nut (4) is provided with a stop block (5), and the prefabricated anchor (1) is arranged inside a wall body (15).
4. The novel construction device for the wall connecting piece of the external scaffold of the building as claimed in claim 1, wherein: one end of the adjusting screw rod (9) is provided with a hand wheel, and one side of the hand wheel is provided with a limiting plate.
5. The novel construction device for the wall connecting piece of the external scaffold of the building as claimed in claim 1, wherein: the inner side of the baffle (10) is fixedly provided with a sliding block (12) through a connecting plate (11), the center of the sliding block (12) is provided with a screw hole (13), the sliding block (12) is movably arranged on the adjusting screw rod (9), and the connecting plate (11) is arranged inside the sliding groove (14) in a sliding manner.
6. The novel construction device for the wall connecting piece of the external scaffold of the building as claimed in claim 1, wherein: one end of the fixed steel pipe (8) is welded at the bottom of one side of the anchor plate (7).
CN202022800795.8U 2020-11-28 2020-11-28 Novel construction of building external scaffolding even wall spare device Active CN214462460U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022800795.8U CN214462460U (en) 2020-11-28 2020-11-28 Novel construction of building external scaffolding even wall spare device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022800795.8U CN214462460U (en) 2020-11-28 2020-11-28 Novel construction of building external scaffolding even wall spare device

Publications (1)

Publication Number Publication Date
CN214462460U true CN214462460U (en) 2021-10-22

Family

ID=78183956

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022800795.8U Active CN214462460U (en) 2020-11-28 2020-11-28 Novel construction of building external scaffolding even wall spare device

Country Status (1)

Country Link
CN (1) CN214462460U (en)

Similar Documents

Publication Publication Date Title
CN208702140U (en) A kind of shear wall joint part formwork reinforcement structure
CN206091299U (en) A floor buried sleeve fixing device for aluminum alloy template
CN201679231U (en) Template clamp for construction
CN209240258U (en) A kind of concrete prefabricated element reinforcing bar positioning fixture
CN214462460U (en) Novel construction of building external scaffolding even wall spare device
CN213038420U (en) Adjustable foundation bolt fixing support for power transmission line foundation construction
CN201276842Y (en) Construction barrel mold for reserved opening of simple building
CN205999854U (en) Lining canal thin-wall construction concrete Fast Modular builds device
CN206655478U (en) Adjustable window hole molding board support meanss
CN207643373U (en) A kind of prefabricated anchor block adjustable composite steel form
CN110056190A (en) A kind of two-part slab thickness control sealing up screw
CN203129626U (en) Early-removal supporting device for beam template
CN114232816B (en) Prefabricated assembled frame structure and assembling method thereof
CN210888058U (en) Length-adjustable concrete column template rapid reinforcing device
CN206428805U (en) A kind of concrete prefabricated balcony of assembled steel
CN201172966Y (en) Securing fixture for bidirectionally adjusting cast-in-situ concrete shuttering
CN206245709U (en) A kind of outrigger wall-connecting piece
CN214658822U (en) Can have enough to meet need building templates anchor clamps of use
CN106884533A (en) Adjustable window hole molding board support meanss
CN216787649U (en) Assembled concrete filled steel tube column splicing structure
CN203514341U (en) Mold supporting structure for concrete foundation hole of large device
CN208899857U (en) Exempt from supporting and shaping template in a kind of assembled architecture primary-secondary beam junction
CN208267375U (en) A kind of efficient plumbing built-in pipe setting tool
CN101736694B (en) Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line
CN202299427U (en) Device for connecting and positioning steel molding plate of building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant