CN211312173U - Energy-consuming tie beam structure of semi-assembly type bridge pier - Google Patents

Energy-consuming tie beam structure of semi-assembly type bridge pier Download PDF

Info

Publication number
CN211312173U
CN211312173U CN201921732496.6U CN201921732496U CN211312173U CN 211312173 U CN211312173 U CN 211312173U CN 201921732496 U CN201921732496 U CN 201921732496U CN 211312173 U CN211312173 U CN 211312173U
Authority
CN
China
Prior art keywords
tie beam
prefabricated outer
outer cylinder
steel
semi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921732496.6U
Other languages
Chinese (zh)
Inventor
林上顺
叶世集
张晓曦
林玉莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Peiyan Engineering Technology Co ltd
Fujian Yongfu Construction Group Co ltd
Fujian University of Technology
Original Assignee
Fuzhou Peiyan Engineering Technology Co ltd
Fujian Yongfu Construction Group Co ltd
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Peiyan Engineering Technology Co ltd, Fujian Yongfu Construction Group Co ltd, Fujian University of Technology filed Critical Fuzhou Peiyan Engineering Technology Co ltd
Priority to CN201921732496.6U priority Critical patent/CN211312173U/en
Application granted granted Critical
Publication of CN211312173U publication Critical patent/CN211312173U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to the technical field of bridge engineering, in particular to a semi-assembly type bridge pier energy dissipation tie beam structure, which comprises two sections of bridge piers with the same structure and a steel tie beam connected between the two bridge piers; the RUHPC adopted by the beam connecting block of the semi-assembly pier energy-consuming beam system structure provided by the utility model has good corrosion resistance, wear resistance and impermeability; the beam connecting blocks at the two ends of the steel tie beam can be used as permanent supports of the steel tie beam, and no support needs to be erected in the installation and replacement processes of the steel tie beam, so that the construction efficiency is high; compared with the traditional bridge tying construction which adopts a steel template, a large amount of steel can be saved; adopt high strength bolted connection between steel tie beam and two piers, make things convenient for the change of later stage steel tie beam.

Description

一种半装配式桥墩耗能系梁结构A semi-fabricated bridge pier energy dissipation tie beam structure

技术领域technical field

本实用新型涉及桥梁工程技术领域,具体涉及一种半装配式桥墩耗能系梁结构。The utility model relates to the technical field of bridge engineering, in particular to a semi-assembled bridge pier energy dissipation tie beam structure.

背景技术Background technique

桥梁桥梁高桥墩混凝土系梁刚度较大,在发生地震时,往往由于混凝土系梁刚度大、耗能能力弱,导致墩柱、系梁同时出现破坏,且难以修复。采用钢材作为模板的整体现浇施工方法时,钢模板数量巨大,而采用全截面预制拼装的施工方法,桥墩和系梁之间不好连接,并且需要大型吊装设备、运输设备和预制场地等。这两种施工方法都存在施工难、费用高与工效低等不足。The rigidity of the concrete tie beams of the high piers of bridges and bridges is relatively large. In the event of an earthquake, the pier columns and the tie beams are damaged at the same time due to the high rigidity and weak energy dissipation capacity of the concrete tie beams, which are difficult to repair. When using steel as the overall cast-in-place construction method of the formwork, the number of steel formwork is huge, while the construction method of full-section prefabricated assembly is not easy to connect the bridge pier and the tie beam, and requires large hoisting equipment, transportation equipment and prefabricated site. These two construction methods have the disadvantages of difficult construction, high cost and low work efficiency.

实用新型内容Utility model content

为了克服上述现有技术的缺陷,本实用新型所要解决的技术问题是:现有桥梁的桥墩和系梁之间施工难度大、系梁难以拆除和更换。In order to overcome the above-mentioned defects of the prior art, the technical problems to be solved by the present invention are: the construction between the piers and the tie beams of the existing bridge is difficult, and the tie beams are difficult to dismantle and replace.

为了解决上述技术问题,本实用新型采用的技术方案为:一种半装配式桥墩耗能系梁结构,包括两段结构相同的桥墩和连接于两个桥墩之间的钢系梁;In order to solve the above-mentioned technical problems, the technical solution adopted by the present utility model is: a semi-assembled bridge pier energy dissipation tie beam structure, comprising two piers with the same structure and a steel tie beam connected between the two piers;

所述桥墩包括下节段预制外筒和上节段预制外筒;The bridge pier includes a lower segment prefabricated outer cylinder and an upper segment prefabricated outer cylinder;

所述下节段预制外筒的顶端设有加厚段,所述下节段预制外筒的顶部中央设有预埋钢管,所述预埋钢管一端埋覆于加厚段内,另一端延伸到下节段预制外筒顶面外,所述下节段预制外筒的加厚段的侧壁上设置有下预制方块;The top of the lower segment prefabricated outer cylinder is provided with a thickened section, the center of the top of the lower segment prefabricated outer cylinder is provided with a pre-embedded steel pipe, one end of the pre-embedded steel pipe is buried in the thickened section, and the other end extends Outside the top surface of the lower segment prefabricated outer cylinder, a lower prefabricated block is arranged on the side wall of the thickened section of the lower segment prefabricated outer cylinder;

所述上节段预制外筒设置于下节段预制外筒的上方,所述上节段预制外筒的底端设置有加厚段,所述下节段预制外筒的底面设置有供预埋钢管伸入的预留孔,所述上节段预制外筒的加厚段的侧壁上设置有上预制方块;The upper segment prefabricated outer cylinder is arranged above the lower segment prefabricated outer cylinder, the bottom end of the upper segment prefabricated outer cylinder is provided with a thickening section, and the bottom surface of the lower segment prefabricated outer cylinder is provided with a prefabricated outer cylinder. A reserved hole into which the buried steel pipe extends, and an upper prefabricated block is arranged on the side wall of the thickened section of the upper segment prefabricated outer cylinder;

所述上预制方块和下预制方块相对组成梁连接方块,所述梁连接方块上设置有多个水平方向的螺纹预制通孔;The upper prefabricated square and the lower prefabricated square form a beam connection square relatively, and the beam connection square is provided with a plurality of threaded prefabricated through holes in the horizontal direction;

所述钢系梁的两端设置有螺纹孔,所述钢系梁通过螺栓固定连接于两个梁连接方块之间。Two ends of the steel tie beam are provided with threaded holes, and the steel tie beam is fixedly connected between two beam connection blocks by bolts.

其中,所述上节段预制外筒和下节段预制外筒的材质均为RUHPC。Wherein, the materials of the prefabricated outer cylinder of the upper segment and the prefabricated outer cylinder of the lower segment are both RUHPC.

其中,所述钢系梁与桥墩之间通过高强度螺栓可拆卸连接。Wherein, the steel tie beam and the bridge pier are detachably connected by high-strength bolts.

其中,所述下节段预制外筒和上节段预制外筒之间涂覆有超高性能砂浆层。Wherein, an ultra-high-performance mortar layer is coated between the prefabricated outer cylinder of the lower segment and the prefabricated outer cylinder of the upper segment.

其中,所述上节段预制外筒、下节段预制外筒和预埋钢管内填充有混凝土。Wherein, the upper segment prefabricated outer cylinder, the lower segment prefabricated outer cylinder and the pre-embedded steel pipe are filled with concrete.

本实用新型的有益效果在于:本实用新型提供的半装配式桥墩耗能系梁结构,梁连接方块采用的RUHPC具有良好的耐腐蚀、耐磨性和抗渗性;钢系梁两端的梁连接方块可作为钢系梁的永久支撑,在钢系梁的安装、更换过程中无需搭设支架,施工效率高;相比传统的桥梁的系梁施工采用钢模板施工,可节省大量钢材;钢系梁和两个桥墩之间采用高强度螺栓连接,方便后期钢系梁的更换。The beneficial effects of the present utility model are: the semi-assembled bridge pier energy-consuming tie beam structure provided by the utility model, the RUHPC used in the beam connecting block has good corrosion resistance, wear resistance and impermeability; the beam connection at both ends of the steel tie beam The square can be used as a permanent support for the steel tie beam, and there is no need to erect a bracket during the installation and replacement of the steel tie beam, and the construction efficiency is high; compared with the traditional bridge tie beam construction using steel formwork construction, a large amount of steel can be saved; steel tie beams It is connected with the two bridge piers by high-strength bolts, which is convenient for the replacement of steel tie beams in the later stage.

附图说明Description of drawings

图1所示为本实用新型具体实施方式的半装配式桥墩耗能系梁结构的结构示意图;1 is a schematic structural diagram of a semi-fabricated bridge pier energy dissipation tie beam structure according to a specific embodiment of the present invention;

图2所示为图1中A-A处视图;Figure 2 shows a view at A-A in Figure 1;

图3所示为图1中B-B处视图;Fig. 3 shows the view at B-B in Fig. 1;

标号说明:Label description:

1、桥墩;11、下节段预制外筒;112、预埋钢管;113、下预制方块;12、上节段预制外筒;121、上预制方块;13、加厚段;1. Bridge pier; 11. Prefabricated outer cylinder in lower segment; 112. Pre-embedded steel pipe; 113. Lower prefabricated block; 12. Prefabricated outer cylinder in upper segment; 121. Upper prefabricated block; 13. Thickened section;

2、钢系梁;21、螺纹孔。2. Steel beams; 21. Threaded holes.

具体实施方式Detailed ways

为详细说明本实用新型的技术内容、所实现目的及效果,以下结合实施方式并配合附图予以说明。In order to describe in detail the technical content, achieved objects and effects of the present invention, the following descriptions are given with reference to the embodiments and the accompanying drawings.

请参照图1、图2和图3所示,本实用新型的一种半装配式桥墩耗能系梁结构,包括两段结构相同的桥墩1和连接于两个桥墩1之间的钢系梁2;Please refer to FIG. 1 , FIG. 2 and FIG. 3 , a semi-assembled bridge pier energy dissipation tie beam structure of the present invention includes two bridge piers 1 with the same structure and a steel tie beam connected between the two bridge piers 1 2;

所述桥墩1包括下节段预制外筒11和上节段预制外筒12;The bridge pier 1 includes a lower segment prefabricated outer cylinder 11 and an upper segment prefabricated outer cylinder 12;

所述下节段预制外筒11的顶端设有加厚段13,所述下节段预制外筒11的顶部中央设有预埋钢管112,所述预埋钢管112一端埋覆于加厚段13内,另一端延伸到下节段预制外筒11顶面外,所述下节段预制外筒11的加厚段13的侧壁上设置有下预制方块113;The top of the lower segment prefabricated outer cylinder 11 is provided with a thickened section 13, and the center of the top of the lower segment prefabricated outer cylinder 11 is provided with a pre-embedded steel pipe 112, and one end of the pre-embedded steel pipe 112 is buried in the thickened section 13, the other end extends to the outside of the top surface of the lower segment prefabricated outer cylinder 11, and a lower prefabricated block 113 is provided on the side wall of the thickened section 13 of the lower segment prefabricated outer cylinder 11;

所述上节段预制外筒12设置于下节段预制外筒11的上方,所述上节段预制外筒12的底端设置有加厚段13,所述下节段预制外筒11的底面设置有供预埋钢管112伸入的预留孔,所述上节段预制外筒12的加厚段13的侧壁上设置有上预制方块121;The upper segment prefabricated outer cylinder 12 is arranged above the lower segment prefabricated outer cylinder 11 , the bottom end of the upper segment prefabricated outer cylinder 12 is provided with a thickening section 13 , and the lower segment prefabricated outer cylinder 11 is provided with a thickened section 13 . The bottom surface is provided with a reserved hole for the embedded steel pipe 112 to extend into, and an upper prefabricated block 121 is provided on the side wall of the thickened section 13 of the upper segment prefabricated outer cylinder 12;

所述上预制方块121和下预制方块113相对组成梁连接方块,所述梁连接方块上设置有多个水平方向的螺纹预制通孔;The upper prefabricated block 121 and the lower prefabricated block 113 form a beam connecting block relatively, and a plurality of horizontal thread prefabricated through holes are arranged on the beam connecting block;

所述钢系梁2的两端设置有螺纹孔21,所述钢系梁2通过螺栓固定连接于两个梁连接方块之间。Both ends of the steel tie beam 2 are provided with threaded holes 21 , and the steel tie beam 2 is fixedly connected between two beam connection blocks by bolts.

施工方式:一、对下节段预制外筒11进行固定,在下节段预制外筒11顶面涂抹超高性能砂浆,将上节段预制外筒12安装到下节段预制外筒11顶面上,让下节段预制外筒11顶面的预埋钢管112插入上节段预制外筒12的预留孔,调整上节段预制外筒12的上预制方块121的方向和位置,完成桥墩1的固定;二、吊装钢系梁2将其架设于两个梁连接方块之间,调整钢系梁2的位置,使钢系梁2上的螺纹孔21梁连接方块上的螺纹预制通孔相对应;三、安装高强度螺栓,使钢系梁2和梁连接方块完成连接;四、钢系梁2安装完毕后再安装上面其它节段的节段预制外筒至标高;五、一次性浇筑内核普通钢筋混凝土。Construction method: 1. Fix the prefabricated outer cylinder 11 of the lower segment, apply ultra-high-performance mortar on the top surface of the prefabricated outer cylinder 11 of the lower segment, and install the prefabricated outer cylinder 12 of the upper segment to the top surface of the prefabricated outer cylinder 11 of the lower segment. Above, insert the embedded steel pipe 112 on the top surface of the prefabricated outer cylinder 11 of the lower segment into the reserved hole of the prefabricated outer cylinder 12 of the upper segment, adjust the direction and position of the upper prefabricated block 121 of the prefabricated outer cylinder 12 of the upper segment, and complete the bridge pier 1. Fixing; 2. Lifting the steel tie beam 2 and erecting it between the two beam connection blocks, adjust the position of the steel tie beam 2, so that the threaded holes on the steel tie beam 2 21 beams are connected to the threaded prefabricated through holes on the block. Correspondingly; 3. Install high-strength bolts to complete the connection between the steel tie beam 2 and the beam connection block; 4. After the steel tie beam 2 is installed, install the prefabricated outer cylinders of other segments above to the elevation; 5. One-time Pour the inner core of ordinary reinforced concrete.

由上述描述可知,本实用新型的有益效果在于:本实用新型提供的半装配式桥墩耗能系梁结构,梁连接方块采用的RUHPC具有良好的耐腐蚀、耐磨性和抗渗性;钢系梁两端的梁连接方块可作为钢系梁的永久支撑,在钢系梁的安装、更换过程中无需搭设支架,施工效率高;相比传统的桥梁的系梁施工采用钢模板施工,可节省大量钢材;钢系梁和两个桥墩之间采用高强度螺栓连接,方便后期钢系梁的更换。It can be seen from the above description that the beneficial effects of the present utility model are: the semi-assembled bridge pier energy-dissipating tie beam structure provided by the present utility model, the RUHPC used in the beam connecting block has good corrosion resistance, wear resistance and impermeability; The beam connection squares at both ends of the beam can be used as the permanent support of the steel tie beam, and there is no need to erect brackets during the installation and replacement of the steel tie beam, and the construction efficiency is high; compared with the traditional bridge tie beam construction using steel formwork construction, it can save a lot of money Steel; high-strength bolts are used between the steel tie beam and the two piers to facilitate the later replacement of the steel tie beam.

进一步的,所述上节段预制外筒12和下节段预制外筒11的材质均为RUHPC。Further, the materials of the upper segment prefabricated outer cylinder 12 and the lower segment prefabricated outer cylinder 11 are both RUHPC.

进一步的,所述钢系梁2与桥墩1之间通过高强度螺栓可拆卸连接。Further, the steel tie beam 2 and the bridge pier 1 are detachably connected by high-strength bolts.

进一步的,所述下节段预制外筒11和上节段预制外筒12之间涂覆有超高性能砂浆层。Further, an ultra-high performance mortar layer is coated between the lower segment prefabricated outer cylinder 11 and the upper segment prefabricated outer cylinder 12 .

进一步的,所述上节段预制外筒12、下节段预制外筒11和预埋钢管112内填充有混凝土。Further, the upper segment prefabricated outer cylinder 12 , the lower segment prefabricated outer cylinder 11 and the embedded steel pipe 112 are filled with concrete.

请参照图1、图2和图3,本实用新型的实施例一为:Please refer to Figure 1, Figure 2 and Figure 3, the first embodiment of the present utility model is:

一种半装配式桥墩耗能系梁结构,包括两段结构相同的桥墩1和连接于两个桥墩1之间的钢系梁2;A semi-fabricated bridge pier energy dissipation tie beam structure, comprising two piers 1 with the same structure and a steel tie beam 2 connected between the two piers 1;

所述桥墩1包括下节段预制外筒11和上节段预制外筒12;The bridge pier 1 includes a lower segment prefabricated outer cylinder 11 and an upper segment prefabricated outer cylinder 12;

所述下节段预制外筒11的顶端设有加厚段13,所述下节段预制外筒11的顶部中央设有预埋钢管112,所述预埋钢管112一端埋覆于加厚段13内,另一端延伸到下节段预制外筒11顶面外,所述下节段预制外筒11的加厚段13的侧壁上设置有下预制方块113;The top of the lower segment prefabricated outer cylinder 11 is provided with a thickened section 13, and the center of the top of the lower segment prefabricated outer cylinder 11 is provided with a pre-embedded steel pipe 112, and one end of the pre-embedded steel pipe 112 is buried in the thickened section 13, the other end extends to the outside of the top surface of the lower segment prefabricated outer cylinder 11, and a lower prefabricated block 113 is provided on the side wall of the thickened section 13 of the lower segment prefabricated outer cylinder 11;

所述上节段预制外筒12设置于下节段预制外筒11的上方,所述上节段预制外筒12的底端设置有加厚段13,所述下节段预制外筒11的底面设置有供预埋钢管112伸入的预留孔,所述上节段预制外筒12的加厚段13的侧壁上设置有上预制方块121;The upper segment prefabricated outer cylinder 12 is arranged above the lower segment prefabricated outer cylinder 11 , the bottom end of the upper segment prefabricated outer cylinder 12 is provided with a thickening section 13 , and the lower segment prefabricated outer cylinder 11 is provided with a thickened section 13 . The bottom surface is provided with a reserved hole for the embedded steel pipe 112 to extend into, and an upper prefabricated block 121 is provided on the side wall of the thickened section 13 of the upper segment prefabricated outer cylinder 12;

所述上预制方块121和下预制方块113相对组成梁连接方块,所述梁连接方块上设置有多个水平方向的螺纹预制通孔;The upper prefabricated block 121 and the lower prefabricated block 113 form a beam connecting block relatively, and a plurality of horizontal thread prefabricated through holes are arranged on the beam connecting block;

所述钢系梁2的两端设置有螺纹孔21,所述钢系梁2通过螺栓固定连接于两个梁连接方块之间;Both ends of the steel tie beam 2 are provided with threaded holes 21, and the steel tie beam 2 is fixedly connected between two beam connection blocks by bolts;

所述上节段预制外筒12和下节段预制外筒11的材质均为RUHPC;The materials of the upper segment prefabricated outer cylinder 12 and the lower segment prefabricated outer cylinder 11 are both RUHPC;

所述钢系梁2与桥墩1之间通过高强度螺栓可拆卸连接;The steel tie beam 2 and the bridge pier 1 are detachably connected by high-strength bolts;

所述下节段预制外筒11和上节段预制外筒12之间涂覆有超高性能砂浆层;An ultra-high-performance mortar layer is coated between the lower segment prefabricated outer cylinder 11 and the upper segment prefabricated outer cylinder 12;

所述上节段预制外筒12、下节段预制外筒11和预埋钢管112内填充有混凝土。The upper segment prefabricated outer cylinder 12 , the lower segment prefabricated outer cylinder 11 and the embedded steel pipe 112 are filled with concrete.

综上所述,本实用新型提供的半装配式桥墩耗能系梁结构,梁连接方块采用的RUHPC具有良好的耐腐蚀、耐磨性和抗渗性;钢系梁两端的梁连接方块可作为钢系梁的永久支撑,在钢系梁的安装、更换过程中无需搭设支架,施工效率高;相比传统的桥梁的系梁施工采用钢模板施工,可节省大量钢材;钢系梁和两个桥墩之间采用高强度螺栓连接,方便后期钢系梁的更换。To sum up, in the semi-fabricated bridge pier energy-dissipating tie beam structure provided by the present invention, the RUHPC used in the beam connecting block has good corrosion resistance, wear resistance and impermeability; the beam connecting blocks at both ends of the steel tie beam can be used as The permanent support of the steel tie beam does not require the erection of brackets during the installation and replacement of the steel tie beam, and the construction efficiency is high; compared with the traditional bridge tie beam construction using steel formwork construction, a large amount of steel can be saved; the steel tie beam and two The bridge piers are connected by high-strength bolts to facilitate the replacement of the steel tie beams in the later stage.

以上所述仅为本实用新型的实施例,并非因此限制本实用新型的专利范围,凡是利用本实用新型说明书及附图内容所作的等同变换,或直接或间接运用在相关的技术领域,均同理包括在本实用新型的专利保护范围内。The above are only the embodiments of the present utility model, and are not intended to limit the scope of the present utility model patent. All equivalent transformations made by using the contents of the present utility model description and accompanying drawings, or directly or indirectly applied in related technical fields, are the same as The principles are included in the scope of patent protection of the present invention.

Claims (5)

1. A semi-assembly type pier energy-consuming tie beam structure is characterized by comprising two sections of piers with the same structure and a steel tie beam connected between the two piers;
the bridge pier comprises a lower section prefabricated outer cylinder and an upper section prefabricated outer cylinder;
the top end of the lower section prefabricated outer barrel is provided with a thickened section, the center of the top of the lower section prefabricated outer barrel is provided with a pre-buried steel pipe, one end of the pre-buried steel pipe is buried in the thickened section, the other end of the pre-buried steel pipe extends out of the top of the lower section prefabricated outer barrel, and the side wall of the thickened section of the lower section prefabricated outer barrel is provided with a lower prefabricated square block;
the upper section prefabricated outer barrel is arranged above the lower section prefabricated outer barrel, a thickened section is arranged at the bottom end of the upper section prefabricated outer barrel, a preformed hole for a pre-buried steel pipe to extend into is formed in the bottom surface of the lower section prefabricated outer barrel, and an upper prefabricated square block is arranged on the side wall of the thickened section of the upper section prefabricated outer barrel;
the upper prefabricated square block and the lower prefabricated square block relatively form a beam connecting square block, and a plurality of threaded prefabricated through holes in the horizontal direction are formed in the beam connecting square block;
threaded holes are formed in two ends of the steel tie beam, and the steel tie beam is fixedly connected between the two beam connecting blocks through bolts.
2. The semi-fabricated pier energy dissipating tie beam structure of claim 1, wherein the upper prefabricated outer cylinder and the lower prefabricated outer cylinder are both RUHPC.
3. The semi-fabricated pier energy dissipation tie beam structure of claim 1, wherein the steel tie beam is detachably connected with a pier through high-strength bolts.
4. The semi-fabricated pier energy dissipating tie beam structure of claim 1, wherein an ultra-high performance mortar layer is coated between the lower section prefabricated outer cylinder and the upper section prefabricated outer cylinder.
5. The semi-assembly type pier energy dissipation tie beam structure of claim 1, wherein the upper section prefabricated outer cylinder, the lower section prefabricated outer cylinder and the embedded steel pipe are filled with concrete.
CN201921732496.6U 2019-10-16 2019-10-16 Energy-consuming tie beam structure of semi-assembly type bridge pier Active CN211312173U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921732496.6U CN211312173U (en) 2019-10-16 2019-10-16 Energy-consuming tie beam structure of semi-assembly type bridge pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921732496.6U CN211312173U (en) 2019-10-16 2019-10-16 Energy-consuming tie beam structure of semi-assembly type bridge pier

Publications (1)

Publication Number Publication Date
CN211312173U true CN211312173U (en) 2020-08-21

Family

ID=72076464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921732496.6U Active CN211312173U (en) 2019-10-16 2019-10-16 Energy-consuming tie beam structure of semi-assembly type bridge pier

Country Status (1)

Country Link
CN (1) CN211312173U (en)

Similar Documents

Publication Publication Date Title
CN108505433B (en) Pier structure and construction method thereof
CN104746422B (en) A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method
CN103924505B (en) Use prefabricated steel-concrete combination T beam and the construction method of Wavelike steel webplate
CN101694110B (en) Beam-column joint connection structure and its construction method
CN107190635B (en) Dumbbell-shaped concrete-filled steel tubular composite pier and its connection structure and method with bearing platform
CN106481023B (en) Prefabricated steel-concrete composite beam structure and its implementation method
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN106381804B (en) A kind of precast assembly bridge pier and its Joining Technology using U-shaped reinforcement fabrication
CN101775844A (en) Connecting joint of ring beam of steel core concrete column used for topdown construction method foundation pit engineering
CN108571070A (en) A kind of Prefabricated concrete-filled steel tube ring beam connection structure and construction method
CN105926427A (en) Pier and beam transitional connecting structure
CN110468727B (en) Temporary prestress tensioning pedestal and lifting point integrated structure of segmental beam and construction method
CN108951399A (en) A kind of Single-box multi-chamber box beam bridge and its construction method
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN114592436A (en) Pier capping beam lower support system and construction method thereof
CN103469735B (en) The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN108755945A (en) A kind of prefabricated assembled concrete bean column node and its construction method
CN206655141U (en) A kind of steel cantilever combined bridge deck widens reconstruction structure
CN209669688U (en) A semi-fabricated thin-walled bridge pier
CN111455802A (en) A bridge upper assembled composite structure and its construction technology
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN109972512A (en) A cast-in-place construction method for a profiled steel plate-concrete composite bridge deck
CN102392417A (en) Dual-cantilever bearing support structure for large steel pipe and installation method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant