CN209669688U - A kind of half assembled thin-wall piers - Google Patents

A kind of half assembled thin-wall piers Download PDF

Info

Publication number
CN209669688U
CN209669688U CN201920084236.6U CN201920084236U CN209669688U CN 209669688 U CN209669688 U CN 209669688U CN 201920084236 U CN201920084236 U CN 201920084236U CN 209669688 U CN209669688 U CN 209669688U
Authority
CN
China
Prior art keywords
steel
cushion cap
prefabricated subsection
high performance
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920084236.6U
Other languages
Chinese (zh)
Inventor
林上顺
林长庚
詹刚毅
夏樟华
杨切
谢铭勤
王金泽
陈苏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian University of Technology
Original Assignee
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian University of Technology filed Critical Fujian University of Technology
Priority to CN201920084236.6U priority Critical patent/CN209669688U/en
Application granted granted Critical
Publication of CN209669688U publication Critical patent/CN209669688U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of half assembled thin-wall piers, belong to technical field of bridge engineering, the half assembled thin-wall piers include cushion cap and multiple prefabricated subsections, the prefabricated subsection includes longitudinal hollow steel pipe, longitudinal exposed steel bar, feeding-passage and the tapping channel of outsourcing ultra-high performance concrete, and hollow steel pipe is axially arranged with feeding-passage and tapping channel along longitudinal direction in the ultra-high performance concrete of the self-compaction.Steel are all embedded in UHPC corrosion-resistant, that impermeability is strong, are suitable for the bridge pier structure of extreme environment by half assembled thin-wall piers provided by the utility model;Entire bridge pier low cost, prefabricated subsection can complete the process in advance, and lifting is light-weight, does not need large scale equipment, is not restricted by construction environment, so that the short construction period of bridge pier, particularly suitable for Oversea bridge and Urban Bridge.

Description

A kind of half assembled thin-wall piers
Technical field
The utility model belongs to technical field of bridge engineering, and in particular to a kind of half assembled thin-wall piers.
Background technique
The thin wall-type reinforced concrete bridge pier of integral cast-in-situ has obtained in the highway in China and Urban Bridge extensively General application.However, the construction due to cast-in-place bridge pier needs installation template at the scene and assembling reinforcement, and pour a large amount of coagulations Soil leads to long construction period, and is affected to surrounding enviroment.Construction in city often occupies existing road, Chang Zao The traffic jam of formative year has seriously affected the road in city.And in some bridge spanning the sea work progress, due to by Construction to the influence of harsh weather and stormy waves, the thin wall-type reinforced concrete bridge pier of integral cast-in-situ is more difficult, construction quality It is difficult to ensure, and the generally existing serious corrosion phenomenon of concrete pier of built bridge spanning the sea.It is some over strait big thus Bridge also uses bridge pier precast segment assembling construction, mostly uses total cross-section precast assembly, but this erection method lifting weight is very Greatly, heavy mechanical equipment is needed, and connector splicing seams mostly use mortar, horizontal shear strength is weaker.
Ultra-high performance concrete (Ultra-HighPerformance Concrete, UHPC), due to its resistance to corrosion By force, gradually it is applied to bridge spanning the sea etc. in recent years in compared on the bridge in adverse circumstances, application No. is 201711028881.8 Chinese patent discloses the construction and the practice of a kind of connection of precast assembly bridge pier segment, the connection structure Make the precast assembly steel pipe encased concrete bridge to connect based on ultra-high performance concrete (UHPC), inner sleeve joint steel pipe with high-strength bolt Pier;UHPC is applied between precast pier segment in connection, takes full advantage of the resistance to compression and tensile property of UHPC brilliance, thus Solve the problems, such as that the connection of precast pier segment is weak.But in the structure, the shrinkage of cast-in-place UHPC connector is larger, with prefabricated portion The concrete divided may be detached from faying face;The used structure that UHPC is poured from horizontal direction, UHPC's is closely knit Degree is difficult to ensure;Prefabricated subsection self weight is larger, constructs difficult;Steel exposure in air, needs periodically to derust, the later period Maintenance cost is big.
Utility model content
In order to overcome the defects of the prior art described above, the technical problem to be solved by the utility model is to provide a kind of resistance to Half strong and easy for construction assembled thin-wall piers of burn into impermeability.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model are as follows: a kind of half assembled thin-wall piers, Including sequentially connected cushion cap from top to bottom and multiple prefabricated subsections;
The cushion cap is equipped with the cushion cap steel pipe and cushion cap longitudinal direction exposed steel bar being vertically arranged;
The prefabricated subsection includes that the longitudinal hollow steel pipe, longitudinal exposed steel bar, charging of outsourcing ultra-high performance concrete are logical Road and tapping channel;Hollow steel pipe is axially arranged with feeding-passage and tapping channel along longitudinal direction in the ultra-high performance concrete, The feeding-passage and tapping channel extend through the setting of self-compaction super performance concrete;
Pass through the exposed steel of welded connecting and the longitudinal direction between longitudinal hollow steel pipe between the prefabricated subsection Welded connecting between muscle is spliced;
Pass through the welded connecting of the longitudinal hollow steel pipe and the cushion cap steel pipe between the prefabricated subsection and cushion cap, with And the welded connecting of the longitudinal exposed steel bar and cushion cap longitudinal direction exposed steel bar is spliced;
Stitching portion between the prefabricated subsection is filled with the ultra-high performance concrete of self-compaction by feeding-passage charging;
Stitching portion between the prefabricated subsection and cushion cap is filled with the very-high performance of self-compaction by feeding-passage charging Concrete.
Wherein, the stitching portion between the prefabricated subsection and the stitching portion between prefabricated subsection and cushion cap are equipped with punching block Plate, the steel form include multiple fixation steel plates, multiple fixed steel bars and multiple fixed anchorages;
Multiple fixed steel bars are horizontally set at the upper end of two ends and cushion cap of prefabricated subsection respectively, multiple described Fixation steel plate is equipped with several apertures, and the diameter of the aperture and the diameter of fixed steel bars are identical, outside described fixed steel bars one end Dew, the exposed junction of the fixed steel bars pass through from the aperture on fixation steel plate and are connected by fixed anchorage and fixation steel plate fastening It connects.
Wherein, several lateral hollow steel pipes are provided through at the top of the prefabricated subsection, in the transverse direction hollow steel pipe Equipped with stress fashioned iron.
The utility model has the beneficial effects that: the half assembled thin-wall piers of the utility model, including from top to bottom according to The cushion cap of secondary connection and multiple prefabricated subsections;The steel of prefabricated subsection are all embedded in superelevation corrosion-resistant, that impermeability is strong In energy concrete (UHPC), it is suitable for the bridge pier structure of extreme environment;The prefabricated subsection is different from existing prefabricated subsection, Feeding-passage and tapping channel are equipped in UHPC, when construction in later period pours to feeding-passage, the very-high performance coagulation of self-compaction Soil is poured into from feeding-passage, is flowed out from tapping channel, and then fill the ultra-high performance concrete of self-compaction in stitching portion, due to it Longitudinal height is higher, when the ultra-high performance concrete of self-compaction is perfused, only relies on the pressure that gravity generates bottom without pressurization It can guarantee that concrete is in dense state at bottom seam, convenient and quick construction substantially increases the speed of splicing, mentions simultaneously The high intensity of stitching portion;And normal concrete is perfused in longitudinal hollow steel pipe, it is common instead of bridge pier over the sea Maritime concrete, can substantially save the cost, reduce bridge cost;All prefabricated subsections can complete the process in advance, lift weight Gently, large scale equipment is not needed when construction in later period, is not restricted by construction environment, conducive to the construction period for shortening bridge pier, to peripheral ring Border and road traffic influence are small, especially suitable for Oversea bridge and Urban Bridge.
Detailed description of the invention
Fig. 1 is the top view cross section structure of the prefabricated subsection of half assembled thin-wall piers of specific embodiment of the present invention Schematic diagram;
Fig. 2 is that half assembled thin-wall piers of specific embodiment of the present invention face the schematic diagram of the section structure;
Fig. 3 is the side of stitching portion between the prefabricated subsection of half assembled thin-wall piers of specific embodiment of the present invention Depending on the schematic diagram of the section structure;
Fig. 4 is the prefabricated subsection of half assembled thin-wall piers of specific embodiment of the present invention and the side of operation platform Depending on the schematic diagram of the section structure;
Label declaration:
1, longitudinal hollow steel pipe;2, longitudinal exposed steel bar;3, ultra-high performance concrete;4, feeding-passage;5, tapping channel; 6, cushion cap;7, cushion cap steel pipe;8, fixation steel plate;9, fixed steel bars;10, fixed anchorage;11, normal concrete;12, laterally hollow Steel pipe;13, stress fashioned iron;14, operation platform.
Specific embodiment
For technology contents, the objects and the effects that the utility model is described in detail, below in conjunction with embodiment and match Attached drawing is closed to be explained.
The design of the utility model most critical is: logical by the feeding-passage and discharging that are arranged vertical in rectangular steel tube Road, convenient in the case where no Additional pressurizations, generating pressure when construction in later period just to stitching portion bottom, guaranteeing at bottom seam Concrete is in dense state, convenient for the assembly between prefabricated subsection and between prefabricated subsection and cushion cap is rapidly completed.
Please refer to Fig. 1 to Fig. 4, a kind of half assembled thin-wall piers, including sequentially connected cushion cap 6 and multiple from top to bottom Prefabricated subsection;
The cushion cap 6 is equipped with the cushion cap steel pipe 7 and cushion cap longitudinal direction exposed steel bar being vertically arranged;
The prefabricated subsection include the longitudinal hollow steel pipe 1 for being surrounded by ultra-high performance concrete 3 outside, longitudinal exposed steel bar 2, into Expect channel 4 and tapping channel 5;The longitudinal direction exposed steel bar 2 is embedded in ultra-high performance concrete 3, the very-high performance coagulation Hollow steel pipe 1 is axially arranged with feeding-passage 4 and tapping channel 5 along longitudinal direction in soil 3, and the feeding-passage 4 and tapping channel 5 divide It Guan Chuan not the setting of ultra-high performance concrete 3;
It is exposed by welded connecting between longitudinal hollow steel pipe 1 and the longitudinal direction between the prefabricated subsection Welded connecting between reinforcing bar 2 is spliced;
Connected between the prefabricated subsection and cushion cap 6 by the welding of longitudinal hollow steel pipe 1 and the cushion cap steel pipe 7 It connects and longitudinal exposed steel bar 2 and the welded connecting of cushion cap longitudinal direction exposed steel bar is spliced;
Stitching portion between the prefabricated subsection is filled with the very-high performance coagulation of self-compaction by the charging of feeding-passage 4 Soil;
Stitching portion between the prefabricated subsection and cushion cap 6 is filled with the superelevation of self-compaction by the charging of feeding-passage 4 It can concrete.
As can be seen from the above description, the utility model has the beneficial effects that: half assembled thin-walled provided by the utility model Bridge pier, including sequentially connected cushion cap from top to bottom and multiple prefabricated subsections;The steel of prefabricated subsection be all embedded in it is corrosion-resistant, In the strong ultra-high performance concrete of impermeability (UHPC), it is suitable for the bridge pier structure of extreme environment;The prefabricated subsection Different from existing prefabricated subsection, feeding-passage and tapping channel are equipped in UHPC, when construction in later period, pours to feeding-passage, from Closely knit ultra-high performance concrete is poured into from feeding-passage, is flowed out from tapping channel, and then fills the super of self-compaction in stitching portion High performance concrete when the ultra-high performance concrete of self-compaction is perfused, only relies on weight without pressurization since its longitudinal height is higher Power can guarantee that concrete is in dense state at bottom seam to the pressure that bottom generates, and convenient and quick construction greatly improves The speed of splicing, while improving the intensity of stitching portion;And normal concrete is perfused in longitudinal hollow steel pipe, instead of The common maritime concrete of bridge pier over the sea, can substantially save the cost, reduce bridge cost;All prefabricated subsections can shift to an earlier date It completes the process, lifts light-weight, when construction in later period does not need large scale equipment, is not restricted by construction environment, conducive to bridge pier is shortened Construction period, it is small on surrounding enviroment and road traffic influence, especially suitable for Oversea bridge and Urban Bridge.
Further, the stitching portion between the prefabricated subsection and the stitching portion between prefabricated subsection and cushion cap are equipped with steel Template, the steel form include multiple fixation steel plates 8, multiple fixed steel bars 9 and multiple fixed anchorages 10;
Multiple fixed steel bars 9 are horizontally set at the upper end of prefabricated subsection at top, under prefabricated subsection respectively It holds at bottom and the upper end of cushion cap, multiple fixation steel plates 8 is equipped with several apertures, the diameter of the aperture and fixation The diameter of reinforcing bar 9 is identical, and one end of the fixed steel bars 9 is exposed, and the exposed junction of the fixed steel bars 9 is from fixation steel plate 8 It passes through in aperture and is fastenedly connected by fixed anchorage 10 with fixation steel plate 8.
Seen from the above description, passed through admittedly by the way that fixation steel plate, the fixation steel plate and fixed steel bars are arranged in stitching portion Determine anchorage to be fastenedly connected, and fixed steel bars are set to the upper and lower end parts in prefabricated subsection, can form steel form in stitching portion, It can play the role of reinforcing stitching portion in the assembled stage, be removed after the completion of splicing, will not influence bridge pier exterior appearance Property.
Further, several lateral hollow steel pipes 12 are provided through at the top of the prefabricated subsection, the transverse direction is hollow Stress fashioned iron 13 is equipped in steel pipe 12.
Seen from the above description, several lateral hollow steel pipes are being reserved at prefabricated subsection pier coping portion, apply force type Steel can extend there through, and to erection construction platform, main part of the force of the stress fashioned iron as operation platform plays carrying platform The effect of upper all workers and weight of equipment.Worker can carry out reinforcing bar binding, steel-pipe welding, steel form assembly on operation platform Equal operations.To the end of operation, platform is dismantled.The use of a large amount of scaffold can be saved, and build and all facilitate with disassembly, Fast, it while can be built between double-limb pier peer prefabricated subsection, the security performance of operation platform also significantly improves.
The embodiments of the present invention one are as follows:
Half assembled thin-wall piers, including sequentially connected cushion cap 6 and multiple prefabricated subsections from top to bottom;
The cushion cap 6 is equipped with the cushion cap steel pipe 7 and cushion cap longitudinal direction exposed steel bar being vertically arranged;
The prefabricated subsection includes two longitudinal hollow steel pipes 1, the exposed steel in multiple longitudinal directions of outsourcing ultra-high performance concrete 3 Muscle 2, feeding-passage 4 and tapping channel 5;Longitudinal direction 1 both ends of hollow steel pipe are exposed, and multiple longitudinal exposed steel bars 2 are pre-buried In ultra-high performance concrete 3 and both ends are exposed, and hollow steel pipe 1 is axially arranged with along longitudinal direction in the ultra-high performance concrete 3 Feeding-passage 4 and tapping channel 5, the feeding-passage 4 and tapping channel 5 extend through the setting of ultra-high performance concrete 3;
It is exposed by welded connecting between longitudinal hollow steel pipe 1 and the longitudinal direction between the prefabricated subsection Welded connecting between reinforcing bar 2 is spliced;
Connected between the prefabricated subsection and cushion cap 6 by the welding of longitudinal hollow steel pipe 1 and the cushion cap steel pipe 7 It connects and longitudinal exposed steel bar 2 and the welded connecting of cushion cap longitudinal direction exposed steel bar is spliced;
Stitching portion between the prefabricated subsection is filled with the very-high performance coagulation of self-compaction by the charging of feeding-passage 4 Soil;
Stitching portion between the prefabricated subsection and cushion cap 6 is filled with the superelevation of self-compaction by the charging of feeding-passage 4 It can concrete.
The embodiments of the present invention two are as follows:
Half assembled thin-wall piers, including sequentially connected cushion cap 6 and multiple prefabricated subsections from top to bottom;
The cushion cap 6 is equipped with the cushion cap steel pipe 7 and cushion cap longitudinal direction exposed steel bar being vertically arranged;
The prefabricated subsection include longitudinal hollow steel pipe 1 of outsourcing ultra-high performance concrete 3, multiple longitudinal exposed steel bars 2, Feeding-passage 4 and tapping channel 5;Longitudinal direction 1 both ends of hollow steel pipe are exposed, and multiple longitudinal exposed steel bars 2 are embedded in super In high performance concrete 3 and both ends are exposed, and hollow steel pipe 1 is axially arranged with charging along longitudinal direction in the ultra-high performance concrete 3 Channel 4 and tapping channel 5, the feeding-passage 4 and tapping channel 5 are vertical circular hollow steel pipe, the feeding-passage 4 and are gone out Material channel 5 extends through the setting of ultra-high performance concrete 3;The reserved of several horizontal directions is arranged in the end of the prefabricated subsection Hole;
It is exposed by welded connecting between longitudinal hollow steel pipe 1 and the longitudinal direction between the prefabricated subsection Welded connecting between reinforcing bar 2 is spliced;
Connected between the prefabricated subsection and cushion cap 6 by the welding of longitudinal hollow steel pipe 1 and the cushion cap steel pipe 7 It connects and longitudinal exposed steel bar 2 and the welded connecting of cushion cap longitudinal direction exposed steel bar is spliced;
Stitching portion between the prefabricated subsection is filled with the very-high performance coagulation of self-compaction by the charging of feeding-passage 4 Soil;
Stitching portion between the prefabricated subsection and cushion cap 6 is filled with the superelevation of self-compaction by the charging of feeding-passage 4 It can concrete;
The equal stitching portion in stitching portion between the prefabricated subsection between prefabricated subsection and cushion cap is equipped with steel form, described Steel form includes multiple fixation steel plates 8, multiple fixed steel bars 9 and multiple fixed anchorages;
Multiple fixed steel bars 9 are horizontally set at the upper end of prefabricated subsection at top, under prefabricated subsection respectively It holds at bottom and the upper end of cushion cap, multiple fixation steel plates 8 is equipped with several apertures, the diameter of the aperture and fixation The diameter of reinforcing bar 9 is identical, and the exposed junction of the fixed steel bars 9 passes through from the aperture on fixation steel plate 8 and by fixed anchorage 10 are fastenedly connected with fixation steel plate 8;The size of the fixed steel bars 9 matches with preformed hole.
The embodiments of the present invention three are as follows:
The half assembled thin-wall piers, including sequentially connected cushion cap 6 and multiple prefabricated subsections from top to bottom;
The cushion cap steel pipe 7 being vertically arranged and cushion cap longitudinal direction exposed steel bar are embedded on the cushion cap 6;
The prefabricated subsection includes longitudinal hollow steel pipe 1 of outsourcing ultra-high performance concrete 3, longitudinal exposed steel bar 2, charging Channel 4 and tapping channel 5;Multiple longitudinal exposed steel bars 2 are embedded in ultra-high performance concrete 3 and both ends are exposed, described Hollow steel pipe 1 is axially arranged with feeding-passage 4 and tapping channel 5, the feeding-passage 4 along longitudinal direction in ultra-high performance concrete 3 It is vertical circular hollow steel pipe with tapping channel 5, the feeding-passage 4 and tapping channel 5 extend through ultra-high performance concrete 3 Setting;The preformed hole of several horizontal directions is arranged in the end of the prefabricated subsection;
Stitching portion between the prefabricated subsection is equipped with steel form, and the steel form includes multiple fixation steel plates 8, Duo Gegu Determine reinforcing bar 9 and multiple fixed anchorages;The size of the fixed steel bars 9 matches with preformed hole;
Multiple fixed steel bars 9 are horizontally set at the upper end of prefabricated subsection at top and under prefabricated subsection respectively It holds at bottom, multiple fixation steel plates 8 are equipped with several apertures, the diameter of the aperture and the diameter of fixed steel bars 9 Identical, the exposed junction of the fixed steel bars 9 passes through from the aperture on fixation steel plate 8 and by fixed anchorage 10 and fixation steel plate 8 are fastenedly connected;
It is provided through several lateral hollow steel pipes 12 at the top of the prefabricated subsection, is set in the transverse direction hollow steel pipe 12 There is stress fashioned iron 13.
The assembly method of above-mentioned half assembled thin-wall piers, specifically includes the following steps:
Step 1: the cushion cap steel pipe 7 of the lower end of longitudinal hollow steel pipe 1 of the first prefabricated subsection and cushion cap 6 is subjected to welding company It connects, then longitudinal exposed steel bar 2 of the first prefabricated subsection and the cushion cap longitudinal direction exposed steel bar of cushion cap 6 is welded to connect;
Step 2: by one end insertion preformed hole of multiple fixed steel bars 9, being set to fixed steel bars 9 under prefabricated subsection The aperture of fixation steel plate 8 is passed through fixed steel bars 9 by the upper end at end and cushion cap, then by fixed anchorage 10 by fixation steel plate 8 and admittedly Determine reinforcing bar 9 to be fastenedly connected, obtains the first steel form;
Step 3: normal concrete 11 being perfused into longitudinal hollow steel pipe 1;Then self-compaction is perfused into feeding-passage 4 Ultra-high performance concrete, until the ultra-high performance concrete of self-compaction is overflowed out of tapping channel 5;
Step 4: stress fashioned iron 13 being passed through from several lateral hollow steel pipes 12 at the top of prefabricated first segment, in stress Erection construction platform 14 on fashioned iron 13;
Step 5: the second prefabricated subsection being lifted to the first prefabricated subsection, by longitudinal hollow steel of the first prefabricated subsection Longitudinal hollow steel pipe 1 of pipe 1 and the second prefabricated subsection is welded to connect, then by longitudinal exposed steel bar 2 of the first prefabricated subsection It is welded to connect with longitudinal exposed steel bar 2 of the second prefabricated subsection;
Step 6: by one end insertion preformed hole of multiple fixed steel bars 9, fixed steel bars 9 being made to be set to the first prefabricated subsection Upper end and the second prefabricated subsection lower end, the aperture of fixation steel plate 8 is passed through into fixed steel bars 9, then will by fixed anchorage 10 Fixation steel plate 8 is fastenedly connected with fixed steel bars 9, obtains the second steel form;
Step 7: repeating step 3-6 until the assembly of all prefabricated subsections is completed;
Step 8: removing steel form;
Step 9: stress fashioned iron 13 being extracted out from lateral hollow steel pipe 12, self-compaction is perfused into lateral hollow steel pipe 12 Ultra-high performance concrete, then lateral hollow steel pipe 12 nozzle smear anticorrosive paint.
The operation platform 14 includes stress fashioned iron 13, the platform being arranged on stress fashioned iron 13, diagonal brace fashioned iron and guardrail, Stress steel plate is arranged in 13 bottom surface of stress fashioned iron.
The operation platform 15 includes operation platform steel bar stress 14 and is arranged in flat on operation platform steel bar stress 14 Platform and guardrail, 14 bottom surface of operation platform steel bar stress be arranged stress steel plate, stress steel plate one end and operation platform by Power reinforcing bar 14 connects the other end and the side wall of prefabricated subsection connects.
In conclusion a kind of half assembled thin-wall piers provided by the utility model, including cushion cap and multiple prefabricated subsections, The steel of prefabricated subsection are all embedded in ultra-high performance concrete (UHPC) corrosion-resistant, that impermeability is strong, are suitable for extremely disliking The bridge pier structure of bad environment;The prefabricated subsection is different from existing prefabricated subsection, and feeding-passage is equipped in UHPC and discharging is logical Road, when construction in later period, pour to feeding-passage, and the ultra-high performance concrete of self-compaction is poured into from feeding-passage, from tapping channel stream Out, and then in stitching portion the ultra-high performance concrete of self-compaction is filled, since its longitudinal height is higher, the superelevation of self-compaction is perfused When performance concrete, only relying on gravity without pressurization can guarantee that concrete is in close at bottom seam to the pressure that bottom generates Real state, convenient and quick construction substantially increases the speed of splicing, while improving the intensity of stitching portion;And longitudinal hollow Normal concrete is perfused in steel pipe, instead of the common maritime concrete of bridge pier over the sea, can substantially save the cost, drop Low bridge beam cost;All prefabricated subsections can complete the process in advance, lift light-weight, and when construction in later period does not need large scale equipment, no Restricted by construction environment, conducive to the construction period for shortening bridge pier, surrounding enviroment and road traffic are influenced it is small, especially suitable for across Sea-bridge beam and Urban Bridge;
Fastening company is carried out by fixed anchorage by the way that fixation steel plate, the fixation steel plate and fixed steel bars are arranged in stitching portion It connects, and fixed steel bars are set to the upper and lower end parts in prefabricated subsection, can form steel form in stitching portion, it can be from the assembled stage To the effect reinforced to stitching portion;
By reserving several lateral hollow steel pipes in prefabricated subsection, operation platform, force type can be built in splicing Steel is passed through from lateral hollow steel pipe, as the main part of the force of operation platform, is played all workers on carrying platform and is set The effect of standby weight, worker can carry out reinforcement welding, steel-pipe welding, the operations such as steel form assembly on operation platform.To operation Terminate, dismantles platform.The use of a large amount of scaffold can be saved, and build with dismantle it is all convenient, fast, while can be in It is built between double-limb pier peer prefabricated subsection, the security performance of operation platform also significantly improves.
The above description is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all Equivalents made based on the specification and figures of the utility model are applied directly or indirectly in relevant technology neck Domain is also included in the patent protection scope of the utility model.

Claims (3)

1. a kind of half assembled thin-wall piers, which is characterized in that including sequentially connected cushion cap from top to bottom and multiple prefabricated Segment;
The cushion cap is equipped with the cushion cap steel pipe and cushion cap longitudinal direction exposed steel bar being vertically arranged;
The prefabricated subsection include longitudinal hollow steel pipe of outsourcing ultra-high performance concrete, longitudinal exposed steel bar, feeding-passage and Tapping channel;The longitudinal direction exposed steel bar is embedded in ultra-high performance concrete, empty along longitudinal direction in the ultra-high performance concrete Heart steel pipe is axially arranged with feeding-passage and tapping channel, and the feeding-passage and tapping channel extend through very-high performance coagulation Soil setting;
Between the prefabricated subsection by welded connecting between longitudinal hollow steel pipe and longitudinal exposed steel bar it Between welded connecting spliced;
Pass through the welded connecting of the longitudinal hollow steel pipe and the cushion cap steel pipe, Yi Jisuo between the prefabricated subsection and cushion cap The welded connecting for stating longitudinal exposed steel bar and cushion cap longitudinal direction exposed steel bar is spliced;
Stitching portion between the prefabricated subsection is filled with the ultra-high performance concrete of self-compaction by feeding-passage charging;
Stitching portion between the prefabricated subsection and cushion cap is filled with the very-high performance coagulation of self-compaction by feeding-passage charging Soil.
2. half assembled thin-wall piers according to claim 1, which is characterized in that the stitching portion between the prefabricated subsection Stitching portion between prefabricated subsection and cushion cap is equipped with steel form, and the steel form includes multiple fixation steel plates, multiple fixations Reinforcing bar and multiple fixed anchorages;
Multiple fixed steel bars are horizontally set at the upper end of two ends and cushion cap of prefabricated subsection, multiple fixations respectively Steel plate is equipped with several apertures, and the diameter of the aperture and the diameter of fixed steel bars are identical, the exposed junctions of the fixed steel bars from It passes through in aperture on fixation steel plate and is fastenedly connected by fixed anchorage with fixation steel plate.
3. half assembled thin-wall piers according to claim 1, which is characterized in that the top of the prefabricated subsection, which is run through, to be set Several lateral hollow steel pipes are equipped with, are equipped with stress fashioned iron in the transverse direction hollow steel pipe.
CN201920084236.6U 2019-01-18 2019-01-18 A kind of half assembled thin-wall piers Active CN209669688U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920084236.6U CN209669688U (en) 2019-01-18 2019-01-18 A kind of half assembled thin-wall piers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920084236.6U CN209669688U (en) 2019-01-18 2019-01-18 A kind of half assembled thin-wall piers

Publications (1)

Publication Number Publication Date
CN209669688U true CN209669688U (en) 2019-11-22

Family

ID=68566032

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920084236.6U Active CN209669688U (en) 2019-01-18 2019-01-18 A kind of half assembled thin-wall piers

Country Status (1)

Country Link
CN (1) CN209669688U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109722984A (en) * 2019-01-18 2019-05-07 福建工程学院 Half assembled thin-wall piers of one kind and its assembly method
CN111827335A (en) * 2020-07-31 2020-10-27 中铁第四勘察设计院集团有限公司 Connection structure of composite steel pipe pile and bearing platform
CN113123219A (en) * 2020-01-10 2021-07-16 中国国家铁路集团有限公司 UHPC seam-based prefabricated assembled pier structure and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109722984A (en) * 2019-01-18 2019-05-07 福建工程学院 Half assembled thin-wall piers of one kind and its assembly method
CN109722984B (en) * 2019-01-18 2024-02-06 福建工程学院 Semi-assembled thin-wall pier and assembly method thereof
CN113123219A (en) * 2020-01-10 2021-07-16 中国国家铁路集团有限公司 UHPC seam-based prefabricated assembled pier structure and construction method
CN111827335A (en) * 2020-07-31 2020-10-27 中铁第四勘察设计院集团有限公司 Connection structure of composite steel pipe pile and bearing platform

Similar Documents

Publication Publication Date Title
CN105113389B (en) Assembled type bridge pier column member with steel-concrete composite structure
CN103938864B (en) Infilled wall Constructional Col-umn Construction engineering method
CN209669688U (en) A kind of half assembled thin-wall piers
CN108505433B (en) Pier structure and construction method thereof
CN206368533U (en) A kind of wide-angle tilt profile steel concrete column constructing structure
CN104746422A (en) Bridge prefabricated hollow pier column post-poured connecting structure and construction method
CN207794327U (en) A kind of precast assembly structure of Subway Station Platform plate
CN203569582U (en) Connecting structure of concrete pipe pile and bearing platform
CN109457597A (en) A kind of flat assembly prefabrication and assembly construction hollow pier splicing structure and its practice
CN107905111B (en) A kind of rigid frame-continuous girder end bay construction technology
CN108252220A (en) A kind of construction method of super-large span stiff skeleton
CN109440623A (en) The interim splicing structure of concrete segment precast bridge
CN209493826U (en) The interim splicing structure of concrete segment precast bridge
CN103590414A (en) Structure for connecting concrete tubular pile with bearing platform
CN210395128U (en) Hollow core plate beam connection structure in bridge widening
CN109722984A (en) Half assembled thin-wall piers of one kind and its assembly method
CN105088961B (en) The construction method that a kind of end bay closure segment is merged with Cast-in-Situ Segment
CN205531016U (en) Precast concrete post component and connected node
CN103938871A (en) Method for constructing concrete-filled steel tube column and bonded prestressed frame beam structure adopting reinforced concrete ring beam joints
CN106192726B (en) A kind of V-arrangement web beam structure and its construction method
CN210031483U (en) Prefabricated pier connection structure
CN104746434B (en) Closure segment formwork system without dismantling outer formwork
CN206635638U (en) Using the prefabricated thin-wall bent cap of prestressing with bond system
CN105951987A (en) Sub-frame post-cast joint with external permanent aluminum plate outer mold
CN208266667U (en) A kind of bridge pier structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant