CN101736694B - Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line - Google Patents

Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line Download PDF

Info

Publication number
CN101736694B
CN101736694B CN2008102267810A CN200810226781A CN101736694B CN 101736694 B CN101736694 B CN 101736694B CN 2008102267810 A CN2008102267810 A CN 2008102267810A CN 200810226781 A CN200810226781 A CN 200810226781A CN 101736694 B CN101736694 B CN 101736694B
Authority
CN
China
Prior art keywords
anchor support
nose
bridge
bridge erecting
erecting machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008102267810A
Other languages
Chinese (zh)
Other versions
CN101736694A (en
Inventor
公彦良
李征
陈胜旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN2008102267810A priority Critical patent/CN101736694B/en
Publication of CN101736694A publication Critical patent/CN101736694A/en
Application granted granted Critical
Publication of CN101736694B publication Critical patent/CN101736694B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a front-nose-girder anchor support when a 900 bridge erecting machine passes a bridge span in a passenger railway line, which is characterized in that: the front-nose-girder anchor support is processed into a box beam by utilizing a flange beam; and the box beam is welded with a support tension rod splint, and is reserved with anchor holes according to erection openings of a prestressed concrete simply supported beam of the passenger railway line. A front auxiliary nose girder of the bridge erecting machine is connected with the erected prestressed concrete simply supported beam of the passenger railway line through a bidirectional telescopic screw rod to achieve the effect of fixing legs of the bridge erecting machine so as to realize the safety and stability in a working state that the bridge erecting machine passes the bridge span. The front-nose-girder anchor support has the advantages of simple structure, low manufacturing cost, high practicability, safe and reliable operation, and high sensitivity, and can be used for various bridge erecting machines only by little changing the size of the screw rod splint; and the structure can be repeatedly utilized so as to reduce repeat waste of materials, reduce the construction difficulty of the front pilot working procedure and save project capital effectively.

Description

Special line for passenger trains 900 type bridge formation machine front launching nose anchor support technology
Technical field
The present technique invention belongs to high-speed railway Line for Passenger Transportation construction field, anchoring temporarily device when solving 900 tonnes of bridge formation machine via holes.
Background technology
During China Express Railway is being built fast now, in the construction of high-speed railway, adopt the mode of viaduct to solve the variety of issue that restricts circuit usually.In the process of building bridge,, have only by specialty bridge formation machine and construct owing to Line for Passenger Transportation precast concrete simple supported box beam volume big (beam length is 32.6m), tonnage heavy (single hole case beam quality reaches 900t).The bridge formation machine main body of using at present is divided into two parts: one is the girder part, main body when working for bridge formation frame beam; Two is the front launching nose part, for the bridge formation machine after successfully setting up a hole simple supported box beam, for crane ' s major girder reach provides support, thus the state that crane ' s major girder is reached work on.When crane ' s major girder via hole state, bridge formation machine front launching nose fixed-site need be caused unstability and causes serious accident with the machine complete machine reach that prevents to build bridge.In the construction be at present: in the Bridge Pier Construction of carrying out in advance that 8 fining twisted steels are buried in pier shaft by the mode of predetermined fixed in the anchoring scheme that adopts with the bridge formation machine.Such cost cost height because fining twisted steel is to adopt pre-buried mode to be fixed on the bridge pier, can not take out usefulness of turnover after simple supported box beam sets up, increased the input of material; Two reclaim difficulty, the material recovery that pier shaft can only be exposed in the removal process, and to adopt the mode of gas cutting, thus increased expenses of labour; Three have increased the difficulty of Bridge Pier Construction, build bridge pier concrete the time for the accuracy that guarantees the built-in fitting position has increased labour cost, because if can not guarantee that the position is accurate in the construction, then can have a strong impact on setting up of case beam.
Summary of the invention
The purpose of present technique invention is to overcome above-mentioned weak point, and a kind of simple in structure, dependable performance, easy to use, the bridge formation machine front launching nose anchor support that can have enough to meet the need use are provided.
For achieving the above object, the technical solution used in the present invention is: design and a kind of bridge formation machine of processing and fabricating front launching nose anchor support, replace pushing up at pier stud the way of pre-buried fining twisted steel.Anchor frame adopts i iron to be processed into the box girder steel, welding tie-strut clamping plate on the box girder steel, and according to Line for Passenger Transportation precast concrete simple supported box beam hole for hoist position reservation anchor hole.Utilize the bi-directional expansion screw mandrel that auxiliary nose girder before the bridge formation machine is connected with frame precast concrete simple supported box beam, can reach the fixedly effect of bridge formation machine supporting leg, thus safety and stability under the realization bridge formation machine via hole duty.The present technique beneficial effect of the invention is:
1, simple in structure, the job site makes easily, and cost is low, can utilize the building-site current material to process, and a cover anchor support expense amounts to and is no more than 5000 yuan.
2, dependable performance, the stability that front launching nose partly supports girder in the time of can satisfying 900t level bridge formation machine via hole.
3, easy to use, can utilize the existing bale handle dolly of bridge formation machine to carry out the carrying of anchor support, reduced labor strength, improved operating efficiency.
4, anchor frame can be reused, and has saved the material input.
5, shortened the cycle of setting a roof beam in place, adopted this technology can significantly reduce the bridge formation machine via hole needed time of operating mode, the cycle of setting up of every hole simple supported box beam can shorten 40~60 minutes.
Description of drawings
Fig. 1 is the positive facade of anchor support;
Fig. 2 is the anchor support vertical view;
Fig. 3 is the anchor support left view;
Fig. 4 is the anchoring pin rod;
Duty when Fig. 5 is the work of bridge formation machine employing present technique invention anchor support;
Fig. 6 is that the bridge formation machine adopts former design anchoring scheme duty.
The specific embodiment
Bridge formation machine front launching nose anchor support adopts the butt welding of 200mm type i iron to be processed into box girder steel integral body, 8 anchoring rod straps with the processing of 20mm steel plate of welding on it.Be be connected with the frame Line for Passenger Transportation precast concrete simple supported box beam anchoring screw mandrel of usefulness of anchor support, during use the anchoring screw mandrel is passed the preformed hole of anchor frame and the hole for hoist of Line for Passenger Transportation precast concrete simple supported box beam, utilize bolt that anchor support and Line for Passenger Transportation precast concrete simple supported box beam are locked together.Rear end face at bridge formation machine front launching nose welds the leading screw strap simultaneously, and makes it corresponding with strap position on the anchor support.In the enforcement, utilize the bi-directional expansion leading screw that to have bought on the market that the strap on the bridge formation machine front launching nose is connected with anchor support.
The present technique invention has been verified its service behaviour through the practical application of Zheng Xi Line for Passenger Transportation high-speed railway JQ900 type bridge formation machine.The stability and the safety of the work of bridge formation machine have been improved.An anchoring temporarily difficult problem had been saved engineering cost greatly when this anchor support had successfully solved bridge formation machine front launching nose via hole, made simply, was applicable to the bridge formation machine of similar model, and employing is worthy to be popularized.

Claims (1)

1. method of utilizing anchor support anchoring bridge formation machine front launching nose, it is characterized in that anchor support is processed into the box girder steel by the i iron butt welding, welding anchoring rod strap on it, and according to precast concrete simple supported box beam hole for hoist position reservation anchor hole, during use the anchoring screw mandrel passed the reservation anchor hole of anchor support and the hole for hoist of precast concrete simple supported box beam, utilize bolt that anchor support and concrete simple supported box beam are locked together, at the rear end face of bridge formation machine front launching nose welding screw mandrel strap, and make it corresponding and the strap on the bridge formation machine front launching nose is connected with anchor support with the bi-directional expansion leading screw with strap position on the anchor support.
CN2008102267810A 2008-11-24 2008-11-24 Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line Active CN101736694B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008102267810A CN101736694B (en) 2008-11-24 2008-11-24 Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008102267810A CN101736694B (en) 2008-11-24 2008-11-24 Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line

Publications (2)

Publication Number Publication Date
CN101736694A CN101736694A (en) 2010-06-16
CN101736694B true CN101736694B (en) 2011-12-07

Family

ID=42460681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008102267810A Active CN101736694B (en) 2008-11-24 2008-11-24 Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line

Country Status (1)

Country Link
CN (1) CN101736694B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590342B (en) * 2012-08-16 2016-09-14 秦皇岛天业通联重工科技有限公司 The system of getting off of the bridge formation unit of a kind of anti-hypsokinesis and utilize its method carrying out building bridge
CN115094776B (en) * 2022-07-27 2023-02-28 中铁二局集团有限公司 Method for anchoring supporting legs of bridge girder erection machine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2570319Y (en) * 2002-09-10 2003-09-03 同济大学 Transferring control device of tied arch bridge hanger rod changing
CN2675729Y (en) * 2003-12-19 2005-02-02 秦皇岛市北戴河通联路桥机械有限公司 Double guiding-beam bridge-laying machine for high-speed railway
CN2742026Y (en) * 2004-11-20 2005-11-23 秦皇岛市北戴河通联路桥机械有限公司 One gap type top guide beam moving mould frame bridge making machine
CN201053105Y (en) * 2007-04-17 2008-04-30 郭文学 Equal span self-balancing bridging machine
CN101250854A (en) * 2007-12-05 2008-08-27 中铁大桥局股份有限公司 Large span double-linear-box beam bunching-frame method construction bridging machine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2570319Y (en) * 2002-09-10 2003-09-03 同济大学 Transferring control device of tied arch bridge hanger rod changing
CN2675729Y (en) * 2003-12-19 2005-02-02 秦皇岛市北戴河通联路桥机械有限公司 Double guiding-beam bridge-laying machine for high-speed railway
CN2742026Y (en) * 2004-11-20 2005-11-23 秦皇岛市北戴河通联路桥机械有限公司 One gap type top guide beam moving mould frame bridge making machine
CN201053105Y (en) * 2007-04-17 2008-04-30 郭文学 Equal span self-balancing bridging machine
CN101250854A (en) * 2007-12-05 2008-08-27 中铁大桥局股份有限公司 Large span double-linear-box beam bunching-frame method construction bridging machine

Also Published As

Publication number Publication date
CN101736694A (en) 2010-06-16

Similar Documents

Publication Publication Date Title
CN106968180B (en) A kind of dry type connection method of the concrete slab and girder steel of the mixed combination beam of steel-
CN201972269U (en) Prefabricated reinforcing steel bar concrete shear wall
CN204849569U (en) Steel pipe concrete stem stem prefabricated unit construction bridge pier stud of putting more energy into
CN102409851B (en) Method and system for reinforcing telescopic supporting system for deformation joint template of shear wall structure
CN209854553U (en) Assembled concrete anticollision barrier based on ultrahigh performance concrete is connected
CN204804057U (en) Beam column connecting device of prefabricated frame
CN209614691U (en) A kind of Precast Pier Columns steel reinforcement cage locating rack
CN101736694B (en) Technology of front-nose-girder anchor support of 900 bridge erecting machine for passenger railway line
CN102493553A (en) Member for connection node of reinforced beam and steel beam and construction method thereof
CN202945798U (en) Overhanging type scaffold corner device
CN202627540U (en) Constructing rack device for assisting prestress tension
CN204266572U (en) Scaffold wall connecting piece
CN204081087U (en) A kind of reinforced concrete column and reinforcing steel bar connecting device
CN204386608U (en) A kind of tunnel invert construction tool
CN209260922U (en) Band girder rib laminated floor slab pre-tensioning system connecting joint structure
CN202913338U (en) Steel truss full-welded truss piece
CN203668894U (en) Concrete prefabricated form structure allowing rapid installation
CN103882840B (en) A kind of surge shaft Cast-in-place concrete assembling falsework and mounting method thereof
CN203113519U (en) Connection structure of structural outer wall and wall-attached rod of power plant cooling tower
CN202672484U (en) Steel pipe single-post structure
CN201826438U (en) Steel column convenient for constructing temporary operating platform
CN202611223U (en) Recyclable bolt type scaffold wall connection piece
CN202347665U (en) Connection node constructional member of reinforced concrete beam and steel beam
CN201339320Y (en) High-altitude overhanging hanging reinforced concrete hanging bracket
CN208533863U (en) A kind of prefabricated girder of armored concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: THE 4TH ENGINEERING CO., LTD. OF CHINA RAILWAY 16T

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20110929

Address after: 100018 Beijing city Chaoyang District No. 2 North Pine dam Park

Applicant after: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Co-applicant after: China Railway 16th Bureau Group Fourth Engineering Co., Ltd.

Address before: 100018 Beijing city Chaoyang District No. 2 North Pine dam Park

Applicant before: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant