CN211735395U - Pile stabilizing device for pile cutting construction - Google Patents

Pile stabilizing device for pile cutting construction Download PDF

Info

Publication number
CN211735395U
CN211735395U CN201922124479.0U CN201922124479U CN211735395U CN 211735395 U CN211735395 U CN 211735395U CN 201922124479 U CN201922124479 U CN 201922124479U CN 211735395 U CN211735395 U CN 211735395U
Authority
CN
China
Prior art keywords
pile
cut
stabilizing
pile stabilizing
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922124479.0U
Other languages
Chinese (zh)
Inventor
杨斌
王荭杰
陈�胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Industry Zhongyuan Construction Co ltd
Original Assignee
China Nuclear Industry Zhongyuan Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Industry Zhongyuan Construction Co ltd filed Critical China Nuclear Industry Zhongyuan Construction Co ltd
Priority to CN201922124479.0U priority Critical patent/CN211735395U/en
Application granted granted Critical
Publication of CN211735395U publication Critical patent/CN211735395U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a pile stabilizing device for pile cutting construction, which comprises a hanging platform, an upper pile stabilizing part and a lower pile stabilizing part, wherein the upper pile stabilizing part and the lower pile stabilizing part are positioned below the hanging platform; the upper pile stabilizing part comprises at least one hoop, two clamping irons are symmetrically welded at the bottom of the lifting platform and clamped at two sides of the top of the pile body to be cut off, and the two clamping irons are tightly held by the hoop to lock the two clamping irons and the pile body; the lower pile stabilizing part is a pile stabilizing column with a diameter matched with the inner diameter of a pile body to be cut off, a lifting device is installed on the lifting platform, the lifting device is connected with the pile stabilizing column through a lifting rope, the pile stabilizing column is inserted into the pile body to be cut off and stays at the cutting position of the pile body to be cut off, and the upper part and the lower part of the pile stabilizing column are respectively positioned at the upper side and the lower side of the cutting position. The utility model discloses a steady pile device stabilizes respectively at the top and the bottom of the pile body part of treating the truncation back in the pile body through last steady pile part and steady pile part down, still keeps the pile body part perpendicular to ground of truncation, can not take place to empty.

Description

Pile stabilizing device for pile cutting construction
Technical Field
The utility model relates to an equipment that construction used specifically is a cut steady stake device of stake construction usefulness.
Background
During pile foundation construction, due to various reasons such as uneven distribution of geological soil layers and the like, the elevation of a plurality of pile tops is higher than the designed elevation, and after a foundation pit is excavated, the pile bodies higher than the designed elevation are cut off, namely, the pile cutting is called.
Generally, when the height of a pile to be cut is low, the pile cutting is relatively safe, but a pile body to be cut is high in height and high in mass, and when the pile is cut, a constructor is extremely easy to collapse and injure at the moment of cutting without taking a pile stabilizing measure. The actual situation of the solution is here as follows: the excavation of the foundation pit can be carried out according to each layer not more than 1 meter in a layering mode for multiple times, the excavation is suspended after each layer is excavated, meanwhile, the pile is cut once, namely, the pile is cut for multiple times in a segmentation mode not more than 1 meter, and when the cut pile is low in height, the cut pile is relatively safe. However, the scheme seriously influences the construction period progress and the economic cost, and is hardly adopted in the actual construction practice; the large excavator is parked near the pile body to be cut, and the pile body to be cut is suspended by a steel cable. Also because of economic cost, the method is hardly adopted in practical construction practice; the tower crane is actually idle at the moment, but the tower crane is not enough to bear the load of suspension pile breaking or pile breaking dumping; in addition, the method of building and supporting the foundation soil around the pile section to be cut is not feasible, because no hardened foundation exists at the moment, only a soft and wet soil layer is formed, and the toppling load of the broken pile cannot be supported; therefore, in actual construction practice, accidents are basically prevented by means of the fact that the tip and the legs of pile cutting operators are fast dodged and avoided, and the accidents are obviously unreliable and leave great potential safety hazards. Thus, such accidents sometimes occur.
Disclosure of Invention
The purpose of the invention is as follows: the utility model aims to provide a steady stake device for cutting pile construction to prior art not enough, at the pile body in-process of cutting off the pile body and shifting after cutting off, guarantee that the pile body can not empty.
The technical scheme is as follows: the pile stabilizing device for pile cutting construction comprises a lifting platform, an upper pile stabilizing part and a lower pile stabilizing part, wherein the upper pile stabilizing part and the lower pile stabilizing part are positioned below the lifting platform;
the upper pile stabilizing part comprises at least one hoop, two clamping irons are symmetrically welded at the bottom of the lifting platform and clamped at two sides of the top of the pile body to be cut off, and the two clamping irons are tightly held by the hoop to lock the two clamping irons and the pile body;
the lower pile stabilizing part is a pile stabilizing column with a diameter matched with the inner diameter of a pile body to be cut off, a lifting device is installed on the lifting platform, the lifting device is connected with the pile stabilizing column through a lifting rope, the pile stabilizing column is inserted into the pile body to be cut off and stays at the cutting position of the pile body to be cut off, and the upper part and the lower part of the pile stabilizing column are respectively positioned at the upper side and the lower side of the cutting position.
The utility model discloses further preferred technical scheme does, steady pile is formed by steel pipe and steel sheet welding, fills high strength concrete in steady pile, transition fit between the outer wall of steady pile and the inner wall of the pile body of treating the truncation.
Preferably, the diameter of the middle part of the pile stabilizing column is smaller than the diameters of the two ends, and after the pile stabilizing column is inserted into the pile body to be cut, the middle part of the pile stabilizing column corresponds to the cutting position of the pile body to be cut.
Preferably, the upper pile stabilizing part comprises an upper hoop and a lower hoop, two hoop plates of the hoops are respectively provided with a clamping block, and the two clamping blocks and the two clamping irons are matched to surround the periphery of the top of the pile body to be cut.
Preferably, the lifting lugs are symmetrically arranged on the lifting platform.
Preferably, the lifting device is a winch.
Has the advantages that: (1) the pile stabilizing device of the utility model is respectively stabilized at the top and the bottom of the pile body part to be cut through the upper pile stabilizing part and the lower pile stabilizing part, the lower pile stabilizing part is inserted into the pile core, and after the pile body is cut, the cut pile body part is still kept to be vertical to the ground, so that the pile body cannot topple over; meanwhile, the upper pile stabilizing part tightly holds the top of the pile body, so that the effect of stabilizing the pile body is achieved, and meanwhile, the cut pile body can be transferred by matching with a crane;
(2) the utility model has the advantages that the transition fit between the outer wall of the middle stable pile and the inner wall of the pile body to be cut off is realized, so that the inclination angle of the pile body is extremely small, and the construction safety is further improved; the diameter of the middle part of the pile stabilizing column is smaller than the diameters of the two ends, so that a cutting machine or other instruments can conveniently cut the pile body;
(3) the utility model discloses be provided with a fixture block, two fixture blocks and two on the two hoop boards of well staple bolt the gib cooperation surrounds around the pile body top of waiting to cut off, and fixture block and gib form the rectangle in the space, guarantee to go up the firm of being connected between steady pile portion and the pile body of cutting off.
Drawings
Fig. 1 is a schematic structural view of the pile stabilizing device of the present invention;
FIG. 2 is a schematic construction view of the pile stabilizing device of the present invention;
in the figure, 1-hanging platform, 2-winch, 3-anchor ear, 4-pile stabilizing column, 5-pile body to be cut off and 6-lifting lug.
Detailed Description
The technical solution of the present invention is described in detail below with reference to the accompanying drawings, but the scope of the present invention is not limited to the embodiments.
Example (b): a pile stabilizing device for pile cutting construction comprises a lifting platform 1, an upper pile stabilizing part and a lower pile stabilizing part, wherein the upper pile stabilizing part and the lower pile stabilizing part are positioned below the lifting platform 1.
Two clamping irons are symmetrically welded at the bottom of the hanging platform 1 and clamped at two sides of the top of the pile body 5 to be cut off. A hoist 2 with a counter is arranged on the hanging platform 1, and two lifting lugs 6 are symmetrically welded.
The upper pile stabilizing part comprises an upper hoop 3 and a lower hoop 3, two hoop plates of the hoop 3 are respectively provided with a clamping block, the hoop 3 tightly holds two clamping irons, and the two clamping blocks and the two clamping irons are matched to surround the periphery of the top of the pile body 5 to be cut off.
The lower pile stabilizing part is a pile stabilizing column 4 of which the diameters of two ends are matched with the inner diameter of a pile body 5 to be cut off, and the diameter of the middle part of the pile stabilizing column 4 is smaller than the diameters of the two ends. The pile stabilizing column 4 is formed by welding steel pipes and steel plates, high-strength concrete is poured into the pile stabilizing column 4, and the outer wall of the pile stabilizing column 4 is in transition fit with the inner wall of the pile body 5 to be cut. The hoist 2 is connected with the pile stabilizing column 4 through a lifting rope, the pile stabilizing column 4 is inserted into the pile body 5 to be cut, and the smaller diameter part of the middle part of the pile stabilizing column 4 corresponds to the cutting position of the pile body 5 to be cut.
When the device is used, the lifting lugs 6 on the lifting platform 1 are connected with lifting equipment, the whole device is lifted to a working area, the upper pile stabilizing part is clamped around the top of the pile body 5 to be cut, then the number of turns of the winch 2 is calculated according to the height of the pile body 5 to be cut, namely the descending length of the lower pile stabilizing part, and the pile stabilizing column 4 is descended to the middle part of the pile stabilizing column and corresponds to the cutting position of the pile body 5 to be cut. And (3) pile cutting operation is carried out, after cutting is finished, the cut pile body is tied from the bottom of the hoop by using a lifting rope, the cut pile body and the upper pile stabilizing part are connected with lifting equipment, and the whole device is lifted together with the cut pile body part.
As mentioned above, although the present invention has been shown and described with reference to certain preferred embodiments, it should not be construed as limiting the invention itself. Various changes in form and detail may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (6)

1. A pile stabilizing device for pile cutting construction is characterized by comprising a lifting platform, an upper pile stabilizing part and a lower pile stabilizing part, wherein the upper pile stabilizing part and the lower pile stabilizing part are positioned below the lifting platform;
the upper pile stabilizing part comprises at least one hoop, two clamping irons are symmetrically welded at the bottom of the lifting platform and clamped at two sides of the top of the pile body to be cut off, and the two clamping irons are tightly held by the hoop to lock the two clamping irons and the pile body;
the lower pile stabilizing part is a pile stabilizing column with a diameter matched with the inner diameter of a pile body to be cut off, a lifting device is installed on the lifting platform, the lifting device is connected with the pile stabilizing column through a lifting rope, the pile stabilizing column is inserted into the pile body to be cut off and stays at the cutting position of the pile body to be cut off, and the upper part and the lower part of the pile stabilizing column are respectively positioned at the upper side and the lower side of the cutting position.
2. The pile stabilizing device for pile cutting construction according to claim 1, wherein the pile stabilizing column is formed by welding steel pipes and steel plates, high-strength concrete is poured into the pile stabilizing column, and the outer wall of the pile stabilizing column is in transition fit with the inner wall of the pile body to be cut.
3. The pile stabilizing device for pile cutting construction according to claim 2, wherein the diameter of the middle part of the pile stabilizing column is smaller than the diameter of the two ends, and the middle part of the pile stabilizing column corresponds to the cutting position of the pile to be cut after the pile stabilizing column is inserted into the pile to be cut.
4. The pile stabilizing device for pile cutting construction according to claim 1, wherein the upper pile stabilizing part comprises an upper hoop and a lower hoop, two hoop plates of the hoop are respectively provided with a clamping block, and the two clamping blocks are matched with the two clamping irons to surround the top of the pile body to be cut.
5. A pile stabilizing device for pile cutting construction according to claim 1, wherein lifting lugs are symmetrically mounted on the lifting platform.
6. The pile stabilizing device for cut pile construction according to claim 1, wherein the lifting device is a hoist.
CN201922124479.0U 2019-12-02 2019-12-02 Pile stabilizing device for pile cutting construction Expired - Fee Related CN211735395U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922124479.0U CN211735395U (en) 2019-12-02 2019-12-02 Pile stabilizing device for pile cutting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922124479.0U CN211735395U (en) 2019-12-02 2019-12-02 Pile stabilizing device for pile cutting construction

Publications (1)

Publication Number Publication Date
CN211735395U true CN211735395U (en) 2020-10-23

Family

ID=72875706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922124479.0U Expired - Fee Related CN211735395U (en) 2019-12-02 2019-12-02 Pile stabilizing device for pile cutting construction

Country Status (1)

Country Link
CN (1) CN211735395U (en)

Similar Documents

Publication Publication Date Title
CN110306524B (en) Foundation reinforcing structure and method for hoisting heavy equipment close to unsealed building
CN107191676A (en) Construction method of buried pipeline
CN113353782B (en) Low-clearance ground wall-connected reinforcement cage rapid hoisting construction method
CN112523215B (en) Multi-equipment efficient construction method for carrier pile
CN102926388B (en) Earth moving method for deep foundation pit excavation
CN113774972A (en) Reinforcing method for overload punching damage of independent foundation under column
CN211735395U (en) Pile stabilizing device for pile cutting construction
CN204983692U (en) Concrete panel's hoist device
CN206753488U (en) A kind of artificial digging pile reaming auxiliary equipment
CN206941596U (en) A kind of shoulder pole boom device for lifting steel reinforcement cage
CN205932883U (en) Pitshaft driving cage
CN217174727U (en) Auxiliary vibrating device
CN114590697A (en) High-span concrete support dismantling method based on reserved lifting hook for closed space
CN212612488U (en) Movable underwater concrete pouring guide pipe trolley
CN108487237A (en) A kind of no auxiliary tool lifting machinery appointed condition descending reinforcing cage processing and transferred
CN211547797U (en) Tower crane foundation structure suitable for basement raft foundation
CN211621558U (en) Bored concrete pile steel reinforcement cage elevation control mounting structure
CN113417281A (en) Cast-in-place pile-prestressed pipe pile composite pile and construction method thereof
CN209758880U (en) self-propelled superelevation super large area steel reinforcement cage lifting equipment
CN114016546A (en) Hole-pile method station steel pipe column hoisting and fixing device and construction method
CN206616552U (en) A kind of support cage assembly of stable spacer bar cage
CN205990200U (en) 360 ° of luffing independent hoist device
CN206986897U (en) A kind of tethered sliding formula toe slab grouting system
CN206299104U (en) A kind of workbench for accelerating anchor shaft anchor cable panel grider pore-forming
CN206070554U (en) Tower crane steel platform pile foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201023